Wind, Solar and Market Related Matters -...
Transcript of Wind, Solar and Market Related Matters -...
Wind, Solar and Market
Related Matters
LOLE Best Practices Working Group
July 25-26, 2013
Vancouver , Canada
Alex Papalexopoulos, Ph.D.
CEO & Founder, ECCO International, Inc.
San Francisco, CA
Outline
Problem Definition & Current Needs
Anatomy of a “Duck”
Power Market Changes
Software Flexibility Capability Requirements
Expected Flexibility Deficiency Definition
Flexibility Mitigation Strategies
Modeling Simulation Results & Metrics
Demand Response
Transmission Modeling
Conclusions
2 © Copyright 2013 ECCO International, Inc.
The Problem
Load is stochastic, variable and uncertain
Wind & solar output is also stochastic, variable and
uncertain
Supplies can also be stochastic
Need to know size, probability and duration of any
shortfalls in both capacity and ramping capability
System needs flexible capacity to deal with the increased
uncertainty and variability
© Copyright 2013 ECCO International, Inc. 3
The Problem - Continued
The penetration of renewables will continue to increase as more states adopt Renewable
Portfolio Standards (RPS) and continue to enforce more stringent targets
4 © Copyright 2013 ECCO International, Inc.
Potential flexibility challenges:
Anatomy of a ‘Duck’
5 © Copyright 2013 ECCO International, Inc.
Key Tools Available to the
Power Market
Change the Power Market design rules to
accommodate Wind and Solar
Implement demand response (Compensate
DRR resources the LMP price; Order 745)
Improve transmission planning and expansion
Invest in flexible generation (gas fired power
plants)
Develop storage facilities
Curtailment of Wind and Solar generation
© Copyright 2013 ECCO International, Inc. 6
Power Market Design Rule
Changes
Develop Ancillary Services products for better balancing,
better price signals, better incentives (Performance based
Frequency Regulation service, Ramping products, Load
Following, etc.) (Order 755)
Allow very large negative bids to clear the market
Develop better forecasting tools for load, wind, solar PV,
ramping requirements, etc. (Order 764)
Develop Intra-Hour Scheduling financially binding Markets
(every 15 minutes) (Order 764)
Develop centralized Capacity Markets that reward flexible
generation to ensure security of supply (i.e., we cannot rely
on scarcity pricing)
7 © Copyright 2013 ECCO International, Inc.
ECCO’s Software Capability to
Address Flexibility Issues
Developed ProMaxLT™ to incorporate flexibility requirements
Full MILP/LP optimizer of energy, ancillary services and
transmission; exactly mimics how ISOs clear the market
MIP solution and full network model utilizes multi-cored parallel
architecture and is orders of magnitude faster than competitive
products (3 min for 365 day optimization with full network model with
6000 buses)
Configured to execute DA, HA and RT for simulations
Implemented a modified Monte Carlo simulation engine by deploying
min by min load, wind and solar data
Implemented Expected Flexibility Deficiency (EFD) function in MIP
© Copyright 2013 ECCO International, Inc. 8
Software Capability
Requirements
Determine the optimal “mix” of resources to meet flexible response over various time horizons
Ensure reliable system operation Capacity Requirements – according to traditional metrics for capacity
planning
Flexibility Requirements – accounting for the limitations of the fleet in time sequential operations
Solution should result in: The least-cost array of portfolio and/or operational changes that satisfy all
the above objectives
The relative value of resource types over multiple time scales, e.g. energy storage can provide fast ramping response over a short-time period, while CCGTs provide load-following capacity and ramping capabilities
© Copyright 2013 ECCO International, Inc. 9
Expected Flexibility
Deficiency Definition
Incorporating Flexibility Requirements
Introduction of an Expected Flexibility Deficiency (EFD) function
To determine the anticipated amount of un-served energy caused by a lack of
flexibility in the generating fleet
The EFD is a function of the ramp and reserve policies in any given region
The EFD is computed before executing the MIP-Based Unit
Commitment
It is derived from historical system load/renewable data, as well as the
forecasts associated with a given unit commitment window
Ramp and reserve policies must be defined, in order to determine
the EFD
© Copyright 2013 ECCO International, Inc. 10
Expected Flexibility
Deficiency Definition
Sample EFD calculation
The EFD surface is built as a function of x and y. Note that the x and y
variables are optimized within the MIP-based Unit Commitment problem
© Copyright 2013 ECCO International, Inc. 11
Flexible Deficiencies
Computing Flexible Deficiencies using Historical Net Load
Data
© Copyright 2013 ECCO International, Inc. 12
Day-Ahead Market Formulation:
Standard Constraint Equations
Equations are used to enforce numerous equality and
inequality constraints, such as: Energy Balance (generation = load)
Unit output limits
Spinning Reserve Requirements
Regulation Reserve Requirements
Ramp rate limits (units, hydro, imports)
Unit temporal constraints (min up, min down, min run, …)
Hydro, Imports, and Pumped Hydro Energy Limits
© Copyright 2013 ECCO International, Inc. 13
Network Constraint Modelling
Optionally, the network constraints may be included in the
simulation
Monte-Carlo dispatch model iterates with full power flow
model (AC or DC) to enforce network constraints, including
contingency constraints
Zonal model may also be used to enforce flow constraints
© Copyright 2013 ECCO International, Inc. 14
Flexibility Mitigation Strategies
Modelling
Relative cost penalties impose flexibility mitigation strategy “loading order”
Costs will depend on specific system and applicable policies
Assuming that all renewables must be delivered is equivalent to placing an infinite penalty on curtailment and over-generation
© Copyright 2013 ECCO International, Inc. 15
Solution Method
Separate power flows for each time interval
Iterate with optimization engine that has a single power
balance constraint and the active inequality constraints for
each time interval
Power Flow Power Flow Optimization
Engine Power Flow Power Flow Power Flow Power Flows
Schedules
PTDFs
Loss marginal rates
© Copyright 2013 ECCO International, Inc. 16
MIP-Based Flexible UC Results
Flexibility Constraint Results
Flexibility violations that may occur, because the penalty
cost of these violations is less than the commitment of
additional resources
Optimal levels of reserves and ramp-rate capability based
on ramp/reserve policy
Economic “pre-curtailment” of renewables that avoid
flexibility violations and/or commitment of excessive fast-
ramping generation
© Copyright 2013 ECCO International, Inc. 17
Three Market Simulations
Day ahead, hour ahead and real-time markets are
simulated sequentially
Load forecast inaccuracy of the day ahead market vs hour
ahead is also simulated via Monte-Carlo draws
In hour ahead simulation only short start units may be
committed
In real-time simulation, only units that were on-line in the
HA market may be re-dispatched
© Copyright 2013 ECCO International, Inc. 18
RES Curtailment
The load forecast is plotted as the heavy black line, and
the curtailment of renewables is shown above that in green
© Copyright 2013 ECCO International, Inc. 19
Curtailment of RES Output Could
Play a Significant Role
Scheduled curtailment of renewables can help position conventional resources to meet ramping requirements
How does the cost of curtailment compare to the cost of procuring new flexible resources?
20 © Copyright 2013 ECCO International, Inc.
Proposed Metrics and
Results
Resource Adequacy (RA) metrics
LOLP, LOLE, EENS
Flexibility deficiency metrics
Separated from RA metrics by
isolating the impact of generator
ramp constraints
Expected Ramp Not Served
(ERNS)
Flexibility Shortage Induced
Curtailment
Production cost metrics
Proxy system cost
Curtailment cost
EENS cost
21
Example of potential flexibility issues caused by
hourly net load ramps
© Copyright 2013 ECCO International, Inc.
Demand Response: Energy
Demand Cloud
Energy Demand Cloud
Individual Wireless Controllers
Home/Facility Management
Systems
Smart Buildings, Commercial & Industrial
DR client is ~10kb—virtually any embedded device can run it
Special Programs
Reliability Signaled
Price Sensitive
Renewable Choice
Distributed Generation
Energy Storage
Electric Vehicles
Electric Vehicle Chargers
Smart Appliances
Distributed Energy & Storage
Demand Monitoring & Feedback over Internet Broadband/Cellular
Affinity Programs
TODAY FUTURE
© Copyright 2013 ECCO International, Inc. 22
Demand Response Software in
Devices
Today - Retrofit Future - Embed External Load Controller OEM Products to Seed Market
Internal Load Controller
WiFi Router
INTERNET
80% of US households have broadband (as of 2011*)
© Copyright 2013 ECCO International, Inc. 23
Transmission Based
Reliability Assessment
24 © Copyright 2013 ECCO International, Inc.
Generation
Model Load Model A/S Model
LoLP
Process
• Thermal, and
• Other
Conventional
Resources
Full
Network
Model
• Load,
• Import Limits,
• Solar Profile,
• Wind Profile
• Spin,
• Non Spin, and
• Reg Up/Down
• Full DC Model
• Constraints, and
• Contingencies
• Effective Load Carrying Capability (ELCC) of wind generation and solar generation at different
locations (reported based on LOLEV),
• Loss of Load Events (LOLEV)
• Loss of Load Hours (LOLH)
• Expected Un-served Energy (EUE)
• Expected Unserved Energy as a percentage of Net Energy for Load (normalized EUE)
• Loss of Load Probability (LOLP)
• Loss of Load Expectation (LOLE)
Load Shed Modeling
At all buses with load add a set of state variables to formulation
to allow load shed
Piecewise linear cost function, higher than all generation costs
but lower than the penalty costs on transmission infeasibility
When constraint is infeasible and cannot be satisfied by moving
generation then load shedding on a bus basis is automatically
invoked
Base case AND contingency constraints are respected
(contingency constraints are not pre-determined; they are
calculated on the fly)
© Copyright 2013 ECCO International, Inc. 25
Performance
High performance parallel hardware and software architecture
Linux or Windows on latest multi-cored high performance CPUs Intel Core i7 2700K processor with 16GB memory
More recent hardware Intel core i7-4770k is even faster
Break-through performance suitable for high iteration reliability studies with Monte-Carlo simulations
180-second calculation time for 365 day optimization (full DC model) Based upon a 6,000-bus network model,
180 X 400/3600 = 20 hours elapsed time for 400 iterations
Studies may be performed in parallel for different load levels
Up to 5 studies per machine
Total elapsed time for study on 5 machines is about 1 hour
Capable to do BOTH Monte Carlo AND Full Unreduced Network 26 © Copyright 2013 ECCO International, Inc.
Conclusions
Due to rapid RES penetration, many loss of load events will be
precipitated from lack of ramping flexibility rather than capacity
shortage or transmission constraints
Power systems will become ramping constrained in a substantial
way as we move forward
Special modeling of stochastic events based on renewable
schedules and load forecast error is required
A robust MIP-based UC approach is proposed based on the
Expected Flexibility Deficiency Function
The proposed methodology determines the optimal levels of
reserves and ramp-rate capability based on ramp/reserve policy
The proposed methodology also is used for optimal procurement
decisions
Demand Response will play a key role in the future
Transmission needs to be fully modeled in the reliability studies
from now on 27 © Copyright 2013 ECCO International, Inc.