50000 MW Hydroelectric Initiatives

download 50000 MW Hydroelectric Initiatives

of 24

Transcript of 50000 MW Hydroelectric Initiatives

  • 8/14/2019 50000 MW Hydroelectric Initiatives

    1/24

    1.0 Power Sector Development in India

    21.1 Advantages of Hydro Power 3

    1.2 Need for Hydro Share Correction 3

    1.3 Investment Step up 4

    2.0 Hydro Development

    2.1 Initiatives Taken by the Government for Hydro Power Development 5

    2.2 First Hydroelectric Survey of India (1953-59) 7

    2.3 Reassessment of Hydroelectric Potential (1978-87) 7

    2.4 Categorisation of Hydroelectric Potential: Ranking Study 8

    3.0 Feasibility Studies

    3.1 Identification of Projects for PFRs 10

    3.2 The Next Step 10

    3.3 Contents of Preliminary Feasibility Reports 10

    3.4 Preparation of Preliminary Feasibility Reports of Hydroelectric Projects- theMethodology and Responsibility of each 12

    3.5 Consultants 15 3.6 Summary of PFRs Entrusted to the Consultants 17

    3.7 Review Mechanism 17

    4.0 Implementation of Projects 18

    Annex -I Regionwise/ Statewise Breakup of Ranking Study 19

    Annex -II Statewise/ Consultant wise Breakup of Schemes for Preparation of PFRs 20

    CONTENTS

  • 8/14/2019 50000 MW Hydroelectric Initiatives

    2/24

  • 8/14/2019 50000 MW Hydroelectric Initiatives

    3/24

  • 8/14/2019 50000 MW Hydroelectric Initiatives

    4/24

    4

    Gross budgetary Support (GBS) and Plan Outlay (Rs. Crs.)

    1.3 Investment Step up

    In view of the various geological risks and engineering difficulties that are encountered in the developmentof hydroelectric power projects, private sector development has been slow in spite of good enthusiasm andincentives. Consequently, hydro power development has been taken up primarily through the public sector

    in the 10

    th

    & 11

    th

    Plans. The Central public sector outlay for hydro power development has been enhancedfrom Rs. 12,306 Crs. to Rs. 25,839 Crs. and Budgetary support from Rs. 9,284 Crs. to Rs. 17,511 Crs.during the 10th Plan as compared to that in the 9th Plan.

  • 8/14/2019 50000 MW Hydroelectric Initiatives

    5/24

    5

    2.0 Hydro Development

    2.1 Initiatives taken by the Government for Hydro Power Development

    To encourage greater participation by Indian and foreign entrepreneurs in hydroelectric power generation, anumber of measures have been taken by the Government for increasing the hydro capacity :

    a) Policy Liberalisation

    To accelerate capacity addition in the Power Sector, a policy to encourage greater participation by privateentrepreneurs in India and abroad in electric power generation has been announced. The Government hasissued notifications for hydro projects incorporating several incentives to private developers which broadlycover incentives for better availability of machines, for generation of extra energy above design energy,compensation for hydrological risks, etc.

    i) Policy on Hydro Power Development

    A Hydro Policy was announced in Aug.1998 for the development of hydro power incorporating severalenabling steps and measures. The Hydro Policy among other things lays emphasis on basin wise development,evolving consensus on inter-state issues, mitigation of geological risks, simplified procedure for transfer ofclearances, promoting joint venture arrangements etc. Main features of the policy are as under:

    Additional budgetary support for ongoing and new Hydro Projects under Central PSUs.

    Creation of Power Development Fund by levying cess on electricity generated in the country.

    Basin-wise Development of hydro Potential.

    Advance action for Capacity Addition in the 10thPlan & beyond.

    Emphasis on Survey & Investigations.

    Resolution of Inter-State issues.

    Renovation, Modernisation & Uprating of existing hydro stations.

    Promoting Small & Mini Hydel Projects.

    Simplified Procedures for Transfer of Clearances by CEA.

    Rationalisation of Hydro Tariff by allowing premium on sale rate during peak period.

    Realistic estimates of completion cost considering geological surprises.

    Promoting Hydel Projects with Joint Ventures.

    Selection of Developer through MOU/Bidding route.

    Govt. Support for Land Acquisition, Resettlement and Rehabilitation, Catchment Area Development etc.

    Some of the measures announced by Govt. of India have already been introduced which include SimplifiedProcedures for transfer of Techno-Economic Clearances, Streamlining of Clearance process and introduction ofThree-Stage Clearance approach for development of hydro Projects in Central Sector/ Joint Ventures etc.

    The CERC has approved 5% hydro development surcharge on annual fixed charges for central hydro power

    generation.

  • 8/14/2019 50000 MW Hydroelectric Initiatives

    6/24

    6

    ii) Three Stage Clearance Procedure

    The Government has also approved a Three Stage Clearance procedure for hydro projects to be executed bythe CPSUs in consultation with the Ministries of Finance and Environment and Forests. Under Stage-I, theCPSUs will incur expenditure on survey, investigation and preparation of a pre-feasibility report. Under

    Stage-II, the CPSUs will undertake activities relating to detailed investigation and preparation of Detailed ProjectReport. During this Stage, pre-construction activities and infrastructure development including land acquisition willalso be undertaken. Under Stage-III, investment sanction will be accorded through the PIB/ CCEA.

    iii) The investment policy has been made more attractive from time to time and provides for (i) Debt:Equity ratioup to 4:1 (ii) 100% foreign equity participation (iii) liberalized rates of depreciation in respect of assets (iv)import of equipment for power projects at concessional customs duty (v) 16% rate of return on equity (vi)Generating companies can sell power on the basis of a suitably structured two part tariff - one part to coverfixed costs and the other to cover variable costs at a prescribed level of performance.

    iv) Since hydroelectric projects have lower internal rate of return compared to the thermal and gas based

    projects, the Government has notified new norms for incentives where the availability factor threshold hasbeen reduced from 90% to 85%. Similarly, the sale rate of secondary energy has been notified at the samerate as primary energy.

    v) The procedures relating to transfer of clearances from State Government to Central Public Sector Undertakingsand State Government to Private Sector have been simplified. Under the revised guidelines, clearance isautomatically transferred to the new agency if the scope of work has not changed and CEA only examinesthe revised cost and financial package of the new proposal before transferring the clearance.

    vi) Ceiling limits of capital costs upto which techno-economic clearance of CEA is not required has beenenhanced, inter-alia, for hydro projects. According to the present notification issued under Section 29 of theElectricity (Supply) Act, 1948, hydro projects are covered by the following limits :

    Rs. 250 Crores for projects awarded through the MOU route.

    Rs. 1,000 Crores for projects awarded through competitive bidding.

    Rs. 2,500 Crores for projects whose tariff is determined by the CERC/ SERCs.

    All hydro-electric projects utilizing water of inter-state rivers shall be submitted to CEA for its concurrence

    (irrespective of capital cost).

    b) Creation of Power Utilities in Central Sector

    Government has taken many steps and measures to boost Hydro Power Development. Hydro power

    corporations in the central sector and the joint sector (central and state) National Hydro-electric Power

    Corporation (NHPC), North-Eastern Electric Power Corporation (NEEPCO), Nathpa-Jhakri Power Corporation

    (NJPC) renamed as Satluj Jal Vidut Nigam Limited (SJVNL) and Tehri Hydro Development Corporation (THDC)

    have been created. Besides, National Thermal Power Corporation Ltd. (NTPC) has also been authorised to

    take up hydro projects (Kol Dam). Narmada Hydro Development Corporation (NHDC), a joint venture of

    NHPC and MP Govt. has been constituted to implement Indirasagar (1000 MW) and Omkareshwar

    (520 MW) HE projects.

  • 8/14/2019 50000 MW Hydroelectric Initiatives

    7/24

    7

    2.2 First Hydroelectric Survey of India (1953-59)

    The first systematic Hydro Electric Survey of India was undertaken by the erstwhile Central Water & Power

    Commission (CW&PC) during1953-59. According to this survey, Hydro Electric Potential of the country was

    assessed as about 42 Million kW from a total of about 250 schemes. The results of the first survey proved

    useful in chartering the course of hydroelectric development of the country for about two decades.

    2.3 Reassessment of Hydroelectric Potential (1978-87)

    The Reassessment Studies (1978-87) of Hydro Electric Potential were undertaken by Central ElectricityAuthority (CEA) on the advice of Planning Commission which had expressed concern over the lack ofavailability of up to date data regarding hydro electric potential of the country.

    Planning Commission had opined that in view of the spurt in fuel cost and technical advancements madein hydro project construction, some of the hydel schemes not considered economically attractive in the fifties

    would have since become viable.

    The countrys power system had experienced tremendous growth and regional grid networks increased theenergy utilization capability.

    Very useful hydrological, meterological and other related data was also available consequent to large-scaledevelopment of water resources in the country during fifties & sixties.

    The scope of the Reassessment Studies also included Assessment of Gross Theoretical Potential, SecondaryEnergy contribution and Identification of possible sites for Pumped Storage development in addition toassessment of economic potential and computation of annual energy contribution in dependable and average

    flow conditions.

    The Reassessment Study completed in 1987 revealed that the Hydro Electric Power Potential of thecountry was of the order of about 84 million kW from a total of 845 schemes as against 42 million kWfrom 250 schemes identified at the time of the first survey. 56 sites for development of Pumped StorageSchemes with total likely installed capacity of about 94,000 MW were also identified in various regions ofthe country.

  • 8/14/2019 50000 MW Hydroelectric Initiatives

    8/24

    8

    River Basin-wise Hydroelectric Power Potential Identified in Reassessment Studies

    River Basin No. of Potential at 60% load Date of Completion

    Schemes factor (MW) of Study

    Indus 190 19,988 March, 1983

    Brahmaputra 226 34,920 January, 1984Ganga 142 10,715 August, 1984

    Central Indian 53 2,740 June, 1985

    River

    West Flowing Rivers 94 6,149 November, 1985

    of Southern India

    East flowing Rivers 140 9,532 April, 1986

    of Southern India

    Total 845 84,044

    (equivalent Installed capacity-1,50,000 MW)Pumped Storage

    Scheme sites 56 94,000 MW August, 1984

    2.4 Categorisation of Hydroelectric Potential: Ranking Studies

    To give necessary fillip for development of the balance Hydroelectric schemes, CEA undertook RankingStudies to determine inter-se priority for their development. The objective of this exercise was to facilitateidentification of the projects for implementation in order of their priority so that hydro development couldbe taken up in appropriate sequence.

    2.4.1 Projects Identified

    With a view to prioritise the large number of identified schemes to harness vast untapped hydro resourcesin the order of their attractiveness for implementation, ranking studies were carried by CEA and 399schemes were prioritised under categories A, B & C. Category-A schemes were considered moreattractive than Category-B schemes and Category-B schemes being more attractive than Category-C schemes. The studies were carried out in consultation with Ministry of Environment & Forest, CentralWater Commission, Geological Survey of India, National Remote Sensing Agency, Survey of India etc. TheRanking Study gives inter-se prioritisation of the projects which could be considered for further implementationincluding their survey & investigation so that hydro power development is effected in an appropriate

    sequence. The Ranking Study was completed in 2001-02.2.4.2 Process of Ranking Study

    Ranking Study generally involved sophisticated desk studies of all secondary topographical and hydrologicaldata. For this purpose latest topo sheets were obtained from Survey of India. In addition, Satellite imagerieswere also obtained from NRSA for Indus Basin.

    Ten major aspects pertaining to development of the identified projects, which play vital role in theimplementation of the hydro projects were adopted in the criteria considered for ranking study. For eachof the criteria, certain marks with weightage ranging from minimum of 6 to maximum of 15 were allotted.These aspects are R&R Aspects, International Aspects, Inter-state Aspects, Potential of the Scheme, Type ofScheme, Height of Dam, Length of Tunnel/Channel, Accessibility to Site, Status of the Project, Status of

  • 8/14/2019 50000 MW Hydroelectric Initiatives

    9/24

    9

    Upstream or Downstream Hydel Development. These criteria were discussed in detail at a ConsultationForum involving various organisations from different spheres involving technical/ commercial/ financialinstitutions/ confederations/ associations/ utilities/ experts and bodies.

    On the basis of the Marks obtained, schemes were ranked into A, B and C categories as below:

    Category Total Marks

    A 80 & above

    B 60 to 79

    C 40 to 59

    2.4.3 Conclusions

    The River Basin-wise summary of categorisation of the schemes ranked by CEA is givenbelow:

    River Basin-wise Summary of Categorisation of the Schemes Ranked by CEA

    Sl. River system Category A Category B Category C Total

    No. Nos MW Nos MW Nos MW Nos. MW1 Indus 11 4088 51 8811 17 6080 79 18979

    2 Ganga 20 2023 54 9616 1 600 75 12239

    3 Central Indian 3 283 9 1425 1 186 13 1894

    4 East Flowing 11 1412 26 6469 2 88 39 7969

    5 West Flowing 1 35 10 958 14 1508 25 2501

    6 Brahmaputra 52 7800 97 42574 19 12954 168 63328

    Total: 98 15641 247 69853 54 21416 399 106910

    State-wise break up of results of Ranking Studies is given in Annex.-I

  • 8/14/2019 50000 MW Hydroelectric Initiatives

    10/24

    10

    3.0 Feasibility Studies

    Based on the preliminary ranking study, the Preliminary Feasibility Reports (PFRs) of selected schemes arebeing prepared incorporating the general description of the schemes, essential drawings, engineering aspects,approximate estimated cost and economic evaluation.

    3.1 Identification of Projects for PFRs

    Projects Identification

    Ranking study carried out by CEA covered 399 Hydro Electric Potential sites with total installed capacity ofabout 1,07,000 MW.

    The results of the Ranking study were discussed at length in a consultation process initiated byMinistry of Power and CEA with various state agencies, CPSUs & other organizations. As a follow up ofthe ranking studies, it was considered appropriate that for development of balance hydro projects in a

    systematic manner, shelf of viable projects needs to be made available so that the same could beoffered for development to prospective entrepreneurs in India and abroad. Two rounds of discussions wereheld in CEA to elicit the views of state authorities/ CPSUs regarding their programme and preparedness totake up hydro power development. Separate consultations were also held with states possessingvast untapped hydro electric potential namely Arunachal Pradesh, Uttaranchal, Himachal Pradesh and Jammu& Kashmir.

    Based on deliberations during the above meetings, it was considered appropriate that Preliminary FeasibilityReports (PFRs) of selected hydro electric projects may be taken up so that feasibility of the scheme consideredin ranking studies could be established.

    In the first instance, PFR formulation of 162 HE schemes has been taken up. Schemes, identified by StateAuthorities/CEA for which S&I are either in initial stages or are yet to be taken up have been consideredfor PFR formulation. Schemes for which DPRs have either been prepared or returned, are generally notincluded under the proposed studies. Schemes for which S&I is in advance stage and DPRs are likely to beformulated shortly, have also not been included in the proposed study. The schemes to be studied for PFRshave a likely installed capacity above 50 MW.

    3.2 The Next Step

    The Preliminary Feasibility Reports will provide information on hydroelectric schemes which are yet to bedeveloped and enable their prioritisation for further action for implementation. The PFRs would also provideuseful information to prospective developers for taking up detailed Survey & Investigation and DPR

    formulation. Results of studies would thus facilitate development of balance hydro electric potential in thecountry in order of the viability/ attractiveness.

    After completion of studies for PFRs, action for taking up detailed S&I and DPR preparation would be initiatedfor schemes considered viable. This is considered essential to generate a shelf of projects which could betaken up for execution during 11thand 12thPlans and beyond.

    3.3 Contents of the Preliminary Feasibility Reports

    The Preliminary Feasibility Report (PFR) of hydroelectric projects would be prepared for various rivers/basins/ sub-basins based on which further work on the projects would be taken up. The different

  • 8/14/2019 50000 MW Hydroelectric Initiatives

    11/24

    11

    aspects to be covered under PFRs are as below :-

    General Project Features

    Salient features of the projectBackground Information

    General Information about the area, river basin/ sub-basinPower Scenario & Existing InstallationsNecessity of the project and related aspects.

    Project Area

    Description of Project including river systemSocio-economic & other aspects.

    Topographic & Geo-technical Aspects

    Regional, Topographical & Geo-technical features of Project AreaTopographical / Geo-technical aspects for locating component structures of the projectSeismicity

    HydrologyWater Availability, Studies based on available meterological/ hydrological data of project/ adjoining areaSedimentation Studies.Design Flood Studies.

    Conceptual Layout and Planning

    Conceptual layout of various project components viz. Diversion/ Storage structure, Water conductor system,Power house, Tail race, etc.

    Preliminary design features to arrive at broad parameters of the project components.Preliminary Drawings showing Project Component and Features

    Power Potential Studies

    Power Potential Studies considering various alternative scenarios and project features.Optimization Studies for selection of installed capacity, Size and No. of generating Units.

    Power Evacuation

    Appraisal of Existing Power Evacuation facilities.Proposed Evacuation Arrangement to the nearest facility

    Environmental Aspects

    Brief description of Environmental impacts of the project on Forestry, Land use, Wild life, etc.R&R AspectsMitigation measures.

    Infrastructure

    Identification of broad infrastructure requirement for implementation of the project.Construction Planning & Schedule

    General Approach for construction planning for execution of Project Components.Construction Schedule.

    Cost Estimates

    Preliminary Cost Estimates for Civil,Hydro-mechanical, Electro-mechanical works, etc.Power Evacuation Facility.

    Economic Evaluation

    Power and energy benefits and financial evaluation of the project.Tariff computation.

  • 8/14/2019 50000 MW Hydroelectric Initiatives

    12/24

    12

    3.4 Preparation of Preliminary Feasibility Reports of Hydroelectric Projects - theMethodology and Responsibility of each

    Preliminary Feasibility Reports of hydroelectric projects are to be prepared by Consultant and shall coverthefollowing activities :-

    3.4.1 Work Identification and Responsibilities

    A) Feasibility Report

    1. General Report2. Water Availability3. Vetting/ review of Water Availability by CWC.4. Map/ Toposheet studies.5. Geology6. Geo-physical investigations.7. Conceptual planning.

    8. Vetting/ review of Conceptual planning by CEA.9. Project Components Identification10. Preliminary Layout - vetting by CEA/ CWC11. Preliminary Structure Outline Drawings of various structure (Typical drawings)12. Power Potential and Sizing of Power Plant.13. Vetting/ review of Power Potential and Sizing of Power Plant by CEA.14. Power Evacuation - Vetting/ review of Power Evacuation by CEA.15. Infrastructure requirement.16. Cost Estimates (Civil & Hydro-Mechanical, Electromechanical)17. Economic Evaluation

    B) Initial Environmental Studies

    1. Digitization of the maps (toposheets) with permission of SOI.2. Satellite imageries as required from NRSA.3. Processing of satellite data for the area of interest by the Consultant.The procedure adopted for processing will be :

    * Multi-spectral LISS (23.5 m resolution) and Single Band PAN (5.8 m resolution) data.

    * Land use classification for the area will be carried out after geo-referencing the satellite data.Land use classification consisting of the following classes :Vegetation crown, Cover (Tree canopy)Built-up Areas / Rocky Outcrops etc.Agricultural Land (Land on which Agriculture is being practiced currently)Vegetation Density classification (Low, Medium, High)

    Water BodiesBarren landAny other peculiar Land use category, as per local scenarioLand use patternVegetation cover/ densityApproximate population density

    The Initial Environmental Study would also take into account boundaries of National Parks, Wildlife Sanctuaries,Biosphere Reserves as any other aspect relevant to the environment in interaction with MOEF.

    C) Preparation of PFR

    1. Preparation of draft PFR2. Vetting of Draft PFR (by CEA)

    3. Finalization of PFR incorporating comments of CEA

  • 8/14/2019 50000 MW Hydroelectric Initiatives

    13/24

    13

    Preliminary Feasibility Reports shall be based on available data/ details pertaining to topography,geology, hydrology etc., preliminary field appraisal and geophysical investigation.

    3.4.2 Broad Scope of Works of Consultant

    a. Responsible for preparation of Preliminary Feasibility Reports of HE projects involving the conceptual designbased on water availability and topographical studies, preparation of project layout incorporating variousprojects components such as dam/ diversion structure, intake, desilting chamber, water conductor system(HRT, surge shaft, pressure shaft), power house and tail race structure etc., preparation of outline drawingsfor civil structures, associated hydro mechanical & electro mechanical equipments and power evacuationarrangements.

    b. The scope of work would also cover assessment of required infrastructure, environmental study, constructionmaterial survey, cost estimate, funds/ financing and financial analysis of the project.

    c. The consultant would take overall single point responsibility for all aspects of the feasibility studies/PFRs.

    3.4.3 Associated Organisations

    i) Central Electricity Authority (CEA)

    Central Electricity Authority (CEA), an attached office of the Ministry of Power and a Statutory Body of theGovt. of India constituted under Section 3(1) of the Electricity (Supply) Act, 1948, has been associated withhydro power development in the country for last five decades. CEA has contributed significantly to thedevelopment of Hydro power and possesses comprehensive expertise like hydro power planning, powerpotential studies, project appraisal, design and engineering, construction monitoring etc. CEA also facilitatesvarious organisations in design and engineering of the projects, wherever asked for. With its vast expertiseand huge data bank, CEA has been over-viewing the entire power sector in statutory/ regulatory as well asdevelopmental roles. Besides, it is also rendering technical assistance in Water Resources Development ofneighbouring countries of Nepal, Bhutan, Myanmar etc. for mutual benefits. Having completed the first hydropotential survey during 1953-59 and re-assessment of hydro potential during 1978-87, CEA carried out

    ranking study for 399 potential sites (1,07,000 MW) in Oct., 2001.

  • 8/14/2019 50000 MW Hydroelectric Initiatives

    14/24

    14

    Role of CEA during PFR preparation is outlined below :

    To facilitate the Consultants by making available the requisite input data for studies.Review/ vetting of conceptual planning.Review/ vetting of Power Potential studies and Sizing of Power Plant.Information on the nearest grid/substation. (based on power system studies)Vetting of Power evacuation arrangement.

    ii) Central Water Commission (CWC)

    CWC, an attached office of the Ministry of Water Resources, has been undertaking the works of Survey &Investigation for various Water Resources Development projects, such as Hydro-electric, Irrigation, Floodcontrol and Multi-purpose River Valley projects since 1971-72.

    CWC alongwith CEA have prepared DPRs for a number of HE Projects in India and neighbouring countriesof Bhutan and Nepal. For carrying out survey & investigation, CWC has a number of field offices and ishaving full back-up of specialised Design Directorates located in New Delhi.

    The role/ responsibility of CWC during PFR preparation is outlined below:To make available the requisite input data to the ConsultantsReview/ vetting of water availabilityVetting of Preliminary layout of the project

    iii) Geological Survey of India (GSI)

    The Geological Survey of India (GSI), one of the oldest Central Government Departments, caters to therequirements of various organisations for engineering geological services for different types of projects all overthe country and abroad. It has been the pioneering agency in the field of systematic engineering geologicalinvestigations since the inception of this kind of work in the country in the early fifties. Regional and

    Operational Centres of the GSI are spread over the whole of country. These engineering geological units ofGSI have a strong back-up of allied and peripheral specialized services (Geological Mapping, Landslide,Seismo-tectonics, Environmental Geology, Remote Sensing, Petrology, Geo-physics, Geo-chemistry, Drillingetc.), which are considered crucial for a meaningful engineering geological assessment of any project. Inaddition, all the engineering geological units of the Deptt. are well equipped with geo-technical laboratories,basically for determination of lab-based rock and soil strength parameters. On request from owner agencies,the Deptt. takes up geological investigations of the projects after including them in its Annual Programmes.

    For preparation of PFRs, GSI would provide inputs on Regional and site specific geological aspects in respectof main civil structures of HE projects.

    iv) Survey of India (SOI)

    SOI is one of the oldest Central Government Departments catering to the requirements of various organisationsfor services in the field of Surveys. It is a pioneer agency in the field of carrying out systematic surveys sinceinception.

    Survey of India would facilitate the Consultants in the following areas of PFRs preparation.

    Maps/topo sheets covering the area of identified HE projects and its catchment.

    Permission for undertaking digitization work of maps/topo sheets.

    v) National Remote Sensing Agency (NRSA)

    NRSA, an organisation of Department of Space, Govt. of India is the apex organisation for study of Satellite

    based Remote Sensing Data in the country.

  • 8/14/2019 50000 MW Hydroelectric Initiatives

    15/24

    15

    The Water Resources Group of NRSA is fully equipped to make use of space technology using satellite andaerial remote sensing and plays an important role in aerial mapping and scientific assessment of groundcondition at a speed which none of other survey methods can provide. This technology is ideally suited forinaccessible mountainous regions where majority of balance hydro potential sites are located. CEA hasmade use of the satellite based evaluation of land use data of NRSA for carrying out Preliminary Ranking

    Study of Indus Basin in 2001.

    For the purpose of preparation of PFRs of Hydro Electric Projects the consultants would make use of SatelliteImageries and data for studies of Environmental and R & R aspects etc.

    vi) Indian Meteorological Department (IMD)

    IMD monitors the rainfall for the whole country at sub-division and districts level on near real time mode.IMD prepares rainfall statistics for 35 meteorological sub divisions comprising 424 meteorological Distts. ofthe country.

    For the purpose of preparation of PFRs, inputs in the form of rainfall data from rain gauge station network

    in the concerned river basin of the project would be obtained by consultants from IMD.3.5 CONSULTANTS

    i). National Hydroelectric Power Corporation Ltd. (NHPC)

    The National Hydroelectric Power Corporation is ScheduleAEnterprise of the Government of India withauthorized share capital of Rs. 100,000 million.

    NHPC has emerged as a major organization for hydro power development in India, with capabilities toundertake all the activities from conceptualization to commissioning in relation to setting up of hydro projects.

    With an investment base of over Rs.1,58,000 million, it is ranked amongst top companies in the country in

    terms of investment. NHPC has been granted ISO-9001 certificate for its quality systems and ISO - 14001for environment standard in Corporate office.

    NHPC has installed capacity of 2,175 MW. It plans to add about 19,000 MW during 10thand 11thPlanperiods. It has also executed projects on deposit / turnkey basis. NHPC is registered as Consultant in areaof hydro power with World Bank, Asian Development Bank, African Development Bank etc.

    Corporate Mission of NHPC is to harness the vast hydro, tidal, wind and geo-thermal potential of the country bycovering all aspects of investigation, planning, design, construction, operation and maintenance to produce pollutionfree and inexhaustible power.

    ii). Water and Power Consultancy Services (India) Ltd. (WAPCOS)

    WAPCOS is a premier International Consultancy Undertaking of the Government of India. Since 1969, the

    Organisation has been providing Engineering Consultancy Services including Field Investigations, preparationof Project Reports, Tender Documents with Specifications and Detailed Project Engineering during constructionand commissioning stages. WAPCOS carries out studies at the Reconnaissance, Pre-feasibility, Feasibility andDetailed Project Report levels in respect of Micro, Mini, Small, Medium and Major Hydro-electric projects.It has received National as well as International acclaim for consultancy expertise, with successful operationsin over 35 countries world-wide as well as throughout India. In recognition of consistent excellence inperformance, Government of India has accorded on WAPCOS the status ofMini Ratna.

    iii) Satluj Jal Vidyut Nigam Ltd. (SJVNL)

    The Satluj Jal Vidyut Nigam Ltd. (formerly Nathpa Jhakri Power Corporation Ltd.) was incorporatedon May 24, 1988 as a joint venture of the Govt. of India (GOI) and the Govt. of Himachal Pradesh

    (GOHP) to Plan, Investigate, Organise, Execute, Operate and Maintain Hydro-electric power projects in the

  • 8/14/2019 50000 MW Hydroelectric Initiatives

    16/24

  • 8/14/2019 50000 MW Hydroelectric Initiatives

    17/24

    17

    vii) Uttaranchal Jal Vidyut Nigam Limited (UJVNL)

    UJVNL is a wholly owned corporation of the Government of Uttaranchal and was set up for managing hydropower generation at existing power stations and development, promotion of new hydro projects with thepurpose of harnessing, the known and yet to be known, hydro power resources of the State.

    Today, UJVNL operates hydro power plants ranging in capacity from 0.2 MW to 240 MW totalling up to1124.26 MW. UJVNL have recently resumed construction of Maneri Bhali St.-II (304 MW) for completionin 10thPlan. UJVNL have taken up work of preparation of uprated and bankable DPRs of Pala Maneri (416MW), Bowla Nand Prayag (132 MW), Arakot Tiuni (70 MW) and Tiuni Palasu (42 MW).

    UJVNL is committed to develop its huge hydro power resources in an early and efficient manner for economicwell-being and growth of the State and its people. With rising hydro power generation and improvingefficiencies in distribution of electricity, UJVNL also hopes to offer energy at stable prices for eco-friendlyindustrial development.

    3.6 Summary of the PFRs entrusted to the Consultants

    S.No. Name of Organisation No. of Schemes Total Installed Capacity (MW)

    1 WAPCOS 71 17419

    2 NHPC 43 21345

    3 NEEPCO 18 4915

    4 HPSEB 10 1685

    5 SJVNL 2 2065

    6 KPCL 5 830

    7 UJVNL 13 2301Total: 162 50560

    Statewise and Consultantwise details of schemes are given at Annex -II.

    3.7 Review Mechanism

    The institutional arrangement for reviewing the progress of PFRs preparation would be as under:

    3.7.1 Coordination Committee

    The Coordination Committee, headed by Member (Hydro), CEA with representatives from organisationsresponsible for providing the input data viz. CEA, CWC, GSI, SOI & NRSA to the Consultants would be setup. The committee would ensure mutual data exchange and oversee formulation of PFRs. The committeewould also undertake monthly review of the inputs to be given to various consultants and formulate theprogramme for making available the data in a systematic manner so as to complete the PFRs in scheduledtime frame.

    3.7.2 Advisory Committee

    An Advisory Committee headed by Chairman, CEA with representatives from CEA, CWC, GSI, MOEF, IMD,SOI & NRSA would be set up. The committee would undertake quarterly review of the progress of the PFRs

    and formulate the programme for completion of PFRs in schedule time frame after considering feed back from

  • 8/14/2019 50000 MW Hydroelectric Initiatives

    18/24

    18

    Consultants, and report the same to the Ministry of Power.

    Following would be the monitoring mechanism for preparation of PFRs.

    Consultants to submit monthly progress reports to CEA.Chairman, CEA would hold monthly reviews.

    Quarterly reviews by Secretary (Power).

    3.7.3 Deliverables/ Outputs with Schedules

    The work of PFRs preparation is to be completed in a period of 18 months with effect from April, 2003 inan evenly distributed manner to ensure that the last draft report is submitted by the end of July, 2004 andthe final reports of all the schemes are submitted by Sept., 2004.

    4.0 Implementation of Projects

    Advance action taken under this initiative will enable implementation of these projects during 11thand 12th

    Plans period (years 2007-2017). Implementation agencies viz. PSUs, State utilities and other organizationswill be identified to develop these projects.

  • 8/14/2019 50000 MW Hydroelectric Initiatives

    19/24

    19

    REGIONWISE/ STATEWISE RESULTS OF

    PRELIMINARY RANKING STUDY

    Category A B C Total

    Region/ State Nos MW Nos. MW Nos. MW Nos. MW

    NORTHERN

    Jammu & Kashmir - - 32 6218 13 3295 45 9513Himachal Pradesh 12 4114 19 2593 4 2785 35 9492Punjab - - - - - - - -Haryana - - - - - - - -Rajasthan - - - - - - - -Uttaranchal 13 1726 50 9003 1 600 64 11329Uttar Pradesh 1 39 - - - - 1 39Sub Total (NR) 26 5879 101 17814 18 6680 145 30373

    WESTERN

    Madhya Pradesh 3 143 2 103 - - 5 246Chhattisgarh 4 331 9 1851 - - 13 2182Gujarat - - - - - - - -Maharashtra 4 342 9 1563 - - 13 1905Goa - - - - 1 55 1 55Sub total (WR) 11 816 20 3517 1 55 32 4388

    SOUTHERN - -

    Andhra Pradesh 4 765 2 1695 - - 6 2460

    Karnataka 1 35 13 1562 3 760 17 2357Kerala - - 5 544 8 583 13 1127Tamilnadu 1 90 - - 4 198 5 288Sub Total (SR) 6 890 20 3801 15 1541 41 6232

    EASTERN

    Jharkhand 2 223 2 480 1 186 5 889Bihar - - - - - - - -Orissa - - 7 1667 - - 7 1667West Bengal 2 133 - - 1 2505 3 2638Sikkim 10 1982 11 1371 - - 21 3353

    Sub Total (ER) 14 2338 20 3518 2 2691 36 8547NORTH EASTERN -

    Meghalaya 2 178 16 1316 4 665 22 2159Tripura - - - - - - - -Manipur 3 135 5 335 3 1771 11 2241Assam 3 247 3 108 1 33 7 388Nagaland 2 111 4 251 4 1030 10 1392Arunachal Pd 31 5047 55 38999 3 5080 89 49126Mizoram - - 3 194 3 1870 6 2064Sub Total (NER) 41 5718 86 41203 18 10449 145 57370

    ALL INDIA 98 15641 247 69853 54 21416 399 106910

    Annex -I

  • 8/14/2019 50000 MW Hydroelectric Initiatives

    20/24

    20

    Annex

    -II

    STATEWISE/C

    ONSULTANTWISEBREAKUPOFSCHEMESFORPREPARATIONOFPRELIMI

    NARYFEASIBILITYREPORTS

    S.

    NHPC

    WAPCOS

    NEEPCO

    HPSEB

    SJVNL

    KPCL

    UJVNL

    Total

    No.

    1

    AndhraPradesh

    -

    -

    3

    705

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    706

    2

    ArunachalPradesh

    25

    18245

    2

    3500

    15

    3945

    -

    -

    -

    -

    -

    -

    -

    -

    42

    25690

    3

    Chhattisgarh

    -

    -

    4

    580

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    4

    580

    4

    HimachalPradesh

    -

    -

    -

    -

    -

    -

    10

    1685

    2

    2065

    -

    -

    -

    -

    12

    3750

    5

    Jammu&Kashmir

    7

    1360

    6

    1621

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    13

    2981

    6

    Karnataka

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    5

    830

    -

    -

    5

    830

    7

    Kerala

    -

    -

    2

    205

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    2

    205

    8

    Maharashtra

    -

    -

    9

    1780

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    9

    1780

    9

    Manipur

    -

    -

    3

    407

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    3

    407

    10

    Meghalaya

    -

    -

    9

    1490

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    9

    1490

    11

    MadhyaPradesh

    1

    60

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    1

    60

    12

    Nagaland

    -

    -

    -

    -

    3

    970

    -

    -

    -

    -

    -

    -

    -

    -

    3

    970

    13

    Orissa

    -

    -

    4

    1188

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    4

    1188

    14

    Sikkim

    10

    1680

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    10

    1680

    15

    Uttaranchal

    -

    -

    26

    4073

    -

    -

    -

    -

    -

    -

    -

    -

    13

    230

    139

    6374

    16

    Mizoram

    -

    -

    3

    1870

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    3

    1870

    TOTAL:

    43

    21345

    71

    17419

    18

    4915

    10

    1685

    2

    2065

    5

    830

    13

    2301

    162

    50560

    IC(MW)

    No.

    of

    Schemes

    IC(MW

    )

    No.

    of

    Schemes

    IC(MW)

    No.

    of

    Schemes

    IC(MW

    )

    No.

    of

    Schemes

    IC(MW)

    No.

    of

    Schemes

    IC(MW)

    No.

    of

    Schemes

    IC(MW)

    No.

    of

    Schemes

    IC(MW)

    N

    o.

    o

    f

    Sche

    mes

    State

  • 8/14/2019 50000 MW Hydroelectric Initiatives

    21/24

    21

    List of Schemes for PFRs by WAPCOSSl.No Name of the Scheme State River Basin IC(MW)

    1 Dummagudem Andhra Pradesh Godavari 360 2 Singareddi Andhra Pradesh Godavari 250

    3 Pondugala Andhra Pradesh Krishna 95 4 Hutong Arunachal Pradesh Luhit 950 5 Kalai Arunachal Pradesh Luhit 2550 6 Nugur-II Chattisgarh Indravati 270 7 Nugur-I Chattisgarh Indravati 160 8 Kotri Chattisgarh Godavari 70 9 Duniadhin Chattisgarh Sone 80 10 Ratle Jammu & Kashmir Chenab 515 11 Ujh Jammu & Kashmir Ravi 9612 Kwar Jammu & Kashmir Chenab 440 13 Kiru Jammu & Kashmir Chenab 295

    14 Shamnot Jammu & Kashmir Chenab 200 15 Bichlari Jammu & Kashmir Chenab 75 16 Barapole-II Kerala Varahi - Kuttiyadi 85 17 Perinjakutty Kerala Perinjakutty 120 18 Kunghara Maharashtra Godavari 115 19 Ghargaon Maharashtra Godavari 105 20 Samda Maharashtra Godavari 95 21 Kasari-I Maharashtra Kasari 215 22 Kadvi Maharashtra Vama 215 23 Kumbhi-i Maharashtra Krishna 170 24 Hiranyakeshi-II Maharashtra Vedganga 405

    25 Pranhita Maharashtra Pranhita/Maharashtra 310 26 Wainganga Maharashtra Godavari 150 27 Nungliban Manipur Barak & Others 85 28 Khongnem Chakha-II Manipur Barak & Others 90 29 Pabaram Manipur Barak & Others 23230 Sushen Meghalaya Barak & Others 150 31 Umjaut Meghalaya Barak & Others 85 32 Umduna Meghalaya Barak & Others 95 33 Kynshi-II Meghalaya Barak & Others 175 34 Umiam Umtru-VI Meghalaya Kalang 145 35 Nongkolait Meghalaya Barak & Others 180

    36 Mawblei Storage Meghalaya Barak & Others 100 37 Kyanshi Storage I Meghalaya Barak & Others 295 38 Umangot Storage Meghalaya Barak & Others 265 39 Baljori Orissa Baitarni 39344 Khartoli Lumti Talli Uttaranchal Sarda 105 45 Harsil Dam Uttaranchal Bhagirathi 350 46 Nelang Uttaranchal Jadhganga 190 47 Jadh Ganga Uttaranchal Jadhganga 110 48 Karmali Uttaranchal Jadhganga 190 49 Gangotri Uttaranchal Bhagirathi 70 50 Kalika Dantu Uttaranchal Sarda 140

    51 Mapang Bogudyar Uttaranchal Sarda 185

  • 8/14/2019 50000 MW Hydroelectric Initiatives

    22/24

  • 8/14/2019 50000 MW Hydroelectric Initiatives

    23/24

    23

    List of Schemes for PFRs by NHPC

    Sl.No Name of the Scheme State River Basin IC(MW)

    1 Hegio Arunachal Pradesh Subansiri 250

    2 Emini Arunachal Pradesh Dihang-Dibang 295

    3 Amulin Arunachal Pradesh Dihang-Dibang 235 4 Agoline Arunachal Pradesh Dihang-Dibang 235

    5 Rigong Arunachal Pradesh Dihang-Dibang 130

    6 Kurung Dam-II Arunachal Pradesh Subansiri 115

    7 Tato-II Arunachal Pradesh Dihang-Dibang 360

    8 Oju-II Arunachal Pradesh Subansiri 2580

    9 Attunli Arunachal Pradesh Dihang-Dibang 175

    10 Naba Arunachal Pradesh Subansiri 1290

    11 Emra-II Arunachal Pradesh Dihang-Dibang 870

    12 Etalin Arunachal Pradesh Dihang-Dibang 3045

    13 Naying Arunachal Pradesh Dihang-Dibang 495 14 Oju-I Arunachal Pradesh Subansiri 1925

    15 Niare Arunachal Pradesh Subansiri 1405

    16 Emra-I Arunachal Pradesh Dihang-Dibang 275

    17 Minnying Arunachal Pradesh Dihang-Dibang 195

    18 Elango Arunachal Pradesh Dihang-Dibang 180

    19 Duimukh Storage Arunachal Pradesh Subansiri 170

    20 Mirak Arunachal Pradesh Dihang-Dibang 160

    21 Hirong Arunachal Pradesh Dihang-Dibang 180

    22 Malinye Arunachal Pradesh Dihang-Dibang 335

    23 Mihumdon Arunachal Pradesh Dihang-Dibang 145 24 Demwe Arunachal Pradesh Dihang-Dibang 3000

    25 Kurung Dam-I Arunachal Pradesh Subansiri 200

    26 Hatian Jammu & Kashmir Jhelum 215

    27 Chenari Jammu & Kashmir Jhelum 475

    28 Karkit Jammu & Kashmir Indus 190

    29 Kanyunche Jammu & Kashmir Indus 105

    30 Khalsi Jammu & Kashmir Indus 170

    31 Takmaching Jammu & Kashmir Indus 75

    32 Dumkhar Jammu & Kashmir Indus 130

    33 Basania Madhya Pradesh Narmada 60

    34 Panan Sikkim Tista 230

    35 Namlum Sikkim Tista 175

    36 Dikchu Sikkim Tista 90

    37 Rangyong Sikkim Tista 175

    38 Lingza Sikkim Tista 160

    39 Rukel Sikkim Tista 90

    40 Rongni Storage Sikkim Tista 95

    41 Jedang Sikkim Tista 185

    42 Ringpi Sikkim Tista 160

    43 Teesta St. I Sikkim Tista 320

    Total 21345

  • 8/14/2019 50000 MW Hydroelectric Initiatives

    24/24

    List of Schemes for PFRs by NEEPCOSl.No Name of the Scheme State River Basin IC(MW)

    1 Bhareli Lift Dam-II Arunachal Pradesh Kameng 330 2 Bhareli Lift Dam-I Arunachal Pradesh Kameng 240

    3 Kapak Leyak Arunachal Pradesh Kameng 195 4 Badao Arunachal Pradesh Kameng 120 5 Pakke Arunachal Pradesh Kameng 120 6 Seba Arunachal Pradesh Kameng 105 7 Chanda Arunachal Pradesh Kameng 110 8 Kimi Arunachal Pradesh Kameng 535 9 Kameng Arunachal Pradesh Kameng 1100 10 Bichom-II Arunachal Pradesh Kameng 205 11 Papu Arunachal Pradesh Kameng 160 12 Talong Arunachal Pradesh Kameng 150 13 Utung Arunachal Pradesh Kameng 110

    14 Tenga Arunachal Pradesh Kameng 275 15 Bichom Storage-I Arunachal Pradesh Kameng 190 16 Yangnyu Stor. Nagaland U.Brahmaputra 135 17 Tizu Nagaland Barak & Others 365 18 Dikhu Dam Nagaland U.Brahmaputra 470

    Total 4915

    List of Schemes for PFRs by UJVNLSl.No Name of the Scheme State River Basin IC(MW)

    1 Tapovan Chunar Uttaranchal Dhauliganga 485

    2 Lata Tapovan Uttaranchal Dhauliganga 320 3 Bhela Tipri Uttaranchal Bhagirathi 100 4 Nand Prayag Langasu Uttaranchal Alaknanda 180 5 Tamak Lata Uttaranchal Dhauliganga 200 6 Khet Tawaghat Uttaranchal Sarda 225 7 Urthing Sobala Uttaranchal Sarda 340 8 Ramganga Dam Uttaranchal Sarda 75 9 Pindar Ghati Uttaranchal Pindar 11210 Arkot Tuini(Nakoti Plasu) Uttaranchal Yamuna 70 11 Jakhol Sankri Uttaranchal Yamuna 60 12 Bagoli Dam Uttaranchal Pindar 64

    13 Naitwar Mori Uttaranchal Yamuna 70 Total 2301

    List of Schemes for PFRs by KPCLSl.No Name of the Scheme State River Basin IC(MW)

    1 Kali Nadi-III (Mardi) Karnataka Mandavi - Sharavati 175 2 Krishnapur Karnataka Mandavi - Sharavati 210 3 Gangavali-II Karnataka Mandavi - Sharavati 105 4 Jaldurg Karnataka Krishna 270 5 Narayanpur Karnataka Krishna 70

    Total 830