MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
INDEX
1.0 Project Background 2
2.0 Third Party Quality Audit Consultant 3
3.0 Major Activities and Review Meetings of the Month 3
4.0 Status of TPQA Visits 4
5.0 Progress of NCRMP works 5
TPQA Status Report for NCRMP Works To the end of(31-07-2012) 6
6.0 District wise status of tests conducted by TPQA 28
7.0 Details of QC Audit Reports Submitted during this Month 29
8.0 Details of Environmental & Social Reports Submitted during this Month 33
-
7/31/2019 11.July Mpr 2012
3/66
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
1.0 Project Background
Andhra Pradesh (AP) state has one of the longest coastal belts in India. Out of 67,362 Km of road network in the state, the
nine coastal districts cover 26,000 km of road length. Every year during the period of April-May and September-December,
cyclonic situations set in to the Bay of Bengal. With the recent changes in climatic conditions, the catastrophic events are
increasing resulting in very devastating cyclones like Laila, Jal etc where the loss is enormous. In the 97 years ranging
from 1892 to 1989, there were as many as 67 cyclones within the State.
It is essential to provide safe residential accommodation to the vulnerable population during any eventuality or disaster due
to natural calamities such as cyclones and associated tidal waves and storm surges. The project is formulated based on
experiences of Government of Andhra Pradesh in mitigating such disasters during the past and also keeping in view the
existing facilities available in the project area in Andhra Pradesh.
The Government of India has applied for a credit of US$ 255 Million equivalent from the International Development
Association (IDA) toward the cost of National Cyclone Risk Mitigation Project (NCRMP), and it intends to apply the
proceeds to payments for goods, works, related services and consulting services under this Project.
National Cyclone Risk Mitigation Project (NCRMP) Project Implementation Unit (PIU), Andhra Pradesh, headquartered atHyderabad has invited the consultants to submit proposals for providing the consultancy services for Third Party Quality
Audit for 9 coastal districts namely Srikakulam, Vijayanagaram, Visakhapatnam, East Godavari, West Godavari, Krishna,
Guntur, Prakasam and Nellore. The project Construction of Multipurpose Cyclone Shelters, Roads to Cyclone
Shelters, and Roads to habitations and Roads & Bridges under NCRMP is funded by International Development
Association and received through Government of India. This consultancy is envisaged to audit the quality of works being
implemented by various line departments working under PIU. The number of works under progress / for which
agreements are concluded in each district is shown in the table below.
District
No. of works(Under Concluded Agreements) No. of works under ProgressNo. ofworks
-
7/31/2019 11.July Mpr 2012
4/66
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
2.0 Third Party Quality Audit Consultant.
To provide Consulting Services of Third Party Quality Auditor for Construction of Multipurpose Cyclone Shelters, Roads to
Cyclone Shelters, Roads to habitations, and Roads and Bridges under NCRMP in 9 coastal districts The Commissioner for
Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP has selected Egis International in JV
with Egis India Consulting Engineers (I) Pvt. Ltd. On 31st
May2011, the Contract for Consultancy Service was signed
between The Commissioner for Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP and
the Egis International in JV with Egis India Consulting Engineers (I) Pvt. Ltd.
3.0 Major Activities and Review Meetings of the Month
S.No. Place Date Activity
Attended NCRMP Office in L block received
-
7/31/2019 11.July Mpr 2012
5/66
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
4.0 Status of TPQA Visits:
The following table shows the details of TPQA visits to sites in respective districts.
DistrictTotal Number of Visits
Up to June.'2012 In July.'2012 Up to July.'2012
Srikakulam 289 17 306
Vizianagaram 57 2 59Vishakhapatnam 255 25 280
East Godavari 462 31 493
West Godavari 347 17 364
Krishna 215 9 224
Guntur 216 34 250
Prakasam 293 19 312
Nellore 234 25 259
No. of Visits by TPQA
-
7/31/2019 11.July Mpr 2012
6/66
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
5.0 Progress of NCRMP works:
The district wise progress of works is shown below. The works in the West Godavari are not started and the works in
Krishna District has just started. At many places the first milestone is completed but works are not started. The line
departments are to analyze the reasons for the slow progress and if necessary penalty for the slow progress as per the
agreement conditions should be imposed.
Third Party Quality Audit by Egis India consulting services
Summary of Activities
S.No. District
Agreements for PackagesCommunicated
Status of works
PR R&B Progress Not Started
1 Srikakulam 6 5 21 0
2 Vizianagaram - 3 3 0
3 Visakhapatnam 13 0 21 0
4 East Godavari 7 0 12 1
5 West Godavari 3 0 10 0
6 Krishna 4 0 8 0
7 Guntur 6 2 16 1
-
7/31/2019 11.July Mpr 2012
7/66
MONTHLY REPORT
6 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
TPQA Status Report for NCRMP Works To the end of(31-07-2012)
S.No. District
Packages /Works
entrustedStatus of Works
No.of
Visitsof
TPQA
TotalNo.
of QCtestsdone
NCRsQC
ReportsIssued
Environmentaland Social
ReportsIssued
Issued closed Pending
PR R&B StartedNot
Started
1 Srikakulam 06_16 5_5 21 0 306 1176 33 25 8 27 27
2 Vizianagaram - 3_3 3 0 59 366 3 1 2 10 6
3 Visakhapatnam 13_21 - 21 0 280 1678 23 19 4 39 21
4 East Godavari 07_13 - 12 1 493 904 18 13 5 35 13
5 West Godavari 03_10 - 10 0 364 349 16 10 6 27 27
6 Krishna 04_08 - 8 0 224 76 3 3 - 20 13
7 Guntur 06_15 2_2 16 1 250 575 12 12 - 21 13
8 Prakasham 12_23 1_1 24 0 312 1862 26 22 4 32 26
9 Nellore 16_24 - 24 0 259 922 26 10 16 32 24
Total 67_130 11_11 139 2 2547 7908 160 115 45 243 170
-
7/31/2019 11.July Mpr 2012
8/66
MONTHLY REPORT
7 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Status of works in Srikakulam District up to 31.07.2012
Category Packages allotted under Phase - 1Names of works under
each packageAgreement No. / Date DHS DFC
Progress up to
31.07.2012
RHB
NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003
Road from DPN R&Broad to Uddandapalem
/2010-11, Dt.30.04.2011
30.04.11 30.04.12 complete Entire work
Road from K. UmiladaJunction to Koduru (LinkRoad)
/2010-11, Dt.30.04.2011
30.04.11 30.04.12 complete Entire work
Road from Borubadra,Malagam to Kollipadu viaSeepuram, Gantapeta
/2010-11, Dt.30.04.2011
30.04.11 30.04.12 complete Entire work
NCRMP/B-W/AP/RHB/PRED/01/Polaki/006
Road from R&B road
Mobagam toDuubakavanipeta viaGajapathinagaram
/2010-11, Dt.30.04.2011
30.04.11 30.04.12
First Milestone i.eEarthwork & Cd
works &GSB
Road fromTalasamudram to DolaRegulator
/2010-11, Dt.30.04.2011
30.04.11 30.04.12
First Milestone i.eEarthwork & Cd
works &GSB
NCRMP/B-W/AP/RHB/PRED/01/Polaki/005
Road from R&B roadEdulavalasa - Killam toJonnam viaTalasamudram
/2011-12, Dt.30.04.2011
30.04.11 31.01.12
First Milestone i.eEarthwork & Cd
works &GSB
Bridges
NCRMP/B-W/ AP/Br/R&B/01/
Patnavanipeta/001
Construction of bridge atKm 11/6-8 of NH-5 toPatnavanipetaConnectingSundarapalem
46/2011, Dt.
17.12.201017.12.10 17.06.12
Completion of entire
work
NCRMP/B-W/AP/Br/R&B/01/ Surampeta/003
Construction of MinorBridge at Km 12/2-4 ofNH-5 to SurampetaRoad via Naruva,Mentada
45/2010-2011,Dt17.12.2010
17.12.10 17.03.12Completion of entire
work
-
7/31/2019 11.July Mpr 2012
9/66
MONTHLY REPORT
8 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/Br/R&B/01/Bendigadda/004
Construction of Highlevel bridge acrossBendigadda at KM 4/10of Pundi-Parlakimidi road
in Srikakulam Dt, A.P.
1/2010,Dt.11.11.2010 11.11.10 11.05.12Completion of entire
work
Roads NCRMP/B-W/AP/RD/R&B/01/Nowpada/006)Improvements Naupada-Venkatapuram road from0/0to15/0km
43/2010-11,17.12.2010 17.12.10 17.03.12Completion of entire
work
RCS
NCRMP/B-W/AP/RCS/PRED/01/V.Kotturui/002
Road from NP road toURK Puram
G.O.Rt.No.451, Dt.06.04.2011
06.04.11 29.09.12WBM GR-II &III
complete
Road from Deppuru,Bahadapalli road toOnkuluru to CycloneShelter
G.O.Rt.No.451, Dt.06.04.2011
06.04.11 29.09.12WBM GR-II &III
complete
Road from R & B Roadto Devunthalada
G.O.Rt.No.451, Dt.06.04.2011
06.04.11 29.09.12 WBM GR-II &IIIcomplete
Road from Pollada toKomarthalada toCyclone Shelter
G.O.Rt.No.451, Dt.06.04.2011
06.04.11 29.09.12WBM GR-II &III
complete
NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005
Road from Koyyam R &B Road toMoosavanipeta
G.O.Rt.No.451, Dt.06.04.2011
30.04.11 07.05.12Completion of entire
work
Road from Mentada toDovupeta
G.O.Rt.No.451, Dt.06.04.2011
30.04.11 07.05.12Completion of entire
work
Road from Kotcherelaroad to Kollibhemavaram& Cyclone Shelter
G.O.Rt.No.451, Dt.06.04.2011
30.04.11 07.05.12Completion of entire
work
Road from Kotcherlaroad toPathesundrapalem
G.O.Rt.No.451, Dt.06.04.2011
30.04.11 07.05.12Completion of entire
work
-
7/31/2019 11.July Mpr 2012
10/66
MONTHLY REPORT
9 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
MPCSNCRMP/B_W/AP/MPCS/PRED/01/Sa
nthabommali/005
Construction of Cyclone shelterat Kollipadu
G.o rt No451 Dt
06.04.2010
07.01.2013
Completion ofGround floorPlinth level
Completion of stilt floor & firstfloor
Construction of Cyclone Shelterat Runku
G.o rt No451 Dt
06.04.2010
07.01.2013
Completion ofGround floorPlinth level
Completion of stilt floor & firstfloor
Status of works in Vizianagaram District up to 31.07.2012
CategoryPackages allottedunder Phase - 1
Names of works under eachpackage
Agreement No./ Date DHS DFCProgress up to
31.07.2012
Bridges
NCRMP/ B-W/ AP/Br/ R&B/ 02/
Puligadda/ 007
Construction of Minor Bridge atKm. 7/2 near Puligadda of Konada Ramatheertham R&B Road toKonathalapalem via Yerukonda,
Pasupam, Kollayavalsa (Z.P.Road)
31/2010-201 Dt.1.12.2010
01.12.10 31.05.12100% of work
completed
NCRMP/ B-W/ AP/Br/ R&B/ 02/
Chakaligadda / 008
Construction of Minor Bridge atKm 15/2 near Chakaligadda of
Konada Ramatheertham R&B roadto Konathalapalem (via)Yerukonda, Pasupam,
Kollayavalsa (ZP Road)
34/2010-2011 Dt.8.12.2010
08.12.10 07.06.1279% of workcompleted
Road (R&B)NCRMP/B-
W/AP/RD/R&B/ 02/Konada/009
Improvements to Road fromKonada Ramatheertham (R&B)Road to Konathalapalem (Via)
Pasupam, Yerukonda,Kollayavalsa from Km 12/0 to 16/5
(Km 0/0 to 4/0 i.e. up to NH-5crossing)
33/2010-201 Dt.8.12.2010
08.12.10 07.03.12100% of work
completed
-
7/31/2019 11.July Mpr 2012
11/66
MONTHLY REPORT
10 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Status of works in Visakhapatnam District up to 31.07.2012
Category Packages allotted under Phase- 1Names of works
under each
package
Agreement
No. / Date
DHS DFC Progress up to 31.07.2012
RHB
NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/001
Road from Vempadu toPatimeeda
/2010-11, Dt.11.01.2011
11.01.11 11.01.12 Work is completed
Road from R&B road toMullaparra up to Beach
end
/2010-11, Dt.11.01.2011
11.01.11 27.10.11 Work is completed
NCRMP/B-W/AP/RHB/PRED/03/Anandapuram/003
Road from R&B B.PKallalu to
Matchvanipalem
/2010-11, Dt.10.03.2011
10.03.11 09.12.11 Work is completed
NCRMP/B-W/AP/RHB/PRED/03/Paravada/004
Road from R & B roadto Pothu Rajannapalem
/2010-11, Dt.28.03.2011
28.03.11 27.12.11 Work is completed
Road from R & B roadto Jalaripeta
/2010-11, Dt.28.03.2011
28.03.22 28.12.11 Work is completed
NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006Road from R & B road
to Venkayyapalem/2010-11, Dt.11.01.2011
11.01.11 11.10.11 Work is completed
NCRMP/B-W/AP/RHB/PRED/03/Achyutapuram/007
Road from R&B road toAva- Somavaram
/2011-12, Dt.27.04.2011
27.04.11 26.01.12 Work is completed
Road from R&B Roadto Avarajam
/2011-12, Dt.27.04.2011
27.04.11 26.01.12 Work is completed
-
7/31/2019 11.July Mpr 2012
12/66
MONTHLY REPORT
11 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Status of works in Visakhapatnam District up to 31.07.2012
CategoryPackages allotted under
Phase - 1
Names of works under each
package
Agreement No. /
Date
DHS DFCProgress up
to
31.07.2012
RCS
NCRMP/B-W/AP/RCS/PRED/03/Anandapuram/001
Road from NH-5 toRamarayadupalem
/2010-11, Dt. 15.09.2011 15.09.11 14.06.12
RoadFurniture &
B.T iscompleted.
NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002
Road from R&B road toKrishnampalem
/2010-11, Dt. 15.09.2011 15.09.11 14.09.12
CD works arecompleted &B.T work isCompleted
Road from R & B road toKattubolu to Marripalem
/2010-11, Dt. 15.09.2011 15.09.11 14.09.12CD works arecompleted &
B.T work isCompleted
Road from R & B road toRajakoduru
/2010-11, Dt. 15.09.2011 15.09.11 14.09.12
CD Work iscompleted &B.T work iscompleted
NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003
Road from R & B road toPedateenarla to Chinatheernala
/2010-11, Dt. 15.09.2011 15.09.11 14.06.12
B.T & C.Croad works
are
Completed.
Road from Upmaka RajayyapetaR & B road to Janakayyapeta
/2010-11, Dt. 15.09.2011 15.09.11 14.06.12
CD works areCompleted &B.T work iscompleted
-
7/31/2019 11.July Mpr 2012
13/66
MONTHLY REPORT
12 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Status of works in Visakhapatnam District up to 31.07.2012
Category Packages allotted under Phase - 1Names of works under
each package
Agreement No.
/ Date
Milestone Completion Dates Progress w.r.t.milestone up to
31.07.2012First Second Third
MPCS
NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003
Construction of cycloneshelter at Gajapathi
Nagaram
/2011-12, Dt.03.10.2011
02.02.12 02.06.12 02.10.12
Columns lay up tobottom of plinthbeam & Plinth
beam to be laid.
Construction of cycloneshelter at Ratnayampeta
/2011-12, Dt.03.10.2011
02.02.12 02.06.12 02.10.12
All slabs arecompleted. Brick
work & Wood workin progress.
NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002
Construction of cycloneshelter at Patimeeda
/2011-12, Dt.03.10.2011
02.03.12 02.08.12 02.01.13Stilt Slab isCompleted
Construction of cycloneshelter at Mullaparra
/2011-12, Dt.03.10.2011
02.03.12 02.08.12 02.01.13Stilt Slab isCompleted
Construction of cycloneshelter at Bangarampeta
/2011-12, Dt.03.10.2011
02.03.12 02.08.12 02.01.131st Floor Slab is
Completed.
NCRMP/B-W/AP/MPCS/PRED/03/Rambilli/004
Construction of cyclone
shelter atVenkayyapalem
/2011-12, Dt.03.10.2011 02.01.12 02.04.12 02.07.12 Footings work is inprogress
NCRMP/B-W/AP/MPCS/PRED/03/Paravada/001Construction of cyclone
shelter atTikkavanipalem
/2011-12, Dt.07.10.2011
06.01.12 06.04.12 06.07.12
E/W foundationexcavation is
completed & Dueto site problem
work is stopped.
-
7/31/2019 11.July Mpr 2012
14/66
MONTHLY REPORT
13 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Status of works in East Godavari District up to 31.07.2012
Category Packages allotted under Phase - I
Names of works
under eachpackage
AgreementNo. / Date Mile stones Remarks
First Second Third
RHB (2 )RCS (8)MPCS (3)
NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/003
Road from PR roadsto Dasarivanipeta and
to Cyclone Shelter
/2011-12Dt:27.04.2011
30-11-2011 30-11-2011 20-01-2012 Completed
NCRMP/B-W /RCS/PRED/04/Karapa/001Approach Road tocyclone Shelter at
Adivipudi
2011-12Dt:20.05.2011
30-11-2011 31-10-2011 31-01-2012 Completed
NCRMP/B-W/AP/RHB/PRED/04/Karapa/001/
Road fromGurjanapalli to
Bandulavaripalem
2011-12Dt:27.04.2011
30-09-2011 31-10-2011 31-01-2012 Completed
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004
Road from R&B Roadto P.Chodipallipeta CS
2011-12Dt:07.09.2011
3 months 3 months 3 months Completed
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004
Road from R&B Roadto K.Chodipallipeta CS
/2011-12Dt:07.09.2011 3 months 3 months 3 months Completed
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004
Road from R&B Roadto Hukumpeta CS
/2011-12Dt:07.09.2011
3 months 3 months 3 months Completed
-
7/31/2019 11.July Mpr 2012
15/66
MONTHLY REPORT
14 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004
Road from R&B Roadto Gaddipeta CS
/2011-12Dt:07.09.2011
3 months 3 months 3 months Completed
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004
Road from R&B Roadto Danavaipeta CS
/2011-12Dt:07.09.2011
3 months 3 months 3 months Completed
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004/
Road from R&B Roadto G.Musalayyapeta
CS
2011-12Dt:07.09.2011
3 months 3 months 3 monthsNot yet Started
NCRMP/B-W/AP/RCS/PRED/04/Uppalaguptam/003
Road from R&B Roadto Chinaraghavulapeta
Cyclone Shelter
/2011-12 Dt:23.09.2011
3 months/22.11.2011
3 months22.06.2011
-----------
600mm dia pipeculvert and CC
PavementCompleted
NCRMP/B-W/AP/MPCS/PRED/04/Uppalaguptam/002
Construction ofCyclone Shelter at
Pedaraghavulapeta ofUppalaguptam Mandal
E.G.Dt.
/2011-12Dt:17.10.2011
3 months16.01.2012
3 months16.04.2012
3 months16.07.2012
Sand filling work isin progress below
plinth beam
NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/004
Construction ofCyclone Shelter at
Laxamanudupadu inThondangi
/2011-12Dt:07.09.2011
Stilt floor SlabCompleted
NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/004
Construction ofCyclone Shelter at
Avulamanda
/2011-12Dt:07.09.2011
RCC Columns is inprogress above
ground level
-
7/31/2019 11.July Mpr 2012
16/66
MONTHLY REPORT
15 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Status of works in West Godavari District up to 31.07.2012
CategoryPackages allotted under Phase
- 1Names of works under
each packageAgreementNo. / Date
Milestone Completion Dates Progress w.r.t.milestone up to
31.07.2012
RemarksFirst Second Third
RHB
NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/0
01
Road from NH 214 A atRanga Statue center to
Harijanawada of Kalipatnam(E) (Mogalthuru Mandal
W.G.Dist.)
16 /2011-12
Dt.27.04.2011
27/4/2011to
22/9/2011
23/9/2011to
24/2/2012
25/2/2012to
26/7/2012
100% Completed.
R&B road at PanchayatOffice to Pulaparthivarithota
via Badava(Mogalthuru Mandal
W.G.Dist.)
100% Completed.
Mogalthuru Vempa R&BRoad at Uchintha Kalava
Bridge to Gogulamma
Harijanapeta (MogalthuruMandal W.G.Dist.)
100% Completed.
From Narsapur MogalthuruR&B road to Dayadaldaspetavia Venkateshwara Swamytemple (Mogalthuru Mandal
W.G.Dist.)
100% Completed.
Road from NH 214 A road toHarijanapeta of Kothota
(Mogalthuru MandalW.G.Dist.)
27/4/2011to
22/9/2011
23/9/2011to
24/2/2012
25/2/2012to
26/7/2012100% Completed.
NCRMP/B-W/AP/RHB/PRED/05/Narsapur/0
02
R&B road to Indira Nagar
(via) Pochamma temple(Narsapur Mandal W.G.Dist.)
21 /2011-12Dt.09.05.2011
09/05/2011to
04/09/2011
05/09/2011to
06/01/2012
07/01/2011to
08/5/2012
100% Completed.
Road from R&B road toPedalanka (Narsapur Mandal
W.G.Dist.)100% Completed.
Road from LB Cheria CCroad to Chillapalemm of LBCheria (Narsapur Mandal
W.G.Dist.
100% Completed.
-
7/31/2019 11.July Mpr 2012
17/66
MONTHLY REPORT
16 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Status of works in Krishna District up to 31.07.2012
Category Packages allotted under Phase - 1Names of works under each
packageAgreement No. /
DateDHS DFC
Progress up to31.07.2012
RHB
NCRMP/B-W/AP/RHB/PRED/06/Machipatnam/001
Road connecting R&B roadthrough Gantalammapalem
/2011-12Dt.27.4.2011
27.04.11 26.01.2012CD works,GSB,Gr-II,Gr-III,BT completed
NCRMP/B-W/AP/RHB/PRED/06/Machipatnam/002
Road from R & B Road to B.VThota
/2011-12Dt.27.4.2011
27.04.11 26.01.2012
CD works,GSB,Gr-II,Gr-III,BT completed
Road from Potalapalem Z.Proad to Chikativanipalem
CD works,GSB,Gr-II,Gr-III,BT completed
NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003
Road from Intheru R&B Road toRangaraopet
/2011-12Dt.27.4.2011 27.04.11 26.01.2012
CD works,GSB,Gr-II,Gr-III,BT completed
Road from R&B road to CycloneShelter at Chandala
CD works,GSB,Gr-II,Gr-III,BT completed
NCRMP/B-W/AP/RHB/PRED/05/Kalla/003
From A-U R&B Road toSatyanarayanapuram (Kalla
Mandal W.G.Dist.)25 /2011-12
Dt.26.05.2011
26/5/2011
To20/8/2011
20/8/2011
to21/11/2011
22/11/2011
To23/2/2012
100% Completed.
From A-U R&B Road toMekaladibba (Kalla Mandal
W.G.Dist.)100% Completed.
-
7/31/2019 11.July Mpr 2012
18/66
MONTHLY REPORT
17 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Status of works in Krishna Districts up to 31.07.2012
Category Packages allotted under Phase - 1
Names of works
under eachpackage
AgreementNo. / Date
Milestone Completion Dates Progressw.r.t.
milestoneup to
31.07.2012
RemarksFirst Second Third
RCSNCRMP/B-W
/AP/RCS/PRED/06/Machipatnam/001
Road fromBhogireddipalliR&B Road to
Ramakhandam
/2011-12/Dt.02.09.2011
01.12.2011 01.03.12 01.06.12 13.20%
CDworks,GSB,Gr-
II,Gr-III,BT,CCcompleted
Road from R&BRoad Chinnapuram
to Gundupalem
/2011-
12/27.04.201101.12.2011 01.03.12 01.06.12
12.14%
CD
works,GSB,Gr-II,Gr-III,BTcompleted
Road fromPotalapalem Z.Proad to Potepalli.
/2011-12/Dt.02.09.2011
01.12.2011 01.03.12 01.06.1231.68%
GSB, Gr-II,Gr-III,BT
completed
-
7/31/2019 11.July Mpr 2012
19/66
MONTHLY REPORT
18 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Status of works in GUNTUR District up to 31.07.2012
CategoryPackages allotted under
Phase - 1Names of works under each package
Agreement No./Date
DHS DFCProgress up to
31.07.2012
RHB
NCRMP/B-W/AP/RHB/PRED/07/KARLAPAL
EM/001
R/f Ganapavaram R&BRoad t o Kesavapuri ST colony 7/2011-2012
27.04.201127.04.11 26.01.2012 Completed.
NCRMP/B-W/AP/PRED/07/Nagaram/002
R/f R&B Road to Mohammad Alipalem
8/2011-201227.04.2011
27.04.11 26.4.2012
CC Road, BTRoad, Shoulder
work is Completed.
R/f R&B Road to Katuivaripalem. CC Road, BTRoad, Shoulder
work is Completed.
Bridges
NCRMP/B-W/AP/Br/R&B/07/Bapatla/010
Reconstruction of High level Bridge @Km5/2 ofBapatla-Suryalanka Road across Perali drain in
Guntur79/2010-2011
1.12.201001.12.10 31.5.2012
Approaches is inprogress
NCRMP/B-W/AP/Br/R&B/07/Bapatla/011
Reconstruction of High level Bridge @Km2/4 ofBapatla-Pandurangapuram Road across Perali
drain in Guntur78/2010-2011
1.12.201001.12.10 31.5.2012
Wearing coat tenslabs is completed,Approaches is in
progress
Status of works in GUNTUR District up to 31.07.2012
Category Packages allotted under Phase - 1Names of works under each
package
Agreement No. /
DateDHS DFC Progress up to 31.07.2012
RCSNCRMP/B-W/AP/RCS/PRED/07/P
Palem/001
Road from R&B Road to
Mandevaripalem
/2010-11
Dt.01.11.201101.11.11 31.07.2012 BT , Shoulder Work is
Completed
-
7/31/2019 11.July Mpr 2012
20/66
MONTHLY REPORT
19 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Road from R&B Road Alluru to
Yadavapalem
/2010-11
Dt.01.11.201101.11.11 31.07.2012
Earth work Completed, Keywalls, GSB, CC road is in
progress.
NCRMP/B-
W/AP/RCS/PRED/07/KarlaPalem/002
Road from Ganapavaram R & B
road to Pedamarpuvaripalem
/2010-11
Dt.01.11.201101.11.11 31.10.2012
Work yet to be start.
Road from R & B Road to
Chinapuluguvaripalem
/2010-11
Dt.01.11.201101.11.11 31.10.2011
Work yet to be start.
Road from R & B road to
Yaramvaripalem
/2010-11
Dt.01.11.201101.11.11 31.10.2011
CC Road work, GSB isCompleted, Shoulders, and
WBM is in progress.
Road from R & B road to
Pedagollapalem Cyclone Shelter
/2010-11
Dt.01.11.201101.11.11 31.10.201 CC Road work, Shoulder work
is Completed.
Pedagollapalem PR Road to
Bonthagorlapalem
/2010-11
Dt.01.11.201101.11.11 31.10.201 Earth work, Key walls is
Completed GSB is in progress.
NCRMP/B-
W/AP/RCS/PRED/07/Nizampatnam/003
Road from R&B Road to
Gurunadhanagar
/2010-11 Dt.
17.10.201117.10.11 16.07.12
Earth work , Slab CulvertCompleted, material collection
work is in Progress
Road from R&B Road to Adavala
H/O Bavajipalem
/2010-11 Dt.
17.10.201117.10.11 16.07.12 CC Road work, Shoulder work
is Completed,
Road from R&B Road to
Atlavaripalem
/2010-11 Dt.
17.10.2011
17.10.11 16.07.12CC Road work is Completed,
GSB, WBM, Shoulder is inProgress
NCRMP/B-
W/AP/RCS/PRED/07/Bapatla/004
Road from R&B Road to
Hanumanthanagar2010-11
Dt13.10.201113.10.11 12.07.2012
CC Road work, Shoulder workis Completed,
Road from R & B road to
AdarsanagarCC Road work, Shoulder work
is Completed,
-
7/31/2019 11.July Mpr 2012
21/66
-
7/31/2019 11.July Mpr 2012
22/66
MONTHLY REPORT
21 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Road from R&Broad to
Chalivendradibba
NCRMP/B-W/AP/RHB/PRED/0
8/S.Konda/002dated -10/02/2011
CC work iscompleted from KM
0/0 to KM 0/270.WBM Gr-II lying
progress.
Not Reached asper Mile stone-III (Awaiting for
2nd
EOTProposal)
NCRMP/B-W/AP/RHB/PRED/0
8/S.Konda/002
Road from PakalaR&B road to
Mosanaladinne
NCRMP/B-W/AP/RHB/PRED/0
8/S.Konda/002dated 10/02/2011
6/9/2011Earth work,CD work,
GSB
10/9/2011WBM, Grade II
& III
2/9/2012 BT,Shoulders &road furniture
WBM-Grade-IImaterial laying
work is in progress
Not Reached asper Mile stone-III (Awaiting for
2nd
EOTProposal)
Road from R&Broad to Binginapalli
HarijanawadaCyclone Shelter
NCRMP/B-W/AP/RHB/PRED/0
8/S.Konda/002dated 10/02/2011
CC road work iscompleted from KM
0/0 to KM 0/220.Shoulders work is
to be taken up.
Mile stone-III(Awaiting for 2
nd
EOT Proposal)
NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/003
Road from R&BRoad Allur to M T
Raju colony
NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/003Dated 27/04/2011
8/26/2011Earth work,CD work,
GSB
12/26/2011WBM, Grade II
& III
4/26/2012 BT,Shoulders &road furniture
BT, CC road,shoulders &culverts are
completed from km0/0 to km 3/8.work
is completed
As permilestonecompleted
NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004
Road from KEMR&B Road to
Sankuvarigunta
NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004
Dated 27/04/2011 9/26/2011Earth work,CD work,
GSB
2/26/2012WBM, Grade II
& III
7/26/2012 BT,Shoulders &road furniture
BT completed.CDwork completed.CC
road workcompleted from km
0/0 to km 1/430and CC dip work is
completed
Reached Milestone-III
Road from KEM R& B Road to
Pullareddypalem
NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004Dated 27/04/2011
BT completed.CDwork completed.CCroad and shoulders
work completedfrom km 0/0 to km
3/900.
As permilestonecompleted
-
7/31/2019 11.July Mpr 2012
23/66
-
7/31/2019 11.July Mpr 2012
24/66
-
7/31/2019 11.July Mpr 2012
25/66
MONTHLY REPORT
24 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
mounds(raised
portion), waterharvesting,septic tank,
slump andsoak pit.etc.
completed,Electrical work iscompleted.work is completed
NCRMP/B-W/APMPCS/PRED/
08/NG Padu/003
Kanaparthy cycloneshelter in
NaguluppapaduMandal Prakasam
district
NCRMP/B-W/AP/MPCS/PRED/08/NG Padu/003
23.11.2011All items upto stilt floor
slabincluding
ramp, staircase
foundations,columns,bea
ms,pccflooring etc.,
23.02.2012 Allitems up to
first floor slaband head
room slab in 2nd floor
including staircase, columns
etc.,
23.05.2012plastering,
flooring, watersupply
arrangements,sanitary fitting,
electricalitems,
compoundwall, cc
pavement.
Earthenmounds(raised
portion), waterharvesting,septic tank,slump and
soak pit.etc.
Stilt floor, first floorroof slabcompleted. Firstfloor plasteringwork is in progress.Head room slab
completed,compound wall is inprogress.
Reached Milestone-III(Awaiting for
EOT Proposal)
Status of works in Nellore District up to 31.07.2012
(RCS)
Package Number Name of Work Milestone1 Milestone2 Milestone3Progress upto 31.07.2012
NCRMP/B-W/AP/09MUTHUKUR/RCS/002
Road from R&B Roadkappaladoruvu to bandla Palem
H.wada
3Months: EarthWork, Pipe Culverts,
GSB
6 Months: WBMGrII,GrII,CC Pavement
and Shoulders
9 Months: BTCC road and
Road Furniture
OGPC+ Sealcoat completed
-
7/31/2019 11.July Mpr 2012
26/66
MONTHLY REPORT
25 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/09/D.V.SATRAM/RCS/008
Road from R&B road to SullurpetaMallam to berjengalapalli cyclone
shelter 3Months: EarthWork, Pipe Culverts,
GSB
6 Months: WBM GrII,GrII Shoulders and
CC Pavement
9 Months: BT,CC Pavement
and Road
Furniture
OGPC+ Sealcoat completed
NCRMP/B-W/AP/09T.P.GUDUR/RCS/005
Road from7/2 M.C Road tovenkannapalem pattapupalem
work completed
NCRMP/B-W/AP/09chillakur/RCS/004
Road from Katuivaripalem R&Broad to vellapalm
3Months: EarthWork,CD Works,
GSB
6 Months: WBM GrII,GrII and Shoulders
9 Months: BT,CC Pavement
and RoadFurniture
OGPC+ Sealcoat completed
NCRMP/B-W/AP/09kota/RCS/001
road from R&B road to A.SPURAM 3Months: Earth
Work, Pipe Culverts,GSB
6 Months: WBM GrII,GrII and Shoulders
9 Months: BT,CC Pavement
and RoadFurniture
work completed
Road from GD Road to
Vavillapalem
OGPC+ Seal
coat completed
NCRMP/B-W/AP/RCS/PRED/09/KAVALI/007
Road from Kotha Satram R&B toIndiranagar (via) Thumalapenta
palam, Patharavadu palam,Ramudu palam, Karaduvari palam&Sreeramapuram in SPSR Nellore
District.
4Months: EarthWork, Pipe Culverts,
GSB
4 Months: WBM GrII,GrII , Shoulders and
CC Pavement
4 Months: BT,CC Pavement
and RoadFurniture
OGPC+ Sealcoat completed
NCRMP/B-W/AP/RCS/PRED/09/KAVALI/006
Road Connecting R&B Roadthrough Voter Village in SPSR
Nellore District.
4 Months: EarthWork, Pipe Culverts,
GSB
4 Months: WBM GrII,GrII , Shoulders and
CC Pavement
4 Months: BT,CC Pavement
and RoadFurniture
GSB 2/0 to 2/8is in progress,
6nos pipeculverts is in
progress
Status of works in Nellore District up to 31.07.2012
RHBNCRMP/B-
W/AP/RHB/PRED/09RHB/KAVALI/004
Road from5/8 ofChennayapalem Road to
Gummadi bandla5Months:
Earthwork, CDWorks,ccpavement
and GSB
10 Months:WBM GrII, GrIIand Shoulders
15 Months:BT and Road
Furniture
OGPC+ Seal coat completed
Road from PedattapupalemR&B road to
Chennayapalem H.wadaOGPC+ Seal coat completed
-
7/31/2019 11.July Mpr 2012
27/66
MONTHLY REPORT
26 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Road from K.T R&B Road toAlliguntapalem
OGPC+ Seal coat completed
NCRMP/B-W/AP/RHB/PRED/09BOGOLU/RHB/002
Road from 1/6 ofJuvvaladinne R&B Road to
Tellagunta KM to 2/720
3Months: EarthWork, Pipe
Culverts, GSB
6 Months:WBM GrII, GrIIand Shoulders
9 Months: BTand RoadFurniture
OGPC+ Seal coat completed
NCRMP/B-W/AP/RHB/PRED/09BOGOLO/RHB/001
1. Road from NH5 toSambasivapuram
5Months: EarthWork, Pipe
Culverts, GSB
10 Months:WBM GrII, GrIIand Shoulders
15 Months:BT and Road
Furniture
OGPC+ Seal coat completed
Road from 9/6 ofJuvvaladinne R&B Road to11/0 of Juvvaladinne R&BRoad Via Venkateshpalem
OGPC+ Seal coat completed
NCRMP/B-W/AP/RHB/PRED/09/VIDAVALURU/005
1)Road from kt R&B ROADTO ALLAGANIPADU to
Vavilla 5Months: EarthWork, Pipe
Culverts, GSB
10 Months:WBM GrII, GrIIand Shoulders
15 Months:BT and Road
Furniture
WBM Gr-III is in progress!
Road from R&B roadKancharapalem HW to
Alaganipadu.Embankment is in progress
NCRMP/B-W/AP/RHB/PRED/09V.CHALEM/RHB/007
ROAD FROM SUVEPALLI-PUDIPARTHI ROAD TO
SRIKANTH COLONY 4Months: EarthWork, Pipe
Culverts, GSB
8 Months:WBM GrII, GrIIand Shoulders
12 Months:BT and Road
Furniture
OGPC+ Seal coat completed
providing BT Surface to theroad from R&B road to
Edagali KandrigaOGPC+ Seal coat completed
-
7/31/2019 11.July Mpr 2012
28/66
MONTHLY REPORT
27 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RHB/PRED/09CHITTAMURU/003
Road from R&B Road toMuttembake Via
Pittuvanipalli 5Months: EarthWork, Pipe
Culverts, GSB
10 Months:WBM GrII, GrII
and Shoulders
15 Months:BT and Road
Furniture
OGPC+ Seal coat completed
Road from R&B Chittamur toSoma Samudram
OGPC+ Seal coat completed
NCRMP/B-W/AP/09/MUTHUKUR/RHB/006
Road from R&B road toPatuvariKandriga
3Months: EarthWork, Pipe
Culverts, GSB
6 Months:WBM
GrII,GrII,CCPavement and
Shoulders
9 Months: BTand RoadFurniture
OGPC+ Seal coat completed
NCRMP/B-W/AP/09Allur/RHB/009Road from R&Broad alluru toGalidibbalu (via)Chukavani
dibba
5Months: EarthWork, Pipe
Culverts, GSB
10 Months:WBM GrII, GrIIand Shoulders
15 Months:BT and Road
FurnitureOGPC+ Seal coat completed
NCRMP/B-W/AP/RHB/PRED/009/T.P.GUDUR/012
Ring Road to TP Gudur-Salipeta R & B Road via CS
Puram and MandapamVillage 3Months: Earth
Work, PipeCulverts, GSB
6 Months:WBM
GrII,GrII,CCPavement and
Shoulders
9 Months: BTand RoadFurniture
OGPC+ Seal coat completed
Road from R & B Road C SPuram to Sivaramapuram
OGPC+ Seal coat completed
-
7/31/2019 11.July Mpr 2012
29/66
-
7/31/2019 11.July Mpr 2012
30/66
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
7.0 Details of Quality Control Audit Reports Submitted During this Month:
Package Number Name of Work District
NCRMP/B-
W/AP/MPCS/PRED/03/Payakaraopeta/003
Construction of cyclone shelter at
Ratnayampeta in Payakaraopeta
Vishakhapatnam
NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002
Providing BT surface to the road from
R&B Road to Kattubolu to Marripalem Vishakhapatnam
-
7/31/2019 11.July Mpr 2012
31/66
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RHB/ PRED/05/Narsapur/002
R&B road to Indira Nagar (via)
Pochamma temple of Narsapur
Mandal
West Godavari
NCRMP/B-W/AP/RHB/ PRED/05/Narsapur/002
Road from LB Cheria CC road to
Chillapalemm of LB Cheria of
Narsapur Mandal
West Godavari
NCRMP/B-W/AP/RHB/ PRED/05/Narsapur/002Road from R&B road to Pedalanka of
Narsapur MandalWest Godavari
NCRMP/B-W/AP/MPCS/PRED/08/NG
Padu/003
Construction of Cyclone shelter at
Thopupalem Kanaparthy in
Naguluppapadu Mandal
Prakasham
NCRMP/B-W/AP/Br/R&B/02/Puligadda/007
Construction of Minor Bridge at Km.
7/2 near Puligadda of Konada
Ramatheertham R&B Road to
Konathalapalem via Yerukonda,
Pasupam, Kollayavalsa (Z.P. Road) in
Vizianagaram District
Vizianagaram
NCRMP/B-W/AP/RCS/PRED/09/Kavali/006Road connecting R&B road through
Voturu villageNellore
NCRMP/B-W/AP/BR/R&B/08/Kanaparthy/012 Construction of HLB at Km 16/10 of
Naguluppalapadu Kanaparthy road
Prakasham
NCRMP/BW/AP/RHB/PRED/09/Vidavalur/005. Road from R&B road Alaganipadu to
Vavilla of Vidavalur of SPSR NelloreDist from KM 0.0 to KM 2.650
Nellore
NCRMP/B- Construction of cyclone shelter atVisakhapatnam
-
7/31/2019 11.July Mpr 2012
32/66
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-
W/AP/RCS/PRED/04/THONDANGI/004Road from R&B Road to Danavaipeta East Godavari
NCRMP/B-
W/AP/RCS/PRED/04/THONDANGI/004
Road from R&B Road to Gaddipeta of
Thondangi Mandal in East Godavari
District.
East Godavari
NCRMP/B-
W/AP/RCS/PRED/04/THONDANGI/004
Road from R&B Road to Hukumpeta
Cyclone ShelterEast Godavari
NCRMP/B-
W/AP/RCS/PRED/04/THONDANGI/004
Road from R&B Road to
K.ChodipallipetaEast Godavari
NCRMP/B-
W/AP/MPCS/PRED/04/Thondangi/001
Construction of Cyclone Shelter at
Lakshmanudipeta in Thondangi
Mandal, E.G.Dist.
East Godavari
NCRMP/B-
W/AP/RCS/PRED/04/THONDANGI/004
Road from R&B Road to
P.ChodipallipetaEast Godavari
NCRMP/B-
W/AP/MPCS/PRED/04/Uppalaguptam/002
Construction of Cyclone Shelter atPedaraghavulapeta in Uppalaguptam
Mandal, E.G.Dt.
East Godavari
NCRMP/B-
W/AP/RCS/PRED/04/Uppalaguptam/003.
Road from R & B road to
Chinaraghavulapeta Cyclone Shelter in
East Godavari District.
East Godavari
NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from Deppuru, Bahadapalli roadto Onkuluru & cyclone shelter.
Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/V Kotturu/002 R&B road to Devunthalada Srikakulam
-
7/31/2019 11.July Mpr 2012
33/66
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RHB/PRED/07/Nagaram/002Road from R&B road to
KaturivaripalemGuntur
NCRMP/B-W/AP/RHB/PRED/09/Bogole/002Road from 1/6 of Zuvvaladinne R&B
road to TellaguntaNellore
NCRMP/B-W/AP/RHB/PRED/09/Vidavalur/005Road from R&B Kancharapalem HW to
Alaganipadu of SPSR NelloreNellore
NCRMP/B-W/AP/RHB/PRED/09/Chittamuru/003
Road from R&B Chittamuru toSomasundaram
Nellore
NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002Road from Pakala R&B Road to
MosanaladinnePrakasam
NCRMP/B-
W/AP/RHB/PRED/03/Nakkapalli/002
Road from R&B Road to Mullaparra up
to Beach EndVishakhapatnam
NCRMP/B-
W/AP/RHB/PRED/03/Nakkapalli/001Road from Vempudi to Patimeeda Vishakhapatnam
NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006Road from R&B road to
VenkayyapalemVishakhapatnam
NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from R&B Road toChalivendradibba
Prakasam
NCR MP/B W/AP/RCS/PRED/09/Muthukur Road from R&B Road kappaladoruvu
-
7/31/2019 11.July Mpr 2012
34/66
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-
W/AP/RCS/PRED/08/Vetapalem/002
Road from NH to Challareddypalem in
PrakasamPrakasam
NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002Road from R&B road to Binginapalli
Harijanawada Cyclone shelterPrakasam
8.0 Details of Environmental and Social Reports Submitted During this Month:
Package Number Name of Work District
NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from NP Road to URK Puram Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002Road from Deppuru, Bahadapalli road
to Onkuluru & to Cyclone ShelterSrikakulam
NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from R&B Road to Devunalthada Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002Road from Pollada to Komaralthada &
to Cyclone ShelterSrikakulam
NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005Road from Koyyam R&B road to
MoosavanipetaSrikakulam
NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from Mentada to Donipeta Srikakulam
NCRMP/B-W/AP/RHB/PRED/01/Polaki/006 Road from R&B road Mobagam toDuubakavanipeta via Gajapathinagaram
Srikakulam
NCRMP/B-W/AP/RHB/PRED/01/Polaki/006Road from Talasamudram to Dola
Srikakulam
-
7/31/2019 11.July Mpr 2012
35/66
-
7/31/2019 11.July Mpr 2012
36/66
MONTHLY REPORT
35 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Consolidated E&S Report for East Godavari District in the Month of July 2012:
Third Party Quality Audit for Construction of Cyclone Shelters, Roads to
Cyclone Shelters & Habitations, Bridges and Culverts under NCRMP (Detailsof East Godavari in July, 2012)
S.No Activity Measures to be implemented by the contractor COMPLICEDNOT
COMPLICEDNOT
APPLICABLETOTAL
1Work Plan forEMPimplementation
The Contractors Project Manager shall be responsible forimplementation of EMP provisions and will coordinate the over-allimplementation of the said plan. Along with the Work Programme, theContractor shall submit a plan including method statement and timelineabout specific actions that will be taken by him to implement theprovisions laid out in the EMP
2 2
2RegulatoryPermissions andConsents
The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtainingpermission/consent for plants, water and extraction and borrow areasoperations. This includes:
Consent for establishment and operation of plant (for concretework) from SPCB.
2 2
PUC certification for all vehicles/equipment used for/duringconstruction.
2 2
Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations formaterials like sand and earth.
2 2
Permission for water extraction, if applicable in the local area
context. 2 2The Contractor shall abide by all conditions laid out in the said
clearances.2 2
3Consultation andCommunityConsent
The Contractor shall consult and obtain written consents oflandowners(individual/panchayat/govt. agency) for temporary use of landfor all construction related activities including:
a) Setting-up and operation of construction camp including labourcamps, stock yards etc.
2 2
-
7/31/2019 11.July Mpr 2012
37/66
MONTHLY REPORT
36 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
b) borrow areas and 2 2
c) Disposal of debris and other waste material. 2 2
4Construction/Labour Camp
a) Location: The camp and plant site/s location and establishment shallbe done in a manner that does not interfere or disturb the activities oflocal inhabitants, particularly those of schools and health facilities.Written permission (no objection certificate) shall be taken from theGramsabha and the land owner prior to location selection and a copyshall be submitted to the Engineer approval.
2 2
b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds.
c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks,Sanctuaries, Biosphere Reserves, Reserve Forests and Ramsar Sites)and Coastal Regulation Zone.
2 2
b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions of
Labour Laws. Separate toilet facilities shall be provided for womenworkers. If a common mess is not provided/operated additional space forcooking shall be provided. The contractor shall ensure that hygienicconditions are maintained during the operation of such camps/facilities.
2 2
c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp.
2 2
d) Potable water supply: Drinking water supply of at least 40Ipcd withthe required supply points shall be provided.
2 2
e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall beprovided by the contractor.
2 2
5 Site Clearance
a) NO tree cutting is to carried out without the written instruction fromthe Employer, who in turn will ensure that relevant regulatorypermission/s (including those from Forest Dept., if required) are obtainedprior to cutting of such trees.
2 2
b) The non-timber grade trees are to be stacked and possession is tobe given to Employer/concerned Govt. Department.
2 2
-
7/31/2019 11.July Mpr 2012
38/66
MONTHLY REPORT
37 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials.The top soil shall be reinstated in the cyclone shelter compound after theconstruction is over.
2
6Protection ofProperties andResources
The Contractor shall take due care to protect and prevent damages to
the following resources during preparatory and construction work:a) Water supply lines 1 1 2
b) Irrigation canals 1 1
c) Cart, cattle and/or foot trail/tracks 2 2
d) Cultural properties and sites/structures of religious importance 2 2
e) Houses, Farmlands, Orchids and/or Trees. 1 1 2
f) School and other existing buildings adjacent to the site ofconstruction.
2 2
In case of damage due to construction activity, the restoration/repairsshall be carried out by the contractor at his own cost.
2 2
7QuarryOperations
The Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shallbe submitted to the Engineer prior to procuring material.
2 2
8 Borrow Areas
a) Borrow areas for the project will be selected by the Contractorfollowing the stipulations given below: The finalisation of all suchlocations shall be dependent on the approval of the Engineer ontechnical and environmental grounds. This includes on-site verification tocross-check the accuracy of details provided by the contractor. Onlyafter receipt of the written approval from the Engineer, the Contractorshall enter into a formal agreement with landowner.
2 2
b) The Contractor shall not procure any kind of construction material(such as aggregates, sand and earth) from ecologically protected areas.
2 2
c) Identification and Selection:
1. The borrow area should not be located in agriculture fields/ unlessunavoidable i.e. barren land is not available. In case borrowing needs tobe done on an agricultural land, top-soil stripping, stacking andpreservation is must.
2 2
2. Borrow pits shall not be located within a distance of 100mts. Fromany NH, SH or other roads.
2 2
-
7/31/2019 11.July Mpr 2012
39/66
MONTHLY REPORT
38 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations.
2 2
4. No borrow pits shall be located within 500mts. from schools,colleges, playgrounds, religious structures and health centres.
2 2
5. No borrow area shall be opened with in 500mts. from a reserved or
protected forest area, protected sites, wildlife movement zone andcultural heritage site.
2 2
6. No tree cutting shall be undertaken. 2 2
7. Borrow area near any surface water body will be at least 100mts.away.
2 2
d) Operation
1. Area up to which material will be extracted shall be cleareddemarcated on ground.
2 2
2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 2 2
3. Borrowing of earth should be preferably limited to a depth of 1.5mtr
from the existing ground level.
2 2
4. Slope at the edges will be maintained not steeper than 2:3 (Vertical: Horizontal)
2 2
e) Rehabilitation of Borrow Areas:
1. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon
2 2
2. Preserved top soil has be spread uniformly over land (except incases where borrow area is developed as a water body) used as aborrow area.
2 2
9Water Extraction/Use
Water for construction and for use at construction camps (includinglabour camps) is to be extracted with prior written permission of(a) the
individual owner, in case the source is private well/tube well; (b) GramPanchayat in case the source belongs to community: and (c) IrrigationDepartment in case the source is an irrigation canal or river.
2 2
10Safety of RoadUsers and LocalResidents
a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety ofroad users and local people, particularly in the internal village roadswhich will be used for transporting materials.
2 2
-
7/31/2019 11.July Mpr 2012
40/66
MONTHLY REPORT
39 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
b) Material shall be covered during transportation to prevent spillage,accidents and pollution.
2 2
c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorised entry into the
construction.
2 2
11 Workers Safety
a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision andenforcement of appropriate personal protective equipment; first aidfacility; emergency response arrangement; proper storage ofhazardous/toxic and polluting materials and; measures for ensuring fireelectrical and mechanical safety arrangements in camp and in work site.
2 2
b) All methods steps and measures are required for ensuring safety ofworkers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.
2 2
c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site. 2 2
12 Air pollut ion a) Wind barriers or screens shall be provided in the downwinddirection at air pollution causing sources like plant sites and fine materialstorage stock yards
1 1 2
b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.
2 2
c) All plants and equipment shall comply with pollution control norms. 2 2
d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100mbefore the settlement)
2 2
13 Water Pollution
a) All measures (including provision of temporary silt fencing tocontrol sediment run-off) required for avoiding adverse impacts to waterbodies (such as ponds, streams, canals and rivers), water sources (suchas hand pumps and wells) and adjacent farmland shall be undertaken bythe Contractor.
1 1 2
b) Storage of materials like fuel, chemicals, and cement shall be donein a manner (with impervious layer on bottom and a covered shed ontop) that does not contaminate land and ground/surface water.
2 2
MONTHLY REPORT
-
7/31/2019 11.July Mpr 2012
41/66
MONTHLY REPORT
40 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
14 Noise Pollution
a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal toensure least disturbance to school children and other adjacent residents.
2
b) Ear plugs shall be provided to the labour facing risk from high
noise pollution such as plant site and those working near generators,heavy equipment /machinery.
2 2
c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimise noise during construction work and operationof camp.
2
15Disposal Debris/wastes
a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.
2
b) Location of Debris Disposal Sites: Debris disposal sites shall belocated preferably away from farmlands, water sources and waterbodies. In no case, debris shall be disposed within 500mts. ofecologically sensitive areas, including forests, wetlands and protected
natural habitats.
2
16Restoration andRehabilitation ofSites
All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.
2
Completion of work(as covered under clause 55.1 of GCC) will alsoinclude completion of rehabilitation and clean-up of the work sitesincluding camps, plants, in and around the construction site; disposal ofdebris/construction wastes at pre-approved locations and; restoration ofborrow areas and other sites/ locations used for material sourcing.
2
17 Liabilities
Any liability arising out of Contractors agreement with landowners/ localpeople/gram panchayat (including those related to temporary use ofland, water extraction and disposal of debris) shall be settled by theContractor.
2
MONTHLY REPORT
-
7/31/2019 11.July Mpr 2012
42/66
MONTHLY REPORT
41 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Consolidated E&S Report for Srikakulam District in the Month of July 2012:
Third Party Quality Audit for Construction of Cyclone Shelters, Roads toCyclone Shelters & Habitations, Bridges and Culverts under NCRMP (Detailsof Srikakulam in July, 2012)
S.No Activity Measures to be implemented by the contractor COMPLICEDNOT
COMPLICEDNOT
APPLICABLETOTAL
1Work Plan forEMPimplementation
The Contractors Project Manager shall be responsible forimplementation of EMP provisions and will coordinate the over-allimplementation of the said plan. Along with the Work Programme, theContractor shall submit a plan including method statement and timelineabout specific actions that will be taken by him to implement the
provisions laid out in the EMP
9 1 10
2RegulatoryPermissions andConsents
The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtainingpermission/consent for plants, water and extraction and borrow areasoperations. This includes:
Consent for establishment and operation of plant (for concretework) from SPCB.
10 10
PUC certification for all vehicles/equipment used for/duringconstruction.
9 1 10
Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations for
materials like sand and earth.
9 1 10
Permission for water extraction, if applicable in the local areacontext.
9 1 10
The Contractor shall abide by all conditions laid out in the saidclearances.
9 1 10
3Consultation andCommunityConsent
The Contractor shall consult and obtain written consents oflandowners(individual/panchayat/govt. agency) for temporary use of landfor all construction related activities including:
9 1 10
MONTHLY REPORT
-
7/31/2019 11.July Mpr 2012
43/66
MONTHLY REPORT
42 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
a) Setting-up and operation of construction camp including labourcamps, stock yards etc.
10 10
b) borrow areas and 9 1 10
c) Disposal of debris and other waste material. 9 1 10
4 Construction/Labour Camp
a) Location: The camp and plant site/s location and establishment shallbe done in a manner that does not interfere or disturb the activities oflocal inhabitants, particularly those of schools and health facilities.Written permission (no objection certificate) shall be taken from theGramsabha and the land owner prior to location selection and a copyshall be submitted to the Engineer approval.
10 10
b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds.
10 10
c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks,Sanctuaries, Biosphere Reserves, Reserve Forests and Ramsar Sites)and Coastal Regulation Zone.
10 10
b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions ofLabour Laws. Separate toilet facilities shall be provided for womenworkers. If a common mess is not provided/operated additional space forcooking shall be provided. The contractor shall ensure that hygienicconditions are maintained during the operation of such camps/facilities.
10 10
c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp.
10 10
d) Potable water supply: Drinking water supply of at least 40Ipcd withthe required supply points shall be provided.
10 10
e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall beprovided by the contractor.
10 10
5 Site Clearance
a) NO tree cutting is to carried out without the written instruction fromthe Employer, who in turn will ensure that relevant regulatorypermission/s (including those from Forest Dept., if required) are obtainedprior to cutting of such trees.
10 10
b) The non-timber grade trees are to be stacked and possession is tobe given to Employer/concerned Govt. Department.
10 10
MONTHLY REPORT
-
7/31/2019 11.July Mpr 2012
44/66
MONTHLY REPORT
43 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials.The top soil shall be reinstated in the cyclone shelter compound after theconstruction is over.
9 1 10
6Protection ofProperties andResources
The Contractor shall take due care to protect and prevent damages to
the following resources during preparatory and construction work:a) Water supply lines 10 10
b) Irrigation canals 10 10
c) Cart, cattle and/or foot trail/tracks 10 10
d) Cultural properties and sites/structures of religious importance 2 8 10
e) Houses, Farmlands, Orchids and/or Trees. 2 8 10
f) School and other existing buildings adjacent to the site ofconstruction.
2 8 10
In case of damage due to construction activity, the restoration/repairsshall be carried out by the contractor at his own cost.
9 1 10
7QuarryOperations
The Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shallbe submitted to the Engineer prior to procuring material.
9 1 10
8 Borrow Areas
a) Borrow areas for the project will be selected by the Contractorfollowing the stipulations given below: The finalisation of all suchlocations shall be dependent on the approval of the Engineer ontechnical and environmental grounds. This includes on-site verification tocross-check the accuracy of details provided by the contractor. Onlyafter receipt of the written approval from the Engineer, the Contractorshall enter into a formal agreement with landowner.
9 1 10
b) The Contractor shall not procure any kind of construction material(such as aggregates, sand and earth) from ecologically protected areas.
9 1 10
c) Identification and Selection:
1. The borrow area should not be located in agriculture fields/ unlessunavoidable i.e. barren land is not available. In case borrowing needs tobe done on an agricultural land, top-soil stripping, stacking andpreservation is must.
9 1 10
2. Borrow pits shall not be located within a distance of 100mts. Fromany NH, SH or other roads.
9 1 10
MONTHLY REPORT
-
7/31/2019 11.July Mpr 2012
45/66
MONTHLY REPORT
44 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations.
9 1 10
4. No borrow pits shall be located within 500mts. from schools,colleges, playgrounds, religious structures and health centres.
9 1 10
5. No borrow area shall be opened with in 500mts. from a reserved or
protected forest area, protected sites, wildlife movement zone andcultural heritage site.
9 1 10
6. No tree cutting shall be undertaken. 9 1 10
7. Borrow area near any surface water body will be at least 100mts.away.
9 1 10
d) Operation
1. Area up to which material will be extracted shall be cleareddemarcated on ground.
9 1 10
2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 9 1 10
3. Borrowing of earth should be preferably limited to a depth of 1.5mtrfrom the existing ground level.
9 1 10
4. Slope at the edges will be maintained not steeper than 2:3 (Vertical: Horizontal)
9 1 10
e) Rehabilitation of Borrow Areas:
1. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon
9 1 10
2. Preserved top soil has be spread uniformly over land (except incases where borrow area is developed as a water body) used as aborrow area.
9 1 10
9
Water Extraction
/Use
Water for construction and for use at construction camps (includinglabour camps) is to be extracted with prior written permission of(a) the
individual owner, in case the source is private well/tube well; (b) GramPanchayat in case the source belongs to community: and (c) IrrigationDepartment in case the source is an irrigation canal or river.
9 1 10
10Safety of RoadUsers and LocalResidents
a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety ofroad users and local people, particularly in the internal village roadswhich will be used for transporting materials.
9 1 10
MONTHLY REPORT
-
7/31/2019 11.July Mpr 2012
46/66
MONTHLY REPORT
45 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
b) Material shall be covered during transportation to prevent spillage,accidents and pollution.
9 1 10
c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorised entry into the
construction.
9 1 10
11 Workers Safety
a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision andenforcement of appropriate personal protective equipment; first aidfacility; emergency response arrangement; proper storage ofhazardous/toxic and polluting materials and; measures for ensuring fireelectrical and mechanical safety arrangements in camp and in work site.
9 1 10
b) All methods steps and measures are required for ensuring safety ofworkers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.
9 1 10
c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site. 9 1 10
12 Air pollution a) Wind barriers or screens shall be provided in the downwinddirection at air pollution causing sources like plant sites and fine materialstorage stock yards
9 1 10
b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.
9 1 10
c) All plants and equipment shall comply with pollution control norms. 9 1 10
d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100mbefore the settlement)
9 1 10
13 Water Pollution
a) All measures (including provision of temporary silt fencing tocontrol sediment run-off) required for avoiding adverse impacts to waterbodies (such as ponds, streams, canals and rivers), water sources (suchas hand pumps and wells) and adjacent farmland shall be undertaken bythe Contractor.
9 1 10
b) Storage of materials like fuel, chemicals, and cement shall be donein a manner (with impervious layer on bottom and a covered shed ontop) that does not contaminate land and ground/surface water.
9 1 10
MONTHLY REPORT
-
7/31/2019 11.July Mpr 2012
47/66
MONTHLY REPORT
46 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
14 Noise Pollution
a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal toensure least disturbance to school children and other adjacent residents.
9 1 10
b) Ear plugs shall be provided to the labour facing risk from high
noise pollution such as plant site and those working near generators,heavy equipment /machinery.
9 1 10
c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimise noise during construction work and operationof camp.
10 10
15Disposal Debris/wastes
a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.
9 1 10
b) Location of Debris Disposal Sites: Debris disposal sites shall belocated preferably away from farmlands, water sources and waterbodies. In no case, debris shall be disposed within 500mts. ofecologically sensitive areas, including forests, wetlands and protected
natural habitats.
9 1 10
16Restoration andRehabilitation ofSites
All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.
9 1 10
Completion of work(as covered under clause 55.1 of GCC) will alsoinclude completion of rehabilitation and clean-up of the work sitesincluding camps, plants, in and around the construction site; disposal ofdebris/construction wastes at pre-approved locations and; restoration ofborrow areas and other sites/ locations used for material sourcing.
9 1 10
17 Liabilities
Any liability arising out of Contractors agreement with landowners/ local
people/gram panchayat (including those related to temporary use ofland, water extraction and disposal of debris) shall be settled by theContractor.
9 1 10
-
7/31/2019 11.July Mpr 2012
48/66
-
7/31/2019 11.July Mpr 2012
49/66
MONTHLY REPORT
-
7/31/2019 11.July Mpr 2012
50/66
MONTHLY REPORT
49 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials.The top soil shall be reinstated in the cyclone shelter compound after theconstruction is over.
1 1
6Protection ofProperties andResources
The Contractor shall take due care to protect and prevent damages to
the following resources during preparatory and construction work:a) Water supply lines 1 1
b) Irrigation canals 1
c) Cart, cattle and/or foot trail/tracks 1 1
d) Cultural properties and sites/structures of religious importance 1 1
e) Houses, Farmlands, Orchids and/or Trees. 1 1
f) School and other existing buildings adjacent to the site ofconstruction.
1 1
In case of damage due to construction activity, the restoration/repairsshall be carried out by the contractor at his own cost.
1 1
7QuarryOperations
The Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shallbe submitted to the Engineer prior to procuring material.
1 1
8 Borrow Areas
a) Borrow areas for the project will be selected by the Contractorfollowing the stipulations given below: The finalisation of all suchlocations shall be dependent on the approval of the Engineer ontechnical and environmental grounds. This includes on-site verification tocross-check the accuracy of details provided by the contractor. Onlyafter receipt of the written approval from the Engineer, the Contractorshall enter into a formal agreement with landowner.
1 1
b) The Contractor shall not procure any kind of construction material(such as aggregates, sand and earth) from ecologically protected areas.
1 1
c) Identification and Selection:
1. The borrow area should not be located in agriculture fields/ unlessunavoidable i.e. barren land is not available. In case borrowing needs tobe done on an agricultural land, top-soil stripping, stacking andpreservation is must.
1 1
2. Borrow pits shall not be located within a distance of 100mts. Fromany NH, SH or other roads.
1 1
MONTHLY REPORT
-
7/31/2019 11.July Mpr 2012
51/66
50 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations.
1 1
4. No borrow pits shall be located within 500mts. from schools,colleges, playgrounds, religious structures and health centres.
1 1
5. No borrow area shall be opened with in 500mts. from a reserved or
protected forest area, protected sites, wildlife movement zone andcultural heritage site.
1 1
6. No tree cutting shall be undertaken. 1 1
7. Borrow area near any surface water body will be at least 100mts.away.
1 1
d) Operation
1. Area up to which material will be extracted shall be cleareddemarcated on ground.
1 1
2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 1 1
3. Borrowing of earth should be preferably limited to a depth of 1.5mtrfrom the existing ground level.
1 1
4. Slope at the edges will be maintained not steeper than 2:3 (Vertical: Horizontal)
1 1
e) Rehabilitation of Borrow Areas: 1
1. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon
1 1
2. Preserved top soil has be spread uniformly over land (except incases where borrow area is developed as a water body) used as aborrow area.
1 1
9
Water Extraction
/Use
Water for construction and for use at construction camps (includinglabour camps) is to be extracted with prior written permission of(a) the
individual owner, in case the source is private well/tube well; (b) GramPanchayat in case the source belongs to community: and (c) IrrigationDepartment in case the source is an irrigation canal or river.
1 1
10Safety of RoadUsers and LocalResidents
a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety ofroad users and local people, particularly in the internal village roadswhich will be used for transporting materials.
1 1
-
7/31/2019 11.July Mpr 2012
52/66
MONTHLY REPORT
-
7/31/2019 11.July Mpr 2012
53/66
52 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
14 Noise Pollution
a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal toensure least disturbance to school children and other adjacent residents.
1 1
b) Ear plugs shall be provided to the labour facing risk from high
noise pollution such as plant site and those working near generators,heavy equipment /machinery.
1 1
c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimise noise during construction work and operationof camp.
1 1
15Disposal Debris/wastes
a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.
1 1
b) Location of Debris Disposal Sites: Debris disposal sites shall belocated preferably away from farmlands, water sources and waterbodies. In no case, debris shall be disposed within 500mts. ofecologically sensitive areas, including forests, wetlands and protected
natural habitats.
1 1
16Restoration andRehabilitation ofSites
All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.
1 1
Completion of work(as covered under clause 55.1 of GCC) will alsoinclude completion of rehabilitation and clean-up of the work sitesincluding camps, plants, in and around the construction site; disposal ofdebris/construction wastes at pre-approved locations and; restoration ofborrow areas and other sites/ locations used for material sourcing.
1 1
17 Liabilities
Any liability arising out of Contractors agreement with landowners/ local
people/gram panchayat ( including those related to temporary use ofland, water extraction and disposal of debris) shall be settled by theContractor.
1 1
MONTHLY REPORT
-
7/31/2019 11.July Mpr 2012
54/66
53 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
9.0 Statement Showing the Inspections and Site Visits of Districts during the Month of July -2012
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN SRIKAKULAM
DISTRICT DURING THE MONTH OF JULY 2012
S
NO
.
PACKAGE NO NAME OF WORK
TPQA INSPECTIONS
DURING THIS MONTH
DATES OF
VISIT
NO. OF
VISITS
1NCRMP/B-
W/AP/RHB/PRED/01/Santhabommali/003
Road from Borubadra, Malagam road to Kollipadu via Seepuram,
Gantapeta in Santhabommali Mandal04.07.12 1
2 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from Mentada to Dovupeta in EtcherlaMandal05.07.12,
25.07.122
3NCRMP/B-
W/AP/MPCS/PRED/01/Santhabommali/005Construction of Cyclone shelter at Runku in Santhabommali Mandal.
06.07.12,
13.07.12,14.07.12,
17.07.12,
25.07.12
5
4 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from Pollada to Komaralthada & to cyclonic shelter.07.07.12,
17.07.122
5 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from R&B Road to Devunthalada.
10.07.12,
11.07.12,
17.07.12,
25.07.12
4
6 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002Road from Deppuru, Bahadapalli road to Onkuluru & cyclone
shelter.
16.07.12,17.
07.12,
19.07.12
3
7NCRMP/B-
W/AP/MPCS/PRED/01/Santhabommali/005
Construction of Cyclone shelter at Kollipadu in Santhabommali
Mandal.23.07.12 1
MONTHLY REPORT
-
7/31/2019 11.July Mpr 2012
55/66
54 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
8 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from NP Road to URK Puram17.07.12,
25.07.122
9 NCRMP/B_W/AP/Br/R&B/01/Bendigadda/004Construction of High level Bridge across Bendigadda at km 4/10 of
Pundi-Parlakimidi road in Srikakulam Dist.
17.07.12,
30.07.122
10 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005Road from Kotcherla road to Pathesundrapalem
25.07.12 1
11 NCRMP/B_W/AP/Br/R&B/01/Surampeta/003 Construction of Minor Bridge at km 12/2-4 of NH-5 to Surampeta
road via Naruva,Mentada25.07.12 1
12 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/006 Road from Talasamudram to Dola regulator 28.07.12 1
TOTAL 25
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VIJAYANAGARAM
DISTRICT DURING THE MONTH OF JULY 2012
S NO. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THIS
MONTH
DATES OF VISIT NO. OF VISITS
1
NCRMP/ B-W/ AP/ Br/ R&B/ 02/
Chakaligadda / 008
Construction of Minor Bridge at Km 15/2 near Chakaligadda
of Konada Ramatheertham R&B road to Konathalapalem(via) Yerukonda, Pasupam, Kollayavalsa (ZP Road)
25-07-2012 1
2NCRMP/B-W/ AP/ Br/ R&B/ 02/ Puligadda/
007
Construction of Minor Bridge at Km. 7/2 near Puligadda ofKonada Ramatheertham R&B Road to Konathalapalem via
Yerukonda, Pasupam, Kollayavalsa (Z.P. Road)25-07-2012 1
TOTAL 2
MONTHLY REPORT
-
7/31/2019 11.July Mpr 2012
56/66
55 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VISHAKAPATNAM
DISTRICT DURING THE MONTH OF JULY 2012
S NO. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING
THIS MONTH
DATES OF VISITNO. OF
VISITS
1NCRMP/B-
W/AP/MPCS/PRED/03/Payakaraopeta/003
Construction of cyclone shelter at Ratnayampeta in Payakaraopeta
Mandal
07.07.12
13.07.122
2NCRMP/B-
W/AP/MPCS/PRED/03/Nakkapalli/002Construction of cyclone shelter at Patimeeda in Nakkapalli Mandal
07.07.12
10.07.12
13.07.12
24.07.12
4
3NCRMP/B-
W/AP/MPCS/PRED/03/Nakkapalli/002Construction of cyclone shelter at Mullaparra in Nakkapalli Mandal
07.07.12
10.07.12
13.07.12
23.07.12
24.07.12
5
4NCRMP/B-
W/AP/MPCS/PRED/03/Payakaraopeta/003
Construction of cyclone shelter at Gajapathinagaram in
Payakaraopeta Mandal
07.07.12
13.07.122
5NCRMP/B-
W/AP/MPCS/PRED/03/Nakkapalli/002
Construction of cyclone shelter at Bangarampeta in Nakkapalli
Mandal
19.07.12
23.07.1224.07.12
3
6 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/004Construction of cyclone shelter at Venkayyapalem in Rambilli
Mandal
11.07.12
24.07.122
MONTHLY REPORT
-
7/31/2019 11.July Mpr 2012
57/66
56 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
7 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002Road from R & B road to Kattubolu to Marripalem in Rambilli
Mandal
09.07.12
13.07.12
19.07.12
21.07.12
24.07.12
5
8 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 Road from R & B road to Rajakoduru in Rambilli Mandal
09.07.12
13.07.12
24.07.12
3
9NCRMP/B-
W/AP/RHB/PRED/03/Nakkapalli/001Road from Vempadu to Patimeeda in Nakkapalli Mandal 24.07.12 1
10NCRMP/B-
W/AP/RHB/PRED/03/Nakkapalli/002
Road from R&B road to Mullaparra up to Beach end in Nakkapalli
Mandal24.07.12 1
11 NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006 Road from R & B road t o Venkayyapalem in Rambilli Mandal 24.07.12 1
TOTAL 29
MONTHLY REPORT
-
7/31/2019 11.July Mpr 2012
58/66
57 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS OF EAST GODAVARI
DISTRICT DURING THE MONTH OF JULY 2012
S NO. PACKAGE NO NAME OF WORKTPQA INSPECTIONS DURING THIS MONTH
DATES OF VISITNO. OF
VISITS
1
NCRMP/B-W /AP/RCS/PRED/04/
Thondangi/004
Road from R&B Road to P.Chodipallipeta
CS10.07.2012 and 24.07.2012 2
2Road from R&B Road to K.Chodipallipeta
CS10.07.2012 and 24.07.2012 2
3 Road from R&B Road to Hukumpeta CS 10.07.2012 and 24.07.2012 2
4 Road from R&B Road to Gaddipeta CS 10.07.2012 and 24.07.2012 2
5 Road from R&B Road to Dana