Trainee Report 2010
-
Upload
slimshady125125 -
Category
Documents
-
view
216 -
download
0
Transcript of Trainee Report 2010
-
8/9/2019 Trainee Report 2010
1/54
1. INTRODUCTION-THE NORTHERNREGION POWER SYSTEM
1.1 Background
India has been divided into five Electricity Boards viz., southern,
northern, western, eastern and north-eastern for the purpose of power
system planning and operation.
The Northern Regional Grid is composed of the generation, transmission
and distribution facilities of the following State Electricity Boards and
other national/regional agencies:
Himachal Pradesh Electricity Board (HPSEB)
Haryana Vidyut Prasan Nigam Limited (HVPNL)
-
8/9/2019 Trainee Report 2010
2/54
Haryana Vidyut Prasan Nigam Limited (HVPNL)
-
8/9/2019 Trainee Report 2010
3/54
Kashmir, Bhakra Beas Management board, Delhi Electric Supply
Undertaking and Central Sector.
Central power stations are regional in character and meant for the
benefit of all the States of the Region. Presently, power from a
Central Power Station is allocated to the various Constituents in
accordance with the following general agreed formula for sharing
of power:
1. 15% power is kept unallocated at the disposal of
Government of India to meet the urgent requirement of the
individual beneficiary States from time to time.
2. 10% of the power is kept allocated to the State in which the
power station is located.
3. The remaining 75% power is distributed amongst the
beneficiary States (including the home State) in
accordance with the energy consumption of these States
and the Central Plan Assistance to them
-
8/9/2019 Trainee Report 2010
4/54
GOI agreed with a three-phase development for Powergrid.
During phase 1, CEA would continue to operate the existing
RSCCs (Regional Systems Control Centres), while Powergrid
takes over transmission facilities from NTPC, NHPC, etc. and
undertakes projects to develop new RSCCs. Then Powergrid
would own and operate the project facilities and take over related
existing facilities from CEA not later than at the completion of the
project marking the commencement of phase 2, viz.
establishment/ augmentation of load dispatch and communication
facilities in various Regions. During phase 1, Powergrid will need
immediate access to and use of the existing control facilities at
the Regional level (present RSCC), co-operation with the various
constituents of REBs and CEA, to facilitate improved operation of
its transmission system, to help ensure a smooth transfer of old
system operational functions from CEA to Powergrid and to
facilitate the implementation of the new RSCC.
-
8/9/2019 Trainee Report 2010
5/54
2. CURRENT INSTITUTIONAL ANDOPERATIONAL PROBLEMS IN THENORTHERN REGION2.1 Current institutional arrangements
The task of regional grid management is vested with the NREB and they
have to co-ordinate the operation of autonomous Central and State
sector organizations in the Region. Under this set up the NREB has to
derive their power from the constituents. Lack of proper communication
and real time load dispatch facilities is the biggest constraint in effective
operation and control of the grid The NREB as association of the
-
8/9/2019 Trainee Report 2010
6/54
2.2 Operational guidelines and discipline
2.2.1 Operational discipline
It is necessary to have proper agreements spelling out the
operations regimes, obligation of suppliers as well as the
beneficially States in terms of maintaining the system parameters,
reliability criteria, penalties for violation of agreed operating
regimes, etc.
The operating norms should cover not only the normal state of
operation of the power system but also the alert, emergency and
restorative states.
At present there are no means to enforce the operational
discipline. In case of overdraws of power by any State, the
Regional Load Despatch Centre (RSCC) can onl req est the
-
8/9/2019 Trainee Report 2010
7/54
2.2.2 Frequency maintenance problems
The grid management problems of the country are compounded
by continuing power shortages in the different systems. While the
demand for power has been increasing at a rapid pace the
generation availability has not been keeping pace with it. The
short fall in availability is due to delays in commissioning for
generating units, lack of funds for construction, problems in
quality of coal and equipments, high level of forced outages, etc.
In most power systems in the world, the system frequency is kept
virtually constant and a combination of generator governors and
automatic generation control systems constantly control the
generators so that:
The total generation is kept equal to the total load and,
Generators are operated at the levels at which the total cost of the
power generated is at the minimum consistent with safe system
ti
-
8/9/2019 Trainee Report 2010
8/54
either case is that the SEB that fails to shed load as agreed
receives more energy than it is entitled to, and the other receives
less.
During light load periods, those SEBs that should back down on
their more expensive units fail to do so. The result is that central
units with lower production cost must be back down instead,
resulting in uneconomical operation of the regional system. In
some cases, hydro units with full reservoir are required to back
down their output resulting in wasteful spilling of water over the
dense.
2.2.3 Lack of flexibility in generation scheduling at present the
energy invoicing is based on a single tariff system with
regards to the actual energy transfers metered under tie-
lines.
-
8/9/2019 Trainee Report 2010
9/54
2.3 Deficiencies in power transmission system
2.3.1 Power transmission lines and sub stations
The transmission system is being planned on a regional basis and
optimized without regard to ownership under the responsibility of
CEA. The establishment of central sector power plants hasincreased the complexity of the regional network by super
imposing a transmission system to the transmission system of the
SEBs.
With a view to optimizing investment, the regional transmissionsystems have been developed on the assumptions that the
shares of some state located far away from the central stations
would be delivered on the principles of net inter states exchanges
where ever feasible without affecting the reliability and security of
the transmission system.
-
8/9/2019 Trainee Report 2010
10/54
networks are very low voltage level at receiving end at the peak,
power swings involving cascade tripping and /or systems
isolations and collapses, massive loss of generation, voltage
collapses, partial and sometimes total power supply failure. One
of the numerous regions for these mishaps is due to the particular
weakness of the 400kv network and its long radial structure that
should be strengthened and reinforced by more intermediate
step-down substations.
2.3.2 Compensation means
Reactive power management has not received the attention it
deserves. Bulk of the present reactive power is being supplied by
the generating plants thereby resulting in large flows of reactive
power all over the transmission and distribution networks towards
the load points from the generating units that are most of them
l t d f f th l d Th l lt l l
-
8/9/2019 Trainee Report 2010
11/54
3. OPERATIONAL AND CONTROLPHILOSOPHY
3.1 Basic operational and functional requirements
-
8/9/2019 Trainee Report 2010
12/54
During the operation planning stage, the basic tasks to be carried out
are:
State wise generation scheduling and load prediction for a
complete day, week, month and year
Determining of the share of each State in Centrally owned
generation on given day
Scheduling of inter-State and inter-Regional exchanges for
a given day
Updating maintenance schedule for generators,
transformers, transmission and/or distribution lines
Spinning reserve assistance
Co-ordination with National Load Dispatch Centre in the
future
Collection of data regarding weather forecasts
Analysis of system performance under disturbances and
devising remedial actions to minimize their effects
-
8/9/2019 Trainee Report 2010
13/54
It is clear that operation of such a large system requires one to set up a
control hierarchy, which will also match the power system organization in
the Region. With this end in mind, a 3-tier hierarchical network has
already been defined , complying with the load dispatch facilities policy
established by Central Electricity Authority (CEA) for all India.
The following load dispatch centers are proposed to be implemented at
the different hierarchical levels:
Hierarchy level 1:
Regional System Control Centre at Delhi covering the region power
systems of Himachal Pradesh, Haryana, Jammu and Kashmir, Punjab,
Rajasthan, Uttar Pradesh, BBMB, DESU, Chandigarh.
Hierarchy level 2:
Comprising State Load Dispatch Centres (SLDCs) and Central Project
Control Centres as below:
SLDC f Hi h l P d h t Shi l
-
8/9/2019 Trainee Report 2010
14/54
Sub-load Dispatch Centres (Sub-LDCs) as below:
Sub LDCs at Kunihar and Hamirpur controlled by SLDC at Shimla
(Jutogh)
Sub LDCs at Dadri, Panipat TPS and Narwana controlled by
SLDC at Panipat;
Sub LDCs at Pampore and Udampur controlled by SLDC at
Udampur (NB: Udhampur Sub LDC is located in the same control
room as the SLDC);
Sub LDCs at Jallandhar, Lalton Kalan and Patiala controlled by
SLDC at Patiala.
Sub-LDCs at Ratangarh, Kota, Bhilwara and Heerapura controlled
by SLDC at Heerapura.
Sub-LDCs at Rishikesh, Moradabad, Panki, Varanasi and
Sultanpur controlled by SLDC Lucknow.
3.3 Functions of the Control Centres and sharing out of
ibiliti
-
8/9/2019 Trainee Report 2010
15/54
The RSCC shall be responsible for the following:
Data acquisition and monitoring of all the transmission system at 220
kV and above, plus the 132 kV interstate lines and all the generating
stations of 50 MW and above.
Supervisory control of the power system operation pertaining to inter-
State/ Regional grid and control of central sector sub-station under its
direct jurisdiction.
Management and supervisory control of the centrally owned
generating unit. Load frequency control for the entire region and
sending corrective area control error messages to all the
constituents.
Monitoring inter-state exchanges of power with references to
schedule and AGC orders.
-
8/9/2019 Trainee Report 2010
16/54
Generation load management according to economic generation
Optimization carried out at state level and according to RSCC
request for inter-state power transfers and frequency regulation.
Transmission of orders directly to state owned power stations from
the state requirements.
Voltage and reactive power control.
3.6 Responsibilities of the Sub-LDCs
The Sub-LDCs will be responsible of the following:
Switching of equipments at 220 and 400 kV as per direction SLDC
V lt d ti t l ith i th i f ibilit
-
8/9/2019 Trainee Report 2010
17/54
-
8/9/2019 Trainee Report 2010
18/54
4.2 Data Transmission Principles
The circuit breakers positions are collected under the shape of
double signals (DS) as this is necessary for remote control functions,
also these are more reliable.
The isolators positions are given single signal as these are not
needed for remote control.
For all apparatus positions, the information will be transmitted
when change of status occurs.
All possible alarms are collected under single signals.
4.3 Principles for Data Acquisition
4 3 1 B b ti
-
8/9/2019 Trainee Report 2010
19/54
33 kV: no value.
c) SS:
1 SS for loss of voltage per busbar.
4.3.2 Busbar coupler and bus section breaker
DS: 1 DS per circuit breaker.
SS: 1 SS for only one out of the 2 disconnectors.
4.3.3 Bus transfer
DS: 1 DS per circuit breaker.
SS: 1 SS for each disconnector on both sides of the C.B.
4.3.4Busbar disconnector
-
8/9/2019 Trainee Report 2010
20/54
1 SS for each bus selector disconnector in case of
single breaker arrangement.
1 SS for each disconnector in case of one-hand-half
breaker arrangement.
4.3.7 Gas generator and Hydroelectric Generator (substation
side)a) Active power:1 value.
b) Reactive power:1 value.
c) DS:
- 1 DS per substation circuit-breaker
- 1 DS per generator bus coupler
d) SS:
- 1 SS for each bus selector disconnector in case of
single breaker arrangement.
- 1 SS for each disconnector in the case of one-and-half
breaker arrangement.
-
8/9/2019 Trainee Report 2010
21/54
substation are to be described as overhead line connections and
remote generators as follows:
- 1 DS per circuit-breaker(if existing for outgoing feeder),
- 1 DS per generator bus coupler,
- one value of P for gross active output of a thermal
generator,
- one value of Q for gross reactive output of a thermal
generator.
4.3.10Overhead line
a) Active power and reactive power
- 400, 220 and 132 kV: one value of P and Q for each
outgoing line .
- 66 kV as a secondary part of Regional interest
substation: one value of P and Q only for outgoing inter-
system tie-line.
33 kV l
-
8/9/2019 Trainee Report 2010
22/54
- 1 SS for each by-pass disconnector in case of single
breaker+by-pass arrangnment
d) DC
- 1 DC for each 132 kV outgoing line.
The choice consisting in the implementation of remote control
only for 132kv feeders and below can be justified by the needs of
quick switching operation requirements for load shedding and
emergency action.
In some particular cases, some remote control facilities may be
interesting also for 220 kV or 400 kV components of the grid.
These specific requirements shall be precisely defined at
technical specification drafting.
4.3.11 Transformers
-
8/9/2019 Trainee Report 2010
23/54
whenever the load supplied by the transformers is
significant.
c) OLTC
The position of each On Load Tap Changer is indicated
with a digital or analog tele measuring. This shall be
specified for each individual case at specification drafting.
d) DS:
1 DS per circuit breaker. If the secondary level doesnt
belong to same network, 1 DS shall also be collected for
the secondary circuit breaker.
e) S S:
1 SS for each bus selector disconnector in
case of single breaker arrangement.
-
8/9/2019 Trainee Report 2010
24/54
-
8/9/2019 Trainee Report 2010
25/54
Magnetic tape storage devices or equivalent
equipment,
Failover system,
Line printer,
Software package,
One time & frequency system,
One receiver for time synchronization signals.
Man machine interface
Control room:
Two dispatcher consoles with two VDUs each, Two hard copy units linked to any console,
Two loggers and one plotter,
One line printer,
One frequency recorder,
-
8/9/2019 Trainee Report 2010
26/54
Reduced equivalent network,
Logical controls,
State estimation,
Contingency analysis,
Load flow,
LFC,
One local RTU.
5.2 SLDCs scope of supply
Two categories of SLDCs have been considered in the northern region,
depending on the size of the constituent:
1st category (large sized SLDC): Lucknow, Heerapura.
2nd category (standred sized SLDC): Shimla, Panipat,
-
8/9/2019 Trainee Report 2010
27/54
One time and frequency system,
One receiver for time synchronization signals.
Man Machine Interface
Control Room:
Dispatcher consoles:
- For SLDCs: 2 dispatcher consoles each with two VDUs,
- For large mixed SLDC/sub-LDC: 3 dispatcher consoles
each with two VDUs.
Two hard copy units linked to any console,
Two loggers and one plotter,
One line printer,
One frequency recorder,
One mimic board along with its driver,
-
8/9/2019 Trainee Report 2010
28/54
Network topology,
Reduced equivalent network,
Logical controls,
State estimation,
Contingency analysis,
Load flow, LFC.
Option two for EMS:
One computer,
At least two disk storage units with controllers,
One streamer or magnetic tape storage device,
One line printer,
Two programming terminals,
One software package.
-
8/9/2019 Trainee Report 2010
29/54
failover system,
line printer,
software pakage:
one time and frequency system,
one receiver for time synchronization signals
-Main Machine interface
-Control Room:
3 PC workstations,
two hard copy units linked to any console,
two loggers,
one line printer ,
one plotter,
one frequency recorder,
one mimic board along with its driver,
one audible alarm.
-computer section:
-
8/9/2019 Trainee Report 2010
30/54
These are :
RTU(substation level )
Sub-LDC, 3rd tier
SLDC or CPCC, 2nd tier
RSCC, 1st tier.
All the state owned RTUs are only linked to Sub-LDCs. Thus a data
communication protocol and procedure shall be provided for this first
layer.
The data transferred on these links are:
Either real-time data
Or files
Or data related to remote logging procedures.
In order to enable all these data transfers between computers, it is
mandatory to have in each control center a communication software
which implements the seven layer of Open System Interconnection(OSI)
ISO Recommendation.
The OSImodel in seven layers is the following one:
-
8/9/2019 Trainee Report 2010
31/54
for acquisition,processing, transmission and display of the necessary
process information. The performance of a telecontrol system is
determind basically by:
The data integrity of information transfer, from a source to its
destination , and ,
The speed with which information is transferred to its
destination.
Since telecontrol systems have to operate in real-time mode, limitations
imposed by the telecommunication channels may heavily impair the
overall system efficiency.The implicatin is restricted bandwidth and
hence restricted bit rates to be transmitted under noisy environment
conditions, which cause distortion of transmitted signals elements. The
data transmission system has to be considered in the sense as an
integrated part of the telecontrol system.
Basic requirements of the data transmission system
Data transmission should fulfill the following requirements:High data
-
8/9/2019 Trainee Report 2010
32/54
required.The data link protocol accepts and transmits arbitrary bit
sequence structures from the data source.
Transmission software and protocol specifications
Transmission software arrangment
For standardization reasons and easy future upgrading of the Data
Transmission Network(DTN) to packet switching, communication
software is based over the latest ISO(CCITT) standards in force
implementing the ISOs OSI model.This subdivision into modular layers
is a useful theoretical model for difining standards. Each layer is
essentially independent of the layers below and above it. It treats the
layer below as a service function and the layer above as a master
with witch it exchanges data and to which it reports errors.
The independent of the layers gives a modularity to the system. It
ispossible to alter one layer without altering others, in the some layers
may be omitted.Telecontrol system functions will be divided into the
-
8/9/2019 Trainee Report 2010
33/54
The protocol to be used for RTU-sub-LDC links and for direct RTU-
RSCC links will be one of the following by order of decreasing
preferences:
- X.25(up to layer 2), -IEC 870-5-1, -Manufactrurs specific.If one of
the first 2 solutions is proposed, it must not induce additional cost with
respect to the manufcturers specific solutions.
The protocol to be used for inter LDClinks will be the X.25 with the
option and particulars alredy applied by department of science and
technology in consulation with CEA.
5.7. Physical structure of the protocol system
5.7.1. General
The structure of the data communication network which is thus a
sub-set of the telecommunication system is mainly determined by
the operational philosophy, i.e.:
National Control Centre,
Regional Control Centre,
-
8/9/2019 Trainee Report 2010
34/54
Transmission link redundancyIn order to maintain a high quality of
service with strategic sites, the physical communication links
arriving on the latter will be duplicated. This will be the case
atleast for:
The links arriving on 400/200kv substation and power station
RTUs,
All the links interconnecting contral centers.
5.8. Transmission modes
5.8.1. Transmission initiation modes
In the case if RTU/sub-LDC links, two basic transmission initiating
modes will be used for telecontrol data transmission:
Event initiated transmission(spontaneous transmission, also
called master-master),
Transmission on demand(interrogative or polling mode, also
called master-slave).
-
8/9/2019 Trainee Report 2010
35/54
For sub-LDC/SLDC links:1200 Bds(1200 bits/s), FSK, CCITT V-
23, 4-wire.
For higher hierarchical rank inter-computer links:4800 Bds(4800
bits/s), phase modulation, CCITT V.29.
For RTUs:
All RTUs would be configured to work at 200 bauds on FSK
channels located above the 300 to 2.4 kHz speech sub-bands of
4 kHz VFTs.
5.10. Modems
5.10.1. Basic requirement of RTUs modems
Frequency shift channel modems are to be used to convert a
binary signal into two distinct frecuencies.The rack modem of
RTU will contain 2 single-card modem boards.The modem will
accept CCITT V.24 serial signals and communicates at the
standardized data rates from 50 to 1200 bauds.
-
8/9/2019 Trainee Report 2010
36/54
Sequential Event recording :
TTY will be provided only at 400kv, 220kv substation and power
station sites.
5.11.2. Charateristics of RTU I/O circuits
RTU will be capable of accepting :Single point information
indication signals, double point information indication signals,
telemetering signals, under the form of potential free contacts.
RTU will be capable of issuing:Single point digital controls,
Double point digital controls,
Under the form of potential free contacts .
RTU basic functional processing requirements
The RTU will be capable of time-tagging the status changes
with a 10ms resolution for transmission to the control centre as
well as local editing on a TTY terminal(sequential event
recording)RTUs bills of quantitiesAn RTU will equip each side
that will be under supervisory. For power station and the control
-
8/9/2019 Trainee Report 2010
37/54
-
8/9/2019 Trainee Report 2010
38/54
efficient, reliable and modern communication system for the Power
authorities. Keeping in view the specific and the Government of India has
recommended an independent Dedicated communication system to be
owned and operated by the Power Utilities up to the State Load
DESPATCH CENTRE level from remote power stations and substations .
As recommended by the Working Group and the Secretariess Steering
Committee, the Government of India decided to appoint a Consultant of
repute for the planning of a comprehensive communication systems for
the Power Sector .
Merz & Mac Lellan (MML) , U.K. , in association with Bharat Electronics
Ltd.(India) working as Consltants to the Central Electricity Authority have
submitted , among other reports, a detailed Project Report for
Telecommunication system of Northern Region including all Constituents
and have recommended for wide-ranging strengthening of
Telecommunication network and requisite organization structure. These
reports have been prepared with active participation of Engineers from
CEA/NREB/SEBs.Electricite de France International(EDF), Consultant for
-
8/9/2019 Trainee Report 2010
39/54
The telecommunication part of the project will cater for the requirements of
the load dispatch computerized scheme in respect of the following
:Speech and data transmission for system operation and control,
Transmission of operational data for generation of reports and statistical
information.
The hierarchy of communication network will start from Remote Terminal
Units at remote substations/power stations participating significantly in the
intrigrated operation of the Northern grid and terminate at Sub Load
dispatch centers .
The communication system will support the following applications
Speech communication on express /dialing basis ,
Data transmission
Teleprinting
Facsimile transmission.
6.2.1. Structure of the switched PABX network
The switched PABX network is designed to provide voice
communication .
-
8/9/2019 Trainee Report 2010
40/54
channel required to protect a line or to transmit a control single is a vital
part of the total system .The consultants have recommended generally
and independent telecommunication network owned and operated by
power utilities .Howerever , DOT lines are proposed from SLDCs
/CPCCs to RLDCs and sub LDCs to SLDCs for back up speech and
data circuits .
Planning Philosophy
For communication between RTUs and sub-LDC , PLCC has been
recommended by the constants , as their requirement is generally not
more than 4 channels which can be accommodated by PLCC .A 200
baud channel , required for RTU communication , can readily be
accommodated above the 300 Hz to 2.4 KHz speech band in a 4 KHz
wide PLC channel . The speed of composite data transmission beyond
sub-LDC is about 1200 baud . This requirment can not be met by PLCC
alone and multichannel system /leased DOT channels have been
recommended by the MML consultants
General
-
8/9/2019 Trainee Report 2010
41/54
The HIMACHAL PRADESH proposed communication will comprise:1
radio link with 2 radio repeater stations1 fiber optic link without repeater
station17 Nos of PLC links No DOT leased circuit.
HARYANA Communication system
The HARYANA proposed communication system will comprise :
7 radio links with 3 radio repeater stations1 fiber optic link without
repeater station (in total 15 Kms)
32 Nos of PLC links
No DOT leased circuit.
JAMMU & KASHMIR Communication system
The JAMMU & KASHMIR proposed communication system will
comprise:
No radio link
2 fiber optic links without repeater stations
25 Nos of PLC links
No DOT leased circuits
-
8/9/2019 Trainee Report 2010
42/54
1400 Kms of leased DOT circuits
Central sector communication system
The central sector communication system will comprise :
16 radio links with 6 radio repeater stations
5 fiber links with 6 repeater stations
79 Nos of PLC links
4005 Kms of leased DOT circuits .
Merits of the network
The merits of communication system so designed are as follows :
The major portion of the network is owned by the Power Sector.leased
DOT circuits have also been envisaged to support the dedicated
communication networkthe system caters for the present requirements
of administrative and operational speech channels with provision for
future growth .Since future expansion is likely to be along the radio /fiber
optic routes, it can be operated at very low cost if tower heights are
adequate, all the towers and parabolic antennas of the existing analogue
microwave back-bone in UTTAR PRADESH will be re-used for the new
-
8/9/2019 Trainee Report 2010
43/54
Power supplies for supply of :New RTU an interface cubicle , new
communication equipment , Data processing equipment in the various
control centers,Airconditioning and security lighting in Control Centres .
They are one of thefollowing types:
Uninterruptible DC source (or DC power system)
Uninterruptible AC source
Standby power supply.
In the scope of this project , it was generally decided by Powergrid and the
constituents that the DC power supply in the sub stations will not be
included.Thus , only the AC and DC power supplies for the sub-LDCs ,
CPCCs, SLDCs and RLCC will be considered .
7.2. AC auxiliary power supplies in Control Centres
7.2.1. Makingup of 415/240V AC uninterruptible power
supply in Control Centres
Two 415V, 3 phase AC supply together with an emergency diesel
generator will ensure a secure supply to the essential services
-
8/9/2019 Trainee Report 2010
44/54
A control center 48V DC power supply system will comprise in fact
two traditional 48V DC system chains , each including:2 rectifiers
simulteneusly operating in parallel ,
1 lead-acid stationary type battery ,
1 distribution board,
An inter-connection between the 48V DC power supply system
distribution boards which will be left normally opened under normal
operating conditions.7.3.2. Sizing the 48V DC system in Control
Centre
The minimum sizing for each DC system chain will be one 800Ah
battery and two 160A rectifires .
7.4. 48V DC system in sub-station
7.4.1. General
Communication and telecontrol means of sub-stations are power
supplied under a mean voltage of 48V DC with possible link of the
positive polarity end to the earth.For this purpose, we must have
DC systems suited to the new equipment.
-
8/9/2019 Trainee Report 2010
45/54
7.4.3. 48V DC system sizing and BOQs in sub-stations
Adequately sized batteries and rectifires will be provided by some
SEBs/boards/central Sectors themselves as a part of the sub-
station power/plant components.
-
8/9/2019 Trainee Report 2010
46/54
8.1 General
As a matter of the fact , once a utilitys network has reached a certain levelof development a modern control system becomes and absolute necessity,
and the question of its profitability is almost secondary .However , even
though a precise economic analysis is not possible , in view of the systems
nature , it is usual practice to evaluate such a project by advantages that it
offers to the utility .These advantages fall into the following two categories:
Economically quantifiable benefits Intangible benefits
8.2 Economically quantifiable benefits
The economically quantifiable benefits may be classified into four main
categories:
Improvement of system reliability and reduction of undelivered energy.
Saving in operating costs.
Capital investment savings.
Reduction of personnel costs.
These benefits have been evaluated on the basis of field data related to
disturbances and on some figures recommended by international
-
8/9/2019 Trainee Report 2010
47/54
halved. Assuming that a general collapes lasts one hour , in
1995:Avoidance of one tripping during one hour :
E=110841 MkWh/8760*1= 12.65 MkWh
Reduction of restoration time:
110841 MkWh / 8760 * 0.5 = 6.33 MkWh
i.e.: 19 MkWh /year.
Assuming that the cost of undelivered energy is 20 times the cost of
generation which is also a standard value and that the cost of generation in
Northern Region is Rs 12 lakhs / MkWh, then theyearly benefit in this area
expected from the control scheme is :
19 * 12 * 20 = Rs 4560 lakhs per year
i.e. Rs 45.6 Crores per year.
Operating costs savings
The reduction of operation costs is mainly expected from a reduction
in fuel expenditures
The control schemes enables a reduction of fuel outlays for three
-
8/9/2019 Trainee Report 2010
48/54
power storage for the Northern grid , these savings are quite real in so far
as there is a correlation between the energy saved and the additional
capacity installed to supply this lost energy .
It may be anticipated that 0.35 % of additional installed capacity could be
saved for an equivalent quality of service if 0.7% of energy is saved by the
implementation of the control scheme .With a 12, 258 MW additional
installed capacity planned for 1995 , the saving is 43 MW.
Assuming a hydro-thermal mix of 35/65 in installed capacity and Rs 3.5
crores /MW of hydel capacity and Rs 3crores /MW of thermal capacity , the
capital investmentSaving for generation facilities is :
43 * 0.35 * 3.5 + 43 * 0.65 * 3 = Rs 137 Crores
Reduction of personnel costs
The following considerations are also valid.
A measure benefit due to SCADA is the increased effectiveness of theLoad
Despatch personnel which can be achieved .Load dispatch personnel spend
an inordinate amount of time on paper work . Automated logging and
reporting software can drastically reduced this tedious tasks.
-
8/9/2019 Trainee Report 2010
49/54
influence in optimizing the hydro operation . It is important if the amount of
the water for power generation is less than volume available in an average
year .
Quick adoption of new operating philosophips according to the development
of the power system requires flexibility , which can be reached in a Control
Centre .Improved Reliability Procedures
It is normal practice to switch capacitors , reactors and cables at different
times during the day for voltage control purposes. Circuit breakers in the
transmission network may be opened or closed to limit short circuit levels .
Improved Operator Training
Operator training simulators are available today . The opening / closing of
breakers , tap changing of transformers , etc. can be simulated without
affecting the status /security of the actual power system . Network analysis
training will also guarantee higher level of understanding the features of a
power network .
Organization Improvent
Establishment of a control centre means that during the implementation
-
8/9/2019 Trainee Report 2010
50/54
Governments are concerned about security problems during blackouts .
Police force and damage costs due to social unrest can be high . Loss of
faith in the ability of the country to handle social problems can be even
higher ;Governments are concerned about their image . Blackouts and
unreliable electric supply are embarrassing.Most of these considerations
apply in the case of the control scheme for the Northern Regional grid.
-
8/9/2019 Trainee Report 2010
51/54
Capital investments savings :
Generation facilities : Rs. 137 Crores.
Transmission facilities : Rs. 21 Crores.
With a 447 Crores Project would be paid off in :
( 447 158) / 137.7 = 2.1 years
---------------********************************-----------------
-
8/9/2019 Trainee Report 2010
52/54
-
8/9/2019 Trainee Report 2010
53/54
-
8/9/2019 Trainee Report 2010
54/54