    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    INDEX

    1.0 Project Background 2

    2.0 Third Party Quality Audit Consultant 3

    3.0 Major Activities and Review Meetings of the Month 3

    4.0 Status of TPQA Visits 4

    5.0 Progress of NCRMP works 5

    TPQA Status Report for NCRMP Works To the end of(31-07-2012) 6

    6.0 District wise status of tests conducted by TPQA 28

    7.0 Details of QC Audit Reports Submitted during this Month 29

    8.0 Details of Environmental & Social Reports Submitted during this Month 33

  • 7/31/2019 11.July Mpr 2012

    3/66

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    1.0 Project Background

    Andhra Pradesh (AP) state has one of the longest coastal belts in India. Out of 67,362 Km of road network in the state, the

    nine coastal districts cover 26,000 km of road length. Every year during the period of April-May and September-December,

    cyclonic situations set in to the Bay of Bengal. With the recent changes in climatic conditions, the catastrophic events are

    increasing resulting in very devastating cyclones like Laila, Jal etc where the loss is enormous. In the 97 years ranging

    from 1892 to 1989, there were as many as 67 cyclones within the State.

    It is essential to provide safe residential accommodation to the vulnerable population during any eventuality or disaster due

    to natural calamities such as cyclones and associated tidal waves and storm surges. The project is formulated based on

    experiences of Government of Andhra Pradesh in mitigating such disasters during the past and also keeping in view the

    existing facilities available in the project area in Andhra Pradesh.

    The Government of India has applied for a credit of US$ 255 Million equivalent from the International Development

    Association (IDA) toward the cost of National Cyclone Risk Mitigation Project (NCRMP), and it intends to apply the

    proceeds to payments for goods, works, related services and consulting services under this Project.

    National Cyclone Risk Mitigation Project (NCRMP) Project Implementation Unit (PIU), Andhra Pradesh, headquartered atHyderabad has invited the consultants to submit proposals for providing the consultancy services for Third Party Quality

    Audit for 9 coastal districts namely Srikakulam, Vijayanagaram, Visakhapatnam, East Godavari, West Godavari, Krishna,

    Guntur, Prakasam and Nellore. The project Construction of Multipurpose Cyclone Shelters, Roads to Cyclone

    Shelters, and Roads to habitations and Roads & Bridges under NCRMP is funded by International Development

    Association and received through Government of India. This consultancy is envisaged to audit the quality of works being

    implemented by various line departments working under PIU. The number of works under progress / for which

    agreements are concluded in each district is shown in the table below.

    District

    No. of works(Under Concluded Agreements) No. of works under ProgressNo. ofworks

  • 7/31/2019 11.July Mpr 2012

    4/66

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    2.0 Third Party Quality Audit Consultant.

    To provide Consulting Services of Third Party Quality Auditor for Construction of Multipurpose Cyclone Shelters, Roads to

    Cyclone Shelters, Roads to habitations, and Roads and Bridges under NCRMP in 9 coastal districts The Commissioner for

    Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP has selected Egis International in JV

    with Egis India Consulting Engineers (I) Pvt. Ltd. On 31st

    May2011, the Contract for Consultancy Service was signed

    between The Commissioner for Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP and

    the Egis International in JV with Egis India Consulting Engineers (I) Pvt. Ltd.

    3.0 Major Activities and Review Meetings of the Month

    S.No. Place Date Activity

    Attended NCRMP Office in L block received

  • 7/31/2019 11.July Mpr 2012

    5/66

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    4.0 Status of TPQA Visits:

    The following table shows the details of TPQA visits to sites in respective districts.

    DistrictTotal Number of Visits

    Up to June.'2012 In July.'2012 Up to July.'2012

    Srikakulam 289 17 306

    Vizianagaram 57 2 59Vishakhapatnam 255 25 280

    East Godavari 462 31 493

    West Godavari 347 17 364

    Krishna 215 9 224

    Guntur 216 34 250

    Prakasam 293 19 312

    Nellore 234 25 259

    No. of Visits by TPQA

  • 7/31/2019 11.July Mpr 2012

    6/66

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    5.0 Progress of NCRMP works:

    The district wise progress of works is shown below. The works in the West Godavari are not started and the works in

    Krishna District has just started. At many places the first milestone is completed but works are not started. The line

    departments are to analyze the reasons for the slow progress and if necessary penalty for the slow progress as per the

    agreement conditions should be imposed.

    Third Party Quality Audit by Egis India consulting services

    Summary of Activities

    S.No. District

    Agreements for PackagesCommunicated

    Status of works

    PR R&B Progress Not Started

    1 Srikakulam 6 5 21 0

    2 Vizianagaram - 3 3 0

    3 Visakhapatnam 13 0 21 0

    4 East Godavari 7 0 12 1

    5 West Godavari 3 0 10 0

    6 Krishna 4 0 8 0

    7 Guntur 6 2 16 1

  • 7/31/2019 11.July Mpr 2012

    7/66

    MONTHLY REPORT

    6 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    TPQA Status Report for NCRMP Works To the end of(31-07-2012)

    S.No. District

    Packages /Works

    entrustedStatus of Works

    No.of

    Visitsof

    TPQA

    TotalNo.

    of QCtestsdone

    NCRsQC

    ReportsIssued

    Environmentaland Social

    ReportsIssued

    Issued closed Pending

    PR R&B StartedNot

    Started

    1 Srikakulam 06_16 5_5 21 0 306 1176 33 25 8 27 27

    2 Vizianagaram - 3_3 3 0 59 366 3 1 2 10 6

    3 Visakhapatnam 13_21 - 21 0 280 1678 23 19 4 39 21

    4 East Godavari 07_13 - 12 1 493 904 18 13 5 35 13

    5 West Godavari 03_10 - 10 0 364 349 16 10 6 27 27

    6 Krishna 04_08 - 8 0 224 76 3 3 - 20 13

    7 Guntur 06_15 2_2 16 1 250 575 12 12 - 21 13

    8 Prakasham 12_23 1_1 24 0 312 1862 26 22 4 32 26

    9 Nellore 16_24 - 24 0 259 922 26 10 16 32 24

    Total 67_130 11_11 139 2 2547 7908 160 115 45 243 170

  • 7/31/2019 11.July Mpr 2012

    8/66

    MONTHLY REPORT

    7 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Srikakulam District up to 31.07.2012

    Category Packages allotted under Phase - 1Names of works under

    each packageAgreement No. / Date DHS DFC

    Progress up to

    31.07.2012

    RHB

    NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003

    Road from DPN R&Broad to Uddandapalem

    /2010-11, Dt.30.04.2011

    30.04.11 30.04.12 complete Entire work

    Road from K. UmiladaJunction to Koduru (LinkRoad)

    /2010-11, Dt.30.04.2011

    30.04.11 30.04.12 complete Entire work

    Road from Borubadra,Malagam to Kollipadu viaSeepuram, Gantapeta

    /2010-11, Dt.30.04.2011

    30.04.11 30.04.12 complete Entire work

    NCRMP/B-W/AP/RHB/PRED/01/Polaki/006

    Road from R&B road

    Mobagam toDuubakavanipeta viaGajapathinagaram

    /2010-11, Dt.30.04.2011

    30.04.11 30.04.12

    First Milestone i.eEarthwork & Cd

    works &GSB

    Road fromTalasamudram to DolaRegulator

    /2010-11, Dt.30.04.2011

    30.04.11 30.04.12

    First Milestone i.eEarthwork & Cd

    works &GSB

    NCRMP/B-W/AP/RHB/PRED/01/Polaki/005

    Road from R&B roadEdulavalasa - Killam toJonnam viaTalasamudram

    /2011-12, Dt.30.04.2011

    30.04.11 31.01.12

    First Milestone i.eEarthwork & Cd

    works &GSB

    Bridges

    NCRMP/B-W/ AP/Br/R&B/01/

    Patnavanipeta/001

    Construction of bridge atKm 11/6-8 of NH-5 toPatnavanipetaConnectingSundarapalem

    46/2011, Dt.

    17.12.201017.12.10 17.06.12

    Completion of entire

    work

    NCRMP/B-W/AP/Br/R&B/01/ Surampeta/003

    Construction of MinorBridge at Km 12/2-4 ofNH-5 to SurampetaRoad via Naruva,Mentada

    45/2010-2011,Dt17.12.2010

    17.12.10 17.03.12Completion of entire

    work

  • 7/31/2019 11.July Mpr 2012

    9/66

    MONTHLY REPORT

    8 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/Br/R&B/01/Bendigadda/004

    Construction of Highlevel bridge acrossBendigadda at KM 4/10of Pundi-Parlakimidi road

    in Srikakulam Dt, A.P.

    1/2010,Dt.11.11.2010 11.11.10 11.05.12Completion of entire

    work

    Roads NCRMP/B-W/AP/RD/R&B/01/Nowpada/006)Improvements Naupada-Venkatapuram road from0/0to15/0km

    43/2010-11,17.12.2010 17.12.10 17.03.12Completion of entire

    work

    RCS

    NCRMP/B-W/AP/RCS/PRED/01/V.Kotturui/002

    Road from NP road toURK Puram

    G.O.Rt.No.451, Dt.06.04.2011

    06.04.11 29.09.12WBM GR-II &III

    complete

    Road from Deppuru,Bahadapalli road toOnkuluru to CycloneShelter

    G.O.Rt.No.451, Dt.06.04.2011

    06.04.11 29.09.12WBM GR-II &III

    complete

    Road from R & B Roadto Devunthalada

    G.O.Rt.No.451, Dt.06.04.2011

    06.04.11 29.09.12 WBM GR-II &IIIcomplete

    Road from Pollada toKomarthalada toCyclone Shelter

    G.O.Rt.No.451, Dt.06.04.2011

    06.04.11 29.09.12WBM GR-II &III

    complete

    NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005

    Road from Koyyam R &B Road toMoosavanipeta

    G.O.Rt.No.451, Dt.06.04.2011

    30.04.11 07.05.12Completion of entire

    work

    Road from Mentada toDovupeta

    G.O.Rt.No.451, Dt.06.04.2011

    30.04.11 07.05.12Completion of entire

    work

    Road from Kotcherelaroad to Kollibhemavaram& Cyclone Shelter

    G.O.Rt.No.451, Dt.06.04.2011

    30.04.11 07.05.12Completion of entire

    work

    Road from Kotcherlaroad toPathesundrapalem

    G.O.Rt.No.451, Dt.06.04.2011

    30.04.11 07.05.12Completion of entire

    work

  • 7/31/2019 11.July Mpr 2012

    10/66

    MONTHLY REPORT

    9 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    MPCSNCRMP/B_W/AP/MPCS/PRED/01/Sa

    nthabommali/005

    Construction of Cyclone shelterat Kollipadu

    G.o rt No451 Dt

    06.04.2010

    07.01.2013

    Completion ofGround floorPlinth level

    Completion of stilt floor & firstfloor

    Construction of Cyclone Shelterat Runku

    G.o rt No451 Dt

    06.04.2010

    07.01.2013

    Completion ofGround floorPlinth level

    Completion of stilt floor & firstfloor

    Status of works in Vizianagaram District up to 31.07.2012

    CategoryPackages allottedunder Phase - 1

    Names of works under eachpackage

    Agreement No./ Date DHS DFCProgress up to

    31.07.2012

    Bridges

    NCRMP/ B-W/ AP/Br/ R&B/ 02/

    Puligadda/ 007

    Construction of Minor Bridge atKm. 7/2 near Puligadda of Konada Ramatheertham R&B Road toKonathalapalem via Yerukonda,

    Pasupam, Kollayavalsa (Z.P.Road)

    31/2010-201 Dt.1.12.2010

    01.12.10 31.05.12100% of work

    completed

    NCRMP/ B-W/ AP/Br/ R&B/ 02/

    Chakaligadda / 008

    Construction of Minor Bridge atKm 15/2 near Chakaligadda of

    Konada Ramatheertham R&B roadto Konathalapalem (via)Yerukonda, Pasupam,

    Kollayavalsa (ZP Road)

    34/2010-2011 Dt.8.12.2010

    08.12.10 07.06.1279% of workcompleted

    Road (R&B)NCRMP/B-

    W/AP/RD/R&B/ 02/Konada/009

    Improvements to Road fromKonada Ramatheertham (R&B)Road to Konathalapalem (Via)

    Pasupam, Yerukonda,Kollayavalsa from Km 12/0 to 16/5

    (Km 0/0 to 4/0 i.e. up to NH-5crossing)

    33/2010-201 Dt.8.12.2010

    08.12.10 07.03.12100% of work

    completed

  • 7/31/2019 11.July Mpr 2012

    11/66

    MONTHLY REPORT

    10 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Visakhapatnam District up to 31.07.2012

    Category Packages allotted under Phase- 1Names of works

    under each

    package

    Agreement

    No. / Date

    DHS DFC Progress up to 31.07.2012

    RHB

    NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/001

    Road from Vempadu toPatimeeda

    /2010-11, Dt.11.01.2011

    11.01.11 11.01.12 Work is completed

    Road from R&B road toMullaparra up to Beach

    end

    /2010-11, Dt.11.01.2011

    11.01.11 27.10.11 Work is completed

    NCRMP/B-W/AP/RHB/PRED/03/Anandapuram/003

    Road from R&B B.PKallalu to

    Matchvanipalem

    /2010-11, Dt.10.03.2011

    10.03.11 09.12.11 Work is completed

    NCRMP/B-W/AP/RHB/PRED/03/Paravada/004

    Road from R & B roadto Pothu Rajannapalem

    /2010-11, Dt.28.03.2011

    28.03.11 27.12.11 Work is completed

    Road from R & B roadto Jalaripeta

    /2010-11, Dt.28.03.2011

    28.03.22 28.12.11 Work is completed

    NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006Road from R & B road

    to Venkayyapalem/2010-11, Dt.11.01.2011

    11.01.11 11.10.11 Work is completed

    NCRMP/B-W/AP/RHB/PRED/03/Achyutapuram/007

    Road from R&B road toAva- Somavaram

    /2011-12, Dt.27.04.2011

    27.04.11 26.01.12 Work is completed

    Road from R&B Roadto Avarajam

    /2011-12, Dt.27.04.2011

    27.04.11 26.01.12 Work is completed

  • 7/31/2019 11.July Mpr 2012

    12/66

    MONTHLY REPORT

    11 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Visakhapatnam District up to 31.07.2012

    CategoryPackages allotted under

    Phase - 1

    Names of works under each

    package

    Agreement No. /

    Date

    DHS DFCProgress up

    to

    31.07.2012

    RCS

    NCRMP/B-W/AP/RCS/PRED/03/Anandapuram/001

    Road from NH-5 toRamarayadupalem

    /2010-11, Dt. 15.09.2011 15.09.11 14.06.12

    RoadFurniture &

    B.T iscompleted.

    NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002

    Road from R&B road toKrishnampalem

    /2010-11, Dt. 15.09.2011 15.09.11 14.09.12

    CD works arecompleted &B.T work isCompleted

    Road from R & B road toKattubolu to Marripalem

    /2010-11, Dt. 15.09.2011 15.09.11 14.09.12CD works arecompleted &

    B.T work isCompleted

    Road from R & B road toRajakoduru

    /2010-11, Dt. 15.09.2011 15.09.11 14.09.12

    CD Work iscompleted &B.T work iscompleted

    NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003

    Road from R & B road toPedateenarla to Chinatheernala

    /2010-11, Dt. 15.09.2011 15.09.11 14.06.12

    B.T & C.Croad works

    are

    Completed.

    Road from Upmaka RajayyapetaR & B road to Janakayyapeta

    /2010-11, Dt. 15.09.2011 15.09.11 14.06.12

    CD works areCompleted &B.T work iscompleted

  • 7/31/2019 11.July Mpr 2012

    13/66

    MONTHLY REPORT

    12 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Visakhapatnam District up to 31.07.2012

    Category Packages allotted under Phase - 1Names of works under

    each package

    Agreement No.

    / Date

    Milestone Completion Dates Progress w.r.t.milestone up to

    31.07.2012First Second Third

    MPCS

    NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003

    Construction of cycloneshelter at Gajapathi

    Nagaram

    /2011-12, Dt.03.10.2011

    02.02.12 02.06.12 02.10.12

    Columns lay up tobottom of plinthbeam & Plinth

    beam to be laid.

    Construction of cycloneshelter at Ratnayampeta

    /2011-12, Dt.03.10.2011

    02.02.12 02.06.12 02.10.12

    All slabs arecompleted. Brick

    work & Wood workin progress.

    NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002

    Construction of cycloneshelter at Patimeeda

    /2011-12, Dt.03.10.2011

    02.03.12 02.08.12 02.01.13Stilt Slab isCompleted

    Construction of cycloneshelter at Mullaparra

    /2011-12, Dt.03.10.2011

    02.03.12 02.08.12 02.01.13Stilt Slab isCompleted

    Construction of cycloneshelter at Bangarampeta

    /2011-12, Dt.03.10.2011

    02.03.12 02.08.12 02.01.131st Floor Slab is

    Completed.

    NCRMP/B-W/AP/MPCS/PRED/03/Rambilli/004

    Construction of cyclone

    shelter atVenkayyapalem

    /2011-12, Dt.03.10.2011 02.01.12 02.04.12 02.07.12 Footings work is inprogress

    NCRMP/B-W/AP/MPCS/PRED/03/Paravada/001Construction of cyclone

    shelter atTikkavanipalem

    /2011-12, Dt.07.10.2011

    06.01.12 06.04.12 06.07.12

    E/W foundationexcavation is

    completed & Dueto site problem

    work is stopped.

  • 7/31/2019 11.July Mpr 2012

    14/66

    MONTHLY REPORT

    13 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in East Godavari District up to 31.07.2012

    Category Packages allotted under Phase - I

    Names of works

    under eachpackage

    AgreementNo. / Date Mile stones Remarks

    First Second Third

    RHB (2 )RCS (8)MPCS (3)

    NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/003

    Road from PR roadsto Dasarivanipeta and

    to Cyclone Shelter

    /2011-12Dt:27.04.2011

    30-11-2011 30-11-2011 20-01-2012 Completed

    NCRMP/B-W /RCS/PRED/04/Karapa/001Approach Road tocyclone Shelter at

    Adivipudi

    2011-12Dt:20.05.2011

    30-11-2011 31-10-2011 31-01-2012 Completed

    NCRMP/B-W/AP/RHB/PRED/04/Karapa/001/

    Road fromGurjanapalli to

    Bandulavaripalem

    2011-12Dt:27.04.2011

    30-09-2011 31-10-2011 31-01-2012 Completed

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto P.Chodipallipeta CS

    2011-12Dt:07.09.2011

    3 months 3 months 3 months Completed

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto K.Chodipallipeta CS

    /2011-12Dt:07.09.2011 3 months 3 months 3 months Completed

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto Hukumpeta CS

    /2011-12Dt:07.09.2011

    3 months 3 months 3 months Completed

  • 7/31/2019 11.July Mpr 2012

    15/66

    MONTHLY REPORT

    14 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto Gaddipeta CS

    /2011-12Dt:07.09.2011

    3 months 3 months 3 months Completed

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto Danavaipeta CS

    /2011-12Dt:07.09.2011

    3 months 3 months 3 months Completed

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004/

    Road from R&B Roadto G.Musalayyapeta

    CS

    2011-12Dt:07.09.2011

    3 months 3 months 3 monthsNot yet Started

    NCRMP/B-W/AP/RCS/PRED/04/Uppalaguptam/003

    Road from R&B Roadto Chinaraghavulapeta

    Cyclone Shelter

    /2011-12 Dt:23.09.2011

    3 months/22.11.2011

    3 months22.06.2011

    -----------

    600mm dia pipeculvert and CC

    PavementCompleted

    NCRMP/B-W/AP/MPCS/PRED/04/Uppalaguptam/002

    Construction ofCyclone Shelter at

    Pedaraghavulapeta ofUppalaguptam Mandal

    E.G.Dt.

    /2011-12Dt:17.10.2011

    3 months16.01.2012

    3 months16.04.2012

    3 months16.07.2012

    Sand filling work isin progress below

    plinth beam

    NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/004

    Construction ofCyclone Shelter at

    Laxamanudupadu inThondangi

    /2011-12Dt:07.09.2011

    Stilt floor SlabCompleted

    NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/004

    Construction ofCyclone Shelter at

    Avulamanda

    /2011-12Dt:07.09.2011

    RCC Columns is inprogress above

    ground level

  • 7/31/2019 11.July Mpr 2012

    16/66

    MONTHLY REPORT

    15 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in West Godavari District up to 31.07.2012

    CategoryPackages allotted under Phase

    - 1Names of works under

    each packageAgreementNo. / Date

    Milestone Completion Dates Progress w.r.t.milestone up to

    31.07.2012

    RemarksFirst Second Third

    RHB

    NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/0

    01

    Road from NH 214 A atRanga Statue center to

    Harijanawada of Kalipatnam(E) (Mogalthuru Mandal

    W.G.Dist.)

    16 /2011-12

    Dt.27.04.2011

    27/4/2011to

    22/9/2011

    23/9/2011to

    24/2/2012

    25/2/2012to

    26/7/2012

    100% Completed.

    R&B road at PanchayatOffice to Pulaparthivarithota

    via Badava(Mogalthuru Mandal

    W.G.Dist.)

    100% Completed.

    Mogalthuru Vempa R&BRoad at Uchintha Kalava

    Bridge to Gogulamma

    Harijanapeta (MogalthuruMandal W.G.Dist.)

    100% Completed.

    From Narsapur MogalthuruR&B road to Dayadaldaspetavia Venkateshwara Swamytemple (Mogalthuru Mandal

    W.G.Dist.)

    100% Completed.

    Road from NH 214 A road toHarijanapeta of Kothota

    (Mogalthuru MandalW.G.Dist.)

    27/4/2011to

    22/9/2011

    23/9/2011to

    24/2/2012

    25/2/2012to

    26/7/2012100% Completed.

    NCRMP/B-W/AP/RHB/PRED/05/Narsapur/0

    02

    R&B road to Indira Nagar

    (via) Pochamma temple(Narsapur Mandal W.G.Dist.)

    21 /2011-12Dt.09.05.2011

    09/05/2011to

    04/09/2011

    05/09/2011to

    06/01/2012

    07/01/2011to

    08/5/2012

    100% Completed.

    Road from R&B road toPedalanka (Narsapur Mandal

    W.G.Dist.)100% Completed.

    Road from LB Cheria CCroad to Chillapalemm of LBCheria (Narsapur Mandal

    W.G.Dist.

    100% Completed.

  • 7/31/2019 11.July Mpr 2012

    17/66

    MONTHLY REPORT

    16 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Krishna District up to 31.07.2012

    Category Packages allotted under Phase - 1Names of works under each

    packageAgreement No. /

    DateDHS DFC

    Progress up to31.07.2012

    RHB

    NCRMP/B-W/AP/RHB/PRED/06/Machipatnam/001

    Road connecting R&B roadthrough Gantalammapalem

    /2011-12Dt.27.4.2011

    27.04.11 26.01.2012CD works,GSB,Gr-II,Gr-III,BT completed

    NCRMP/B-W/AP/RHB/PRED/06/Machipatnam/002

    Road from R & B Road to B.VThota

    /2011-12Dt.27.4.2011

    27.04.11 26.01.2012

    CD works,GSB,Gr-II,Gr-III,BT completed

    Road from Potalapalem Z.Proad to Chikativanipalem

    CD works,GSB,Gr-II,Gr-III,BT completed

    NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003

    Road from Intheru R&B Road toRangaraopet

    /2011-12Dt.27.4.2011 27.04.11 26.01.2012

    CD works,GSB,Gr-II,Gr-III,BT completed

    Road from R&B road to CycloneShelter at Chandala

    CD works,GSB,Gr-II,Gr-III,BT completed

    NCRMP/B-W/AP/RHB/PRED/05/Kalla/003

    From A-U R&B Road toSatyanarayanapuram (Kalla

    Mandal W.G.Dist.)25 /2011-12

    Dt.26.05.2011

    26/5/2011

    To20/8/2011

    20/8/2011

    to21/11/2011

    22/11/2011

    To23/2/2012

    100% Completed.

    From A-U R&B Road toMekaladibba (Kalla Mandal

    W.G.Dist.)100% Completed.

  • 7/31/2019 11.July Mpr 2012

    18/66

    MONTHLY REPORT

    17 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Krishna Districts up to 31.07.2012

    Category Packages allotted under Phase - 1

    Names of works

    under eachpackage

    AgreementNo. / Date

    Milestone Completion Dates Progressw.r.t.

    milestoneup to

    31.07.2012

    RemarksFirst Second Third

    RCSNCRMP/B-W

    /AP/RCS/PRED/06/Machipatnam/001

    Road fromBhogireddipalliR&B Road to

    Ramakhandam

    /2011-12/Dt.02.09.2011

    01.12.2011 01.03.12 01.06.12 13.20%

    CDworks,GSB,Gr-

    II,Gr-III,BT,CCcompleted

    Road from R&BRoad Chinnapuram

    to Gundupalem

    /2011-

    12/27.04.201101.12.2011 01.03.12 01.06.12

    12.14%

    CD

    works,GSB,Gr-II,Gr-III,BTcompleted

    Road fromPotalapalem Z.Proad to Potepalli.

    /2011-12/Dt.02.09.2011

    01.12.2011 01.03.12 01.06.1231.68%

    GSB, Gr-II,Gr-III,BT

    completed

  • 7/31/2019 11.July Mpr 2012

    19/66

    MONTHLY REPORT

    18 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in GUNTUR District up to 31.07.2012

    CategoryPackages allotted under

    Phase - 1Names of works under each package

    Agreement No./Date

    DHS DFCProgress up to

    31.07.2012

    RHB

    NCRMP/B-W/AP/RHB/PRED/07/KARLAPAL

    EM/001

    R/f Ganapavaram R&BRoad t o Kesavapuri ST colony 7/2011-2012

    27.04.201127.04.11 26.01.2012 Completed.

    NCRMP/B-W/AP/PRED/07/Nagaram/002

    R/f R&B Road to Mohammad Alipalem

    8/2011-201227.04.2011

    27.04.11 26.4.2012

    CC Road, BTRoad, Shoulder

    work is Completed.

    R/f R&B Road to Katuivaripalem. CC Road, BTRoad, Shoulder

    work is Completed.

    Bridges

    NCRMP/B-W/AP/Br/R&B/07/Bapatla/010

    Reconstruction of High level Bridge @Km5/2 ofBapatla-Suryalanka Road across Perali drain in

    Guntur79/2010-2011

    1.12.201001.12.10 31.5.2012

    Approaches is inprogress

    NCRMP/B-W/AP/Br/R&B/07/Bapatla/011

    Reconstruction of High level Bridge @Km2/4 ofBapatla-Pandurangapuram Road across Perali

    drain in Guntur78/2010-2011

    1.12.201001.12.10 31.5.2012

    Wearing coat tenslabs is completed,Approaches is in

    progress

    Status of works in GUNTUR District up to 31.07.2012

    Category Packages allotted under Phase - 1Names of works under each

    package

    Agreement No. /

    DateDHS DFC Progress up to 31.07.2012

    RCSNCRMP/B-W/AP/RCS/PRED/07/P

    Palem/001

    Road from R&B Road to

    Mandevaripalem

    /2010-11

    Dt.01.11.201101.11.11 31.07.2012 BT , Shoulder Work is

    Completed

  • 7/31/2019 11.July Mpr 2012

    20/66

    MONTHLY REPORT

    19 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Road from R&B Road Alluru to

    Yadavapalem

    /2010-11

    Dt.01.11.201101.11.11 31.07.2012

    Earth work Completed, Keywalls, GSB, CC road is in

    progress.

    NCRMP/B-

    W/AP/RCS/PRED/07/KarlaPalem/002

    Road from Ganapavaram R & B

    road to Pedamarpuvaripalem

    /2010-11

    Dt.01.11.201101.11.11 31.10.2012

    Work yet to be start.

    Road from R & B Road to

    Chinapuluguvaripalem

    /2010-11

    Dt.01.11.201101.11.11 31.10.2011

    Work yet to be start.

    Road from R & B road to

    Yaramvaripalem

    /2010-11

    Dt.01.11.201101.11.11 31.10.2011

    CC Road work, GSB isCompleted, Shoulders, and

    WBM is in progress.

    Road from R & B road to

    Pedagollapalem Cyclone Shelter

    /2010-11

    Dt.01.11.201101.11.11 31.10.201 CC Road work, Shoulder work

    is Completed.

    Pedagollapalem PR Road to

    Bonthagorlapalem

    /2010-11

    Dt.01.11.201101.11.11 31.10.201 Earth work, Key walls is

    Completed GSB is in progress.

    NCRMP/B-

    W/AP/RCS/PRED/07/Nizampatnam/003

    Road from R&B Road to

    Gurunadhanagar

    /2010-11 Dt.

    17.10.201117.10.11 16.07.12

    Earth work , Slab CulvertCompleted, material collection

    work is in Progress

    Road from R&B Road to Adavala

    H/O Bavajipalem

    /2010-11 Dt.

    17.10.201117.10.11 16.07.12 CC Road work, Shoulder work

    is Completed,

    Road from R&B Road to

    Atlavaripalem

    /2010-11 Dt.

    17.10.2011

    17.10.11 16.07.12CC Road work is Completed,

    GSB, WBM, Shoulder is inProgress

    NCRMP/B-

    W/AP/RCS/PRED/07/Bapatla/004

    Road from R&B Road to

    Hanumanthanagar2010-11

    Dt13.10.201113.10.11 12.07.2012

    CC Road work, Shoulder workis Completed,

    Road from R & B road to

    AdarsanagarCC Road work, Shoulder work

    is Completed,

  • 7/31/2019 11.July Mpr 2012

    21/66

  • 7/31/2019 11.July Mpr 2012

    22/66

    MONTHLY REPORT

    21 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Road from R&Broad to

    Chalivendradibba

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/002dated -10/02/2011

    CC work iscompleted from KM

    0/0 to KM 0/270.WBM Gr-II lying

    progress.

    Not Reached asper Mile stone-III (Awaiting for

    2nd

    EOTProposal)

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/002

    Road from PakalaR&B road to

    Mosanaladinne

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/002dated 10/02/2011

    6/9/2011Earth work,CD work,

    GSB

    10/9/2011WBM, Grade II

    & III

    2/9/2012 BT,Shoulders &road furniture

    WBM-Grade-IImaterial laying

    work is in progress

    Not Reached asper Mile stone-III (Awaiting for

    2nd

    EOTProposal)

    Road from R&Broad to Binginapalli

    HarijanawadaCyclone Shelter

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/002dated 10/02/2011

    CC road work iscompleted from KM

    0/0 to KM 0/220.Shoulders work is

    to be taken up.

    Mile stone-III(Awaiting for 2

    nd

    EOT Proposal)

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/003

    Road from R&BRoad Allur to M T

    Raju colony

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/003Dated 27/04/2011

    8/26/2011Earth work,CD work,

    GSB

    12/26/2011WBM, Grade II

    & III

    4/26/2012 BT,Shoulders &road furniture

    BT, CC road,shoulders &culverts are

    completed from km0/0 to km 3/8.work

    is completed

    As permilestonecompleted

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004

    Road from KEMR&B Road to

    Sankuvarigunta

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004

    Dated 27/04/2011 9/26/2011Earth work,CD work,

    GSB

    2/26/2012WBM, Grade II

    & III

    7/26/2012 BT,Shoulders &road furniture

    BT completed.CDwork completed.CC

    road workcompleted from km

    0/0 to km 1/430and CC dip work is

    completed

    Reached Milestone-III

    Road from KEM R& B Road to

    Pullareddypalem

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004Dated 27/04/2011

    BT completed.CDwork completed.CCroad and shoulders

    work completedfrom km 0/0 to km

    3/900.

    As permilestonecompleted

  • 7/31/2019 11.July Mpr 2012

    23/66

  • 7/31/2019 11.July Mpr 2012

    24/66

  • 7/31/2019 11.July Mpr 2012

    25/66

    MONTHLY REPORT

    24 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    mounds(raised

    portion), waterharvesting,septic tank,

    slump andsoak pit.etc.

    completed,Electrical work iscompleted.work is completed

    NCRMP/B-W/APMPCS/PRED/

    08/NG Padu/003

    Kanaparthy cycloneshelter in

    NaguluppapaduMandal Prakasam

    district

    NCRMP/B-W/AP/MPCS/PRED/08/NG Padu/003

    23.11.2011All items upto stilt floor

    slabincluding

    ramp, staircase

    foundations,columns,bea

    ms,pccflooring etc.,

    23.02.2012 Allitems up to

    first floor slaband head

    room slab in 2nd floor

    including staircase, columns

    etc.,

    23.05.2012plastering,

    flooring, watersupply

    arrangements,sanitary fitting,

    electricalitems,

    compoundwall, cc

    pavement.

    Earthenmounds(raised

    portion), waterharvesting,septic tank,slump and

    soak pit.etc.

    Stilt floor, first floorroof slabcompleted. Firstfloor plasteringwork is in progress.Head room slab

    completed,compound wall is inprogress.

    Reached Milestone-III(Awaiting for

    EOT Proposal)

    Status of works in Nellore District up to 31.07.2012

    (RCS)

    Package Number Name of Work Milestone1 Milestone2 Milestone3Progress upto 31.07.2012

    NCRMP/B-W/AP/09MUTHUKUR/RCS/002

    Road from R&B Roadkappaladoruvu to bandla Palem

    H.wada

    3Months: EarthWork, Pipe Culverts,

    GSB

    6 Months: WBMGrII,GrII,CC Pavement

    and Shoulders

    9 Months: BTCC road and

    Road Furniture

    OGPC+ Sealcoat completed

  • 7/31/2019 11.July Mpr 2012

    26/66

    MONTHLY REPORT

    25 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/09/D.V.SATRAM/RCS/008

    Road from R&B road to SullurpetaMallam to berjengalapalli cyclone

    shelter 3Months: EarthWork, Pipe Culverts,

    GSB

    6 Months: WBM GrII,GrII Shoulders and

    CC Pavement

    9 Months: BT,CC Pavement

    and Road

    Furniture

    OGPC+ Sealcoat completed

    NCRMP/B-W/AP/09T.P.GUDUR/RCS/005

    Road from7/2 M.C Road tovenkannapalem pattapupalem

    work completed

    NCRMP/B-W/AP/09chillakur/RCS/004

    Road from Katuivaripalem R&Broad to vellapalm

    3Months: EarthWork,CD Works,

    GSB

    6 Months: WBM GrII,GrII and Shoulders

    9 Months: BT,CC Pavement

    and RoadFurniture

    OGPC+ Sealcoat completed

    NCRMP/B-W/AP/09kota/RCS/001

    road from R&B road to A.SPURAM 3Months: Earth

    Work, Pipe Culverts,GSB

    6 Months: WBM GrII,GrII and Shoulders

    9 Months: BT,CC Pavement

    and RoadFurniture

    work completed

    Road from GD Road to

    Vavillapalem

    OGPC+ Seal

    coat completed

    NCRMP/B-W/AP/RCS/PRED/09/KAVALI/007

    Road from Kotha Satram R&B toIndiranagar (via) Thumalapenta

    palam, Patharavadu palam,Ramudu palam, Karaduvari palam&Sreeramapuram in SPSR Nellore

    District.

    4Months: EarthWork, Pipe Culverts,

    GSB

    4 Months: WBM GrII,GrII , Shoulders and

    CC Pavement

    4 Months: BT,CC Pavement

    and RoadFurniture

    OGPC+ Sealcoat completed

    NCRMP/B-W/AP/RCS/PRED/09/KAVALI/006

    Road Connecting R&B Roadthrough Voter Village in SPSR

    Nellore District.

    4 Months: EarthWork, Pipe Culverts,

    GSB

    4 Months: WBM GrII,GrII , Shoulders and

    CC Pavement

    4 Months: BT,CC Pavement

    and RoadFurniture

    GSB 2/0 to 2/8is in progress,

    6nos pipeculverts is in

    progress

    Status of works in Nellore District up to 31.07.2012

    RHBNCRMP/B-

    W/AP/RHB/PRED/09RHB/KAVALI/004

    Road from5/8 ofChennayapalem Road to

    Gummadi bandla5Months:

    Earthwork, CDWorks,ccpavement

    and GSB

    10 Months:WBM GrII, GrIIand Shoulders

    15 Months:BT and Road

    Furniture

    OGPC+ Seal coat completed

    Road from PedattapupalemR&B road to

    Chennayapalem H.wadaOGPC+ Seal coat completed

  • 7/31/2019 11.July Mpr 2012

    27/66

    MONTHLY REPORT

    26 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Road from K.T R&B Road toAlliguntapalem

    OGPC+ Seal coat completed

    NCRMP/B-W/AP/RHB/PRED/09BOGOLU/RHB/002

    Road from 1/6 ofJuvvaladinne R&B Road to

    Tellagunta KM to 2/720

    3Months: EarthWork, Pipe

    Culverts, GSB

    6 Months:WBM GrII, GrIIand Shoulders

    9 Months: BTand RoadFurniture

    OGPC+ Seal coat completed

    NCRMP/B-W/AP/RHB/PRED/09BOGOLO/RHB/001

    1. Road from NH5 toSambasivapuram

    5Months: EarthWork, Pipe

    Culverts, GSB

    10 Months:WBM GrII, GrIIand Shoulders

    15 Months:BT and Road

    Furniture

    OGPC+ Seal coat completed

    Road from 9/6 ofJuvvaladinne R&B Road to11/0 of Juvvaladinne R&BRoad Via Venkateshpalem

    OGPC+ Seal coat completed

    NCRMP/B-W/AP/RHB/PRED/09/VIDAVALURU/005

    1)Road from kt R&B ROADTO ALLAGANIPADU to

    Vavilla 5Months: EarthWork, Pipe

    Culverts, GSB

    10 Months:WBM GrII, GrIIand Shoulders

    15 Months:BT and Road

    Furniture

    WBM Gr-III is in progress!

    Road from R&B roadKancharapalem HW to

    Alaganipadu.Embankment is in progress

    NCRMP/B-W/AP/RHB/PRED/09V.CHALEM/RHB/007

    ROAD FROM SUVEPALLI-PUDIPARTHI ROAD TO

    SRIKANTH COLONY 4Months: EarthWork, Pipe

    Culverts, GSB

    8 Months:WBM GrII, GrIIand Shoulders

    12 Months:BT and Road

    Furniture

    OGPC+ Seal coat completed

    providing BT Surface to theroad from R&B road to

    Edagali KandrigaOGPC+ Seal coat completed

  • 7/31/2019 11.July Mpr 2012

    28/66

    MONTHLY REPORT

    27 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/RHB/PRED/09CHITTAMURU/003

    Road from R&B Road toMuttembake Via

    Pittuvanipalli 5Months: EarthWork, Pipe

    Culverts, GSB

    10 Months:WBM GrII, GrII

    and Shoulders

    15 Months:BT and Road

    Furniture

    OGPC+ Seal coat completed

    Road from R&B Chittamur toSoma Samudram

    OGPC+ Seal coat completed

    NCRMP/B-W/AP/09/MUTHUKUR/RHB/006

    Road from R&B road toPatuvariKandriga

    3Months: EarthWork, Pipe

    Culverts, GSB

    6 Months:WBM

    GrII,GrII,CCPavement and

    Shoulders

    9 Months: BTand RoadFurniture

    OGPC+ Seal coat completed

    NCRMP/B-W/AP/09Allur/RHB/009Road from R&Broad alluru toGalidibbalu (via)Chukavani

    dibba

    5Months: EarthWork, Pipe

    Culverts, GSB

    10 Months:WBM GrII, GrIIand Shoulders

    15 Months:BT and Road

    FurnitureOGPC+ Seal coat completed

    NCRMP/B-W/AP/RHB/PRED/009/T.P.GUDUR/012

    Ring Road to TP Gudur-Salipeta R & B Road via CS

    Puram and MandapamVillage 3Months: Earth

    Work, PipeCulverts, GSB

    6 Months:WBM

    GrII,GrII,CCPavement and

    Shoulders

    9 Months: BTand RoadFurniture

    OGPC+ Seal coat completed

    Road from R & B Road C SPuram to Sivaramapuram

    OGPC+ Seal coat completed

  • 7/31/2019 11.July Mpr 2012

    29/66

  • 7/31/2019 11.July Mpr 2012

    30/66

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    7.0 Details of Quality Control Audit Reports Submitted During this Month:

    Package Number Name of Work District

    NCRMP/B-

    W/AP/MPCS/PRED/03/Payakaraopeta/003

    Construction of cyclone shelter at

    Ratnayampeta in Payakaraopeta

    Vishakhapatnam

    NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002

    Providing BT surface to the road from

    R&B Road to Kattubolu to Marripalem Vishakhapatnam

  • 7/31/2019 11.July Mpr 2012

    31/66

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/RHB/ PRED/05/Narsapur/002

    R&B road to Indira Nagar (via)

    Pochamma temple of Narsapur

    Mandal

    West Godavari

    NCRMP/B-W/AP/RHB/ PRED/05/Narsapur/002

    Road from LB Cheria CC road to

    Chillapalemm of LB Cheria of

    Narsapur Mandal

    West Godavari

    NCRMP/B-W/AP/RHB/ PRED/05/Narsapur/002Road from R&B road to Pedalanka of

    Narsapur MandalWest Godavari

    NCRMP/B-W/AP/MPCS/PRED/08/NG

    Padu/003

    Construction of Cyclone shelter at

    Thopupalem Kanaparthy in

    Naguluppapadu Mandal

    Prakasham

    NCRMP/B-W/AP/Br/R&B/02/Puligadda/007

    Construction of Minor Bridge at Km.

    7/2 near Puligadda of Konada

    Ramatheertham R&B Road to

    Konathalapalem via Yerukonda,

    Pasupam, Kollayavalsa (Z.P. Road) in

    Vizianagaram District

    Vizianagaram

    NCRMP/B-W/AP/RCS/PRED/09/Kavali/006Road connecting R&B road through

    Voturu villageNellore

    NCRMP/B-W/AP/BR/R&B/08/Kanaparthy/012 Construction of HLB at Km 16/10 of

    Naguluppalapadu Kanaparthy road

    Prakasham

    NCRMP/BW/AP/RHB/PRED/09/Vidavalur/005. Road from R&B road Alaganipadu to

    Vavilla of Vidavalur of SPSR NelloreDist from KM 0.0 to KM 2.650

    Nellore

    NCRMP/B- Construction of cyclone shelter atVisakhapatnam

  • 7/31/2019 11.July Mpr 2012

    32/66

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-

    W/AP/RCS/PRED/04/THONDANGI/004Road from R&B Road to Danavaipeta East Godavari

    NCRMP/B-

    W/AP/RCS/PRED/04/THONDANGI/004

    Road from R&B Road to Gaddipeta of

    Thondangi Mandal in East Godavari

    District.

    East Godavari

    NCRMP/B-

    W/AP/RCS/PRED/04/THONDANGI/004

    Road from R&B Road to Hukumpeta

    Cyclone ShelterEast Godavari

    NCRMP/B-

    W/AP/RCS/PRED/04/THONDANGI/004

    Road from R&B Road to

    K.ChodipallipetaEast Godavari

    NCRMP/B-

    W/AP/MPCS/PRED/04/Thondangi/001

    Construction of Cyclone Shelter at

    Lakshmanudipeta in Thondangi

    Mandal, E.G.Dist.

    East Godavari

    NCRMP/B-

    W/AP/RCS/PRED/04/THONDANGI/004

    Road from R&B Road to

    P.ChodipallipetaEast Godavari

    NCRMP/B-

    W/AP/MPCS/PRED/04/Uppalaguptam/002

    Construction of Cyclone Shelter atPedaraghavulapeta in Uppalaguptam

    Mandal, E.G.Dt.

    East Godavari

    NCRMP/B-

    W/AP/RCS/PRED/04/Uppalaguptam/003.

    Road from R & B road to

    Chinaraghavulapeta Cyclone Shelter in

    East Godavari District.

    East Godavari

    NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from Deppuru, Bahadapalli roadto Onkuluru & cyclone shelter.

    Srikakulam

    NCRMP/B-W/AP/RCS/PRED/01/V Kotturu/002 R&B road to Devunthalada Srikakulam

  • 7/31/2019 11.July Mpr 2012

    33/66

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/RHB/PRED/07/Nagaram/002Road from R&B road to

    KaturivaripalemGuntur

    NCRMP/B-W/AP/RHB/PRED/09/Bogole/002Road from 1/6 of Zuvvaladinne R&B

    road to TellaguntaNellore

    NCRMP/B-W/AP/RHB/PRED/09/Vidavalur/005Road from R&B Kancharapalem HW to

    Alaganipadu of SPSR NelloreNellore

    NCRMP/B-W/AP/RHB/PRED/09/Chittamuru/003

    Road from R&B Chittamuru toSomasundaram

    Nellore

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002Road from Pakala R&B Road to

    MosanaladinnePrakasam

    NCRMP/B-

    W/AP/RHB/PRED/03/Nakkapalli/002

    Road from R&B Road to Mullaparra up

    to Beach EndVishakhapatnam

    NCRMP/B-

    W/AP/RHB/PRED/03/Nakkapalli/001Road from Vempudi to Patimeeda Vishakhapatnam

    NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006Road from R&B road to

    VenkayyapalemVishakhapatnam

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from R&B Road toChalivendradibba

    Prakasam

    NCR MP/B W/AP/RCS/PRED/09/Muthukur Road from R&B Road kappaladoruvu

  • 7/31/2019 11.July Mpr 2012

    34/66

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-

    W/AP/RCS/PRED/08/Vetapalem/002

    Road from NH to Challareddypalem in

    PrakasamPrakasam

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002Road from R&B road to Binginapalli

    Harijanawada Cyclone shelterPrakasam

    8.0 Details of Environmental and Social Reports Submitted During this Month:

    Package Number Name of Work District

    NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from NP Road to URK Puram Srikakulam

    NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002Road from Deppuru, Bahadapalli road

    to Onkuluru & to Cyclone ShelterSrikakulam

    NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from R&B Road to Devunalthada Srikakulam

    NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002Road from Pollada to Komaralthada &

    to Cyclone ShelterSrikakulam

    NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005Road from Koyyam R&B road to

    MoosavanipetaSrikakulam

    NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from Mentada to Donipeta Srikakulam

    NCRMP/B-W/AP/RHB/PRED/01/Polaki/006 Road from R&B road Mobagam toDuubakavanipeta via Gajapathinagaram

    Srikakulam

    NCRMP/B-W/AP/RHB/PRED/01/Polaki/006Road from Talasamudram to Dola

    Srikakulam

  • 7/31/2019 11.July Mpr 2012

    35/66

  • 7/31/2019 11.July Mpr 2012

    36/66

    MONTHLY REPORT

    35 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Consolidated E&S Report for East Godavari District in the Month of July 2012:

    Third Party Quality Audit for Construction of Cyclone Shelters, Roads to

    Cyclone Shelters & Habitations, Bridges and Culverts under NCRMP (Detailsof East Godavari in July, 2012)

    S.No Activity Measures to be implemented by the contractor COMPLICEDNOT

    COMPLICEDNOT

    APPLICABLETOTAL

    1Work Plan forEMPimplementation

    The Contractors Project Manager shall be responsible forimplementation of EMP provisions and will coordinate the over-allimplementation of the said plan. Along with the Work Programme, theContractor shall submit a plan including method statement and timelineabout specific actions that will be taken by him to implement theprovisions laid out in the EMP

    2 2

    2RegulatoryPermissions andConsents

    The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtainingpermission/consent for plants, water and extraction and borrow areasoperations. This includes:

    Consent for establishment and operation of plant (for concretework) from SPCB.

    2 2

    PUC certification for all vehicles/equipment used for/duringconstruction.

    2 2

    Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations formaterials like sand and earth.

    2 2

    Permission for water extraction, if applicable in the local area

    context. 2 2The Contractor shall abide by all conditions laid out in the said

    clearances.2 2

    3Consultation andCommunityConsent

    The Contractor shall consult and obtain written consents oflandowners(individual/panchayat/govt. agency) for temporary use of landfor all construction related activities including:

    a) Setting-up and operation of construction camp including labourcamps, stock yards etc.

    2 2

  • 7/31/2019 11.July Mpr 2012

    37/66

    MONTHLY REPORT

    36 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    b) borrow areas and 2 2

    c) Disposal of debris and other waste material. 2 2

    4Construction/Labour Camp

    a) Location: The camp and plant site/s location and establishment shallbe done in a manner that does not interfere or disturb the activities oflocal inhabitants, particularly those of schools and health facilities.Written permission (no objection certificate) shall be taken from theGramsabha and the land owner prior to location selection and a copyshall be submitted to the Engineer approval.

    2 2

    b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds.

    c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks,Sanctuaries, Biosphere Reserves, Reserve Forests and Ramsar Sites)and Coastal Regulation Zone.

    2 2

    b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions of

    Labour Laws. Separate toilet facilities shall be provided for womenworkers. If a common mess is not provided/operated additional space forcooking shall be provided. The contractor shall ensure that hygienicconditions are maintained during the operation of such camps/facilities.

    2 2

    c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp.

    2 2

    d) Potable water supply: Drinking water supply of at least 40Ipcd withthe required supply points shall be provided.

    2 2

    e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall beprovided by the contractor.

    2 2

    5 Site Clearance

    a) NO tree cutting is to carried out without the written instruction fromthe Employer, who in turn will ensure that relevant regulatorypermission/s (including those from Forest Dept., if required) are obtainedprior to cutting of such trees.

    2 2

    b) The non-timber grade trees are to be stacked and possession is tobe given to Employer/concerned Govt. Department.

    2 2

  • 7/31/2019 11.July Mpr 2012

    38/66

    MONTHLY REPORT

    37 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials.The top soil shall be reinstated in the cyclone shelter compound after theconstruction is over.

    2

    6Protection ofProperties andResources

    The Contractor shall take due care to protect and prevent damages to

    the following resources during preparatory and construction work:a) Water supply lines 1 1 2

    b) Irrigation canals 1 1

    c) Cart, cattle and/or foot trail/tracks 2 2

    d) Cultural properties and sites/structures of religious importance 2 2

    e) Houses, Farmlands, Orchids and/or Trees. 1 1 2

    f) School and other existing buildings adjacent to the site ofconstruction.

    2 2

    In case of damage due to construction activity, the restoration/repairsshall be carried out by the contractor at his own cost.

    2 2

    7QuarryOperations

    The Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shallbe submitted to the Engineer prior to procuring material.

    2 2

    8 Borrow Areas

    a) Borrow areas for the project will be selected by the Contractorfollowing the stipulations given below: The finalisation of all suchlocations shall be dependent on the approval of the Engineer ontechnical and environmental grounds. This includes on-site verification tocross-check the accuracy of details provided by the contractor. Onlyafter receipt of the written approval from the Engineer, the Contractorshall enter into a formal agreement with landowner.

    2 2

    b) The Contractor shall not procure any kind of construction material(such as aggregates, sand and earth) from ecologically protected areas.

    2 2

    c) Identification and Selection:

    1. The borrow area should not be located in agriculture fields/ unlessunavoidable i.e. barren land is not available. In case borrowing needs tobe done on an agricultural land, top-soil stripping, stacking andpreservation is must.

    2 2

    2. Borrow pits shall not be located within a distance of 100mts. Fromany NH, SH or other roads.

    2 2

  • 7/31/2019 11.July Mpr 2012

    39/66

    MONTHLY REPORT

    38 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations.

    2 2

    4. No borrow pits shall be located within 500mts. from schools,colleges, playgrounds, religious structures and health centres.

    2 2

    5. No borrow area shall be opened with in 500mts. from a reserved or

    protected forest area, protected sites, wildlife movement zone andcultural heritage site.

    2 2

    6. No tree cutting shall be undertaken. 2 2

    7. Borrow area near any surface water body will be at least 100mts.away.

    2 2

    d) Operation

    1. Area up to which material will be extracted shall be cleareddemarcated on ground.

    2 2

    2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 2 2

    3. Borrowing of earth should be preferably limited to a depth of 1.5mtr

    from the existing ground level.

    2 2

    4. Slope at the edges will be maintained not steeper than 2:3 (Vertical: Horizontal)

    2 2

    e) Rehabilitation of Borrow Areas:

    1. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon

    2 2

    2. Preserved top soil has be spread uniformly over land (except incases where borrow area is developed as a water body) used as aborrow area.

    2 2

    9Water Extraction/Use

    Water for construction and for use at construction camps (includinglabour camps) is to be extracted with prior written permission of(a) the

    individual owner, in case the source is private well/tube well; (b) GramPanchayat in case the source belongs to community: and (c) IrrigationDepartment in case the source is an irrigation canal or river.

    2 2

    10Safety of RoadUsers and LocalResidents

    a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety ofroad users and local people, particularly in the internal village roadswhich will be used for transporting materials.

    2 2

  • 7/31/2019 11.July Mpr 2012

    40/66

    MONTHLY REPORT

    39 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    b) Material shall be covered during transportation to prevent spillage,accidents and pollution.

    2 2

    c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorised entry into the

    construction.

    2 2

    11 Workers Safety

    a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision andenforcement of appropriate personal protective equipment; first aidfacility; emergency response arrangement; proper storage ofhazardous/toxic and polluting materials and; measures for ensuring fireelectrical and mechanical safety arrangements in camp and in work site.

    2 2

    b) All methods steps and measures are required for ensuring safety ofworkers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.

    2 2

    c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site. 2 2

    12 Air pollut ion a) Wind barriers or screens shall be provided in the downwinddirection at air pollution causing sources like plant sites and fine materialstorage stock yards

    1 1 2

    b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.

    2 2

    c) All plants and equipment shall comply with pollution control norms. 2 2

    d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100mbefore the settlement)

    2 2

    13 Water Pollution

    a) All measures (including provision of temporary silt fencing tocontrol sediment run-off) required for avoiding adverse impacts to waterbodies (such as ponds, streams, canals and rivers), water sources (suchas hand pumps and wells) and adjacent farmland shall be undertaken bythe Contractor.

    1 1 2

    b) Storage of materials like fuel, chemicals, and cement shall be donein a manner (with impervious layer on bottom and a covered shed ontop) that does not contaminate land and ground/surface water.

    2 2

    MONTHLY REPORT

  • 7/31/2019 11.July Mpr 2012

    41/66

    MONTHLY REPORT

    40 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    14 Noise Pollution

    a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal toensure least disturbance to school children and other adjacent residents.

    2

    b) Ear plugs shall be provided to the labour facing risk from high

    noise pollution such as plant site and those working near generators,heavy equipment /machinery.

    2 2

    c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimise noise during construction work and operationof camp.

    2

    15Disposal Debris/wastes

    a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.

    2

    b) Location of Debris Disposal Sites: Debris disposal sites shall belocated preferably away from farmlands, water sources and waterbodies. In no case, debris shall be disposed within 500mts. ofecologically sensitive areas, including forests, wetlands and protected

    natural habitats.

    2

    16Restoration andRehabilitation ofSites

    All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.

    2

    Completion of work(as covered under clause 55.1 of GCC) will alsoinclude completion of rehabilitation and clean-up of the work sitesincluding camps, plants, in and around the construction site; disposal ofdebris/construction wastes at pre-approved locations and; restoration ofborrow areas and other sites/ locations used for material sourcing.

    2

    17 Liabilities

    Any liability arising out of Contractors agreement with landowners/ localpeople/gram panchayat (including those related to temporary use ofland, water extraction and disposal of debris) shall be settled by theContractor.

    2

    MONTHLY REPORT

  • 7/31/2019 11.July Mpr 2012

    42/66

    MONTHLY REPORT

    41 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Consolidated E&S Report for Srikakulam District in the Month of July 2012:

    Third Party Quality Audit for Construction of Cyclone Shelters, Roads toCyclone Shelters & Habitations, Bridges and Culverts under NCRMP (Detailsof Srikakulam in July, 2012)

    S.No Activity Measures to be implemented by the contractor COMPLICEDNOT

    COMPLICEDNOT

    APPLICABLETOTAL

    1Work Plan forEMPimplementation

    The Contractors Project Manager shall be responsible forimplementation of EMP provisions and will coordinate the over-allimplementation of the said plan. Along with the Work Programme, theContractor shall submit a plan including method statement and timelineabout specific actions that will be taken by him to implement the

    provisions laid out in the EMP

    9 1 10

    2RegulatoryPermissions andConsents

    The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtainingpermission/consent for plants, water and extraction and borrow areasoperations. This includes:

    Consent for establishment and operation of plant (for concretework) from SPCB.

    10 10

    PUC certification for all vehicles/equipment used for/duringconstruction.

    9 1 10

    Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations for

    materials like sand and earth.

    9 1 10

    Permission for water extraction, if applicable in the local areacontext.

    9 1 10

    The Contractor shall abide by all conditions laid out in the saidclearances.

    9 1 10

    3Consultation andCommunityConsent

    The Contractor shall consult and obtain written consents oflandowners(individual/panchayat/govt. agency) for temporary use of landfor all construction related activities including:

    9 1 10

    MONTHLY REPORT

  • 7/31/2019 11.July Mpr 2012

    43/66

    MONTHLY REPORT

    42 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    a) Setting-up and operation of construction camp including labourcamps, stock yards etc.

    10 10

    b) borrow areas and 9 1 10

    c) Disposal of debris and other waste material. 9 1 10

    4 Construction/Labour Camp

    a) Location: The camp and plant site/s location and establishment shallbe done in a manner that does not interfere or disturb the activities oflocal inhabitants, particularly those of schools and health facilities.Written permission (no objection certificate) shall be taken from theGramsabha and the land owner prior to location selection and a copyshall be submitted to the Engineer approval.

    10 10

    b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds.

    10 10

    c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks,Sanctuaries, Biosphere Reserves, Reserve Forests and Ramsar Sites)and Coastal Regulation Zone.

    10 10

    b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions ofLabour Laws. Separate toilet facilities shall be provided for womenworkers. If a common mess is not provided/operated additional space forcooking shall be provided. The contractor shall ensure that hygienicconditions are maintained during the operation of such camps/facilities.

    10 10

    c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp.

    10 10

    d) Potable water supply: Drinking water supply of at least 40Ipcd withthe required supply points shall be provided.

    10 10

    e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall beprovided by the contractor.

    10 10

    5 Site Clearance

    a) NO tree cutting is to carried out without the written instruction fromthe Employer, who in turn will ensure that relevant regulatorypermission/s (including those from Forest Dept., if required) are obtainedprior to cutting of such trees.

    10 10

    b) The non-timber grade trees are to be stacked and possession is tobe given to Employer/concerned Govt. Department.

    10 10

    MONTHLY REPORT

  • 7/31/2019 11.July Mpr 2012

    44/66

    MONTHLY REPORT

    43 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials.The top soil shall be reinstated in the cyclone shelter compound after theconstruction is over.

    9 1 10

    6Protection ofProperties andResources

    The Contractor shall take due care to protect and prevent damages to

    the following resources during preparatory and construction work:a) Water supply lines 10 10

    b) Irrigation canals 10 10

    c) Cart, cattle and/or foot trail/tracks 10 10

    d) Cultural properties and sites/structures of religious importance 2 8 10

    e) Houses, Farmlands, Orchids and/or Trees. 2 8 10

    f) School and other existing buildings adjacent to the site ofconstruction.

    2 8 10

    In case of damage due to construction activity, the restoration/repairsshall be carried out by the contractor at his own cost.

    9 1 10

    7QuarryOperations

    The Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shallbe submitted to the Engineer prior to procuring material.

    9 1 10

    8 Borrow Areas

    a) Borrow areas for the project will be selected by the Contractorfollowing the stipulations given below: The finalisation of all suchlocations shall be dependent on the approval of the Engineer ontechnical and environmental grounds. This includes on-site verification tocross-check the accuracy of details provided by the contractor. Onlyafter receipt of the written approval from the Engineer, the Contractorshall enter into a formal agreement with landowner.

    9 1 10

    b) The Contractor shall not procure any kind of construction material(such as aggregates, sand and earth) from ecologically protected areas.

    9 1 10

    c) Identification and Selection:

    1. The borrow area should not be located in agriculture fields/ unlessunavoidable i.e. barren land is not available. In case borrowing needs tobe done on an agricultural land, top-soil stripping, stacking andpreservation is must.

    9 1 10

    2. Borrow pits shall not be located within a distance of 100mts. Fromany NH, SH or other roads.

    9 1 10

    MONTHLY REPORT

  • 7/31/2019 11.July Mpr 2012

    45/66

    MONTHLY REPORT

    44 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations.

    9 1 10

    4. No borrow pits shall be located within 500mts. from schools,colleges, playgrounds, religious structures and health centres.

    9 1 10

    5. No borrow area shall be opened with in 500mts. from a reserved or

    protected forest area, protected sites, wildlife movement zone andcultural heritage site.

    9 1 10

    6. No tree cutting shall be undertaken. 9 1 10

    7. Borrow area near any surface water body will be at least 100mts.away.

    9 1 10

    d) Operation

    1. Area up to which material will be extracted shall be cleareddemarcated on ground.

    9 1 10

    2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 9 1 10

    3. Borrowing of earth should be preferably limited to a depth of 1.5mtrfrom the existing ground level.

    9 1 10

    4. Slope at the edges will be maintained not steeper than 2:3 (Vertical: Horizontal)

    9 1 10

    e) Rehabilitation of Borrow Areas:

    1. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon

    9 1 10

    2. Preserved top soil has be spread uniformly over land (except incases where borrow area is developed as a water body) used as aborrow area.

    9 1 10

    9

    Water Extraction

    /Use

    Water for construction and for use at construction camps (includinglabour camps) is to be extracted with prior written permission of(a) the

    individual owner, in case the source is private well/tube well; (b) GramPanchayat in case the source belongs to community: and (c) IrrigationDepartment in case the source is an irrigation canal or river.

    9 1 10

    10Safety of RoadUsers and LocalResidents

    a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety ofroad users and local people, particularly in the internal village roadswhich will be used for transporting materials.

    9 1 10

    MONTHLY REPORT

  • 7/31/2019 11.July Mpr 2012

    46/66

    MONTHLY REPORT

    45 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    b) Material shall be covered during transportation to prevent spillage,accidents and pollution.

    9 1 10

    c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorised entry into the

    construction.

    9 1 10

    11 Workers Safety

    a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision andenforcement of appropriate personal protective equipment; first aidfacility; emergency response arrangement; proper storage ofhazardous/toxic and polluting materials and; measures for ensuring fireelectrical and mechanical safety arrangements in camp and in work site.

    9 1 10

    b) All methods steps and measures are required for ensuring safety ofworkers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.

    9 1 10

    c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site. 9 1 10

    12 Air pollution a) Wind barriers or screens shall be provided in the downwinddirection at air pollution causing sources like plant sites and fine materialstorage stock yards

    9 1 10

    b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.

    9 1 10

    c) All plants and equipment shall comply with pollution control norms. 9 1 10

    d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100mbefore the settlement)

    9 1 10

    13 Water Pollution

    a) All measures (including provision of temporary silt fencing tocontrol sediment run-off) required for avoiding adverse impacts to waterbodies (such as ponds, streams, canals and rivers), water sources (suchas hand pumps and wells) and adjacent farmland shall be undertaken bythe Contractor.

    9 1 10

    b) Storage of materials like fuel, chemicals, and cement shall be donein a manner (with impervious layer on bottom and a covered shed ontop) that does not contaminate land and ground/surface water.

    9 1 10

    MONTHLY REPORT

  • 7/31/2019 11.July Mpr 2012

    47/66

    MONTHLY REPORT

    46 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    14 Noise Pollution

    a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal toensure least disturbance to school children and other adjacent residents.

    9 1 10

    b) Ear plugs shall be provided to the labour facing risk from high

    noise pollution such as plant site and those working near generators,heavy equipment /machinery.

    9 1 10

    c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimise noise during construction work and operationof camp.

    10 10

    15Disposal Debris/wastes

    a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.

    9 1 10

    b) Location of Debris Disposal Sites: Debris disposal sites shall belocated preferably away from farmlands, water sources and waterbodies. In no case, debris shall be disposed within 500mts. ofecologically sensitive areas, including forests, wetlands and protected

    natural habitats.

    9 1 10

    16Restoration andRehabilitation ofSites

    All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.

    9 1 10

    Completion of work(as covered under clause 55.1 of GCC) will alsoinclude completion of rehabilitation and clean-up of the work sitesincluding camps, plants, in and around the construction site; disposal ofdebris/construction wastes at pre-approved locations and; restoration ofborrow areas and other sites/ locations used for material sourcing.

    9 1 10

    17 Liabilities

    Any liability arising out of Contractors agreement with landowners/ local

    people/gram panchayat (including those related to temporary use ofland, water extraction and disposal of debris) shall be settled by theContractor.

    9 1 10

  • 7/31/2019 11.July Mpr 2012

    48/66

  • 7/31/2019 11.July Mpr 2012

    49/66

    MONTHLY REPORT

  • 7/31/2019 11.July Mpr 2012

    50/66

    MONTHLY REPORT

    49 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials.The top soil shall be reinstated in the cyclone shelter compound after theconstruction is over.

    1 1

    6Protection ofProperties andResources

    The Contractor shall take due care to protect and prevent damages to

    the following resources during preparatory and construction work:a) Water supply lines 1 1

    b) Irrigation canals 1

    c) Cart, cattle and/or foot trail/tracks 1 1

    d) Cultural properties and sites/structures of religious importance 1 1

    e) Houses, Farmlands, Orchids and/or Trees. 1 1

    f) School and other existing buildings adjacent to the site ofconstruction.

    1 1

    In case of damage due to construction activity, the restoration/repairsshall be carried out by the contractor at his own cost.

    1 1

    7QuarryOperations

    The Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shallbe submitted to the Engineer prior to procuring material.

    1 1

    8 Borrow Areas

    a) Borrow areas for the project will be selected by the Contractorfollowing the stipulations given below: The finalisation of all suchlocations shall be dependent on the approval of the Engineer ontechnical and environmental grounds. This includes on-site verification tocross-check the accuracy of details provided by the contractor. Onlyafter receipt of the written approval from the Engineer, the Contractorshall enter into a formal agreement with landowner.

    1 1

    b) The Contractor shall not procure any kind of construction material(such as aggregates, sand and earth) from ecologically protected areas.

    1 1

    c) Identification and Selection:

    1. The borrow area should not be located in agriculture fields/ unlessunavoidable i.e. barren land is not available. In case borrowing needs tobe done on an agricultural land, top-soil stripping, stacking andpreservation is must.

    1 1

    2. Borrow pits shall not be located within a distance of 100mts. Fromany NH, SH or other roads.

    1 1

    MONTHLY REPORT

  • 7/31/2019 11.July Mpr 2012

    51/66

    50 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations.

    1 1

    4. No borrow pits shall be located within 500mts. from schools,colleges, playgrounds, religious structures and health centres.

    1 1

    5. No borrow area shall be opened with in 500mts. from a reserved or

    protected forest area, protected sites, wildlife movement zone andcultural heritage site.

    1 1

    6. No tree cutting shall be undertaken. 1 1

    7. Borrow area near any surface water body will be at least 100mts.away.

    1 1

    d) Operation

    1. Area up to which material will be extracted shall be cleareddemarcated on ground.

    1 1

    2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 1 1

    3. Borrowing of earth should be preferably limited to a depth of 1.5mtrfrom the existing ground level.

    1 1

    4. Slope at the edges will be maintained not steeper than 2:3 (Vertical: Horizontal)

    1 1

    e) Rehabilitation of Borrow Areas: 1

    1. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon

    1 1

    2. Preserved top soil has be spread uniformly over land (except incases where borrow area is developed as a water body) used as aborrow area.

    1 1

    9

    Water Extraction

    /Use

    Water for construction and for use at construction camps (includinglabour camps) is to be extracted with prior written permission of(a) the

    individual owner, in case the source is private well/tube well; (b) GramPanchayat in case the source belongs to community: and (c) IrrigationDepartment in case the source is an irrigation canal or river.

    1 1

    10Safety of RoadUsers and LocalResidents

    a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety ofroad users and local people, particularly in the internal village roadswhich will be used for transporting materials.

    1 1

  • 7/31/2019 11.July Mpr 2012

    52/66

    MONTHLY REPORT

  • 7/31/2019 11.July Mpr 2012

    53/66

    52 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    14 Noise Pollution

    a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal toensure least disturbance to school children and other adjacent residents.

    1 1

    b) Ear plugs shall be provided to the labour facing risk from high

    noise pollution such as plant site and those working near generators,heavy equipment /machinery.

    1 1

    c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimise noise during construction work and operationof camp.

    1 1

    15Disposal Debris/wastes

    a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.

    1 1

    b) Location of Debris Disposal Sites: Debris disposal sites shall belocated preferably away from farmlands, water sources and waterbodies. In no case, debris shall be disposed within 500mts. ofecologically sensitive areas, including forests, wetlands and protected

    natural habitats.

    1 1

    16Restoration andRehabilitation ofSites

    All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.

    1 1

    Completion of work(as covered under clause 55.1 of GCC) will alsoinclude completion of rehabilitation and clean-up of the work sitesincluding camps, plants, in and around the construction site; disposal ofdebris/construction wastes at pre-approved locations and; restoration ofborrow areas and other sites/ locations used for material sourcing.

    1 1

    17 Liabilities

    Any liability arising out of Contractors agreement with landowners/ local

    people/gram panchayat ( including those related to temporary use ofland, water extraction and disposal of debris) shall be settled by theContractor.

    1 1

    MONTHLY REPORT

  • 7/31/2019 11.July Mpr 2012

    54/66

    53 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    9.0 Statement Showing the Inspections and Site Visits of Districts during the Month of July -2012

    STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN SRIKAKULAM

    DISTRICT DURING THE MONTH OF JULY 2012

    S

    NO

    .

    PACKAGE NO NAME OF WORK

    TPQA INSPECTIONS

    DURING THIS MONTH

    DATES OF

    VISIT

    NO. OF

    VISITS

    1NCRMP/B-

    W/AP/RHB/PRED/01/Santhabommali/003

    Road from Borubadra, Malagam road to Kollipadu via Seepuram,

    Gantapeta in Santhabommali Mandal04.07.12 1

    2 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from Mentada to Dovupeta in EtcherlaMandal05.07.12,

    25.07.122

    3NCRMP/B-

    W/AP/MPCS/PRED/01/Santhabommali/005Construction of Cyclone shelter at Runku in Santhabommali Mandal.

    06.07.12,

    13.07.12,14.07.12,

    17.07.12,

    25.07.12

    5

    4 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from Pollada to Komaralthada & to cyclonic shelter.07.07.12,

    17.07.122

    5 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from R&B Road to Devunthalada.

    10.07.12,

    11.07.12,

    17.07.12,

    25.07.12

    4

    6 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002Road from Deppuru, Bahadapalli road to Onkuluru & cyclone

    shelter.

    16.07.12,17.

    07.12,

    19.07.12

    3

    7NCRMP/B-

    W/AP/MPCS/PRED/01/Santhabommali/005

    Construction of Cyclone shelter at Kollipadu in Santhabommali

    Mandal.23.07.12 1

    MONTHLY REPORT

  • 7/31/2019 11.July Mpr 2012

    55/66

    54 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    8 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from NP Road to URK Puram17.07.12,

    25.07.122

    9 NCRMP/B_W/AP/Br/R&B/01/Bendigadda/004Construction of High level Bridge across Bendigadda at km 4/10 of

    Pundi-Parlakimidi road in Srikakulam Dist.

    17.07.12,

    30.07.122

    10 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005Road from Kotcherla road to Pathesundrapalem

    25.07.12 1

    11 NCRMP/B_W/AP/Br/R&B/01/Surampeta/003 Construction of Minor Bridge at km 12/2-4 of NH-5 to Surampeta

    road via Naruva,Mentada25.07.12 1

    12 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/006 Road from Talasamudram to Dola regulator 28.07.12 1

    TOTAL 25

    STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VIJAYANAGARAM

    DISTRICT DURING THE MONTH OF JULY 2012

    S NO. PACKAGE NO NAME OF WORK

    TPQA INSPECTIONS DURING THIS

    MONTH

    DATES OF VISIT NO. OF VISITS

    1

    NCRMP/ B-W/ AP/ Br/ R&B/ 02/

    Chakaligadda / 008

    Construction of Minor Bridge at Km 15/2 near Chakaligadda

    of Konada Ramatheertham R&B road to Konathalapalem(via) Yerukonda, Pasupam, Kollayavalsa (ZP Road)

    25-07-2012 1

    2NCRMP/B-W/ AP/ Br/ R&B/ 02/ Puligadda/

    007

    Construction of Minor Bridge at Km. 7/2 near Puligadda ofKonada Ramatheertham R&B Road to Konathalapalem via

    Yerukonda, Pasupam, Kollayavalsa (Z.P. Road)25-07-2012 1

    TOTAL 2

    MONTHLY REPORT

  • 7/31/2019 11.July Mpr 2012

    56/66

    55 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VISHAKAPATNAM

    DISTRICT DURING THE MONTH OF JULY 2012

    S NO. PACKAGE NO NAME OF WORK

    TPQA INSPECTIONS DURING

    THIS MONTH

    DATES OF VISITNO. OF

    VISITS

    1NCRMP/B-

    W/AP/MPCS/PRED/03/Payakaraopeta/003

    Construction of cyclone shelter at Ratnayampeta in Payakaraopeta

    Mandal

    07.07.12

    13.07.122

    2NCRMP/B-

    W/AP/MPCS/PRED/03/Nakkapalli/002Construction of cyclone shelter at Patimeeda in Nakkapalli Mandal

    07.07.12

    10.07.12

    13.07.12

    24.07.12

    4

    3NCRMP/B-

    W/AP/MPCS/PRED/03/Nakkapalli/002Construction of cyclone shelter at Mullaparra in Nakkapalli Mandal

    07.07.12

    10.07.12

    13.07.12

    23.07.12

    24.07.12

    5

    4NCRMP/B-

    W/AP/MPCS/PRED/03/Payakaraopeta/003

    Construction of cyclone shelter at Gajapathinagaram in

    Payakaraopeta Mandal

    07.07.12

    13.07.122

    5NCRMP/B-

    W/AP/MPCS/PRED/03/Nakkapalli/002

    Construction of cyclone shelter at Bangarampeta in Nakkapalli

    Mandal

    19.07.12

    23.07.1224.07.12

    3

    6 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/004Construction of cyclone shelter at Venkayyapalem in Rambilli

    Mandal

    11.07.12

    24.07.122

    MONTHLY REPORT

  • 7/31/2019 11.July Mpr 2012

    57/66

    56 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    7 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002Road from R & B road to Kattubolu to Marripalem in Rambilli

    Mandal

    09.07.12

    13.07.12

    19.07.12

    21.07.12

    24.07.12

    5

    8 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 Road from R & B road to Rajakoduru in Rambilli Mandal

    09.07.12

    13.07.12

    24.07.12

    3

    9NCRMP/B-

    W/AP/RHB/PRED/03/Nakkapalli/001Road from Vempadu to Patimeeda in Nakkapalli Mandal 24.07.12 1

    10NCRMP/B-

    W/AP/RHB/PRED/03/Nakkapalli/002

    Road from R&B road to Mullaparra up to Beach end in Nakkapalli

    Mandal24.07.12 1

    11 NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006 Road from R & B road t o Venkayyapalem in Rambilli Mandal 24.07.12 1

    TOTAL 29

    MONTHLY REPORT

  • 7/31/2019 11.July Mpr 2012

    58/66

    57 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS OF EAST GODAVARI

    DISTRICT DURING THE MONTH OF JULY 2012

    S NO. PACKAGE NO NAME OF WORKTPQA INSPECTIONS DURING THIS MONTH

    DATES OF VISITNO. OF

    VISITS

    1

    NCRMP/B-W /AP/RCS/PRED/04/

    Thondangi/004

    Road from R&B Road to P.Chodipallipeta

    CS10.07.2012 and 24.07.2012 2

    2Road from R&B Road to K.Chodipallipeta

    CS10.07.2012 and 24.07.2012 2

    3 Road from R&B Road to Hukumpeta CS 10.07.2012 and 24.07.2012 2

    4 Road from R&B Road to Gaddipeta CS 10.07.2012 and 24.07.2012 2

    5 Road from R&B Road to Dana