Wind Onshore cost development - diw.de · > Some turbines are extra designed for sites with lower...

20
Wind Onshore cost development Philip Vogel; RWE Innogy GmbH

Transcript of Wind Onshore cost development - diw.de · > Some turbines are extra designed for sites with lower...

Page 1: Wind Onshore cost development - diw.de · > Some turbines are extra designed for sites with lower wind speeds > They offer higher efficiency during periods of lower wind speeds >

Wind Onshore cost development

Philip Vogel; RWE Innogy GmbH

Page 2: Wind Onshore cost development - diw.de · > Some turbines are extra designed for sites with lower wind speeds > They offer higher efficiency during periods of lower wind speeds >

PAGE 2 RWE Innogy Strategy | 12/03/2013

Expected LCOE developments of wind onshore

> IEA Meta-study (based on 18 separate studies) foresees significant reduction of Wind Onshore LCOE in the longer run (15-40% until 2030) from 2011 level

> Potentials in cost reduction occur from

– Economies of scale in manufacturing from standardisation and automatisation

– Optimisation of turbine designs and control

– Application of light weighted materials (e.g. carbon fibre)

– Cost reduction due to increased competition in turbine and O&M markets

– Improved power electronics and conversion

Relative reduction of Capex* and o&m-cost, increased reliability and load factors

Absolute level of LCOE depends also on average wind speed.

Source: IEA The past and future cost of wind (2012)

Source: Wiser et al. (2012)

* Certain turbines itself will become cheaper; but in terms of LCOE it might be necessary to increase Capex in wind projects

Page 3: Wind Onshore cost development - diw.de · > Some turbines are extra designed for sites with lower wind speeds > They offer higher efficiency during periods of lower wind speeds >

PAGE 3 RWE Innogy Strategy | 12/03/2013

Europe onshore wind turbine pricing Prices continue to vary significantly within the same year by vendor, market, and turbine. This is because turbine prices are usually contingent on several factors:

Turbine model is a key determinant

Two megawatt and larger machines as well as new roll-outs and turbines designed for lower-wind-speed sites and higher towers command higher prices. With European orders, it remains common for turbine prices to vary by machine size, illustrating a nonlinear price premium for higher-output machines.

Country variations are key to supply agreements In supplying over 25 countries, all with varying market environments, turbine prices offered by turbine manufacturers vary significantly in Europe. Key levers for this variation include revenue levels, technology delivered, level of competition and transportation costs.

Limited demand results in pressure on prices With 18 turbine manufacturers delivering to Europe, all of which have production capacity in the region (except Hyundai), lower and more concentrated demand has resulted in vendors reducing prices to capture orders and increase utilization rates of production facilities to avoid or delay downsizing.

Source: IHS cera –Global wind supply chain strategies 2012.

Page 4: Wind Onshore cost development - diw.de · > Some turbines are extra designed for sites with lower wind speeds > They offer higher efficiency during periods of lower wind speeds >

PAGE 4 RWE Innogy Strategy | 12/03/2013

Technology suppliers aim at performance increase plus cost reduction

Source: Nordex capital market day presentation 2011

Process cost optimisation

Turbine performance optimisation

Cost optimisation Capacity ↓ Rotor ∅ ↑

Hub height ↑

Swept area per MW [m2/MW]

Change in Levelised Cost of Energy [€/MWh]

Page 5: Wind Onshore cost development - diw.de · > Some turbines are extra designed for sites with lower wind speeds > They offer higher efficiency during periods of lower wind speeds >

PAGE 5 RWE Innogy Strategy | 12/03/2013

Increasing rotor diameter and hub heights lowers wind generation cost

> Captured Energy (E) of the turbine is increasing with the rotor diameter (D) exponentially and with the hub height due to increased average wind speed

> However, also costs of the rotor and turbine are exponentially increased from increased diameter size and hub height (see graph below; source: Narasimalu/Funk)

> Generally diameters/hub heights have increased significantly in recent years, hence revenue increase seems to be higher than cost increase

> Furthermore, suppliers offer wider range of turbines with different combinations of rated capacity/ hub height and rotor diameter, which gives more flexibility in lowering LCOE of generation and optimisation of sites

E = Captured Energy v =velocity of wind

D = rotor diameter cp = efficiency of turbine (as function of v)

Π = pi ρ = air density

Rotor Diameter (m)

Page 6: Wind Onshore cost development - diw.de · > Some turbines are extra designed for sites with lower wind speeds > They offer higher efficiency during periods of lower wind speeds >

PAGE 6 RWE Innogy Strategy | 12/03/2013

Optimal siting – Optimizing Capex cost vs. revenues by technology selection

> Generally it is tried to optimize the ratio between capex cost and discounted revenues

> Optimal turbine for a site is given where marginal increase of capex equals marginal increase of revenues

> This maximizes economic value per MWh or LCOE for a certain site

> Taking different local characteristics into account different turbines are selected for different wind sites

> Major issues are:

– Wind speed average and distribution

– Maximum load on turbine

– Subsidy scheme for revenues

– Regulation, e.g. constraints on hub heights, noise emission (see next slide)

Hub height/ diameter/ rated capacity

Marginal increase in Capex cost

Marginal increase in Revenues (depending on site

specific wind distribution)

Economic Value per MWh

Page 7: Wind Onshore cost development - diw.de · > Some turbines are extra designed for sites with lower wind speeds > They offer higher efficiency during periods of lower wind speeds >

PAGE 7 RWE Innogy Strategy | 12/03/2013

Differences in wind sites lead to a range of turbines offered to the market

> Different turbines are optimal for different sites. This explains wide range of turbines offered to the market and used by Operators

> Very large turbines are too expensive and capex cost out-level increase in revenues (so far). Hence, they are often not used (yet)

> Very small turbines are not state of the art and there exist functioning alternatives with better revenue/ capex ratio

> However, in older wind farms older technologies are often still in place – often with higher fixed subsidies, which explain continuation of operation

Marginal increase in Revenues (depending

on site specific wind distribution)

Turbine range offered in market

Turbines not yet economic

Turbines not economic anymore

Hub height/ diameter/ rated capacity

€ Marginal increase in Capex cost

Page 8: Wind Onshore cost development - diw.de · > Some turbines are extra designed for sites with lower wind speeds > They offer higher efficiency during periods of lower wind speeds >

PAGE 8 RWE Innogy Strategy | 12/03/2013

Optimal siting – Optimizing capex vs. revenues by technology selection with constraints and subsequent tender

> Development is trying to optimize ratio of capex and NPV of future returns in order to maximize economic value of a project

> Furthermore, constraining site parameters need to be taken into account, which limit the potential for economic optimisation

– Grid connection points

– Regulation of noise

– Regulation of hubheight

– Environmental regulation etc.

> Constraints usually increase the LCOE of a project and limit potential for optimisation

Screening of target suppliers for suitable turbines

Hub height/ diameter/ rated capacity

Marginal increase in Capex cost

Marginal increase in Revenues (depending on site

specific wind distribution)

Economic Value per MWh

Identification of optimal possible turbine design for site

Optimal wind turbine design

€ Constraining site conditions: grid;

noise; hub height

Page 9: Wind Onshore cost development - diw.de · > Some turbines are extra designed for sites with lower wind speeds > They offer higher efficiency during periods of lower wind speeds >

PAGE 9 RWE Innogy Strategy | 12/03/2013

Offered range of turbines is changing with technical progress in the industry

> During the last years, offered turbines have changed significantly and new prototypes were getting onto the market frequently (until now)

Marginal increase in Revenues (depending

on site specific wind distribution)

Hub height/ diameter/ rated capacity

€ Marginal increase in Capex cost – old

Old Turbine range offered in market

New Turbine range offered in market

Technical Innovation

Page 10: Wind Onshore cost development - diw.de · > Some turbines are extra designed for sites with lower wind speeds > They offer higher efficiency during periods of lower wind speeds >

PAGE 10 RWE Innogy Strategy | 12/03/2013

0255075

100125150175200

20% 25% 30% 35% 40% 45% 50%

Hubh

eigh

t

Loadfactor

112m-3.0MW-80m

114m-3.2MW-140m

82m-2,3MW-80m

82m-2,3MW-140m

82m-3,0MW-80m

117m-2,4MW-140m

bubble size = swept area

3.0 2.3 3.0 3.2 2.4

Example for turbine design – performance increase

Assumptions on wind value dimension Weibull-A-Parameter 7 m/sec

Weibull-k-Parameter 3 -

average wind speed 80 m 6.3 m/sec

air density 1.225 kg/m3

average wind speed 140 m 7.2 m/sec

Efficiency of wind turbines Cp manufacturer data depending on wind speed %

> Using a simplified example for available turbines at different hub heights/ rotor diameter and rated capacity on the same site shows significant differences of load factors (or full load hours)

> Local inefficiencies are not considered here, which might reduce the output of a turbine significantly, e.g. turbulence and wake effects

> This alone is no indication for improved economics in low wind areas

Rotor - capacity - hub height

2.3

Page 11: Wind Onshore cost development - diw.de · > Some turbines are extra designed for sites with lower wind speeds > They offer higher efficiency during periods of lower wind speeds >

PAGE 11 RWE Innogy Strategy | 12/03/2013

€0

€500

€1.000

€1.500

€2.000

> Optimal turbine for example is with high hub height, large rotor diameter and smaller rated capacity (pink data)

> Lowest LCOE are associated with higher Capex cost, which are more than outlevelled by increase in returns

> This does not necessarily hold true for all wind sites

> Results indicate that newer turbines at low wind sites (~6,5m/sec) could become even cheaper than conventional generation

Capex increase but LCOE decrease

Further economic parameters Opex cost 38.7 €/KW

Availability 97 %

Inefficiencies via turbulence, wake effect etc. 10 %

Lifetime 20 a

Assumed Interest rate 7 %

LCOE €/MWh

Invest cost €/kW (assumptions)

€0

€20

€40

€60

€80

€100

€120

Optimal turbine with lowest

LCOE*

* This might look different for other wind sites/ distributions; it also is driven by assumptions on CAPEX/ which might differ significantly.

Page 12: Wind Onshore cost development - diw.de · > Some turbines are extra designed for sites with lower wind speeds > They offer higher efficiency during periods of lower wind speeds >

PAGE 12 RWE Innogy Strategy | 12/03/2013

Backup: Smaller turbine – less energy but larger load factor

0

25

50

75

100

125

18% 23% 28%

Hubh

eigh

t

Loadfactor

82m-2,3MW-80m

82m-3,0MW-80m

bubble size = swept area

??? 2.3 3.0

> Building a turbine with lower rated capacity but same design, results in decrease of produced energy as absolute measure, because in high wind situations less is produced

> However, the load factor/ fullloadhours are a relative measure and energy produced is only part of the enumerator. At the same time rated capacity is the denominator

> If the reduction of the denominator is larger than the decrease of the enumerator, the fulload hours/load factor as relative measure is increasing – which might not seem intuitive on first thought

> Turbines are not optimal if they maximize MWh, they are optimal if they minimize the specific cost of generating one MWh at a site ( optimal siting)

> Smaller generators are cheaper and if load factor is increasing by reducing rated capacity, LCOE are also decreasing

Rotor - capacity - hub height

Energy [MWh]

Fullload hours

[MWh/MW]

Load factor [Flh/8760]

Specific Capex [€/kW]

LCOE [€/MWh]

82m-3,0MW-80m 5826 1942 22,17% 1.250 108 82m-2,3MW-80m 5478 2382 27,19% 1.100 80

∆ 𝑀𝑀𝑀∆𝑀𝑀

=(5826−5478)

5826(3−2,3)

3

= 6%23%

Increase in energy

Increase in capacity

Larger turbine leads to relative decrease of

Output – despite increasing output

Page 13: Wind Onshore cost development - diw.de · > Some turbines are extra designed for sites with lower wind speeds > They offer higher efficiency during periods of lower wind speeds >

PAGE 13 RWE Innogy Strategy | 12/03/2013

0

500

1000

1500

2000

2500

3000

158

511

6917

5323

3729

2135

0540

8946

7352

5758

4164

2570

0975

9381

77

82m-2,3W-80m

117m-2,4MW-140m

Backup: Turbine design affects generation profile

> Improving hub height increases wind speed and rotor diameter increases captured wind energy - in total increasing energy generation

> Meanwhile there are always periods with no or almost no wind, hence improved design is not increasing the capacity credit/ secured capacity of wind power

> In this example production is smoother in windy situations and incremental changes in wind generation are lowered sometimes (at least in this example)

> By increasing hub height and rotor and capacity, the production duration curves are not fully comparable, because average wind is increasing etc.

0

50

100

150

200

25,00% 30,00% 35,00% 40,00% 45,00%

Hubh

eigh

t

Loadfactor

82m-2,3MW-80m

117m-2,4MW-140m

bubble size = swept area bubble size = swept area

2.4 2.3

Rotor - capacity - hub height

More generation

No firm capacity independent of

design

h

Wind generation duration curve

Partially smoother generation

Page 14: Wind Onshore cost development - diw.de · > Some turbines are extra designed for sites with lower wind speeds > They offer higher efficiency during periods of lower wind speeds >

PAGE 14 RWE Innogy Strategy | 12/03/2013

Optimal siting – Different technology designs for different wind speed sites

Prob

abili

ty

Wind in m/s

Potential wind distributions

> Some turbines are extra designed for sites with lower wind speeds

> They offer higher efficiency during periods of lower wind speeds

> Despite, lower maximum rated capacity (kW) the green curve might yield higher energy returns (kWh) than the red curve if the green wind probability density is considered

> There is no turbine that fits to all sites, local measurement on wind distribution is necessary

> Optimisation is done site specific during development of projects

> No manufacturer offers turbines suitable for all wind sites, hence several suppliers are needed for developing a wider range of wind projects

Page 15: Wind Onshore cost development - diw.de · > Some turbines are extra designed for sites with lower wind speeds > They offer higher efficiency during periods of lower wind speeds >

PAGE 15 RWE Innogy Strategy | 12/03/2013

Annex: Offshore

Page 16: Wind Onshore cost development - diw.de · > Some turbines are extra designed for sites with lower wind speeds > They offer higher efficiency during periods of lower wind speeds >

PAGE 16 RWE Innogy Strategy | 12/03/2013

New projects will be in deeper water and further from shore

Distance to shore and water depths pose additional challenges

2015 + X

8

6

5

4

Princess Amalia (Q7)

Burbo Bank

Samso

Belwind

Robin Rigg

Lynn & Inner Dowsing

Lillgrund

Barrow

Beatrice Field

Kentish Flats Scroby Sands

Arklow Bank

North Hoyle

Nysted

Innogy Nordsee 1 London Array

Nordsee Ost Sheringham Shoal

Lincs

Rød- sand II

Côte d'Albâtre

Baltic 1

Bard Off- shore 1

Greater Gabbard

Thanet

Gunfleet Sands

Horns Rev 2

Rhyl Flats

Alpha Ventus

Thornton Bank

Gwynt y Môr

Global Tech 1

Amrum Bank West

Dan-Tysk

Sandbank 24

Hochsee- windpark De Dreiht

Gode Wind

Butendiek

0

10

20

30

40

50

10 20 30 40 50 60 70 80 90 100

Distance to shore [km]

Avg.

wat

er d

epth

[m]

7

Hochsee Windpark Nordsee

1

9

Dogger Bank [125 km]

Wind farms in operation Planned projects Projects with RWE participation

1

2

2 3

3

Triton Knoll 4

5

6

7

8 Horns Rev

Nordergründe 9

Commer- cial

Albatros

Egmond aan Zee

“Pioneer” phase

Page 17: Wind Onshore cost development - diw.de · > Some turbines are extra designed for sites with lower wind speeds > They offer higher efficiency during periods of lower wind speeds >

PAGE 17 RWE Innogy Strategy | 12/03/2013

RWE Innogy’s stepwise approach to reduce execution risk

Bigger, deeper, further offshore – an inevitable path forward

Pipeline

Gravity

Monopile

Operational

Under Construction Dogger Bank

2017+ 250 × 6.0MW+

18 – 50m depth Nordsee Ost 2012

48 × 6.15MW 22 – 26m depth

Thornton Bank 2009

6 × 5.0MW 12 – 25m

depth

North Hoyle 2003

30 × 2.0MW 7 – 11m

depth Jacket

Rhyl Flats 2009

25 × 3.6MW 10 – 15m

depth

Dogger Bank – 125km

North Hoyle – 7km

Rhyl Flats – 8km

Gwynt Y Môr – 13km

Greater Gabbard – 25km

Thornton Bank – 30km

Nordsee Ost – 45km1

Gwynt y Môr 2012

160 × 3.6MW 12 – 28m

depth

Greater Gabbard

2010 140 × 3.6MW

25 – 30m depth

Page 18: Wind Onshore cost development - diw.de · > Some turbines are extra designed for sites with lower wind speeds > They offer higher efficiency during periods of lower wind speeds >

PAGE 18 RWE Innogy Strategy | 12/03/2013

Cost reductions to be expected for: foundations

1 Comparing weights and thus costs of 48 jacket foundations at Nordsee Ost (built according to German regulations) and at Thornton Bank (built according to international regulations) shows the effect. Given similar average water depths (Nordsee Ost: 23m, Thornton Bank: 18m) and comparable soil conditions the average weight of a Thornton Bank jacket is only 500t whereas the average weight of a Nordsee Ost jacket is 600t and thus 20% above the weight of the jacket built according to international regulations.

Serial production of foundations leads to reduced prices and faster production

Optimised designs for various foundations types (monopiles, jackets, gravity foundations etc.) redu-ce prices (e.g. due to lesser steel requirements)

Alignment of German industry regulations with international regulations would lead to significant reductions of foundation costs (e.g. due to less strict requirements regarding steel thicknesses1)

Page 19: Wind Onshore cost development - diw.de · > Some turbines are extra designed for sites with lower wind speeds > They offer higher efficiency during periods of lower wind speeds >

PAGE 19 RWE Innogy Strategy | 12/03/2013

Cost reductions to be expected for: O&M

Increased in-house activities regarding O&M for offshore wind farms will partly or fully replace costly O&M contacts with turbine manufacturers

Geographical clusters for offshore wind farms (e.g. off the coast of North Wales: North Hoyle, Rhyl Flats, Gwynt y Môr) create synergies for O&M activities

Increased reliability of components (turbines, foundations, substations etc.) reduces numbers of arduous and expensive offshore service activities

Increased rated power of turbines means a reduced number of turbines to be maintained without reducing the capacity of the wind farm

Page 20: Wind Onshore cost development - diw.de · > Some turbines are extra designed for sites with lower wind speeds > They offer higher efficiency during periods of lower wind speeds >

PAGE 20 RWE Innogy Strategy | 12/03/2013

Average LCOE [€/MWh]

Cost reductions with 2020 target level of €120/MWh in mind

UK industry task force has shown development paths to achieve a LCOE1 level of €120/MWh by 2020 – reduction in the range of 30% required

1 LCOE: Levelised cost of energy including development and capital expenditure | Data source: Desertec Initiative 2011; RWE 2012

020406080

100120140160180200

2010 2020 2030

Offshore development path

Large PV Southern Europe Large hydro Onshore wind

Approx. range CCGT (depends on gas & CO2 price)

Main cost reduction drivers > Cost reduction turbines > Design & cost improvements

foundations > Advanced O&M solutions

and increased reliability