TW@ESI 22 nd November 2015 Hope that you and all your families had a good weekend .. The following is an update of what was achieved during the past week and a forecast of the next week By now we have most of our employees on this discussion group except Ludovic, Clinton, Lino, Manuel, Victor, Brian, Rodney, Daniele, Pawlu, Michael ... Please... All of you.. Join!! John can you issue an internal memo to your people asking them to join in

Transcript of TW@ESI 22nd November 2015

Page 1: TW@ESI 22nd November 2015

TW@ESI22nd November 2015Hope that you and all your families had a good weekend .. The following is an update of what was achieved during the past week and a forecast of the next week

By now we have most of our employees on this discussion group except Ludovic, Clinton, Lino, Manuel, Victor, Brian, Rodney, Daniele, Pawlu, Michael ... Please... All of you.. Join!! John can you issue an internal memo to your people asking them to join in

Page 2: TW@ESI 22nd November 2015

Projects and deadlines• We are presently executing a number of fast track projects

and I would like to summarise the major ones them as follows:– 14_081 - Siggiewi Primary School BMS- Most of the 3rd fix

installation is now completed and we now need to proceed and commission and finish all we have to finish by first week of December

– 13_076 - MDH Block D Ext MAU- Panel termination to be completed at the earliest possible date and IO testing has commenced and advanced by now- We have reached a target of some form of closed loop control on the AHU – Well done to all of you. We also need to have most testing and commissioning works done by the end of November 2015.

Page 3: TW@ESI 22nd November 2015

Projects and deadlines– 15_008 - Aurobindo PH02 BMS- The panel has been delivered and

assembled on site with everyones good will and effort. We need to plan the programming and development of the system which is now extremely urgent. We have the first phase of handover which is to be done by 13th November 2015... This date has been delayed by the contractor – so my message is to press on doing software until the contractor starts meeting the deadlines

– 14_089_MGA_DAC_PA_VA – needs to be completed by 20th November 2015 – including PA-VA- We have managed to commission the PA/VA and are also snagging the 2 floors for DAC

– 14_027_SCM_FTIS- needs to be completed by 27th November 2015- the sooner the better!!

– 13_070 SCM Lagoona – needs to be completely commissioned by 15th December 2015

Page 4: TW@ESI 22nd November 2015

DesignLast Week• Siggiewi – Created Tag Refs for Ltg Fixtures & Heaters, printed Ltg Tags,

remaining printing of Heaters Tags• Life Sciences – SCP – Concluded Panel Design & Control Description, submitted

& Approved, ordered Material & received it, released for Panel Build• OTM – 3 Work Orders – met SSa, tentative completion – end of Nov.• Research – Looked into Rittal trunking, to test on Intercontinental• Intercontinental - Panels Sizing• SCM Lagoon – sized additional DDC expansion to use In-stock EnclosureNext Week• Siggiewi – remaining printing of Heaters Tags• FM Env – Implement Panel Drawings As Built feedback• Siggiewi – Implement Panel Drawings As Built feedback• SCM Lagoon – start on Panel Mods / DDC expansion

Page 5: TW@ESI 22nd November 2015

Installation

• Last week we were focused on– Life Sciences Commissioning– MAU Panel terminations and IO testing– MGA/FTIAS DAC systems

• Next week– MGA/FTIAS DAC installation and commissioning – Life Sciences Commissioning– MAU Panel terminations

Page 6: TW@ESI 22nd November 2015

Panel Build• Next to be done is Siggiewi DDCs- we need to

focus on finishing off these to move on to the panel for the meters of Siggiewi too

• Also we have to finish off the FM Environmental panels

• We are now building Life Sciences Smoke extraction system panel

Page 7: TW@ESI 22nd November 2015

Mater Dei

• The team at MDH is working full blast to assist the MAU installation and a lot of effort is being done in order for ESI to succeed

• The team at Mater Dei are working hard to fill in the missing people and hopefully, by the month of November 2015, we should settle on our new complement.

Page 8: TW@ESI 22nd November 2015

Development and Commissioning• We have done large important steps on finishing off the Parliament we need

to get the documentation out of the way too to avoid us going time and time again on site

• We finalised on the DAC for FTIAS – we need to close off on the pending doors by 27/11 or earlier... The earlier the better!!

• 14_089_MGA_PA_DAC- commissioning needs to be completed by the next week

• The last issues on the DAC for SCM PH2• SCM PH2 needs also some attention on the tagging purchase order for the

BMS- CVA is to work on this• Hilton Hotel Guest room AHU project the drive is now here and we need to

close off the project• The Bosch HSDK interface is well advanced and we awaiting the client• The PLC/SCADA team have been working on the IO testing of MAU

Page 9: TW@ESI 22nd November 2015

Development and Commissioning• There is huge amount of work to do with the commissioning of Life

Sciences 12_043!! We are on a very tight time frame here and we need to dig really deep and perform

• OTM urgent jobs and snags were also done in the last weeks• Aurobindo is another important and, now, fast track project We are

awaiting the main contractor for us to start commissioning the Priority A items

• Another project that needs attention is CCA Villa ... We need to see to snags and convince the client on the system we have installed- LVA to look into issues of intruder alarm too.

• The Siggiewi Primary school project is an extremely urgent project which needs to be completed and commissioned by first week of December 2015. There is a lot of commissioning work to be done and we need to work efficiently to make the commissioning time as short as possible

Page 10: TW@ESI 22nd November 2015

Sales and Business Development

• We have been working on Home automation offerings and quotes for variations for existing projects.

• We are working on a metering solution for commercial outlets as well as new AHU control system for Hilton Hotel

Page 11: TW@ESI 22nd November 2015

• I have asked all of you involved in projects, what have you learnt? How can we improve? So that next time we do things better!! Please give this attention so that we can start documenting a list of lessons we have learned from past projects and try to do things better the next time round

Page 12: TW@ESI 22nd November 2015

Team ESI• I urge you all to follow this blog and keep up to date with what is

happening at ESI • I await all your feedback on all the ESI discussions – without this

feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment

• Please urge and assist all you colleagues to have a linkedin profile and join this discussion group

• Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for

• Send me pictures of all your work and what you are up to , so that I may create some videos on this blog- Julian, Claudio, Clifton, Silvio, and Clinton.... Well done!!

Page 13: TW@ESI 22nd November 2015

Team ESI

• Lets all work to get the work done on time, on budget and to the required quality

• We need to communicate, pull the rope in the same direction to make our projects a success and profitable

• HAVE A GOOD WEEK