waste water project

download waste water project

of 28

Transcript of waste water project

  • 8/10/2019 waste water project

    1/28

    Notre Dame University

    Faculty of EngineeringDepartment of Civil and Environmental

    Engineering

    Water And Waste Water Networks

    CEN 463

    Spring 2014

    Final Project

    Fanar Water Distribution Network

    Submitted to: Dr, Fadi Matar

    Submitted by: Karl El Hachem

    Joseph DagherSalim Abou Samra

  • 8/10/2019 waste water project

    2/28

    Abstract

    The hereby study is a tentative to improve/modify the water network of a

    selected area and have for purpose the study of a whole system as part of water

    networks engineering.

    The purpose of such study is to become familiar with the different possible

    systems and networks as well as their application to real life situations. Our aim

    in this project is to study/design a new network and its facility for Fanar town(El Meten) as an area of study in order to fulfill the requirements of this project.

    EPAnet software will be used later on in order to design the network system for

    this town.

    For the time being we are requested to investigate the current area to get all the

    required data required to estimate the demand and inquire about the actual

    facility, its use and the possible improvements we can bring to such existing

    system.

  • 8/10/2019 waste water project

    3/28

    Table of Contents

    Abstract .................................................................................................................................. 2

    Introduction ......................................................................................................................... 4

    Fanar descriptive map ...................................................................................................... 5

    Data Collection ..................................................................................................................... 6

    Demand Analysis ................................................................................................................ 8

    Residential water demand: ...................................................................................................... 8

    Non-residential water demand............................................................................................... 8

    Academicals water demand ..................................................................................................... 9

    Fire demand analysis: ..............................................................................................................10

    Model Design ..................................................................................................................... 11

    The pipe characteristics: .........................................................................................................11

    Junction characteristics: .........................................................................................................11

    Chosen trial network ................................................................................................................12

    Consideration for the design .................................................................................................14

    Overview of the network carachteristics ..........................................................................15Units and defaults used ...........................................................................................................16

    Conclusion .......................................................................................................................... 17

    Annexes ............................................................................................................................... 19

    Appendix A1 design guidelines ............................................................................................19

    APENDIX A2 link-node table ..................................................................................................22

    Appendix A2 node details .......................................................................................................24

    Appendix 4 link details ............................................................................................................26

    Appendix 5 clear network on map ......................................................................................28

  • 8/10/2019 waste water project

    4/28

    Introduction

    In a first time we tried investigating the Zekrit area specifically for its industry

    presence as well as the known scarcity of water resources and wastewater

    network. Unfortunately due to the lack of serviceability of the municipality and

    the lack of cooperation from their part forced us to move our focus on a different

    area. Fanar was our best bet since the mayor of the area is very reachable and

    available to all our questions.

    The town already has a fairly working infrastructure system for the area but

    definitely needs improvement and upgrades to serve efficiently this area.

    Especially since it is a major zone of educational facilities housing several

    schools and colleges.

    Fanar is located over 2.3 Km2 d has an altitude of 250m above the sea level.

    Contacting officials, visual inspection and research has collected the following

    data.

  • 8/10/2019 waste water project

    5/28

    Fanar descriptive map

  • 8/10/2019 waste water project

    6/28

    Data Collection

    First, we would like to thank the mayor Mr. Ghoussoub for sharing with us useful

    information in order to achieve this report. The following are some technical,

    environmental, geographical and demographic data about the area of study

    arranged in no particular order.

    -Location:

    Fanar is located 8km from Beirut District,

    -Demographic:

    Fanar has an estimated population of 39000 capita distributed in around 12000

    houses over an area of 2.3 km2. Fanar early expansion began in the late 80s and

    still expanding exponentially till today.

    -Academicals facilities:

    Fanar holds 7 schools with 5000 students, 4 Lebanese universities

    -Hospitals and other Facilities:

    Fanar hosts no hospitals for the moment, but we find important to mention that

    in 2020 a project for building a hospital will be very likely feasible due its

    continuous growth.

    -Projected growth:

    The estimated growth from previous years leads us to take a growth of 5% per

    year.

    -Economic:

    On an economic scale, as Fanar expanding, the price of land increased from 200$

    to reach 1200$ in 2014.

    -Environmental:

  • 8/10/2019 waste water project

    7/28

    Fanar is known for its green environment where we can notice the pine trees

    covering most of its green spot and when it comes to soil the major soil type

    across this city is sand and rocks.

    -Industrial/buisnesses

    Fanar holds a large number of companies and industries while it has a wide

    variety of industries around 17 industries are registered and more than 300

    companies are located in fanar.

    -Pluviometry:

    Average pluviometer registered in 2013 is 920mm per year.

    -Water facilities:

    Two containing tanks are located in fanar one on top of the area and the other in

    the middle near municipality.

    Water provenance is from Jal eldib (maslahat miyah Beirut) and from ain saadeh

    on emergency basis.

    There are two networks one for each reservoir and the reservoir themselves are

    connected to each others. Water is pumped from Jal el Dib to the lower reservoir

    and then pumped back to the higher one in case it is emptied. The other way

    around is possible when they bring water from Ain Saadeh they fill the higher

    one by gravity and then the second one if needed.

    The piping network is in continuous expansion and there is no accurate track of

    it and the as for the actual pipes map is either unavailable or inaccessible

    information. If we cannot access the actual map we may have to assume the path

    of the pipe for the scope of this project

  • 8/10/2019 waste water project

    8/28

    Demand Analysis

    Following the steps documented in the annex we can formulate the needs of the

    town.

    We seek to find:

    Average Day Water Demand: ADD = Daily average water demand

    Maximum Day Water Demand: MDD = 1.6 x ADD

    Peak Hour Water Demand: PHD = 2.5 x ADD

    Residential water demand:

    ADD: Average daily water demand = 225 L/capita/day + 10%

    We have 39000 capita assuming each one of them consumes 225 L and increased

    10% we get 39000*225*1.1= 9,652,500L

    Non-residential water demand

    Commercial ADD: 16,800 L/ha/day

    Light Industrial ADD: 22,500 L/ha/day

    Wet Industrial ADD: 33,600 L/ha/day

    We have 300 businesses assuming each of 200m2 leads to 60,000m2, which

    converts to 6ha

    ADD commercial equal 6*16,800 = 100,800L

  • 8/10/2019 waste water project

    9/28

    We have 17 industries assuming a mix between light and wet for a usage of

    30,000 L/ha/day and an average of 800m2 each ie 13600m2 = 1.36ha

    ADD Industrial equal 1.36*30,000= 48,000L

    Academicals water demand

    Schools and universities ADD: 16,800 L/ha/day

    We have 7 schools and 4 universities for an average area of 4000m2 each

    44000m2 ie 4.4ha

    ADD academicals = 4.4*16800= 73,920L

    Adding all ADD we have 9,652,500L+100,800L+48,000L+73,920L=9,875,220L

    Rounding up: ADD total = 10,000,000L

    MDD = 1.6 x ADD = 16,000,000L

    PHD = 2.5 x ADD (hr.) = 1,042,000L/hr.

  • 8/10/2019 waste water project

    10/28

    Fire demand analysis:

    The following fire flow targets are suggested in the absence of building

    construction details based on the Fire Underwriters Survey Water Supply for

    Fire Protection:

    Residential Single-family: 100 L/s

    Residential Multi-family: 200 L/s

    Street side Commercial: 250 L/s

    Elementary Schools: 167 L/s Junior and Senior High Schools: 267 L/s

    Institutional: 250 L/s

    Industrial: 383 L/s

  • 8/10/2019 waste water project

    11/28

    Model Design

    We fitted all pipes in EPAnet to be located under the road with as

    much manhole as efficient to secure ease of repair and access without

    having to damage the road pavement therefore minimizing car

    accident traffic and other problems since fanar is a high traffic zone

    with many schools.

    The pipe characteristics:

    Using HDPE (High Density Polyethylene) pipes:

    Diameter =100mm

    Roughness: C=150

    Check appendix A2 with a table with all details regarding pipes

    Junction characteristics:

    The junction have right data imputed by estimating the roughly how

    many building will be supplied and their type

    The total supply have to be around the calculated projected AAD of

    10,000,00

    Check appendix A3 with a table with all details regarding junctions

  • 8/10/2019 waste water project

    12/28

    Chosen trial network

    The preceding image is a screenshot of EPAnet showing the loaded scaled map

    from which we could determine the length of each using the built in function of

    EPAnet: Auto-length

  • 8/10/2019 waste water project

    13/28

    Figure: Network with clear legend of pipe and junction number

    The boundaries where created on google maps creator then imported to googleearth from which we could get the exact elevation of each of our nodes

  • 8/10/2019 waste water project

    14/28

    Consideration for the design

    Fanar region has already a reservoir that is located at half altitude so we need apump to supply the high parts of the region as a first trial we used the followingpump curve:

  • 8/10/2019 waste water project

    15/28

    We started the system and found that it all runs ok with no issue at all

    Overview of the network carachteristics

    Nodes with pressure below 100:

  • 8/10/2019 waste water project

    16/28

    Links with high velocity (we can consider larger diameter pipes if needed toreduce velocity):

    Units and defaults used

  • 8/10/2019 waste water project

    17/28

    Conclusion

    As a first part of a greater project this paper is preliminary study for the fanararea and has been done the most accurately as possible with all assumptionsclearly stated and well documented.The purpose of this paper is to prepare for the following part that will be thenetwork and facilities for this town.For now we have developed all the water requirements of the town usingstandards and the data we could collect from the municipalities.Our main goal will be implement the actual facilities instead of building a new

    one from scratch.

  • 8/10/2019 waste water project

    18/28

    References

    http://winnipeg.ca/waterandwaste/dept/waterdemand.stm

    http://en.wikipedia.org/wiki/Fanar_(Matn)

    http://www.baldati.com/networks/community.php?networkid=978

    http://winnipeg.ca/waterandwaste/dept/waterdemand.stmhttp://winnipeg.ca/waterandwaste/dept/waterdemand.stmhttp://en.wikipedia.org/wiki/Fanar_(Matnhttp://en.wikipedia.org/wiki/Fanar_(Matnhttp://www.baldati.com/networks/community.php?networkid=978http://www.baldati.com/networks/community.php?networkid=978http://www.baldati.com/networks/community.php?networkid=978http://en.wikipedia.org/wiki/Fanar_(Matnhttp://winnipeg.ca/waterandwaste/dept/waterdemand.stm
  • 8/10/2019 waste water project

    19/28

    Annexes

    Appendix A1 design guidelines

  • 8/10/2019 waste water project

    20/28

  • 8/10/2019 waste water project

    21/28

  • 8/10/2019 waste water project

    22/28

    APENDIX A2 link-node table

    Link - Node Table:

    --------------------------------------------------------------------

    --

    Link Start End Length Diameter

    ID Node Node ft in

    --------------------------------------------------------------------

    --

    2 24 30 316.27 12

    3 25 30 255.97 12

    4 25 26 610.46 12

    5 26 27 595.17 12

    6 27 28 342.55 12

    7 28 29 613.90 12

    8 30 31 719.32 12

    9 31 32 161.19 12

    10 32 33 723.84 12

    11 33 34 581.06 12

    12 34 35 507.38 12

    13 35 36 840.76 12

    14 33 37 462.87 12

    16 40 39 258.60 12

    17 39 41 315.44 12

    19 9 18 282.94 12

    20 18 19 164.99 12

    21 19 20 306.26 12

    22 20 22 162.24 12

    23 22 23 267.52 12

    24 20 21 308.58 12

    25 21 17 695.21 12

    26 9 10 171.68 12

    27 10 11 329.98 12

    28 11 12 384.63 12

    29 12 13 315.14 12

    30 13 14 314.13 12

    31 6 7 343.76 12

    32 7 8 399.85 12

    33 8 15 323.46 12

    34 15 16 447.70 12

    35 31 48 141.07 12

    36 48 49 474.84 1237 48 53 317.99 12

  • 8/10/2019 waste water project

    23/28

    38 53 52 399.00 12

    39 52 51 424.98 12

    40 53 50 501.76 12

    41 23 47 225.31 1242 24 54 545.67 12

    43 6 24 424.19 12

    44 40 44 484.24 12

    45 39 43 429.11 12

    46 41 42 317.34 12

    47 38 45 488.37 12

    48 45 46 724.23 12

    49 9 6 150.25 12

    51 38 37 613.26 12

    52 38 40 329.98 121 1 6 #N/A #N/A Pump

    Energy Usage:

    ----------------------------------------------------------------------

    Usage Avg. Kw-hr Avg. Peak Cost

    Pump Factor Effic. /Mgal Kw Kw /day

    ----------------------------------------------------------------------

    1 100.00 75.00 819.52 85.70 85.70 0.00----------------------------------------------------------------------

    Demand Charge: 0.00

    Total Cost: 0.00

  • 8/10/2019 waste water project

    24/28

    Appendix A2 node details

    Node Results:

    ----------------------------------------------------------------------

    Node Demand Head Pressure Quality

    ID GPM ft psi

    --------------------------------------------------------------------

    --

    6 24.75 445.64 89.11 0.00

    7 24.75 445.63 80.43 0.00

    8 24.75 445.62 80.43 0.00

    9 40.30 445.43 89.01 0.00

    10 40.30 445.41 80.34 0.0011 40.30 445.39 76.00 0.00

    12 40.30 445.37 75.99 0.00

    13 40.30 445.36 80.32 0.00

    14 40.30 445.36 84.65 0.00

    15 40.30 445.61 76.09 0.00

    16 40.30 445.61 80.42 0.00

    17 40.30 445.27 80.28 0.00

    18 43.00 445.36 88.98 0.00

    19 43.00 445.33 88.97 0.00

    20 43.00 445.28 75.95 0.0021 43.00 445.28 75.95 0.00

    22 43.00 445.28 75.95 0.00

    23 43.00 445.27 75.95 0.00

    24 43.00 444.79 93.07 0.00

    25 43.00 444.20 105.81 0.00

    26 37.00 444.17 114.46 0.00

    27 37.00 444.15 140.45 0.00

    28 37.00 444.14 136.12 0.00

    29 37.00 444.14 157.78 0.00

    30 37.00 444.23 101.49 0.0031 37.00 443.46 114.16 0.00

    32 37.00 443.36 109.78 0.00

    33 15.60 442.98 122.62 0.00

    34 15.60 442.96 139.94 0.00

    35 51.00 442.95 144.27 0.00

    36 51.00 442.94 157.26 0.00

    37 38.50 442.85 122.56 0.00

    38 38.50 442.54 126.76 0.00

    39 38.50 442.43 144.04 0.00

    40 38.50 442.45 139.72 0.00

  • 8/10/2019 waste water project

    25/28

    41 38.50 442.43 148.37 0.00

    42 38.50 442.43 148.37 0.00

    43 38.50 442.43 139.71 0.00

    44 38.50 442.45 135.38 0.0045 25.60 442.53 126.76 0.00

    46 25.60 442.53 105.09 0.00

    47 27.50 445.27 123.61 0.00

    48 27.50 443.45 122.82 0.00

    49 27.50 443.45 135.82 0.00

    50 25.60 443.44 144.48 0.00

    51 25.60 443.43 153.14 0.00

    52 25.60 443.44 148.81 0.00

    53 25.60 443.44 140.15 0.00

    54 25.60 444.79 97.40 0.001 -1742.85 250.00 4.33 0.00 Tank

  • 8/10/2019 waste water project

    26/28

  • 8/10/2019 waste water project

    27/28

    47 51.20 0.15 0.01 Open

    48 25.60 0.07 0.00 Open

    49 -567.60 1.61 1.44 Open

    51 -320.70 0.91 0.50 Open52 231.00 0.66 0.27 Open

    1 1742.85 0.00 -195.64 Open Pump

  • 8/10/2019 waste water project

    28/28

    Appendix 5 clear network on map