Thurrock Flexible Generation Plant · Gravesend particularly Windmill Gardens and Windmill Hill,...
Transcript of Thurrock Flexible Generation Plant · Gravesend particularly Windmill Gardens and Windmill Hill,...
Thurrock Flexible
Generation Plant
Environmental Statement Volume 4: Cumulative Effects Assessment Chapter 19: Landscape and Visual Resources
Date: May 2020
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
i
Environmental Impact Assessment
Cumulative Effects Assessment
Volume 4
Chapter 19
Report Number: OXF10872
Version: Final
Date: May 2020
This report is also downloadable from the Thurrock Flexible Generation Plant website at:
http://www.thurrockpower.co.uk
Thurrock Power Ltd
1st Floor
145 Kensington Church Street
London W8 7LP
Copyright © RPS
The material presented in this report is confidential. This report has been prepared for the
exclusive use of Thurrock Power Ltd and shall not be distributed or made available to any other
company or person without the knowledge and written consent of RPS.
Prepared by: Mark Wilson
Checked by: Peter Ireland
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
1
1. Introduction and Approach
1.1 Purpose of this chapter
1.1.1 This chapter of the Environmental Statement (ES) provides an assessment of the ES
Volume 3, Chapter 6: Landscape and Visual Resources effects of the proposed
development in combination with other relevant future development projects that have
been scoped into the cumulative assessment.
1.1.2 In particular, this LVIA cumulative effects assessment (CEA):
• identifies the potential impact interactions of the proposed development in
combination with other relevant future development projects;
• identifies the receptors with the potential to be significantly affected by these
potential impact interactions and characterises these receptors, including their
sensitivity and any relevant environmental thresholds;
• evaluates the likely significant cumulative effects on these key receptors as a result
of the proposed development in combination with other development projects;
• identifies any additional mitigation measures that are proposed to prevent,
minimise, reduce or offset these significant cumulative effects; and
• taking into account any proposed mitigation measures, evaluates the significance
of predicted residual cumulative effects.
1.2 Approach to cumulative assessment
1.2.1 Landscape and visual impacts assessment (LVIA) cumulative effects follow the
approach set out in Section 3 of Volume 2, Chapter 4: EIA Methodology.
1.3 Study area
1.3.1 The site of the proposed development is divided into a number of Zones (Figure 1.5 of
Volume 2, Chapter 2: Project Description). A study area of radius 10 km from the outer
edges of the proposed development for the LVIA was adopted. This was based on the
proposed Flexible Generation Plant development having stack heights of 40 m and the
main generating station building height of 20 m. It was also based on experience of
assessing this type of development and the industrial and dockside context in which
the proposed development is located.
1.3.2 The same 10 km radius study area used in the Volume 3, Chapter 6: Landscape and
Visual Resources has been adopted for the cumulative developments assessment as
those developments have the potential to affect the same area as the proposed
Flexible Generation Plant. In particular, the Nationally Significant Infrastructure
Projects (NSIPs) which are likely to have the most significant impacts in combination
with the proposed development, are located adjacent to the Flexible Generation Plant.
1.4 Screening of cumulative developments
1.4.1 The purpose of this section is to provide a short list of the potential cumulative
developments which will be assessed in combination with the Flexible Generation
Plant. Potential developments have been shortlisted where, there is potential for
cumulative effects that require further assessment and there is enough information to
do so, albeit this may be qualitative or relatively high level for some projects.
1.4.2 Table 2.1 of Volume 4, Chapter 18: Cumulative Effects Assessment Introduction and
Screening identifies a short-list of potential cumulative developments that have been
screened as potentially relevant to the CEA overall (i.e. for one or more topic areas).
From this shortlist of cumulative development projects, Table 1.1 below identifies those
projects that fall within the zone of influence for LVIA and have potential for cumulative
effects that require assessment in this topic area.
1.4.3 Developments have been shortlisted in Table 1.1 where:
• the conclusions of the environmental assessments for those developments
predicted significant effects on receptors within the zone of influence for the
proposed Thurrock Flexible Generation Plant development; or
• where there is considered to be potential for effects that were not predicted to be
significant for those individual developments but that may become significant in
the cumulative scenario; or
• where environmental studies for those developments have not been published but
there is sufficient information available about the development to both indicate the
potential for cumulative effects and allow assessment.
1.4.4 Where sufficient information about a development to consider its potential for
cumulative effects was not publicly available, the development has not been
shortlisted.
Visual receptor groups
1.5.1 The visual receptors have been grouped up based on similar locations in relation the
Flexible Generation Plant in order to make this assessment more concise. They have
been divided into those north (N) and south (S) of the River Thames. Subsequently
five locations in the north and four in the south have been grouped up based on
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
2
similar locations. For further details of which visual receptors are included in which of
the areas, see Table 1.1.
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
3
Table 1.1: Shortlist of relevant cumulative developments.
ID Development Potential cumulative
impacts (construction)
Potential cumulative
impacts (operation and
maintenance)
Potential cumulative impacts
(decommissioning) Receptor(s) and receptor groups affected
NSIPs
042
TR030003
Tilbury2: A new port facility acting alongside the existing Port of Tilbury. This will involve the extension of existing jetty facilities and the dredging of berth pockets in the River Thames, and land works and facilities for: a “Roll-On / Roll-Off” (Ro-Ro) terminal for importing and exporting containers on road trailers; a facility for importing and processing bulk construction materials; and areas of external storage for a variety of goods such as imported cars. The project also involves the construction of road and rail links to the site from adjacent networks.
Landscape and visual impacts on the surrounding character and views of the Tilbury2 site in the form of construction traffic haul routes, construction plant, machinery including cranes and the emerging development. Potential landscape receptors affected: LCA 5; LCAs C5, D6 and D7. Potential visual receptor groups affected: Groups N1, N2, N3, N4, N5 S1, S2, S3 & S4.
Landscape and visual impacts on the surrounding character and views of the Tilbury2 development. Principally, this includes a RoRo terminal and Construction Materials and Aggregates Terminal (CMAT) to the north of the substation. Components of the development include new dockside storage and warehouses, aggregate storage and processing, new railhead link and road access, loading wharves for aggregates and sea going freight and cargo. Potential landscape receptors affected: LCA 5; LCAs C5, D6 and D7. Potential visual receptor groups affected: Groups N1, N2, N3, N4, N5, S1, S2, S3 & S4
Landscape and visual impacts on the surrounding character and views of the Tilbury2 site in the form of demolition / decommissioning traffic haul routes, demolition plant, machinery including cranes. Potential landscape receptors affected: LCA 5; LCAs C5, D6 and D7. Potential visual receptor groups affected: Groups N1, N2, N3, N5, S1, S2, S3 & S4.
Landscape Receptors:
LCA C5: Tilbury Marshes, LCA D6: Chadwell Escarpment Urban fringe, LCA D7: West Tilbury Urban Fringe.
Visual Receptors:
Viewpoint receptors north side of the River Thames near to waterfront
Group N1 (North shore waterfront): Thames Estuary/Two Forts Way (FP146). tourist attractions including Tilbury Fort, representative Viewpoints 12, to 16 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3.15 to 3.17).
Group N2 (Coastal Plain): Residential receptors on the east side of Tilbury, Access Land (including Walton and Parsonage Commons, commercial and industrial receptors which include people working at the sewage works, and National Grid’s 400kV Tilbury Substation (Zone B), dynamic receptors using Fort Road and Cooper Shaw Road, representative Viewpoints 6, 8, 9 and 11 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3.9, 3.11, 3.12 and 3.14).
Group N3 (South facing Chadwell St Mary escarpment): community facility of St James’ Church graveyard and representative Viewpoints 3, 4, 7 and10 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3.6, 3.7, 3.10 and 3.13).
Viewpoint receptors north of the River Thames mid and far distance (>3km)
Group N5: Representative Viewpoints 1, 2, 5, 33 and 34 (ES Volume 3, Chapter 5: Landscape and Visual Resources, Figures 3.4, 3.5, 3.8, 3.28 and 3.29).
Viewpoint receptors south side of the River Thames near to (Gravesend waterfront)
Group S1: (South shore waterfront): Residential and commercial visual receptors Gravesend waterfront, public access and tourist attractions at Gravesend Gordon Recreation Ground and gardens, New Tavern Fort, Saxon Shore Way, commercial and industrial receptors at Milton, dynamic receptors vessels using River Thames, Representative Viewpoints 18, 19, 20, 21, 23 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3..18 to 3.21).
Group S2 (elevated locations Gravesend): Residential and public access receptors in Gravesend particularly Windmill Gardens and Windmill Hill, PRoW east of Gravesend, representative Viewpoints 22 and 28 (ES Volume3, Chapter 6: Landscape and Visual Resources, Figures 3.20 and 3.23) (near, elevated).
Viewpoint receptors south of the River Thames mid and far distance (>3km)
Group S3 (AONB): Dynamic road receptors Harts Hill north edge of the Kent Downs AONB Representative Viewpoint 29 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figure 3.24).
Group S4 (south shore marshes): Tourist attractions including Cliffe Pools RSPB Reserve, Cliffe Fort and Shornmead Fort, Saxon Shore Way and PRoW on Shorne and Higham Marshes, Representative Viewpoints 24, 25, 26, 27 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3.21 to 3.23).
058
TR010032
The Lower Thames Crossing will be a new road crossing connecting Essex and Kent proposed by the Highway Agency. Located east of Gravesend and Tilbury, this new crossing will offer the improved journeys, new connections and network reliability, and economic benefits that only a new, alternative
Landscape and visual impacts on the surrounding character and views of the LTC site in the form of construction traffic haul routes, construction plant, machinery including cranes and the emerging road and tunnel development.
Landscape and visual impacts on the surrounding character and views of the LTC development. New structures include three lanes in both directions, cuttings and embankments, bridges, buildings tunnel entrances, viaducts, utilities
Landscape and visual impacts on the surrounding character and views of the LTC site in the form of demolition / decommissioning traffic haul routes, demolition plant, machinery including cranes. Potential landscape receptors affected: LCA 5; LCAs C5, D6 and D7. Potential visual receptor
Landscape Receptors:
LCA C5: Tilbury Marshes, LCA D6: Chadwell Escarpment Urban fringe, LCA D7: West Tilbury Urban Fringe.
Visual Receptors:
Viewpoint receptors north side of the River Thames near to waterfront
Group N1 (North shore waterfront): PRoW: Long distance PRoW, Thames Estuary/Two Forts Way (FP146). Tourist attractions including Tilbury Fort, Representative Viewpoints 12, to 16 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3.15 to 3.17).
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
4
ID Development Potential cumulative
impacts (construction)
Potential cumulative
impacts (operation and
maintenance)
Potential cumulative impacts
(decommissioning) Receptor(s) and receptor groups affected
crossing, away from Dartford, can provide.
Principally, this a new road link between the A2 and M25, crossing the A13 at Orsett before crossing under the River Thames east of Tilbury and Gravesend. A new link road will take traffic to the A2 near Shorne close to where the route becomes the M2.
Potential landscape receptors affected: LCA 5; LCAs C5, D6 and D7. Potential visual receptor groups affected: Groups N1, N2, N3, N4, N5, S1, S2, S3 & S4.
such as pylons. 4km of tunnels. Tunnel under the Thames starts at the Gravesend Road and emerges on the north side of the Thames at east of Zone A. Potential landscape receptors affected: LCA 5; LCAs C5, D6 and D7. Potential visual receptor groups affected: N1, N2, N3, N4, N%, S1, S2, S3 & S4.
groups affected: Groups N1, N2, N3, N4, N5, S1, S2, S3 & S4.
Group N2 (Coastal Plain): Residential receptors on the east side of Tilbury, Access Land (including Walton and Parsonage Commons, commercial and industrial receptors which include people working at the sewage works, and National Grid’s 400kV Tilbury Substation (Zone B), dynamic receptors along Fort Road and Cooper Shaw Road, Representative Viewpoints 6, 8, 9 and 11 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3.9, 3.11, 3.12 and 3.14).
Group N3: (South facing Chadwell St Mary escarpment) Community facility of St James’ Church graveyard and Representative Viewpoints 3, 4, 7 and,10 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3.6, 3.7, 3.10 and 3.13).
Viewpoint receptors north of the River Thames mid and far distance (>3km)
Group N4: Representative Viewpoints 17, 30, 31 and 32 (ES Volume 3, Chapter 5: Landscape and Visual Resources, Figures 3.18 and 3.25 to 3.27) (Coalhouse Fort area).
Group N5: : Representative Viewpoints 1, 2, 5, 33 and, 34 (ES Volume 3, Chapter 5: Landscape and Visual Resources, Figures 3.4, 3.5, 3.8, 3.28 and 3.29) (to the west of East Tilbury).
Viewpoint receptors south side of the River Thames near to (Gravesend waterfront)
Group S1 (south shore waterfront): Residential and commercial visual receptors Gravesend waterfront, public access and tourist attractions at Gravesend Gordon Recreation Ground and gardens, New Tavern Fort, PRoW Saxon Shore Way, commercial and industrial receptors at Milton, dynamic receptors vessels using River Thames, Representative Viewpoints 18, 19, 20, 21, 23 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3..18 to 3.21).
Group S2 (elevated locations Gravesend): Residential and public access receptors in Gravesend particularly Windmill Gardens and Windmill Hill, PRoW east of Gravesend Viewpoints 22 and 28 (ES Volume3, Chapter 6: Landscape and Visual Resources, Figures 3.20 and 3.23) (near elevated)
Viewpoint receptors south of the River Thames mid and far distance (>3km)
Group S3 (AONB): Dynamic road receptors Harts Hill north edge of the Kent Downs AONB Representative Viewpoint 29 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figure 3.24).
Group S4 (south shore marshes): Tourist attractions including Cliffe Pools RSPB, Cliffe Fort and Shoremead Fort Saxon Shore Way and PRoWs ona Shorne and Higham Marshes, Representative Viewpoints 24, 25, 26, 27 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3.21 to 3.23).
East Tilbury Developments
005
18/00664/CONDC
Redevelopment of an area of previously developed land towards the southern boundary of Thames Industrial Estate to provide 50 dwellings, together with an associated financial commitment towards the repair, upkeep and stewardship of surrounding former factory buildings (some of which are listed), improved access arrangements and the creation of an area of public open space along the site frontage.
One Big Self Store Ltd Trafalgar House Thames Industrial Park Princess Margaret Road East Tilbury Essex.
Landscape and visual impacts on the surrounding character and views in the form of construction traffic haul routes, construction plant, machinery. Potential landscape receptors affected: LCA D7.
Landscape and visual impacts on the surrounding character and views of the new housing development. Potential landscape receptors affected: LCA D7; visual receptor groups affected: Group N5. (excluding VP1)
Landscape and visual impacts on the surrounding character and views of the LTC site in the form of demolition / decommissioning traffic haul routes, demolition plant, machinery. Potential landscape receptors affected: LCA D7
Landscape Receptors:
LCA D7: West Tilbury Urban Fringe.
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
5
ID Development Potential cumulative
impacts (construction)
Potential cumulative
impacts (operation and
maintenance)
Potential cumulative impacts
(decommissioning) Receptor(s) and receptor groups affected
011
16/01475/SCR
Request for Environmental Impact Assessment (EIA) Screening Opinion: Proposed development of up to 200 dwellings with associated access and open space
Gothards Field Rear of The George And Dragon, East Tilbury Road, Linford, Essex
Landscape and visual impacts on the surrounding character and views in the form of construction traffic haul routes, construction plant, machinery. Potential landscape receptors affected: LCA D7; visual receptor groups affected: Group N5. (excluding VP1)
Landscape and visual impacts on the surrounding character and views of the new housing development. Potential landscape receptors affected: LCA D7; visual receptor groups affected: Group N5. (excluding VP1)
Landscape and visual impacts on the surrounding character and views of the LTC site in the form of demolition / decommissioning traffic haul routes, demolition plant, machinery. Potential landscape receptors affected: LCA D7; visual receptor groups affected: Group N5. (excluding VP1)
Landscape Receptors:
LCA D7: West Tilbury Urban Fringe.
Visual Receptors:
Viewpoint receptors north side of the River Thames near to waterfront
Group N5: Representative Viewpoints 1, 2, 5, 33 and, 34 (ES Volume 3, Chapter 5: Landscape and Visual Resources, Figures 3.4, 3.5, 3.8, 3.28 and 3.29) (to the west of East Tilbury).
012
16/01232/OUT
Application for outline planning permission with some matters (appearance, landscaping, layout and scale) reserved: Proposed development of up to 1,000 dwellings (Use Class C3), a new local road network including a vehicular / pedestrian railway crossing, a new single form entry primary school, local centre including provision for a maximum of 750 sq.m. Use Class A1 (shops) / Use Class A3 (food and drink) / Use Class D1 (non-residential institutions) floorspace, and new areas of open space, including formal recreation.
Land for Development Muckingford Road, Linford, Essex
Landscape and visual impacts on the surrounding character and views in the form of construction traffic haul routes, construction plant, machinery. Potential landscape receptors affected: LCA D7; visual receptor groups affected: Group N5. (excluding VP1)
Landscape and visual impacts on the surrounding character and views of the new housing, school, retail and road development. Potential landscape receptors affected: LCA D7; visual receptor groups affected: Group N5. (excluding VP1)
Landscape and visual impacts on the surrounding character and views in the form of demolition / decommissioning traffic haul routes, demolition plant, machinery. Potential landscape receptors affected: LCA D7; visual receptor groups affected: Group N5. (excluding VP1)
Landscape Receptors:
LCA D7: West Tilbury Urban Fringe.
Visual Receptors:
Viewpoint receptors north side of the River Thames near to waterfront
Group N5: Representative Viewpoints 1, 2, 5, 33 and, 34 (ES Volume 3, Chapter 5: Landscape and Visual Resources, Figures 3.4, 3.5, 3.8, 3.28 and 3.29) (to the west of East Tilbury).
Chadwell St Mary Developments
014
16/00412/OUT
Outline application for proposed residential redevelopment, with all matters reserved apart from principle and access (Indicative layout provided indicates up to 203 dwellings)
Star Industrial Estate Linford Road Chadwell St Mary Essex
Landscape and visual impacts on the surrounding character and views in the form of construction traffic haul routes, construction plant, machinery. Potential landscape receptors affected: LCA D6.
Landscape and visual impacts on the surrounding character and views of the new housing development. Potential landscape receptors affected: LCA D6.
Landscape and visual impacts on the surrounding character and views in the form of demolition / decommissioning traffic haul routes, demolition plant, machinery. Potential landscape receptors affected: LCA D6.
Landscape Receptors:
LCA D6: West Tilbury Urban Fringe
034
15/00379/OUT
Outline application (with all matters reserved for a subsequent application) for proposed residential redevelopment of land between 39 and 41 St John's Road consisting of up to 43 dwellings, landscaping and new access.
Land Adjacent 39 And 41 And to The South Of St Johns Road Chadwell St Mary Essex
Landscape and visual impacts on the surrounding character and views in the form of construction traffic haul routes, construction plant, machinery. Potential landscape receptors affected: LCA D6.
Landscape and visual impacts on the surrounding character and views of the new housing development. Potential landscape receptors affected: LCA D6
Landscape and visual impacts on the surrounding character and views in the form of demolition / decommissioning traffic haul routes, demolition plant, machinery. Potential landscape receptors affected: LCA D6.
Landscape Receptors:
LCA D6: West Tilbury Urban Fringe
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
6
ID Development Potential cumulative
impacts (construction)
Potential cumulative
impacts (operation and
maintenance)
Potential cumulative impacts
(decommissioning) Receptor(s) and receptor groups affected
Tilbury Developments
016
17/00977/FUL
Retention and completion of waste wood processing plant (Class B2/B8) & fire retained area bounded by concrete push walls, erection of buildings to form associated storage, reception/ administration, security, and staff welfare area; formation of impermeable surface to form a lorry parking/waiting area; weighbridge and staff parking area together with associated highways and drainage works
Land Part of Marsh Farm Sewage Treatment Plant Fort Road Tilbury Essex
Landscape and visual impacts on the surrounding character and views in the form of construction traffic haul routes, construction plant, machinery. Potential landscape receptors affected: LCA C5; visual receptor groups affected: Group N1, N2, S1 and S2.
Landscape and visual impacts on the surrounding character and views of the industrial processing plant. Potential landscape receptors affected: LCA C5; visual receptor groups affected: Group N1, N2, S1 and S2.
Landscape and visual impacts on the surrounding character and views in the form of demolition / decommissioning traffic haul routes, demolition plant, machinery. Potential landscape receptors affected: LCA C5; visual receptor groups affected: Group N1, N2, S1 and S2.
Landscape Receptors:
LCA C5: Tilbury Marshes
Visual Receptors:
Viewpoint receptors north side of the River Thames near to waterfront
Group N1 (North shore waterfront): PRoW: Long distance PRoW, Thames Estuary/Two Forts Way (FP146). Tourist attractions including Tilbury Fort, Representative Viewpoints 12 to 16 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3.15 to 3.17).
Group N2 (Coastal Plain): Residential receptors on the east side of Tilbury, Access Land (including Walton and Parsonage Commons, commercial and industrial receptors which include people working at the sewage works, and National Grid’s 400kV Tilbury Substation (Zone B), dynamic receptors along Fort Road and Cooper Shaw Road, Representative Viewpoints 6, 8, 9 and 11 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3.9, 3.11, 3.12 and 3.14).
Viewpoint receptors south side of the River Thames near to (Gravesend waterfront)
Group S1 (south shore waterfront): Residential and commercial visual receptors Gravesend waterfront, public access and tourist attractions at Gravesend Gordon Recreation Ground and gardens, New Tavern Fort, Saxon Shore Way, commercial and industrial receptors at Milton, dynamic receptors vessels using River Thames, Representative Viewpoints 18, 19, 20, 21, 23 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3..18 to 3.21).
Group S2 (elevated locations Gravesend): Residential and public access receptors in Gravesend particularly Windmill Gardens and Windmill Hill, PRoW east of Gravesend Representative Viewpoints 22 and, 28 (ES Volume3, Chapter 6: Landscape and Visual Resources, Figures 3.20 and 3.23) (near elevated).
018
11/50361/TTGETL
An extension of time limit for implementation of planning permission ref 01.08.04/87C. To construct and operate a Biomass and Energy from waste fuelled generating station for a period of two years to 26 Aug 2014.
Former Cargill Plant Tilbury Freeport Tilbury Essex
Landscape and visual impacts on the surrounding character and views in the form of construction traffic haul routes, construction plant, machinery. Potential landscape receptors affected: LCA C5.
Landscape and visual impacts on the surrounding character and views of the industrial processing plant. Potential landscape receptors affected: LCA C5.
Landscape and visual impacts on the surrounding character and views in the form of demolition / decommissioning traffic haul routes, demolition plant, machinery. Potential landscape receptors affected: LCA C5.
Landscape Receptors:
LCA C5: Tilbury Marshes
Visual Receptors:
Viewpoint receptors north side of the River Thames near to waterfront
Group N1 (North shore waterfront): PRoW: Long distance PRoW, Thames Estuary/ Two Forts Way (FP146). Tourist attractions including Tilbury Fort, Representative Viewpoints 12 to 16 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3.15 to 3.17).
Group N2 (Coastal Plain): Residential receptors on the east side of Tilbury, Access Land (including Walton and Parsonage Commons, commercial and industrial receptors which include people working at the sewage works, and National Grid’s 400kV Tilbury Substation (Zone B), dynamic receptors along Fort Road and Cooper Shaw Road, Representative Viewpoints 6, 8, 9 and 11 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3.9, 3.11, 3.12 and 3.14).
Viewpoint receptors south side of the River Thames near to (Gravesend waterfront)
Group S1 (south shore waterfront): Residential and commercial visual receptors Gravesend waterfront, public access and tourist attractions at Gravesend Gordon Recreation Ground and gardens, New Tavern Fort, Saxon Shore Way, commercial and industrial receptors at Milton, dynamic receptors vessels using River Thames, Representative Viewpoints 18, 19, 20, 21, 23 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3..18 to 3.21).
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
7
ID Development Potential cumulative
impacts (construction)
Potential cumulative
impacts (operation and
maintenance)
Potential cumulative impacts
(decommissioning) Receptor(s) and receptor groups affected
Group S2 (elevated locations Gravesend): Residential and public access receptors in Gravesend particularly Windmill Gardens and Windmill Hill, PRoW east of Gravesend Representative Viewpoints 22 and, 28 (ES Volume3, Chapter 6: Landscape and Visual Resources, Figures 3.20 and 3.23) (near elevated)
050
17/00349/SCR
EIA Screening Opinion - Application for a Certificate of Lawfulness of Proposed Use or Development: Proposed processing of biofuels and other suitable waste derived feedstocks into a manufactured clean gas product (Use Class B2).
Land Part of Marsh Farm Sewage Treatment Plant Fort Road Tilbury Essex
Landscape and visual impacts on the surrounding character and views in the form of construction traffic haul routes, construction plant, machinery. Potential landscape receptors affected: LCA C5; visual receptor groups affected: Group N1, N2, S1 and S2.
Landscape and visual impacts on the surrounding character and views of the industrial processing plant. Potential landscape receptors affected: LCA C5; visual receptor groups affected: Group N1, N2, S1 and S2.
Landscape and visual impacts on the surrounding character and views in the form of demolition / decommissioning traffic haul routes, demolition plant, machinery. Potential landscape receptors affected: LCA C5; visual receptor groups affected: Group N1, N2, S1 and S2.
Landscape Receptors:
LCA C5: Tilbury Marshes
Visual Receptors:
Viewpoint receptors north side of the River Thames near to waterfront
Group N1 (North shore waterfront): PRoW: Long distance PRoW, Thames Estuary/Two Forts Way (FP146). Tourist attractions including Tilbury Fort, Representative Viewpoints 12, to 16 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3.15 to 3.17).
Group N2 (Coastal Plain): Residential receptors on the east side of Tilbury, Access Land (including Walton and Parsonage Commons, commercial and industrial receptors which include people working at the sewage works, and National Grid’s 400kV Tilbury Substation (Zone B), dynamic receptors along Fort Road and Cooper Shaw Road, Representative Viewpoints 6, 8, 9 and 11 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3.9, 3.11, 3.12 and 3.14).
Viewpoint receptors south side of the River Thames near to (Gravesend waterfront)
Group S1 (south shore waterfront): Residential and commercial visual receptors Gravesend waterfront, public access and tourist attractions at Gravesend Gordon Recreation Ground and gardens, New Tavern Fort, Saxon Shore Way, commercial and industrial receptors at Milton, dynamic receptors vessels using River Thames, Representative Viewpoints 18, 19, 20, 21, 23 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3..18 to 3.21).
Group S2 (elevated locations Gravesend): Residential and public access receptors in Gravesend particularly Windmill Gardens and Windmill Hill, PRoW east of Gravesend Representative Viewpoints 22 and, 28 (ES Volume3, Chapter 6: Landscape and Visual Resources, Figures 3.20 and 3.23) (near elevated).
079
19/01274/FUL
Proposed Short Term Operation Reserve (STOR) electricity generating station comprising 14 no. gas-fired generators with a capacity up to 21 MW with associated development at land adjacent to Tilbury Waste Water Treatment Works, Fort Road, Tilbury.
Anglian Water Services Sewage Treatment Plant Fort Road Tilbury Essex
Landscape and visual impacts on the surrounding character and views in the form of construction traffic haul routes, construction plant, machinery. Potential landscape receptors affected: LCA C5
Landscape and visual impacts on the surrounding character and views of the industrial processing plant. Potential landscape receptors affected: LCA C5
Landscape and visual impacts on the surrounding character and views in the form of demolition / decommissioning traffic haul routes, demolition plant, machinery. Potential landscape receptors affected: LCA C5
Landscape Receptors:
LCA C5: Tilbury Marshes
Visual Receptors:
Viewpoint receptors north side of the River Thames near to waterfront
Group N1 (North shore waterfront): PRoW: Long distance PRoW, Thames Estuary/Two Forts Way (FP146). Tourist attractions including Tilbury Fort, Representative Viewpoints 12 to 16 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3.15 to 3.17).
Group N2 (Coastal Plain): Residential receptors on the east side of Tilbury, Access Land (including Walton and Parsonage Commons, commercial and industrial receptors which include people working at the sewage works, and National Grid’s 400kV Tilbury Substation (Zone B), dynamic receptors along Fort Road and Cooper Shaw Road, Representative Viewpoints 6, 8, 9 and 11 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3.9, 3.11, 3.12 and 3.14).
Viewpoint receptors south side of the River Thames near to (Gravesend waterfront)
Group S1 (south shore waterfront): Residential and commercial visual receptors Gravesend waterfront, public access and tourist attractions at Gravesend Gordon Recreation Ground and gardens, New Tavern Fort, Saxon Shore Way, commercial and industrial receptors at Milton, dynamic receptors vessels using River Thames, Representative Viewpoints 18, 19, 20, 21, 23 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3..18 to 3.21).
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
8
ID Development Potential cumulative
impacts (construction)
Potential cumulative
impacts (operation and
maintenance)
Potential cumulative impacts
(decommissioning) Receptor(s) and receptor groups affected
Group S2 (elevated locations Gravesend): Residential and public access receptors in Gravesend particularly Windmill Gardens and Windmill Hill, PRoW east of Gravesend Representative Viewpoints 22 and, 28 (ES Volume3, Chapter 6: Landscape and Visual Resources, Figures 3.20 and 3.23) (near elevated).
081
12.04.09.04/266C
Tilbury Green Power Phase 2 S36C application. Biomass and energy from waste fuelled generation station at Tilbury Docks, Essex: variation application under section 36c of the electricity act 1989.
Former Cargill Plant Tilbury Freeport Tilbury Essex.
Landscape and visual impacts on the surrounding character and views in the form of construction traffic haul routes, construction plant, machinery. Potential landscape receptors affected: LCA C5; visual receptor groups affected: Group N1, N2, S1 and S2.
Landscape and visual impacts on the surrounding character and views of the industrial processing plant. Potential landscape receptors affected: LCA C5; visual receptor groups affected: Group N1, N2, S1 and S2.
Landscape and visual impacts on the surrounding character and views in the form of demolition / decommissioning traffic haul routes, demolition plant, machinery. Potential landscape receptors affected: LCA C5; visual receptor groups affected: Group N1, N2, S1 and S2.
Landscape Receptors:
LCA C5: Tilbury Marshes
Visual Receptors:
Viewpoint receptors north side of the River Thames near to waterfront
Group N1 (North shore waterfront): PRoW: Long distance PRoW, Thames Estuary/Two Forts Way (FP146). Tourist attractions including Tilbury Fort, Representative Viewpoints 12, to 16 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3.15 to 3.17).
Group N2 (Coastal Plain): Residential receptors on the east side of Tilbury, Access Land (including Walton and Parsonage Commons, commercial and industrial receptors which include people working at the sewage works, and National Grid’s 400kV Tilbury Substation (Zone B), dynamic receptors along Fort Road and Cooper Shaw Road, Representative Viewpoints 6, 8, 9 and 11 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3.9, 3.11, 3.12 and 3.14).
Viewpoint receptors south side of the River Thames near to (Gravesend waterfront)
Group S1 (south shore waterfront): Residential and commercial visual receptors Gravesend waterfront, public access and tourist attractions at Gravesend Gordon Recreation Ground and gardens, New Tavern Fort, Saxon Shore Way, commercial and industrial receptors at Milton, dynamic receptors vessels using River Thames, Representative Viewpoints 18, 19, 20, 21, 23 (ES Volume 3, Chapter 6: Landscape and Visual Resources, Figures 3..18 to 3.21).
Group S2 (elevated locations Gravesend): Residential and public access receptors in Gravesend particularly Windmill Gardens and Windmill Hill, PRoW east of Gravesend Representative Viewpoints 22 and, 28 (ES Volume3, Chapter 6: Landscape and Visual Resources, Figures 3.20 and 3.23) (near elevated).
Gravesend Developments
064 (policy ref CS04)
Canal Basin Regeneration Area: Gravesend Local Plan Core Strategy Policy CS04 for mixed-use development of around 650 dwellings and 4,650 sq m of B1a and B1c employment floorspace.
Gordon Promenade East, Gravesend
Landscape and visual impacts on the surrounding character and views in the form of construction traffic haul routes, construction plant, machinery. Potential visual receptor groups affected: Group S1 and S2.
Landscape and visual impacts on the surrounding character and views of the new housing, school, retail and road development. Potential visual receptor groups affected: Group S1 and S2.
Landscape and visual impacts on the surrounding character and views in the form of demolition / decommissioning traffic haul routes, demolition plant, machinery. visual receptor groups affected: Group S1 and S2.
Visual Receptors:
Viewpoint receptors south side of the River Thames near to (Gravesend waterfront)
Group S2 (elevated locations Gravesend): Residential and public access receptors in Gravesend particularly Windmill Gardens and Windmill Hill, PRoW east of Gravesend Representative Viewpoints 22 and, 28 (ES Volume3, Chapter 6: Landscape and Visual Resources, Figures 3.20 and 3.23) (near elevated).
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
9
1.5 Identifying cumulative developments affecting each
receptor
1.5.1 Table 1.2 to Table 1.4 summarise the cumulative developments that have the potential
to cause cumulative effects at each identified receptor, the sensitivity of that receptor
to cumulative impacts, and the starting position to the cumulative effects assessment,
which is the predicted residual effect of Thurrock Flexible Generation Plant alone
during construction, operation and decommissioning (as established in ES Volume 3,
Chapter 6: Landscape and Visual Resources).
Table 1.2: Summary of cumulative developments affecting each receptor (construction).
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with the
potential to affect this
receptor
Landscape Receptors:
LCA C5: Tilbury Marshes Medium
Magnitude of impact: Moderate
Significance of effect: Moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Moderate (Tilbury2)
Moderate to major (LTC)
LCA C5: Tilbury Marshes Medium
Magnitude of impact: Moderate
Significance of effect: Moderate (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
018 11/50361/TTGETL
050 17/00349/SCR
079 19/01274/FUL
081 12.04.09.04/266C
Magnitude of impact: Minor to negligible
LCA D6: Chadwell Escarpment Urban Fringe
Medium
Magnitude of impact: Minor
Significance of effect: Minor (not significant)
NSIPs:
058 TR010032 LTC only
Magnitude of impact: Minor
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with the
potential to affect this
receptor
LCA D6: Chadwell Escarpment Urban Fringe
Medium
Magnitude of impact: Minor
Significance of effect: Minor (not significant)
Other relevant developments:
Chadwell St Mary Developments:
014 16/00412/OUT
034 15/00379/OUT
Magnitude of impact: Negligible to minor
LCA D7: West Tilbury Urban Fringe
Medium
Magnitude of impact: Minor
Significance of effect: Minor (not significant)
NSIPs:
058 TR010032 LTC only
Magnitude of impact: Minor
LCA D7: West Tilbury Urban Fringe
Medium
Magnitude of impact: Minor
Significance of effect: Minor (not significant)
Other relevant developments:
East Tilbury Developments:
005 18/00664/CONDC
011 16/01475/SCR
012 16/01232/OUT
Magnitude of impact: Minor
Visual Receptors:
N1: Public Access: Thames Estuary Path PRoW
High
Users of Footpath 146, adjacent to the sewage works (Viewpoint 12) will have a medium sensitivity to the proposed development
Magnitude of impact: No change to minor and moderate (Viewpoint 15 for work on the causeway in Zone G only)
Significance of effect: Minor (not significant) to major (Viewpoint 15 for work on the causeway in Zone G only – significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Moderate
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
10
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with the
potential to affect this
receptor
N1: Public Access: Thames Estuary Path PRoW
High
Users of Footpath 146, adjacent to the sewage works (Viewpoint 12) will have a medium sensitivity to the proposed development
Magnitude of impact: No change to moderate (Viewpoints 15 and 16 for work on the causeway in Zone G only)
Significance of effect: Minor (not significant) to major (Viewpoints 15 and 16 for work on the causeway in Zone G only – significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Minor
N1: Tourist attraction: Tilbury Fort
High
Users of Footpath 146, adjacent to the sewage works (Viewpoint 12) will have a medium sensitivity to the proposed development
Magnitude of impact: No change to minor
Significance of effect: Minor to moderate (not significant)
NSIPs:
058 TR010032 LTC
Magnitude of impact: Minor
N1: Tourist attraction: Tilbury Fort
High
Users of Footpath 146, adjacent to the sewage works (Viewpoint 12) will have a medium sensitivity to the proposed development
Magnitude of impact: No change to minor
Significance of effect: Minor to moderate (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Negligible to no change
N1: Viewpoints: 12, 13 and 14
High
Users of Footpath 146, adjacent to the sewage works (Viewpoint 12) will have a medium sensitivity to the proposed development
Magnitude of impact: No change to minor
Significance of effect: Minor to moderate (not significant)
NSIPs:
058 TR010032 LTC
Magnitude of impact: Minor
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with the
potential to affect this
receptor
N1: Viewpoints: 12, 13 and 14
High
Users of Footpath 146, adjacent to the sewage works (Viewpoint 12) will have a medium sensitivity to the proposed development
Magnitude of impact: No change to minor
Significance of effect: Minor to moderate (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Negligible to no change
N1: Viewpoints 15 and 16 High
Magnitude of impact: Minor (Zone A) and moderate (for work on the causeway in Zone G)
Significance of effect: Moderate (not significant) to Major (for work on the causeway in Zone G only – significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Moderate
N1: Viewpoints 15 and 16 High
Magnitude of impact Minor (Zone A) and moderate (for work on the causeway in Zone G)
Significance of effect: Moderate (not significant) to Major (for work on the causeway in Zone G only – significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Negligible to no change
N2: Residential groups east side of Tilbury and Access Land at Walton and Parsonage Commons, as well as either side of Fort Road and Cooper Shaw Road
High
Magnitude of impact: No change to Minor
Significance of effect: Moderate (not significant) to major (Parsonage Common Access Land) (significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Minor to moderate
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
11
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with the
potential to affect this
receptor
N2: Residential groups east side of Tilbury and Access Land at Walton and Parsonage Commons, as well as either side of Fort Road and Cooper Shaw Road
High
Magnitude of impact: Minor
Significance of effect: Moderate (not significant) to major (Access Land) (significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Negligible to no change
N2: Dynamic receptors (rail, Fort Road and Cooper Shaw Road users)
Low to high (rail passengers travelling for pleasure)
Magnitude of impact: Minor to moderate
Significance of effect: Minor to moderate (rail passengers) (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Moderate
N2: Dynamic receptors (rail, Fort Road and Cooper Shaw Road users)
Low to high (rail passengers travelling for pleasure)
Magnitude of impact: Minor to moderate
Significance of effect: Minor to moderate (rail passengers) (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Negligible to no change
N2: Viewpoints 6, 8, 9 and 11
Low (road users) to high (pedestrians using Access Land)
Magnitude of impact: Minor to moderate
Significance of effect: Minor (not significant) to major (users of Access Land - significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Moderate to major
N2: Viewpoints 6, 8, 9 and 11
Low (road users) to high (pedestrians using Access Land)
Magnitude of impact: Minor to moderate
Significance of effect: Minor (not significant) to major (users of Access Land - significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Negligible to no change
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with the
potential to affect this
receptor
N3: Community facility – St James’ Church graveyard (Viewpoint 7)
High
Magnitude of impact: Moderate
Significance of effect: Moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Moderate
N3: Viewpoints 3, 4, 7 and 10
High
Magnitude of impact: Negligible to moderate
Significance of effect: minor to moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Negligible to moderate
N3: None of the receptors in this location will be significantly adversely affected by the construction phases of the other cumulative / non NSIP developments and are not considered further in this assessment. Only the NSIPs have the potential to have cumulative effects.
N4: Tourist Attraction and Public Open Space (Coalhouse Fort)
High
Magnitude of impact: No change to negligible
Significance of effect: None to Minor (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Minor
N4: Viewpoints 17, 30, 31 and 32
High
Magnitude of impact: No change to negligible
Significance of effect: None to minor (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Minor
N4: None of the receptors in this location will be significantly adversely affected by the construction phases of the other cumulative / non NSIP developments and are not considered further in this assessment. Only the NSIPs have the potential to have cumulative effects on the receptors.
N5: Residential receptors: (Dwellings on the west side of East Tilbury) and PRoWs footpath 67 and bridleways 58 and 63
High
Magnitude of impact: No change to minor
Significance of effect: None to moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Minor to negligible
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
12
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with the
potential to affect this
receptor
N5: Viewpoints 5, 33 and 34
High
Magnitude of Change: Negligible
Significance of effect: Minor (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Minor
N5: None of the receptors in this location will be significantly adversely affected by the construction phases of the other cumulative / non NSIP developments and are not considered further in this assessment. Only the NSIPs have the potential to have cumulative effects on the receptors.
S1: Residential (Gravesend waterfront); Saxon Shore Way, tourist attractions and recreation (Gordon Gardens, New Tavern Fort, Gravesend waterfront); marine-based dynamic receptors
Low (people working on marine-vessels) to high
Magnitude of impact: Negligible to minor
Significance of effect: Negligible to moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Moderate
S1: Residential (Gravesend waterfront); Saxon Shore Way, tourist attractions and recreation (Gordon Gardens, New Tavern Fort, Gravesend waterfront); marine-based dynamic receptors
Low (people working on marine vessels) to high
Magnitude of impact: Negligible to Minor
Significance of effect: Negligible to moderate (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Negligible to minor
S1: Residential (Gravesend waterfront); Saxon Shore Way, tourist attractions and recreation (Gordon Gardens, New Tavern Fort, Gravesend waterfront); marine-based dynamic receptors
Low (people working on marine vessels) to high
Magnitude of impact: Negligible to Minor
Significance of effect: Negligible to moderate (not significant)
Other relevant developments
Gravesend Developments:
064 (policy ref CS04)
Magnitude of impact: Negligible to minor
S1: Viewpoints 18, 19 to 21 and 23Viewpoint
Medium (people working at these locations) to high
Magnitude of impact: Negligible to minor
Significance of effect: Negligible to moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Moderate
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with the
potential to affect this
receptor
S1: Viewpoint 20 and Viewpoint 21
High
Magnitude of impact: Minor
Significance of effect: Moderate (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Negligible to minor
S2: Residents and public open space users (Windmill Hill, Windmill Gardens, Gravesend), PRoW east of Gravesend
High
Magnitude of impact: Negligible
Significance of effect: (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC y
Magnitude of impact: Minor to moderate
S2: Residents and public open space users (Windmill Hill, Windmill Gardens, Gravesend), PRoW east of Gravesend
High
Magnitude of impact: Negligible
Significance of effect: Minor (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Minor
S2: Residents and public open space users (Windmill Hill, Windmill Gardens, Gravesend), PRoWs east of Gravesend
High
Magnitude of impact: Negligible
Significance of effect:
Minor (not significant)
Other relevant developments:
Gravesend Developments:
064 (Policy reference CS04)
Magnitude of impact: Negligible to minor
S2: Viewpoint 22 and Viewpoint 28
High
Magnitude of impact: Negligible
Significance of effect: Minor (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Moderate to minor
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
13
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with the
potential to affect this
receptor
S2: Viewpoint 22 and Viewpoint 28
High
Magnitude of impact: Negligible
Significance of effect: Minor (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Minor
S2: Viewpoint 22 and Viewpoint 28
High
Magnitude of impact: Negligible
Significance of effect: Minor (not significant)
Other relevant developments:
Gravesend Developments:
064 (Policy reference CS04)
Magnitude of impact: Negligible
S3: Dynamic road receptors - Harts Hill, Kent Downs AONB
Medium (within the AONB)
Magnitude of impact: Negligible to no change
Significance of effect: None to Minor (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Negligible to minor
S3: Viewpoint 29 Very High
Magnitude of impact: Negligible
Significance of effect: Moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Minor
S3: None of the receptors in this location will be significantly adversely affected by the construction phases of the other cumulative / non NSIP developments and are not considered further in this assessment. Only the NSIPs have the potential to have cumulative effects.
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with the
potential to affect this
receptor
S4: Tourist attractions including Cliffe Pools RSPB reserve, Cliffe Fort and Shornmead Fort, Saxon Shore Way (long distance footpath) and PRoW across Shorne and Higham Marshes
High
Magnitude of impact: Negligible
Significance of effect: Minor (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Minor
S4: Viewpoints 24 to 27 High
Magnitude of impact: Negligible
Significance of effect:
Minor (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Minor
S4: None of the receptors in this location will be significantly adversely affected by the construction phases of the other cumulative / non NSIP developments and are not considered further in this assessment. Only the NSIPs have the potential to have cumulative effects.
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
14
Table 1.3: Summary of cumulative developments affecting each receptor (operation and maintenance)
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with
the potential to affect
this receptor
Landscape Receptors:
LCA C5: Tilbury Marshes Medium
Magnitude of impact: Moderate
Significance of effect: Moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Moderate (Tilbury2)
Moderate to Major (LTC)
LCA C5: Tilbury Marshes Medium
Magnitude of impact: Moderate
Significance of effect: Moderate (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
018 11/50361/TTGETL
050 17/00349/SCR
079 19/01274/FUL
081 12.04.09.04/266C
Magnitude of impact: Minor to Negligible
LCA D6: Chadwell Escarpment Urban Fringe
Medium
Magnitude of impact: Minor
Significance of effect: Minor (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Minor
LCA D6: Chadwell Escarpment Urban Fringe
Medium
Magnitude of impact: Minor
Significance of effect: Minor (not significant)
Other relevant developments:
Chadwell St Mary Developments:
014 16/00412/OUT
034 15/00379/OUT
Magnitude of impact: Negligible to Minor
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with
the potential to affect
this receptor
LCA D7: West Tilbury Urban Fringe
Medium
Magnitude of impact: Minor
Significance of effect: Minor (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Minor
LCA D7: West Tilbury Urban Fringe
Medium
Magnitude of impact: Minor
Significance of effect: Minor (not significant)
Other relevant developments:
East Tilbury Developments:
005 18/00664/CONDC
011 16/01475/SCR
012 16/01232/OUT
Magnitude of impact: Minor
Visual Receptors:
N1: Public Access: Thames Estuary Path PRoW
High
Medium (PRoW footpath 146 – Viewpoint 12)
Magnitude of impact: Negligible to minor
Significance of effect: Negligible to Moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Moderate
N1: Public Access: Thames Estuary Path PRoW
High
Medium (PRoW footpath 146 – Viewpoint 12)
Magnitude of impact: Negligible to minor
Significance of effect: Negligible to moderate (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Negligible
N1: Tourist attraction: Tilbury Fort
High
Magnitude of impact: Minor
Significance of effect: Moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Minor
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
15
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with
the potential to affect
this receptor
N1: Tourist attraction: Tilbury Fort
High
Magnitude of impact: Minor
Significance of effect: Moderate (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Negligible to no change
N1: Viewpoints: 12, 13 and 14
High
Medium (PRoW footpath 146 – Viewpoint 12)
Magnitude of impact Negligible to Minor
Significance of effect: Minor to Moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of Change: Minor
N1: Viewpoints: 12, 13 and 14
High
Medium (PRoW footpath 146 – Viewpoint 12)
Magnitude of impact: Negligible to minor
Significance of effect: Minor to Moderate (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Negligible to no change
N1: Viewpoints 15 and 16 High
Magnitude of impact: Minor
Significance of effect: Moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Moderate
N1: Viewpoints 15 and 16 High
Magnitude of impact: Minor
Significance of effect: Moderate (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Negligible to no change
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with
the potential to affect
this receptor
N2: Residential groups east side of Tilbury and Access Land Walton and Parsonage Commons, as well as either side of Fort Road and Cooper Shaw Road
High
Magnitude of impact: No change to minor
Significance of effect: None to Moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Minor to Moderate
N2: Residential groups east side of Tilbury and Access Land Parsonage Commons, as well as either side of Fort Road and Cooper Shaw Road and the Exchange Common Land (Zone E)
High
Magnitude of impact: No change to minor
Significance of effect: None to moderate (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Negligible to no change
N2: Commercial / industrial (Tilbury sewage and substation) and dynamic receptors (rail, Fort Road and Cooper Shaw Road users)
High (rail passengers travelling for pleasure)
Low (people in motor vehicles)
Magnitude of impact: Minor to moderate
Significance of effect: Minor to moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Moderate
N2: Commercial / industrial (Tilbury sewage and substation) and dynamic receptors (rail, Fort Road and Cooper Shaw Road users)
High (rail passengers travelling for pleasure)
Low (people in motor vehicles)
Magnitude of impact: Minor to moderate
Significance of effect: Minor to moderate (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Negligible to no change
N2: Viewpoints 6, 8, 9 and 11
Low (road users)
High (pedestrians VPs 6 and 9)
Magnitude of impact: Minor to Moderate
Significance of effect: Minor to moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Moderate to major
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
16
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with
the potential to affect
this receptor
N2: Viewpoints 6, 8, 9 and 11
Low (road users)
High (pedestrians VPs 6 and 9)
Magnitude of impact: Minor to moderate
Significance of effect: Minor to moderate (Not Significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Negligible to no change
N3: Community facility – St James’ Church graveyard
High
Magnitude of impact: Moderate
Significance of effect: Moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Moderate
N3: Viewpoints 3,4,7 and 10
High
Magnitude of impact: Minor to moderate
Significance of effect: Minor to moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of Change Negligible to moderate
N3: None of the receptors in this location will be significantly adversely affected by the operation and maintenance phases of the other cumulative / non NSIP developments and are not considered further in this assessment. Only the NSIPs have the potential to have cumulative effects.
N4: Tourist attraction and public open space (Coalhouse Fort)
High
Magnitude of impact: No change to negligible
Significance of effect: None to minor (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Minor
N4: Viewpoints 17, 30, 31 and 32
High
Magnitude of impact: No change to Negligible
Significance of effect: None to minor (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Minor
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with
the potential to affect
this receptor
N4: None of the receptors in this location will be significantly adversely affected by the operation and maintenance phases of the other cumulative / non NSIP developments and are not considered further in this assessment. Only the NSIPs have the potential to have cumulative effects on the receptors.
N5: Residential receptors: (Dwellings on the west side of East Tilbury) and PRoWs footpath 67 and bridleways 58 and 63
High
Magnitude of impact: No change to minor
Significance of effect: None to moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Minor to negligible
N5: Viewpoints 1, 2, 5, 33 and 34
High
Magnitude of impact: No change to Negligible
Significance of effect: None to minor to (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Minor
N5: None of the receptors in this location will be significantly adversely affected by the operation and maintenance phases of the other cumulative / non NSIP developments and are not considered further in this assessment. Only the NSIPs have the potential to have cumulative effects on the receptors.
S1: Residential (Gravesend waterfront); Saxon Shore Way, tourist attractions and recreation (Gordon Gardens, New Tavern Fort, Gravesend waterfront); marine-based dynamic receptors
Low (people working on marine vessels) to high
Magnitude of impact: Negligible to minor
Significance of effect: Negligible to moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Moderate
S1: Residential (Gravesend waterfront); Saxon Shore Way, tourist attractions and recreation (Gordon Gardens, New Tavern Fort, Gravesend waterfront); marine-based dynamic receptors
Low (people working on marine vessels) to high
Magnitude of impact: Negligible to Minor
Significance of effect: Negligible to moderate (not significant)
Other relevant developments
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Negligible to no change
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
17
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with
the potential to affect
this receptor
S1: Residential (Gravesend waterfront); Saxon Shore Way, tourist attractions and recreation (Gordon Gardens, New Tavern Fort, Gravesend waterfront); marine-based dynamic receptors
Low (people working on marine vessels) to high
Magnitude of impact: Negligible to minor
Significance of effect: Negligible to Moderate (not significant)
Other relevant developments:
Gravesend Developments:
064 (Policy reference CS04)
Magnitude of impact: Negligible to minor
S1: Viewpoints 18, 19, and 23
Medium (people working at these locations) to high
Magnitude of impact: Negligible to minor
Significance of effect: Minor to Moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Moderate
S1: Viewpoints 20, 21 High
Magnitude of impact: Minor
Significance of effect: Moderate (not significant)
Other relevant developments:
Gravesend Developments:
064 (Policy reference CS04)
Magnitude of impact: Negligible to minor
S2: Residents and public open space users (Windmill Hill, Windmill Gardens, Gravesend), PRoW east of Gravesend
High
Magnitude of impact: Negligible
Significance of effect: Minor (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Minor to moderate
S2: Residents and public open space users (Windmill Hill, Windmill Gardens, Gravesend), PRoW east of Gravesend
High
Magnitude of impact: Negligible
Significance of effect: Minor (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Minor
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with
the potential to affect
this receptor
S2: Residents and public open space users (Windmill Hill, Windmill Gardens, Gravesend), PRoWs east of Gravesend
High
Magnitude of impact: Negligible
Significance of effect: Minor (not significant)
Other relevant developments:
Gravesend Developments:
064 (Policy reference CS04)
Magnitude of impact: Negligible to minor
S2: Viewpoints 22 and 28 High
Magnitude of impact: Negligible
Significance of effect: Minor (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Moderate
S2: Viewpoints 22 and 28 High
Magnitude of impact: Negligible
Significance of effect: Minor (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Minor
S2: Viewpoints 22 and 28 High
Magnitude of impact: Negligible
Significance of effect: Minor (not significant)
Other relevant developments:
Gravesend Developments:
064 (Policy reference CS04)
Magnitude of impact: Negligible
S3: Dynamic road receptors - Harts Hill Kent Downs AONB
Medium (within the AONB)
Magnitude of impact: No change to negligible
Significance of effect: None to minor (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Negligible to minor
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
18
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with
the potential to affect
this receptor
S3: Viewpoint 29 Very High (within the AONB)
Magnitude of impact: Negligible
Significance of effect: Moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Minor
S3: None of the receptors in this location will be significantly adversely affected by the operation and maintenance phases of the other cumulative / non NSIP developments and are not considered further in this assessment. Only the NSIPs have the potential to have cumulative effects.
S4: Tourist attractions including Cliffe Pools RSPB reserve, Cliffe Fort and Shornmead Fort, Saxon Shore Way and PRoWs on Shorne and Higham Marshes
High
Magnitude of impact: Negligible to minor
Significance of effect: Minor to moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Minor to negligible
S4: Viewpoints 24 to 27 High
Magnitude of impact: Negligible to minor
Significance of effect: Minor to moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
058 TR010032 LTC
Magnitude of impact: Minor to negligible
S4: None of the receptors in this location will be significantly adversely affected by the operation and maintenance phases of the other cumulative / non NSIP developments and are not considered further in this assessment. Only the NSIPs have the potential to have cumulative effects.
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
19
Table 1.4: Summary of cumulative developments affecting each receptor (decommissioning).
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with the
potential to affect this
receptor
Landscape Receptors:
LCA C5: Tilbury Marshes Medium
Magnitude of impact: Moderate
Significance of effect: Moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
Magnitude of impact: Moderate (Tilbury2)
LCA C5: Tilbury Marshes Medium
Magnitude of impact: Moderate
Significance of effect: Moderate (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
018 11/50361/TTGETL
050 17/00349/SCR
079 19/01274/FUL
081 12.04.09.04/266C
Magnitude of impact: Minor to negligible
LCA D6: Chadwell Escarpment Urban Fringe
Medium
Magnitude of impact: Minor
Significance of effect: Minor (not significant)
NSIPs:
042 TR030003 Tilbury2
Magnitude of impact: Minor
LCA D6: Chadwell Escarpment Urban Fringe
Medium
Magnitude of impact: Minor
Significance of effect: Minor (not significant)
Other relevant developments:
Chadwell St Mary Developments:
014 16/00412/OUT
034 15/00379/OUT
Magnitude of impact: Negligible to minor
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with the
potential to affect this
receptor
LCA D7: West Tilbury Urban Fringe
Medium
Magnitude of impact: Minor
Significance of effect: Minor (not significant)
NSIPs:
042 TR030003 Tilbury2
Magnitude of impact: Minor
LCA D7: West Tilbury Urban Fringe
Medium
Magnitude of impact: Minor
Significance of effect: Minor (not significant)
Other relevant developments:
East Tilbury Developments:
005 18/00664/CONDC
011 16/01475/SCR
012 16/01232/OUT
Magnitude of impact: Minor
Visual Receptors:
N1: Public Access: Thames Estuary Path PRoW
High
Medium (users of Footpath 146, adjacent to the sewage works, Viewpoint 12)
Magnitude of impact: No change to minor
Significance of effect: None to moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
Magnitude of impact: Minor to Moderate
N1: Public Access: Thames Estuary Path PRoW
High
Medium (users of Footpath 146, adjacent to the sewage works, Viewpoint 12)
Magnitude of impact: No change to minor
Significance of effect: None to moderate (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Negligible
N1: Tourist attraction: Tilbury Fort
High
Medium (users of Footpath 146, adjacent to the sewage works, Viewpoint 12)
Magnitude of impact: No change to minor
Significance of effect: None to moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
Magnitude of impact: Minor
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
20
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with the
potential to affect this
receptor
N1: Tourist attraction: Tilbury Fort
High
Medium (users of Footpath 146, adjacent to the sewage works, Viewpoint 12)
Magnitude of impact: No change to minor
Significance of effect: None to moderate (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: No change to negligible
N1: Viewpoints: 12, 13 and 14
High
Medium (users of Footpath 146, adjacent to the sewage works, Viewpoint 12)
Magnitude of impact: No change to minor
Significance of effect: None to moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
Magnitude of impact: Minor to moderate
N1: Viewpoints: 12, 13 and 14
High
Medium (users of Footpath 146, adjacent to the sewage works, Viewpoint 12)
Magnitude of impact: No change to minor
Significance of effect: None to moderate (Not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: No change to negligible
N1: Viewpoints 15 and 16 High
Magnitude of impact: Negligible to minor
Significance of effect: Minor to moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
Magnitude of impact: Minor to moderate
N1: Viewpoints 15 and 16 High
Magnitude of impact: Negligible to minor
Significance of effect: Minor to moderate (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: No change to negligible
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with the
potential to affect this
receptor
N2: Residential groups east side of Tilbury and Access Land Parsonage Commons, as well as either side of Fort Road and Cooper Shaw Road and Exchange Common Land (Zone E)
High
Magnitude of impact: No change to minor
Significance of effect: None to moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
Magnitude of impact: Minor to moderate
N2: Residential groups east side of Tilbury and Access Land Parsonage Commons, as well as either side of Fort Road and Cooper Shaw Road and Exchange Common Land (Zone E)
High
Magnitude of impact: No change to minor
Significance of effect: None to moderate (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: No change to negligible
N2: Commercial / industrial (Tilbury sewage and substation) and dynamic receptors (rail, Fort Road and Cooper Shaw Road users)
Low to high (rail passengers travelling for pleasure)
Magnitude of impact: Minor to moderate
Significance of effect: Minor to moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
Magnitude of impact: Moderate
N2: Commercial / industrial (Tilbury sewage and substation) and dynamic receptors (rail, Fort Road and Cooper Shaw Road users)
Low to high (rail passengers travelling for pleasure)
Magnitude of impact: Minor to moderate
Significance of effect: Minor to moderate (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: No change to negligible
N2: Viewpoints 6, 8, 9 and 11
Low (road users) to high (pedestrians using Access Land)
Magnitude of impact: Minor to moderate
Significance of effect: Minor (not significant) to major (significant)
NSIPs:
042 TR030003 Tilbury2
Magnitude of impact: Moderate to major
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
21
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with the
potential to affect this
receptor
N2: Viewpoints 6, 8, 9 and 11
Low (road users) to high (pedestrians using Access Land)
Magnitude of impact: Minor to moderate
Significance of effect: Minor (not significant) to major (significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: No change to negligible
N3: Community facility – St James’ Church graveyard
High
Magnitude of impact: Moderate
Significance of effect: Moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
Magnitude of impact: Moderate
N3: Viewpoints 3, 4, 7 and 10
High
Magnitude of impact: Negligible to moderate
Significance of effect: Minor to moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
Magnitude of impact: Negligible to moderate
N3: None of the receptors in this location will be significantly adversely affected by the decommissioning phases of the other cumulative / non NSIP developments and are not considered further in this assessment. Only the NSIPs have the potential to have cumulative effects.
N4: Tourist attraction and public open space (Coalhouse Fort)
High
Magnitude of impact: No Change to negligible
Significance of effect: None to minor (not significant)
NSIPs:
042 TR030003 Tilbury2
Magnitude of impact: Minor
N4: Viewpoints 17, 30, 31 and 32
High
Magnitude of impact: No change to negligible
Significance of effect: None to minor (not significant)
NSIPs:
042 TR030003 Tilbury2
Magnitude of impact: Minor
N4: None of the receptors in this location will be significantly adversely affected by the decommissioning phases of the other cumulative / non NSIP developments and are not considered further in this assessment. Only the NSIPs have the potential to have cumulative effects on the receptors.
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with the
potential to affect this
receptor
N5: Residential receptors: (Dwellings on the west side of East Tilbury) and PRoWs footpath 67 and bridleways 58 and 63
High
Magnitude of impact: No change to minor
Significance of effect: None to moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
Magnitude of impact: Negligible to minor
N5: Viewpoints 5, 33 and 34
High
Magnitude of impact: No change to negligible
Significance of effect: Minor (not significant)
NSIPs:
042 TR030003 Tilbury2
Magnitude of impact: Minor
N5: None of the receptors in this location will be significantly adversely affected by the decommissioning phases of the other cumulative / non NSIP developments and are not considered further in this assessment. Only the NSIPs have the potential to have cumulative effects on the receptors.
S1: Residential (Gravesend waterfront); Saxon Shore Way, tourist attractions and recreation (Gordon Gardens, New Tavern Fort, Gravesend waterfront); marine-based dynamic receptors
Low (people working on marine vessels) to high
Magnitude of impact: Negligible to minor
Significance of effect: Negligible to moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
Magnitude of impact: Moderate
S1: Residential (Gravesend waterfront); Saxon Shore Way, tourist attractions and recreation (Gordon Gardens, New Tavern Fort, Gravesend waterfront); marine-based dynamic receptors
Low (people working on marine vessels) to high
Magnitude of impact: Negligible to Minor
Significance of effect: Negligible to moderate (not significant)
Other relevant developments
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Negligible to no change
S1: Residential (Gravesend waterfront); Saxon Shore Way, tourist attractions and recreation (Gordon Gardens, New Tavern Fort, Gravesend water front); marine-based dynamic receptors
Low (people working on marine vessels) to high
Magnitude of impact: Negligible to minor
Significance of effect: Negligible to moderate (not significant)
Other relevant developments:
Gravesend Developments:
064 (Policy reference CS04)
Magnitude of impact: Negligible to minor
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
22
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with the
potential to affect this
receptor
S1: Viewpoints 18, 19, 20, 21 and 23
Medium (people working at these locations) to high
Magnitude of impact: Negligible to minor
Significance of effect: Negligible to moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
Magnitude of impact: Minor to Moderate
S1: Viewpoints 20 and 21 High
Magnitude of impact: Minor
Significance of effect: Moderate (not significant)
Other relevant developments:
Gravesend Developments:
064 (Policy reference CS04)
Magnitude of impact: Negligible to minor
S2: Residents and public open space users (Windmill Hill, Windmill Gardens, Gravesend), PRoW east of Gravesend
High
Magnitude of impact: Negligible
Significance of effect: Minor (not significant)
NSIPs:
042 TR030003 Tilbury2
Magnitude of impact: Minor to moderate
S2: Residents and public open space users (Windmill Hill, Windmill Gardens, Gravesend), PRoW east of Gravesend
High
Magnitude of impact: Negligible
Significance of effect: Minor (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Negligible
S2: Residents and public open space users (Windmill Hill, Windmill Gardens, Gravesend), PRoW east of Gravesend
High
Magnitude of impact: Negligible
Significance of effect: Minor (not significant)
Other relevant developments:
Gravesend Developments:
064 Policy reference CS04)
Magnitude of impact: Negligible to minor
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with the
potential to affect this
receptor
S2: Viewpoints 22 and 28 High
Magnitude of impact: Negligible
Significance of effect: Minor (not significant)
NSIPs:
042 TR030003 Tilbury2
Magnitude of impact: Negligible to moderate
S2: Viewpoints 22 and 28 High
Magnitude of impact: Negligible
Significance of effect: Minor (not significant)
Other relevant developments:
Tilbury Developments:
016 17/00977/FUL
050 17/00349/SCR
Magnitude of impact: Negligible to minor
S2: Viewpoints 22 and 28 High
Magnitude of impact: Negligible
Significance of effect: Minor (not significant)
Other relevant developments:
Gravesend Developments:
064 Policy reference CS04)
Magnitude of impact: Negligible
S3: Dynamic road receptors - Harts Hill Kent Downs AONB
Medium (within the AONB)
Magnitude of impact: No change to negligible
Significance of effect: None to minor (not significant)
NSIPs:
042 TR030003 Tilbury2
Magnitude of impact: Negligible to minor
S3: Viewpoint 29 Very High
Magnitude of impact: Negligible
Significance of effect: Moderate (not significant)
NSIPs:
042 TR030003 Tilbury2
Magnitude of impact: Minor
S3: None of the receptors in this location will be significantly adversely affected by the decommissioning phases of the other cumulative / non NSIP developments and are not considered further in this assessment. Only the NSIPs have the potential to have cumulative effects.
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
23
Receptor affected Sensitivity of receptor
to cumulative effects
Standalone effect of
Thurrock Flexible
Generation Plant on
receptor
Cumulative
development(s) with the
potential to affect this
receptor
S4: Tourist attractions including Cliffe Pools RSPB reserve, Cliffe Fort and Shornmead Fort, the Saxon Shore Way and PRoWs on Shorne and Higham Marshes
High
Magnitude of impact: Negligible
Significance of effect: Minor (not significant)
NSIPs:
042 TR030003 Tilbury2
Magnitude of impact: Minor
S4: Viewpoints 24 to 27 High
Magnitude of impact: Negligible
Significance of effect: Minor (not significant)
NSIPs:
042 TR030003 Tilbury2
Magnitude of impact: Minor
S4: None of the receptors in this location will be significantly adversely affected by the decommissioning phases of the other cumulative / non NSIP developments and are not considered further in this assessment. Only the NSIPs have the potential to have cumulative effects.
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
24
2. Assessment of Cumulative Effects
2.1 Introduction
2.1.1 The sensitivity judgements stated in this section for each of the landscape and visual
receptors is the same as stated in the main LVIA for the Thurrock FGP proposed
development, Vol 3 Chapter 6.
2.1.2 The location of the representative viewpoints can be found in Figure 1.1 below.
2.1.3 The descriptions for the references given for each of the cumulative developments are
provided in Section 1; Table 1.1. The locations for the individual cumulative
developments can be found at Volume 4, Chapter 18: Cumulative Effects Assessment
Introduction and Screening.
2.1.4 The magnitude of change for each of the receptors results from combining the Thurrock
FGP and cumulative developments with the potential to affect the receptor (columns 3
and 4 in Table 1.2, Table 1.3 and Table 1.4).
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
25
Figure 1.1: Representative Viewpoint Locations
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
26
2.2 Construction phase of Thurrock Flexible Generation Plant
Thurrock Landscape Character Areas
LCA C5: Tilbury Marshes
2.2.1 LCA C5: Tilbury Marshes, will be directly affected by the construction phases of the
cumulative developments within Zones A, to G including most of Zone C. The
sensitivity of the LCA to the proposed construction works is considered to be medium.
2.2.2 The following projects will have the potential for cumulative effects in combination with
the proposed development. The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
○ 058 TR010032 LTC
• Tilbury Developments:
○ 016 17/00977/FUL
○ 018 11/50361/TTGETL
○ 050 17/00349/SCR
○ 079 19/01274/FUL
○ 081 12.04.09.04/266C
NSIPs
2.2.3 The Tilbury2 and LTC NSIPs have the potential to have the following landscape
impacts on this character area in the form of construction traffic haul routes,
construction plant, machinery including cranes and the emerging development.
2.2.4 The construction of Tilbury2 is located directly to the west of Zone A and the causeway
within Zone G. The landscape impacts on the surrounding character of the Tilbury2
site would be in the form of construction traffic haul routes, construction plant,
machinery including cranes and the emerging new dock development.
2.2.5 The LTC is located to the east of Zone A and Zone G and crosses this LCA north to
south. The entrance to the tunnel under the River Thames would be located to the east
of Zone A. The construction phase would be in the form of traffic haul routes,
construction plant, machinery including cranes and the emerging road development.
2.2.6 This landscape character area has historically been subject to large-scale industrial
and dock development as Tilbury has expanded. The magnitude of impact of the
construction works in this area is also considered to be moderate to major.
2.2.7 The LTC would introduce construction traffic and ground modelling into the landscape.
The landscape has an industrial and industrial fringe character which is dynamic and
changing. The significance of the temporary cumulative effect experienced by the LCA
will be moderate to major adverse, which is significant.
Tilbury Developments
2.2.8 The Tilbury developments identified as having the potential for cumulative effects in
combination with the proposed Thurrock Flexible Generation Plant during the
construction phases are located to the west of Zone A of the proposed development
and are associated within or on the edge of the built up area of Tilbury on brownfield
and disused sites and on the western side of the LCA. The construction of these
cumulative developments will involve construction traffic haul routes, construction
plant, machinery including cranes and the respective emerging developments.
2.2.9 This part of the landscape character area has historically been subject to large-scale
industrial land uses and dock development as Tilbury has expanded. The magnitude
of impact of the construction works of these cumulative developments in this area is
considered to be negligible to minor.
2.2.10 These developments would introduce development construction features into an
already dynamic, changing and industrial landscape. The temporary, cumulative effect
experienced by the LCA will be negligible to minor adverse, which are not significant.
LCA D6: Chadwell Escarpment Urban Fringe
2.2.11 LCA D6: Chadwell Escarpment Urban Fringe will be directly affected by the
construction works proposed phase of the proposed development of Zone C (north-
east part) and F1 and F2 (part). It is also indirectly affected by the construction works
within the adjacent Tilbury Marshes LCA. The sensitivity of the LCA to the proposed
construction works is considered to be medium.
2.2.12 The following projects will have the potential for cumulative effects in combination with
the proposed development. The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
○ 058 TR010032 LTC
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
27
• Chadwell St Mary Developments:
○ 014 16/00412/OUT
○ 034 15/00379/OUT
NSIPs
2.2.13 The Tilbury2 and LTC NSIPs have the potential to have the following landscape
impacts on this character area in the form of construction traffic haul routes,
construction plant, machinery including cranes and the emerging development. The
potential effects of Tilbury2 would be indirect and, as noted above, unlikely to coincide
with the Flexible Generation Plant construction. The effects from the construction of
the LTC would be direct.
2.2.14 The LTC is located to the east of Zone A and crosses this character north to south, to
the east of the village of West Tilbury. The construction phase would be in the form of
traffic haul routes, construction plant, machinery including cranes and the emerging
road development which is likely to have substantial cut and fill in this section including
the formation of an embankment, where the land rises from Tilbury Marshes.
2.2.15 The magnitude of impact of the construction works in this area is considered to be
minor. The LTC route would introduce construction traffic and ground modelling into
the landscape. The landscape has an industrial and settlement fringe character. The
temporary, cumulative effect experienced by the LCA will be minor adverse, which is
not significant.
Chadwell St Mary Developments
2.2.16 These two cumulative developments are both potential housing developments for 203
(014) and 43 (034) dwellings at Chadwell St Mary. They have the potential to cause
direct and indirect effects on the western part of the character. They are both located
on the south-eastern edge of Chadwell St Mary. The construction phase would be in
the form of traffic haul routes, construction plant, machinery and the emerging houses.
2.2.17 The magnitude of impact of the construction works in this character area is considered
to be negligible to minor. The landscape here has an urban fringe character. The
temporary, cumulative effect experienced by the LCA will be negligible to minor
adverse, which is not significant.
LCA D7: West Tilbury Urban Fringe
2.2.18 LCA D7: West Tilbury Urban Fringe, will be directly affected by the construction works
proposed for Zones D and I. The sensitivity of this LCA to the proposed construction
works in these zones is medium.
2.2.19 The following projects will have the potential for cumulative effects in combination with
the proposed development. The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
○ 058 TR010032 LTC
• East Tilbury Developments:
○ 005 18/00664/CONDC
○ 011 16/01475/SCR
○ 012 16/01232/OUT
NSIPs
2.2.20 The Tilbury2 and LTC NSIPs have the potential to have the following landscape
impacts on this character area in the form of construction traffic haul routes,
construction plant, machinery including cranes and the emerging development. The
potential effects of Tilbury2 would be indirect and unlikely to coincide with the Flexible
Generation Plant construction. The effects from the construction of the LTC would be
direct.
2.2.21 The LTC is located to the east of Zone A and the route crosses this character east of
West Tilbury across farmland.
2.2.22 The magnitude of impact of the construction works in this area are considered to be
minor. The LTC route would introduce construction traffic and ground modelling into
the landscape. The landscape has a settlement fringe character and although farmland
would be affected there are numerous pylons and overhead wires crossing the
landscape north to south. The temporary, cumulative effect experienced by the LCA
will be minor adverse, which is not significant.
East Tilbury Developments
2.2.23 The three cumulative developments are potential housing developments for 200 (Ref
011) and 1000 (Ref 012) dwellings west of East Tilbury. Development 005 is for 50
dwellings and is located on south side of East Tilbury on the character area boundary.
Developments 011 and 012 have a greater potential than 005 to cause direct impacts
on the character area. The construction phase would be in the form of traffic haul
routes, construction plant, machinery and the emerging houses.
2.2.24 The magnitude of impact of the construction works in this character area is considered
to be minor. The landscape here has an urban fringe character. The temporary,
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
28
cumulative effect experienced by the LCA will be minor adverse, which is not
significant.
Visual Receptors
Group N1: North Thames shore waterfront:
2.2.25 This visual receptor group is located close to where Zone G meets the shoreline on the
north side of the River Thames.
2.2.26 Public Access: Thames Estuary Path / Two Forts Way (Footpath 146) ; tourist
attractions, e.g. visitors to Tilbury Fort are high sensitivity visual receptors. Walkers
using a Section of Footpath 146, adjacent to the sewage works, are medium sensitivity
receptors, due to the location and condition of the footpath at this point.
2.2.27 Representative Viewpoints: 13, 14 ,15 and 16 are all viewpoints that would be
frequented by high sensitivity visual receptors on PRoW FP146. Users of the section
of the footpath at Viewpoint 12 would be medium sensitivity receptors. The viewpoints
are at varying distances from the proposed cumulative developments and within
different visual settings. Viewpoint 12 is close and to the north of Tilbury Fort,
Viewpoints 13 and 14 are close and to the south of Tilbury Fort, whilst Viewpoints 15
and 16 are to the south-east and east of Zones A and G.
2.2.28 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
○ 058 TR010032 LTC
• Tilbury Developments:
○ 016 17/00977/FUL
○ 050 17/00349/SCR
NSIPs
2.2.29 The Tilbury2 and LTC NSIPs have the potential to have the following visual impacts on
these visual receptors in the form of construction traffic haul routes, construction plant,
machinery including cranes and the emerging development. The construction of
Tilbury2 is unlikely to coincide with the Flexible Generation Plant. The construction of
the approach road and tunnelled section of the LTC under the River Thames, is located
on a raised reclaimed section of Tilbury Marshes just east of the Flexible Generation
Plant. The LTC construction development would be dominant in the close views from
the Thames Estuary Path between the former Tilbury B site to where the land at Tilbury
Marshes has been raised and the magnitude of impact would be moderate diminishing
to minor further east. Additionally, for Viewpoints 15 and 16 the construction impact of
the LTC crossing would be moderate to major.
2.2.30 The significance of temporary, cumulative effect would be moderate to major adverse
and significant for a short section approximately 2 km of the Thames Estuary Path. For
representative Viewpoints 15 and 16 the temporary, cumulative effects would be
moderate to major adverse and significant. Whereas, Viewpoints 13 and 14 would
experience minor to moderate adverse temporary, cumulative effects, which are not
significant. Overall, the temporary, cumulative effects of the construction phases of the
three NSIP developments on Group N1: North Thames shore waterfront are significant.
Tilbury developments
2.2.31 Both developments are industrial-related processing facilities set within the context of
existing industrial landscape. Development 016 is for the retention and completion of
a waste wood processing plant and 050 is a screening stage application for a proposed
processing of biofuels and other suitable waste facility, derived from feedstocks to
provide a clean gas product (Use Class B2). The construction phases are likely to take
the form of construction traffic haul routes, construction plant, machinery including
cranes and the emerging development. The construction phases of these
developments are likely to be visible but not prominent in views from the Thames
Estuary Path on the stretch between Tilbury Fort to where the land at Tilbury Marshes
has been raised. The magnitude of impact would be minor diminishing to negligible
further east. Likewise, the impact would be minor within and from Tilbury Fort. The
magnitude of impact would be negligible to minor for Viewpoints 13 and 14 as views
would be partially obscured of the cumulative NSIP construction activities, by Tilbury
Fort. However, for Viewpoints 15 and 16 the construction impact would be negligible.
2.2.32 The significance of the temporary, cumulative effect would be minor adverse (not
significant) for a short section of the Thames Estuary Path directly south of these
developments and minor from Tilbury Fort. Whilst for Viewpoints 15 and 16 the
temporary, cumulative effect would be minor to negligible adverse (not significant).
Whereas, Viewpoints 13 and 14 would experience a temporary minor cumulative effect
(not significant). Therefore, the temporary, cumulative effect of the construction phases
of the Tilbury developments, altogether, on these receptors/representative viewpoints
is not significant.
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
29
Group N2: North side Thames coastal plain:
2.2.33 This visual receptor group is located on the north shore of the River Thames and within
the coastal plain which is similar in extent to the Tilbury Marshes landscape character
area but also includes the built-up area of Tilbury. Group N2 excludes receptors at
Coalhouse Fort which are assessed separately..
2.2.34 The following visual receptors are relevant: Residential receptors - dwellings on the
east and south east side of Tilbury; Access Land - Parsonage and Walton Commons
as well as the areas of Access Land associated with Fort Road and Cooper Shaw
Road; PRoW - footpaths south of Buckland and south of Zone A. All are high sensitivity
receptors.
2.2.35 Visual commercial and industrial facility receptors at the Tilbury substation and sewage
works and dynamic road receptors on Fort Road and Cooper Shaw Road, together
with rail travellers on the rail line which runs from Tilbury north-eastwards across this
area vary between having a low and high sensitivity.
2.2.36 Representative Viewpoints: 6, 8, 9 and 11 are all low sensitivity visual road user
receptors and where relevant represent the views of high sensitivity pedestrian users
of Access Land. The viewpoints are located at varying distances from the proposed
cumulative developments and within different visual settings. Viewpoint 8 is close to
the LTC whilst Viewpoints 9 and 11 are close to Tilbury2. Viewpoint 6 is a similar
distance to both cumulative NSIPs.
2.2.37 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
○ 058 TR010032 LTC
• Tilbury Developments:
○ 016 17/00977/FUL
○ 050 17/00349/SCR
NSIPs
2.2.38 The Tilbury2 and LTC NSIPs have the potential to have the following visual impacts on
receptors in the form of construction traffic haul routes, construction plant, machinery
including cranes and the emerging development. The construction of Tilbury2 is
unlikely to coincide with the Flexible Generation Plant. The construction of the LTC
under the River Thames and approach road, on the north side of the River Thames will
be extensive and adjacent to Zones A, G and C of the proposed Flexible Generation
Plant development. The LTC construction works would be dominant in close views
experienced by receptors on Access Land at Parsonage Common, the areas of Access
Land associated with Fort Road and Cooper Shaw Road and the PRoW to the east of
the site of the former Tilbury B power station. The magnitude of impact would be minor
to moderate. Likewise, the magnitude of impact would be moderate for visual
receptors at Tilbury sewage works and the electricity substation. The magnitude of
impact for dynamic receptors would be moderate to minor depending on proximity
and level of intervening screening. The impact would be moderate to major for
Viewpoints, 6, 8 and 9 for the LTC, as views of the construction would dominate from
these locations..
2.2.39 The temporary, cumulative significance of effect would be minor to major adverse for
residential groups on the eastern edge of Tilbury (not significant) and users of the
Access Land at Walton and Parsonage Commons and the areas of Access Land
associated with Fort Road and Cooper Shaw Road (significant). The commercial and
industrial visual receptors at the sewage works and substation on the east side of
Tilbury would experience a temporary moderate adverse cumulative effect, which is
not significant. The effect on the relevant representative viewpoints would be minor to
major (not significant to significant).
Tilbury developments
2.2.40 Both developments are for industrial related processing facilities set within the context
of existing industrial use landscape. 016 is for the retention and completion of a waste
wood processing plant and 050 is a screening stage application for a proposed facility
for processing of biofuels and other suitable feedstocks into a manufactured clean gas
product (Use Class B2). The construction phases are likely to take the form of
construction traffic haul routes, construction plant, machinery including cranes and the
emerging development. The construction phases of these developments are likely to
vary from being barely perceptible to visible but not prominent in views. From
residential receptor groups on the east side of Tilbury and Access Land views will be
perceptible but set against the backdrop of a changing and industrial landscape the
magnitude of impact will be no change to negligible. For commercial and industrial
visual receptors at the sewage works and substation, as well as dynamic receptors on
Fort Road, Cooper Shaw Road and using the railway, the impact will also be no
change to negligible.
2.2.41 The representative Viewpoints 6, 8, 9 and 11 would all experience a magnitude of
impact varying from no change to negligible.
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
30
2.2.42 The temporary, cumulative significance of effects would be none to minor adverse for
residential groups on the eastern edge of Tilbury and users of the Access Land at
Walton and Parsonage Commons as well as the areas of Access Land associated with
Fort Road and Cooper Shaw Road, which are not significant. The commercial and
industrial visual receptors at the sewage works and substation on the east side of
Tilbury would experience temporary none to negligible adverse cumulative effects,
which are not significant. The temporary, cumulative effects on representative
viewpoints would be none to minor adverse and not significant.
Group N3: South facing Chadwell St Mary escarpment
2.2.43 This visual receptor group is located on the south facing escarpment of the Chadwell
Escarpment Urban Fringe character area. There is potential for elevated views over
the coastal plain from vantage points. However, there are few publicly accessible
locations and the representative viewpoints are from specific and generally non-
extensive areas or sections of PRoW.
2.2.44 The community facility of St James’ Church graveyard together with specific locations
along PRoW Footpaths 200 and 72 are the only receptor groups that have the potential
to be adversely affected in this area. These are of high sensitivity.
2.2.45 Representative Viewpoints: 3, 4, 7 and 10 are all high sensitivity visual receptors. The
viewpoints are at varying distances from the proposed cumulative developments and
within different visual settings.
2.2.46 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
○ 058 TR010032 LTC
2.2.47 None of the receptors in this location will be significantly adversely affected by the
construction phases of the other cumulative developments and are not considered
further in this assessment. Only the above NSIPs have the potential to have significant
adverse cumulative effects.
NSIPs
2.2.48 The Tilbury2 and LTC NSIPs have the potential to have the following visual impacts on
these visual receptors in the form of construction traffic haul routes, construction plant,
machinery including cranes and the emerging development. The construction of
Tilbury2 is unlikely to coincide with the Flexible Generation Plant. The construction of
the LTC under the River Thames, on the north side of the River Thames will be
extensive and adjacent to Zones A, G and C of the proposed Flexible Generation Plant
development. The LTC construction development would be prominent in specific and
not extensive near views diminishing to visible but not prominent in more distant views
and those restricted in extent by intervening vegetation.
2.2.49 Views from St James’ Church graveyard of the construction phases of both NSIPs but
particularly the LTC are available from a small area and would be prominent and
therefore the magnitude of impact would be moderate. Views from footpath 200 of the
construction of the LTS is very restricted by thick intervening vegetation and landform,
whilst from footpath 72 the views are distant, over 1.2 km away, and viewed from an
industrial urban fringe setting. These factors limit the magnitude of the impact to
negligible to minor.
2.2.50 From the representative viewpoints the magnitude of impact on the view would vary
from minor for Viewpoints 3 and 4 due to the distance to the development, the
industrial urban fringe setting and intervening landform and vegetation. The magnitude
of the impact would be moderate for Viewpoints 7 and 10.
2.2.51 The temporary, cumulative significance of effect would be minor adverse (not
significant) for footpaths 72 and 200 apart from a small section represented by
Viewpoint 10 which would be moderate adverse (not significant). For Viewpoints 3 and
4 the effect would be minor adverse (not significant). However, for St James’ Church
graveyard and Viewpoint 7 the temporary, cumulative effect would be major adverse,
which is significant.
Group N4: Coalhouse Fort area
2.2.52 This visual receptor group is located at Coalhouse Fort and its immediate surroundings
including public open space extending to the disused radar station structure on the
foreshore and the defensive moats. This group is comprised of high sensitivity visual
receptors which includes people using the public open space, PRoW and Coalhouse
Fort itself.
2.2.53 The representative Viewpoints 17, 30, 31 and 32 are all accessed by high sensitivity
receptors.
2.2.54 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 058 TR010032 LTC
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
31
2.2.55 None of the receptors in this location will be significantly adversely affected by the
construction phases of the other cumulative developments and are not considered
further in this assessment. Only the NSIPs have the potential to have significant
adverse effects.
NSIPs
2.2.56 The LTC NSIP has the potential to have the following visual impacts on these visual
receptors in the form of construction traffic haul routes, construction plant, machinery
including cranes and the emerging development. The construction of the LTC under
the River Thames and approach road, on the north side of the River Thames will be
extensive and adjacent to Zones A, G and C of the proposed Flexible Generation Plant
development. However, the LTC construction development would be partly visible to
barely perceptible and not prominent from when viewed from within the public open
space surrounding Coahouse Fort, or from the fort itself. Therefore, the magnitude of
impact would not exceed minor.
2.2.57 Overall, the temporary, cumulative significance of effect on views would be minor to
moderate adverse which are not significant.
Group N5: North of the Chadwell St Mary to east Tilbury escarpment ridge line
2.2.58 This visual receptor group is located north of the ridge of the Chadwell St Mary to East
Tilbury escarpment, where the land gradually falls northward allowing views across the
farmed landscape to the north and more restricted views south. The location of these
receptors coincides with the West Tilbury Urban Fringe LCA. The following visual
receptors are relevant and are of high sensitivity; Residential receptors: dwellings on
the west side of Tilbury and PRoW footpaths 67 and bridleways 58 and 63. Although
there are other receptor groups like dynamic road user receptors they are not
considered to be of high sensitivity and because the magnitude of change is reduced
because of distance, intervening landform and vegetation from the cumulative
developments they are not considered further in this assessment.
2.2.59 The representative Viewpoints 5, 33 and 34 are high sensitivity receptors and have
the potential to be adversely affected. The effects on Viewpoints 1 and 2 have been
dismissed for further assessment as they are too distant, well screened from the
cumulative developments.
• NSIPs:
○ 042 TR030003 Tilbury2
○ 058 TR010032 LTC
2.2.60 None of the receptors in this location will be significantly adversely affected by the
construction phases of the other cumulative developments and are not considered
further in this assessment. Only the NSIPs have the potential to have significant
adverse effects.
NSIPs
2.2.61 The Tilbury2 and LTC NSIPs have the potential to have the following visual impacts on
these visual receptors in the form of construction traffic haul routes, construction plant,
machinery including cranes and the emerging development. The construction of
Tilbury2 is unlikely to coincide with the Flexible Generation Plant. The construction of
the LTC under the River Thames, on the north side of the River Thames will be fairly
extensive and adjacent to Zones A, G and C of the proposed Flexible Generation Plant
development and construction activities would extend into the West tilbury Urban
Fringe. The NSIP LTC development would be visible but not prominent and Tilbury2
would be barely perceptible from the PRoWs in most views in this receptor group. The
magnitude of impact would be negligible to minor. The representative Viewpoints 5,
33 and 34 represent the worse-case scenarios from the PRoW in this area and the
magnitude of impact from these locations would also be negligible to minor.
2.2.62 Overall, the temporary, cumulative significance of effect would be minor to moderate
adverse, as it would be for the N5 representative Viewpoints 5, 33 and 34, which are
not significant.
Group S1: River Thames south shore and waterfront
2.2.63 This visual receptor group is located on the River Thames south shore and waterfront
and have generally open views across the river to the north shore. The following visual
receptor groups includes: Residents located along the Gravesend waterfront; public
access and tourist attractions at Gravesend’s Gordon Recreation Ground and
Gardens; visitors to New Tavern Fort; and walkers using the Saxon Shore Way. These
receptors are all deemed to have a high sensitivity to the proposed developments.
Commercial receptors at Gravesend and industrial receptors at Milton and dynamic
receptors onboard marine vessels are judged to be of low to high (passengers on
marine vessels) sensitivity. Only the high sensitivity receptors have the potential to be
significantly adversely affected by the cumulative developments, consequently the
medium and low sensitivity visual receptors are not considered further in this
assessment.
2.2.64 The following representative viewpoints have the potential to be adversely affected,
they are Viewpoints 18, 19, 20, 21 and 23 which are on the Saxon Shore Way and
Viewpoint 19 which is on the passenger wharf for the Thames ferry and consequently
they are all of high sensitivity.
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
32
2.2.65 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
○ 058 TR010032 LTC
• Tilbury Developments:
○ 016 17/00977/FUL
○ 050 17/00349/SCR
• Gravesend Developments:
○ 064 (Policy ref CS04)
NSIPs
2.2.66 The Tilbury2 and LTC NSIPs have the potential to have the following visual impacts on
these visual receptors in the form of construction traffic haul routes, construction plant,
machinery including cranes and the emerging development. The construction of
Tilbury2 is unlikely to coincide with the Flexible Generation Plant. The entrance works
to the north side of the LTC tunnel under the River Thames and approach road, will be
next to a raised section of Tilbury Marshes. The NSIP’s construction would be visible,
but not prominent in views on the Gravesend waterfront. The magnitude of impact
would be moderate from the Saxon Shore Way as well as the public access and tourist
attractions along the Gravesend waterfront including the Gravesend Gordon
Recreation Ground and Gardens and New Tavern Fort.
2.2.67 The magnitude of impact for Viewpoints 18, 19, 20, 21 and 23, will be moderate
because of the proximity and open nature of views of the southern sections of both of
the NSIP’s construction phases.
2.2.68 Overall people using the Saxon Shore Way and Gravesend waterfront, public access
and tourist attractions will experience temporary, cumulative moderate to major
adverse effects, which are not significant to significant. People at the representative
viewpoint locations in will experience temporary, cumulative moderate to major
adverse effects, which are not significant to significant.
Tilbury Developments
2.2.69 Both cumulative developments are for industrial related processing facilities set within
the context of existing industrial use landscape. Development 016 is for the retention
and completion of a waste wood processing plant and 050 is a screening stage
application for a facility processing biofuels and other suitable waste, derived from
feedstocks, to produce a clean gas product (Use Class B2). The construction impacts
are likely to take the form of construction traffic haul routes, construction plant
machinery, including cranes, as well as the emerging developments. The construction
phases of these projects will be visible, but not prominent or barely perceptible, in views
across the river to the stretch of shoreline between Tilbury Fort and the ongoing land
raising scheme on Tilbury Marshes. The magnitude of impact on available views from
the Gravesend waterfront and the Saxon Shore Way would be negligible to moderate.
The magnitude of impact would be moderate for Viewpoints 18, 19, and 23 would be
negligible to minor for Viewpoints 20, 21 as views would be partially obscured by
existing intervening features such as Tilbury Fort and the Tilbury2 (NSIP) construction
activities / operational phase.
2.2.70 The temporary, cumulative significance of effect would be minor to negligible adverse
(not significant) for a short section (approximately 0.5 km) of Gravesend waterfront and
Saxon Shore Way visual receptors. Representative Viewpoints 20 and 21 would also
experience a temporary minor adverse cumulative effect (not significant). The
cumulative construction phases of thedevelopments will not have a significant effect.
Gravesend Developments
2.2.71 The construction of the Canal Basin Regeneration project will have impacts on the
surrounding character and views. Receptors will have views of the construction of the
new housing, school, retail and road development. The magnitude of impact will vary
between negligible to minor.
2.2.72 The significance of the temporary, cumulative effect of the proposed development on
the high sensitivity visual receptors would be minor to moderate, depending on the
location of the receptor and the intervening buildings, which are not significant.
Group S2: Elevated locations at Gravesend
2.2.73 This visual receptor group is located at elevated locations within and on the fringes of
Gravesend. These include residential and public access receptors in Gravesend,
particularly Windmill Gardens and Windmill Hill, and the PRoW footpath east of
Gravesend and south of Chalk which rises through farmland to the south- east. These
receptors are all deemed to be of high sensitivity.
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
33
2.2.74 The following representative viewpoints have the potential to be adversely affected;
Viewpoints 22 at Windmill Gardens and Viewpoint 28 from a PRoW located in an open
field south of Chalk, which are elevated views over Gravesend and Chalk respectively.
People at these locations will have a high sensitivity to the proposed developments.
2.2.75 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
○ 058 TR010032 LTC
• Tilbury Developments:
○ 016 17/00977/FUL
○ 050 17/00349/SCR
• Gravesend Developments:
○ 064 (policy ref CS04)
NSIPs
2.2.76 The Tilbury2 and LTC NSIPs have the potential to have the following visual impacts on
receptors in the form of construction traffic haul routes, construction plant, machinery
including cranes and the emerging development. The construction of Tilbury2 is
unlikely to coincide with the Flexible Generation Plant. The entrance works to the north
side of the LTC tunnel under the River Thames and approach road, will be next to a
raised/reclaimed section of Tilbury Marshes. More of the LTC construction
development would be visible than receptor group S1, due to the raised locations of
the views but also the views of the rest of the landscape on the north side of the
Thames would be more extensive. The construction phase of the LTC would vary from
visible but not prominent from theses elevated residential and public access visual
receptors and the change would be minor to moderate depending on the elevation
and the amount of intervening development and vegetation.
2.2.77 The magnitude of change for the Viewpoint 28 for the construction phase of the LTC,
will be moderate because of the open exposed views from this location and negligible
for Viewpoint 22 due to the long-distance views to the LTC.
2.2.78 Overall the residential and publicly accessible locations on the Footpath east of
Gravesend and to the south of Chalk will experience temporary minor to moderate
adverse cumulative effects which are not significant. Viewpoint 28 will also experience
a temporary moderate adverse cumulative visual effect, which is not significant.
Tilbury Developments
2.2.79 Both cumulative developments are for industrial related processing facilities set within
the context of existing industrial land uses. Development 016 is for the retention and
completion of a waste wood processing plant and 050 is a screening stage application
for a proposed facility for processing biofuels and other suitable waste, derived from
feedstocks to produce clean gas product (Use Class B2). The construction phases are
likely to take the form of construction traffic haul routes, construction plant, machinery
including cranes and the emerging development. The construction phases of these
developments are likely to be visible (but not prominent) to barely perceptible in
elevated views from Gravesend across the Thames. The magnitude of impact from
Gravesend-based visual receptors would be minor diminishing to negligible for views
located at lower elevations and for those where the views are interrupted by intervening
development and/or vegetation.
2.2.80 The magnitude of impact would be negligible for Viewpoints 22 and 28 as views would
be partially obscured by existing intervening features such as Tilbury Fort and the
Tilbury2 (NSIP) construction phase.
2.2.81 The significance of the temporary, cumulative effects would be minor to moderate
adverse (not significant).. Visual receptors at representative Viewpoints 22 and 28
would also experience a temporary minor or moderate adverse cumulative effect (not
significant). The construction phases of these developments will not have a significant
effect on these visual receptors.
Gravesend Development
2.2.82 This development is for a residential redevelopment of a former waterside industrial
use area in east Gravesend known as Gordon Promenade East. The construction
phase is likely to take the form of construction traffic, construction plant, machinery
including cranes and the emerging development. The construction phase of this
development is likely to be visible (but not prominent) to barely perceptible in elevated
views from Gravesend across the Thames. The magnitude of impact experienced by
Gravesend-based visual receptors would negligible. The magnitude of impact would
also be negligible for receptors at Viewpoints 22 and 28. Views would be obscured by
existing intervening existing buildings, although higher structures such as cranes would
be visible.
2.2.83 The temporary, cumulative significance of effect would be minor adverse (not
significant). People at representative Viewpoints 22 and 28 would also experience a
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
34
temporary minor adverse cumulative effect and therefore not significant. The
construction phase of this development would not have a significant cumulative effect.
Group S3: Northern edge Kent Downs AONB
2.2.84 This visual receptor group is located on the northern edge and north facing slopes of
the national landscape designation of the Kent Downs. These are dynamic visual
receptors, which have intermittent and infrequent views through from the minor road
running through Brummelhill Wood. These dynamic visual receptors are deemed to be
of a medium sensitivity.
2.2.85 Representative Viewpoint 29 is on the minor road which runs along the northern
boundary of the Kent Downs AONB with elevated views over the River Thames coastal
plain landscape. A pedestrian at this location would have ahigh sensitivity to the
proposed cumulative developments.
2.2.86 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
○ 058 TR010032 LTC
2.2.87 None of the receptors in this location will be significantly adversely affected by the
construction phases of the other cumulative developments and are not considered
further in this assessment. Only the NSIPs have the potential to have significant
adverse effects.
2.2.88 The Tilbury2 and LTC NSIPs have the potential to have the following visual impacts on
these visual receptors in the form of construction traffic haul routes, construction plant,
machinery including cranes and the emerging development. The construction of
Tilbury2 is unlikely to coincide with the Flexible Generation Plant. The entrance works
and approach road construction on the north side of the LTC tunnel under the River
Thames, will be next to a raised reclaimed section of Tilbury Marshes. However, the
southern entrance of the LTC would be the closest part of the project to the AONB and
Viewpoint 29. The transient views of the LTC construction would vary from barely
perceptible for most of receptor views to occasionally visible (but not prominent) from
this rural road therefore the magnitude of impact would be negligible to minor
depending on the amount of intervening roadside vegetation. The magnitude of impact
would be minor for Viewpoint 29 as views would be long distance (>6km) and the
change set in the context of a predominantly dynamic industrial landscape.
2.2.89 The temporary, cumulative significance of effect would be minor adverse (not
significant) for the people in vehicles. For pedestrians at representative Viewpoint 29
there would be a minor effect and therefore not significant. Receptors viewing the
construction phases of these developments would not experience a significant impact.
Group S4: South side Thames coastal plain
2.2.90 This visual receptor group is located on the south side of the Thames on marshes and
reclaimed marshland and includes the following visual receptor groups greater than 2.5
km from the proposed Flexible Generation Plant: Tourist attractions including Cliffe
Pools RSPB reserve, Cliffe Fort and Shornmead Fort are located in this area. The
Saxon Shore Way and footpaths on Shorne and Higham Marshes form part of the
PRoW network. People visiting or using these attractions/PRoW are all judged to be
high sensitivity visual receptors.
2.2.91 People at Representative Viewpoints: 24, 25, 26 and 27 are all high sensitivity visual
receptors. The viewpoints are at varying distances from the proposed cumulative
developments and within similar estuary side settings with a predominantly low-lying
and flat marsh or drained marsh, farmed hinterland.
2.2.92 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
○ 058 TR010032 LTC
2.2.93 None of the receptors in this location will be significantly adversely affected by the
construction phases of the other cumulative developments and are not considered
further in this assessment. Only the NSIPs have the potential to have significant
adverse effects.
2.2.94 The Tilbury2 and LTC NSIPs have the potential to have the following visual impacts on
these visual receptors in the form of construction traffic haul routes, construction plant,
machinery including cranes and the emerging development. The construction of
Tilbury2 is unlikely to coincide with the Flexible Generation Plant. The entrance works
and approach road construction on the north side of the LTC tunnel under the River
Thames, will be next to a raised reclaimed section of Tilbury Marshes. The
construction work on the southern entrance to the LTC tunnel will be closer to these
visual receptors, but will not be seen in the same view as the Tilbury2 and Thurrock
Flexible Generation Plant works as they are situated behind or to the side of the viewer.
The views of the NSIPs, particularly the LTC construction would vary from barely
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
35
perceptible to visible (but not prominent) for the closer visual receptors such as
Shornmead Fort and the Saxon Shore Way to the north of Shorne Marshes. Therefore,
the magnitude of impact is judged to be minor.
2.2.95 The magnitude of impact for Viewpoints 24, 25, 26 and 27, will be minor.
2.2.96 Overall, the temporary, cumulative significance of effect experienced by visual
receptors in this area and at the location of the representative viewpoints would be no
greater than moderate, which is not significant.
2.3 Operation and maintenance phase of Thurrock Flexible
Generation Plant
Thurrock Landscape Character Areas
LCA C5: Tilbury Marshes
2.3.1 LCA C5: Tilbury Marshes, will be directly affected by the operation and maintenance
phases of the cumulative developments. It is a large-scale landscape with extensive
open and exposed land dominated by the sky. The sensitivity of the LCA to the
proposed operation and maintenance works is considered to be medium.
2.3.2 The following projects will have the potential for cumulative effects in combination with
the proposed development. The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
○ 058 TR010032 LTC
• Tilbury Developments:
○ 016 17/00977/FUL
○ 018 11/50361/TTGETL
○ 050 17/00349/SCR
○ 079 19/01274/FUL
○ 081 12.04.09.04/266C
NSIPs
2.3.3 The Tilbury2 and LTC NSIPs have the potential to have the following landscape
impacts on the Tilbury Marshes LCA in the form of new dockside development
buildings, loading wharf, lifting gear, road access and container storage. Tilbury2 will
extend over the former Tilbury B power station site northwards to the railway line. The
LTC NSIP development will consist of a new road, tunnel under the River Thames and
road infrastructure on the north side of the River Thames. The Tilbury Marshes LCA,
will be directly affected by the Tilbury2 and LTC NSIPs have the potential to have visual
and perceptual impacts on the landscape.
2.3.4 This landscape character area has historically been subject to large scale industrial
and dockland development as Tilbury has expanded. The magnitude of impact of both
NSIPs in this area is also considered to be moderate to major.
2.3.5 The Tilbury2 NSIP will be on a brownfield site which was part of the recently
demolished Tilbury B power station site. The LTC would introduce a new road, tunnel
junctions and road bridges into the Tilbury Marshes farmland landscape. However, the
landscape has an industrial and industrial fringe character which is dynamic. The
significance of effect on the LCA will be moderate to major adverse, which are not
significant to significant effects.
Tilbury Developments
2.3.6 The Tilbury developments identified as having the potential for cumulative effects in
combination with the proposed Thurrock Flexible Generation Plant are located to the
west of Zone A of the proposed development and are associated within or on the edge
of the built up area of Tilbury on brownfield and disused sites and on the western side
of the LCA. The developments will repurpose predominantly brownfield sites with a
mixture of industrial processing and energy generation facilities, together with
associated storage and access.
2.3.7 This part of the landscape character area has historically been subject to large scale
industrial and dock development as Tilbury has expanded. The magnitude of impact of
the construction works of these cumulative developments in this area is considered to
be minor to negligible.
2.3.8 These developments would add similar function, style and massing into an already
dynamic and industrial landscape. The effect experienced the LCA will be negligible
to minor which is not significant.
LCA D6: Chadwell Escarpment Urban Fringe
2.3.9 The sensitivity of the LCA to the proposed cumulative developments is considered to
be medium. The fairly unspoilt rural character in the east of the character area is the
most sensitive part of this LCA to change from developments.
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
36
2.3.10 The following projects will have the potential for cumulative effects in combination with
the proposed development. The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
○ 058 TR010032 LTC
• Chadwell St Mary Developments:
○ 014 16/00412/OUT
○ 034 15/00379/OUT
NSIPs
2.3.11 Tilbury2 and LTC NSIPs have the potential to have the following landscape direct
impacts on this character area. The LTC NSIP development will consist of a new road,
tunnel under the River Thames and road infrastructure on the north side of the River
Thames. The LTC NSIP would have the potential to have direct effects of a new major
approach road to the tunnel and indirect effects in the form of visual and traffic and
noise intrusion from the LTC development on the landscape character. The potential
effects of Tilbury2 would be indirect and direct from LTC.
2.3.12 The magnitude of impact of the LTC major development is also considered to be
minor. The LTC route would introduce a new major road, traffic and new landform into
a landscape which has an industrial and settlement fringe character. The effect
experienced by the LCA will be minor adverse, which is not significant.
Chadwell St Mary Developments
2.3.13 The two cumulative developments are both potential housing developments for 203
and 43 dwellings respectively at Chadwell St Mary. They have the potential to cause
direct and indirect effects on the western part of the character. They are both located
on the south eastern edge of Chadwell St Mary. The direct effects on the landscape
would be a new road and associated landform.
2.3.14 The magnitude of Impact of the development in this character area is considered to be
negligible to minor. The landscape here has an urban fringe character. The effect
experienced by the LCA will be negligible to minor adverse, which is not significant.
LCA D7: West Tilbury Urban Fringe
2.3.15 This character area is a fairly open landscape with limited tree cover, visual intrusion
of existing developments including pylons and industrial use areas gives the landscape
an urban fringe character. The sensitivity of this LCA to the proposed construction
works in these zones is medium.
• NSIPs:
○ 042 TR030003 Tilbury2
○ 058 TR010032 LTC
• East Tilbury Developments:
○ 005 18/00664/CONDC
○ 011 16/01475/SCR
○ 012 16/01232/OUT
NSIPs
2.3.16 The LTC NSIPs has the potential to have the following landscape impacts on this
character area. The development will consist of a new road, tunnel under the River
Thames and road infrastructure on the north side of the River Thames. The LTC NSIP
would have the potential to have direct effects of a new major approach road to the
tunnel and indirect effects in the form of visual and traffic and noise intrusion on the
landscape character. The potential effects of Tilbury2 would be indirect and unlikely to
coincide with the Flexible Generation Plant construction.
2.3.17 The magnitude of impact due to the direct effects of the LTC development on this
character area are considered to be minor. The landscape has a settlement fringe
character and although farmland would be affected there are numerous pylons and
overhead wires crossing the landscape south to north. The effect experienced by the
LCA will be minor adverse, which is not significant.
East Tilbury Developments
2.3.18 The three cumulative developments are potential housing developments for 200 (Ref
011) and 1000 (Ref 012) dwellings west of East Tilbury. In addition, development 005
is for 50 dwellings and is located on south side of East Tilbury on the character area
boundary. Developments 011 and 012 have a greater potential than 005 to cause direct
impacts on the character area. The developments would take the form of settlement
edge housing and access roads.
2.3.19 The magnitude of Impact of the construction works in this character area is considered
to be minor. The landscape here has an urban fringe character. The effect experienced
by the LCA will be minor adverse, which is not significant.
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
37
Visual Receptors
Group N1: North Thames shore waterfront
2.3.20 This visual receptor group is located close to where Zone G meets the shoreline on the
north side of the River Thames.
2.3.21 Public Access: Thames Estuary Path / Two Forts Way (Footpath146); and Tourist
Attractions: visitor receptors to Tilbury Fort in group N1 are high sensitivity visual
receptors.
2.3.22 Representative Viewpoints: 13, 14 ,15 and 16 are all high sensitivity visual receptors
on PRoW FP146. The viewpoints are at varying distances from the proposed
cumulative developments and within different visual settings. Viewpoints 13 and 14 are
close to Tilbury Fort whilst 15 and 16 are to the south east and east of Zones A and G.
2.3.23 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
○ 058 TR010032 LTC
• Tilbury Developments:
○ 016 17/00977/FUL
○ 050 17/00349/SCR
NSIPs
2.3.24 The LTC NSIP has the potential to have the following visual impacts on the N1 group
of visual receptors in the form of new dockside development buildings, loading wharf,
lifting gear, road access and container storage. Tilbury2 will extend over the former
Tilbury B power station site northwards to the railway line. It will be adjacent to the
section of the Thames Estuary path from Tilbury Fort to the former Tilbury B power
station site. The LTC NSIP development will consist of a new road, tunnel under the
River Thames and road infrastructure on the north side of the River Thames. The
approach road and tunnelled section of the LTC under the River Thames, will be over
a raised reclaimed section of Tilbury Marshes. The NSIP developments would be
significant to dominant in the close views from the Thames Estuary Path between
Tilbury Fort to stretch adjacent to where the land at Tilbury Marshes has been raised
and the magnitude of change would be moderate diminishing to minor further east.
Likewise, the impact would be minor within and from Tilbury Fort.
2.3.25 The change would be minor for Viewpoints 12, 13 and 14 as views would be partially
obscured of the cumulative NSIP developments, by Tilbury Fort. However, the impact
of change for Viewpoints 15 and 16 particularly the LTC road and related infrastructure
and the new wharf at Tilbury2 would be moderate.
2.3.26 The significance of effect would be moderate to major and significant for a short
section (approximately 2km) of the Thames Estuary path where the developments
coincide with the shoreline and minor to moderate from Tilbury Fort diminishing
westwards. For representative Viewpoints 15 and 16 the impact would be moderate
to major and significant. Whereas Viewpoints 13 and 14 would experience a minor to
moderate effect and not significant. Overall the operation and maintenance phases of
these developments are significant for a few specific receptors.
Tilbury developments
2.3.27 Both developments are for industrial related processing facilities set within the context
of existing industrial use landscape. Development 016 is for the retention and
completion of a waste wood processing plant and 050 is a screening stage application
for a proposed processing of biofuels and other suitable waste facility, derived from
feedstocks into a manufactured clean gas product (Use Class B2). The operation and
maintenance phases are likely to take the form of industrial use buildings and
associated infrastructure. The developments are likely to be visible but not prominent
in views from the Thames Estuary Path on the stretch between Tilbury Fort to where
the land at Tilbury Marshes has been raised. The magnitude of change would be minor
diminishing to negligible further east. Likewise, the impact would be minor within and
from Tilbury Fort.
2.3.28 The change would be negligible to no change for Viewpoints 12, 13 and 14 as views
would be partially obscured of the cumulative NSIP developments, by Tilbury Fort. For
Viewpoints 15 and 16 the effect of these developments would be negligible to none.
2.3.29 The significance of effect would be minor and not significant for a short section of the
Thames Estuary path directly south of these developments and minor from Tilbury
Fort. Whilst for representative Viewpoints 15 and 16 the impact would be minor to
negligible and not significant. Whereas Viewpoints 13 and 14 would experience a
minor effect and not significant. Therefore, the operation and maintenance phases of
these developments are not a significant impact.
Group N2: North side Thames coastal plain
2.3.30 This visual receptor group is located on the north shore of the River Thames and within
the coastal plain which is similar in extent to the Tilbury Marshes landscape character
area but also includes the built-up area of Tilbury. Coalhouse Fort is dealt with as a
separate visual receptor group.
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
38
2.3.31 The following visual receptors are relevant; Residential receptors: Dwellings on the
east and south east side of Tilbury. Access Land: Parsonage and Walton Commons.
PRoW: footpaths south of Buckland and south of Zone A are all high sensitivity
receptors.
2.3.32 Visual commercial and industrial facility receptors at the Tilbury substation and sewage
works and dynamic road receptors along Fort Road and Cooper Shaw Road together
with rail passengers on the rail line which runs from Tilbury north eastwards across this
area are medium sensitivity visual receptors.
2.3.33 Representative Viewpoints: 6, 8, 9 and 11 are low sensitivity road user visual receptors
and Viewpoints 6 and 9 are also high sensitivity pedestrian visual receptors. Although
from fieldwork it appears that there are very few pedestrians using the areas where
Viewpoints 6 and 9 are located. The viewpoints are at varying distances from the
proposed cumulative developments and within different visual settings. Viewpoint 8 is
close to the LTC whilst 9 and 11 are close to Tilbury2. Viewpoint 6 is a similar distance
to both cumulative NSIPs.
2.3.34 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the
planningapplication reference:
• NSIPs:
○ 042 TR030003 Tilbury2
○ 058 TR010032 LTC
• Tilbury Developments:
○ 016 17/00977/FUL
○ 050 17/00349/SCR
NSIPs
2.3.35 Tilbury2 NSIP has the potential to have the following visual impacts on the N2 group
of visual receptors in the form of new dockside development buildings, loading wharf,
lifting gear, road access and container storage. Tilbury2 will extend over the former
Tilbury B power station site northwards to the railway line. The LTC NSIP development
will consist of a new road, tunnel under the River Thames and road infrastructure on
the north side of the River Thames. This will be fairly extensive and adjacent to Zones
A, G and C of the proposed Flexible Generation Plant development. The NSIP
developments would be significant to dominant in the close views experienced from
visual receptors on Access Land at Parsonage and Walton Commons, and the PRoW
east of the former Tilbury B power station site and therefore the magnitude of change
would be minor to moderate. Likewise, the change would be moderate for visual
receptors at Tilbury sewage works and the electricity substation. The magnitude of
change for the dynamic receptor group would be moderate.
2.3.36 The change would be moderate for Viewpoints 6, 8, 9 and11 for Tilbury2. and
moderate for Viewpoint 11and for the LTC as views of the NSIPs would be dominant
from these locations. However, for Viewpoints 6, 8 and 9, particularly the LTC the
change would be major.
2.3.37 The overall significance of effect would be minor to moderate rising to moderate to
major for residential groups on the eastern edge of Tilbury and users of the Access
Land at Walton and Parsonage Commons and pedestrian visual receptors from
Viewpoints 6 and 9 which is significant. The commercial and industrial visual receptors
at the sewage works and substation on the east side of Tilbury would experience a
moderate, not significant, visual effect. The effect on representative viewpoints would
be minor to moderate and not significant.
Tilbury developments
2.3.38 Both developments are for industrial related processing facilities set within the context
of existing industrial land uses. 016 is for the retention and completion of a waste wood
processing plant and 050 is a screening stage application for a proposed processing
of biofuels and other suitable waste facility, derived from feedstocks into a
manufactured clean gas product (Use Class B2). The developments will repurpose
predominantly brownfield sites with a mixture of industrial processing and energy
generation facilities, together with associated storage and access. The developments
are likely to vary from being barely perceptible to visible but not prominent in views.
From residential receptor groups on the east side of Tilbury, Access Land views will be
perceptible but set against the backdrop of a changing and industrial landscape the
magnitude of change would be negligible to no change. For commercial / industrial
visual receptors at the sewage works and sub-station and also dynamic transport route
receptors; Fort Road, Cooper Shaw Road and the railway the change would be
negligible to no change.
2.3.39 The representative Viewpoints 6, 8, 9 and 11 would all experience a change varying
from negligible to no change.
2.3.40 The significance of effect would be minor to negligible for residential groups on the
eastern edge of Tilbury and users of the Access Land at Walton and Parsonage
Commons, which is significant. The commercial and industrial visual receptors at the
sewage works and substation on the east side of Tilbury would experience a
moderate, not significant, visual effect. The effect on representative viewpoints would
be minor to moderate and not significant.
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
39
Group N3: South facing Chadwell St Mary escarpment
2.3.41 This visual receptor group is located on the south facing escarpment of the Chadwell
Escarpment Urban Fringe character area. There is potential for elevated views over
the coastal plain below vantage points. There are few publicly accessible locations
here and the representative viewpoints are from specific and generally non extensive
areas.
2.3.42 The community facility of St James’ Church graveyard together with specific locations
along PRoW Footpaths 200 and 72 are the only receptor groups that has the potential
to be adversely affected in this area. These are of high sensitivity.
2.3.43 Representative Viewpoints: 3, 4, 7 and 10 are all high sensitivity visual receptors. The
viewpoints are at varying distances from the proposed cumulative developments and
within different visual settings.
2.3.44 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
○ 058 TR010032 LTC
2.3.45 None of the receptors in this location will be significantly adversely affected by the other
cumulative development and are not considered further in this assessment. Only the
NSIPs have the potential to have significant adverse effects on the N3 visual receptor
group.
NSIPs
2.3.46 The Tilbury2 NSIP has the potential to have the following visual impacts on the N3
group of visual receptors in the form of new dockside development buildings, loading
wharf, lifting gear, road access and container storage. Tilbury2 will extend over the
former Tilbury B power station site northwards to the railway line. The LTC NSIP
development will consist of a new road, tunnel under the River Thames and road
infrastructure on the north side of the River Thames. The LTC development would be
fairly extensive and adjacent to Zones A, G and C of the proposed Flexible Generation
Plant development. The NSIPs would be prominent in specific locations in near views
diminishing to visible but not prominent in more distant views in eastern locations and
at locations restricted in extent by intervening vegetation.
2.3.47 Views from St James’ Church graveyard of the both NSIPs but particularly the LTC are
available from a small area and would be prominent and therefore the change would
be moderate. Views from footpath 200 of the NSIPs are very restricted by thick
intervening vegetation and landform, whilst from footpath 72 the views are distant, over
1.2km away and viewed from an industrial urban fringe setting. These factors limit the
magnitude of the change to moderate.
2.3.48 From the representative viewpoints the change to the view would vary from negligible
for Viewpoints 3 and 4 because of the distance to the development, the industrial urban
fringe setting and intervening landform and vegetation, to moderate for Viewpoints 7
and 10.
2.3.49 Overall, the significance of effect would be negligible for footpaths 72 and 200 apart
from a small stretch represented by Viewpoint 10 which would be moderate to major.
For Viewpoints 3 and 4 the effect would also be negligible and not significant.
However, for St James’ Church graveyard and Viewpoint 7 the effect would be
moderate to major and significant.
Group N4: Coalhouse Fort area
2.3.50 This visual receptor group is located at Coalhouse Fort and its immediate surroundings
including public open space extending to the disused radar station structure on the
foreshore and the defensive moats. This group is comprised of high sensitivity visual
receptors which include, public open space and public rights of way and tourist
attraction.
2.3.51 The representative Viewpoints 17, 30, 31 and 32 are all high sensitivity receptors.
2.3.52 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 058 TR010032 LTC
2.3.53 None of the receptors in this location will be significantly adversely affected by the other
cumulative development and are not considered further in this assessment. Only the
LTC has the potential to have significant adverse effects on the N4 visual receptor
group.
NSIPs
2.3.54 The LTC NSIP development will consist of a new road, tunnel under the River Thames
and road infrastructure on the north side of the River Thames. The LTC development
would be fairly extensive and adjacent to Zones A, G and C of the proposed Flexible
Generation Plant development. The NSIP development would be visible to barely
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
40
perceptible particularly the LTC but not prominent from any visual receptor sites.
Therefore, the magnitude of change would minor at worse.
2.3.55 Overall, the significance of effect would be minor to moderate from N4 group visual
receptors and not significant.
Group N5: North of the Chadwell St Mary to east Tilbury escarpment ridge line
2.3.56 This visual receptor group is located north of the ridge of the Chadwell St Mary to East
Tilbury escarpment, where the land gradually falls northwards across farmland
landscape. The following visual receptors are relevant and are of high sensitivity;
Residential receptors: dwellings on the west side of Tilbury and PRoW footpaths 67
and bridleways 58 and 63. Although there are other receptor groups like dynamic road
user receptors they are considered to be of medium sensitivity or less and because the
magnitude of change is reduced because of distance, intervening landform and
vegetation from the cumulative developments they are not considered further in this
assessment.
2.3.57 The representative Viewpoints 5, 33 and 34 are high sensitivity receptors and have
the potential to be adversely affected. The effects on Viewpoints 1 and 2 have been
dismissed for further assessment as they are too distant, well screened from the
cumulative developments.
• NSIPs:
○ 042 TR030003 Tilbury2
○ 058 TR010032 LTC
2.3.58 None of the receptors in this location will be significantly adversely affected by the other
cumulative development and are not considered further in this assessment. Only the
NSIPs have the potential to have significant adverse effects on the N5 visual receptor
group.
NSIPs
2.3.59 The Tilbury2 and LTC NSIPs have the potential to have the following visual impacts on
the N5 group of visual receptors in the form of new dockside development buildings,
loading wharf, lifting gear, road access and container storage. Tilbury2 will extend over
the former Tilbury B power station site northwards to the railway line. The LTC NSIP
development will consist of a new road, tunnel under the River Thames and road
infrastructure on the north side of the River Thames. The LTC development would be
fairly extensive and the approach road would extend into this area. The NSIP LTC
development would be visible but not prominent and Tilbury2 would be barely
perceptible from the PRoWs in most views in this receptor group. The change would
be minor to negligible at worse. The representative Viewpoints 1, 2, 5, 33 and 34
represent the worse-case scenarios from the PRoW in this area and the magnitude of
change is minor.
2.3.60 Overall, the significance of effect would be minor or moderate at worse for the N5
group of visual receptors at the representative Viewpoints 5, 33 and 34 and not
significant.
Group S1: River Thames south shore and waterfront
2.3.61 This visual receptor group is located on the River Thames south shore and waterfront
and have generally open views across the river to the north shore. The following visual
receptor groups include: residential visual receptors Gravesend waterfront, public
access and tourist attractions at Gravesend Gordon Recreation Ground and gardens,
New Tavern Fort, PRoW: Saxon Shore Way long distance footpath. These receptors
are all deemed to be of high sensitivity. Visual commercial receptors at Gravesend
and industrial receptors at Milton and dynamic receptors vessels using River Thames
are judged to be of medium to low sensitivity. Only the high sensitivity receptors have
the potential to be significantly adversely affected by the cumulative developments,
consequently the medium and low sensitivity visual receptors are not considered
further in this assessment.
2.3.62 The following representative viewpoints have the potential to be adversely affected,
they are Viewpoints 18, 19, 20, 21 and 23 which are on the Saxon Shore Way and
Viewpoint 19 which is on the passenger wharf for the Thames ferry and consequently,
they are all of medium to high sensitivity.
2.3.63 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
○ 058 TR010032 LTC
• Tilbury Developments:
○ 016 17/00977/FUL
○ 050 17/00349/SCR
• Gravesend Developments:
○ 064 (policy ref CS04)
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
41
NSIPs
2.3.64 The Tilbury2 and LTC NSIPs have the potential to have the following visual impacts on
the S1 group of visual receptors in the form of new dockside development buildings,
loading wharf, lifting gear, road access and container storage. Tilbury2 will extend over
the former Tilbury B power station site northwards to the railway line. The LTC NSIP
development will consist of a new road, tunnel under the River Thames and road
infrastructure on the north side of the River Thames. The NSIP developments would
be mostly visible but not prominent to barely perceptible, particularly associated with
the LTC development from viewpoints on the north side of Gravesend. Whilst the
Tilbury2 wharf development would be visible, given the existing industrial context of
the northern shore of the Thames in this location, overall the magnitude of change
would be negligible to minor, occasionally moderate, from locations the Saxon Shore
Way and public access and tourist attractions viewpoints associated with Gravesend
waterfront including the Gravesend Gordon Recreation Ground and gardens and New
Tavern Fort.
2.3.65 The magnitude of change for the Viewpoints 18, 19, 20, 21 and 23, would be moderate
because of the open exposed views of the southern sides of both NSIP developments.
2.3.66 Overall the Saxon Shore Way and Gravesend waterfront, public access and tourist
attractions visual receptors will experience moderate to minor and not significant to
moderate to major and significant effects. All the viewpoints in this receptor group will
experience a moderate to major visual effect, which is significant.
Tilbury Developments
2.3.67 Both developments are for industrial related processing facilities set within the context
of an existing industrial use landscape. 016 is for the retention and completion of a
waste wood processing plant and 050 is a screening stage application for a proposed
processing of biofuels and other suitable waste facility, derived from feedstocks into a
manufactured clean gas product (Use Class B2). The developments will repurpose
predominantly brownfield sites with a mixture of industrial processing and energy
generation facilities, together with associated storage and access. These
developments are likely to be visible but not prominent to barely perceptible in views
over the stretch of shoreline between Tilbury Fort to where the land at Tilbury Marshes
has been raised. The magnitude of change from Gravesend waterfront and the Saxon
Shore Way visual receptors would be negligible diminishing to no change to views
further east.
2.3.68 The magnitude of change would be negligible to no change for Viewpoints 18, 19,
20, 21 and 23 as views would be partially obscured by existing intervening features
such as Tilbury Fort and the Tilbury2 (NSIP) development.
2.3.69 The significance of effect would be minor to negligible and not significant for a short
section of Gravesend waterfront and Saxon Shore Way visual receptors. Whilst for
representative Viewpoints 18, 19, and 23 would also experience a minor to no effects
and therefore not significant. The operational and maintenance phases of these
developments would not have a significant effect.
Gravesend Developments
2.3.70 The Canal Basin Regeneration will have impacts on the surrounding character and
views. Receptors will have views of the new housing, school, retail and road
development. The magnitude of impact will vary between negligible and minor.
2.3.71 The significance of effect of the proposed development on the high sensitivity visual
receptors would be minor to moderate, depending on the location of the receptor and
the intervening buildings, which are not significant.
Group S2: Elevated locations at Gravesend
2.3.72 This visual receptor group is located at elevated locations within and on the fringes of
Gravesend. These include residential and public access receptors in Gravesend,
particularly Windmill Gardens and Windmill Hill, and the PRoW footpath east of
Gravesend and south of Chalk which rises through farmland to the south east. These
receptors are all deemed to be of high sensitivity.
2.3.73 The following representative viewpoints have the potential to be adversely affected;
Viewpoint 22 at Windmill Gardens, Gravesend and Viewpoint 28, aPRoW crossing
arable farmland, to the south of Chalk, which have elevated views from Gravesend and
across Chalk respectively. These receptors are of high sensitivity.
2.3.74 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
○ 058 TR010032 LTC
• Tilbury Developments:
○ 016 17/00977/FUL
○ 050 17/00349/SCR
• Gravesend Developments:
○ 064 (policy ref CS04)
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
42
NSIPs
2.3.75 The Tilbury2 and LTC NSIPs have the potential to have the following visual impacts on
the S2 group of visual receptors in the form of new dockside development buildings,
loading wharf, lifting gear, road access and container storage. Tilbury2 will extend over
the former Tilbury B power station site, northwards to the railway line. The LTC NSIP
development will consist of a new road, tunnel under the River Thames and road
infrastructure on the north side of the River Thames. More of the NSIP developments
would be visible than for receptor group S1, due to the raised locations of the S2
receptor group views but also the views of the rest of the landscape on the north side
of the Thames would be more extensive. The developments would vary from prominent
to visible but not prominent from the elevated residential and public access visual
receptors and the change would be minor to moderate depending on the elevation
and the amount of intervening development and vegetation.
2.3.76 The magnitude of change for the Viewpoints 22 and 28, will be moderate because of
the open exposed views from these locations of both NSIP construction phases. The
Tilbury2 construction phase is likely to affect Viewpoint 22 the most whilst the LTC will
affect Viewpoint 28 more.
2.3.77 Overall the residential and public access visual receptors of Windmill Gardens and
Windmill Hill, and the PRoW footpath east of Gravesend and south of Chalk will
experience minor to moderate and not significant to moderate to major and
significant effects. Both viewpoints in this receptor group will experience a moderate
to major visual effect, which is significant.
Tilbury Developments
2.3.78 Both cumulative developments are for industrial related processing facilities set within
the context of existing industrial use landscape. Development 016 is for the retention
and completion of a waste wood processing plant and 050 is a screening stage
application for a proposed processing of biofuels and other suitable waste facility,
derived from feedstocks into a manufactured clean gas product (Use Class B2). The
developments will repurpose predominantly brownfield sites with a mixture of industrial
processing and energy generation facilities, together with associated storage and
access. The developments are likely to be visible but not prominent to barely
perceptible in elevated views from Gravesend across the Thames. The magnitude of
change from Gravesend visual receptors would be minor for lower views and those
where the views are interrupted by intervening development and / or vegetation.
2.3.79 The magnitude of change would be minor for Viewpoints 22 and 28 as views would be
partially obscured by existing intervening features such as Tilbury Fort and the Tilbury2
(NSIP) development.
2.3.80 The significance of effect would be minor to moderate and not significant at worse for
visual receptors. Whilst for representative Viewpoints 22 and 28 would also experience
a minor to moderate effect and therefore not significant. The construction phases of
these developments are not a significant effect.
Gravesend Developments
2.3.81 Development 064 is for a residential redevelopment of a former waterside industrial
use area in east Gravesend known as Gordon Promenade East. The development is
likely to be medium rise at worse and in character with the surrounding townscape. The
development is likely to be visible but not prominent to barely perceptible in elevated
views from Gravesend across the Thames. The magnitude of change from Gravesend
visual receptors would be generally negligible to minor.
2.3.82 The magnitude of change would be negligible for Viewpoints 22 and 28. Views would
be obscured and filtered by existing intervening existing buildings.
2.3.83 The significance of effect would be minor and not significant for at worse for visual
receptors. Whilst for representative Viewpoints 22 and 28 would also experience a
minor effect and therefore not significant. This development would not have a
significant effect.
Group S3: Northern edge Kent Downs AONB
2.3.84 This visual receptor group is located on the northern edge and north facing slopes of
the national AONB landscape designation of the Kent Downs. These are dynamic road
visual receptors, which have intermittent infrequent views from the minor road running
through Brummelhill Wood. These visual receptors are deemed to be of medium
sensitivity.
2.3.85 Representative Viewpoint 29 is on the minor road which runs parallel with the northern
boundary of the Kent Downs AONB with elevated views over the River Thames coastal
plain landscape. This receptor is judged to be of very high sensitivity.
2.3.86 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
○ 058 TR010032 LTC
2.3.87 None of the receptors in this location will be significantly adversely affected by the other
cumulative development and are not considered further in this assessment. Only the
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
43
NSIPs have the potential to have significant adverse effects on the S3 visual receptor
group.
2.3.88 The Tilbury2 and LTC NSIPs have the potential to have the following visual impacts on
the S3 group of visual receptors in the form of new dockside development buildings,
loading wharf, lifting gear, road access and container storage. Tilbury2 will extend over
the former Tilbury B power station site, northwards to the railway line. The LTC NSIP
development will consist of a new road, tunnel under the River Thames and road
infrastructure on the north side of the River Thames. The views of the NSIP
developments would vary from barely perceptible for most receptor views from this
rural road therefore the change would be negligible to minor depending on the
amount of intervening roadside vegetation.
2.3.89 The magnitude of change would be minor for Viewpoint 29 as views would be long
distance and the change set in the context of a predominantly dynamic industrial
landscape.
2.3.90 The significance of effect would be minor to moderate and not significant at worse for
the rural road visual receptors. Similarly, for representative Viewpoint 29 there would
be a minor to moderate effect and therefore not significant. These developments
would not have a significant impact.
Group S4: South side Thames coastal plain
2.3.91 This visual receptor group is located on the south side of the Thames on marshes and
reclaimed marshland and includes the following visual receptor groups greater than
2.5km from the proposed Flexible Generation Plant: Tourist attractions including Cliffe
Pools RSPB, Cliffe Fort and Shornmead Fort, PRoW Saxon Shore Way and across
Shorne and Higham marshes. These are all judged to be high sensitivity visual
receptors.
2.3.92 Representative Viewpoints: 24, 25, 26 and 27 are all high sensitivity visual receptors
on the River Thames southern shoreline. The viewpoints are at varying distances from
the proposed cumulative developments and within similar estuary side settings with a
predominantly low lying and flat marsh or drained marshland farmland hinterland.
2.3.93 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
○ 058 TR010032 LTC
2.3.94 None of the receptors in this location will be significantly adversely affected by the other
cumulative development and are not considered further in this assessment. Only the
NSIPs have the potential to have significant adverse effects on the S4 visual receptor
group.
2.3.95 The Tilbury2 and LTC NSIPs have the potential to have the following visual impacts on
the S4 group of visual receptors in the form of new dockside development buildings,
loading wharf, lifting gear, road access and container storage. Tilbury2 will extend over
the former Tilbury B power station site, northwards to the railway line. The LTC NSIP
development will consist of a new road, tunnel under the River Thames and road
infrastructure on the north side of the River Thames. The views of the NSIP, particularly
the LTC development would vary from barely perceptible to small for the closer visual
receptors such as at Shornmead Fort and the Saxon Shore Way to the north of Shorne
marshes. Therefore, the change is judged to be minor.
2.3.96 The magnitude of change for the Viewpoints 24, 25, 26 and 27, will be minor to
negligible because of the increasing distance from the cumulative developments –
particularly the LTC from west to east. The views are open and exposed over the River
Thames. The magnitude of change would vary between minor Viewpoint 24 and 25
and negligible for Viewpoints 26 and 27.
2.3.97 Overall the significance of effect would be no greater than minor to moderate for the
western most receptor groups at Shornmead Fort, and Saxon Shore Way and for
Viewpoints 24 and 25, which is not significant.
Further mitigation or enhancement
2.3.98 As part of the proposals there will be landscape planting, thickening of the boundary
planting between the exchange common land (Zone E) and the railway line. Hedge
planting along the access track off Cooper Shaw Road is also proposed. Ecological
mitigation in the form of habitat creation, some of which will be tree and shrub planting
in Zone F which will help to soften views of the operational phases of the Flexible
Generation Plant and LTC particularly for visual receptors in N2 and N3 particularly
high sensitivity visual receptors using the Access Land at Parsonage Common and the
new Exchange Common land and also residential receptors on the west side of Tilbury.
Medium sensitivity visual receptors using Fort Road and Cooper Shaw Road will also
benefit from these landscape and ecology proposals.
Residual effects
2.3.99 In time as the planting matures the significance of effect will be reduced for the visual
receptors mentioned above. In some locations such as receptors in the open access
common land the effect would be reduced below significant levels
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
44
2.4 Decommissioning phase of Thurrock Flexible Generation
Plant
2.4.1 The LTC NSIP is unlikely to be decommissioned and therefore is not considered in this
part of the assessment.
Thurrock Landscape Character Areas
LCA C5: Tilbury Marshes
2.4.2 LCA C5: Tilbury Marshes, will be directly affected by the decommissioning phase of
the cumulative developments. It is a large-scale landscape with extensive open and
exposed land dominated by the sky. The sensitivity of the LCA to the proposed
operation and maintenance works is considered to be medium.
2.4.3 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
• Tilbury Developments:
○ 016 17/00977/FUL
○ 018 11/50361/TTGETL
○ 050 17/00349/SCR
○ 079 19/01274/FUL
○ 081 12.04.09.04/266C
NSIPs
2.4.4 The decommissioning and demolition of Tilbury2 NSIP would have the potential to have
the following landscape impacts on the Tilbury Marshes LCA in the form of demolition
and removal of dockside development buildings, loading wharf, lifting gear, road
access and container storage. The LTC NSIP is unlikely to be decommissioned and is
not considered in this part of the assessment. The Tilbury Marshes LCA, will be directly
affected by the Tilbury2.
2.4.5 This landscape character area has historically been subject to large scale industrial
and dock development as Tilbury has expanded. The magnitude of impact of the NSIP
in this area is also considered to be moderate.
2.4.6 The effect experienced by the LCA will be moderate adverse, which is not significant.
Tilbury Developments
2.4.7 The Tilbury developments identified as having the potential for cumulative effects in
combination with the proposed Thurrock Flexible Generation Plant are located to the
west of Zone A and associated within or on the edge of the built up area of Tilbury on
brownfield and disused sites and on the western side of the LCA. The decommssioning
of these developments will involve the demolition and removal of a mixture of industrial
processing and energy generation facilities, together with associated storage and
access.
2.4.8 This part of the landscape character area has historically been subject to dynamic
change to large scale industrial and dock development as Tilbury has expanded. The
magnitude of Impact of the decommissioning works of these cumulative developments
in this area is considered to be minor to negligible.
2.4.9 The effect experienced the LCA will be negligible to minor which is not significant.
LCA D6: Chadwell Escarpment Urban Fringe
2.4.10 The sensitivity of the LCA to the proposed cumulative developments is considered to
be medium. The fairly unspoilt rural character in the east of the character area is the
most sensitive part of this LCA to change from developments.
2.4.11 The following projects will have the potential for cumulative effects in combination with
the proposed development. The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
• Chadwell St Mary Developments:
○ 014 16/00412/OUT
○ 034 15/00379/OUT
NSIPs
2.4.12 The decommissioning and demolition of Tilbury2 would have the potential to have the
following landscape impacts on the character area in the form of demolition and
removal of dockside development buildings, loading wharf, lifting gear, road access
and container storage. The potential effects of Tilbury2 would be indirect.
2.4.13 The magnitude of impact of decommissioning Tilbury2 is considered to be minor. The
overall significance of effect experienced by the LCA will be minor adverse, which is
not significant.
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
45
Chadwell St Mary Developments
2.4.14 The two cumulative developments are both potential housing developments for 203
and 43 dwellings respectively at Chadwell St Mary. They have the potential to cause
direct and indirect effects on the western part of the character. They are both located
on the south eastern edge of Chadwell St Mary. The direct effects on the landscape
would be demolition and removal of housing.
2.4.15 The magnitude of impact of decommissioning the development in this character area
is considered to be negligible to minor. The overall significance of effect experienced
by the LCA will be negligible to minor adverse, which is not significant.
LCA D7: West Tilbury Urban Fringe
2.4.16 This character area is a fairly open landscape with limited tree cover, visual intrusion
of existing developments including pylons and industrial use areas gives the landscape
an urban fringe character. The sensitivity of this LCA to the proposed construction
works in these zones is medium.
2.4.17 The following projects will have the potential for cumulative effects in combination with
the proposed development. The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
• East Tilbury Developments:
○ 005 18/00664/CONDC
○ 011 16/01475/SCR
○ 012 16/01232/OUT
NSIPs
2.4.18 The decommissioning and demolition of Tilbury2 would have the potential to have the
following landscape impacts on the character area in the form of demolition and
removal of dockside development buildings, loading wharf, lifting gear, road access
and container storage. The potential effects of Tilbury2 would be indirect.
2.4.19 Tilbury2 is in the main, visually separated from this character area.
2.4.20 The magnitude of impact of decommissioning Tilbury2 is considered to be minor. The
overall significance of effect experienced by the LCA will be minor adverse, which is
not significant.
East Tilbury Developments
2.4.21 The three cumulative developments are potential housing developments for 200 (Ref
011) and 1000 (Ref 012) dwellings west of East Tilbury. Development 005 is for 50
dwellings and is located on south side of East Tilbury on the character area boundary.
The decommissioning of developments 011 and 012 have a greater potential than 005
to cause direct impacts on the character area. The direct effects on the landscape
would be demolition and removal of housing.
2.4.22 The magnitude of impact of the decommissioning works in this character area is
considered to be minor. The landscape here has an urban fringe character. The overall
significance of effect experienced by the LCA will be minor adverse, which is not
significant.
Visual Receptors
Group N1: North Thames shore waterfront
2.4.23 This visual receptor group is located close to where Zone G meets the shoreline on the
north side of the River Thames.
2.4.24 Public Access: Thames Estuary Path / Two Forts Way (Footpath146); Tourist
Attractions: visitor receptors to Tilbury Fort are both high sensitivity visual receptors
(Medium for users of Footpath 146, adjacent to the sewage works, Viewpoint 12).
2.4.25 Representative Viewpoints: 13, 14 ,15 and 16 are all high sensitivity visual receptors
on PRoW FP146. The viewpoints are at varying distances from the proposed
cumulative developments and within different visual settings. Viewpoints 13 and 14
and close to Tilbury Fort whilst 15 and 16 are to the south east and east of Zones A
and G.
2.4.26 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
• Tilbury Developments:
○ 016 17/00977/FUL
○ 050 17/00349/SCR
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
46
NSIPs
2.4.27 The decommissioning and demolition of Tilbury2 would have the potential to have the
following visual impacts on the Group N1 in the form of demolition and removal of
dockside development buildings, loading wharf, lifting gear, road access and container
storage. The decommissioning of the NSIP development would be significant to
dominant in the close views from the Thames Estuary Path east of Tilbury Fort for a
stretch approximately 1km long where the Tilbury 2 development adjoins the shoreline.
The magnitude of change would be moderate for this stretch diminishing to minor
further east. Likewise, the magnitude of change would be minor within and from Tilbury
Fort.
2.4.28 The change would be minor to moderate for Viewpoints 12, 13 and 14 as views would
be partially obscured of the cumulative NSIP development, by Tilbury Fort. The impact
of change for Viewpoints 15 and 16 particularly the decommissioning the new wharf at
Tilbury2 would also be minor to moderate.
2.4.29 Overall, the significance of effect would be moderate to major and significant for a
short, approximately 1km section of the Thames Estuary path where the
decommissioning operation of the developments meet the shoreline and minor to
moderate from Tilbury Fort. Whilst for representative Viewpoints 15 and 16 the impact
would be moderate to major and significant. Whereas Viewpoints 13 and 14 would
experience a minor to moderate effect and not significant. Overall the
decommissioning phase of Tilbury2 is significant for a few specific receptors.
Tilbury developments
2.4.30 Both developments are for industrial related processing facilities set within the context
of existing industrial use landscape. Development 016 is for the retention and
completion of a waste wood processing plant and 050 is a screening stage application
for a proposed processing of biofuels and other suitable waste facility, derived from
feedstocks into a manufactured clean gas product (Use Class B2). The
decommissioning of these developments will involve the demolition and removal of a
mixture of industrial processing and energy generation facilities, together with
associated storage and access. The magnitude of change would be negligible further
east. The impact would be no change to negligible within and from Tilbury Fort.
2.4.31 The change would be no change to negligible for Viewpoints 12, 13 and 14 as views
would be partially obscured of the cumulative NSIP developments, by Tilbury Fort. For
Viewpoints 15 and 16 the effect of the decommissioning developments would also be
no change to negligible.
2.4.32 Overall, the significance of effect would be minor and not significant for a short
approximately 1km long section of the Thames Estuary path directly south of these
developments where the Tilbury 2 development adjoins the shoreline. It would be
minor from Tilbury Fort. Whilst for representative Viewpoints 15 and 16 the impact
would be minor to negligible and not significant. Whereas, Viewpoints 13 and 14
would experience a minor effect and not significant. Therefore, the decommissioning
phase of these developments are not a significant impact.
Group N2: North side Thames coastal plain
2.4.33 This visual receptor group is located on the north shore of the River Thames and within
the coastal plain which is similar in extent to the Tilbury Marshes landscape character
area but also includes the built-up area of Tilbury. Coalhouse Fort is dealt with as a
separate visual receptor.
2.4.34 The following visual receptors are relevant; Residential receptors: Dwellings on the
east and south east side of Tilbury. Access Land: Parsonage and Walton Commons.
PRoW: footpaths south of Buckland and south of Zone A are all high sensitivity
receptors.
2.4.35 Visual commercial and industrial facility receptors at the Tilbury substation and sewage
works and dynamic road receptors along Fort Road and Cooper Shaw Road together
with rail passengers on the rail line which runs from Tilbury north eastwards across this
area are medium sensitivity visual receptors.
2.4.36 Representative Viewpoints: 6, 8, 9 and 11 are all low sensitivity visual road user
receptors and Viewpoints 6 and 9 are also high sensitivity pedestrian visual receptors.
Although from fieldwork it appears that there are very few pedestrians using the areas
where Viewpoints 6 and 9 are located The viewpoints are at varying distances from the
proposed cumulative developments and within different visual settings. Viewpoint 8 is
close to the LTC whilst 9 and 11 are close to Tilbury2. Viewpoint 6 is a similar distance
to both cumulative NSIPs.
2.4.37 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the
planningapplication reference:
• NSIPs:
○ 042 TR030003 Tilbury2
• Tilbury Developments:
○ 016 17/00977/FUL
○ 050 17/00349/SCR
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
47
NSIPs
2.4.38 The decommissioning and demolition of Tilbury2 would have the potential to have the
following visual impacts on the Group N2 in the form of demolition and removal of
dockside development buildings, loading wharf, lifting gear, road access and container
storage. The decommissioning of the NSIP development would be significant to
dominant in the close views experienced from visual receptors on Access Land at
Parsonage and Walton Commons, and the PRoW east of the former Tilbury B power
station site and therefore the magnitude of change would be minor to moderate.
Likewise, the change would be moderate for visual receptors at Tilbury sewage works
and the electricity substation. The magnitude of change for the dynamic receptor group
would be moderate depending on proximity and level of intervening screening.
2.4.39 The change would be moderate to major for Viewpoints 6, 8, 9 & 11 for Tilbury2 as
views of the NSIP decommissioning would be dominant from these locations.
2.4.40 The significance of effect would be minor to moderate rising to moderate to major
for residential groups on the eastern edge of Tilbury, pedestrian visual receptors from
Viewpoints 6 and 9 and users of the Access Land at Walton and Parsonage Commons,
which is significant. The commercial and industrial visual receptors at the sewage
works and substation on the east side of Tilbury would experience a moderate, not
significant, visual effect. The effect on representative viewpoints would be minor to
moderate and not significant.
Tilbury developments
2.4.41 Both developments are for industrial related processing facilities set within the context
of existing industrial use landscape. Development 016 is for the retention and
completion of a waste wood processing plant and 050 is a screening stage application
for a proposed processing of biofuels and other suitable waste facility, derived from
feedstocks into a manufactured clean gas product (Use Class B2). The
decommissioning of these developments will involve the demolition and removal of a
mixture of industrial processing and energy generation facilities, together with
associated storage and access. The demolition and removal phases are likely to vary
from being barely perceptible to visible but not prominent in views. From residential
receptor groups on the east side of Tilbury, Access Land views will be perceptible but
set against the backdrop of a changing and industrial landscape the magnitude of
change will be no change to negligible. For commercial / industrial visual receptors
at the sewage works and sub-station and also dynamic transport route receptors; Fort
Road, Cooper Shaw Road and the railway the change will be negligible to no change.
2.4.42 The representative Viewpoints 6, 8, 9 and 11 would all experience a change varying
from negligible to no change.
2.4.43 The significance of effect would be minor to negligible for residential groups on the
eastern edge of Tilbury, pedestrian visual receptors from Viewpoints 6 and 9 and users
of the Access Land at Walton and Parsonage Commons, which is not significant. The
commercial and industrial visual receptors at the sewage works and substation on the
east side of Tilbury would experience a moderate significance of effect, and not
significant. The effect on representative viewpoints would be minor to moderate and
not significant.
Group N3: South facing Chadwell St Mary escarpment
2.4.44 This visual receptor group is located on the south facing escarpment of the Chadwell
Escarpment Urban Fringe character area. There is potential for elevated views over
the coastal plain below vantage points. There are few publicly accessible locations
here and the representative viewpoints are from specific and generally non extensive
areas.
2.4.45 The community facility of St James’ Church graveyard together with specific locations
along PRoW Footpaths 200 and 72 are the only receptor groups that has the potential
to be adversely affected in this area. These are of high sensitivity.
2.4.46 Representative Viewpoints: 3, 4, 7 and 10 are all high sensitivity visual receptors. The
Viewpoints are at varying distances from the proposed cumulative developments and
within different visual settings.
2.4.47 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
2.4.48 None of the receptors in this location will be significantly adversely affected by the
decommissioning of the other cumulative developments and are not considered further
in this assessment. Only the NSIP has the potential to have significant adverse effects
on the N3 visual receptor group.
NSIPs
2.4.49 The decommissioning and demolition of Tilbury2 would have the potential to have the
following visual impacts on the Group N3 in the form of demolition and removal of
dockside development buildings, loading wharf, lifting gear, road access and container
storage. The decommissioning of the NSIP would be prominent in specific locations in
near views diminishing to visible but not prominent in more distant views in eastern
locations and at locations restricted in extent by intervening vegetation.
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
48
2.4.50 Views from St James’ Church graveyard of the NSIP are available from a small area
and would be prominent and therefore the change would be moderate. Views from
footpath 200 of the NSIPs are very restricted by thick intervening vegetation and
landform, whilst from footpath 72 the views are distant, over 1.2km away and viewed
from an industrial urban fringe setting. These factors limit the magnitude of the change
to minor.
2.4.51 From the representative viewpoints the change to the view would vary from minor for
Viewpoints 3 and 4 because of the distance to the demolition and removal of the
development, the industrial urban fringe setting and intervening landform and
vegetation. However, the change would be negligible to moderate for Viewpoints 7
and 10.
2.4.52 The significance of effect would be negligible for footpaths 72 and 200 apart from a
small stretch represented by Viewpoint 10 which would be moderate. For viewpoints
3 and 4 the effect would also be negligible and not significant. However, for St James’
Church graveyard and Viewpoint 7 the effect would be moderate and not significant.
Group N4: Coalhouse Fort area
2.4.53 This visual receptor group is located at Coalhouse Fort and its immediate surroundings
including public open space extending to the disused radar station structure on the
foreshore and the defensive moats. This group is comprised of high sensitivity visual
receptors which include, public open space and public rights of way and tourist
attraction.
2.4.54 The representative Viewpoints 17, 30, 31 and 32 are all high sensitivity receptors.
2.4.55 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the planning
application reference:
• NSIPs:
o 042 TR030003 Tilbury2
2.4.56 The visual receptors at and around Coalhouse Fort will have views of the taller plant
involved in the decommissioning of Tilbury2. The temporary magnitude of impact will
be minor at most. This will have a moderate significance of effect, which is not
significant.
2.4.57 None of the receptors in this location will be significantly adversely affected by the
decommissioning of the other cumulative developments.
Group N5: North of the Chadwell St Mary to east Tilbury escarpment ridge line
2.4.58 This visual receptor group is located north of the ridge of the Chadwell St Mary to East
Tilbury escarpment, where the land gradually falls northwards across farmland
landscape. The following visual receptors are relevant and are of high sensitivity;
Residential receptors: dwellings on the west side of Tilbury and PRoW footpaths 67
and bridleways 58 and 63. Although there are other receptor groups like dynamic road
user receptors they are considered to be of medium sensitivity or less and because the
magnitude of change is reduced because of distance, intervening landform and
vegetation from the cumulative developments they are not considered further in this
assessment.
2.4.59 The representative Viewpoints 5, 33 and 34 are high sensitivity receptors and have
the potential to be adversely affected. The effects on Viewpoints 1 and 2 have been
dismissed for further assessment as they are too distant, well screened from the
cumulative developments.
2.4.60 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
2.4.61 None of the receptors in this location will be significantly adversely affected by the
decommissioning of the other cumulative developments and are not considered further
in this assessment. Only the NSIP has the potential to have significant adverse effects
on the N5 visual receptor group.
NSIPs
2.4.62 The decommissioning and demolition of Tilbury2 would have the potential to have the
following landscape impacts on Group N5 in the form of demolition and removal of
dockside development buildings, loading wharf, lifting gear, road access and container
storage. Tilbury2 decommissioning would be barely perceptible from the PRoWs in
most views in this receptor group. The change would be minor to negligible at worse.
The representative Viewpoints 5, 33 and 34 represent the worse-case scenarios from
the PRoW in this area and the magnitude of change is minor.
2.4.63 Overall, the significance of effect would be minor to moderate at worse for the N5
group of visual receptors at the representative Viewpoints 5, 33 and 34 and not
significant.
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
49
Group S1: River Thames south shore and waterfront
2.4.64 This visual receptor group is located on the River Thames south shore and waterfront
and have generally open views across the river to the north shore. The following visual
receptor groups include: residential visual receptors Gravesend waterfront, public
access and tourist attractions at Gravesend Gordon Recreation Ground and gardens,
New Tavern Fort, PRoW: Saxon Shore Way. These receptors are all deemed to be of
high sensitivity. Visual commercial receptors at Gravesend and industrial receptors at
Milton and dynamic receptors vessels using River Thames are judged to be of medium
to low sensitivity. Only the high sensitivity receptors have the potential to be
significantly adversely affected by the cumulative developments, consequently the
medium and low sensitivity visual receptors are not considered further in this
assessment.
2.4.65 The following representative viewpoints have the potential to be adversely affected,
they are Viewpoints 18, 19, 20, 21 and 23 which are on the Saxon Shore Way and
Viewpoint 19 which is on the passenger wharf for the Thames ferry and consequently,
they are all of high sensitivity.
2.4.66 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
• Tilbury Developments:
○ 016 17/00977/FUL
○ 050 17/00349/SCR
• Gravesend Developments:
○ 064 (policy ref CS04)
NSIPs
2.4.67 The decommissioning and demolition of Tilbury2 NSIP would have the potential to have
the following visual impacts on Group S1 in the form of demolition and removal of
dockside development buildings, loading wharf, lifting gear, road access and container
storage. The decommissioning of the Tilbury2 wharf would be visible, given the existing
dynamic industrial context of the northern shore of the Thames in this location, overall
the magnitude of change would be minor tomoderate from locations the Saxon Shore
Way and public access and tourist attractions viewpoints associated with Gravesend
waterfront including the Gravesend Gordon Recreation Ground and gardens and New
Tavern Fort.
2.4.68 The magnitude of change for the Viewpoints 18, 19, 20, 21 and 23, will be moderate
because of the open exposed views of the southern sides of the NSIP development.
2.4.69 Overall the Saxon Shore Way and Gravesend waterfront, public access and tourist
attractions visual receptors will experience moderate to minor significance of effect
and not significant to moderate to major effects which are significant. All the
viewpoints in this receptor group will experience a moderate to major visual effect,
which is significant.
Tilbury Developments
2.4.70 Both developments are for industrial related processing facilities set within the context
of existing industrial use landscape. Development 016 is for the retention and
completion of a waste wood processing plant and 050 is a screening stage application
for a proposed processing of biofuels and other suitable waste facility, derived from
feedstocks into a manufactured clean gas product (Use Class B2). The
decommissioning of these developments will involve the demolition and removal of a
mixture of industrial processing and energy generation facilities, together with
associated storage and access. The decommissioning of these developments are
likely to be visible but not prominent to barely perceptible in views over the stretch of
shoreline between Tilbury Fort to where the land at Tilbury Marshes has been raised.
The magnitude of change from Gravesend waterfront and the Saxon Shore Way visual
receptors would be negligible to minor.
2.4.71 The magnitude of change would be negligible to minor for Viewpoints, 20 and 21 as
views would be partially obscured by existing intervening features such as Tilbury Fort
and the Tilbury2 (NSIP) development.
2.4.72 The significance of effect would be minor to moderate and not significant for a short
section of Gravesend waterfront and Saxon Shore Way visual receptors. Whilst for
representative Viewpoints 18, 19, 20, 21 and 23 would also experience a minor to no
effects and therefore not significant. The decommissioning phases of these
developments would not have a significant impact.
Gravesend Development
2.4.73 This development is for a residential redevelopment of a former waterside industrial
use area in east Gravesend known as Gordon Promenade East. The demolition and
removal is likely to be visible but not prominent to barely perceptible in elevated views
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
50
from Gravesend across the Thames. The magnitude of change from Gravesend visual
receptors would be generally, negligible to minor.
2.4.74 The temporary significance of effect would be minor to moderate and not significant
for visual receptors.
2.4.75
Group S2: Elevated locations at Gravesend
2.4.76 This visual receptor group is located at elevated locations within and on the fringes of
Gravesend. These include residential and public access receptors in Gravesend,
particularly Windmill Gardens and Windmill Hill, and the PRoW footpath east of
Gravesend and south of Chalk which rises through farmland to the south east. These
receptors are all deemed to be of high sensitivity.
2.4.77 The following representative viewpoints have the potential to be adversely affected;
Viewpoints 22 at Windmill Gardens, Gravesend and Viewpoint 28 on a PRoW crossing
an arable field footpath to the south of Chalk, which have elevated views form
Gravesend and across Chalk respectively. These receptors are of high sensitivity.
2.4.78 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
• Tilbury Developments:
○ 016 17/00977/FUL
○ 050 17/00349/SCR
• Gravesend Developments:
○ 064 (policy ref CS04)
NSIPs
2.4.79 The decommissioning and demolition of Tilbury2 would have the potential to have the
following visual impacts on Group S2 in the form of demolition and removal of dockside
development buildings, loading wharf, lifting gear, road access and container storage.
More of the NSIP decommissioning would be visible than for receptor group S1, due
to the raised locations of the S2 receptor group views but also the views of the rest of
the landscape on the north side of the Thames would be more extensive. The
decommissioning of this development would vary from prominent to visible but not
prominent from the elevated residential and public access visual receptors and the
change would be minor to moderate depending on the elevation and the amount of
intervening development and vegetation.
2.4.80 The magnitude of change for the Viewpoint 22, will be moderate because of the
elevated views from of the Tilbury 2 NSIP decommissioning phase. Viewpoint 28 is
sufficiently far from the Tilbury 2 to have a negligible magnitude of change and not
considered further.
2.4.81 Overall the residential and public access visual receptors of Windmill Gardens and
Windmill Hill will experience a temporary minor to moderate effect, which are not
significant.
Tilbury Developments
2.4.82 Both developments are for industrial related processing facilities set within the context
of existing industrial use landscape. Development 016 is for the retention and
completion of a waste wood processing plant and 050 is a screening stage application
for a proposed processing of biofuels and other suitable waste facility, derived from
feedstocks into a manufactured clean gas product (Use Class B2). The
decommissioning of these developments will involve the demolition and removal of a
mixture of industrial processing and energy generation facilities, together with
associated storage and access. The decommissioning of these developments is likely
to be visible but not prominent to barely perceptible in elevated views from Gravesend
across the Thames. The magnitude of change from Gravesend visual receptors would
be negligible due to distance and intervening development and / or vegetation.
2.4.83 The magnitude of change would be minor for Viewpoints 22 and 28 as views would be
partially obscured by existing intervening features such as Tilbury Fort.
2.4.84 Overall, the significance of effect would be minor to moderate and not significant at
worse for visual receptors. Whilst representative Viewpoint 22 would also experience
a minor to moderate effect and therefore not significant. The decommissioning phases
of these developments do not have a significant effect.
Gravesend Development
2.4.85 This development is for a residential redevelopment of a former waterside industrial
use area in east Gravesend known as Gordon Promenade East. The demolition and
removal is likely to be visible but not prominent to barely perceptible in elevated views
from Gravesend across the Thames. The magnitude of change from Gravesend visual
receptors would be generally, negligible to minor.
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
51
2.4.86 The magnitude of change would be negligible for Viewpoints 22 and 28. Views would
be obscured and filtered by existing intervening existing buildings.
2.4.87 The significance of effect would be minor and not significant for at worse for visual
receptors. Whilst for representative Viewpoints 22 and 28 would also experience a
minor effect and therefore not significant. The decommissioning phases of this
development would not have a significant effect.
Group S3: Northern edge Kent Downs AONB
2.4.88 This visual receptor group is located on the northern edge and north facing slopes of
the national AONB landscape designation of the Kent Downs. These are dynamic road
visual receptors, which have intermittent infrequent views from the minor road running
through Brummelhill Wood. These visual receptors are deemed to be of medium
sensitivity.
2.4.89 Representative Viewpoint 29 is on the minor road which runs parallel with the northern
boundary of the Kent Downs AONB with elevated views over the River Thames coastal
plain landscape. This receptor is judged to be of high sensitivity.
2.4.90 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
2.4.91 None of the receptors in this location will be significantly adversely affected by the
decommissioning of the other cumulative developments and are not considered further
in this assessment. Only the Tilbury2 NSIP has the potential to have significant adverse
effects on the S3 visual receptor group.
NSIPs
2.4.92 The decommissioning and demolition of Tilbury2 would have the potential to have the
following visual impacts on Group S3 in the form of demolition and removal of dockside
development buildings, loading wharf, lifting gear, road access and container storage.
The views of the NSIP decommissioning would vary from barely perceptible for most
receptor views from this rural road therefore the change would be negligible to minor
depending on the amount of intervening roadside vegetation.
2.4.93 The magnitude of change would be minor for Viewpoint 29 as views would be long
distance and the change set in the context of a predominantly dynamic industrial
landscape.
2.4.94 Overall, the significance of effect would be minor to moderate and not significant at
worse for the rural road visual receptors. Similarly, for representative Viewpoint 29
there would be a minor to moderate effect and therefore not significant. The
decommissioning phase would not have a significant impact.
Group S4: South side Thames coastal plain
2.4.95 This visual receptor group is located on the south side of the Thames on marshes and
reclaimed marshland and includes the following visual receptor groups greater than
2.5km from the proposed Flexible Generation Plant: Tourist attractions including Cliffe
Pools RSPB, Cliffe Fort and Shornmead Fort, PRoW Saxon Shore Way and across
Shorne and Higham marshes. These are all judged to be high sensitivity visual
receptors.
2.4.96 Representative Viewpoints: 24, 25, 26 and 27 are all high sensitivity visual receptors
on the River Thames southern shoreline. The viewpoints are at varying distances from
the proposed cumulative developments and within similar estuary side settings with a
predominantly low lying and flat marsh or drained marshland farmland hinterland.
2.4.97 The following projects will have the potential for cumulative effects in combination with
the proposed development The RPS identification code is followed by the planning
application reference:
• NSIPs:
○ 042 TR030003 Tilbury2
2.4.98 None of the receptors in this location will be significantly adversely affected by the
decommissioning of the other cumulative developments and are not considered further
in this assessment. Only the Tilbury2 NSIP has the potential to have significant adverse
effects on the S4 visual receptor group.
NSIPs
2.4.99 The decommissioning and demolition of Tilbury2 would have the potential to have the
following visual impacts on the Group S4 in the form of demolition and removal of
dockside development buildings, loading wharf, lifting gear, road access and container
storage. The views of the decommissioning of the NSIP, would vary from barely
perceptible to visible but not prominent for the closer visual receptors such as at
Shornmead Fort and the Saxon Shore Way to the north of Shorne marshes. Therefore,
the change is judged to be minor.
2.4.100 The magnitude of change for the Viewpoints 24, 25, 26 and 27, will be minor to
negligible because of the increasing distance from the cumulative development –. The
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
52
views are open and exposed over the River Thames. The magnitude of change would
be minor.
2.4.101 Overall the significance of effect would be no greater than minor for the western most
receptor groups at Shornmead Fort, and Saxon Shore Way and for Viewpoints 24 and
25, which is not significant.
2.5 Summary of potential effects from cumulative
developments
2.5.1 The landscape receptor that is predicted to experience significant cumulative effects is
the host landscape character area, Tilbury Marshes LCA: C5. The large scale NSIP
projects are likely to contribute most to the potential source of effects in combination
with the Flexible Generation Plant. However, this character area has had a history of
large scale industrial uses which impart an urban / industrial fringe character on the
this LCA. This is particularly the case in the western parts of the character area where
the proposed NSIPs are located and less so further east towards Coalhouse Fort which
has more rural qualities. Therefore, although overall the character area is judged to be
of medium sensitivity to these forms of development, the western side is judged less
sensitive than the eastern side.
2.5.2 The visual receptors that are predicted to experience significant cumulative effects are
confined to those closest to the large scale NSIP projects and the Flexible Generation
Plant proposed development that are also judged to be of high sensitivity. The other
shortlisted schemes are likely not to have significant effects on the visual receptors
either in combination or sequentially.
2.5.3 The visual receptor groups have been grouped up in to those north and south of the
Thames. Subsequently, five locations in the north and four in the south have been
grouped up based on similar locations. This has been done to make the assessment
more concise.
2.5.4 The visual receptors that are predicted to experience significant cumulative effects from
the NSIP projects in group N1 include users of the PRoW Thames Estuary Path, the
section between Tilbury Fort and the point where the LTC tunnel emerges on the north
shore of the Thames. Representative Viewpoints 15 and 16 are within this stretch of
the path. The Flexible Generation Plant in combination with these NSIPs in views from
these visual receptors is likely to only slightly increase the likely significance of effect
from the representative viewpoints. Additionally, there will sequential views from short
stretches of the Thames Estuary Path where views of the proposed development that
are not obscured by the NSIPs but seen side by side in transient views of users of the
path.
2.5.5 The visual receptors that are predicted to experience significant cumulative effects from
the NSIP projects in group N2 include users of open Access Land at Parsonage and
Walton Common and residential receptors on the eastern edge of Tilbury. There are
no representative viewpoints that are of high sensitivity that are likely to be significantly
affected. The Flexible Generation Plant in combination with these NSIPs in receptor
views from the open access is likely to only slightly increase the significance of effect
from the representative viewpoints. The proposed development will be seen in front of
the NSIP developments and in combination but there will be sequential views where
the developments are seen side by side in the view as people move though the
common land.
2.5.6 The visual receptors that are predicted to experience significant cumulative effects from
the NSIP projects in group N3, which typically have elevated views over the
developments, include users of the PRoW FP200, for very short sections that have
uninterrupted views of the proposed development and NSIPs, but due to intervening
landform and vegetation these are uncommon. The view from St James’ Church
graveyard has more elevated and open views of the developments than other publicly
accessible locations in this receptor group. Representative Viewpoint 7 is within the
church graveyard and Viewpoint 10, on PRoW FP200. The Flexible Generation Plant
in combination with the NSIPs in views from these visual receptors is likely to only
slightly increase the likely significance of effect from these representative viewpoints.
From the church graveyard and Viewpoint 7 the Flexible Generation Plant will be seen
in combination with both NSIPs. However, the LTC will be seen in the foreground with
the Flexible Generation Plant and Tilbury2 developments behind.
2.5.7 It is predicted that there will be no likely significant cumulative impacts on receptor
groups N4 and N5.
2.5.8 The visual receptors that are predicted to experience significant cumulative effects from
the NSIP projects in group S1 include users of the Saxon Shore Way, from Gravesend
waterfront to the Shorne Marshes, public access and tourist attractions at Gravesend
Gordon Recreation Ground and Gardens and New Tavern Fort. Representative
Viewpoints 18, 19, 20, 21 and 23 are within this stretch of waterfront. The Flexible
Generation Plant in combination with these NSIPs in views from these visual receptors
is likely to only slightly increase the likely significance of effect from the representative
viewpoints. Views of the Flexible Generation plant will be obscured by the Tilbury2
development along the Gravesend waterfront stretch and it will have very little affect in
increasing the level of significance. Travelling eastwards visual receptors will see first
the Flexible Generation Plant and then the LTC in sequence. However, the significance
of effect of the Flexible Generation Plant is likely not to increase the significance of
effect of the visual impact of the LTC.
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
53
2.5.9 The visual receptors that are predicted to experience significant cumulative effects from
the NSIP projects in group S2, which typically have elevated views some of which
extend over the developments on the north side of the Thames, include Windmill Hill
and some upper floor north facing views from residencies off this public open space.
Representative Viewpoints 22 and 28 are also likely to experience significant visual
effects from the NSIPs. From Windmill Hill the Flexible Generation Plant will be seen
beyond the Tilbury2 development and the latter is likely to obscure and limit the extent
of what visual receptors can see of the Flexible Generation Plant. Therefore, the
significance of effect is unlikely to be increased by more than a negligible amount. The
LTC will be seen still further in the distance. From Viewpoint 28 the Flexible Generation
Plant will be seen next to the LTC but again is unlikely to increase the visual
significance of effect as the Flexible Generation Plant will be seen in the context of
other dockside and industrial uses, albeit at the edge of Tilbury.
2.5.10 It is predicted that there will be no likely significant cumulative impacts on receptor
groups S3 and S4.
2.5.11 Accurate details for all the cumulative developments are not available. Judgements
have had to be made on location and dimensions based in written information and
publicly available images. The cumulative development visualisations are wirelines of
the NSIPs and a selection of viewpoints can be found in section 3 Figures 1.2 to 1.11.
Cumulative developments in a ‘maximum development’ scenario
2.5.12 Two Nationally Significant Infrastructure Project (NSIP) developments are proposed on
land adjacent to and in some cases overlapping with the Thurrock Flexible Generation
Plant application boundary. The Tilbury2 port expansion adjacent to the west is under
construction and Lower Thames Crossing (LTC) motorway to the east and north is at
the pre-application consultation stage, having published a Preliminary Environmental
Information Report (PEIR) in 2018.
2.5.13 As part of this ES, cumulative wirelines from the representative viewpoints have been
generated (Figures 1.2 to 1.11 in this chapter).
2.5.14 The visualisations of Tilbury2 have been modelled using publicly available information
and dimensions. The visualisations of the LTC are based on area extents and do not
include cuttings or embankments or storage and stock piling areas that are likely during
construction. The development extent is based on publicly available information from
Highways England.
2.5.15 Outline planning permission has been granted for several residential and mixed-use
developments expanding Linford and East Tilbury in the direction of Thurrock Flexible
Generation Plant and a number of other relevant cumulative developments in the
surrounding area have been shortlisted for assessment in Table 1.1.
2.5.16 Should the LTC and other smaller developments proceed, Thurrock Flexible
Generation Plant’s main development site would be closely surrounded by the
temporary or permanent works areas Tilbury2 and the LTC, and other smaller
developments.
2.6 Cumulative Effects on Landscape Resources and
Receptors
2.6.1 GLVIA3 refers to Scottish Natural Heritage when defining cumulative landscape effects
as “effects that can impact on either the physical fabric or character of the landscape,
or any special values attached to it” (SNH, 2012).
Designated Landscapes
2.6.2 In the ‘maximum development’ scenario set out above, the indirect, incremental,
cumulative effects of Thurrock Flexible Generation Plant on designated landscape
resources would be minor. None of the projects are within a designated landscape.
Although the larger NSIP projects on the Thurrock side of the Thames Estuary will be
identifiable from the Kent Downs AONB, due to the scale and distance of the built
structures and extent they will not break the skyline when viewed from the AONB. The
LTC by contrast also directly impacts north Kent and may well affect the special
qualities of the Kent Downs AONB. In contrast to the other NSIPs, Thurrock Flexible
Generation Plant will be barely visible, situated further away from the river, closer to
the higher land to the north.
2.6.3 The negligible incremental cumulative impact of the Thurrock Flexible Generation Plant
development on the high sensitivity landscape receptor will have minor effects, which
will not affect the special qualities of the AONB or compromise the reasons for its
designation. It should be noted that the LTC has the potential to have significant effects,
on the AONB on its own, but that the other NSIPs would not incrementally tip this from
a non-significant effect to a significant one.
Non-designated Landscapes
2.6.4 The development proposals for the Thurrock/Essex area that lies within NCA 81:
Greater Thames Estuary are an intensification of the industrial character of this part of
the River Thames. The incremental impact of the Thurrock Flexible Generation Plant
development on this medium sensitivity receptor will be small and will not increase the
effects upon this LCA significantly.
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
54
2.6.5 Two other NSIP projects are located with LCA C5: Tilbury Marshes and together these
projects will have a significant effect on the LCA. The direct, incremental impact of the
Thurrock Flexible Generation Plant development in this character area would not
change the effect to a significant one.
2.6.6 The direct, incremental, cumulative, impact of the installation of the gas pipeline and
connection point on LCA D7: West Tilbury Urban Fringe will be negligible on this
medium sensitivity receptor. The cumulative effect of the Thurrock Flexible Generation
Plant development in this LCA would be negligible will not increase the effects on this
LCA significantly.
2.7 Cumulative Effects on Visual Resources and Receptors
2.7.1 GLVIA3 also quotes Scottish Natural Heritage in defining cumulative visual effects, as
effects that can be caused by combined visibility, which “occurs where the observer is
able to see two or more developments from one viewpoint” and/or sequential effects
“which occur when the observer has to move to another viewpoint to see different
developments” (SNH, 2012).
2.7.2 In the ‘maximum development’ scenario set out above, the direct, cumulative effects of
Tilbury2 on visual resources and receptors are shown in Viewpoint 7 Figure 1.2,
Viewpoint 8 Figure 1.3, Viewpoint 11 Figure 1.4, Viewpoint 12 Figure 1.5, Viewpoint 15
Figure 1.6, Viewpoint 19 Figure 1.7, Viewpoint 22 Figure 1.8,.Viewpoint 24 Figure 1.9
and Viewpoint 26 Figure, 1.10,
2.7.3 In some views and for some groups of receptors, the Tilbury2 NSIP would screen or
partly screen the Thurrock Flexible Generation Plant development (Viewpoint 11
Figure 1.4, Viewpoint 19 Figure 1.7 and Viewpoint 22 Figure 1.8). From these
viewpoints the impacts of the Thurrock Flexible Generation Plant development will not
increase the significance of effects on visual receptors.
2.7.4 In some views, usually due to distance but sometimes due to intervening infrastructure,
the cumulative views of both NSIPs will not be significant. Indeed, the incremental,
cumulative effects of Thurrock Flexible Generation Plant on visual receptors from most
viewpoints would not change the effect to a significant one (Viewpoint 8, Figure 1.3,
Viewpoint 12, Figure 1.5, Viewpoint 24, Figure 1.9, Viewpoint 26, Figure 1.10) and
Viewpoint 28, Figure 1.11.
2.7.5 From certain points on the Chadwell St. Mary – West Tilbury – East Tilbury ridgeline,
Tilbury2, and Thurrock Flexible Generation Plant will be seen with little
overlap/screening of the projects. The taller elements of both proposed developments
are visible above the skyline.
Cumulative Night Time Landscape Effects
2.7.6 This section includes an assessment of the potential cumulative night-time landscape
effects of the proposed development in association with the NSIPs; the Tilbury2 and
LTC developments if they are all operational. These two NSIP projects are located
partly within LCA C5: Tilbury Marshes and together they will have a significant adverse
effect on the LCA. The Thurrock Flexible Generation Plant development in this
character would be in addition to the 2 other NSIPs.
2.7.7 The direct, incremental, cumulative, impact of the installation of the gas pipeline and
connection point on LCA D7: West Tilbury Urban Fringe will be negligible on this
medium sensitivity receptor. The cumulative effect of the Thurrock Flexible Generation
Plant development in this LCA would be negligible adverse but will not increase the
effects on this LCA significantly.
Cumulative Night Time Visual Effects
2.7.8 This section includes an assessment of the potential cumulative night-time visual
effects of the proposed development in association with the NSIPs; the Tilbury2 and
LTC developments if they are all operational.
2.7.9 In the ‘maximum development’ scenario set out above, the light sources from Tilbury2
will appear in front of the Flexible Generation Plant in the following visual resources: at
Viewpoint 11 Figure 1.4,. Viewpoint 19 Figure 1.7 and Viewpoint 22 Figure 1.8. In
conjunction the effect of both schemes would not increase the level of effect to
significant.
2.7.10 There is no permanent external lighting proposed for the Thurrock Flexible Generation
Plant. However, when maintenance work is being undertaken there would be an
intensification of light sources experienced at Viewpoint 7, Figure 1.2 and Access Land
users either side of Gun Hill lane, Cooper Shaw Road and Fort Road, as well as those
using the larger area of Parsonage Common when compared to the Flexible
Generation Plant light sources on their own. However, although the temporary effect
would be significant there would be very few receptors using/traversing these areas at
night that involving the view. Consequently, the impacts will not be considered further
in this assessment
2.7.11 A combination of intervening vegetation, existing development, and landform seen in
relation to the cumulative schemes and in the context of existing lighting at night time
will not raise the significance of effect form the night time level of effect for the other
representative viewpoints.
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
55
Cumulative Decommissioning Effects
2.7.12 It is assumed that the LTC and the housing developments will not be decommissioned
and that they are permanent developments.
Short Listed Projects - Nationally Significant Infrastructure Projects
(NSIPs)
CP 042 Ref: TRO30003 – Site of Tilbury B Power Station, East Tilbury
CP 058 TR010032 LTC - Lower Thames Crossing
2.7.13 Tilbury2 is a new port facility alongside the existing Port of Tilbury. This will involve the
extension of existing jetty facilities and the dredging of berth pockets in the River
Thames, and land works and facilities for: a ’Roll-On-Roll-Off’ (Ro-Ro) terminal for
importing and exporting containers on road trailers; a facility for importing and
processing bulk construction materials; and areas of external storage for a variety of
goods such as imported cars. The project also involves the construction of road and
rail links to the site from adjacent networks.
2.7.14 The Lower Thames Crossing (LTC) will be a new road crossing connecting Essex and
Kent proposed by the Highways England. Principally, this a new road link between the
A2 and M25, crossing the A13 at Orsett before crossing under the River Thames east
of Tilbury and Gravesend. A new link road will take traffic to the A2 near the village of
Shorne, close to the M2.
2.7.15 The landscape and visual receptors which are most likely to be most adversely affected
by the NSIPs in combination with the FGP are assessed below. They have been
selected from the assessment process in section 2. Those receptors which are judged
to be potentially significantly adversely affected by the NSIP developments are
assessed below.
2.8 Potentially Significant Cumulative Landscape Effects
LCA C5 Tilbury Marshes
2.8.1 The construction phases of the Tilbury2 and LTC projects are largely situated within
LCA C5: Tilbury Marshes, as is Thurrock Flexible Generation Plant.
2.8.2 It is considered that Tilbury2 will be operational before the construction of Thurrock
Flexible Generation Plant commences. The construction of Tilbury 2 started
construction in February 2020 and is currently due to be operational by the end of 2020
for the aggregates terminal part of the project. Therefore, no cumulative construction
impacts on either landscape or visual resources and receptors are anticipated.
2.8.3 The construction phase of the LTC is likely to commence after Thurrock FGP (as its
application has not been submitted) but it is considered that it could overlap with the
construction phase of the Thurrock FGP. The effect of the construction phase of the
LTC on its own is expected to have a temporary moderate to major significance of
effect on LCA5: Tilbury Marshes. The significance of effect of the construction phase
of the Flexible Generation Plant on its own is predicted to be moderate adverse.
Paragraphs 2.2.1 to 2.2.7 set out the reasons why the effect of the construction of both
the Flexible Generation Plant and the LTC on the landscape in combination is not likely
to increase the level from moderate to major adverse.
2.8.4 The Tilbury 2 and LTC developments are situated within LCA C5: Tilbury Marshes, as
is Thurrock Flexible Generation Plant. The Thurrock Flexible Generation Plant
development is separated from the proposed Tilbury2 jetty and silo by Tilbury
Substation. The silo and container storage area are to be located on areas of
brownfield land. The three processing buildings and piles of aggregates are proposed
for areas that are rough grassland with some scrub. The cumulative impact will be to
reduce the areas of open grassland within the LCA. However, given the baseline
character of this part of the LCA, the cumulative effect of Tilbury2 and the Flexible
Generation Plant projects will not have a significant effect on this LCA.
2.8.5 The approach road and tunnel entrance of the LTC will result in the loss of agricultural
land, change to the landform over a large area. The effect of the operational phase of
the LTC on its own is expected to have a moderate to major significant effect on LCA
C5: Tilbury Marshes The effect experienced by the LCA from the Flexible Generation
Plant, alone will be moderate adverse, which is not significant. The effect of both these
developments in combination is not likely to increase the level of effect from moderate
to major adverse.
2.8.6 The cumulative effects of the timings of the potential decommissioning phases of
Tilbury2, LTC and Flexible Generation Plant are unlikely to coincide with one another.
Therefore, the likely effects are not likely to be increased to a significant level.
2.9 Potentially Significant Cumulative Visual Effects
Visual receptor group N1
2.9.1 Views from representative Viewpoints 15 and 16 on the Thames Estuary Path long
distance route / Footpath 146 of the Tilbury2 operational phase and the LTC
construction and operational phases are judged be moderate to major and would
significantly affect these receptor views, when considered on their own. Likewise, a
short section of the Thames Estuary Path between Viewpoint 16 to directly south of
and between the Tilbury 2 and LTC sites, would be affected to a moderate to major
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
56
level, particularly by the new wharf at Tilbury2. The effect on these views of the Flexible
Generation Plant construction and operational phases is judged to be moderate. The
effect of the Flexible Generation Plant in combination with either the LTC or Tilbury2
development in combination is not likely to increase the level of effect from moderate
to major adverse.
2.9.2 The cumulative effects of the timings of the potential decommissioning phases of
Tilbury 2, and Flexible Generation Plant are unlikely to coincide with one another.
However, if they do coincide the significance of effect would be moderate to major
and significant for a short, approximately 1km section of the Thames Estuary path
including Representative Viewpoints 15 and 16 (Chapter 6 Landscape and Visual
Resources, Figure 3.17) where the decommissioning operation of the developments
meet the shoreline. The likely cumulative effects are not likely to increase the level of
effect from moderate to major adverse.
2.9.3 The visual effect on other representative viewpoints in this receptor group are not likely
to be increased to a significant level when the Flexible Generation Plant is assessed in
combination with either Tilbury2 or the LTC at the construction, operational or
decommissioning phases.
Visual receptor group N2
2.9.4 The visual receptors judged to be significantly adversely affected by the Tilbury2 and/or
the LTC in this group, are residential groups on the east side of Tilbury and those using
Access Land Walton and Parsonage Commons (in the construction phase) and
Parsonage Common and the Exchange Common Land (Zone E) during the operational
and decommissioning phases. The visual effect of the Tilbury 2 operational phase and
the LTC construction and operational phases on these receptors are judged to be
moderate increasing to moderate to major for some more vulnerable locations within
these areas. However, on its own, the effect on views from the Access Land and for
residential receptors on the east side of Tilbury is judged to be moderate at worse.
From specific Viewpoints 6 and 9 pedestrian receptors would experience a major
adverse effect at worse, for the Flexible Generation Plant construction and operational
phases. However there appears to be very few pedestrians using these areas. The
effect of the Flexible Generation Plant in combination with either the LTC or Tilbury2
development in combination is not likely to increase the level of effect from moderate
to major adverse.
2.9.5 The cumulative effects of the timings of the potential decommissioning phases of
Tilbury2, LTC and Flexible Generation Plant are unlikely to coincide with one another.
Therefore, the likely effects are not likely to be increased to a significant level.
2.9.6 The visual effect on other representative viewpoints in this receptor group are not likely
to be increased to a significant level when the Flexible Generation Plant is assessed in
combination with either Tilbury2 or the LTC at the construction, operational or
decommissioning phases.
Visual receptor group N3
2.9.7 The visual receptors judged to be significantly adversely affected by the Tilbury2 and/or
the LTC in this group, are the community facility of St James’ Church graveyard and
Viewpoints 7 and 10. The visual effect of the Tilbury2 operational phase and the LTC
construction and operational phases on these receptors are judged to be moderate or
major and would significantly affect these receptor views. The effect on these receptor
views of the Flexible Generation Plant construction and operational phases is judged
to be moderate. The effect of the Flexible Generation Plant in combination with either
the LTC or Tilbury 2 development is not likely to increase the level of effect from
moderate to major adverse.
2.9.8 The cumulative effects of the timings of the potential decommissioning phases of
Tilbury2, LTC and Flexible Generation Plant are unlikely to coincide with one another.
Therefore, the likely effects are not likely to be increased to a significant level.
2.9.9 The visual effect on other representative viewpoints in this receptor group are not likely
to be increased to a significant level when the Flexible Generation Plant is assessed in
combination with either Tilbury2 or the LTC at the construction, operational or
decommissioning phases.
Visual receptor group N4
2.9.10 There are no visual receptors judged to be significantly adversely affected by the
Tilbury2 and/or the LTC in this group. There are no visual receptors judged to be
significantly adversely affected by the Flexible Generation Plant. The cumulative
effects of the Flexible Generation Plant in combination with either of the NSIP
developments is not likely to be increased to a significant level at the construction,
operational or decommissioning stages.
Visual receptor group N5
2.9.11 There are no visual receptors judged to be significantly adversely affected by the
Tilbury2 and/or the LTC in this group. There are no visual receptors judged to be
significantly adversely affected by the Flexible Generation Plant. The cumulative
effects of the Flexible Generation Plant in combination with either of the NSIP
developments is not likely to be increased to a significant level at the construction,
operational or decommissioning stages.
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
57
Visual receptor group S1
2.9.12 The visual receptors judged to be significantly adversely affected by the Tilbury2 and/or
the LTC in this group, are residential (Gravesend waterfront); PRoW (Saxon Shore
Way) tourist attractions & recreation (Gordon Gardens, New Tavern Fort, Gravesend
water front); dynamic users (boat passengers on Thames) and Viewpoints 18, 19, 20,
21 (Tilbury2) and 23 (LTC). The visual effect of the Tilbury 2 operational phase and the
LTC construction and operational phases on these receptors are judged to be
moderate to major and would significantly affect these receptor views. There are no
visual receptors judged to be significantly adversely affected by the Flexible Generation
Plant construction and operational phases. The effect of the Flexible Generation Plant
in combination with either the LTC or Tilbury2 development is not likely to increase the
level of effect from moderate to major adverse.
2.9.13 The cumulative effects of the timings of the potential decommissioning phases of
Tilbury2, LTC and Flexible Generation Plant are unlikely to coincide with one another.
Therefore, the likely effects are not likely to be increased to a significant level.
2.9.14 The visual effect on other representative viewpoints in this receptor group are not likely
to be increased to a significant level when the Flexible Generation Plant is assessed in
combination with either Tilbury2 or the LTC at the construction, operational or
decommissioning phases.
Visual receptor group S2
2.9.15 The visual receptors judged to be significantly adversely affected by the Tilbury2 and/or
the LTC in this group are residents and Public open Space users (Windmill Hill,
Windmill Gardens, Gravesend), PRoW east of Gravesend (LTC only) and Viewpoints
22 and 28 (LTC only). The visual effect of the Tilbury2 operational phase and the LTC
construction and operational phases on these receptors are judged to be moderate to
major and would significantly affect these receptor views. None of these visual
receptors are judged to be significantly adversely affected by the Flexible Generation
Plant construction and operational phases. The effect of the Flexible Generation Plant
in combination with either the LTC or Tilbury2 development is not likely to increase the
level of effect from moderate to major adverse.
2.9.16 The cumulative effects of the timings of the potential decommissioning phases of
Tilbury2, LTC and Flexible Generation Plant are unlikely to coincide with one another.
Therefore, the likely effects are not likely to be increased to a significant level.
Visual receptor group S3
2.9.17 There are no visual receptors judged to be significantly adversely affected by the
Tilbury2 and/or the LTC in this group. There are no visual receptors judged to be
significantly adversely affected by the Flexible Generation Plant. The cumulative
effects of the Flexible Generation Plant in combination with either of the NSIP
developments is not likely to be increased to a significant level at the construction,
operational or decommissioning stages.
2.9.18 Neither NSIP project is within the Kent Downs AONB designated landscape, where
visual receptor group S3 is located. The LTC project will be identifiable from the Kent
Downs AONB, due to the scale of project. It will impact on the landscape in north Kent,
to the north of the Kent Downs AONB and will be clearly visible from parts of the AONB
(Viewpoint 29, Figure 3.22) and will pass very close to, if not on the alignment of
Viewpoint 28, Figure 3.21. The LTC might affect the special qualities of the AONB, as
a result of the north Kent section of the proposed transport infrastructure. The Thurrock
Flexible Generation Plant does not intensify the effects on the AONB caused by the
construction or operational phases of the LTC.
Visual receptor group S4
2.9.19 There are no visual receptors judged to be significantly adversely affected by the
Tilbury2 and/or the LTC in this group. There are no visual receptors judged to be
significantly adversely affected by the Flexible Generation Plant. The cumulative
effects of the Flexible Generation Plant in combination with either of the NSIP
developments is not likely to be increased to a significant level at the construction,
operational or decommissioning stages.
Other short listed potential cumulative projects
2.9.20 This section provides a short summary description of the short-listed projects that have
the potential to have cumulative impacts in combination with the Flexible Generation
Plant development.
2.9.21 None of these developments on their own have the potential to have significant adverse
effects on the landscape or visual receptors assessed for the Flexible Generation Plant
development at the construction, operational or decommissioning phases.
CP 005 Application Ref: 18/00664/COND – One Big Self Store Ltd Trafalgar House
Thames Industrial Park, Princess Margaret Road, East Tilbury, Essex
2.9.22 Redevelopment of an area of previously developed land towards the southern
boundary of Thames Industrial Estate to provide 50 dwellings, improved access
arrangements and the creation of an area of public open space.
2.9.23 Neither project is within, or adjacent to, a designated landscape. The residential
development is located within LCA D7: West Tilbury Urban Fringe, the same character
area as the gas connection point of the Thurrock Flexible Generation Plant
development. The cumulative impact will be negligible during the construction,
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
58
operational and decommissioning phases of the Thurrock Flexible Generation Plant
and the effects would not be significant.
2.9.24 Should the construction phases of the two projects overlap, cumulative visual impacts
would be negligible. No cumulative visual impacts would be experienced during the
decommissioning phase and the effects would not be significant.
CP 011 Application Ref: 16/01475/SCR Proposed development of up to 200
dwellings with associated access and open space Gothards Field Rear of The
George And Dragon, East Tilbury Road, Linford, Essex
2.9.25 Screening opinion for proposed development of up to 200 dwellings with associated
access and open space.
2.9.26 Neither project is within, or adjacent to, a designated landscape. This residential
development is located within LCA D7: West Tilbury Urban Fringe. the cumulative
impact will be negligible during both the construction, operational and
decommissioning phases of the Thurrock Flexible Generation Plant and the effects of
no significance.
2.9.27 Similarly, the cumulative visual impacts for the closest receptor group N5, will be
negligible during the construction phase (should the construction phases of the two
projects overlap) and operational phase and no change during the decommissioning
phase. The effects would not be significant.
CP 012 Application Ref: 16/01232/OUT – Land for Development, Muckingford Road,
Linford, Essex
2.9.28 Application for outline planning permission for a proposed development of up to 1,000
dwellings, a new local road network, a new single form entry primary school, local
centre including provision for shops and new areas of open space, including formal
recreation.
2.9.29 Neither project is within, or adjacent to, a designated landscape. This residential
development with school and shops/local centre is located within two LCAs, LCA D5:
Linford/Buckingham Hill Urban Fringe and LCA D7: West Tilbury Urban Fringe. It
shares the latter with the Thurrock Flexible Generation Plant gas connection point.
However, the cumulative impact will be negligible during both the construction,
operational and decommissioning phases of the Thurrock Flexible Generation Plant
and the effects of no significance.
2.9.30 Similarly, the cumulative visual impacts will be negligible for the closest receptor group
N5, during the construction phase (should the construction phases of the two projects
overlap) and operational phase and no change during the decommissioning phase.
The effects would not be significant.
CP 016 Application Ref: 17/00977/FUL – Land Part of Marsh Farm Sewage
Treatment Plant, Fort Road, Tilbury, Essex
2.9.31 Retention and completion of waste wood processing plant and fire retained area
bounded by concrete push walls, erection of buildings to form associated storage,
reception/administration, security, and staff welfare area; formation of impermeable
surface to form a lorry parking/waiting area; weighbridge and staff parking area
together with associated highways and drainage works.
2.9.32 Neither project is within, or adjacent to, a designated landscape. The cumulative impact
of the two projects would not affect the special qualities of the Kent Downs AONB.
2.9.33 The waste wood processing plant project is situated within LCA C5: Tilbury Marshes,
as is Thurrock Flexible Generation Plant. It is anticipated that the remaining
construction works at the waste wood processing plant, at Marsh Farm, will be
completed before the construction of Thurrock Flexible Generation Plant commences,
therefore there would be no cumulative construction effects. The cumulative impacts
on landscape character are considered to be small, as the waste wood processing
plant is already part of the baseline to some degree. The effects on the landscape
character of the LCA are not considered to be significant.
2.9.34 The processing plant is not seen in the same view as the Thurrock Flexible Generation
Plant facility in elevated views from the north. In the views from the north-east (visual
receptor group N1 and N2), situated in the flat landscape the two schemes would only
be seen, either by turning the head, or with the processing plant forming an indistinct,
distant element behind the Thurrock Flexible Generation Plant facility. The cumulative
impacts of the two schemes would be negligible to small and not significant.
2.9.35 Similarly, in elevated views from the north-west, (visual receptor group N3 - e.g.
Viewpoint 3, Figure 5.44) the processing plant would be barely noticeable against the
backdrop of the surrounding woodland and infrastructure. The cumulative impacts
would be small to negligible and the effects not significant.
2.9.36 The closest elevated location from which the two schemes might be visible is Fort Road
Bridge (Viewpoint 11, Figure 5.49). However, the viewer would have to turn their head
to glimpse both projects. The impact from this location is considered to be small and
the cumulative visual effect not significant.
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
59
CP 025 Application Ref: 16/00186/DMI – National Power PLC, Tilbury Power Station,
Fort Road, Tilbury, Essex
2.9.37 Demolition of Tilbury B power station and all associated buildings and structures
(including remaining structures from Tilbury A power station). The jetty will not be
demolished.
2.9.38 This project is considered as having been completed for the purpose of this
assessment and the land following demolition forms part of the future baseline.
CP 079 Application Ref: 19/01274/FUL Short Term Operations Reserve (STOR), Fort
Road, Tilbury, Essex
2.9.39 The site is on the former Anglian Water Services Sewage treatment Plant site and lies
to the north west of the proposed Thurrock Flexible Generation Plant facility. The
application is awaiting a decision as of 7th October 2019. The development comprises
14 no. gas-fired generators with a capacity up to 21 MW.
2.9.40 The STOR site is located in the same character area, Tilbury Marshes LCA C5, as the
proposed development. The cumulative impacts of the proposed STOR on landscape
character are considered to be small, as the site is an area of scrub land adjacent to a
number of industrial uses such as sewage works and wood processing facility which
already form part of the baseline. It is a relatively small area of land contained by these
industrial uses. It is also separated from Tilbury Fort by a sewage works to the south
west. The effects on the landscape character of the LCA are not considered to be
significant.
2.9.41 The STOR facility occupies some 0.4ha and has 7.4m high stacks. Existing scrub and
adjoining industrial uses effectively screen this development from sensitive visual
receptors. The STOR would be screened effectively by existing vegetation to the north
west and from sensitive visual residential receptors on the eastern side of Tilbury and
to the north of the STOR at Viewpoints 9 and 11 (part of receptor group N2). From the
south at Viewpoints 12 and 14 (part of receptor group N1) the STOR will be seen in
front of the proposed Thurrock Flexible Generation Plant, and in the visual context of
the existing sewage works. The cumulative impacts of the two schemes would be small
and not significant.
2.9.42 Neither project is within, or adjacent to, a designated landscape. The cumulative impact
of the two projects would not affect the special qualities of the Kent Downs AONB.
CP 081 Application Ref: 12.04.09.04/266C; Tilbury Green Power Phase 2 S36C
application. Former Cargill Plant Tilbury Freeport Tilbury Essex
2.9.43 The variation application is for a Biomass and energy from waste fuelled generation
station at Tilbury Docks, Essex: variation application under section 36c of the electricity
act 1989. The site is located between Grays and Tilbury Docks and is situated within
LCA C5: Tilbury Marshes, as is Thurrock Flexible Generation Plant. The site formerly
comprised factory buildings, plant, warehousing and car parking areas operated by
Cargill for the production of sweeteners from cereals. Production ceased in 2005 and
the site remained unused thereafter. It is anticipated that the construction works for the
Tilbury Green Power (TGP) Station Ph 2, will be completed before the construction of
Thurrock Flexible Generation Plant commences, therefore there would be no
cumulative construction effects. The cumulative impacts of the operational phase of
both developments on landscape character are considered to be small, as the sites are
separated from each other by Tilbury Docks and reusing existing brownfield sites. The
effects on the landscape character of the LCA are not considered to be significant
2.9.44 The TGP is not seen in the same view as the Thurrock Flexible Generation Plant facility
and separated by Tilbury docks. The cumulative landscape impacts of the two schemes
would be negligible to small and not significant.
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
60
3. References
Landscape Institute and Institute of Environmental Management and Assessment (2013)
Guidelines for Landscape and Visual Impact Assessment: Third Edition. London, Routledge
Scottish Natural Heritage (2012) Assessing the cumulative impact of onshore wind energy
development. Inverness, Scottish Natural Heritage
Chapter 19 Landscape and Visual Resources Volume 4: Cumulative Environmental Assessment
May 2020
61
Figures 1.2 to 1.11: Representative Viewpoints and Wirelines of the Thurrock FGP and NSIP developments
(Summer and Winter)
Stacks in pairs
Ref
: 108
72-0
179-
005
Figure 1.2
Thurrock FGP Facility
Tilbury2
Lower Thames Crossing Route
Date of Photo: 12/09/2019
Lens Type: 50mm
Distance to site: 0.65km
OS reference: 565967, 177449
Direction to site: South
Viewpoint height: 25.68m AOD
Horizontal field of view: Approx. 750
Viewing distance: 300mm @ A3
Existing view
Proposed wireline view
Viewpoint 7
Stacks in pairs
Ref
: 108
72-0
179-
005
Figure 1.3
Thurrock FGP Facility
Tilbury2Date of Photo: 12/09/2019
Lens Type: 50mm
Distance to site: 0.84km
OS reference: 566911, 177559
Direction to site: South West
Viewpoint height: 3.5m AOD
Horizontal field of view: Approx. 750
Viewing distance: 300mm @ A3
Existing view
Proposed wireline view
Viewpoint 8
Stacks in pairs
Ref
: 108
72-0
179-
005
Figure 1.4
Thurrock FGP Facility
Tilbury2Date of Photo: 30/08/2018
Lens Type: 50mm
Distance to site: 0.776km
OS reference: 565335, 176364
Direction to site: East North East
Viewpoint height: 6.4m AOD
Horizontal field of view: Approx. 750
Viewing distance: 300mm @ A3
Existing view
Proposed wireline view
Viewpoint 11
Stacks in pairs
Ref
: 108
72-0
179-
005
Figure 1.5
Thurrock FGP Facility
Tilbury2Date of Photo: 04/09/2018
Lens Type: 50mm
Distance to site: 1.093km
OS reference: 565278,175783
Direction to site: North East
Viewpoint height: 4.567m AOD
Horizontal field of view: Approx. 750
Viewing distance: 300mm @ A3
Existing view
Proposed wireline view
Viewpoint 12
Stacks in pairs
Ref
: 108
72-0
179-
005
Figure 1.6
Thurrock FGP Facility
Tilbury2Date of Photo: 12/09/2019
Lens Type: 50mm
Distance to site: 1.093km
OS reference: 566905, 175513
Direction to site: North North West
Viewpoint height: 8.8m AOD
Horizontal field of view: Approx. 750
Viewing distance: 300mm @ A3
Existing view
Proposed wireline view
Viewpoint 15
Stacks in pairs
Ref
: 108
72-0
179-
005
Figure 1.7
Thurrock FGP Facility
Tilbury2Date of Photo: 27/09/2019
Lens Type: 50mm
Distance to site: 2.31km
OS reference: 564842, 174534
Direction to site: NE
Viewpoint height: 3.5m AOD
Horizontal field of view: Approx. 750
Viewing distance: 300mm @ A3
Existing view
Proposed wireline view
Viewpoint 19
Stacks in pairs
Ref
: 108
72-0
179-
005
Figure 1.8
Thurrock FGP Facility
Tilbury2Date of Photo: 27/09/2019
Lens Type: 50mm
Distance to site: 3.3km
OS reference: 564846, 173387
Direction to site: North North East
Viewpoint height: 55.85m AOD
Horizontal field of view: Approx. 750
Viewing distance: 300mm @ A3
Existing view
Proposed wireline view
Viewpoint 22
Stacks in pairs
Ref
: 108
72-0
179-
005
Figure 1.9
Thurrock FGP Facility
Tilbury2Date of Photo: 07/09/2018
‘Former Tilbury B building removed’
Lens Type: 50mm
Distance to site: 3.23km
OS reference: 569169, 174825
Direction to site: West North West
Viewpoint height: 5.25m AOD
Horizontal field of view: Approx. 750
Viewing distance: 300mm @ A3
Existing view
Proposed wireline view
Viewpoint 24
Approximate location of Causeway for barge deliveries during construction
Stacks in pairs
Ref
: 108
72-0
179-
005
Figure 1.10
Thurrock FGP Facility
Tilbury2Photo Date: 05/09/2018
‘Former Tilbury B building removed’
Lens Type: 50mm
Distance to site: 4.18km
OS reference: 570611, 176687
Direction to site: West
Viewpoint height: 6.1m AOD
Horizontal field of view: Approx. 750
Viewing distance: 300mm @ A3
Existing view
Proposed wireline view
Viewpoint 26
Stacks in pairs
Ref
: 108
72-0
179-
005
Figure 1.11
Thurrock FGP Facility
Tilbury2
Lower Thames Crossing Route Alignment
Date of Photo: 12/09/2019
Lens Type: 50mm
Distance to site: 0.65km
OS reference: 567301, 172538
Direction to site: North
Viewpoint height: 41.50m AOD
Horizontal field of view: Approx. 750
Viewing distance: 300mm @ A3
Existing view
Proposed wireline view
Viewpoint 28