VC Summer Unit 2/3 Update - NRC: Home PageVC Summer Unit 2/3 Update. CV Assembly MAB NND Site Aerial...
Transcript of VC Summer Unit 2/3 Update - NRC: Home PageVC Summer Unit 2/3 Update. CV Assembly MAB NND Site Aerial...
Alan TorresNew Nuclear DeploymentSCANA/South Carolina Electric & Gas
NUCLEAR | South Carolina’s Clean Energy Solution
VC Summer Unit 2/3 Update
CV Assembly
MAB
NND Site Aerial View
2
Cooling Towers Contractor Support Personnel
Unit 3
Unit 2
Storage
HLD
Turbine Building
First Quarter 2014 | Earnings Conference Call
3
Unit 2 Module CA‐20
3
• Module CA‐20 is the Auxiliary Building and Fuel Handling area
• On hook date is May 2014
| Unit 2 Nuclear Island Concrete Placement
7
Inside Unit 2 Containment Vessel
Unit 2 Nuclear Island
Aux Building
7
8
Unit 3 Nuclear Island
CR‐10 module
U2/U3 Containment Vessel Rings
| New Nuclear Project
U2 CWS Pump House Excavation
U3 Containment Vessel Bottom Head
Offsite Water Treatment
New Nuclear Project
9
WaterBoxes
CH‐80
Condenser A
CH‐81B
Condenser B
Condenser CCH‐81A
Turbine Building Layout
10
CH‐82
CH‐81C
Condenser C
CH81B CH81A
CH80
Condenser B
11
U2 Turbine Building
Condenser A
CH82
12
Unit 2 Diesel Generators
Unit 2 Integrated Head Package
Unit 2 Aux Transformers
Components Arriving on Site
12
13
Upcoming 2014 Construction Milestones
13
Unit 2Nuclear Island• Set Structural Module CA20—Auxiliary Building &
Fuel Handling area• Place Concrete in CA20• Fabricate and Set CA05—CVS / Access Tunnel / PXS‐B Walls• Fabricate and Set CA01—Steam Generator and Refueling Canal • Fabricate and Set CA02 —IRWST / Pressurizer Wall • Fabricate and Set CA03 —IRWST Southwest Walls • Set First‐Floor Mechanical Modules• Start Shield Building
Turbine Building• Complete Condenser component installation• Complete foundation at Elevation 100’0”• Start First‐Bay foundation
14
Upcoming 2014 Construction Milestones
14CA Modules in Nuclear Island
CA20CVBH
CA05
CA04
15
Upcoming 2014 Construction Milestones
15CA Modules Inside Containment
16
Upcoming 2014 Construction Milestones
16First Quarter 2014 | Earnings Conference CallUnit 2 Auxiliary Building First Floor Mechanical Modules
17
Upcoming 2014 Construction Milestones
17First Quarter 2014 | Earnings Conference Call
Unit 3Nuclear Island• Set Containment Vessel Bottom Head (CVBH)• Grout CVBH• Place first level of concrete in CVBH• Fabricate and Set CA04—Reactor Vessel Cavity• Place Auxiliary Building walls – A2 Elevation (66’6”‐82’6”)
Turbine Building• Complete Backfill• Install 82’6” basement foundation and walls• Fabricate and install Condenser components• Install CH Structural Steel modules
Doosan Manufacturing Update
18
Unit 2 RV‐Ready to Ship
Hydro test Complete for Unit 2A SG Upper internal welding of Final Vessel for Unit 2B SG
Mangiarotti Manufacturing Update
19
CMT – Unit 3 Upper Pedals ACC – Unit 2 – Tanks 1 & 2
CMT – Unit 2 Tanks 1 & 2 ACC – Unit 3 ‐ Tank 2 – Shell to Lower Crown
Low Pressure “B” Turbine –Prep for Blade Assembly
Generator Rotor Low Pressure “A” Turbine
20
Toshiba, Keihin ‐ Japan