Project Management Operations -- Prof. Juran. 2 Outline Definition of Project Management –Work...

Post on 15-Dec-2015

216 views 0 download

Tags:

Transcript of Project Management Operations -- Prof. Juran. 2 Outline Definition of Project Management –Work...

Project Management

Operations -- Prof. Juran

Operations -- Prof. Juran 2

Outline • Definition of Project Management

– Work Breakdown Structure– Project Control Charts– Structuring Projects

• Critical Path Scheduling– By Hand– Linear Programming

• PERT– By Hand

Project Management

• A Project is a series of related jobs usually directed toward some major output and requiring a significant period of time to perform

• Project Management is the set of management activities of planning, directing, and controlling resources (people, equipment, material) to meet the technical, cost, and time constraints of a project

• An extreme case: Smallest possible production volume, greatest possible customization

Project Control Charts: Gantt Chart

Operations -- Prof. Juran 5

A pure project is where a self-contained team works full-time on the project

Advantages:• The project manager has full authority over the

project• Team members report to one boss• Shortened communication lines• Team pride, motivation, and commitment are high

Disadvantages:• Duplication of resources• Organizational goals and policies are ignored• Lack of technology transfer• Team members have no functional area "home"

Functional Projects

President

Research andDevelopment

Engineering Manufacturing

ProjectA

ProjectB

ProjectC

ProjectD

ProjectE

ProjectF

ProjectG

ProjectH

ProjectI

Example: Project “B” is in the functional area of Research and

Development.

Example: Project “B” is in the functional area of Research and

Development.

Functional ProjectsAdvantages:• A team member can work on several projects• Technical expertise is maintained within the

functional area• The functional area is a “home” after the project

is completed• Critical mass of specialized knowledge

Disadvantages:• Aspects of the project that are not directly related

to the functional area get short-changed• Motivation of team members is often weak• Needs of the client are secondary and are

responded to slowly

Matrix Project Organization Structure

President

Research andDevelopment

Engineering Manufacturing Marketing

ManagerProject A

ManagerProject B

ManagerProject C

Matrix Structure

Advantages:• Enhanced communications between functional

areas• Pinpointed responsibility• Duplication of resources is minimized• Functional “home” for team members• Policies of the parent organization are followed

Disadvantages:• Too many bosses• Depends on project manager’s negotiating

skills• Potential for sub-optimization

Work Breakdown Structure

Program

Project 1 Project 2

Task 1.1

Subtask 1.1.1

Work Package 1.1.1.1

Level

1

2

3

4

Task 1.2

Subtask 1.1.2

Work Package 1.1.1.2

A hierarchy of project tasks, subtasks, and work packages

Network Models• A project is viewed as a sequence of

activities that form a “network” representing a project

• The path taking longest time through this network of activities is called the “critical path”

• The critical path provides a wide range of scheduling information useful in managing a project

• Critical Path Method (CPM) helps to identify the critical path(s) in the project network

Prerequisites for Critical Path Method

A project must have:• well-defined jobs or tasks whose

completion marks the end of the project;

• independent jobs or tasks;• and tasks that follow a given

sequence.

Types of Critical Path Methods• CPM with a Single Time Estimate

– Used when activity times are known with certainty

– Used to determine timing estimates for the project, each activity in the project, and slack time for activities

• Time-Cost Models– Used when cost trade-off information is a major

consideration in planning– Used to determine the least cost in reducing total

project time • CPM with Three Activity Time Estimates

– Used when activity times are uncertain – Used to obtain the same information as the

Single Time Estimate model and probability information

CPM with Single Time Estimate

1. Activity Identification2. Activity Sequencing and Network

Construction3. Determine the critical path

– From the critical path all of the project and activity timing information can be obtained

Operations -- Prof. Juran 16

House-Building Example

Activity Description Predecessors Duration (days) Activity A Build foundation — 5 Activity B Build walls and ceilings A 8 Activity C Build roof B 10 Activity D Do electrical wiring B 5 Activity E Put in windows B 4 Activity F Put on siding E 6 Activity G Paint house C, F 3

Operations -- Prof. Juran 17

Managerial Problems• Find the minimum number of days

needed to build the house.• Find the “critical path”.• Find the least expensive way to

finish the house in a certain amount of time.

• Study the possible effects of randomness in the activity times.

Operations -- Prof. Juran 18

Activity-on-Arc Network1

0Start

43

2

A5

B8

C10

E4

D5

G3

F6

5End

Operations -- Prof. Juran 19

Method 1: “By Hand”

1

0Start

43

2

A5

B8

C10

E4

D5

G3

F6

5End

Operations -- Prof. Juran 20

Procedure• Draw network• Forward pass to find earliest times• Backward pass to find latest times• Analysis: Critical Path, Slack Times• Extensions (really hard!):

– Crashing– PERT

Operations -- Prof. Juran 21

CPM Jargon

1

0Start

43

2

A5

B8

C10

E4

D5

G3

F6

5End

Every network of this type has at least one critical path, consisting of a set of critical activities.

In this example, there are two critical paths: A-B-C-G and A-B-E-F-G.

Operations -- Prof. Juran 22

Conclusions

The project will take 26 days to complete.

The only activity that is not critical is the electrical wiring (Activity D).

Time-Cost Models

• Basic Assumption: Relationship between activity completion time and project cost

• Time Cost Models: Determine the optimum point in time-cost tradeoffs– Activity direct costs– Project indirect costs– Activity completion times

Operations -- Prof. Juran 24

Crashing Parameters

Activity Cost per Day to

Reduce Duration Maximum Possible Reduction (Days)

Build foundation $30 2 Walls and ceilings $15 3 Build roof $20 1 Electrical wiring $40 2 Put in windows $20 2 Put on siding $30 3 Paint house $40 1

What is the least expensive way to finish this project in 20 days? (This is hard!)

Operations -- Prof. Juran 25

CPM with Three Activity Time Estimates

Activity Optimistic Most Likely Pessimistic A 3 5 7 B 5 8 11 C 9 10 11 D 3 5 7 E 2 4 6 F 3 6 9 G 2 3 4

Operations -- Prof. Juran 26

Expected Time Calculations

6Time Pess. + Time) Likely 4(Most + Time Opt.

= Time Expected

12345678

A B C D E F GActivity Optimistic Most Likely Pessimistic Expected

A 3 5 7 5B 5 8 11 8C 9 10 11 10D 3 5 7 5E 2 4 6 4F 3 6 9 6G 2 3 4 3

=(B2+C2*4+D2)/6

Operations -- Prof. Juran 27

Expected Time Calculations

12345678

A B C D E F GActivity Optimistic Most Likely Pessimistic Expected

A 3 5 7 5B 5 8 11 8C 9 10 11 10D 3 5 7 5E 2 4 6 4F 3 6 9 6G 2 3 4 3

=(B2+C2*4+D2)/6

Note: the expected time of an activity is not necessarily equal to the most likely time (although that is true in this problem).

Operations -- Prof. Juran 28

1

0Start

43

2

A5

B8

C10

E4

D5

G3

F6

5End

The sum of the critical path expected times is the expected duration of the whole project (in this case, 26 days).

Operations -- Prof. Juran 29

What is the probability of finishing this project in less than 25 days?

What is the probability of finishing this project in less than 25 days?

Z = D - TE

cp2

Operations -- Prof. Juran 30

22

6 Variance Activity Estimated

OptimisticcPessimisti

12345678

A B C D E F GActivity Optimistic Most Likely Pessimistic Expected Variance

A 3 5 7 5 0.4444B 5 8 11 8 1.0000C 9 10 11 10 0.1111D 3 5 7 5 0.4444E 2 4 6 4 0.4444F 3 6 9 6 1.0000G 2 3 4 3 0.1111

=((D2-B2)/6)^2

Operations -- Prof. Juran 31

Sum the variances along the critical path. (In this case, with two critical paths, we’ll take the one with the larger variance.)

3=2

Activity Optimistic Most Likely Pessimistic Expected Variance Criticial Path 1 Criticial Path 2A 3 5 7 5 0.444 0.444 0.444B 5 8 11 8 1.000 1.000 1.000C 9 10 11 10 0.111 0.111D 3 5 7 5 0.444E 2 4 6 4 0.444 0.444F 3 6 9 6 1.000 1.000G 2 3 4 3 0.111 0.111 0.111

Expected 26.000 26.000Variance 3.000 1.667St Dev 1.732 1.291

Operations -- Prof. Juran 32

There is a 28.19% probability that this project will be completed in less than 25 days.There is a 28.19% probability that this project will be completed in less than 25 days.

p(Z < -.156) = .438, or 43.8 % (NORMSDIST(-.156)p(Z < -.156) = .438, or 43.8 % (NORMSDIST(-.156)

0.5774- =326-25

=T - D

= Z2

cp

E

CPM Assumptions/Limitations• Project activities can be identified as entities

(there is a clear beginning and ending point for each activity).

• Project activity sequence relationships can be specified and networked.

• Project control should focus on the critical path.

• The activity times follow the beta distribution, with the variance of the project assumed to equal the sum of the variances along the critical path.

Operations -- Prof. Juran 34

Method 2: Excel Solver(Linear Programming)

1

0Start

43

2

A5

B8

C10

E4

D5

G3

F6

5End

Operations -- Prof. Juran 35

Procedure• Define Decision Variables• Define Objective Function• Define Constraints• Solver Dialog and Options• Run Solver• “Sensitivity” Analysis: Critical Path,

Slack• Extensions:

– Crashing (not too bad)– PERT (need simulation, not Solver)

Operations -- Prof. Juran 36

LP FormulationDecision VariablesWe are trying to decide when to begin and end each of the activities.ObjectiveMinimize the total time to complete the project.ConstraintsEach activity has a fixed duration.There are precedence relationships among the activities.We cannot go backwards in time.

Operations -- Prof. Juran 37

Formulation

Decision VariablesDefine the nodes to be discrete events. In other words, they occur at one exact point in time. Our decision variables will be these points in time.Define ti to be the time at which node i occurs, and at which time all activities preceding node i have been completed.Define t0 to be zero.

ObjectiveMinimize t5.

Operations -- Prof. Juran 38

FormulationConstraintsThere is really one basic type of constraint. For each activity x, let the time of its starting node be represented by tjx and the time of its ending node be represented by tkx.

Let the duration of activity x be represented as dx.

For every activity x,

For every node i,

xjxkx dtt

0it

Operations -- Prof. Juran 39

Solution Methodology

123

456

789

101112131415161718

A B C D E F G H I J K L M N O P

1

t0 t1 t2 t3 t4 t50 1 1 1 1 1

t0 t1 t2 t3 t4 t5A -1 1 0 0 0 0 1 >= 5B 0 -1 1 0 0 0 0 >= 8C 0 0 -1 0 1 0 0 >= 10D 0 0 -1 0 0 1 0 >= 5E 0 0 -1 1 0 0 0 >= 4F 0 0 0 -1 1 0 0 >= 6G 0 0 0 0 -1 1 0 >= 3

1

0Start

43

2

A5

B8

C10

E4

D5

G3

F6

5End

=G6

=SUMPRODUCT($B$6:$G$6,B12:G12)

Operations -- Prof. Juran 40

Solution Methodology

The matrix of zeros, ones, and negative ones (B12:G18) is a means for setting up the constraints.

The sumproduct functions in H12:H18 calculate the elapsed time between relevant pairs of nodes, corresponding to the various activities.

The duration times of the activities are in J12:J18.

Operations -- Prof. Juran 41

Operations -- Prof. Juran 42

Optimal Solution123

456

789101112131415161718

A B C D E F G H I J K L M N O P

26

t0 t1 t2 t3 t4 t50 5 13 17 23 26

t0 t1 t2 t3 t4 t5A -1 1 0 0 0 0 5 >= 5B 0 -1 1 0 0 0 8 >= 8C 0 0 -1 0 1 0 10 >= 10D 0 0 -1 0 0 1 13 >= 5E 0 0 -1 1 0 0 4 >= 4F 0 0 0 -1 1 0 6 >= 6G 0 0 0 0 -1 1 3 >= 3

1

0Start

43

2

A5

B8

C10

E4

D5

G3

F6

5End

Operations -- Prof. Juran 43

CPM Jargon

Any activity for which

is said to have slack time, the amount of time by which that activity could be delayed without affecting the overall completion time of the whole project. In this example, only activity D has any slack time (13 – 5 = 8 units of slack time).

xjxkx dtt

Operations -- Prof. Juran 44

CPM Jargon

Any activity x for which

is defined to be a “critical” activity, with zero slack time.

xjxkx dtt

Operations -- Prof. Juran 45

Excel Tricks: Conditional Formatting1

2

3

45

6

789101112131415161718

A B C D E F G H I J K L M N O P

26

t0 t1 t2 t3 t4 t5

0 5 13 17 23 26

t0 t1 t2 t3 t4 t5A -1 1 0 0 0 0 5 >= 5B 0 -1 1 0 0 0 8 >= 8C 0 0 -1 0 1 0 10 >= 10D 0 0 -1 0 0 1 13 >= 5E 0 0 -1 1 0 0 4 >= 4F 0 0 0 -1 1 0 6 >= 6G 0 0 0 0 -1 1 3 >= 3

1

0Start

43

2

A5

B8

C10

E4

D5

G3

F6

5End

Operations -- Prof. Juran 46

Critical Activities: Using the Solver Answer Report

ConstraintsCell Name Cell Value Formula Status Slack

$H$12 A 5 $H$12>=$J$12 Binding 0$H$13 B 8 $H$13>=$J$13 Binding 0$H$14 C 10 $H$14>=$J$14 Binding 0$H$15 D 13 $H$15>=$J$15 Not Binding 8$H$16 E 4 $H$16>=$J$16 Binding 0$H$17 F 6 $H$17>=$J$17 Binding 0$H$18 G 3 $H$18>=$J$18 Binding 0

Operations -- Prof. Juran 47

House-Building Example, Continued

Suppose that by hiring additional workers, the duration of each activity can be reduced. Use LP to find the strategy that minimizes the cost of completing the project within 20 days.

Operations -- Prof. Juran 48

Crashing Parameters

Activity Cost per Day to

Reduce Duration Maximum Possible Reduction (Days)

Build foundation $30 2 Walls and ceilings $15 3 Build roof $20 1 Electrical wiring $40 2 Put in windows $20 2 Put on siding $30 3 Paint house $40 1

Operations -- Prof. Juran 49

Managerial Problem Definition

Find a way to build the house in 20 days.

Operations -- Prof. Juran 50

Formulation

Decision VariablesNow the problem is not only when to schedule the activities, but also which activities to accelerate. (In CPM jargon, accelerating an activity at an additional cost is called “crashing”.)

ObjectiveMinimize the total cost of crashing.

Operations -- Prof. Juran 51

FormulationConstraintsThe project must be finished in 20 days.Each activity has a maximum amount of crash time.Each activity has a “basic” duration. (These durations were considered to have been fixed in Part a; now they can be reduced.)There are precedence relationships among the activities.We cannot go backwards in time.

Operations -- Prof. Juran 52

Formulation

Decision VariablesDefine the number of days that activity x is crashed to be Rx.

For each activity there is a maximum number of crash days Rmax, x

Define the crash cost per day for activity x to be Cx

 

ObjectiveMinimize Z =

7

1xxxCR

Operations -- Prof. Juran 53

FormulationConstraints

For every activity x,

For every activity x,

For every node i,

xxjxkx Rdtt

xx RR max,

0it

Operations -- Prof. Juran 54

Solution Methodology

123

456

7891011

12131415161718

A B C D E F G H I J K L M N O

30

t0 t1 t2 t3 t4 t50 5 13 17 23 26

20 <-- Max Completion Time

t0 t1 t2 t3 t4 t5 Improved Duration Basic Duration Crash Time Max Crash Cost/Time

A -1 1 0 0 0 0 5 >= 4 5 1 2 30$ B 0 -1 1 0 0 0 8 >= 8 8 0 3 15$ C 0 0 -1 0 1 0 10 >= 10 10 0 1 20$ D 0 0 -1 0 0 1 13 >= 5 5 0 2 40$ E 0 0 -1 1 0 0 4 >= 4 4 0 2 20$ F 0 0 0 -1 1 0 6 >= 6 6 0 3 30$ G 0 0 0 0 -1 1 3 >= 3 3 0 1 40$

1

0Start

43

2

A5

B8

C10

E4

D5

G3

F6

5End

=SUMPRODUCT($B$6:$G$6,B12:G12) =L12-M12

=SUMPRODUCT(M12:M18,O12:O18)

Operations -- Prof. Juran 55

Solution Methodology

G3 now contains a formula to calculate the total crash cost. The new decision variables (how long to crash each activity x, represented by Rx) are in M12:M18.

G8 contains the required completion time, and we will constrain the value in G6 to be less than or equal to G8.

The range J12:J18 calculates the revised duration of each activity, taking into account how much time is saved by crashing.

Operations -- Prof. Juran 56

Operations -- Prof. Juran 57

Optimal Solution12

3

45

6

7891011

12131415161718

A B C D E F G H I J K L M N O

145

t0 t1 t2 t3 t4 t5

0 3 8 11 17 20

20 <-- Max Completion Time

t0 t1 t2 t3 t4 t5 Improved Duration Basic Duration Crash Time Max Crash Cost/Time

A -1 1 0 0 0 0 3 >= 3 5 2 2 30$ B 0 -1 1 0 0 0 5 >= 5 8 3 3 15$ C 0 0 -1 0 1 0 9 >= 9 10 1 1 20$ D 0 0 -1 0 0 1 12 >= 5 5 0 2 40$ E 0 0 -1 1 0 0 3 >= 3 4 1 2 20$ F 0 0 0 -1 1 0 6 >= 6 6 0 3 30$ G 0 0 0 0 -1 1 3 >= 3 3 0 1 40$

1

0Start

43

2

A5

B8

C10

E4

D5

G3

F6

5End

Operations -- Prof. Juran 58

Crashing Solution

Basic Duration Crash Time Improved Duration Cost/Time Cost A 5 2 3 $30 $60 B 8 3 5 $15 $45 C 10 1 9 $20 $20 D 5 0 5 $40 $- E 4 1 3 $20 $20 F 6 0 6 $30 $- G 3 0 3 $40 $- $145

Operations -- Prof. Juran 59

Crashing SolutionIt is feasible to complete the project in 20 days, at a cost

of $145.

1

0Start

43

2

A3

B5

C9

E3

D5

G3

F6

5End

Operations -- Prof. Juran 60

Summary• Definition of Project Management

– Work Breakdown Structure– Project Control Charts– Structuring Projects

• Critical Path Scheduling– By Hand– Linear Programming

• PERT– By Hand