Three-Stage GI Study Process Overviewopsportal.spp.org/documents/studies/SPP Three Stage... ·...

19

Transcript of Three-Stage GI Study Process Overviewopsportal.spp.org/documents/studies/SPP Three Stage... ·...

Page 1: Three-Stage GI Study Process Overviewopsportal.spp.org/documents/studies/SPP Three Stage... · •MOPC approved the GIITF whitepaper at the April 2018 meeting •Tariff changes were
Page 2: Three-Stage GI Study Process Overviewopsportal.spp.org/documents/studies/SPP Three Stage... · •MOPC approved the GIITF whitepaper at the April 2018 meeting •Tariff changes were

Three-Stage GI Study Process OverviewMarch 2019

2SouthwestPowerPool SPPorg southwest-power-pool

Page 3: Three-Stage GI Study Process Overviewopsportal.spp.org/documents/studies/SPP Three Stage... · •MOPC approved the GIITF whitepaper at the April 2018 meeting •Tariff changes were

Interconnection CustomersAs SPP is working on the transitional plans to migrate for them previous Interconnection Study and Process methodology to the coming “Three Stage Process”, as outlined in this presentation, we also provide this link below to the SPP Compliance Filing with FERC, filed 16 April 2019.

https://www.spp.org/documents/59793/20190416_revisions%20to%20implement%20gi%20three-stage%20study%20process_er19-1579-000.pdf

Tariff Services Team

[email protected]

31 May 2019

3

Page 4: Three-Stage GI Study Process Overviewopsportal.spp.org/documents/studies/SPP Three Stage... · •MOPC approved the GIITF whitepaper at the April 2018 meeting •Tariff changes were

Benefits

• Streamlined, simplified, less confusing. Easier for SPP to administer

Easier for customers to understand and navigate

• Majority of upgrades are identified in Stage 1 which permits customers to make an informed decision prior to committing to a lengthy and expensive stability analysis.

• Tying financial security to upgrade cost allocation encourages customers to weigh the risks of proceeding at an earlier stage.

• Reduce the number of requests withdrawing late in the process, which reduces re-studies and uncertainty. 4

Page 5: Three-Stage GI Study Process Overviewopsportal.spp.org/documents/studies/SPP Three Stage... · •MOPC approved the GIITF whitepaper at the April 2018 meeting •Tariff changes were

Tariff Filing

• FERC Docket: ER19-1579

• Filed: April 16, 2019

• Requested effective date: July 1, 2019

• Current status: Awaiting FERC Order

5

Page 6: Three-Stage GI Study Process Overviewopsportal.spp.org/documents/studies/SPP Three Stage... · •MOPC approved the GIITF whitepaper at the April 2018 meeting •Tariff changes were

6

DISIS Phase 2Stability and

Short-Circuit

Entry

Withdraw

SPP GI Study Process(Three-Stage)

DISIS Phase 1Steady-State

Analysis

Facilities

Study

Study

Deposit*

and Financial

Security 1†

Financial

Security 2 †

Financial

Security 3 †

SPP

Generator

Interconnection

Agreement

Decision

Point 1

Decision

Point 2

Decision

Point 3

*Study Deposit Schedule

• 0-2 MW: $25,000

• >2-20 MW: $35,000

• >20-74 MW: $50,000

• 75 MW+: $90,000

† Financial Security Deposits

• Financial Security 1: $2000/MW

• Financial Security 2: 10% of allocated upgrade

costs or $2000/MW (minimum)

• Financial Security 3: Additional 10% of allocated

upgrade costs (total of 20%)

Page 7: Three-Stage GI Study Process Overviewopsportal.spp.org/documents/studies/SPP Three Stage... · •MOPC approved the GIITF whitepaper at the April 2018 meeting •Tariff changes were

7

Stage 1

Application

Application and

Study Agreement

Technical Data

Evidence of Site Control

Financial Security

Deposit 1 = $2,000/MW

Application Fee and

Study Deposit

Open Season Stage 1Decision Point 1

Stage 2Decision Point 2

Stage 3Decision Point 3

GIA

5 Months + 1 Month Review Period

Page 8: Three-Stage GI Study Process Overviewopsportal.spp.org/documents/studies/SPP Three Stage... · •MOPC approved the GIITF whitepaper at the April 2018 meeting •Tariff changes were

8

• Steady-State Thermal and Voltage Analysis

• Short-Circuit Ratio

• Cost Estimates (+/-30%) for each new upgrade

• Initial Interconnection Facilities and Network Upgrades required

• Available affected system impacts, upgrades, and estimated costs

Stage 1 Deliverables

Open Season Stage 1Decision Point 1

Stage 2Decision Point 2

Stage 3Decision Point 3

GIA

90 Days

STAGE

Page 9: Three-Stage GI Study Process Overviewopsportal.spp.org/documents/studies/SPP Three Stage... · •MOPC approved the GIITF whitepaper at the April 2018 meeting •Tariff changes were

Open Season Stage 1Decision Point 1

Stage 2Decision Point 2

Stage 3Decision Point 3

GIA

9

Refund Stage 1 Financial Security Deposit

Pay Financial Security Deposit 2

$2,000/MW

10% of SPP upgrade costs x cost allocation factor2 less FS1

Withdraw

Continue

Optional Changes

Reduce request by up to 50%

Drop from NRIS to ERIS

Turbine/Inverter Change

Gre

ate

r o

f:

15 Business Days

Financial

Security 1

is at risk

Page 10: Three-Stage GI Study Process Overviewopsportal.spp.org/documents/studies/SPP Three Stage... · •MOPC approved the GIITF whitepaper at the April 2018 meeting •Tariff changes were

10

• Dynamic and Transient Stability Analysis

• Short-Circuit Analysis

• Refresh of the Stage 1 thermal and voltage analysis as needed

• Cost Estimates (+/-30%) for each new upgrade allocated to a request in the study.

• Available affected system impacts, upgrades, and estimated costs

Stage 2 Deliverables

Open Season Stage 1Decision Point 1

Stage 2Decision Point 2

Stage 3Decision Point 3

GIA

120 Days

STAGE

Page 11: Three-Stage GI Study Process Overviewopsportal.spp.org/documents/studies/SPP Three Stage... · •MOPC approved the GIITF whitepaper at the April 2018 meeting •Tariff changes were

Open Season Stage 1Decision Point 1

Stage 2Decision Point 2

Stage 3Decision Point 3

GIA

11

• Stage 2 Financial Security Deposit is refunded

• Stage 1 Financial Security is refundable if

costs exceed “penalty-free” threshold

Pay Financial Security Deposit 3

20% of SPP upgrade costs less FS1 and FS2

Withdraw

Continue

Optional Changes

Reduce request by up to 10%

15 Business Days

Financial

Security 1

and 2 are at

risk

Page 12: Three-Stage GI Study Process Overviewopsportal.spp.org/documents/studies/SPP Three Stage... · •MOPC approved the GIITF whitepaper at the April 2018 meeting •Tariff changes were

12

• Refresh analysis as needed

• Facilities Study-level Cost Estimates (+/-20%) for each new upgrade allocated to a request in the study.

• Construction Lead Time Estimates

• Available affected system impacts, upgrades, and estimated costs

Stage 3 Deliverables

Open Season Stage 1Decision Point 1

Stage 2Decision Point 2

Stage 3Decision Point 3

GIA

135 Days

STAGE

Page 13: Three-Stage GI Study Process Overviewopsportal.spp.org/documents/studies/SPP Three Stage... · •MOPC approved the GIITF whitepaper at the April 2018 meeting •Tariff changes were

Open Season Stage 1Decision Point 1

Stage 2Decision Point 2

Stage 3Decision Point 3

GIA

13

Review Report

Provide comments on Stage 3 report

Begin negotiations on GIA with TO

Withdraw

Continue

15 Business Days

• Financial Security 1, 2, and 3 are refundable if

costs exceed “penalty-free” threshold

Financial

Security 1, 2,

and 3 are at

risk

Page 14: Three-Stage GI Study Process Overviewopsportal.spp.org/documents/studies/SPP Three Stage... · •MOPC approved the GIITF whitepaper at the April 2018 meeting •Tariff changes were

Penalty-Free Withdrawal• If estimated costs increase between stages, the

customer can withdraw without risking financial security if the increase meets these requirements Costs of Stage 2 compared with Stage 1 increase by

25% or greater, and

$10,000/MW or greater

Costs of Stage 3, or any Stage 3 revision, compared with Stage 2 increase by

35% or greater, and

$15,000/MW or greater

• Known affected-system upgrade costs are included for purposes of determining if penalty-free withdrawal applies.

14

Page 15: Three-Stage GI Study Process Overviewopsportal.spp.org/documents/studies/SPP Three Stage... · •MOPC approved the GIITF whitepaper at the April 2018 meeting •Tariff changes were

Security Refund

15

Open Season DRP DISIS Stage 1 DP1 DISIS Stage 2 DP2 Facilities Study DP3

Full Refund

Full Refund Refund Subject to Adverse Impact Test

Refund Subject to Adverse

Impact Test

FullRefund Subject to Adverse

Impact Test

Exc1

FS-1 paid FS-2 paid FS-3 paid

Disposition of

FS-1 if request

is withdrawn

during the

period shown

above

Exc2

Exc2

Exc2

Disposition of

FS-2 if request

is withdrawn

during the

period shown

above

Disposition of

FS-3 if request

is withdrawn

during the

period shown

above

FS = Financial Security

Deposit

DRP = DISIS Review Period

DP = Decision Point

Exc1 = Exception to Adverse Impact Test: Full

refund if cost increases by 25% and $10k/MW

Exc2 = Exception to Adverse Impact Test: Full

refund if cost increases by 35% and $15k/MW

Study Cycle

Page 16: Three-Stage GI Study Process Overviewopsportal.spp.org/documents/studies/SPP Three Stage... · •MOPC approved the GIITF whitepaper at the April 2018 meeting •Tariff changes were

GI Process Timeline

FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JANJANDECNOV FEB APR

16

DISIS

Review

Period 1 month

Decision

Point 115 bus. days

Decision

Point 215 bus. days

Decision

Point 315 bus. days

DISIS Phase 1 DISIS Phase 2 Facilities Study

90 days 120 days 135 days

GIA

Negotiation

and Filing

75 days

Approx. 485 days

Page 17: Three-Stage GI Study Process Overviewopsportal.spp.org/documents/studies/SPP Three Stage... · •MOPC approved the GIITF whitepaper at the April 2018 meeting •Tariff changes were

TransitionOn the effective date of the new process:

• Feasibility and PISIS Queues

Studies that are in progress will continue to completion under the legacy process

Requests in studies that have not begun will be terminated and can be entered in the open season for Stage 1

• DISIS Queue

The cluster study currently under way will continue to completion under the legacy process, then enter Decision Point 1 of the new process

Clusters that have been queued, but have not commenced, will enter Stage 1 by satisfying the Stage 1 requirements within 20 Business Days after the previously-queued Stage 2 DISIS study is posted

• Facilities Study Queue

Requests having signed Facilities Study Agreements will continue under the legacy process to a signed GIA

• Open Seasons will be paired until the last DISIS cluster posts its Stage 1 report. Paired open season requests will comprise one Stage 1 study and will have the same queue priority.

17

Page 18: Three-Stage GI Study Process Overviewopsportal.spp.org/documents/studies/SPP Three Stage... · •MOPC approved the GIITF whitepaper at the April 2018 meeting •Tariff changes were

Stakeholder Approval Process

• GIITF developed a whitepaper describing the three-stage process for MOPC

• MOPC approved the GIITF whitepaper at the April 2018 meeting

• Tariff changes were drafted in RR335 and were approved by Regional Tariff Working Group on Nov. 29, 2018

Reliability Coordination Working Group on Dec. 12, 2018

Transmission Working Group on Dec. 19, 2018

MOPC on January 15, 2019 (unanimously)

18

Page 19: Three-Stage GI Study Process Overviewopsportal.spp.org/documents/studies/SPP Three Stage... · •MOPC approved the GIITF whitepaper at the April 2018 meeting •Tariff changes were

19

Questions?

If you have any questions, please submit a ticket on RMS.