TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management...

53
TransCanada’s Risk Management System for Pipeline Integrity Management Warren Peterson Louis Fenyvesi CORS March 19, 2009

Transcript of TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management...

Page 1: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

TransCanada’s Risk Management System for Pipeline Integrity Management

Warren Peterson

Louis Fenyvesi

CORS

March 19, 2009

Page 2: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

2

Pipeline Risk & Integrity Management Enabler

The PRIME project was started in 1998 to develop a Risk Management process for Pipeline Integrity and the infrastructure necessary to support it.

Through the PRIME project, the following items and processes were developed/acquired:

• Facilities and integrity data model.

• System wide facility data.

• A GIS system.

• PRIME Process: The Risk Management and Decision Analysis process used to develop TransCanada’s Integrity Programs.

• PRIME Risk Models: The Hazard, Consequence, Risk Assessment and Decision Analysis Models used to execute the PRIME Process.

Page 3: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

3

PRIME Process

The PRIME Process is a risk-based decision making process used to develop and evaluate the majority of maintenance programs:

• MFL In-Line Inspections

• Hydrostatic Tests

• Condition Monitoring Investigations & Repairs

• Discrete Pipe Replacement/Recoating.

Page 4: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

4

Risk-Based Program Development

PRIME Process Flow Diagram

UnacceptableNot EnoughInformation

Analyze Risks

1. Hazard Identification2a. Consequence Analysis

2b. Hazard Frequency Analysis3. Risk Analysis

Audit Results

Data Management

Risk ControlCondition Monitoring Evaluate RiskAcceptability

Pipeline Surveillance

StakeholderParticipation

Acceptable

Page 5: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

5

Decision Making Framework

PRIME contains a framework for evaluating risk acceptability that provides:

• Common Goals

• Common Measures

• Common Decision Criteria

…to facilitate decision making

Page 6: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

6

Pipeline Maintenance Goals

A Risk Management methodology should flow from the goals of a company’s pipeline maintenance program.

Decision Criteria should reflect and be directly traceable to the company’s goals.

Page 7: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

7

Pipeline Maintenance Goals

TransCanada’s Pipeline Maintenance Goals include:

1. Provide an adequate level of safety to the public and employees.

2. Maintain lowest long-term operating and capital costs, except where there is conflict the above goal.

…among others

Page 8: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

8

Measures of Safety

Goal: 1. Safety of Public and Employees

Measure: Individual Risk

Individual risk is a measure of the total risk faced by a risk receptor from all potential risk sources measured as an annual risk of fatality.

Page 9: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

9

Measures of Safety - Individual Risk

Individual Risk can be calculated both for known population and generically.

• Specific population data can quickly become ‘out-of-date’.

• Generic or ‘inherent’ individual risk can be used to establish and maintain a ‘baseline’ level of safety for a pipeline.

Page 10: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

10

Measures of Safety -Inherent Individual Risk

‘Inherent’ individual risk assumes constant occupation by a single individual on top of the right-of-way.

Main variable is failure frequency.

Each meter of ROW is evaluated independently.

Individual Risk is calculated for each meter (Risk Source) of P/L relative to a specific point on the ROW (Risk Receptor).

Page 11: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

11

48”

36”

Point on ROW under analysis

Pipe beyond these points do not have an

effect on the point under evaluation.

∫+

××=X

X

xFatalityIgnitionx dxRRPPFRiskIndividual ))',((

The sum of the risk from each meter of pipe highlighted gives

the Individual Risk for the point on the ROW below.

Page 12: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

12

Safety Decision Criteria

Goal: 1. Safety of Public and Employees

Measure: Individual Risk

Decision Criteria: MIACC Land Use Guidelines

MIACC (Major Industrial Accidents Council of Canada) published risk-based land use guideline in the early 1990’s.

Land uses types have been interpreted in the context of pipeline class location definitions.

Page 13: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

13

Class I Equivalent Class II

EquivalentClass III & IV

Equivalent

Risks exceeding the risk acceptance threshold for the pipeline’s

corresponding class must be reduced to a level below that threshold.

Page 14: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

14

Safety Decision Criteria

Goal: 1. Provide an adequate level of safety to the public and employees.

Measure: Individual Risk measure of the annual risk of fatality. Inherent risk and risk to known receptors.

Decision Criteria: MIACC Land Use Guidelines define ‘an adequate level of safety’.

Page 15: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

15

Financial Measures

Goal: 2. Lowest long-term operating and capital costs

Measure: ‘Value Ratio’ VR

Key to achieving low long-term costs is considering both the cost of pipeline incidences and the cost to mitigate risk.

VR generated on a project by project basis.

VR = Risk Reduced ($) / Cost of Project ($)

Page 16: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

16

Financial Measures -Calculating ‘Risk Reduced’

A pipeline failure can generate a variety of consequences.

• Consequences are measured as:

• A short-term direct financial loss.

• A longer term indirect financial loss.

• Losses to the company or society that are not financial in nature.

• In order to produce the VR measure, non-financial losses need to be mapped to an equivalent dollar loss

Page 17: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

17

Financial Measures -Calculating ‘Risk Reduced’

Major consequence categories are:

• Direct Financial Impact

• Cost of repair.

• Purchase of linepack.

• Indirect Financial Impact

• Fines

• Proving the integrity or ‘fitness for service’ of the affected pipeline.

• Longer term impact to the company’s image or ability to do business.

• Community or regulatory relationship.

Page 18: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

18

Financial Measures -Calculating ‘Risk Reduced’

Major consequence categories are:

• Customer Impact

• Financial loss incurred by the customer

• Through-put restriction

• Impact to Firm Service contracts

• Third-Party Impact

• Property Damage

• Court Settlements

• Environmental Impact

• Fines and Penalties

• Site Restoration Costs

Page 19: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

19

Financial Measures -Calculating ‘Risk Reduced’

The total consequence of a pipeline failure is the sum of the consequences calculated under the previous five categories.

The total failure frequency of a pipeline is the sum of the annual per meter failure frequencies contributed by each applicable hazard.

Risk = Total Consequence X Total Failure Frequency

Units of $/m*yr.

Page 20: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

20

Financial Measures -Calculating ‘Risk Reduced’

The risk reduction benefit of a pipeline maintenance project requires risk to be calculated for both the ‘as is’ or base case and the ‘after maintenance’ or remaining risk case.

∑ ∑= =−=

m

i mainingti

n

t Baseti RRReducedRisk1 )(Re,1 )(, ))((

m is the affected length of pipe.

n is the number of years over which

the project will have a measurable

benefit.

Page 21: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

21

Financial Decision Criteria

Goal: 2. Maintain lowest long-term operating and capital costs, except where there is conflict with the first two goals.

Measure: VR

Decision Criteria: VR’s greater than one represent projects whose cost is justified based on an expectation of future aversion of loss.

Page 22: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

22

Example

Evaluating a 35km NPS 36 Class I pipe.

Analysis Steps:

• Individual Risk is calculated and evaluated against acceptance criteria.

• Projects are identified that mitigate safety risk to an acceptable level.

• Project with most beneficial VR implemented.

Page 23: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

23

Individual Risk Example

1.00E-08

1.00E-07

1.00E-06

1.00E-05

1.00E-04

1.00E-03

1.00E-02

1.00E-01

1.00E+00

0 5000 10000 15000 20000 25000 30000 35000

Chainage

Individual Risk

These areas exceed

safety criteria and

require mitigation.

Page 24: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

24

Pipeline Maintenance Options Cost Risk Reduction IPV

Hydrostatic Test $900,000 $5,300,000 5.89

Traps + In-Line Inspection + Digs $2,000,000 $2,300,000 1.15

Pipe Recoating (~5 km) $5,100,000 $2,200,000 0.43

Pipe Replacement (~5 km) $8,700,000 $2,500,000 0.29

Example - Alternative Analysis

The following four options were identified as being able

to reduce the safety risk to an acceptable level.

The VR analysis identifies hydrostatic testing as

providing the greatest risk reduction value.

Page 25: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

25

Risk Based Decision Framework

This framework for quantitative risk-based decision making provides:

• Consistent decision making

• Clear relationship between company goals, risk measures, and decision criteria

• Prioritizes safety

• Facilitates alternative analysis

Page 26: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

26

Risk Analysis - Hazard Identification

Focused on hazards that are a relevant to the TransCanada system, including:

• Corrosion

• Mechanical Damage

• Stress Corrosion Cracking

• Geotechnical - Slope Movement

Page 27: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

27

Corrosion Management

The primary method for addressing the hazard of external corrosion is through MFL In-Line Inspection and Defect Management

• Majority of the system can be inspected

• ILI provides the most accurate information on External Corrosion of any available technique

• MFL data is still an indirect measurement

Page 28: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

28

Standard Industry Practice

Standard industry practice is to excavate MFL defects based on deterministic depth and failure pressure criteria. TransCanada’s are:

• Depth > 70%

• Failure Pressure < 1.25(MOP)

Deterministic criteria implicitly accounts for uncertainty by increasing conservatism

Goal is to restore original design factor and prevent pipeline incidents

Page 29: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

29

1.25 x MOP

MOP

0

1

2

3

4

5

6

7

8

9

10

0 50 100 150 200 250 300 350 400

Defect Length (mm)

Defect Depth (mm)

Deterministic Criteria

Pass

Fail

Page 30: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

30

Probabilistic Criteria

1.25 x MOP

MOP

0

1

2

3

4

5

6

7

8

9

10

0 50 100 150 200 250 300 350 400

Defect Length (mm)

Defect Depth (mm)

Area = Failure Probability

Page 31: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

31

Calculating Defect Failure Probability

Defect Risk Management Process:

• Probabilistically quantify:

• depth error

• length error

• growth rate

• As applicable

• Identify failure probability through simulation

• Simulation Size Depends on Desired Accuracy

• Assess defect acceptability (Risk Management Process)

{ })Erri i(P(L ,AD (L,W))-P M)1

( ) I /N

i

p Rupture N>

==∑

Page 32: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

32

MFL Data – Depth Uncertainty

Depth Accuracy: +/- 10% 80% of the time

• Equivalent to a normal distribution with:

• Mean: 0%

• Standard Deviation: 7.8%

• More complex corrosion:

• Standard Deviation: 11%

• As more data is collected for a particular line, these statistics are updated

Page 33: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

33

MFL Data – Peak Depth Accuracy

0%

25%

50%

75%

100%

0% 25% 50% 75% 100%

MFL Reported Peak Depth

LPIT Measured Peak Depth

Forecast: Fitted Depth Error Distribution

0

1000

2000

3000

4000

5000

6000

7000

8000

-0.437108672-0.248762431 -0.06041619 0.127930052 0.316276293

Frequency

Page 34: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

34

MFL Data – Length Uncertainty

Length Accuracy: +/- 20mm 80% of the time

• Equivalent to:

• Mean: 0 mm

• Standard Deviation: 15.6 mm

• Also affected by complexity of the corrosion

• Clusters consisting of several boxes:

• Standard Deviation: 22 mm

Page 35: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

35

501 mm

Page 36: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

36

Signal Comparison

Estimating corrosion growth critical to determining when currently sub-critical defects will require repair

Corrosion growth rates estimated through a comparison of MFL signal data

Page 37: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

37

Segmenting Pipeline by Measured Growth

Growth

0

5

10

15

20

25

30

0 20000 40000 60000 80000 100000 120000 140000

Abs. Distance (m)

Growth (%w)

S1 S2 S3 S4 S5 S6 S7 S8 S9 S10S11S12S13 S14 S15 S16 S17

Histogram (S2)

0

10

20

30

40

50

0 3 6 9 12 15 18 21 24 27 30

Bin

Frequency

Page 38: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

38

Regression Tree Analysis

Page 39: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

39

Risk Acceptance – Individual Risk Criteria

48”

36”

Point on ROW under analysis –

Assumed constant occupation

Escape Distance: Pipe beyond these points do

not have an effect on the point under evaluation

( ( , '))

X

x Ignition Fatality x

X

IndividualRisk P P P R R dx

+

= × ×∫

Page 40: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

40

Correlation Results – Risk Based Digs

1.00

1.20

1.40

1.60

1.80

2.00

1.00 1.20 1.40 1.60 1.80 2.00

MFL Safety Factor (Relative to MAOP)

LPIT Safety Factor (Relative to MAOP)

Page 41: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

41

Risk Based Digs - Results

Increased Dig Program

• 27 Defects Deterministic -> 73 Defects Risk Based

Significant Defects Found and Repaired

• 18 Defects Deterministic -> 37 Defects Risk Based

Worst Defect Identified Through Risk Process

Page 42: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

42

Improving Rupture Frequency Trend1994

1996

1998

2000

2002

2004

Year

Frequency per km*yr

Page 43: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

43

Pipe Maintenance Program Spending Trend

1998 1999 2000 2001 2002 2003 2004 2005 2006

Maintenance Spending

Page 44: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

44

Conclusions

The PRIME process resulted in both:

• Significant cost savings relative to the industry standard approach

• Improving reliability and reduced risk exposure relative to the industry standard approach.

Provides a rationale for determining maintenance spending levels and allocating those resources

Provides a mechanism for continuous improvement through the incorporation of new quantitative information.

Page 45: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

45

Second Generation Pipeline Risk Management Why Upgrade?

Operating Experience

Scope

Regulatory Change

Scientific Advancement

Data Availability

Computing Power

Obsolescence and Support

Page 46: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

46

Operating Experience

Decision criteria dominated by two types of consequence

High dependence on data

• Physical and spatial attributes

• Maintenance data

• Third-party data sources (ILI, LPIT, Imagery, etc.)

• Industry statistics

Platform dependence is an issue (OS, desktop, network, related apps)

Ongoing technical support burdens

Limited ability to revise and enhance

Page 47: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

47

Scope

System growth, primarily through acquisitions

Support required for several pipelines in U.S.

Need for liquids pipeline support

Acquisition of off-shore facilities

Greater number of users; differing areas of expertise

Page 48: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

48

Regulatory Change

Changes to Canadian regulations

Introduction and Changes to U.S. regulations

Changes to Industry standards (CSA Z662 and ASME B31)

Page 49: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

49

Scientific Advancement

Improvements to existing engineering models

New engineering models

Capitalizing on previous R&D effort

Page 50: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

50

Data Availability

Electronic access to 3rd party information

Migration of old data

Industry adoption of standardized data structures (ISAT, PODS, etc.)

Page 51: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

51

Computing Power

Order of magnitude increase in desktop computing power

Order of magnitude increase in server/network throughput

Fewer compromises required

Better tools for development, deployment and support

Page 52: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

52

Obsolescence and Support

Tools (PERL SDK, Tk, ODBC)

Platform (PERL runtime, Windows XP, IE, Office 2003, Oracle)

Stand-alone versus I.S. support

Page 53: TransCanada’s Risk Management System for Pipeline ... · 2 Pipeline Risk & Integrity Management Enabler The PRIME project was started in 1998 to develop a Risk Management process

Thank you