Module 2 Commissioning Switch Gear Assemblies

Post on 28-Nov-2014

718 views 1 download

Transcript of Module 2 Commissioning Switch Gear Assemblies

04/09/23 Module Two 1

SUBSTATION COMMISSIONING COURSE

MODULE TWO

SWITCHGEAR ASSEMBLIESTESTING PROCEDURES

04/09/23 Module Two 2

INTRODUCTION

• The electrical commissioning and acceptance testing of electric power systems is essential for the energization of any electrical system for the first time.

04/09/23 Module Two 3

INTRODUCTION

Module Two:• Introduce the NETA acceptance

testing procedures– Visual and mechanical

inspections– Electrical tests– Assessment of test results

• Test equipment operation & hands on testing

• Adopting safe work practices

04/09/23 Module Two 4

INTRODUCTION

By the end of MODULE ZERO:• Perform acceptance testing

procedure for switchgear assemblies

• Operate insulation and dielectric test equipment

• Operate Digital Low Resistance Ohmmeter (DLRO)

• Apply safe work practices• Analyze test values• Complete test forms

04/09/23 Module Two 5

ELECTRICAL TESTING

• Majority of testing is to check the insulation system integrity

• Types of Solid Insulation testing:– Insulation Resistance test

• Prelude for the Dielectric Withstand– Dielectric Withstand test

• Survivability for high voltage spikes– Switching, lightning induced over

voltages and transients

04/09/23 Module Two 6

TESTING

Insulation Testing:• Insulation

Resistance

DC Insulation Resistance Test• Conducted at 100% of

operating stress level• AC RMS voltage x 1.414• Voltage applied < 1000 V/s• Voltage held for 1 minute• If “pass”, proceed to dielectric

withstand test

– NOTE: Voltage level specified is higher than NETA test voltage

04/09/23 Module Two 7

TESTING

Insulation Testing:• Insulation

Resistance

Test Volt. Calculation example:

Nameplate Rated voltage: 5 kV

Ø – gnd voltage = 5 kV / 1.732

= 2.887 kV

Crest Voltage = 2.9 kV x 1.414

= 4.1 kV

Test Voltage = 4.1 kV

04/09/23 Module Two 8

ELECTRICAL TESTING

04/09/23 Module Two 9

TESTING

Insulation Testing:• Insulation

Resistance

IR Test Procedure:• Isolate equipment• Prepare the DUT• Prepare the Test set• Apply test voltage

04/09/23 Module Two 10

TESTING

Insulation Testing:• Insulation Resistance

Test Procedure– Isolate equipment– Prepare the DUT– Prepare the Test set– Apply test voltage

Isolate Equipment / DUT:• Apply isolation / lock-out /

grounding procedure• Obtain test and work

permit• Install DANGER HIGH

VOLTAGE – TESTING IN PROGRESS warning signs

• Install barrier tape or high visibility rope barrier

04/09/23 Module Two 11

TESTING

04/09/23 Module Two 12

TESTING

Insulation Testing:• Insulation Resistance

Test Procedure– Isolate equipment– Prepare the DUT– Prepare the Test set– Apply test voltage

Prepare the DUT:• Disconnect all incoming

and outgoing cables– Maintain adequate

clearance• Remove primary fuses

from VT / PT’s and CPT• Disconnect surge arrestors

04/09/23 Module Two 13

TESTING

Insulation Testing:• Insulation Resistance

Test Procedure– Isolate equipment– Prepare the DUT– Prepare the Test set– Apply test voltage

Prepare the Test Set:• Functional check

– Battery Level– Calibration date– Short circuit test– Recording paper

• Link computer software• Use grounded plug / GFI if

AC powered

04/09/23 Module Two 14

TESTING

Insulation Testing:• Insulation Resistance

Test Procedure– Isolate equipment– Prepare the DUT– Prepare the Test set– Apply test voltage

Apply test voltage:• Apply test voltage• Test to the desired time

interval• Discharge / ground tested

phase before changing / removing connections

• Review test data• Proceed to dielectric test

IF results are satisfactory !

04/09/23 Module Two 15

TESTINGNETA Insulation Resistance Test Voltage level

04/09/23 Module Two 16

TESTING

Insulation Testing:• Dielectric Withstand

Dielectric Withstand Test• AC / DC depending on class• Factory Test + 200% of rated

voltage• Field acceptance test @ 75% of

Factory level

04/09/23 Module Two 17

ELECTRICAL TESTING

Insulation Testing:• Dielectric Withstand

AC Dielectric Withstand Test• Rated power frequency, 60 Hz • Voltage applied at a rate

< 1000 V per second• Voltage held for 1 minute

CAUTION: AC Hipot can be a destructive test

04/09/23 Module Two 18

ELECTRICAL TESTING

Insulation Testing:• Dielectric Withstand

Factory AC Dielectric Withstand Test as per IEEE C37.20.2

Rated max Volts Test Volts

(kV rms) (kV rms)

4.76 14.0

8.25 27.0

15.0 27.0

27.0 38.0

38.0 60.0

04/09/23 Module Two 19

ELECTRICAL TESTING

Phase A Hot: AC Hipot, Breaker Connected & Closed

04/09/23 Module Two 20

ELECTRICAL TESTING

Phase B Hot: AC Hipot, Breaker Connected & Closed

04/09/23 Module Two 21

ELECTRICAL TESTING

Phase C Hot: AC Hipot, Breaker Connected & Closed

04/09/23 Module Two 22

ELECTRICAL TESTING

Phase A Hot: AC Hipot, Breaker Connected & Opened

04/09/23 Module Two 23

ELECTRICAL TESTING

Phase B Hot: AC Hipot, Breaker Connected & Opened

04/09/23 Module Two 24

ELECTRICAL TESTING

Phase C Hot: AC Hipot, Breaker Connected & Opened

04/09/23 Module Two 25

TESTING

Insulation Testing:• Dielectric Withstand

60 Hz

Dielectric Test Procedure:• Isolate equipment• Prepare the DUT• Prepare the Test set• Apply test voltage

04/09/23 Module Two 26

TESTING

Insulation Testing:• Dielectric Withstand Test

Procedure - 60 Hz– Isolate equipment– Prepare the DUT– Prepare the Test set– Apply test voltage

Isolate Equipment / DUT:• Apply isolation / lock-out /

grounding procedure• Obtain test and work

permit• Install DANGER HIGH

VOLTAGE – TESTING IN PROGRESS warning signs

• Install barrier tape or high visibility rope barrier

04/09/23 Module Two 27

TESTING

04/09/23 Module Two 28

TESTING

Insulation Testing:• Dielectric Withstand Test

Procedure – 60 Hz– Isolate equipment– Prepare the DUT– Prepare the Test set– Apply test voltage

Prepare the DUT:• Disconnect all incoming

and outgoing cables– Maintain adequate

clearance• Remove primary fuses

from VT / PT’s and CPT• Disconnect surge arrestors• Ensure equipment is

grounded

04/09/23 Module Two 29

TESTING

Insulation Testing:• Dielectric Withstand Test

Procedure – 60 Hz– Isolate equipment– Prepare the DUT– Prepare the Test set– Apply test voltage

Prepare the Test Set:• Perform functional check

– Spark Gap test– Recording paper

• Link computer software• Use grounded plug / GFI• Ground test set to

equipment ground

04/09/23 Module Two 30

TESTING

Insulation Testing:• Dielectric Withstand Test

Procedure – 60 Hz– Isolate equipment– Prepare the DUT– Prepare the Test set– Apply test voltage

Apply test voltage:• Apply test voltage• Test to the desired time

interval• Discharge / ground tested

phase before changing / removing connections

• Review test data

04/09/23 Module Two 31

TESTING

Dielectric Withstand Test – 60 Hz• Some manufacturer recommend Low Frequency

withstand voltage VS Power Frequency• Field test voltage levels are the same• Field test voltage at 75% of factory test voltage• DC Hipot is not recommended but not prohibited

04/09/23 Module Two 32

TESTING

Dielectric Withstand Test – DC• Will not be presented• Included in the manual for the sake of

completeness

04/09/23 Module Two 33

TESTING

Low Resistance test• Measures bolted connection resistance

– Bus bar to bus bar resistance– Bus bars to cable resistance

• DC test at constant 100 ADC or higher• Joints must be torque to specified force (ft-lbs)• Values are compared to similar joints• High reading joints are inspected / retorque /

reassembled and retested

04/09/23 Module Two 34

TESTING

Low Resistance test• Access to main bus compartment required

– Remove metal barriers for access– Insulating boots for bolted joints removed

• Measure on a per phase basis• Resistance calculated based on Ohm’s Law

– Example: – 1 mV across joint equates to 10 μΩ– (1 X 10-3 V) / (1 x 102 A) = 1 x 10-5 = 10 x 10-6

04/09/23 Module Two 35

TESTING

04/09/23 Module Two 36

TESTING

Low Voltage Testing:• Low Resistance

Test Procedure

Low Resistance test:• Isolate equipment• Prepare the DUT• Prepare the Test set• Apply test current

04/09/23 Module Two 37

TESTING

Low Test Resistance Procedure– Isolate equipment– Prepare the DUT– Prepare the Test set– Apply test current

Isolate Equipment / DUT:• Apply isolation / lock-out /

grounding procedure• Obtain test and work

permit• Install DANGER HIGH

VOLTAGE – TESTING IN PROGRESS warning signs

• Install barrier tape or high visibility rope barrier

04/09/23 Module Two 38

TESTING

04/09/23 Module Two 39

TESTING

Low Test Resistance Procedure– Isolate equipment– Prepare the DUT– Prepare the Test set– Apply test current

Prepare the DUT:• Ensure equipment is

grounded

04/09/23 Module Two 40

TESTING

Low Test Resistance Procedure– Isolate equipment– Prepare the DUT– Prepare the Test set– Apply test current

Prepare the Test Set:• Perform functional check

– Calibration resistor• Use grounded plug / GFI

04/09/23 Module Two 41

TESTING

Low Test Resistance Procedure– Isolate equipment– Prepare the DUT– Prepare the Test set– Apply test current

Apply test current:• Apply test current• Measure resistance of all

bolted connections• Measure resistance of all

breaker connections– Sliding contacts– Main contacts

• Review test data

04/09/23 Module Two 42

SAFETY AWARENESS & PRACTICE

• HV testing is an electrical shock potential• Test set operators must:

– be aware of the hazards involved in performing the task

– take the required safety precautions and restrict access to anyone not involved in the testing process

– be properly trained in the equipment operations – recognize and avoid the hazards– be trained in safe work practices and procedures

04/09/23 Module Two 43

SAFETY AWARENESS & PRACTICEQualified person

A qualified person shall be trained and knowledgeable of the construction and operation of equipment or a specific work method, and be trained to recognize and avoid the electrical hazard that might be present with respect to

that equipment or work method. Such persons shall also be familiar with the proper use of special precautionary techniques, personal protective equipment, insulating and shielding material, and insulating tools and test

equipment.

04/09/23 Module Two 44

Qualification of Qualified Person1. Basic understanding of

electricity

2. Working knowledge of test equipment and hazards with the test and equipment

3. Understand approach distances

4. Trained is safe work practices and procedures

5. Understand the factors affecting severity of electrical shock

6. Know the effects of current to the body

7. Trained on releasing a victim from energized circuit

8. Trained not to contact a device under test

9. Understand that enclosure and test equipment must be grounded

10. Know that DUT must be discharge before changing / removing any connections

04/09/23 Module Two 45

SAFETY AWARENESS & PRACTICE

• Engineering controls and work practices primary factors for safeguarding against risk of injury

• PPE is not an alternative to safe work practices

04/09/23 Module Two 46

SAFETY AWARENESS & PRACTICE

Resources:• IEEE Standard 510 – 1983,

Recommended Practice for Safety in High Voltage & High Power Testing

• NEMA Standard Publication SG 10 – 2008, Guide to OSHA and NFPA 70E Safety Requirements When Servicing and Maintaining Medium-Voltage Switchgear and Circuit Breakers Rated above 1000 Volts.

04/09/23 Module Two 47

NETA STANDARD

3. NETA Acceptance Testing Procedures 3.1 Visual and Mechanical Inspection 3.2 Electrical Test 3.3 Test values analysis 3.3.1 Visual and Mechanical 3.3.2 Electrical

04/09/23 Module Two 48

TEST SET MANUALS

15 KV Insulation Resistance Test set

AC High Potential Test set DC High Potential Test set Digital Low Resistance Test set

04/09/23 Module Two 49

TEST FORM

Switchgear Inspection Check List Form Bus Resistance Test Form Bus Insulation Test Form

04/09/23 Module Two 50

04/09/23 Module Two 51

04/09/23 Module Two 52