Heimdal

Our Modular Concept ready when required Presentation to: NPF P&A Forum

Presented by Jarle Liland

30rd October 2014

.

Introduction to Archer 2

Archer’s heritage

Archer is the integration of several well-specialist companies

Over 8,500 employees

108 Wireline trucks

24 Coiled tubing units

30 Snubbing units

20 Nitrogen units

208,000 HHP/6 fleets

77 Land rigs

30 Platforms

2 MODU

32 Offshore Wireline units

3

Our global footprint and reach

Michigan

Pennsylvania

West Virginia

Arkansas

Mississippi

Louisiana

Aracaju

Rio De Janeiro

Pico Truncado

Buenos Aires

Rincon de los Sauces

Rio Grande

Stavanger

Esbjerg

Abu Dhabi

Beijing

New Mexico

Oklahoma

Colorado

Wyoming

North Dakota

Santa Cruz de la Sierra

Tartagal

Nequen

Lagos

Bergen

Al Khobar

Perth

New Plymouth

Kuala Lumpur

Aberdeen

Newcastle

London

Catu

Texas

Doha Dubai

Singapore Labuan

Jakarta

Pau

100+ global locations

Platform drilling operations

4

Brazil - 2 installations

2 Drilling

UK - 17 installations

9 Drilling

1 Well intervention (roving crews)

3 Maintenance (warm stack)

4 Non operational (cold stack)

Norway - 11 installations

7 Drilling

4 Maintenance (warm stack)

1 MDR (under construction)

New Zealand - 1 MDR

1 MDR Drilling

> 2,300 offshore personnel

Currently 31 global installations

Specialists do the job best - © 2013 5

1. Archer Emerald the first Modular rig operated in New Zealand (Going to UK and will start operating for Talisman next year)

2. Archer Topaz Heimdal

Market

Private and Confidential 6

Today’s Agenda

• Scope of Work

• Challenges

• Time Schedule

• Solution

• Preparations

• Rig Up on Heimdal

• Animation

Scope of Work

Private and Confidential 7

Scope of Work

Specialists do the job best - © 2013 8

The award demonstrates the attractiveness of the modular rig concept

which combines flexibility and efficiency.

1. Build a new Modular Rig fit for Heimdal and deliver at Mongstad latest

15 of August 2014, 18 months later

- Contract award: 1 February 2013

- Contract duration 34 months

2. Offshore

- Upgrade of the Mud mix system onboard Heimdal and all utility interfaces

- Plug & Abandon of 14 wells on Heimdal

Archer Topaz - Just the right size!

Specialists do the job best - © 2013 9

• Rotation

• Pull

• Well controll systems

• Pipe handling

• On Heimdal also Pipe deck

• Mudpumps

• Active mud systems

• Shakers

• Swarf

• Power

• Power distribution

• HVAC

Our concept = You get it all!

In addition: (Upgrade of the existing equipment)

Cement unit

Reserve pits and mixing systems including

Bulk system

MDR specifications

Specialists do the job best - © 2013 10

• Weight: 1500 ton in total

• Total number of lifts: 220

• No lift over 120 ton

• Pull Capacity: 380 ton

• Torque: 62.000 ft/lbs

• Max RPM: 190

• Circulation pressure: 5000 psi

• Pipedeck Capacity: 150 ton

Challenges

Private and Confidential 11

1. Challenges

Challenges

Specialists do the job best - © 2013

12

Onshore:

• Building Schedule and Delivery time

• Safe and Correct planned logisticks

Offshore:

• Lay down areas

• Space

• No existing pipe deck

• Blind zones when rigging up

• Interface work offshore

• Upgrade of some drilling support

system

Only one miss gave us 6 hours downtime

Private and Confidential 13

3. Solution

Time Schedule

Schedule / Real time

Specialists do the job best - © 2013 14

1 February 2013 18 June 2014

Building

Transport Germany - Norway

Plan

Arrived 12th of August, one day ahead of plan

1 February 2013 18 June 2014

12 August

15 August

Time Schedule

Specialists do the job best - © 2013 15

• Four Canal Boats from Deggendorf to Antwerpen

• Two Supply boats from Antwerpen to Mongstad

• +15 Truck direct to Mongstad

Rigging up in Deggendorf (March 2014)

Mongstad to Heimdal

Specialists do the job best - © 2013 16

• Number of Supply boats arrived 12

• First Boat arrived to Heimdal 16 August

• Last boat arrived 26 September

• Number of lifts from boat to Heimdal 220

• Total weight 1500 Ton

Further plan

Specialists do the job best - © 2013 17

• Integration test started week 42

• Commisioning started week 43 (20 October)

• Week 44 perform ESD tests

• 12 November start with both day- and night shifts

(Up to now only day shift)

• 15 November start Wireline Operations

• 15 January 2015 the PP&A will start

Private and Confidential 18

3. Solution

Solution

First 3D made of the Concept

Specialists do the job best - © 2013 19

Private and Confidential 20

3. Solution

Preparations

Preparations

Specialists do the job best - © 2013 21

• Establish a maintenance program

• Establish all the operating procedures that are required in the Compass

• Crews (Liberation/training/training/comp) all against internal requirements as

well as Statoil and contract, and regulatory requirements

• Meet all the documentation requirements according to regulations and

contract

• Planning/preparing/logistics management from Mongstad to the Heimdal

• Interoperability between all companies and departments

Private and Confidential 22

3. Solution

Rig up on Heimdal

Rig up on Heimdal

Specialists do the job best - © 2013 23

• Start the Lifting Operations the 26 August

• Finished the 26 September

In Total 37 Days with a POB like xx

Hatch-/skid Deck

Specialists do the job best - © 2013 24

Specialists do the job best - © 2013 25

Power distribution

Specialists do the job best - © 2013 26

Power distribution

Skid beams Basic Rig

Dragchain

Specialists do the job best - © 2013 27

Cables Yes

Specialists do the job best - © 2013 28

All cables with a unik key

Basic Rig

Specialists do the job best - © 2013 29

Drill floor

Specialists do the job best - © 2013 30

Private and Confidential 31

Top drive

Specialists do the job best - © 2013 32

Specialists do the job best - © 2013 33

Drill floor

Specialists do the job best - © 2013 34

Specialists do the job best - © 2013 35

Skid beams for the

Mud- and pump units

Specialists do the job best - © 2013 36

4 Mud pumps

Specialists do the job best - © 2013 37

Active mud tanks

DAY 37 Friday 26.09.2014

• Rig Up and Lifting phase finished

• Than the Hook Up and connection phase

Private and Confidential 38

Specialists do the job best - © 2013 39

Rig Up Animation

Safety Summary

Specialists do the job best - © 2013 40

• 623 OBS Cards

• 0 LTI

• 0 Dropped objects

• 0 Serious incidents

• 0 Harm to personnel, enviroment or equipment

Private and Confidential 41

Everything according to plan so far!

Thank you.