Post on 15-Feb-2017
BIM INTERNATIONAL CONFERENCEBIC2016 | LISBON, OCTOBER 13&14
BIM Project Execution Plans and Open BIM via IFC2x3*
Carmona, Covadonga; Carrato, AlfredoMadrid, Spain
* Full article at https://www.academia.edu/29639430/BIM_Project_Execution_Plans_and_Open_BIM_via_IFC2x3
BIM (Project) Execution Plan
BPEPs contain the following information:
• Project Information.• Responsible Parties.• Goals and BIM Uses.• Model/s Structure.• Collaboration Strategy.• Schedules & Deliverables.
2.1. Guides and Templates for the Creation of BIM Project Execution Plans
BIM Project Execution Plans and Open BIM via IFC2x3 2BIC2016 | Lisbon
According to BSI PAS 1192-2:2013, “
1. Introduction
BIM (Project) Execution Plan
BPEPs contain the following information:
• Project Information.• Responsible Parties.• Goals and BIM Uses.• Model/s Structure.• Collaboration Strategy.• Schedules & Deliverables.• BIM Interoperability & Quality Control.
3.1. Open Standards for BIM
BIM Project Execution Plans and Open BIM via IFC2x3 3BIC2016 | Lisbon
According to BSI PAS 1192-2:2013: “
BIM Project Execution Plans and Open BIM via IFC2x3 4BIC2016 | Lisbon
2. Materials and Method
4.1. buildingSMART CV2.0 certified software reports
IFC2x3
IFC2x3
BIM Project Execution Plans and Open BIM via IFC2x3 5BIC2016 | Lisbon
5.1. buildingSMART CV2.0 certified software reports
IFC2x3
IFC2x3
BIM Project Execution Plans and Open BIM via IFC2x3 6BIC2016 | Lisbon
6.1. buildingSMART CV2.0 certified software reports
IFC2x3
IFC2x3
BIM Project Execution Plans and Open BIM via IFC2x3 7BIC2016 | Lisbon
7.1. buildingSMART CV2.0 certified software reports
IFC2x3
IFC2x3
BIM Project Execution Plans and Open BIM via IFC2x3 8BIC2016 | Lisbon
Beam_01 / 2x3 10 concepts analyzedSlab 02A / 2x3 24 concepts analyzed
Window 01 / 2x3 22 concepts analyzed
56 concepts analyzedx 4 authoring tools
224 concepts analyzed
8.1. buildingSMART CV2.0 certified software reports
BIM Project Execution Plans and Open BIM via IFC2x3 9BIC2016 | Lisbon
3. Results and Discussion
Supported Restricted Not Supported
Beam_01 / 2x3
Bentley AECOsim 8 80,00% 0,00% 2 20,00%
Nemetschek Allplan 7 70,00% 3 30,00% 0,00%
Graphisoft ArchiCAD 8 80,00% 1 10,00% 1 10,00%
Autodesk Revit 6 60,00% 4 40,00% 0,00%
Slab 02A / 2x3
Bentley AECOsim 17 70,80% 0,00% 7 29,20%
Nemetschek Allplan 9 37,50% 3 12,50% 12 50,00%
Graphisoft ArchiCAD 14 58,30% 1 4,16% 9 37,54%
Autodesk Revit 9 37,50% 2 8,33% 13 54,17%
Window 01 / 2x3
Bentley AECOsim 19 86,36% 0,00% 3 13,64%
Nemetschek Allplan 16 72,73% 0,00% 6 27,27%
Graphisoft ArchiCAD 15 68,18% 1 4,55% 6 27,27%
Autodesk Revit 13 59,09% 4 18,18% 5 22,73%
24 100,00%
22 100,00%
Concepts analyzed
10 100,00%
9.1. Export of building elements to IFC2x3 by differentBIM authoring tools
Supported Restricted Not Supported
Beam_01 / 2x3 6 60,00% 4 40,00% 0,00% 10 100,00%
Slab 02A / 2x3 9 37,50% 2 8,33% 13 54,17% 24 100,00%
Window 01 / 2x3 13 59,09% 4 18,18% 5 22,73% 22 100,00%
Concepts analyzed
Supported Restricted Not Supported
Beam_01 / 2x3 8 80,00% 0,00% 2 20,00% 10 100,00%
Slab 02A / 2x3 17 70,80% 0,00% 7 29,20% 24 100,00%
Window 01 / 2x3 19 86,36% 0,00% 3 13,64% 22 100,00%
Concepts analyzed
BIM Project Execution Plans and Open BIM via IFC2x3 10BIC2016 | Lisbon
• Best average results – Bentley AECOsim
78.57% of supported concepts, best overall export in Window 01 / 2x3 (86.36% of accuracy).
• Worst average results – Autodesk Revit
50.00% of supported concepts, lowest global accuracy in Slab 02A / 2x3 (37.50%).
10.1. Export of building elements to IFC2x3by Bentley AECOsim
10.2. Export of building elements to IFC2x3by Autodesk Revit
BIM Project Execution Plans and Open BIM via IFC2x3 11BIC2016 | Lisbon
11.1. Combination analyses of exported building elements to IFC2x3
BIM Project Execution Plans and Open BIM via IFC2x3 12BIC2016 | Lisbon
4. Conclusions
12.1. Sample IFC2x3 models from different BIM authoring toolsCourtesy of AGi architects
BIM Project Execution Plans and Open BIM via IFC2x3 13BIC2016 | Lisbon
• As the number of building elements and/orthe number of BIM authoring tools rises,the number of unsupported IFC2x3 itemsincreases too.
• Unsupported items start rising linearly, butsoon experience an exponential growth.
• Therefore, interoperability issues should beaddressed thoroughly in BIM ExecutionPlans prior to any modeling, in order toanticipate and minimize – at a lower cost –potential problems that may arise.
• The ideal (utopian?) situation would reveala flat number of unsupported items –tending to zero – regardless the number ofbuilding elements and/or BIM authoringtools that are employed in the project.
BIM Project Execution Plans and Open BIM via IFC2x3 14BIC2016 | Lisbon
14.1 IFC – Levels of MaturityCredits: Keenliside, Liebich, Grobler (2012)
BIM Project Execution Plans and Open BIM via IFC2x3 15BIC2016 | Lisbon
5. References
• buildingSMART. CV 2.0 / Export - Bentley Systems, Incorporated AECOsim Building Designer. 18/12/2015. [Online] Available at http://87.106.145.222/ords/ifc/certification/getCertificationReport/481. 04/06/2016.
• buildingSMART. CV 2.0 / Export – NEMETSCHEK Allplan Allplan 2013. 03/05/2013.[Online] Available at http://87.106.145.222/ords/ifc/certification/getCertificationReport/102. 04/06/2016.
• buildingSMART. CV 2.0 / Export – GRAPHISOFT ArchiCAD. 25/09/2014.[Online] Available at http://87.106.145.222/ords/ifc/certification/getCertificationReport/101. 04/06/2016.
• buildingSMART. CV 2.0 / Export – Autodesk-R Autodesk Revit. 04/05/2013.[Online] Available at http://87.106.145.222/ords/ifc/certification/getCertificationReport/103. 04/06/2016.
• buildingSMART. Comparison RV & DTV. 10/07/2015. [Online] Available athttp://www.buildingsmart-tech.org/specifications/ifc-view-definition/ifc4-reference-view/comparison-rv-dtv#entity. 30/10/2016.
BIM INTERNATIONAL CONFERENCEBIC2016 | LISBON, OCTOBER 13&14
BIM Project Execution Plans and Open BIM via IFC2x3 16BIC2016 | Lisbon
Thank you very much for your attention! Muito obrigado pela sua atenção!
Covadonga Carmona: covadonga.carmona.ayuela@gmail.com
Alfredo Carrato: acarrato@agi-architects.com