Alan TorresNew Nuclear DeploymentSCANA/South Carolina Electric & Gas

NUCLEAR | South Carolina’s Clean Energy Solution

VC Summer Unit 2/3 Update

CV Assembly

MAB

NND Site Aerial View

2

Cooling Towers Contractor Support Personnel

Unit 3

Unit 2

Storage

HLD

Turbine Building

First Quarter 2014 |  Earnings Conference Call

3

Unit 2 Module CA‐20

3

• Module CA‐20 is the Auxiliary Building and Fuel Handling area

• On hook date is May 2014

| Unit 2 Nuclear Island Concrete Placement

7

Inside Unit 2 Containment Vessel

Unit 2 Nuclear Island

Aux Building

7

8

Unit 3 Nuclear Island

CR‐10 module

U2/U3 Containment Vessel Rings 

| New Nuclear Project

U2 CWS Pump House Excavation

U3 Containment Vessel Bottom Head

Offsite Water Treatment

New Nuclear Project

9

WaterBoxes

CH‐80

Condenser A 

CH‐81B

Condenser B 

Condenser CCH‐81A

Turbine Building Layout

10

CH‐82

CH‐81C

Condenser C

CH81B CH81A

CH80

Condenser B

11

U2 Turbine Building

Condenser A

CH82

12

Unit 2 Diesel Generators

Unit 2 Integrated Head Package

Unit 2 Aux Transformers

Components Arriving on Site

12

13

Upcoming 2014 Construction Milestones

13

Unit 2Nuclear Island• Set Structural Module CA20—Auxiliary Building  & 

Fuel Handling area• Place Concrete in CA20• Fabricate and Set CA05—CVS / Access Tunnel / PXS‐B Walls• Fabricate and Set CA01—Steam Generator and Refueling Canal • Fabricate and Set CA02 —IRWST / Pressurizer Wall • Fabricate and Set CA03 —IRWST Southwest Walls • Set First‐Floor Mechanical Modules• Start Shield Building

Turbine Building• Complete Condenser component installation• Complete foundation at Elevation 100’0”• Start First‐Bay foundation

14

Upcoming 2014 Construction Milestones

14CA Modules in Nuclear Island

CA20CVBH

CA05

CA04

15

Upcoming 2014 Construction Milestones

15CA Modules Inside Containment

16

Upcoming 2014 Construction Milestones

16First Quarter 2014 |  Earnings Conference CallUnit 2 Auxiliary Building First Floor Mechanical Modules

17

Upcoming 2014 Construction Milestones

17First Quarter 2014 |  Earnings Conference Call

Unit 3Nuclear Island• Set Containment Vessel Bottom Head (CVBH)• Grout CVBH• Place first level of concrete in CVBH• Fabricate and Set CA04—Reactor Vessel Cavity• Place Auxiliary Building walls – A2 Elevation  (66’6”‐82’6”)

Turbine Building• Complete Backfill• Install 82’6” basement foundation and walls• Fabricate and install Condenser components• Install CH Structural Steel modules

Doosan Manufacturing Update

18

Unit 2 RV‐Ready to Ship

Hydro test Complete for Unit 2A SG Upper internal welding of Final Vessel for Unit 2B SG

Mangiarotti Manufacturing Update

19

CMT – Unit 3 Upper Pedals ACC – Unit  2 – Tanks 1 & 2

CMT – Unit 2 Tanks 1 & 2 ACC – Unit 3 ‐ Tank 2 – Shell to Lower Crown

Low Pressure “B” Turbine –Prep for Blade Assembly

Generator Rotor Low Pressure “A” Turbine

20

Toshiba, Keihin ‐ Japan