TW@ESI 10 th April 2016 Hope that you and all your families had a good weekend. The following is a record of what was done during the past week and a forecast of the next week.....

Transcript of TW@ESI 10th April 2016

Page 1: TW@ESI 10th April 2016

TW@ESI10th April 2016Hope that you and all your families had a good weekend.

The following is a record of what was done during the past week and a forecast of the next week.....

Page 2: TW@ESI 10th April 2016

A General Note before we startDesign and Installation office have been transferred and we have now also transferred the server and IT rack (A Big thank you to Julian and Clifton who assisted on Saturday to do this with IBIS). The following are the next steps a) Installation of Glass door in show room and in

reception area upstairsb) Intercom installation on new door c) Lighting, power, data installation in design and

commissioning offices- target for these to be completed and all of us to move back to our places – by End April 2016

Page 3: TW@ESI 10th April 2016

Projects and deadlines

• 15_033_Westin_7-AHU- With everyone’s effort we have managed to change over the Banquet hall AHUs- not only but start these remotely from the engineering PC- Next target- finish all Testing and commissioning works by 15/4

• 13_070_SCM Lagoona_Pump room- We have pulled most cables and need to now start terminations on site... This, too, is going to become a hot project- All terminations possible are to be completed ASAP

• 14_001_Fadalah-There are some snags here which are to be resolved (by others)

Page 4: TW@ESI 10th April 2016

Projects and deadlines• 15_044_Hilton_Restaurant_Kitchen_AHU and

15_034_Hilton_Calorifier_Monitoring. We have managed to start up all equipment- there will be a whole rush now to commission basic automatic controls for temperature controls on AHUs and speed controls on the pumps

• Projects 12_026 SCM Buildings 02, 03, R3 & R4 and 12_027 Security Systems Parliament- are still pending projects.

Page 5: TW@ESI 10th April 2016

Projects and deadlines• 15_008 - Aurobindo PH02 BMS- We have made

progress on commissioning here- we will also soon need to come up with a plan and target date here.

• 13_052 New offices- Now a target is – Complete all installations and everyone to move back to their places by end of April 2016

Page 6: TW@ESI 10th April 2016

DesignLast week• MDH MAU –Prints 5x A4 copies for Mekanika• ESI Offices – Patched SAA back into Office/Move

Design office• OVt New Residence 15_038 – successfully

completed 1st run of Ltg P&Ids / started BMS P&IDs

Page 7: TW@ESI 10th April 2016

DesignNext Week:• Siggiewi - conclude As Built feedback with CCI &

start implementing updates• OTM – meet Silvio & start on SAS000756• OVt New Residence 15_038 – continue on BMS

P&IDs / start on Plans

Page 8: TW@ESI 10th April 2016

InstallationPast week:– Completed all cable pulling and installation of field

devices at Hilton. Completed all terminations at Hilton 15_034 and 15_044

– Manual start up of Hilton Panels– Started commissioning at Westin– Continued with terminations at SCM Lagoon– Pulled Data and telephone cables at ESI offices /

Started marking data, power outlets etc

Page 9: TW@ESI 10th April 2016

InstallationNext week:– Panel modifications at SCM Lagoon– Install field devices at SCM Lagoon– Testing of field devices I/O’s at Hilton– Complete commissioning at Westin– Remove old BMS panel at ESI offices – First, second and third fix at ESI offices– Start painting at ESI offices

Page 10: TW@ESI 10th April 2016

Panel Build• modifications of SCM Lagoona• IO testing at Hilton

Page 11: TW@ESI 10th April 2016

Mater DeiThe following are the tasks being worked on and planned for the next weeks• FIELD DEVICES CHECKS FROM SITE E01-CC1, E02-CC1, EP1-CC1• COORDINATED FRIDGE / FREEZER TEST BETWEEN ESI AND BIOMEDICAL - APRIL• QUARTERLY REVISED BMS DOCUMENTATION QUARTERLY BACKUP• BMS Field Devices PPM -A01-CC1. AP1-CC1 / A03-CC1. A03-CC3 / A02-CC1.

A02-CC2, AP2-CC1• Coordinated Checks of Alarms from 3rd party devices A01-CC1, AP1-CC1, A02-

CC1, A02-CC2, AP2-CC1, A03-CC1, A03-CC3 and Various REF Equipment• PANEL THERMOGRAPHICAL IMAGES A01-CC1, AP1-CC1, A02-CC1, A02--CC2,

AP2-CC1, A02-CC1, A03-CC3• MCC PANEL CHECKS C01-CC1, CP1-CC1. C01-CC2, C02-CC1, C03-CC1, C04-CC1,

D05-CC1, C05-CC1, C07-CC1, C07-CC2, C08-CC1, CP2-CC1 CF1-CC1• MCC PANEL CHECKS A01-CC1, AP1-CC1. A02-CC1, A02-CC2, AP2-CC1, A03--CC1,

B01-CC1, BP1-CC1, B02-CC1, BP2-CC1, B03-CC11• WEEKLY UPDATE OF ANTI-VIRUS ON ALL BMS STATIONS• WinCC upgrade HMI D05-CC1 /D06-CC1 / D07-CC1

Page 12: TW@ESI 10th April 2016

Development and Commissioning• We have done large important steps on finishing off the

Parliament we need to get the documentation out of the way too to avoid us going time and time again on site- IT IS NOW A PRORITY AND WE NEED TO GET A COMPLETION

• The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION

• Life Sciences- We have also concluded with Training now... Documentation and some snags are pending

• SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this

• The Bosch HSDK interface is well advanced and we awaiting the client

Page 13: TW@ESI 10th April 2016

Development and Commissioning

• OTM urgent jobs and snags were also done in the last weeks• Another project that needs attention is CCA Villa ... There are

still some snags to be addressed –intruder alarm integration• Oncology 14_066- We have done most of the work here and

are waiting from Panta on this• The Siggiewi Primary school project – we need to close off

with snags and documentation here• Aurobindo we are proceeding with software development

and we have done quite some progress – we are also now commissioning this project- we will need to come up with a plan here.

Page 14: TW@ESI 10th April 2016

Development and Commissioning• 16_004_Microbiz_PW_Otis_Interface- We are

presently working on a task list and POW as well as setting up the test rigs

Page 15: TW@ESI 10th April 2016

Sales and Business Development

• We have been working on quotes for OTM (some of which are quite large) , a quote for CCTV at Enemalta and quotes for variations for existing projects.

• Last Friday we also sponsored and attended a SEWCU event on Energy Efficiency and Water Conservation Measures for non-SMEs ... Well done to Trevor and Karolina on organising and working on this event

Page 16: TW@ESI 10th April 2016

• More lessons to follow shortly – this next week

Page 17: TW@ESI 10th April 2016

Team ESI• I urge you all to follow this blog and keep up to date with

what is happening at ESI • I await all your feedback on all the ESI discussions –

without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment

• Please urge and assist all you colleagues to have a linkedin profile and join this discussion group

• Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for

Page 18: TW@ESI 10th April 2016

Team ESI

• Lets all work to get the work done on time, on budget and to the required quality

• We need to communicate, pull the rope in the same direction to make our projects a success and profitable

• Have a good week