Feedback and Complaints World Bank Group Procurement Event – 2 November 2016 WORLD BANK GROUP

Transcript of WORLD BANK GROUP · PDF fileFeedback and Complaints World Bank Group Procurement Event –...

Page 1: WORLD BANK GROUP · PDF fileFeedback and Complaints World Bank Group Procurement Event – 2 November 2016 WORLD BANK GROUP

Feedback and Complaints

World Bank Group Procurement Event – 2 November 2016

WORLD BANKGROUP

Page 2: WORLD BANK GROUP · PDF fileFeedback and Complaints World Bank Group Procurement Event – 2 November 2016 WORLD BANK GROUP

Topics

• Procurement routes

• Feedback

• Complaints

World Bank Group Procurement Event – 2 November 20162

Page 3: WORLD BANK GROUP · PDF fileFeedback and Complaints World Bank Group Procurement Event – 2 November 2016 WORLD BANK GROUP

Two Procurement Routes

Operational Procurement (Country Executed Projects)

• World Bank finances a project in a developingcountry:

o Sustainable Railways (Croatia)

o Coastal Embankment Improvement Project(Bangladesh)

• Procurement is responsibility of the borrowingcountry, but is subject to WB procurementframework – declaring misprocurement possible

• World Bank is a supervisor, not a party to thecontract

World Bank Group Procurement Event – 2 November 20163

Page 4: WORLD BANK GROUP · PDF fileFeedback and Complaints World Bank Group Procurement Event – 2 November 2016 WORLD BANK GROUP

Two Procurement Routes

Corporate Procurement (Bank Executed Projects)

• World Bank procures goods, works, orconsulting services

• <$50,000 WB can request CVs of 3 consultants

• >$50,000 tendered via eConsultant2

World Bank Group Procurement Event – 2 November 20164

Page 5: WORLD BANK GROUP · PDF fileFeedback and Complaints World Bank Group Procurement Event – 2 November 2016 WORLD BANK GROUP

How do I get feedback ?

Operational Procurement

• Project TTL or Borrowing Country

Corporate Procurement

• eConsultant2 ‘Contact Us’ page

World Bank Group Procurement Event – 2 November 20165

Page 6: WORLD BANK GROUP · PDF fileFeedback and Complaints World Bank Group Procurement Event – 2 November 2016 WORLD BANK GROUP

Common Complaints

• Money

o Not paid on time

o Received part of the money

• Process

o Communications unclear

o Complaints on winner project

o Variety of things can go wrong during the process

World Bank Group Procurement Event – 2 November 20166

Page 7: WORLD BANK GROUP · PDF fileFeedback and Complaints World Bank Group Procurement Event – 2 November 2016 WORLD BANK GROUP

NEW: Standstill Period

• Standstill Period: a pause between identifying who should winthe contract and actually awarding them the contract so thatother bidders can voice any concerns before a contract isactually legally formed and awarded

• Standstill Period lasts ten business days

• No Standstill Period when:

only one Bid/Proposal was submitted in an open competitiveprocess

direct selection

call-off process among firms holding Framework Agreements

Emergency Situations recognized by the Bank

World Bank Group Procurement Event – 2 November 20167

Page 8: WORLD BANK GROUP · PDF fileFeedback and Complaints World Bank Group Procurement Event – 2 November 2016 WORLD BANK GROUP

Roles and Responsibilities of the World Bank

• Complaints addressed to the Bank are forwarded to theBorrower for review and resolution

• In the case of prior review contracts: assist Borrower withaction to resolve the complaint

• Except for acknowledging receipt of a Complaint, the WorldBank does not discuss or communicate with any bidder duringthe evaluation and review process

World Bank Group Procurement Event – 2 November 20168

Page 9: WORLD BANK GROUP · PDF fileFeedback and Complaints World Bank Group Procurement Event – 2 November 2016 WORLD BANK GROUP

Roles and Responsibilities of the Borrower

• Provide timely and sufficient information to Bidders

• Promptly acknowledge Complaints received

• Resolve Complaints promptly and fairly

• Maintain complete records of all debriefings and Complaintsand their resolution

• Contracts subject to prior review: inform the World Bank of anycomplaint submitted and consult with the Bank throughout thereview and resolution process

World Bank Group Procurement Event – 2 November 20169

Page 10: WORLD BANK GROUP · PDF fileFeedback and Complaints World Bank Group Procurement Event – 2 November 2016 WORLD BANK GROUP

Roles and Responsibilities of the Bidders

• Be familiar with the necessary documents and the procurementprocess

• Timely request for debriefing, if desired

• Submit any complaint within the permitted timeframe

• Ensure that any complaint submitted is as specific as possiblein explaining the Bidder’s issues or concerns, and the allegedviolation of the applicable procurement rules

World Bank Group Procurement Event – 2 November 201610

Page 11: WORLD BANK GROUP · PDF fileFeedback and Complaints World Bank Group Procurement Event – 2 November 2016 WORLD BANK GROUP

Where do I submit a complaint?

Operational Procurement

Borrower (and TTL)

Corporate procurement

World Bank Group

Process on how to submit a complaint is set out in therequest for bids/request for proposals document

World Bank Group Procurement Event – 2 November 201611

Page 12: WORLD BANK GROUP · PDF fileFeedback and Complaints World Bank Group Procurement Event – 2 November 2016 WORLD BANK GROUP

What to do?

DO

• Step 1: Contact the Borrower and TTL of the project

• Step 2: Contact World Bank Group Liaisons StephanieBroeder and Vincent Kooijman

DO NOT

• Contact the World Bank Group Executive Directors office(Kiesgroep) or Frank Heemskerk

• Contact a bunch of people you may know at Ministry ofForeign Affairs

World Bank Group Procurement Event – 2 November 201612

Page 13: WORLD BANK GROUP · PDF fileFeedback and Complaints World Bank Group Procurement Event – 2 November 2016 WORLD BANK GROUP

World Bank/IDB Liaisons in Washington

Stephanie Broeder

[email protected]

Vincent Kooijman

[email protected]

www.nl4worldbank.org

Twitter: @NL4WB

World Bank Group Procurement Event – 2 November 201613

Page 14: WORLD BANK GROUP · PDF fileFeedback and Complaints World Bank Group Procurement Event – 2 November 2016 WORLD BANK GROUP

14

Questions & Comments

World Bank Group Procurement Event – 2 November 201614

Page 15: WORLD BANK GROUP · PDF fileFeedback and Complaints World Bank Group Procurement Event – 2 November 2016 WORLD BANK GROUP

15

Thank you!