TRAINING REPORT-2002
-
Upload
sachin-garg -
Category
Documents
-
view
503 -
download
2
Transcript of TRAINING REPORT-2002
PREFACE
The objective or main motive of this practical training is to getting a true practical knowledge about the industries, that how their industrial setups are held, and their communication techniques used in industry technologies to be made or used in the environment.This report is presented on the basis of practical training acquired in “SCADA/EMS” SLDC Section RRVPNL, Heerapura, Jaipur. This report is on with relevant diagrams & by their proper description & explanation.The term “SCADA(Supervisory control and data aquisition)/ EMS(Energy management system)” generally refers to an industrial control system : a computer system monitoring and controlling a process.The term “SCADA” usually refers to centralized systems which monitor and control entire sites,or cmplexes of system spread out over large area (anything between industrial plant and a country). In spite of all my best efforts some unintentional errors might have eluded, it is requested to abrogated them.
ACKNOLEDGEMENT
I am very grateful to Mr. M.P. Mathur (Assistant Engineer) & Mr. Dhiresh saini (Junior Engineer) for his very useful guidance, technical & much advantageous lectures . I would also like to express my sincere thanks towards SLDC Section, RRVPNL, Heerapura, Jaipur. for their co-ordination & support in problem solving . I am also thankful to Mr.Ashok sirohi (H.O.D.,Electronics & communication) because he encouraged me throughout the practical training and helped to understood correctly.
2
CONTENTS
1. INTRODUCTION-THE NORTHERN REGION POWER
SYSTEM
1.1 Background
S.NO TOPIC PAGE NO.
1Introduction-The northern region power system
4
2Current institutional and operational problems in the northern region
8
3Operational & control philosophy
15
4Principle for Data Aquisition
21
5Data processing system of control centers
6DC system & AC auxillary power supply
7Total cost benefits of project
8 Conclusion
3
India has been divided into five Electricity Boards viz.,
southern, northern, western, eastern and north-eastern for the
purpose of power system planning and operation.
The Northern Regional Grid is composed of the generation,
transmission and distribution facilities of the following State
Electricity Boards and other national/regional agencies:
Himachal Pradesh Electricity Board (HPSEB)
Haryana State Electricity Board (HSEB)
Jammu & Kashmir (J&K) PDD
Punjab State Electricity Board (PSEB)
Rajasthan State Electricity Board (RSEB)
Uttar Pradesh Electricity Board (UPSEB)
Union Territory Of Chandigarh
Bhakra Beas Management Board (BBMB)
Delhi Electric Supply Undertaking (DESU)
Central Sector (CS), that is made up of:
Power Grid Corporation of India Limited (Powergrid)
National Thermal Power Corporation Limited (NTPC)
National Hydro-electric Power Corporation Limited (NHPC)
Nuclear Power Corporation (NPC)
Nathapa Jhakri Power Corporation (NJPC)
Tehri Hydro Development Corporation Limited (THDC)
Today, the Northern Regional Electricity Board (NREB) is
vested with the responsibility of coordinating smooth
4
integrated operation of the regional grid. The operation of
such a grid, spanning over such a large territory is technically
complex and all the more complicated as not less than 15
Boards or Agencies are involved in operation.
1.2 The Northern Regional Power System
1.2.1 The Constituents
The Northern Region comprises the power systems of
the constituents of Himachal Pradesh, Haryana, Punjab,
Rajasthan, Uttar Pradesh, Jammu & Kashmir plus the
Union Territories of Delhi and Chandigarh. While the
power systems of Haryana, Jammu & Kashmir, Punjab,
Rajasthan, and Uttar Pradesh have both hydro and
thermal power plants, Himachal Pradesh is purely a
hydro system. Besides the State power systems, in
1992 there were 5 Central Sector Power Agencies viz.
Powergrid, NTPC, NHPC, NPC and THDC.
1.2.2 Functions of NREB
The Northern Regional Electricity Board is today in
charge of co-ordinating the planning and operation of all
the constituents in the Northern Region, i.e., the five
State Electricity Boards, Jammu & Kashmir, Bhakra
Beas Management board, Delhi Electric Supply
Undertaking and Central Sector.
5
Central power stations are regional in character and
meant for the benefit of all the States of the Region.
Presently, power from a Central Power Station is
allocated to the various Constituents in accordance with
the following general agreed formula for sharing of
power:
1. 15% power is kept unallocated at the disposal of
Government of India to meet the urgent
requirement of the individual beneficiary States
from time to time.
2. 10% of the power is kept allocated to the State in
which the power station is located.
3. The remaining 75% power is distributed amongst
the beneficiary States (including the home State)
in accordance with the energy consumption of
these States and the Central Plan Assistance to
them.
One of its major duties of RSCC is to monitor the inter-
State Exchanges of power with reference to schedules
and control of net off-take of power and energy from
these Central projects.
1.2.3 The new role of the Power Grid Corporation of India
Limited
6
The government of India (GOI) recently agreed to
modify the scope of responsibilities for control facilities
and operation of the grid, which involves for the long
term: Powergrid as a developer, owner and operator of
transmission facilities and regional system co-ordination
and control systems; CEA as a regulator agency;
GOI agreed with a three-phase development for
Powergrid. During phase 1, CEA would continue to
operate the existing RSCCs (Regional Systems Control
Centres), while Powergrid takes over transmission
facilities from NTPC, NHPC, etc. and undertakes
projects to develop new RSCCs. Then Powergrid would
own and operate the project facilities and take over
related existing facilities from CEA not later than at the
completion of the project marking the commencement of
phase 2, viz. establishment/ augmentation of load
dispatch and communication facilities in various
Regions. During phase 1, Powergrid will need
immediate access to and use of the existing control
facilities at the Regional level (present RSCC), co-
operation with the various constituents of REBs and
CEA, to facilitate improved operation of its transmission
system, to help ensure a smooth transfer of old system
operational functions from CEA to Powergrid and to
facilitate the implementation of the new RSCC.
7
Powergrid will also undertake in co-operation with the
State Electricity Boards (SEBs) the projects to develop
new SEB load dispatch centers and to augment existing
facilities as a part of its regional co-ordination and
control system projects. SEBs will operate the facilities
in co-ordination with the concerned RSCC.
2. CURRENT INSTITUTIONAL AND OPERATIONAL
PROBLEMS IN THE NORTHERN REGION
2.1 Current institutional arrangements
The task of regional grid management is vested with the
NREB and they have to co-ordinate the operation of
autonomous Central and State sector organizations in the
Region. Under this set up the NREB has to derive their power
from the constituents. Lack of proper communication and real
time load dispatch facilities is the biggest constraint in
effective operation and control of the grid. The NREB, as
association of the Constituents of the Northern Region, was
created to co-ordinate the integrated operation of the Northern
Regional Grid System. The GOI made the decision to form a
National Power Grid, along with necessary load dispatch and
communications facilities, in order to make best use of India’s
unevenly distributed energy resources and to transfer large
amounts of surplus power from the North and East to the
other regions.
8
2.2 Operational guidelines and discipline
2.2.1 Operational discipline
It is necessary to have proper agreements spelling out
the operations regimes, obligation of suppliers as well as
the beneficially States in terms of maintaining the
system parameters, reliability criteria, penalties for
violation of agreed operating regimes, etc.
The operating norms should cover not only the normal
state of operation of the power system but also the alert,
emergency and restorative states.
At present there are no means to enforce the
operational discipline. In case of overdraws of power by
any State, the Regional Load Despatch Centre (RSCC)
can only request the erring State to regulate its demand.
The continual overdraws of power of some deficient
States at the peak time while the same are not backing
down during off-peak as the frequency becomes very
high is a testimony to this kind of problems.
There is a lack of load management in most of the
States. It is a basic tenet of integrated operation that
each state restricts its load to match with the availability
9
from its own sources of generation plus legitimate
shares from common/central generating sources, plus
eventually agreed by lateral power exchange
agreements.
2.2.2 Frequency maintenance problems
The grid management problems of the country are
compounded by continuing power shortages in the
different systems. While the demand for power has been
increasing at a rapid pace the generation availability has
not been keeping pace with it. The short fall in
availability is due to delays in commissioning for
generating units, lack of funds for construction, problems
in quality of coal and equipments, high level of forced
outages, etc. In most power systems in the world, the
system frequency is kept virtually constant and a
combination of generator governors and automatic
generation control systems constantly control the
generators so that:
The total generation is kept equal to the total load and,
Generators are operated at the levels at which the total
cost of the power generated is at the minimum
consistent with safe system operation.
The remaining matching of load to generation is
obtained by allowing the system frequency to vary up
10
and down; this in turn increases or decreases the power
consumption of motor operated loads such as pumps,
refrigerators and many similar devices, until either the
load is brought to match the power generated or the
system collapse when frequencies become so low that
the generating plants cannot operate.
During peak periods, many of the SEBs fail to shed their
loads in the quantities agreed at the NREB level. This
forces other SEBs to shed more lot than they were
required to do, or causes frequencies to drop lower than
it would have. The net result in either case is that the
SEB that fails to shed load as agreed receives more
energy than it is entitled to, and the other receives less.
During light load periods, those SEBs that should back
down on their more expensive units fail to do so. The
result is that central units with lower production cost
must be back down instead, resulting in uneconomical
operation of the regional system. In some cases, hydro
units with full reservoir are required to back down their
output resulting in wasteful spilling of water over the
dense.
2.2.3 Lack of flexibility in generation scheduling at present the
energy invoicing is based on a single tariff system with
11
regards to the actual energy transfers metered under tie-
lines.
The world wide basic principle of invoicing the power
transfers with regards to the agreed commitments and
calculations of inadvertent deviations between this
program and the actual transfers for compensation, etc
payments, penalties and what so ever, has not yet been
considered in the Indian practice. As far as the hydro
scheduling is concerned, the REBs only recommended
to most of the hydro stations to supply their maximum of
the power at the peak period but the power scheduled of
each power unit remains the responsibility of the hydro
stations mainly with regards with the irrigation
requirements.
2.3 Deficiencies in power transmission system
2.3.1 Power transmission lines and sub stations
The transmission system is being planned on a regional
basis and optimized without regard to ownership under
the responsibility of CEA. The establishment of central
sector power plants has increased the complexity of the
regional network by super imposing a transmission
system to the transmission system of the SEBs.
12
With a view to optimizing investment, the regional
transmission systems have been developed on the
assumptions that the shares of some state located far
away from the central stations would be delivered on the
principles of net inter states exchanges where ever
feasible without affecting the reliability and security of
the transmission system.
There is also a tendency on the part of all the states to
cover only the very minimum works under the scope of
these projects
In several systems, the transmission capacities are not
sufficient to evacuate power from the generating
stations. This restricts full use of generating plants.
A single central agency that will be in charge of the
complete regional inter connected grid would bring more
rationality in this regard. It will be possible to construct
many more missing links, which are neither associated
with the evacuation of power from any power plant nor
required for load management. The major problems
encountered in daily operation of the northern 400 kV
networks are very low voltage level at receiving end at
the peak, power swings involving cascade tripping
and /or systems isolations and collapses, massive loss
of generation, voltage collapses, partial and sometimes
total power supply failure. One of the numerous regions
13
for these mishaps is due to the particular weakness of
the 400kv network and its long radial structure that
should be strengthened and reinforced by more
intermediate step-down substations.
2.3.2 Compensation means
Reactive power management has not received the
attention it deserves. Bulk of the present reactive power
is being supplied by the generating plants thereby
resulting in large flows of reactive power all over the
transmission and distribution networks towards the load
points from the generating units that are most of them
located far away from the load .The very low voltage
levels indicate conditions close to Voltage collapse or
transmission instability .The power swings typical of
transient instability.
2.3.3 Transmission planning tools
Eliminating transmission constraints, which prevent full
use of generating capacity, should be a priority in
efficiency improvement programs. For this purpose the
various Regions involved may need adequate planning
and design tools to be able to define in a more efficient
way the reinforcement needs.
14
3. OPERATIONAL AND CONTROL PHILOSOPHY
3.1 Basic operational and functional requirements
The basic operational requirements of the Northern Regional
Grid are as follows:
Scheduling in advance a healthy mode of operation Constant
surveillance of the system’s conditions with the help of a well-
knit communication network so as to ensure the security of the
system at all times and at all points restoration of the system
to normalcy as early as possible in case of abnormalities by
taking corrective measures. These operational requirements
entail that the finicalities be implemented at the various levels
of control hierarchy both for operation planning activities and
real-time control activities.
During the operation planning stage, the basic tasks to be
carried out are:
State wise generation scheduling and load prediction for
a complete day, week, month and year
Determining of the share of each State in Centrally
owned generation on given day
Scheduling of inter-State and inter-Regional exchanges
for a given day
15
Updating maintenance schedule for generators,
transformers, transmission and/or distribution lines
Spinning reserve assistance
Co-ordination with National Load Dispatch Centre in the
future
Collection of data regarding weather forecasts
Analysis of system performance under disturbances and
devising remedial actions to minimize their effects
System operations statistics
Computing of tariffs for inter-system exchanges based
on pre-defined guidelines.
For the real-time control stage, the tasks to be performed may
be classified into two categories:
(1) On-line Real-Time Operation Control
(2) On-line Real-Time emergency and Reliability
Control
3.2 Outline of the overall control organization
It is clear that operation of such a large system requires one to
set up a control hierarchy, which will also match the power
system organization in the Region. With this end in mind, a 3-
tier hierarchical network has already been defined , complying
with the load dispatch facilities policy established by Central
Electricity Authority (CEA) for all India.
16
The following load dispatch centers are proposed to be
implemented at the different hierarchical levels:
Hierarchy level 1:
Regional System Control Centre at Delhi covering the region
power systems of Himachal Pradesh, Haryana, Jammu and
Kashmir, Punjab, Rajasthan, Uttar Pradesh, BBMB, DESU,
Chandigarh.
Hierarchy level 2:
Comprising State Load Dispatch Centres (SLDCs) and
Central Project Control Centres as below:
SLDC for Himachal Pradesh at Shimla;
SLDC for Haryana at Panipat;
SLDC for Jammu & Kashmir at Udhampur;
SLDC for Punjab at Patiala;
SLDC for Rajasthan at Heerapura;
SLDC for Uttar Pradesh at Lucknow;
CPCC at Moga for Central Sector Stations in the northern
area of the Region;
CPCC at Kanpur for Central Sector Stations in the south-
eastern area of the Region;
CPCC at Ballabhgarh for Central Sector Stations in the
central area of the region.
Hierarchy level 3:
Sub-load Dispatch Centres (Sub-LDCs) as below:
17
Sub LDCs at Kunihar and Hamirpur controlled by SLDC at
Shimla (Jutogh)
Sub LDCs at Dadri, Panipat TPS and Narwana controlled
by SLDC at Panipat;
Sub LDCs at Pampore and Udampur controlled by SLDC at
Udampur (NB: Udhampur Sub LDC is located in the same
control room as the SLDC);
Sub LDCs at Jallandhar, Lalton Kalan and Patiala
controlled by SLDC at Patiala.
Sub-LDCs at Ratangarh, Kota, Bhilwara and Heerapura
controlled by SLDC at Heerapura.
Sub-LDCs at Rishikesh, Moradabad, Panki, Varanasi and
Sultanpur controlled by SLDC Lucknow.
3.3 Functions of the Control Centres and sharing out of
responsibilities
GOI has agreed that Power Grid shall develop into a national
service oriented transmission company. The performance of
these activities requires a transmission network with adequate
capacity going well beyond the basic requirements of
evacuating power produced by specific plants and a minimal
connection to the load centre.
Powergrid will be organized primarily for impartial service to all
parts of the power sector. The SEBs will retain the basic
responsibilities of operating and dispatching their plants.
18
3.4 Responsibilities of the RSCC
The RSCC shall be responsible for the following:
Data acquisition and monitoring of all the transmission
system at 220 kV and above, plus the 132 kV interstate
lines and all the generating stations of 50 MW and above.
Supervisory control of the power system operation
pertaining to inter-State/ Regional grid and control of
central sector sub-station under its direct jurisdiction.
Management and supervisory control of the centrally
owned generating unit. Load frequency control for the
entire region and sending corrective area control error
messages to all the constituents.
Monitoring inter-state exchanges of power with references
to schedule and AGC orders.
Supervision of generation/ load balance in the various
states with respect to the power exchange schedule, the
frequency requirements and the generation management
according to the merit order list prepared on a regional
basis.
19
3.5 Responsibilities of SLDCs
The SLDC shall be responsible of the following:
Acquisition of information from central sector and some
part of the neighboring state systems from RSCC.
Generation load management according to economic
generation
Optimization carried out at state level and according to
RSCC request for inter-state power transfers and
frequency regulation.
Transmission of orders directly to state owned power
stations from the state requirements.
Voltage and reactive power control.
3.6 Responsibilities of the Sub-LDCs
The Sub-LDCs will be responsible of the following:
Switching of equipments at 220 and 400 kV as per direction
SLDC
20
Voltage and reactive power control with in their area of
responsibility, according to SLDC’s requirements and
guidelines
Security assessment of the sub transmission network in
their area
4. PRINCIPLES FOR DATA ACQUISITION
4.1 General
The tele information plan corresponds to the requirements for
data collection that will enable the various levels of the power
system control hierarchy to fulfill their role. That means in
particular that apparatus status like bus selector disconnect or
position, and alarms like loss of voltage are considered and
some circuit breakers remote control facilities are planned.
4.2 Data Transmission Principles
The circuit breakers positions are collected under the
shape of double signals (DS) as this is necessary for
remote control functions, also these are more reliable.
The isolators positions are given single signal as these
are not needed for remote control.
21
For all apparatus positions, the information will be
transmitted when change of status occurs.
All possible alarms are collected under single signals.
4.3 Principles for Data Acquisition
4.3.1 Busbar section
a) Voltage:
400, 220 & 132 kV: one value per main busbar.
66 kV: one value per station.
33 kV: no value.
b) Frequency:
400 kV: one value per busbar.
220 kV: one unit per station except for stations
where power units are connected to or having
inter-state feeders (2 values: one per main
busbar).
132, 66 kV: one value per station where power
units are connected.
33 kV: no value.
c) SS:
1 SS for loss of voltage per busbar.
4.3.2 Busbar coupler and bus section breaker
22
DS: 1 DS per circuit breaker.
SS: 1 SS for only one out of the 2 disconnectors.
4.3.3 Bus transfer
DS: 1 DS per circuit breaker.
SS: 1 SS for each disconnector on both sides of the
C.B.
4.3.4 Busbar disconnector
SS: 1 SS for each busbar disconnector (whatever the
voltage level & including busbar transfer).
4.3.5 Capacitor
DS: 1 DS per circuit breaker.
SS: 1 SS for each bus selector disconnector.
4.3.6 Reactor connected to busbar & synchronous
compensator
a) Reactive power: 1 value.
b) D S: 1 DS per circuit breaker.
c) SS:
1 SS for each bus selector disconnector in case
of single breaker arrangement.
23
1 SS for each disconnector in case of one-
hand-half breaker arrangement.
4.3.7 Gas generator and Hydroelectric Generator (substation
side)
a) Active power:1 value.
b) Reactive power:1 value.
c) DS:
- 1 DS per substation circuit-breaker
- 1 DS per generator bus coupler
d) SS:
- 1 SS for each bus selector disconnector in case
of single breaker arrangement.
- 1 SS for each disconnector in the case of one-
and-half breaker arrangement.
- 1 SS for each by-pass disconnector in the case
of single breaker +by-pass arrangement.
e) Reservoir level: 1 ATM per hydro station when it is
already available on site.
4.3.8 Thermal generator (substation side)
One value of P for gross active output,
One value of Q for gross reactive output.
4.3.9 Remote generator
In case of power plant needs its own RTU because of
the distance to the substation, connections in the
24
corresponding substation are to be described as
overhead line connections and remote generators as
follows:
- 1 DS per circuit-breaker(if existing for outgoing
feeder),
- 1 DS per generator bus coupler,
- one value of P for gross active output of a
thermal generator,
- one value of Q for gross reactive output of a
thermal generator.
4.3.10 Overhead line
a) Active power and reactive power
- 400, 220 and 132 kV: one value of P and Q for
each outgoing line .
- 66 kV as a secondary part of Regional interest
substation: one value of P and Q only for
outgoing inter-system tie-line.
- 33 kV : no value.
b) DS
For each 400, 220 and 132 kV outgoing line and
66 kV outgoing tie-line:
- 1 DS per substation circuit-breaker
- 1 DS per reactor disconnector(or circuit-breaker
in the future) connecting it to the 400 kV line.
c) SS
25
For each 400, 220 and 132 kV outgoing line and
66 kV outgoing tie-line:
- 1 SS for each bus selector disconnector in case
of single breaker arrangement
- 1 SS for each disconnector in case of one-and-
half breaker arrangement
- 1 SS for each by-pass disconnector in case of
single breaker+by-pass arrangnment
d) DC
- 1 DC for each 132 kV outgoing line.
The choice consisting in the implementation of remote
control only for 132kv feeders and below can be justified
by the needs of quick switching operation requirements
for load shedding and emergency action.
In some particular cases, some remote control facilities
may be interesting also for 220 kV or 400 kV
components of the grid. These specific requirements
shall be precisely defined at technical specification
drafting.
4.3.11 Transformers
a) Active power and reactive power
26
One value of p and one value of q measured on
the secondary level for the 400/220 kV or 220/132
kV transformers, or on the primary level for the
132/66, 132/33 or 132/11 kV transformers. If the
secondary level does not belong to the same
constituent as the primary level, p and q are
measured on the primary level.
b) Current
One current value (I) measured on primary level
for the 66/33 kV, 66/22 kV, 66/11 kV or 33/11 kV
transformers whenever the load supplied by the
transformers is significant.
c) OLTC
The position of each On Load Tap Changer is
indicated with a digital or analog tele measuring.
This shall be specified for each individual case at
specification drafting.
d) DS:
1 DS per circuit breaker. If the secondary level
doesn’t belong to same network, 1 DS shall also
be collected for the secondary circuit breaker.
e) S S:
27
1 SS for each bus selector disconnector
in case of single breaker arrangement.
1 SS for each disconnector in case of
one & half breaker arrangement.
1 SS for each by-pass disconnector in
case of single breaker arrangement.
f) D C:
One DC on the secondary level for the 132/33 kV,
132/22 kV 132/11 kV, 66/33 kV, 66/22 kV, 66/11
kV, 33/11 kV transformer whenever the load
supplied by the transformers is significant.
5 DATA PROCESSING SYSTEMS OF CONTROL
CENTRES
5.1 RSCC Scope of supply
The following list details the requirements as regard hardware
& software for the RSCC computer system.
One dual computer system for SCADA, PAS & MMI
functions including at least:
System CRTs console,
Disks strage units,
28
Magnetic tape storage devices or equivalent
equipment,
Failover system,
Line printer,
Software package,
One time & frequency system,
One receiver for time synchronization
signals.
Man machine interface
Control room:
Two dispatcher consoles with two VDUs each,
Two hard copy units linked to any console,
Two loggers and one plotter,
One line printer,
One frequency recorder,
One mimic board, along with its driver,
One audible alarm.
Computer section:
One dispatcher console equipped with two VDUs,
Two programming terminals,
One hard copy unit,
One line printer.
SCADA and MMI software.
29
Power application software:
Network topology,
Reduced equivalent network,
Logical controls,
State estimation,
Contingency analysis,
Load flow,
LFC,
One local RTU.
5.2 SLDCs scope of supply
Two categories of SLDCs have been considered in the
northern region, depending on the size of the constituent:
1st category (large sized SLDC): Lucknow,
Heerapura.
2nd category (standred sized SLDC): Shimla,
Panipat, Patiala, Udhampur.
One normal dual configuration is provided for the first category
and a medium dual configuration is provided for the second
category.
One dual computer configuration for SCADA, PAS and
MMI functions including at least:
30
System CRTs console,
Disks storage units,
Magnetic tape storage devices or equivalent
equipments,
Fail over system,
Line printer,
Software package,
One time and frequency system,
One receiver for time synchronization signals.
Man Machine Interface
Control Room:
Dispatcher consoles:
- For SLDCs: 2 dispatcher consoles each with two
VDUs,
- For large mixed SLDC/sub-LDC: 3 dispatcher
consoles each with two VDUs.
Two hard copy units linked to any console,
Two loggers and one plotter,
One line printer,
One frequency recorder,
One mimic board along with its driver,
One audible alarm.
Computer section:
31
One dispatcher console equipped with two VDUs,
Two programming terminals,
One hard copy unit,
One line printer,
One local RTU.
SCADA and MMI software.
Power application software:
Network topology,
Reduced equivalent network,
Logical controls,
State estimation,
Contingency analysis,
Load flow,
LFC.
Option two for EMS:
One computer,
At least two disk storage units with controllers,
One streamer or magnetic tape storage device,
One line printer,
Two programming terminals,
One software package.
5.3 CPCC’s scope of supply
32
Two categories of CPCC have been considered in the
NorthernRegion depending on the quantity of RTUs
controlled:
1st category: more than or equal to 15 RTUs(large sized
CPCC )
2nd category : less than 15 RTUs(standard sized CPCC)
one medium dual cofiguration is provided for the 1st category
and the PC dual configuration is provided for the 2nd category.
The following list details the requirements as regards
hardware and
MMI functions including at least -One dual computer
configuration for SCADAand MMIfunctions including at least:
system CRTs console ,
disks storage units,
magnetic tape storage devices or equivalent equipment,
failover system,
line printer,
software pakage:
one time and frequency system,
one receiver for time synchronization signals
-Main Machine interface
-Control Room:
3 PC workstations,
two hard copy units linked to any console,
two loggers,
one line printer ,
one plotter,
one frequency recorder,
33
one mimic board along with its driver,
one audible alarm.
-computer section:
one dispatcher console equipped with its driver,
two programming terminals,
one hard copy unit,
one line printer,
-SCADA and MMI software,
5.4. Sub-LDCs scope of supply
Two categories of Sub-LDCs have been considered in the
Northern Region, depending on the quantity of RTUs
controlled:
1 St category:more than or equal to 15 RTUs-2nd category:
less than 15 RTUs
5.5 Control Centres communication
The hierarchy of the Control Centre is a three tiers hierarchy.
These are :
RTU(substation level )
Sub-LDC, 3rd tier
SLDC or CPCC, 2nd tier
RSCC, 1st tier.
All the state owned RTUs are only linked to Sub-LDCs. Thus a
data communication protocol and procedure shall be provided
for this first layer.
The data transferred on these links are:
Either real-time data
Or files
34
Or data related to remote logging procedures.
In order to enable all these data transfers between computers,
it is mandatory to have in each control center a
communication software which implements the seven layer of
Open System Interconnection(OSI) ISO Recommendation.
The OSImodel in seven layers is the following one:
Layer 1: physical,
Layer 2:link,
Layer3:network,
Layer4:transport,
Layer5:session,
Layer6:presentation,
Layer7:application.
5.6. GENERAL
Telecontrol systems serve for monitoring and control of
processes which are geographically widespread.They include
all equipment and functions for acquisition,processing,
transmission and display of the necessary process
information. The performance of a telecontrol system is
determind basically by:
The data integrity of information transfer, from a
source to its destination , and ,
The speed with which information is transferred to its
destination.
35
Since telecontrol systems have to operate in real-time mode,
limitations imposed by the telecommunication channels may
heavily impair the overall system efficiency.The implicatin is
restricted bandwidth and hence restricted bit rates to be
transmitted under noisy environment conditions, which cause
distortion of transmitted signals elements. The data
transmission system has to be considered in the sense as an
integrated part of the telecontrol system.
Basic requirements of the data transmission system
Data transmission should fulfill the following
requirements:High data integrity and data consistencyUnder
these conditions, it is necessary to provide efficient protection
of messages against :
undetected bit errors,
Undetected frame errors caused by synchronization
errors,
Undetected loss of information ,
Gain of unintended information ,
Separation of perterbation of coherent information.
Short telecontrol transferred time
Provision of short information transmission by application of
efficient frame transmission protocols, particularly for event
intiated messages over transmission paths with limited
bandwidth and with uncertain noise characteristic has to be
ensured.Support of bit oriented (code transparent ) data
transmissionNo code restrictions on user data required.The
36
data link protocol accepts and transmits arbitrary bit sequence
structures from the data source.
Transmission software and protocol specifications
Transmission software arrangment
For standardization reasons and easy future upgrading of the
Data Transmission Network(DTN) to packet switching,
communication software is based over the latest ISO(CCITT)
standards in force implementing the ISO’s OSI model.This
subdivision into modular layers is a useful theoretical model
for difining standards. Each layer is essentially independent of
the layers below and above it. It treats the layer below as a
“service” function and the layer above as a “master” with witch
it exchanges data and to which it reports errors.
The independent of the layers gives a modularity to the
system. It ispossible to alter one layer without altering others,
in the some layers may be omitted.Telecontrol system
functions will be divided into the following layers:
Application functions:
Cover the special needs of the process to which a telecontrol
system is applied, thus dealing with the types of information
emanating from the process or from the operator.This
information is transferred to the telecontrol system by signals
and is handled with in this system in the form of data.
Operational processing functions including presentation
functions:Conversion of information into signals and in the
37
operational equipment.Data transport, network, link and
physical transmission functions.
Tansmission protocol
The protocol to be used for RTU-sub-LDC links and for direct
RTU-RSCC links will be one of the following by order of
decreasing preferences:
- X.25(up to layer 2), -IEC 870-5-1, -Manufactrur’s
specific.If one of the first 2 solutions is proposed, it must not
induce additional cost with respect to the manufcturer’s
specific solutions.
The protocol to be used for inter –LDClinks will be the X.25
with the option and particulars alredy applied by department of
science and technology in consulation with CEA.
5.7. Physical structure of the protocol system
5.7.1. General
The structure of the data communication network which
is thus a sub-set of the telecommunication system is
mainly determined by the operational philosophy, i.e.:
National Control Centre,
Regional Control Centre,
State Control Centre,
Sub-state Control centre,
Substations,
And the real-time character of the requirements .
The solution of designing a complete Packet switching Data
Network(PSDN) has also been examined.
5.7.2. Geographical configuration of telecontrol channels
38
For RTUs a combination of multipoint-party line
configuration and multiple point-to-point configuration
will be used. The first type involves serial polling, i.e.
several RTUs share the same telecontrol channel, while
the second type involves parallel polling from the sub-
LDC.
Transmission link redundancyIn order to maintain a high
quality of service with strategic sites, the physical
communication links arriving on the latter will be
duplicated. This will be the case atleast for:
The links arriving on 400/200kv substation and power
station RTUs,
All the links interconnecting contral centers.
5.8. Transmission modes
5.8.1. Transmission initiation modes
In the case if RTU/sub-LDC links, two basic
transmission initiating modes will be used for telecontrol
data transmission:
Event initiated transmission(spontaneous transmission,
also called master-master),
Transmission on demand(interrogative or polling mode,
also called master-slave).
Types of traffic in transmission channelsFull duplex
traffic will be used,
39
Independent transmission channels exist for the
incoming and outgoing directions .
5.9. Transmission speed
5.9.1.Basic requirements
Total control system refresh time for indications must not
exceed 2s under normal operating conditions.
For analog measurenments, the age of a displayed
values must not exceed 10s.
5.9.2. Final results
The following is required:
For sub-LDC/SLDC links:1200 Bds(1200 bits/s), FSK,
CCITT V-23, 4-wire.
For higher hierarchical rank inter-computer links:4800
Bds(4800 bits/s), phase modulation, CCITT V.29.
For RTUs:
All RTUs would be configured to work at 200 bauds on
FSK channels located above the 300 to 2.4 kHz speech
sub-bands of 4 kHz VFTs.
5.10. Modems
5.10.1. Basic requirement of RTUs modems
Frequency shift channel modems are to be used to
convert a binary signal into two distinct frecuencies.The
rack modem of RTU will contain 2 single-card modem
boards.The modem will accept CCITT V.24 serial
40
signals and communicates at the standardized data
rates from 50 to 1200 bauds.
basic requirement of modems for control centre
computerThe communication speed will be settable from
50 to 9600 bits/s.
5.11. Remote terminal unit
5.11.1. General
The typical RTU will perform two functions:
The basic RTU function:Processes and
transmits:Indication signal change messages,
Telemeasuring value messages andTelemetering value
messagesPicked-up on the RTU location site devices to
a control centreReceives and processes digital or
analogue command messages coming from a control
centre so as to feed them to the relevant devices located
at the RTU location site.
Sequential Event recording :
TTY will be provided only at 400kv, 220kv substation
and power station sites.
5.11.2. Charateristics of RTU I/O circuits
RTU will be capable of accepting :Single point
information indication signals, double point information
indication signals, telemetering signals, under the form
of potential free contacts.
RTU will be capable of issuing:Single point digital
controls,
41
Double point digital controls,
Under the form of potential free contacts .
RTU basic functional processing requirements
The RTU will be capable of time-tagging the status
changes with a 10ms resolution for transmission to the
control centre as well as local editing on a TTY
terminal(sequential event recording)RTUs bills of
quantitiesAn RTU will equip each side that will be
under supervisory. For power station and the control
room of which is farther than 1km from the substation
control room, a separate RTU will be
installed.Subsequently, the following quantities of
RTUs have to be supplied :
HIMACHAL PRADESH : 14(14 stations)
HARYANA : 32(31 stations+SLDC)
JAMMU & KASHMIR : 14(14 stations)
PUNJAB : 47(47 stations)
RAJASTHAN : 53(53 stations)
UTTAR PRADESH : 98(97 stations+SLDC)
CENTRAL SECTOR : 44(43 station + RSCC)
TOTAL : 302
6. DC SYSTEM AND AC AUXILIARY POWER SUPPLIES
6.1 General
42
For the purpose of a control and telecommunication scheme , the
auxiliary power supplies are usually categorized as under .
Power supplies for supply of :New RTU an interface cubicle ,
new communication equipment , Data processing equipment in
the various control centers,Airconditioning and security lighting in
Control Centres .
They are one of thefollowing types:
Uninterruptible DC source (or DC power system)
Uninterruptible AC source
Standby power supply.
In the scope of this project , it was generally decided by
Powergrid and the constituents that the DC power supply in the
sub stations will not be included.Thus , only the AC and DC
power supplies for the sub-LDCs , CPCCs, SLDCs and RLCC
will be considered .
6.2. AC auxiliary power supplies in Control Centres
6.2.1. Making–up of 415/240V AC uninterruptible power supply
in Control Centres
Two 415V, 3 phase AC supply together with an
emergency diesel generator will ensure a secure supply
to the essential services which can support a power
failure for a short period of time , i.e. : stand-by power
supply .An uninterruptible power supply consisting of DC
supply chargers , batteries and invertors will provide 3
phase 50Hz power supplies to the computers ,
peripherals, etc….
6.2.2. 415/240V stand-by and UPS power sizing.The
minimum sizing will be:125KVA for the diesel generator
43
and 2*50kVA for the AC UPS of RSCC and large sized
SLDCs , 25kVA for the diesel generator and 2*25kVA for
the AC UPS of large sized sub-LDCs and small sized
SLDC , 45kVA for the diesel generator and 2*15 kVA for
the AC UPS of a small sized Sub-LDCs and CPCC.
6.3. 48V DC system in control center
6.3.1. 48V DC power supply make-up in control center
A control center 48V DC power supply system will
comprise in fact two traditional 48V DC system chains ,
each including:2 rectifiers simulteneusly operating in
parallel ,
1 lead-acid stationary type battery ,
1 distribution board,
An inter-connection between the 48V DC power supply
system distribution boards which will be left normally
opened under normal operating conditions.7.3.2. Sizing
the 48V DC system in Control Centre
The minimum sizing for each DC system chain will be one
800Ah battery and two 160A rectifires .
6.4. 48V DC system in sub-station
6.4.1. General
Communication and telecontrol means of sub-stations are
power supplied under a mean voltage of 48V DC with
possible link of the positive polarity end to the earth.For
this purpose, we must have DC systems suited to the new
equipment.
The following operational figures are usually used for the
48V DC systems plus 20 degree Centigrade:
44
End- of-discharge voltage per lead-acid cell:1.90V
Floating battery mode voltage per lead-acid cell :2.20V
Equalisation mode voltage per lead-acid cell :2.30V
Manual commissioning boost mode per lead-acid :2.70V
Elementry lead-acid stationary type cell quantity: 24
6.4.2. 48V DC system making-up in sub-station
A sub-station 48V DC system compries2 rectifires
simultaneously operating in parallel and sharing the total
current demand
1 lead-acid battery
1 distribution board
6.4.3. 48V DC system sizing and BOQs in sub-stations
Adequately sized batteries and rectifires will be provided
by some SEBs/boards/central Sectors themselves as a
part of the sub-station power/plant components.
7. TOTAL COST BENEFITS OF THE PROJECT
7.1 General
As a matter of the fact , once a utility’s network has reached a
certain level of development a modern control system becomes
and absolute necessity, and the question of its profitability is
almost secondary .However , even though a precise economic
analysis is not possible , in view of the system’s nature , it is
usual practice to evaluate such a project by advantages that it
offers to the utility .These advantages fall into the following two
categories:
Economically quantifiable benefits Intangible benefits
45
7.2 Economically quantifiable benefits
The economically quantifiable benefits may be classified into four
main categories:
Improvement of system reliability and reduction of undelivered
energy.
Saving in operating costs.
Capital investment savings.
Reduction of personnel costs.
These benefits have been evaluated on the basis of field data
related to disturbances and on some figures recommended by
international agencies.Improvement of system reliability and
reduction of undelivered energy
The benefits expected in this area are mainly based on two
aspects : System security will be considerably improved by
providing the operater with real-time information and also by the
various EMS functions.They will avoid numerous cascade
trippings both at an area level and at the Region level.For the
trippings and disturbances which will occur anyway, the
restoration to normalcy will be significantly speeded up. A
savings of 20 to 30 minutes in restoration time is more than
plausible.To estimate the reduction of undelivered energy we
may consider that the control scheme will make it possible to
avoid one tripping per year of the entire Northern grid and that
restoration time will be
halved. Assuming that a general collapes lasts one hour , in
1995:Avoidance of one tripping during one hour :
E=110841 MkWh/8760*1= 12.65 MkWh
Reduction of restoration time:
46
110841 MkWh / 8760 * 0.5 = 6.33 MkWh
i.e.: 19 MkWh /year.
Assuming that the cost of undelivered energy is 20 times the cost
of generation which is also a standard value and that the cost of
generation in Northern Region is Rs 12 lakhs / MkWh, then
theyearly benefit in this area expected from the control scheme is
:
19 * 12 * 20 = Rs 4560 lakhs per year
i.e. Rs 45.6 Crores per year.
Operating costs savings
The reduction of operation costs is mainly expected from a
reduction
in fuel expenditures
The control schemes enables a reduction of fuel outlays for three
reasons:
an integrated management of all generation facilities in Northern
Region during the operation planning stage will enable a better
use of the thermo-hydroelectric generation pattern in real-
time .This benefit is expected to be at least 0.5 % of fuel
costs .inter-State exchange possibilities in real-time will be
enhanced.Therelated benefit is expected to be 0.2% of fuel costs
.The total energy saved can be estimated at 0.7%.The yearly
benefit will be , in 1995 , assuming a Rs 12 lakhs /MkWh
generation cost:
110841 * 0.7 % * 12 = Rs 9310 lakhs /year
i.e.: Rs 93.1 Crores per year.
47
Capital investment savings
Capital investment savings are expected both for generation
facilities and for transmission networks facilities .For generation
facilities and due to peak power storage for the Northern grid ,
these savings are quite real in so far as there is a correlation
between the energy saved and the additional capacity installed to
supply this lost energy .
It may be anticipated that 0.35 % of additional installed capacity
could be saved for an equivalent quality of service if 0.7% of
energy is saved by the implementation of the control
scheme .With a 12, 258 MW additional installed capacity planned
for 1995 , the saving is 43 MW.
Assuming a hydro-thermal mix of 35/65 in installed capacity and
Rs 3.5 crores /MW of hydel capacity and Rs 3crores /MW of
thermal capacity , the capital investmentSaving for generation
facilities is :
43 * 0.35 * 3.5 + 43 * 0.65 * 3 = Rs 137 Crores
Reduction of personnel costs
The following considerations are also valid.
A measure benefit due to SCADA is the increased effectiveness
of theLoad Despatch personnel which can be achieved .Load
dispatch personnel spend an inordinate amount of time on paper
work . Automated logging and reporting software can drastically
reduced this tedious tasks.
It is extremely important that load dispatch personnel be relieved
of manual report preparation task and equipped to concentrate
on operating the system with complete and accurate information.
48
It would have been possible to quantify the reduction of
personnel costs.
7.3 Intangible Benefits
The intangible benefits expected from a control scheme are
numerous
.The following considerations are extracted from the CIGRE
paper mentioned before :
Better management information
SCADA systems contain facilities to retrieve data required for
preparation of reports and “time tagging” of events for post
mortem analysis.These reports and data are useful to operational
staff in verifying that protection equipment operated correctly in
response to a fault.System statistics suitable for generation and
transmission planning studies may be store.This has influence in
optimizing the hydro operation . It is important if the amount of
the water for power generation is less than volume available in
an average year .
Quick adoption of new operating philosophips according to the
development of the power system requires flexibility , which can
be reached in a Control Centre .Improved Reliability Procedures
It is normal practice to switch capacitors , reactors and cables at
different times during the day for voltage control purposes. Circuit
–breakers in the transmission network may be opened or closed
to limit short circuit levels .
Improved Operator Training
Operator training simulators are available today . The opening /
closing of breakers , tap changing of transformers , etc. can be
simulated without affecting the status /security of the actual
49
power system . Network analysis training will also guarantee
higher level of understanding the features of a power network .
Organization Improvent
Establishment of a control centre means that during the
implementation phase most operations , planning and monitoring
functions are critically reviewed . This often means a complete
reorganization of the entire organization which in the long run will
result in more efficient power system operations.Technology
transfer will assist the Utility in future attempts to rationalize and
improve operations by using computer technology.
Other Non-technical Factors
Most Utilities in developing countries are linked closely to Central
Government . The Utility are urged for political reasons to
increase their operating reliability . Some of the reasons for this
are :Governments are concerned about the substantial lost
revenues that industries suffer when power interruptions
occur ;Governments are usually interested in attracting foreign
companies and other investments to their countries . High
operating reliability of a country’s power supply is a major factor
in encouraging foreign investment ;
Governments are concerned about security problems during
blackouts . Police force and damage costs due to social “unrest”
can be high . Loss of faith in the ability of the country to handle
social problems can be even higher ;Governments are
concerned about their image . Blackouts and unreliable electric
supply are embarrassing.Most of these considerations apply in
the case of the control scheme for the Northern Regional grid.
8. CONCLUSION
50
The various economically quantifiable benefits expected from the
implementation of the Northern Regional Control scheme are summarized
below :
Yearly recurrent benefits :
Improvement of system security and reduction of undelivered
energy
: Rs 45.6 Crores per year.
Operating cost savings: Rs 93.1 Crores per year.
Totalling Rs. 137.7 Crores per year.
Capital investments savings :
Generation facilities : Rs. 137 Crores.
Transmission facilities : Rs. 21 Crores.
With a 447 Crores Project would be paid off in :
( 447 – 158) / 137.7 = 2.1 years
51
Control Hierarchy – NR
JALLANDHAR IISub-L.D.C. of
P.S.E.B.
LALTONKALANSub-L.D.C. of
P.S.E.B.
MOGA *Sub-L.D.C. of
P.S.E.B.
PATIALAS.L.D.C. of
P.S.E.B.
SHIMLAS.L.D.C. ofH.P.S.E.B.
KUNIHARSub-L.D.C. of
H.P.S.E.B.
HAMIRPURSub-L.D.C. of
H.P.S.E.B.
PANIPATS.L.D.C. ofH.S.E.B.
NARWANASub-L.D.C. of
H.S.E.B.
DADRISub-L.D.C. of
H.S.E.B.
HEERAPURAS.L.D.C. of
R.S.E.B.
RATANGARHSub-L.D.C. of
R.S.E.B.
KOTASub-L.D.C. of
R.S.E.B.
BHILWARASub-L.D.C. of
R.S.E.B.
LUCKNOWS.L.D.C. ofU.P.S.E.B.
RISHIKESHSub-L.D.C. of
U.P.S.E.B.
VARANASISub-L.D.C. of
U.P.S.E.B.
MORADABADSub-L.D.C. of
U.P.S.E.B.
SULTANPURSub-L.D.C. of
U.P.S.E.B.
PANKISub-L.D.C. of
U.P.S.E.B.
MINTO ROADS.L.D.C. ofD.E.S.U.
BAWANASub-L.D.C. of
D.E.S.U.
GOPALPURSub-L.D.C. of
D.E.S.U.
GAZIPURSub-L.D.C. of
D.E.S.U.
BAMNAULISub-L.D.C. of
D.E.S.U.
CHANDIGARHS.L.D.C. ofB.B.M.B.
DADRISub-L.D.C. of
B.B.M.B.
PANIPATSub-L.D.C. of
B.B.M.B.
JAMALPURSub-L.D.C. of
B.B.M.B.
GANGUWALSub-L.D.C. of
B.B.M.B.
GLADNIS.L.D.C. of
J & K
BENIMASub-L.D.C. of
J & K
KANPUR
C.P.C.C.
R.S.C.C.DELHI
53
Control Hierarchy – NR
RSCC
SLDCJ&K
(GLADNI)
SLDCBBMB
(CHANDIGARH)
SLDCHPSEB
(SIMLA)
SLDCDVB
(DELHI)
SLDCHVPNL
(PANIPAT)
SLDCPSEB
(PATIALA)
SLDCRSEB
(HEERAPURA)
SLDCUPSEB
(LUCKNOW)
SUBLDC(5)
SUBLDC(1)
SUBLDC(4)
SUBLDC(2)
SUBLDC(4)
SUBLDC(2)
SUBLDC(2)
SUBLDC(3)
CPCC
RTUs RTUs RTUs RTUs RTUs RTUs RTUs RTUs
RTUs
Control Hierarchy – NR
RSCC
SLDCJ&K
(GLADNI)
SLDCBBMB
(CHANDIGARH)
SLDCHPSEB
(SIMLA)
SLDCDVB
(DELHI)
SLDCHVPNL
(PANIPAT)
SLDCPSEB
(PATIALA)
SLDCRSEB
(HEERAPURA)
SLDCUPSEB
(LUCKNOW)
SUBLDC(5)
SUBLDC(1)
SUBLDC(4)
SUBLDC(2)
SUBLDC(4)
SUBLDC(2)
SUBLDC(2)
SUBLDC(3)
CPCC
RTUs RTUs RTUs RTUs RTUs RTUs RTUs RTUs
RTUs
54