Trainee Report 2010

download Trainee Report 2010

of 54

Transcript of Trainee Report 2010

  • 8/9/2019 Trainee Report 2010

    1/54

    1. INTRODUCTION-THE NORTHERNREGION POWER SYSTEM

    1.1 Background

    India has been divided into five Electricity Boards viz., southern,

    northern, western, eastern and north-eastern for the purpose of power

    system planning and operation.

    The Northern Regional Grid is composed of the generation, transmission

    and distribution facilities of the following State Electricity Boards and

    other national/regional agencies:

    Himachal Pradesh Electricity Board (HPSEB)

    Haryana Vidyut Prasan Nigam Limited (HVPNL)

  • 8/9/2019 Trainee Report 2010

    2/54

    Haryana Vidyut Prasan Nigam Limited (HVPNL)

  • 8/9/2019 Trainee Report 2010

    3/54

    Kashmir, Bhakra Beas Management board, Delhi Electric Supply

    Undertaking and Central Sector.

    Central power stations are regional in character and meant for the

    benefit of all the States of the Region. Presently, power from a

    Central Power Station is allocated to the various Constituents in

    accordance with the following general agreed formula for sharing

    of power:

    1. 15% power is kept unallocated at the disposal of

    Government of India to meet the urgent requirement of the

    individual beneficiary States from time to time.

    2. 10% of the power is kept allocated to the State in which the

    power station is located.

    3. The remaining 75% power is distributed amongst the

    beneficiary States (including the home State) in

    accordance with the energy consumption of these States

    and the Central Plan Assistance to them

  • 8/9/2019 Trainee Report 2010

    4/54

    GOI agreed with a three-phase development for Powergrid.

    During phase 1, CEA would continue to operate the existing

    RSCCs (Regional Systems Control Centres), while Powergrid

    takes over transmission facilities from NTPC, NHPC, etc. and

    undertakes projects to develop new RSCCs. Then Powergrid

    would own and operate the project facilities and take over related

    existing facilities from CEA not later than at the completion of the

    project marking the commencement of phase 2, viz.

    establishment/ augmentation of load dispatch and communication

    facilities in various Regions. During phase 1, Powergrid will need

    immediate access to and use of the existing control facilities at

    the Regional level (present RSCC), co-operation with the various

    constituents of REBs and CEA, to facilitate improved operation of

    its transmission system, to help ensure a smooth transfer of old

    system operational functions from CEA to Powergrid and to

    facilitate the implementation of the new RSCC.

  • 8/9/2019 Trainee Report 2010

    5/54

    2. CURRENT INSTITUTIONAL ANDOPERATIONAL PROBLEMS IN THENORTHERN REGION2.1 Current institutional arrangements

    The task of regional grid management is vested with the NREB and they

    have to co-ordinate the operation of autonomous Central and State

    sector organizations in the Region. Under this set up the NREB has to

    derive their power from the constituents. Lack of proper communication

    and real time load dispatch facilities is the biggest constraint in effective

    operation and control of the grid The NREB as association of the

  • 8/9/2019 Trainee Report 2010

    6/54

    2.2 Operational guidelines and discipline

    2.2.1 Operational discipline

    It is necessary to have proper agreements spelling out the

    operations regimes, obligation of suppliers as well as the

    beneficially States in terms of maintaining the system parameters,

    reliability criteria, penalties for violation of agreed operating

    regimes, etc.

    The operating norms should cover not only the normal state of

    operation of the power system but also the alert, emergency and

    restorative states.

    At present there are no means to enforce the operational

    discipline. In case of overdraws of power by any State, the

    Regional Load Despatch Centre (RSCC) can onl req est the

  • 8/9/2019 Trainee Report 2010

    7/54

    2.2.2 Frequency maintenance problems

    The grid management problems of the country are compounded

    by continuing power shortages in the different systems. While the

    demand for power has been increasing at a rapid pace the

    generation availability has not been keeping pace with it. The

    short fall in availability is due to delays in commissioning for

    generating units, lack of funds for construction, problems in

    quality of coal and equipments, high level of forced outages, etc.

    In most power systems in the world, the system frequency is kept

    virtually constant and a combination of generator governors and

    automatic generation control systems constantly control the

    generators so that:

    The total generation is kept equal to the total load and,

    Generators are operated at the levels at which the total cost of the

    power generated is at the minimum consistent with safe system

    ti

  • 8/9/2019 Trainee Report 2010

    8/54

    either case is that the SEB that fails to shed load as agreed

    receives more energy than it is entitled to, and the other receives

    less.

    During light load periods, those SEBs that should back down on

    their more expensive units fail to do so. The result is that central

    units with lower production cost must be back down instead,

    resulting in uneconomical operation of the regional system. In

    some cases, hydro units with full reservoir are required to back

    down their output resulting in wasteful spilling of water over the

    dense.

    2.2.3 Lack of flexibility in generation scheduling at present the

    energy invoicing is based on a single tariff system with

    regards to the actual energy transfers metered under tie-

    lines.

  • 8/9/2019 Trainee Report 2010

    9/54

    2.3 Deficiencies in power transmission system

    2.3.1 Power transmission lines and sub stations

    The transmission system is being planned on a regional basis and

    optimized without regard to ownership under the responsibility of

    CEA. The establishment of central sector power plants hasincreased the complexity of the regional network by super

    imposing a transmission system to the transmission system of the

    SEBs.

    With a view to optimizing investment, the regional transmissionsystems have been developed on the assumptions that the

    shares of some state located far away from the central stations

    would be delivered on the principles of net inter states exchanges

    where ever feasible without affecting the reliability and security of

    the transmission system.

  • 8/9/2019 Trainee Report 2010

    10/54

    networks are very low voltage level at receiving end at the peak,

    power swings involving cascade tripping and /or systems

    isolations and collapses, massive loss of generation, voltage

    collapses, partial and sometimes total power supply failure. One

    of the numerous regions for these mishaps is due to the particular

    weakness of the 400kv network and its long radial structure that

    should be strengthened and reinforced by more intermediate

    step-down substations.

    2.3.2 Compensation means

    Reactive power management has not received the attention it

    deserves. Bulk of the present reactive power is being supplied by

    the generating plants thereby resulting in large flows of reactive

    power all over the transmission and distribution networks towards

    the load points from the generating units that are most of them

    l t d f f th l d Th l lt l l

  • 8/9/2019 Trainee Report 2010

    11/54

    3. OPERATIONAL AND CONTROLPHILOSOPHY

    3.1 Basic operational and functional requirements

  • 8/9/2019 Trainee Report 2010

    12/54

    During the operation planning stage, the basic tasks to be carried out

    are:

    State wise generation scheduling and load prediction for a

    complete day, week, month and year

    Determining of the share of each State in Centrally owned

    generation on given day

    Scheduling of inter-State and inter-Regional exchanges for

    a given day

    Updating maintenance schedule for generators,

    transformers, transmission and/or distribution lines

    Spinning reserve assistance

    Co-ordination with National Load Dispatch Centre in the

    future

    Collection of data regarding weather forecasts

    Analysis of system performance under disturbances and

    devising remedial actions to minimize their effects

  • 8/9/2019 Trainee Report 2010

    13/54

    It is clear that operation of such a large system requires one to set up a

    control hierarchy, which will also match the power system organization in

    the Region. With this end in mind, a 3-tier hierarchical network has

    already been defined , complying with the load dispatch facilities policy

    established by Central Electricity Authority (CEA) for all India.

    The following load dispatch centers are proposed to be implemented at

    the different hierarchical levels:

    Hierarchy level 1:

    Regional System Control Centre at Delhi covering the region power

    systems of Himachal Pradesh, Haryana, Jammu and Kashmir, Punjab,

    Rajasthan, Uttar Pradesh, BBMB, DESU, Chandigarh.

    Hierarchy level 2:

    Comprising State Load Dispatch Centres (SLDCs) and Central Project

    Control Centres as below:

    SLDC f Hi h l P d h t Shi l

  • 8/9/2019 Trainee Report 2010

    14/54

    Sub-load Dispatch Centres (Sub-LDCs) as below:

    Sub LDCs at Kunihar and Hamirpur controlled by SLDC at Shimla

    (Jutogh)

    Sub LDCs at Dadri, Panipat TPS and Narwana controlled by

    SLDC at Panipat;

    Sub LDCs at Pampore and Udampur controlled by SLDC at

    Udampur (NB: Udhampur Sub LDC is located in the same control

    room as the SLDC);

    Sub LDCs at Jallandhar, Lalton Kalan and Patiala controlled by

    SLDC at Patiala.

    Sub-LDCs at Ratangarh, Kota, Bhilwara and Heerapura controlled

    by SLDC at Heerapura.

    Sub-LDCs at Rishikesh, Moradabad, Panki, Varanasi and

    Sultanpur controlled by SLDC Lucknow.

    3.3 Functions of the Control Centres and sharing out of

    ibiliti

  • 8/9/2019 Trainee Report 2010

    15/54

    The RSCC shall be responsible for the following:

    Data acquisition and monitoring of all the transmission system at 220

    kV and above, plus the 132 kV interstate lines and all the generating

    stations of 50 MW and above.

    Supervisory control of the power system operation pertaining to inter-

    State/ Regional grid and control of central sector sub-station under its

    direct jurisdiction.

    Management and supervisory control of the centrally owned

    generating unit. Load frequency control for the entire region and

    sending corrective area control error messages to all the

    constituents.

    Monitoring inter-state exchanges of power with references to

    schedule and AGC orders.

  • 8/9/2019 Trainee Report 2010

    16/54

    Generation load management according to economic generation

    Optimization carried out at state level and according to RSCC

    request for inter-state power transfers and frequency regulation.

    Transmission of orders directly to state owned power stations from

    the state requirements.

    Voltage and reactive power control.

    3.6 Responsibilities of the Sub-LDCs

    The Sub-LDCs will be responsible of the following:

    Switching of equipments at 220 and 400 kV as per direction SLDC

    V lt d ti t l ith i th i f ibilit

  • 8/9/2019 Trainee Report 2010

    17/54

  • 8/9/2019 Trainee Report 2010

    18/54

    4.2 Data Transmission Principles

    The circuit breakers positions are collected under the shape of

    double signals (DS) as this is necessary for remote control functions,

    also these are more reliable.

    The isolators positions are given single signal as these are not

    needed for remote control.

    For all apparatus positions, the information will be transmitted

    when change of status occurs.

    All possible alarms are collected under single signals.

    4.3 Principles for Data Acquisition

    4 3 1 B b ti

  • 8/9/2019 Trainee Report 2010

    19/54

    33 kV: no value.

    c) SS:

    1 SS for loss of voltage per busbar.

    4.3.2 Busbar coupler and bus section breaker

    DS: 1 DS per circuit breaker.

    SS: 1 SS for only one out of the 2 disconnectors.

    4.3.3 Bus transfer

    DS: 1 DS per circuit breaker.

    SS: 1 SS for each disconnector on both sides of the C.B.

    4.3.4Busbar disconnector

  • 8/9/2019 Trainee Report 2010

    20/54

    1 SS for each bus selector disconnector in case of

    single breaker arrangement.

    1 SS for each disconnector in case of one-hand-half

    breaker arrangement.

    4.3.7 Gas generator and Hydroelectric Generator (substation

    side)a) Active power:1 value.

    b) Reactive power:1 value.

    c) DS:

    - 1 DS per substation circuit-breaker

    - 1 DS per generator bus coupler

    d) SS:

    - 1 SS for each bus selector disconnector in case of

    single breaker arrangement.

    - 1 SS for each disconnector in the case of one-and-half

    breaker arrangement.

  • 8/9/2019 Trainee Report 2010

    21/54

    substation are to be described as overhead line connections and

    remote generators as follows:

    - 1 DS per circuit-breaker(if existing for outgoing feeder),

    - 1 DS per generator bus coupler,

    - one value of P for gross active output of a thermal

    generator,

    - one value of Q for gross reactive output of a thermal

    generator.

    4.3.10Overhead line

    a) Active power and reactive power

    - 400, 220 and 132 kV: one value of P and Q for each

    outgoing line .

    - 66 kV as a secondary part of Regional interest

    substation: one value of P and Q only for outgoing inter-

    system tie-line.

    33 kV l

  • 8/9/2019 Trainee Report 2010

    22/54

    - 1 SS for each by-pass disconnector in case of single

    breaker+by-pass arrangnment

    d) DC

    - 1 DC for each 132 kV outgoing line.

    The choice consisting in the implementation of remote control

    only for 132kv feeders and below can be justified by the needs of

    quick switching operation requirements for load shedding and

    emergency action.

    In some particular cases, some remote control facilities may be

    interesting also for 220 kV or 400 kV components of the grid.

    These specific requirements shall be precisely defined at

    technical specification drafting.

    4.3.11 Transformers

  • 8/9/2019 Trainee Report 2010

    23/54

    whenever the load supplied by the transformers is

    significant.

    c) OLTC

    The position of each On Load Tap Changer is indicated

    with a digital or analog tele measuring. This shall be

    specified for each individual case at specification drafting.

    d) DS:

    1 DS per circuit breaker. If the secondary level doesnt

    belong to same network, 1 DS shall also be collected for

    the secondary circuit breaker.

    e) S S:

    1 SS for each bus selector disconnector in

    case of single breaker arrangement.

  • 8/9/2019 Trainee Report 2010

    24/54

  • 8/9/2019 Trainee Report 2010

    25/54

    Magnetic tape storage devices or equivalent

    equipment,

    Failover system,

    Line printer,

    Software package,

    One time & frequency system,

    One receiver for time synchronization signals.

    Man machine interface

    Control room:

    Two dispatcher consoles with two VDUs each, Two hard copy units linked to any console,

    Two loggers and one plotter,

    One line printer,

    One frequency recorder,

  • 8/9/2019 Trainee Report 2010

    26/54

    Reduced equivalent network,

    Logical controls,

    State estimation,

    Contingency analysis,

    Load flow,

    LFC,

    One local RTU.

    5.2 SLDCs scope of supply

    Two categories of SLDCs have been considered in the northern region,

    depending on the size of the constituent:

    1st category (large sized SLDC): Lucknow, Heerapura.

    2nd category (standred sized SLDC): Shimla, Panipat,

  • 8/9/2019 Trainee Report 2010

    27/54

    One time and frequency system,

    One receiver for time synchronization signals.

    Man Machine Interface

    Control Room:

    Dispatcher consoles:

    - For SLDCs: 2 dispatcher consoles each with two VDUs,

    - For large mixed SLDC/sub-LDC: 3 dispatcher consoles

    each with two VDUs.

    Two hard copy units linked to any console,

    Two loggers and one plotter,

    One line printer,

    One frequency recorder,

    One mimic board along with its driver,

  • 8/9/2019 Trainee Report 2010

    28/54

    Network topology,

    Reduced equivalent network,

    Logical controls,

    State estimation,

    Contingency analysis,

    Load flow, LFC.

    Option two for EMS:

    One computer,

    At least two disk storage units with controllers,

    One streamer or magnetic tape storage device,

    One line printer,

    Two programming terminals,

    One software package.

  • 8/9/2019 Trainee Report 2010

    29/54

    failover system,

    line printer,

    software pakage:

    one time and frequency system,

    one receiver for time synchronization signals

    -Main Machine interface

    -Control Room:

    3 PC workstations,

    two hard copy units linked to any console,

    two loggers,

    one line printer ,

    one plotter,

    one frequency recorder,

    one mimic board along with its driver,

    one audible alarm.

    -computer section:

  • 8/9/2019 Trainee Report 2010

    30/54

    These are :

    RTU(substation level )

    Sub-LDC, 3rd tier

    SLDC or CPCC, 2nd tier

    RSCC, 1st tier.

    All the state owned RTUs are only linked to Sub-LDCs. Thus a data

    communication protocol and procedure shall be provided for this first

    layer.

    The data transferred on these links are:

    Either real-time data

    Or files

    Or data related to remote logging procedures.

    In order to enable all these data transfers between computers, it is

    mandatory to have in each control center a communication software

    which implements the seven layer of Open System Interconnection(OSI)

    ISO Recommendation.

    The OSImodel in seven layers is the following one:

  • 8/9/2019 Trainee Report 2010

    31/54

    for acquisition,processing, transmission and display of the necessary

    process information. The performance of a telecontrol system is

    determind basically by:

    The data integrity of information transfer, from a source to its

    destination , and ,

    The speed with which information is transferred to its

    destination.

    Since telecontrol systems have to operate in real-time mode, limitations

    imposed by the telecommunication channels may heavily impair the

    overall system efficiency.The implicatin is restricted bandwidth and

    hence restricted bit rates to be transmitted under noisy environment

    conditions, which cause distortion of transmitted signals elements. The

    data transmission system has to be considered in the sense as an

    integrated part of the telecontrol system.

    Basic requirements of the data transmission system

    Data transmission should fulfill the following requirements:High data

  • 8/9/2019 Trainee Report 2010

    32/54

    required.The data link protocol accepts and transmits arbitrary bit

    sequence structures from the data source.

    Transmission software and protocol specifications

    Transmission software arrangment

    For standardization reasons and easy future upgrading of the Data

    Transmission Network(DTN) to packet switching, communication

    software is based over the latest ISO(CCITT) standards in force

    implementing the ISOs OSI model.This subdivision into modular layers

    is a useful theoretical model for difining standards. Each layer is

    essentially independent of the layers below and above it. It treats the

    layer below as a service function and the layer above as a master

    with witch it exchanges data and to which it reports errors.

    The independent of the layers gives a modularity to the system. It

    ispossible to alter one layer without altering others, in the some layers

    may be omitted.Telecontrol system functions will be divided into the

  • 8/9/2019 Trainee Report 2010

    33/54

    The protocol to be used for RTU-sub-LDC links and for direct RTU-

    RSCC links will be one of the following by order of decreasing

    preferences:

    - X.25(up to layer 2), -IEC 870-5-1, -Manufactrurs specific.If one of

    the first 2 solutions is proposed, it must not induce additional cost with

    respect to the manufcturers specific solutions.

    The protocol to be used for inter LDClinks will be the X.25 with the

    option and particulars alredy applied by department of science and

    technology in consulation with CEA.

    5.7. Physical structure of the protocol system

    5.7.1. General

    The structure of the data communication network which is thus a

    sub-set of the telecommunication system is mainly determined by

    the operational philosophy, i.e.:

    National Control Centre,

    Regional Control Centre,

  • 8/9/2019 Trainee Report 2010

    34/54

    Transmission link redundancyIn order to maintain a high quality of

    service with strategic sites, the physical communication links

    arriving on the latter will be duplicated. This will be the case

    atleast for:

    The links arriving on 400/200kv substation and power station

    RTUs,

    All the links interconnecting contral centers.

    5.8. Transmission modes

    5.8.1. Transmission initiation modes

    In the case if RTU/sub-LDC links, two basic transmission initiating

    modes will be used for telecontrol data transmission:

    Event initiated transmission(spontaneous transmission, also

    called master-master),

    Transmission on demand(interrogative or polling mode, also

    called master-slave).

  • 8/9/2019 Trainee Report 2010

    35/54

    For sub-LDC/SLDC links:1200 Bds(1200 bits/s), FSK, CCITT V-

    23, 4-wire.

    For higher hierarchical rank inter-computer links:4800 Bds(4800

    bits/s), phase modulation, CCITT V.29.

    For RTUs:

    All RTUs would be configured to work at 200 bauds on FSK

    channels located above the 300 to 2.4 kHz speech sub-bands of

    4 kHz VFTs.

    5.10. Modems

    5.10.1. Basic requirement of RTUs modems

    Frequency shift channel modems are to be used to convert a

    binary signal into two distinct frecuencies.The rack modem of

    RTU will contain 2 single-card modem boards.The modem will

    accept CCITT V.24 serial signals and communicates at the

    standardized data rates from 50 to 1200 bauds.

  • 8/9/2019 Trainee Report 2010

    36/54

    Sequential Event recording :

    TTY will be provided only at 400kv, 220kv substation and power

    station sites.

    5.11.2. Charateristics of RTU I/O circuits

    RTU will be capable of accepting :Single point information

    indication signals, double point information indication signals,

    telemetering signals, under the form of potential free contacts.

    RTU will be capable of issuing:Single point digital controls,

    Double point digital controls,

    Under the form of potential free contacts .

    RTU basic functional processing requirements

    The RTU will be capable of time-tagging the status changes

    with a 10ms resolution for transmission to the control centre as

    well as local editing on a TTY terminal(sequential event

    recording)RTUs bills of quantitiesAn RTU will equip each side

    that will be under supervisory. For power station and the control

  • 8/9/2019 Trainee Report 2010

    37/54

  • 8/9/2019 Trainee Report 2010

    38/54

    efficient, reliable and modern communication system for the Power

    authorities. Keeping in view the specific and the Government of India has

    recommended an independent Dedicated communication system to be

    owned and operated by the Power Utilities up to the State Load

    DESPATCH CENTRE level from remote power stations and substations .

    As recommended by the Working Group and the Secretariess Steering

    Committee, the Government of India decided to appoint a Consultant of

    repute for the planning of a comprehensive communication systems for

    the Power Sector .

    Merz & Mac Lellan (MML) , U.K. , in association with Bharat Electronics

    Ltd.(India) working as Consltants to the Central Electricity Authority have

    submitted , among other reports, a detailed Project Report for

    Telecommunication system of Northern Region including all Constituents

    and have recommended for wide-ranging strengthening of

    Telecommunication network and requisite organization structure. These

    reports have been prepared with active participation of Engineers from

    CEA/NREB/SEBs.Electricite de France International(EDF), Consultant for

  • 8/9/2019 Trainee Report 2010

    39/54

    The telecommunication part of the project will cater for the requirements of

    the load dispatch computerized scheme in respect of the following

    :Speech and data transmission for system operation and control,

    Transmission of operational data for generation of reports and statistical

    information.

    The hierarchy of communication network will start from Remote Terminal

    Units at remote substations/power stations participating significantly in the

    intrigrated operation of the Northern grid and terminate at Sub Load

    dispatch centers .

    The communication system will support the following applications

    Speech communication on express /dialing basis ,

    Data transmission

    Teleprinting

    Facsimile transmission.

    6.2.1. Structure of the switched PABX network

    The switched PABX network is designed to provide voice

    communication .

  • 8/9/2019 Trainee Report 2010

    40/54

    channel required to protect a line or to transmit a control single is a vital

    part of the total system .The consultants have recommended generally

    and independent telecommunication network owned and operated by

    power utilities .Howerever , DOT lines are proposed from SLDCs

    /CPCCs to RLDCs and sub LDCs to SLDCs for back up speech and

    data circuits .

    Planning Philosophy

    For communication between RTUs and sub-LDC , PLCC has been

    recommended by the constants , as their requirement is generally not

    more than 4 channels which can be accommodated by PLCC .A 200

    baud channel , required for RTU communication , can readily be

    accommodated above the 300 Hz to 2.4 KHz speech band in a 4 KHz

    wide PLC channel . The speed of composite data transmission beyond

    sub-LDC is about 1200 baud . This requirment can not be met by PLCC

    alone and multichannel system /leased DOT channels have been

    recommended by the MML consultants

    General

  • 8/9/2019 Trainee Report 2010

    41/54

    The HIMACHAL PRADESH proposed communication will comprise:1

    radio link with 2 radio repeater stations1 fiber optic link without repeater

    station17 Nos of PLC links No DOT leased circuit.

    HARYANA Communication system

    The HARYANA proposed communication system will comprise :

    7 radio links with 3 radio repeater stations1 fiber optic link without

    repeater station (in total 15 Kms)

    32 Nos of PLC links

    No DOT leased circuit.

    JAMMU & KASHMIR Communication system

    The JAMMU & KASHMIR proposed communication system will

    comprise:

    No radio link

    2 fiber optic links without repeater stations

    25 Nos of PLC links

    No DOT leased circuits

  • 8/9/2019 Trainee Report 2010

    42/54

    1400 Kms of leased DOT circuits

    Central sector communication system

    The central sector communication system will comprise :

    16 radio links with 6 radio repeater stations

    5 fiber links with 6 repeater stations

    79 Nos of PLC links

    4005 Kms of leased DOT circuits .

    Merits of the network

    The merits of communication system so designed are as follows :

    The major portion of the network is owned by the Power Sector.leased

    DOT circuits have also been envisaged to support the dedicated

    communication networkthe system caters for the present requirements

    of administrative and operational speech channels with provision for

    future growth .Since future expansion is likely to be along the radio /fiber

    optic routes, it can be operated at very low cost if tower heights are

    adequate, all the towers and parabolic antennas of the existing analogue

    microwave back-bone in UTTAR PRADESH will be re-used for the new

  • 8/9/2019 Trainee Report 2010

    43/54

    Power supplies for supply of :New RTU an interface cubicle , new

    communication equipment , Data processing equipment in the various

    control centers,Airconditioning and security lighting in Control Centres .

    They are one of thefollowing types:

    Uninterruptible DC source (or DC power system)

    Uninterruptible AC source

    Standby power supply.

    In the scope of this project , it was generally decided by Powergrid and the

    constituents that the DC power supply in the sub stations will not be

    included.Thus , only the AC and DC power supplies for the sub-LDCs ,

    CPCCs, SLDCs and RLCC will be considered .

    7.2. AC auxiliary power supplies in Control Centres

    7.2.1. Makingup of 415/240V AC uninterruptible power

    supply in Control Centres

    Two 415V, 3 phase AC supply together with an emergency diesel

    generator will ensure a secure supply to the essential services

  • 8/9/2019 Trainee Report 2010

    44/54

    A control center 48V DC power supply system will comprise in fact

    two traditional 48V DC system chains , each including:2 rectifiers

    simulteneusly operating in parallel ,

    1 lead-acid stationary type battery ,

    1 distribution board,

    An inter-connection between the 48V DC power supply system

    distribution boards which will be left normally opened under normal

    operating conditions.7.3.2. Sizing the 48V DC system in Control

    Centre

    The minimum sizing for each DC system chain will be one 800Ah

    battery and two 160A rectifires .

    7.4. 48V DC system in sub-station

    7.4.1. General

    Communication and telecontrol means of sub-stations are power

    supplied under a mean voltage of 48V DC with possible link of the

    positive polarity end to the earth.For this purpose, we must have

    DC systems suited to the new equipment.

  • 8/9/2019 Trainee Report 2010

    45/54

    7.4.3. 48V DC system sizing and BOQs in sub-stations

    Adequately sized batteries and rectifires will be provided by some

    SEBs/boards/central Sectors themselves as a part of the sub-

    station power/plant components.

  • 8/9/2019 Trainee Report 2010

    46/54

    8.1 General

    As a matter of the fact , once a utilitys network has reached a certain levelof development a modern control system becomes and absolute necessity,

    and the question of its profitability is almost secondary .However , even

    though a precise economic analysis is not possible , in view of the systems

    nature , it is usual practice to evaluate such a project by advantages that it

    offers to the utility .These advantages fall into the following two categories:

    Economically quantifiable benefits Intangible benefits

    8.2 Economically quantifiable benefits

    The economically quantifiable benefits may be classified into four main

    categories:

    Improvement of system reliability and reduction of undelivered energy.

    Saving in operating costs.

    Capital investment savings.

    Reduction of personnel costs.

    These benefits have been evaluated on the basis of field data related to

    disturbances and on some figures recommended by international

  • 8/9/2019 Trainee Report 2010

    47/54

    halved. Assuming that a general collapes lasts one hour , in

    1995:Avoidance of one tripping during one hour :

    E=110841 MkWh/8760*1= 12.65 MkWh

    Reduction of restoration time:

    110841 MkWh / 8760 * 0.5 = 6.33 MkWh

    i.e.: 19 MkWh /year.

    Assuming that the cost of undelivered energy is 20 times the cost of

    generation which is also a standard value and that the cost of generation in

    Northern Region is Rs 12 lakhs / MkWh, then theyearly benefit in this area

    expected from the control scheme is :

    19 * 12 * 20 = Rs 4560 lakhs per year

    i.e. Rs 45.6 Crores per year.

    Operating costs savings

    The reduction of operation costs is mainly expected from a reduction

    in fuel expenditures

    The control schemes enables a reduction of fuel outlays for three

  • 8/9/2019 Trainee Report 2010

    48/54

    power storage for the Northern grid , these savings are quite real in so far

    as there is a correlation between the energy saved and the additional

    capacity installed to supply this lost energy .

    It may be anticipated that 0.35 % of additional installed capacity could be

    saved for an equivalent quality of service if 0.7% of energy is saved by the

    implementation of the control scheme .With a 12, 258 MW additional

    installed capacity planned for 1995 , the saving is 43 MW.

    Assuming a hydro-thermal mix of 35/65 in installed capacity and Rs 3.5

    crores /MW of hydel capacity and Rs 3crores /MW of thermal capacity , the

    capital investmentSaving for generation facilities is :

    43 * 0.35 * 3.5 + 43 * 0.65 * 3 = Rs 137 Crores

    Reduction of personnel costs

    The following considerations are also valid.

    A measure benefit due to SCADA is the increased effectiveness of theLoad

    Despatch personnel which can be achieved .Load dispatch personnel spend

    an inordinate amount of time on paper work . Automated logging and

    reporting software can drastically reduced this tedious tasks.

  • 8/9/2019 Trainee Report 2010

    49/54

    influence in optimizing the hydro operation . It is important if the amount of

    the water for power generation is less than volume available in an average

    year .

    Quick adoption of new operating philosophips according to the development

    of the power system requires flexibility , which can be reached in a Control

    Centre .Improved Reliability Procedures

    It is normal practice to switch capacitors , reactors and cables at different

    times during the day for voltage control purposes. Circuit breakers in the

    transmission network may be opened or closed to limit short circuit levels .

    Improved Operator Training

    Operator training simulators are available today . The opening / closing of

    breakers , tap changing of transformers , etc. can be simulated without

    affecting the status /security of the actual power system . Network analysis

    training will also guarantee higher level of understanding the features of a

    power network .

    Organization Improvent

    Establishment of a control centre means that during the implementation

  • 8/9/2019 Trainee Report 2010

    50/54

    Governments are concerned about security problems during blackouts .

    Police force and damage costs due to social unrest can be high . Loss of

    faith in the ability of the country to handle social problems can be even

    higher ;Governments are concerned about their image . Blackouts and

    unreliable electric supply are embarrassing.Most of these considerations

    apply in the case of the control scheme for the Northern Regional grid.

  • 8/9/2019 Trainee Report 2010

    51/54

    Capital investments savings :

    Generation facilities : Rs. 137 Crores.

    Transmission facilities : Rs. 21 Crores.

    With a 447 Crores Project would be paid off in :

    ( 447 158) / 137.7 = 2.1 years

    ---------------********************************-----------------

  • 8/9/2019 Trainee Report 2010

    52/54

  • 8/9/2019 Trainee Report 2010

    53/54

  • 8/9/2019 Trainee Report 2010

    54/54