Trulift presentation
-
Upload
rmd-kwikform-ltd -
Category
Engineering
-
view
159 -
download
0
description
Transcript of Trulift presentation
![Page 1: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/1.jpg)
Tru-lift: summary Self lifting, core forming system
Formwork: Tru beams
• Faced with 19mm high quality plywood
• Backed by twin steel channel walers
Proven, robust and efficient
Designed for:
• Speed: forming up to 5m in a single lift
• Minimising construction cycle times
• Maximising safety
![Page 2: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/2.jpg)
System characteristics
• 4.1 m Stroke on long cylinder.
• 0.9m Stroke on small extension cylinder.
• Power supply 230v single phase 60 Hz.
• Maximum allowable working load on form support brackets = 155kN.
• Maximum allowable working load on cylinder brackets = 289kN.
• Taper Ties = 150kN (with FOS 2:1).
• Platform loading = 1.2kN/m2.
![Page 3: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/3.jpg)
Features & Benefits (1) • Complete system raised during the
lifting cycle MAXIMISING SYSTEM EFFECTIVENESS
• All sizes of core walls can be accommodated MAXIMISING SYSTEM VERSATILITY
• Controlled lifting of equipment using hydraulics ELIMINATING CRANAGE & MAXIMISING SAFETY
• Fully boarded working platform ENSURES SAFE WORKING AREA
• Trailing platforms allow access to previous pours MAXIMISING EFFICIENCY, ELIMINATING THE NEED FOR INDEPENDENT ACCESS SYSTEMS
![Page 4: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/4.jpg)
Features & Benefits (2)
• Minimal number of components ensures quick and easy erection MAXIMISING CONSTRUCTION CYCLE TIMES
• Unique striking corners QUICK AND EASY RELEASE OF FORMWORK
• Concrete placement from top platform MAXIMISING SAFE WORKING PRACTICES
• Reusable tapered tie system MINIMISING HARDWARE COSTS
• External panels supported from overhead beams SAFE ACCESS FOR PANEL CLEANING AND REBAR FIXING
![Page 5: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/5.jpg)
Raised position
• Forms fully extended to
subsequent pour position.
• Wall support brackets bolted to inserts cast in previous pour.
• Weight of system transferred to wall support brackets.
![Page 6: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/6.jpg)
Setting position
• Bolts securing cylinder brackets to wall
removed.
• Cylinder and bracket retracted and bolted to inserts cast in previous pour.
• Internal forms cleaned and reset into position.
• External forms cleaned whilst retracted.
![Page 7: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/7.jpg)
Pouring position
• External forms rolled back into
pouring position.
• Ties and external yokes installed.
• Concrete placed through hinged hatches on top platform.
![Page 8: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/8.jpg)
Safety features
![Page 9: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/9.jpg)
Safety: handrails
Full perimeter handrails for areas, including:
• Upper platforms.
• Lower platforms.
• Internal hanging platforms.
![Page 10: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/10.jpg)
Safety: Perimeter Screen
• Fully enclosed system.
• Welded loops for securing screen to perimeter framework.
• Screen:
• Reinforced PVC sheeting.
• Strong and puncture resistant.
• UV stabilised.
• Fully printable.
• Ideal for advertising.
• Optional.
![Page 11: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/11.jpg)
Safety: enclosed ladders
Full ladder access between platforms.
• Easy and safe accessibility at all times.
![Page 12: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/12.jpg)
Safety: inbuilt stair access
• Modular stair access tower system.
• Supported off internal platforms.
• Length of tower determined by
floor level egress/ingress required.
• Optional.
![Page 13: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/13.jpg)
Safety: Working Platforms
Safe, level working environment created using timber beams and plywood.
• Minimises trip hazards.
• Fully covered work areas.
• Ply hatches for concrete placement.
![Page 14: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/14.jpg)
Outer Corner Assembly
• External corners easily tied between
yoke blocks, using fast thread ties.
• Yoke blocks bolted to horizontal channel walers.
![Page 15: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/15.jpg)
Inner Corner Assembly
Corner pin used to strike internal forms:
• Drives through offset holes and reversed for ‘reset’.
![Page 16: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/16.jpg)
Trolley
• Designed to roll along lower flange of
overhead beam.
•
Supports the external form using threaded rod
for vertical adjustment.
•
Attached to brackets bolted to Tru Beams.
![Page 17: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/17.jpg)
Internal form hanging bracket
• Adjustable form support bracket head
and clamp plates bolted into wall
support frame.
• Facilitates the connection to the
overhead primary beam.
![Page 18: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/18.jpg)
Internal Corners
• Rigid, flexible and strippable corners
(depending on core profile).
• Where possible, flexible corners used in
conjunction with corner pins.
• Eliminates need to dismantle forms.
![Page 19: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/19.jpg)
Wall Bracket Assembly
• Brackets bolted into inserts cast in
previous pour.
• Connected to wall support frame,
supporting formwork once in lifted
position.
• Finite adjustment for levelling using
Threaded Bar (if required).
![Page 20: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/20.jpg)
Jack Bracket
• Supports and houses hydraulic cylinder.
• Bolted into inserts cast in previous pour.
• Supports the formwork system during
lifting sequence.
• Remain fixed to hydraulic cylinder
during retraction and relocation.
![Page 21: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/21.jpg)
Walkway Bracket
• Bolted to overhead beam system.
• Hanging below the bottom of the
formwork system.
• Facilitates retracting of forms, steel
reinforcement fixing and cleaning of
forms.
• Designed to be used in conjunction with
timber beams and plywood.
• Creating a level and hazard free working
platform.
![Page 22: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/22.jpg)
Internal Trailing Platform
• Supported from overhead steel beams.
• Provide safe access for operatives.
![Page 23: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/23.jpg)
Ducab EHV, UAE
155m
![Page 24: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/24.jpg)
Ducab EHV, UAE
![Page 25: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/25.jpg)
340 N. LaSalle Chicago, IL.
60 Floors
![Page 26: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/26.jpg)
J.W. Marriott Hotel Indianapolis, IN.
33 Floors
![Page 27: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/27.jpg)
The Revel Atlantic City, N.J.
65 Floors
![Page 28: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/28.jpg)
Queen City Square Cincinnati, OH.
47 Floors
![Page 29: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/29.jpg)
Trump Tower Chicago, IL.
95 Floors
![Page 30: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/30.jpg)
The Echelon Las Vegas, NV.
![Page 31: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/31.jpg)
Ducab VCV tower, Dubai - UAE
Project: Ducab-HV (400kV) Cable Factory - 1st Facility of it’s kind - Fast Track (12 month program) Sector: Industrial Details: RC Tower - 24 x 22m footprint - 44 storey – 153m high - Unique – large core structure, large openings, changing wall thickness Contractor: Khansaheb Civil Engineering
![Page 32: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/32.jpg)
Ducab VCV tower
![Page 33: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/33.jpg)
Ducab VCV tower
![Page 34: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/34.jpg)
Shutter assembly
Pre-assembly of many components greatly reduces the set up time onsite and can be started well in advance of the site being ready to install the formwork.
![Page 35: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/35.jpg)
Shutter assembly Pre-assembly of the formwork is carried out using fabrication jigs and can also be done well in advance of the actual site set up (on or off site).
![Page 36: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/36.jpg)
Shutter assembly
In some cases, by prior arrangement, the fabrication of the formwork panels can be assembled off site, then transported to site fully assembled and ready to install. This can save space on congested work sites.
![Page 37: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/37.jpg)
Shutter assembly
Larger panels that are too big to be transported by road can be assembled on site.
![Page 38: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/38.jpg)
Set Up
The formwork panels are then prepared and oiled prior to lifting into position.
![Page 39: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/39.jpg)
Set Up
The Internal Rigid Boxes are installed first and fixes the internal shape/dimensions of the core – this is a unique feature of the Tru-lift Self Climbing Formwork System.
![Page 40: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/40.jpg)
Set Up The Steel Walers are easily spliced to any length enabling very large panels such as this 4.2m high x 20m long panel to be fabricated and lifted into position in one piece.
![Page 41: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/41.jpg)
Set Up
![Page 42: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/42.jpg)
Set Up
![Page 43: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/43.jpg)
Set Up On completion of the rebar and formwork installation the steel grid beams are positioned.
![Page 44: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/44.jpg)
Set Up
![Page 45: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/45.jpg)
Set Up
Bolts and Grid Plates are used for the connections between the grid beams, the Formwork and Hydraulics.
![Page 46: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/46.jpg)
Set Up Top Decking and Edge Protection are added upon completion of the Grid Beam placement.
![Page 47: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/47.jpg)
Operation The Tru-lift Self Climbing System is operated from a central control room. Each of the Hydraulic Rams can be controlled individually or collectively with the flick of one switch.
![Page 48: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/48.jpg)
Operation The Tru-lift Self Climbing System is generally mounted to the walls of the first pour. However if the customer would prefer, it can be designed to form the first pour and push off the base slab as was done on this particular project.
![Page 49: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/49.jpg)
Operation The Tru-lift Self Climbing System is truly unique in that the whole system is jacked in one Jack stroke, eliminating the need for resetting the hydraulics throughout the lift saving a great deal of time. On this particular project the 3.8m typical floor height was easily accommodated by jack stoke and capacity.
![Page 50: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/50.jpg)
Operation The Tru-lift Self Climbing System is to be used to form the first pour. The Hydraulic Rams should be prevented from movement by setting brackets around the bottom of it into the base slab.
![Page 51: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/51.jpg)
Operation
External Hanging access brackets are added on the initial lifts until the desired length is achieved.
![Page 52: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/52.jpg)
Operation
Suspended access scaffolds can also be accommodated as seen here from below.
![Page 53: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/53.jpg)
Operation
![Page 54: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/54.jpg)
Operation
Rebar cages can be prefabricated and craned into position to speed up the cycle times if desired.
![Page 55: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/55.jpg)
Operation When the setup is complete the Tru-lift self climbing system is operated completely independently, without the need for a crane to handle the Formwork and easily out performs traditional Jump form systems.
![Page 56: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/56.jpg)
Operation The contractor using the Tru-lift System on this particular project was able to achieve a pour cycle of just 48 hours with 1,100m2 of formwork being jacked in 20-30 minutes.
![Page 57: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/57.jpg)
Dismantle
Upon completion of the structure the system is dismantled in the reverse order to that of the erection. The Hanging access platforms are removed first.
![Page 58: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/58.jpg)
Dismantle Followed by the external formwork.
![Page 59: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/59.jpg)
Dismantle Next the top decking is systematically removed.
![Page 60: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/60.jpg)
Dismantle
![Page 61: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/61.jpg)
Dismantle
The final step is the removal of the internal formwork and wall brackets.
![Page 62: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/62.jpg)
Methods
Detailed method statements are provided for assembly, erection, running and dismantle of the system. Site supervision is provided at all stages of the contract.
![Page 63: Trulift presentation](https://reader034.fdocuments.in/reader034/viewer/2022042814/554a2023b4c90507558b5ac9/html5/thumbnails/63.jpg)
RMD Australia - Tru-lift Self lifting, core forming system