Heimdal
Our Modular Concept ready when required Presentation to: NPF P&A Forum
Presented by Jarle Liland
30rd October 2014
.
Introduction to Archer 2
Archer’s heritage
Archer is the integration of several well-specialist companies
Over 8,500 employees
108 Wireline trucks
24 Coiled tubing units
30 Snubbing units
20 Nitrogen units
208,000 HHP/6 fleets
77 Land rigs
30 Platforms
2 MODU
32 Offshore Wireline units
3
Our global footprint and reach
Michigan
Pennsylvania
West Virginia
Arkansas
Mississippi
Louisiana
Aracaju
Rio De Janeiro
Pico Truncado
Buenos Aires
Rincon de los Sauces
Rio Grande
Stavanger
Esbjerg
Abu Dhabi
Beijing
New Mexico
Oklahoma
Colorado
Wyoming
North Dakota
Santa Cruz de la Sierra
Tartagal
Nequen
Lagos
Bergen
Al Khobar
Perth
New Plymouth
Kuala Lumpur
Aberdeen
Newcastle
London
Catu
Texas
Doha Dubai
Singapore Labuan
Jakarta
Pau
100+ global locations
Platform drilling operations
4
Brazil - 2 installations
2 Drilling
UK - 17 installations
9 Drilling
1 Well intervention (roving crews)
3 Maintenance (warm stack)
4 Non operational (cold stack)
Norway - 11 installations
7 Drilling
4 Maintenance (warm stack)
1 MDR (under construction)
New Zealand - 1 MDR
1 MDR Drilling
> 2,300 offshore personnel
Currently 31 global installations
Specialists do the job best - © 2013 5
1. Archer Emerald the first Modular rig operated in New Zealand (Going to UK and will start operating for Talisman next year)
2. Archer Topaz Heimdal
Market
Private and Confidential 6
Today’s Agenda
• Scope of Work
• Challenges
• Time Schedule
• Solution
• Preparations
• Rig Up on Heimdal
• Animation
Scope of Work
Private and Confidential 7
Scope of Work
Specialists do the job best - © 2013 8
The award demonstrates the attractiveness of the modular rig concept
which combines flexibility and efficiency.
1. Build a new Modular Rig fit for Heimdal and deliver at Mongstad latest
15 of August 2014, 18 months later
- Contract award: 1 February 2013
- Contract duration 34 months
2. Offshore
- Upgrade of the Mud mix system onboard Heimdal and all utility interfaces
- Plug & Abandon of 14 wells on Heimdal
Archer Topaz - Just the right size!
Specialists do the job best - © 2013 9
• Rotation
• Pull
• Well controll systems
• Pipe handling
• On Heimdal also Pipe deck
• Mudpumps
• Active mud systems
• Shakers
• Swarf
• Power
• Power distribution
• HVAC
Our concept = You get it all!
In addition: (Upgrade of the existing equipment)
Cement unit
Reserve pits and mixing systems including
Bulk system
MDR specifications
Specialists do the job best - © 2013 10
• Weight: 1500 ton in total
• Total number of lifts: 220
• No lift over 120 ton
• Pull Capacity: 380 ton
• Torque: 62.000 ft/lbs
• Max RPM: 190
• Circulation pressure: 5000 psi
• Pipedeck Capacity: 150 ton
Challenges
Private and Confidential 11
1. Challenges
Challenges
Specialists do the job best - © 2013
12
Onshore:
• Building Schedule and Delivery time
• Safe and Correct planned logisticks
Offshore:
• Lay down areas
• Space
• No existing pipe deck
• Blind zones when rigging up
• Interface work offshore
• Upgrade of some drilling support
system
Only one miss gave us 6 hours downtime
Private and Confidential 13
3. Solution
Time Schedule
Schedule / Real time
Specialists do the job best - © 2013 14
1 February 2013 18 June 2014
Building
Transport Germany - Norway
Plan
Arrived 12th of August, one day ahead of plan
1 February 2013 18 June 2014
12 August
15 August
Time Schedule
Specialists do the job best - © 2013 15
• Four Canal Boats from Deggendorf to Antwerpen
• Two Supply boats from Antwerpen to Mongstad
• +15 Truck direct to Mongstad
Rigging up in Deggendorf (March 2014)
Mongstad to Heimdal
Specialists do the job best - © 2013 16
• Number of Supply boats arrived 12
• First Boat arrived to Heimdal 16 August
• Last boat arrived 26 September
• Number of lifts from boat to Heimdal 220
• Total weight 1500 Ton
Further plan
Specialists do the job best - © 2013 17
• Integration test started week 42
• Commisioning started week 43 (20 October)
• Week 44 perform ESD tests
• 12 November start with both day- and night shifts
(Up to now only day shift)
• 15 November start Wireline Operations
• 15 January 2015 the PP&A will start
Private and Confidential 18
3. Solution
Solution
First 3D made of the Concept
Specialists do the job best - © 2013 19
Private and Confidential 20
3. Solution
Preparations
Preparations
Specialists do the job best - © 2013 21
• Establish a maintenance program
• Establish all the operating procedures that are required in the Compass
• Crews (Liberation/training/training/comp) all against internal requirements as
well as Statoil and contract, and regulatory requirements
• Meet all the documentation requirements according to regulations and
contract
• Planning/preparing/logistics management from Mongstad to the Heimdal
• Interoperability between all companies and departments
Private and Confidential 22
3. Solution
Rig up on Heimdal
Rig up on Heimdal
Specialists do the job best - © 2013 23
• Start the Lifting Operations the 26 August
• Finished the 26 September
In Total 37 Days with a POB like xx
Hatch-/skid Deck
Specialists do the job best - © 2013 24
Specialists do the job best - © 2013 25
Power distribution
Specialists do the job best - © 2013 26
Power distribution
Skid beams Basic Rig
Dragchain
Specialists do the job best - © 2013 27
Cables Yes
Specialists do the job best - © 2013 28
All cables with a unik key
Basic Rig
Specialists do the job best - © 2013 29
Drill floor
Specialists do the job best - © 2013 30
Private and Confidential 31
Top drive
Specialists do the job best - © 2013 32
Specialists do the job best - © 2013 33
Drill floor
Specialists do the job best - © 2013 34
Specialists do the job best - © 2013 35
Skid beams for the
Mud- and pump units
Specialists do the job best - © 2013 36
4 Mud pumps
Specialists do the job best - © 2013 37
Active mud tanks
DAY 37 Friday 26.09.2014
• Rig Up and Lifting phase finished
• Than the Hook Up and connection phase
Private and Confidential 38
Specialists do the job best - © 2013 39
Rig Up Animation
Safety Summary
Specialists do the job best - © 2013 40
• 623 OBS Cards
• 0 LTI
• 0 Dropped objects
• 0 Serious incidents
• 0 Harm to personnel, enviroment or equipment
Private and Confidential 41
Everything according to plan so far!