W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the...

46
The Maidenhead Bridge over the River Thames at Maidenhead is a Grade II* listed structure. Overhead electrification on top of the structure will be installed. The design is being undertaken with advice from heritage specialists to help ensure that the impact on the structure is acceptable. Once installed, the gantries would be visible on the bridge from viewpoints along the river and nearby. As an example, electrification for the Heathrow Express involved the provision of overhead electrification over Wharncliffe Viaduct in Ealing. Example of similar overhead electrification installations. Maidenhead Bridge W1.R3.1 Crossing the Capital Connecting the UK Email: [email protected] www.crossrail.co.uk Helpdesk 0845 602 3813 24 hours a day, 7 days a week Maidenhead Bridge at present Wharncliffe Viaduct at present

Transcript of W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the...

Page 1: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

The Maidenhead Bridge over the RiverThames at Maidenhead is a Grade II* listedstructure. Overhead electrification on top ofthe structure will be installed. The design isbeing undertaken with advice from heritagespecialists to help ensure that the impact onthe structure is acceptable. Once installed, the gantries would be visible on the bridgefrom viewpoints along the river and nearby.

As an example, electrification for theHeathrow Express involved the provision of overhead electrification over WharncliffeViaduct in Ealing.

Example of similar overhead electrificationinstallations.

Maidenhead BridgeW1.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Maidenhead Bridge at present

Wharncliffe Viaduct at present

5393_W01.R3.1_Maidenhead 01/02/05 18:38 Page 1

Page 2: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

A stabling facility will be provided for 6Crossrail trains in the former goods yard westof Maidenhead station, immediately beyondthe junction of the Bourne End Branch.

Six tracks will be laid out as single sidings.Between alternate tracks, a platform will beprovided to allow access to the trains fordrivers and other staff.

The eastbound Relief line track will be realignednorthwards (and re-routed through platform 5 at Maidenhead station).

Two reversing sidings will be installed betweenthe existing westbound Relief line andrealigned eastbound line tracks.

Staff facilities and car parking will be needed.The road access from Silco Drive will beextended to the staff facilities building and car parking will be modified.

The likely environmental effects of theproposals will be:

■ Operational noise from the use of the sidings

■ Lighting of the stabling area. (This will bedesigned to control light pollution into thesky or toward adjacent buildings inaccordance with best practice)

Maidenhead Stabling & TurnbackMaidenhead

W2.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

THIS MAP IS BASED UPON ORDNANCE SURVEY MATERIAL WITH THE PERMISSION OF ORDNANCE SURVEY ON BEHALF OF THE CONTROLLER OF HER MAJESTY’S STATIONERY OFFICE © CROWN COPYRIGHT. UNAUTHORISED REPRODUCTION INFRINGES CROWN COPYRIGHT AND MAY LEAD TO PROSECUTION OR CIVIL PROCEEDINGS. (GLA - 100032379) (2005).

Maidenhead Stabling & Turnback

Stabling site

5393_W02.R3.1_Maidenhead 01/02/05 18:39 Page 1

Page 3: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Improvements to ensure that efficient station facilities areprovided include opportunities to improve the integration ofthe station with other types of transport and:

� Improve passenger access from Shoppenhanger’s Road to the station ticket hall

� Provide a new ticket hall

� Re-arrange forecourt

The existing platforms will be extended to cater for Crossrail10-car trains. A modified layout has been designed to providea new terminating platform for Marlow Bourne End services(platform 6).

There are 5 worksites for the works planned for the stationand the turnback facilities. These are at:

� The northern station car park

� The northern platform

� Silco Drive

� Shoppenhanger’s Road

� The southern station car park

Some parking spaces will be temporarily lost duringconstruction. Exact details will be subject to detailed design and discussions with Windsor and MaidenheadBorough Council.

Lorries will route from the M4 and A4 to all five worksites via the A303 Braywick Road/Grenfell Place.

Mitigation measures will be employed to limit constructionnoise impacts. These will include 3.6m high hoardings and the provision of noise insulation if appropriate.

Station ImprovementsMaidenhead

W3.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

THIS MAP IS BASED UPON ORDNANCE SURVEY MATERIAL WITH THE PERMISSION OF ORDNANCE SURVEY ON BEHALF OF THE CONTROLLER OF HER MAJESTY’S STATIONERY OFFICE © CROWN COPYRIGHT. UNAUTHORISED REPRODUCTION INFRINGES CROWN COPYRIGHT AND MAY LEAD TO PROSECUTION OR CIVIL PROCEEDINGS. (GLA - 100032379) (2005).

Maidenhead Station

5393_W03.R3.1_Maidenhead 01/02/05 18:41 Page 1

Page 4: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Train services to and from Maidenhead will be improved by providing some journey time savings and a greater variety of journey opportunities.

Crossrail Maidenhead station will provide:

■ Direct journey opportunities to central London

■ 4 trains per hour during peak periods to central London

■ Substantial new passenger capacity andcrowding relief into central London

Bourne End/Marlow services will terminate in a new bay platform at Maidenhead. Passengerswishing to travel beyond Maidenhead will needto interchange. One through train from BourneEnd to Paddington could be provided in themorning peak.

The diagram below highlights some of the journey times that will be possible bypassengers travelling on Crossrail services to and from Maidenhead station.

The Crossrail service pattern will be set by the relevant railway bodies in consultation with the train operating company responsiblefor operating Crossrail services.

With Crossrail operational, the total number of seats available on trains to and fromMaidenhead will increase, as a result of longer, more frequent trains.

Canary Wharf

35 60

Canary Wharf 60 minutes Liverpool Street 52 minutesFarringdon 49 minutesTottenham Court Road 46 minutes Paddington 41 minutes Heathrow Airport * 35 minutes

Maidenhead – From / To

*5 minutes interchange presumed & included

Service ImprovementsMaidenhead

W5.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Typical Crossrail journey times from Maidenhead

5393_W05.R3.1_Maidenhead 1/2/05 7:50 PM Page 1

Page 5: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Station ImprovementsTaplow

W6.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Station improvements at Taplow

There will be a number of minor improvementsat Taplow, including new ticket machines andplatform extensions.

There will be extensions to platforms 3 and 4 at the western end to cater for 10-carCrossrail trains.

There will be no major alterations to the station.

Overhead electrification will be installed along the route between Maidenhead and Airport Junction.

THIS MAP IS BASED UPON ORDNANCE SURVEY MATERIAL WITH THE PERMISSION OF ORDNANCE SURVEY ON BEHALF OF THE CONTROLLER OF HER MAJESTY’S STATIONERY OFFICE © CROWN COPYRIGHT. UNAUTHORISED REPRODUCTION INFRINGES CROWN COPYRIGHT AND MAY LEAD TO PROSECUTION OR CIVIL PROCEEDINGS. (GLA - 100032379) (2005).

5393_W06.R3.1_Taplow 01/02/05 18:43 Page 1

Page 6: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Train services to and from Taplow station will be improved by providing direct journeyopportunities, substantial new passengercapacity and crowding relief into central London.

Crossrail Taplow station will provide:

■ Direct journey opportunities to central London

■ 4 trains per hour during peak times tocentral London

The diagram below highlights some of thejourney times that will be possible by travelling on Crossrail services to and fromTaplow station.

With Crossrail operational, the total number ofseats available on trains to and from Taplowwill increase as a result of the longer trains.

The Crossrail service pattern will be set by therelevant railway bodies in consultation with the train operating company responsible foroperating Crossrail services.

Service ImprovementsTaplow

W7.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Taplow Station at present

49 minutes to

Liverpool Street

57 minutes to Canary Wharf

37 minutes to Paddington

Canary Wharf

34 minutes to Heathrow Airport *

Canary Wharf 57 minutes Liverpool Street 49 minutesFarringdon 46 minutesTottenham Court Road 43 minutes Paddington 37 minutes Heathrow Airport * 32 minutes

Taplow – From / To

*5 minutes interchange presumed & included

*5 minutes interchange presumed & included

Typical Crossrail journey times from Taplow

5393_W07.R3.1_Taplow 1/2/05 7:49 PM Page 1

Page 7: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Station ImprovementsBurnham

W8.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Station improvements at Taplow

Improvements at Burnham include new ticketmachines, customer information facilities andplatform extensions.

Burnham station has a single island platformbetween the Relief lines serving platforms 1 and 2. The station platform at the westernend will be extended to take new 10-car Crossrail trains.

A worksite is proposed adjacent to BurnhamLane on the northeast side of the station.

No major alterations to the station are proposed.

Overhead line electrification would be installed along the route between Maidenheadand Airport Junction. These are relativelyminor works.

THIS MAP IS BASED UPON ORDNANCE SURVEY MATERIAL WITH THE PERMISSION OF ORDNANCESURVEY ON BEHALF OF THE CONTROLLER OF HER MAJESTY’S STATIONERY OFFICE © CROWN COPYRIGHT. UNAUTHORISED REPRODUCTION INFRINGES CROWN COPYRIGHT AND MAY LEAD TOPROSECUTION OR CIVIL PROCEEDINGS. (GLA - 100032379) (2005).

5393_W08.R3.1_Burnham 01/02/05 18:45 Page 1

Page 8: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Train services to and from Burnham station will be improved by providing new directjourney opportunities to central London and substantial new transport capacity and crowding relief into central London.

Crossrail Burnham station would provide:

■ Direct journey opportunities to central London

■ 4 trains per hour during peak times to central London

The diagram below highlights some of the journey times that will be possible bytravelling on Crossrail services to and fromBurnham station.

The Crossrail service pattern will be set by the relevant railway bodies in consultation with the train operating company responsiblefor operating Crossrail services.

46 minutes to

Liverpool Street

53 minutes to Canary Wharf

34 minutes to Paddington

Canary Wharf

Canary Wharf 53 minutes Liverpool Street 46 minutesFarringdon 43 minutesTottenham Court Road 40 minutes Paddington 34 minutes Heathrow Airport * 29 minutes

Burnham – From / To

*5 minutes interchange presumed & included

29 minutes to Heathrow Airport *

*5 minutes interchange presumed & included

Service ImprovementsBurnham

W9.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Burnham Station at present

Typical Crossrail journey times from Burnham

5393_W09.R3.1_Burnham 1/2/05 7:51 PM Page 1

Page 9: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Stoke Poges LaneBridge Stoke Poges Lane Bridge is a narrow road bridge with a separate footbridge. Crossrail propose raisingthe road bridge to provide the necessary headroomfor overhead electrification and raising the parapets to comply with modern safety requirements. The footbridge parapets will be renewed, again to comply with these requirements.

William StreetBridge No major work to William Street Bridge is anticipated.The parapets would be raised to comply with modernsafety requirements. The northern most track will berelaid at a lower level as part of the general trackworkremodelling west of Slough station.

Burnham to Slough (2)

W10.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

William Street Bridge

Stoke Poges Lane Bridge

5393_W10.R3.1_Slough 01/02/05 18:46 Page 1

Page 10: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Leigh Road Bridge Leigh Road is carried over the railway in a southerlydirection by means of a rail overbridge accommodatinga single lane of traffic controlled by traffic signals. The bridge is made up of two spans of brick arch and brick wall parapets.

Subject to reaching an agreement with Slough BoroughCouncil, Crossrail will reconstruct this bridge as a single span structure formed of steel main girders and composite (steel and concrete) bridge deck.

A temporary bridge is proposed on the eastern side ofthe existing bridge.

It is not proposed to provide a temporary road bridge as diversions to the east over Farnham Road and to the west over Dover Road could be made.

Dover Road BridgeNo major work to the bridge will be required. The trackswill be lowered to provide adequate headroomclearance for overhead electrification. The parapets willbe raised to comply with modern safety requirements.

Farnham RoadBridge No major work to Farnham Road Bridge will be required.The parapets will be raised to comply with modernsafety requirements and the tracks will be lowered toprovide adequate headroom clearance for overheadelectrification. A temporary narrowing of the carriagewayand temporary footway will be constructed.

Burnham to Slough (1)

W11.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Leigh Road Bridge

Farnham Road Bridge

Dover Road Bridge

5393_W11.R3.1_Slough 2/2/05 11:57 AM Page 1

Page 11: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Improvements to ensure that efficient stationfacilities are provided at Slough station include:

■ Rearranged southern ticket hall with newticket gates and ticket machines

■ Improved northern entry to Platform 5

■ Lift access to all platforms

■ Improved passenger facilities

■ Improved station access

Platforms 2 to 5 will be extended to cater for10-car Crossrail trains.

The Windsor bay platform will be widened andthe track realigned.

A new station footbridge with lifts will beconstructed at the western end of the existing platform.

There are four worksites for construction.

■ Railway Terrace west

■ Slough station north

■ Slough station south

■ Brunel Way

All materials will be taken to and from the sitesby road, with access from William Street.

Some parking spaces will be temporarily lostduring construction. Exact details will besubject to detailed design and discussionswith Slough Borough Council.

Station ImprovementsSlough (2)

W13.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Architect’s impression

5393_W13.R3.1_Slough 01/02/05 18:50 Page 1

Page 12: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

The bay platform and associated tracks on the northern side of the station will be removedto allow widening and extension of platform 5.There will be a new siding will run between therunning lines to the west of the station.

A new bay platform will be constructed whereservices from Reading will terminate.

Overhead electrification will be installed along the route between Maidenhead andAirport Junction.

The unique character of this Grade II listedstation will be recognised as it is upgraded inline with modern safety requirements.

Works to the station canopies to accommodatethe overhead electrification could have animpact on the listed structure. The design isbeing undertaken in conjunction with heritagespecialists to manage any impact.

Mitigation measures will be employed to limitconstruction noise impacts. These will include3.6m high hoardings and the provision of noise insulation if appropriate.

Station ImprovementsSlough (2)

W14.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

THIS MAP IS BASED UPON ORDNANCE SURVEY MATERIAL WITH THE PERMISSION OF ORDNANCE SURVEY ON BEHALF OF THE CONTROLLER OF HER MAJESTY’S STATIONERY OFFICE © CROWN COPYRIGHT. UNAUTHORISED REPRODUCTION INFRINGES CROWN COPYRIGHT AND MAY LEAD TO PROSECUTION OR CIVIL PROCEEDINGS. (GLA - 100032379) (2005).

Station improvements at Slough

5393_W14.R3.1_Slough 01/02/05 18:53 Page 1

Page 13: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

42 minutes to

Liverpool Street

49 minutes to Canary Wharf

30 minutes to Paddington

Canary Wharf

Canary Wharf 49 minutes Liverpool Street 42 minutesFarringdon 39 minutesTottenham Court Road 36 minutes Paddington 30 minutes Heathrow Airport * 25 minutes

Slough – From / To

*5 minutes interchange presumed & included

25 minutes to Heathrow Airport *

*5 minutes interchange presumed & included

Crossrail Slough station will provide newdestinations to central London and otherbenefits include:

■ Direct journey opportunities to central London

■ 4 trains per hour during peak periods to central London

■ Substantial new passenger capacity and crowding relief into central London

■ Access to Heathrow Airport via aninterchange at Hayes & Harlington station

The diagram below highlights some of the journey times that will be possible bypassengers travelling on Crossrail services to and from Slough station.

With Crossrail operational, the total number of seats available on trains to and from Sloughwill increase as a result of the longer trains.

The Crossrail service pattern will be set by the relevant railway bodies in consultation with the train operating company responsiblefor operating Crossrail services.

Service ImprovementsSlough

W15.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Typical Crossrail journey times from Slough

5393_W15.R3.1_Slough 1/2/05 7:51 PM Page 1

Page 14: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

St Mary’s RoadBridge St Mary’s Road Bridge will be partially reconstructed.A temporary highway bridge controlled by temporarytraffic lights will be provided during the works. The plans will take account of the traffic assessmentstudies carried out as part of the overall EnvironmentalImpact Assessment and will also take account ofadvice from relevant highway authorities.

There will be a worksite to the south west of the bridge.

Trenches Bridge Trenches Bridge will be reconstructed as acombined footbridge/cycleway. The bridge will beclosed temporarily during the construction period.The plans will take account of the traffic assessmentstudies carried out as part of the overallEnvironmental Impact Assessment and advice fromrelevant highway authorities.

A worksite will be located north east of the bridge.Access to the worksite will be from the east throughan industrial site, via Waterside Drive.

Bridge WorksSlough to Langley (2)

W16.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Trenches Bridge

St Mary’s Road Bridge

5393_W16.R3.1_Langley 01/02/05 18:56 Page 1

Page 15: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Wexham RoadBridge Wexham Road Bridge will require reconstruction of the southern arch to provide clearance for overheadelectrification. A temporary road bridge will beconstructed on the west side of the existing bridge, to maintain traffic flows during construction. Two worksites will be created at the north west and south west of the bridge.

Uxbridge RoadBridge No significant works to Uxbridge Road Bridge will berequired. The parapets will be replaced to comply withmodern safety requirements during this work. There willbe temporary closure of the footways with pedestriansdiverted to the opposite side.

Middlegreen RoadBridge Middlegreen Road Bridge will be reconstructed toprovide clearance for overhead electrification. Both brick arches will be removed to give the requiredclearance. The existing brick arches will be replacedwith pre-cast concrete arches. The parapets will beupgraded to comply with modern safety requirements.The areas northwest and southwest of the bridge will beused for working and storage areas. There will be a worksite on the north side of the bridge.

Bridge WorksSlough to Langley (1)

W17.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Wexham Road Bridge

Uxbridge Road Bridge

Middlegreen Road Bridge

5393_W17.R3.1_Langley 01/02/05 18:57 Page 1

Page 16: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

There will be a number of minor improvements including:

■ New ticket machines

■ Improved customer information facilities

Platform 1 will be extended at the eastern end to cater for a 5-car Crossrail train, andplatforms 2 to 4 at the eastern end to cater for the 10-car Crossrail trains.

A worksite will be constructed within thevacant oil terminal land on the northern side of the station. Access will be off Station Road.

Overhead line electrification will be installedalong the route between Maidenhead andAirport Junction.

Station ImprovementsLangley

W19.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

THIS MAP IS BASED UPON ORDNANCE SURVEY MATERIAL WITH THE PERMISSION OF ORDNANCE SURVEY ON BEHALF OF THE CONTROLLER OF HER MAJESTY’S STATIONERY OFFICE © CROWN COPYRIGHT. UNAUTHORISED REPRODUCTION INFRINGES CROWN COPYRIGHT AND MAY LEAD TO PROSECUTION OR CIVIL PROCEEDINGS. (GLA - 100032379) (2005).

Station improvements at Langley

5393_W19.R3.1_Langley 01/02/05 18:58 Page 1

Page 17: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Train services to and from Langley station willbe improved by providing journey time savingsand a greater variety of new destinations.

The diagram below highlights some of the journey times that will be possible bytravelling on Crossrail services to and fromLangley station.

Crossrail Langley station will provide:

■ Direct journey opportunities to central London

■ 4 trains per hour during peak periods to central London

■ Substantial new passenger capacity and crowding relief into central London

The Crossrail service pattern will be set by the relevant railway bodies in consultationwith the train operating company responsiblefor operating Crossrail services.

39 minutes to

Liverpool Street

46 minutes to Canary Wharf

27 minutes to Paddington

22 minutes to Heathrow Airport*

Canary Wharf

Canary Wharf 46 minutes Liverpool Street 39 minutesFarringdon 36 minutesTottenham Court Road 33 minutes Paddington 27 minutes Heathrow Airport* 22 minutes

*5min interchange presumed and included

Langley – From / To

Service ImprovementsLangley

W20.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Langley station at present

Typical Crossrail journey times from Langley

5393_W20.R3.1_Langley 1/2/05 7:58 PM Page 1

Page 18: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

A new underbridge will be constructed on the north side of the existing ChequerBridge to take an additional track. Theembankment between Chequer Bridge and Dog Kennel Bridge will be widened,requiring permanent acquisition of a narrowstrip of adjacent open land. Temporary road closures will be needed during thenight and occasionally on a Sunday.

Phasing of construction works at thislocation will require integration with workon adjacent bridges to limit disruption to the local road network. A worksite will be constructed to the north of theexisting bridge.

To accommodate overhead electrification,Dog Kennel Bridge will be demolished. The path running southward from the Grand Union Canal to the railway is a public footpath, but the bridge is not. The demolition of the Dog Kennel Bridge will remove the link between publicfootpaths north and south of the railway.

The materials generated from thedemolition of the brick arches will be taken away by road. Vehicle access to the worksite will be from North Park and from Market Lane.

Mitigation measures will manageconstruction noise. These will include 3.6m high hoardings and the provision of noise insulation if appropriate.

Chequer Bridge

Bridge WorksLangley to Iver

W21.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Dog Kennel Bridge

Chequer Bridge

Dog Kennel Bridge

5393_W21.R3.1_Iver 01/02/05 18:59 Page 1

Page 19: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

There will be a number of improvementsincluding a new ticket office and passenger facilities.

The station platforms at the western end of Iver station will be extended. Platforms 3 and 4 will be extended to provide for new 10-car Crossrail trains. A new platform(platform 5) will be built.

Work on the station platforms will be co-ordinated from a temporary worksite on the north side of the tracks.

Overhead line electrification will be installed along the route betweenMaidenhead and Airport Junction and Maidenhead.

Mitigation measures will manage construction noise. These will include 3.6m high hoardings and the provision of noise insulation if appropriate.

Station ImprovementsIver

W22.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

THIS MAP IS BASED UPON ORDNANCE SURVEY MATERIAL WITH THE PERMISSION OF ORDNANCE SURVEY ON BEHALF OF THE CONTROLLER OF HER MAJESTY’S STATIONERY OFFICE © CROWN COPYRIGHT. UNAUTHORISED REPRODUCTION INFRINGES CROWN COPYRIGHT AND MAY LEAD TO PROSECUTION OR CIVIL PROCEEDINGS. (GLA - 100032379) (2005).

Station improvements at Iver

5393_W22.R3.1_Iver 01/02/05 19:00 Page 1

Page 20: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Train services to and from Iver station will be improved by providing a greater variety of new destinations into central London and substantial new passenger capacity and crowding relief into central London.

Crossrail Iver station will provide:

■ Direct journey opportunities to central London

■ 4 trains per hour during peak times to central London

The diagram below highlights some of thejourney times that will be possible by travellingon Crossrail services to and from Iver station.

With Crossrail operational, the total number of seats available on trains to and from Iver willincrease as a result of the longer trains.

The Crossrail service pattern will be set by the relevant railway bodies in consultationwith the train operating company responsiblefor operating Crossrail.

Iver station at present

36 minutes to

Liverpool Street

43 minutes to Canary Wharf

24 minutes to Paddington

19 minutes to

Heathrow Airport*

Canary Wharf

Canary Wharf 43 minutes Liverpool Street 36 minutesFarringdon 33 minutesTottenham Court Road 30 minutes Paddington 24 minutes Heathrow Airport* 19 minutes*5min interchange presumed and included

Iver – From / To

Service ImprovementsIver

W23.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Typical Crossrail journey times from Iver

5393_W23.R3.1_Iver 1/2/05 8:05 PM Page 1

Page 21: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

West Drayton Yard was a coal depot and currently has asingle freight sidings. Train stabling will be developed withinthe yard to accommodate up to 22 (10-car) trains during off-peak hours and overnight.

To accomodate the proposed layout the access road into thedepot will need to be realigned. This will require a new bridgeover Fray’s river and a new and upgraded level crossing overColnbrook branch.

The Yard will be a worksite for electrification works.

The existing bridge over Fray’s river will be used to carrysome of the new railway tracks.

The likely environmental effects of the proposals are:

■ Operational noise from the use of the sidings. The newsidings will be distanced from most buildings on the northside (Tavistock Road) and those located to the south

■ The lighting of the stabling area. (This will be designed to control light pollution into the sky or upon buildings inaccordance with best practice).

Langley to West Drayton Loop Currently along the Great Western Main line there are Mainand Relief lines. Freight trains can use additional sections of track between Langley and West Drayton (Langley andWest Drayton Loop lines). The track is in two parts, the firstsection is between Langley and Chequer Bridge and thesecond section is between Dog Kennel Bridge and WestDrayton station.

To construct the new overtaking track a new bridge span is required at Chequers Lane Bridge on the north side of therailway. With the provision of the new track, the formation asan extension to the existing embankment both west and eastof the bridge is required. This will involve the acquisition ofsome nearby land.

The new track will link the existing goods loop east of Langley station with the loop commencing immediately east of Dog Kennel Bridge.

At West Drayton station the northern platform will be remodelled and extended to accommodate the new track realignment.

West Drayton StablingW24.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

THIS MAP IS BASED UPON ORDNANCE SURVEY MATERIAL WITH THE PERMISSION OF ORDNANCE SURVEY ON BEHALF OF THE CONTROLLER OF HER MAJESTY’S STATIONERY OFFICE © CROWN COPYRIGHT. UNAUTHORISED REPRODUCTION INFRINGES CROWN COPYRIGHT AND MAY LEAD TO PROSECUTION OR CIVIL PROCEEDINGS. (GLA - 100032379) (2005).

Wset Drayton Train Depot

5393_W24.R3.1_West Drayton 01/02/05 19:02 Page 1

Page 22: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

To provide the necessary clearance for overhead electrification, Thorney Lane Bridge will bereconstructed on a new road alignment to the east of the existing bridge. The new single span bridge will accomodate a 7.3m wide carriage way.

The existing footbridge on the west side of the existing bridge will remain. The parapets will berenewed to comply with modern safety requirements.

This is covered by the ‘Thorney Park Golf Course’ display panel.

Bridge WorksWest Drayton to Iver

W25.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Thorney Lane Bridge at present

5393_W25.R3.1_West Drayton 01/02/05 19:02 Page 1

Page 23: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Station ImprovementsWest Drayton

W26.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Station improvements at Taplow

A range of improvements will help to ensure that efficientstation facilities are provided.

These include improvements to integrate the station withother types of transport.

Improvements include:

■ New ticket hall

■ New ticket gates and ticket machines

■ Lift access to all platforms

■ Passenger facilities including disabled parking and toilets

■ Staff facilities

■ Reconstruction and extension of platforms 4 and 5

■ Extension of platform 3

Overhead line electrification will be installed along the routebetween Maidenhead and Airport Junction.

A worksite will be constructed between the railway line and the Grand Union Canal with access off Station Approach and the High Street.

Access to the station worksite, between the railway and the Grand Union Canal to the north of the railway, will be from the High Street via Station Approach. The Stabling Yard worksite will be reached from the High Street using the existing access off Tavistock Road. Lorries for both worksites will be routed from the A408 Stockley Road, via Horton Road and the High Street.

Mitigation measures will manage construction noise. These will include 3.6m high hoardings and the provision of noise insulation if appropriate.

THIS MAP IS BASED UPON ORDNANCE SURVEY MATERIAL WITH THE PERMISSION OF ORDNANCE SURVEY ON BEHALF OF THE CONTROLLER OF HER MAJESTY’S STATIONERY OFFICE © CROWN COPYRIGHT. UNAUTHORISED REPRODUCTION INFRINGES CROWN COPYRIGHT AND MAY LEAD TO PROSECUTION OR CIVIL PROCEEDINGS. (GLA - 100032379) (2005).

5393_W26.R3.1_West Drayton 01/02/05 19:04 Page 1

Page 24: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Crossrail will improve train services to and from West Drayton by providing journey time savings and a greater variety of new destinations.

Crossrail will provide:

■ Direct journey opportunities to central London

■ 6 trains per hour during peak times to central London

■ Substantial new passenger capacity and crowding relief into central London

The diagram below highlights some of the journey times that will be possible by travelling on Crossrail services to and fromWest Drayton station.

With Crossrail operational, the total number of seats available on trains to and from West Drayton will increase as a result of longer, more frequent trains.

The Crossrail service pattern will be set by the relevant railway bodies in consultation with the train operating company responsiblefor operating Crossrail services.

33 minutes to

Liverpool Street

40 minutes to Canary Wharf

21 minutes to Paddington

16 minutes to Heathrow Airport*

Canary Wharf

Canary Wharf 40 minutes Liverpool Street 33 minutesFarringdon 30 minutesTottenham Court Road 27 minutes Paddington 21 minutes Heathrow Airport* 16 minutes

*5min interchange presumed and included

West Drayton – From / To

Service ImprovementsWest Drayton

W28.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

West Drayton station at present

Typical Crossrail journey times from West Drayton

5393_W28.R3.1_West Drayton 2/2/05 10:56 AM Page 1

Page 25: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Kingston Lane Bridge Horton Road/Kingston Lane Bridge is a foot and cycle bridgethat will be reconstructed to provide adequate headroom foroverhead electrification. The new bridge will be constructedimmediately to the west of the existing bridge, and will becompleted prior to demolition of the existing bridge.

Old Stockley Road Bridge Old Stockley Road Bridge is located to the west of StockleyRoad Bridge. The bridge will be demolished and all vehiculartraffic diverted to Stockley Road Bridge permanently. A pedestrian/cycle path bridge will replace the existing bridge.

Bridge Works

West Drayton to Stockley FlyoverW29.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Kingston Lane Bridge

Old Stockley Road Bridge

Stockley Road Bridge No major work will be required to Stockley Road Bridge, but the parapets will need to be raised to comply with modern safety requirements.

Mitigation measures will manage construction noise. These will include 3.6m high hoardings and the provision of noise insulation if appropriate.

Stockley Road Bridge

5393_W29.R3.1_Stockley 01/02/05 19:05 Page 1

Page 26: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Service ImprovementsHeathrow Airport Access (1)

W30.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Work at Stockley Flyover

The existing flyover (Stockley Flyover) currently carriesHeathrow Express trains heading to Paddington from the Heathrow tunnel over the two Main line tracks.

This structure will be used to carry Crossrail trains fromLondon to the Airport, running on the Relief lines, up the ramp and over the two Main line tracks: the two existingAirport line tracks would merge together just before entering the Heathrow tunnel portal.

Immediately after leaving the tunnel mouth, all trains fromHeathrow Airport (both Heathrow Express and Crossrail) will use a new single track viaduct built on the western side of the existing Airport line tracks.

The viaduct will be as close to the existing embankment as possible to mitigate the effect on Stockley Ponds. This new track will cross over all five railway tracks (the Main lines, the Relief lines and the Goods line) on a newflyover. A further viaduct approximately 400 metres long will carry the new track alongside the Goods line.

A second flyover will be built across the three northern tracks(Goods line and two Relief line tracks) and will support a newjunction. One branch of the junction will carry HeathrowExpress trains on this structure back over these three tracksbefore descending on a new ramp to be built between theMain lines and Relief lines: this track will merge with thecurrent Up Airport line at Dawley Road bridge.

The other branch of the junction will carry Crossrail trains on a second new ramp built on the north side of the Relief lines.Crossrail trains will then use the current Goods line track fromDawley Road bridge towards Hayes & Harlington station.

It will be necessary to move the Relief line tracks northwardsto create sufficient space for the new ramp structures. Theform of this second box structure and the ramps to the eastwill provide effective screening of the Relief lines tracks fromthe residential property on the south side of the railway.

The new viaduct will require the permanent acquisition of land from a number of the premises that abut the northernrailway boundary.

5393_W30.R3.1_Stockley 01/02/05 19:06 Page 1

Page 27: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

The Crossrail service from Heathrow Airport will replace theHeathrow Connect service to Paddington, with a more frequentservice that stops at Hayes and Harlington, Southall, WestEaling, Ealing Broadway, Acton Main Line, Paddington andcontinues into central London.

Crossrail will run beyond Paddington to directly serve the WestEnd, City and Canary Wharf. This will substantially reducejourney times for many existing Heathrow passengers.

The diagram below highlights some of the journey times thatwill be possible by travelling on Crossrail services to and fromHeathrow Airport.

The Crossrail timetable and service pattern will be set by therelevant railway bodies in consultation with the train operatingcompany responsible for operating Crossrail services.

The Crossrail service to Heathrow is subject to agreement with British Airports Authority plc (BAA).

Crossrail will fit in with the existing rail network enablingcommuters and tourists to benefit from fast and efficienttravel into and across London.

Current services to Heathrow Airport – BAA plc Heathrow Express

■ Heathrow Expressfast – a non-stop 4 train per hour service in each direction between Paddington andHeathrow Airport. Heathrow Connect provides 2 trains perhour connecting Paddington to Heathrow Airport via localstations including Ealing Broadway, Southall and Hayes & Harlington

Crossrail services to Heathrow Airport

■ 4 trains per hour in each direction between Paddington andHeathrow Airport replacing the 2 trains per hour HeathrowConnect. Crossrail services to and from Heathrow Airportwill call at local stations into central London. The 4 trainsper hour Heathrow Express fast service will remain

This corridor will provide significant journey time savings to the West End, City and Canary Wharf. Crossrail services to Heathrow Airport will increase service frequencies andattract passengers from Underground services, therebyproviding crowding relief.

36 minutes to

Liverpool Street

43 minutes to Canary Wharf

26 minutes to Paddington

Canary Wharf

Canary Wharf 43 minutes Liverpool Street 36 minutesFarringdon 34 minutesTottenham Court Road 31 minutes Paddington 26 minutes

Heathrow Central – From / To

(may require a change of train)

Service ImprovementsHeathrow Airport

W31.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Typical Crossrail journey times from Heathrow Airport

Xrail train

5393_W31.R3.1_Heathrow 2/2/05 10:57 AM Page 1

Page 28: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Station ImprovementsHayes & Harlington

W32.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Improvements will help ensure that efficient station facilities are provided. These will include the integration of the station with other types of transport. Redevelopment of the station is planned.

This will include:

■ Creation of an important interchange for services toHeathrow Airport

■ New ticket hall, footbridge, stairs and lifts to platforms

■ Station canopies

A new platform will be constructed on the north side of the station, with the existing buildings demolished.

The proposals include the creation of a new track north of the existing London bound platform. The existing bay platform will be removed to make way for the new alignment.The new track will travel under Station Road through a new span opening.

A temporary bridge to the west side of Station Road bridge will be provided whilst the new span is constructed.

To construct the new opening, a temporary bridge will beconstructed to the west of Station Road. Traffic andpedestrians will use the temporary bridge during construction.Where necessary temporary station facilities will be providedduring reconstruction.

A new ticket hall and fully accessible footbridge with lifts will be provided to all platforms.

All existing platforms will be extended eastwards to provide for 10-car Crossrail trains. Platform canopies and additionalshelters will be provided.

West of Hayes and Harlington station, Crossrail trains toHeathrow will connect into the existing westbound Airport trackto Heathrow Airport.

Works will be undertaken from three worksites. One is at the west end of the Station Road Bridge on the south side of the railway. The other two will be east of Station Road.

All materials will be taken to and from the sites by road.Access will be via either Station Road Bridge or StationApproach.

Some parking spaces will be temporarily lost duringconstruction. Exact details will be subject to detailed designand discussions with the London Borough of Hillingdon.

Mitigation measures will manage construction noise. These will include 3.6m high hoardings and the provision of noiseinsulation if appropriate.

The scheme for Hayes & Harlington station may be adjusted to incorporate proposals from the local authority, Transport for London (TfL) and British Airways Authority (BAA).

THIS MAP IS BASED UPON ORDNANCE SURVEY MATERIAL WITH THE PERMISSION OF ORDNANCE SURVEY ON BEHALF OF THE CONTROLLER OF HER MAJESTY’S STATIONERY OFFICE © CROWN COPYRIGHT. UNAUTHORISED REPRODUCTION INFRINGES CROWN COPYRIGHT AND MAY LEAD TO PROSECUTION OR CIVIL PROCEEDINGS. (GLA - 100032379) (2005).

Station improvements at Hayes & Harlington

5393_W32.R3.1_Hayes 01/02/05 19:07 Page 1

Page 29: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

29 minutes to

Liverpool Street

37 minutes to Canary Wharf

17 minutes to Paddington

7 minutes to Heathrow Airport

Canary Wharf

Canary Wharf 37 minutes Liverpool Street 28 minutesFarringdon 25 minutesTottenham Court Road 22 minutes Paddington 17 minutes Heathrow Airport 7 minutes

Hayes & Harlington – From / To

*5 minutes interchange presumed & included

Train services will be improved to and fromHayes & Harlington Station by providingjourney time savings and a greater variety of new destinations.

Crossrail Hayes & Harlington station will provide:

■ Direct journey opportunities to centralLondon and Heathrow Airport

■ 10 trains per hour during peak times to central London

■ Substantial new passenger capacity andcrowding relief into central London

The diagram below highlights some of thejourney times that will be possible travelling on Crossrail services to and from Hayes andHarlington station.

With Crossrail operational, the total number of seats available on trains to central Londonfrom Hayes & Harlington will increase as a result of longer, more frequent trains.

The service pattern will be set by the relevantrailway bodies in consultation with the trainoperating company responsible for operatingCrossrail services.

Service ImprovementsHayes & Harlington

W34.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Typical Crossrail journey times from Hayes & Harlington

5393_W34.R3.1_Hayes 2/2/05 10:58 AM Page 1

Page 30: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Station ImprovementsSouthall

W36.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Southall Station

Improvements will ensure that appropriate station facilities areprovided. These include improving the integration of thestation with other types of transport. The station will also be redeveloped.This includes:� Ticket hall located north of platform 4 with access from

South Road� Island platform 2 & 3 widened� Platform shelters� Lift access to all Crossrail platforms� Refurbishment of staff facilities� Extension of all the platforms to provide for 10-car

Crossrail trains � Full mobility impaired access from street to platforms� A new footbridge with stairs and lifts to all platforms� The existing island platform 2/3 widened to provide space

for a new footbridge� Platforms 3 and 4 lengthened to accommodate the 10-car

Crossrail trains, with additional platform shelters

The existing ticket hall will remain operational during the alterations.There will be temporary worksites on both sides of the tracksat the station. The present island platform 3/4 will be widenedto allow the new footbridge and lift to be installed. TheCrossrail trains travelling to Maidenhead and Heathrow will continue on the Relief lines, stopping at the existingwestbound and eastbound platforms.Works at the station will be undertaken from the Southallstation worksite. The worksite is bounded by Merrick Road footbridge to the east,by Station Road to the west and by the railway to the south.All materials will be taken to and from the site by road. Accessto the worksite will be from Avenue Road and Park Avenue.Lorries will access the worksite from the A4020 Uxbridge Roadvia Station Road and Merrick Road. It will be necessary toclose the junction of Merrick Road – Park Avenue for shortperiods during the work.Mitigation measures will manage construction noise. These willinclude 3.6m high hoardings and the provision of noiseinsulation if appropriate.

THIS MAP IS BASED UPON ORDNANCE SURVEY MATERIAL WITH THE PERMISSION OF ORDNANCE SURVEY ON BEHALF OF THE CONTROLLER OF HER MAJESTY’S STATIONERY OFFICE © CROWN COPYRIGHT. UNAUTHORISED REPRODUCTION INFRINGES CROWN COPYRIGHT AND MAY LEAD TO PROSECUTION OR CIVIL PROCEEDINGS. (GLA - 100032379) (2005).

5393_W36.R3.1_Southall 2/2/05 1:44 PM Page 1

Page 31: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Train services to and from Southall station willbe improved by providing journey time savingsand a greater variety of new destinations.

The diagram below highlights some of the journey times that will be possible bytravelling on Crossrail services to and fromSouthall station.

Crossrail Southall station will provide:

■ Direct journey opportunities to centralLondon, Heathrow Airport and the west

■ 8 Crossrail trains per hour during peak timesto central London

■ Substantial passenger capacity andcrowding relief into central London

With Crossrail operational, the total number of seats available on trains to and fromSouthall will increase as a result of longer,more frequent trains.

The Crossrail service pattern will be set by the relevant railway bodies in consultation withthe train operating company responsible foroperating Crossrail services.

25 minutes to

Liverpool Street

35 minutes to Canary Wharf

14 minutes to Paddington

9 minutes to

Heathrow Airport

Canary Wharf

Canary Wharf 35 minutes Liverpool Street 25 minutesFarringdon 22 minutesTottenham Court Road 19 minutes Paddington 14 minutes Heathrow Airport 9 minutes

Southall – From / To

*5 minutes interchange presumed & included

Service ImprovementsSouthall

W38.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Southall station at present

Typical Crossrail journey times from Southall

5393_W38.R3.1_Southall 2/2/05 10:59 AM Page 1

Page 32: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Station ImprovementsHanwell

W39.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Station improvements at Hanwell

There will be passenger facility, safety and securityimprovements.

The station platforms will be extended at the western end.The extensions will be on piled foundations. Crossrail will takeinto account likely environmental impact and local concernsduring construction.

The unique character of this Grade II listed station isrecognised and efforts will be made to preserve it, in line with modern safety requirements.

Space will be required for a work and storage area duringconstruction of the platform extensions.

Works will be undertaken from 3 worksites:

■ Churchfields Gardens

■ East of Golden Manor

■ Hanwell Station forecourt

Material will be taken to and from sites by road, with accessalong Golden Manor, Aldwyne Road and Campbell Road.

Mitigation measures will manage construction noise. These will include 3.6m high hoardings and the provision of noise insulation if appropriate.

THIS MAP IS BASED UPON ORDNANCE SURVEYMATERIAL WITH THE PERMISSION OF ORDNANCESURVEY ON BEHALF OF THE CONTROLLER OF HERMAJESTY’S STATIONERY OFFICE © CROWN COPYRIGHT.UNAUTHORISED REPRODUCTION INFRINGES CROWNCOPYRIGHT AND MAY LEAD TO PROSECUTION OR CIVILPROCEEDINGS. (GLA - 100032379) (2005).

5393_W39.R3.1_Hanwell 01/02/05 19:11 Page 1

Page 33: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Train services will be improved to and from Hanwell station by providing journey time savings and a greater variety of new destinations.

Crossrail Hanwell station will provide:

■ The journey to Heathrow requires a changeof train at Hayes & Harlington. The HeathrowAirport service improvements display panelindicates that the Crossrail service toHeathrow does not call at Hanwell

■ 2 trains per hour during peak times to central London

■ Substantial new passenger capacity and crowding relief into and out of central London

The diagram below highlights some of the journey times that will be possible bytravelling on Crossrail services to and fromHanwell station.

The service pattern will be set by the relevantrailway bodies in consultation with the trainoperating company responsible for operatingCrossrail services.

23 minutes to

Liverpool Street

30 minutes to Canary Wharf

13 minutes to Paddington

18 minutes to

Heathrow Airport

Canary Wharf

Canary Wharf 30 minutes Liverpool Street 23 minutesFarringdon 21 minutesTottenham Court Road 18 minutes Paddington 13 minutes Heathrow Airport 18 minutes

Hanwell – From / To

*5 minutes interchange presumed & included

Service ImprovementsHanwell

W40.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Hanwell station at present

Typical Crossrail journey times from Hanwell

5393_W40.R3.1_Hanwell 2/2/05 11:01 AM Page 1

Page 34: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Station ImprovementsWest Ealing

W41.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Improvements will help ensure that efficient station facilitiesare provided. These will include opportunities to improving the integration of the station with other types of transport.

Changes include:

■ Ticket hall relocated with access from Manor Road

■ Provision of a terminus platform for the Greenford service

■ Construction of an overbridge with stairs and lift

■ Platforms 3 and 4 extended to the west to take Crossrail 10-car trains

■ Remodelling of Greenford Branch Junction

■ Additional platform canopies and shelters

To provide train paths for Crossrail services on the Relief lines,the existing Greenford to Paddington services will terminate at West Ealing station. A shuttle service will run between

Greenford and West Ealing at a frequency of up to 4 trains perhour. Passengers will need to change trains at West Ealing forCrossrail services to central London and eastern destinations.

Terminating the Greenford to Paddington services will requireplatform and track work and a worksite will extendnorthwards along the railway towards Drayton Green.

Works will be coordinated from a disused area of railway landbetween the railway and Manor Road.

Access will be from Manor Road and construction traffic willbe routed from Uxbridge Road via Drayton Green Road.

Mitigation measures will manage construction noise. Thesewill include 3.6m high hoardings and the provision of noiseinsulation if appropriate.

Station improvements at West Ealing

THIS MAP IS BASED UPON ORDNANCE SURVEY MATERIAL WITH THE PERMISSION OF ORDNANCE SURVEY ON BEHALF OF THE CONTROLLER OF HER MAJESTY’S STATIONERY OFFICE © CROWN COPYRIGHT. UNAUTHORISED REPRODUCTION INFRINGES CROWN COPYRIGHT AND MAY LEAD TO PROSECUTION OR CIVIL PROCEEDINGS. (GLA - 100032379) (2005).

5393_W41.R3.1_West Ealing 01/02/05 19:12 Page 1

Page 35: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Train services will be improved to and from West Ealing byproviding journey time savings and a greater variety of new destinations.

The diagram below highlights some of the journey times thatwill be possible by travelling on Crossrail services to and fromWest Ealing station.

Crossrail West Ealing station will provide:

■ Direct journey opportunities to central London, Heathrow Airport and the west

■ 4 trains per hour during peak times to central London

■ Substantial new passenger capacity and crowding relief into central London

With Crossrail operational, the total number of seats availableon trains to and from West Ealing will increase as a result of longer trains.

The service pattern will be set by the relevant railway bodiesin consultation with the train operating company responsiblefor operating Crossrail services.

To provide train paths for Crossrail services on the Relief lines,the Greenford to Paddington services will stop at West Ealingstation. A shuttle service will run between Greenford and WestEaling at a frequency of up to 4 trains per hour. Passengerswill need to change trains at West Ealing for Crossrail servicesto central London and eastern destinations.

39 minutes to Liverpool

Street*

24 minutes to Liverpool

Street

46 minutes to Canary Wharf*

31 minutes to Canary Wharf

29 minutes to Paddington*

14 minutes to Paddington

27 minutes to Heathrow Airport*

12 minutes to Heathrow Airport*

Canary Wharf

Canary Wharf 31 minutes Liverpool Street 24 minutesFarringdon 22 minutesTottenham Court Road 19 minutes Paddington 14 minutes Heathrow Airport* 12 minutes

West Ealing – From / To

Canary Wharf * 46 minutes Liverpool Street * 39 minutesFarringdon * 37 minutesTottenham Court Road * 34 minutes Paddington * 29 minutes Heathrow Airport * 27 minutes* 3 minute interchange included & assumed at West Ealing

Greenford – From / To

3 3

3

3

*5 minutes interchange presumed & included

Service ImprovementsWest Ealing

W42.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

West Ealing station at present

Typical Crossrail journey times from West Ealing & Greenford

5393_W42.R3.1_West Ealing 2/2/05 11:07 AM Page 1

Page 36: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Station ImprovementsEaling Broadway (1)

W43.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Ealing Broadway station will be redeveloped toprovide a new high quality interchange betweenCrossrail, First Great Western Link and LondonUnderground services. This will include:

■ New ticket hall south of the existing tower block

■ Upgrade of the existing station forecourt

■ Deck structure providing access to platforms 1 to 4 and links to the Central and District lines

■ Lifts to create step free access from thestreet to platforms

■ Extension of platforms 1 to 4 at theireastern end to provide for 10-car Crossrail trains

The existing ticket hall and passenger routes will stay open during the construction of the new station. The construction works will obstruct the station forecourt and requiretemporary walkways for pedestrians andstation users.

The platform level kiosks will have to berepositioned to allow the construction of theoverbridge and to provide vertical circulation.

Current proposals are to retain Villiers Houseand demolish the shop units to the south of the tower block.

Design of Ealing Broadway station will allow for any future proposals by Transport for London (TfL) for new bus facilities.

Station redevelopment

Station redevelopment

5393_W43.R3.1_Ealing Broadway 2/2/05 11:59 AM Page 1

Page 37: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Works will be coordinated from three sites:

■ Haven Green

■ Ealing Broadway station forecourt

■ South of Ealing Broadway station

All materials will be taken to and from sites by road.

The Haven Green worksite will require the relocation of anexisting bus layover space. The lorry route for this site will be from A4020 Uxbridge Road and a one-way routenorthbound on Spring Bridge Road, and then clockwisearound Haven Green.

The Ealing Broadway station worksite will occupy privateparking spaces in College Court. This worksite will beaccessed from Uxbridge Road, immediately to the west of its junction with Hamilton Road.

Mitigation measures will manage construction noise. These will include 3.6m high hoardings and the provision of noiseinsulation if appropriate.

The likely environmental effect of the proposals will be:

■ Noise impact on nearby buildings due to construction. This will be mitigated using best practicable means tocontrol noise at source. These means will be incorporatedwithin the Crossrail Construction Code.

■ There are a number of high quality mature trees surroundingthe proposed Haven Green temporary worksite. As part ofthe current proposals, the trees will be kept

There will be consultation with local authorities to help ensurethat suitable traffic management is introduced to manageimpact during construction. Consideration will be given to localauthority policies and the road network in the area to reach an acceptable solution.

Station ImprovementsEaling Broadway (2)

W44.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

THIS MAP IS BASED UPON ORDNANCE SURVEY MATERIAL WITH THE PERMISSION OF ORDNANCE SURVEY ON BEHALF OF THE CONTROLLER OF HER MAJESTY’S STATIONERY OFFICE © CROWN COPYRIGHT. UNAUTHORISED REPRODUCTION INFRINGES CROWN COPYRIGHT AND MAY LEAD TO PROSECUTION OR CIVIL PROCEEDINGS. (GLA - 100032379) (2005).

Station improvements at Ealing Broadway

5393_W44.R3.1_Ealing Broadway 2/2/05 12:01 PM Page 1

Page 38: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

The diagram below highlights some of thejourney times that will be possible by travellingon Crossrail services to and from EalingBroadway station.

Train services will be improved to and fromEaling Broadway Station by providing journeytime savings and a greater variety of new destinations.

There will be:

■ Direct journey opportunities to centralLondon, Heathrow Airport and the west

■ 10 trains per hour during peak times tocentral London

■ Substantial new passenger capacity andcrowding relief into central London

With Crossrail operational, the total number of seats available on trains to and from EalingBroadway will increase as a result of longer,more frequent trains.

The service pattern will be set by the relevantrailway bodies in consultation with the trainoperating company responsible for operatingCrossrail services.

20 minutes to

Liverpool Street

27 minutes to Canary Wharf

10 minutes to Paddington

14 minutes to Heathrow Airport*

Canary Wharf

Canary Wharf 27 minutes Liverpool Street 20 minutesFarringdon 18 minutesTottenham Court Road 15 minutes Paddington 10 minutes Heathrow Airport * 14 minutes

Ealing Broadway – From / To

*5 minutes interchange presumed & included

Service ImprovementsEaling Broadway

W45.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Typical Crossrail journey times from Ealing Broadway

5393_W45.R3.1_Ealing Broadway 2/2/05 11:59 AM Page 1

Page 39: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

To achieve the planned Crossrail service, the freight movementsto and from the existing Acton Yard will be made via a junctionsegregating the Crossrail trains, avoiding conflicting trainmovements (known as a grade separated junction). Thejunction will require the realignment of the eastbound Relief linetrack northwards into a newly constructed cut-and-cover tunnel(dive-under) allowing the lines going into the yard to cross overthe top.

The dive-under will be located between Acton Main Linestation and the eastern end of Hanger Lane.

Most construction traffic access will be from Horn Lane,opposite York Road.

Noel Road BridgeSome temporary closures of Noel Road bridge will benecessary in order to temporarily divert utilities as part of the construction works for the dive-under.

Various parts of Acton Yard will be used as worksites atdifferent stages for the construction of the dive-under andassociated work. Structural, civil and excavated materials willbe moved by road.

Access will be from Horn Lane to the North of the station. A secondary access will be provided from Noel Road close tothe bridge over the Great Western Main Line. Material for trackwork will largely be transported to the Yard by rail.

Mitigation measures will manage construction noise. These willinclude 3.6m high hoardings and the provision of noiseinsulation if appropriate.

Acton Dive Under &Freight Yard

W46.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

THIS MAP IS BASED UPON ORDNANCE SURVEY MATERIAL WITH THE PERMISSION OF ORDNANCE SURVEY ON BEHALF OF THE CONTROLLER OF HER MAJESTY’S STATIONERY OFFICE © CROWN COPYRIGHT. UNAUTHORISED REPRODUCTION INFRINGES CROWN COPYRIGHT AND MAY LEAD TO PROSECUTION OR CIVIL PROCEEDINGS. (GLA - 100032379) (2005).

Work at Acton Dive Under & Freight Yard

Acton Yard at present

5393_W46.R3.1_Acton 01/02/05 19:16 Page 1

Page 40: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Station ImprovementsActon Main Line

W47.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

More passengers are expected to use Acton Main Linestation. Improvements will ensure that suitable stationfacilities are provided.

These include:

■ A new ticket hall on the south side of the railway

■ Platform canopies

■ A mobility fully accessible accessible footbridge

■ Extended platforms at the western end of the station to take Crossrail 10- car trains

The likely environmental effect is:

■ Noise impact on nearby buildings due to construction.This would be mitigated using best practical means.These means would be incorporated within the Crossrail construction code

There are two worksites for this station.

They are:

■ South of the existing station, adjacent to the railway & bounded to the south by Horn Lane

■ West of the station on the north side of the railway,bounded to the north by Acton Yard

The western worksite is within the freight yard and will beaccessed from Horn Lane. The main worksite will be to thesouth of the railway between the station and Horn Lane. All materials will be taken to and from the sites by road.

It will be necessary to extend the worksite into the nearside of Horn Lane close to its signal – controlled junction withFriary Road for periods during the works.

A preliminary assessment has indicated that the signalphasing can be temporarily modified so that the junction can still operate satisfactorily.

Mitigation measures will manage construction noise. Thesewill include 3.6m high hoardings and the provision of noiseinsulation if appropriate.

Station redevelopment

5393_W47.R3.1_Acton 01/02/05 19:17 Page 1

Page 41: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Train services will be improved to and fromActon Main Line station by providing journeytime savings, a greater variety of newdestinations with increased passengercapacity and crowding relief for journeys into central London.

Crossrail Acton Main Line station will provide:

■ Direct journey opportunities to centralLondon, Heathrow Airport and the west

■ 4 trains per hour during peak periods tocentral London

The diagram below highlights some of thejourney times that will be possible by travellingon Crossrail services to and from Acton MainLine station.

With Crossrail operational, the total number of seats available on trains to and from Acton Main Line will increase as a result of the longer trains.

The service pattern will be set by the relevantrailway bodies in consultation with the trainoperating company responsible for operatingCrossrail services.

18 minutes to

Liverpool Street

25 minutes to Canary Wharf

8 minutes to Paddington

17 minutes to Heathrow Airport*

Canary Wharf

Canary Wharf 25 minutes Liverpool Street 18 minutesFarringdon 16 minutesTottenham Court Road 13 minutes Paddington 8 minutes Heathrow Airport* 17 minutes

Acton Main Line – From / To

*5 minutes interchange presumed & included

Service ImprovementsActon Main Line

W48.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Acton Main Line station at present

Typical Crossrail journey times from Acton Main Line

5393_W48.R3.1_Acton 2/2/05 11:11 AM Page 1

Page 42: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Crossrail trains will be stabled within Old Oak Common Depoton new Crossrail sidings. An area for the stabling sidings hasbeen identified to the north of the existing First Great Westerndepot, to stable up to 13 Crossrail trains during off-peak hoursand at night.

A carriage washing facility will be required.

Construction of the sidings will be co-ordinated from atemporary worksite within Old Oak Common Depot.

The site will be cleared, buildings erected, tracks laid andoverhead electrification and walkways constructed.

There will be additional track work associated with facilitiesused by other operators.

Works at Old Oak Common are to be carried out fromCoronation Sidings within the depot. Track works material willgenerally be brought into the site by rail, using appropriateexisting track as a railhead.

Excavated/demolition material, and civil and structural material(steel and concrete) will be transported in and out of the site by road.

The depot site is bordered to the north by Old Oak CommonLane and the Grand Union Canal. Access to the depot is fromOld Oak Common Lane. Most materials will be taken to andfrom the site by rail. Construction traffic will use the existingaccess on Old Oak Common Lane.

Mitigation measures will manage construction noise. These willinclude 3.6m high hoardings and the provision of noiseinsulation if appropriate.

Old Oak Common DepotW49.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

THIS MAP IS BASED UPON ORDNANCE SURVEY MATERIAL WITH THE PERMISSION OF ORDNANCE SURVEY ON BEHALF OF THE CONTROLLER OF HER MAJESTY’S STATIONERY OFFICE © CROWN COPYRIGHT. UNAUTHORISED REPRODUCTION INFRINGES CROWN COPYRIGHT AND MAY LEAD TO PROSECUTION OR CIVIL PROCEEDINGS. (GLA - 100032379) (2005).

Work at Old Oak Common Depot

Old Oak Common Depot at present

5393_W49.R3.1_Old Oak 01/02/05 19:19 Page 1

Page 43: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Crossrail’s trains would be electricallypowered. The existing electrification (betweenPaddington and Airport Junction) will beextended along the Great Western Main Linefrom Airport Junction to Maidenhead. This willinvolve the installation of masts and gantries to support the overhead lines andconstruction of line side sub-stations.

The overhead lines and their supports couldbe visible from areas adjoining the track,although long sections of the track are wellscreened by mature trees. The visual effectsare not likely to be significant along most ofthe route.

Electrification could require works to bridgesto provide clearance for the overhead linesand to modify parapets to ensure safety.These would range from minor works to the reconstruction of bridges. The worksproposed are described on the relevantdisplay panels.

Some of the existing diesel train services will be replaced. The electrically poweredCrossrail trains would be quieter than thediesel trains. This would have the effect ofimproving the overall operational noise levels in the rail corridor.

ElectrificationW50.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Xrail train

5393_W50.R3.1_Electrification 2/2/05 12:02 PM Page 1

Page 44: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Service ImprovementsGreat Western Corridor

W51.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

The service pattern will be set by the relevant railway bodies inconsultation with the train operating company responsible foroperating service Crossrail services.

It is hoped to provide a consistent service with a 7-days a weekat all stations Crossrail will serves.

Summary of indicative services to central London per hour: The Greenford Branch has an increased level of service in the peak hoursto compensate for withdrawal of through trains to Paddington.

Crossrail services to Central London

■ 4 trains per hour from Heathrow Airport

■ 4 trains per hour from Maidenhead

■ 2 trains per hour from West Drayton

First Great Western Link services

■ 2 trains per hour from Reading calling at Twyford,Maidenhead, Slough, Hayes & Harlington and EalingBroadway to Paddington

■ 2 trains per hour from Reading calling at Twyford,Maidenhead, Taplow, Burnham and terminating at Slough

Maidenhead

Taplow

BurnhamSlough

Langley

Iver

West Drayton

Heathrow

Hayes & Harlington

Southall

West Ealing

Ealing Broadway

Hanwell

Acton Main Line

44 4

6 24104

810

4

444

Station Peak Off Peak

Crossrail Other Services Crossrail Other Services

Maidenhead 4 2 4 2

Taplow 4 2

Burnham 4 2

Slough 4 2 4 2

Langley 4 4

Iver 4 4

West Drayton 6 4

Heathrow Airport 4 4 Heathrow Express 4 4 Heathrow Express

Hayes & Harlington 10 2 8 2

Southall 8 8

Hanwell 2 2

West Ealing 4 4 Greenford 4 2 Greenford

Ealing Broadway 10 2 8 2

Acton Main Line 4 4

5393_W51.R3.1_Gt Western 01/02/05 19:20 Page 1

Page 45: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

There is an existing Scottish and SouthernPower (SSP) 132kV overhead power line that runs in a north south direction across the Great Western Railway and Thorney ParkGolf Course.

As part of the works, overhead electrificationwill be installed on the railway, but there isinsufficient clearance between the proposedoverhead electrification and existing overheadpower lines. Therefore, the existing overheadpower lines must be raised.

To raise the power lines two new masts will be installed, either side of the current line inthe area immediately south of the railway, andnorth of the pond. These masts will be approx20m high and have a base area of 4 x4m. The cables will then be restrung between theexisting pylons and over the masts, raising the cables to provide the required clearance.The works will have to take place during thesummer when electricity usage is lower andthe power can be isolated.

Thorney Park Golf CourseW55.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

THIS MAP IS BASED UPON ORDNANCE SURVEY MATERIAL WITH THE PERMISSION OF ORDNANCE SURVEY ON BEHALF OF THE CONTROLLER OF HER MAJESTY’S STATIONERY OFFICE © CROWN COPYRIGHT. UNAUTHORISED REPRODUCTION INFRINGES CROWN COPYRIGHT AND MAY LEAD TO PROSECUTION OR CIVIL PROCEEDINGS. (GLA - 100032379) (2005).

Thorney Park Golf Course

5393_W55.R3.1_Thorney GCourse 2/2/05 11:57 AM Page 1

Page 46: W1.R3.1 Maidenhead Bridge - Crossrail Learning Legacy · 2019-11-25 · W1.R3.1 Crossing the Capital Connecting the UK Email: helpdesk@crossrail.co.uk Helpdesk 0845 602 3813 24 hours

Service ImprovementsHeathrow Airport Access (2)

W56.R3.1

Crossing the Capital Connecting the UK

Email: [email protected]

Helpdesk 0845 602 381324 hours a day, 7 days a week

Four worksites will be used for theconstruction of the flyover.

These are at:

■ Stockley Close

■ H G Timber

■ Allpoint Packaging

■ Dagenham Motors

Material for the viaducts and transferstructures will be taken to and from theworksites by road. Materials for track works will be partly delivered by rail.

The Stockley Close worksite will be located east of the A408 Stockley Road, with access from Stockley Close. The HG Timber and Allpoint Packagingworksites will be accessed via Swallowfield Way and Rigby Lane. The Dagenham Motors worksite will beaccessed directly from Dawley Road.

Mitigation measures will manage construction noise. These will include 3.6m high hoardings and the provision of noise insulation if appropriate.

5393_W56.R3.1_Heathrow 01/02/05 19:22 Page 1