Three-Stage GI Study Process Overviewopsportal.spp.org/documents/studies/SPP Three Stage... ·...
Transcript of Three-Stage GI Study Process Overviewopsportal.spp.org/documents/studies/SPP Three Stage... ·...
Three-Stage GI Study Process OverviewMarch 2019
2SouthwestPowerPool SPPorg southwest-power-pool
Interconnection CustomersAs SPP is working on the transitional plans to migrate for them previous Interconnection Study and Process methodology to the coming “Three Stage Process”, as outlined in this presentation, we also provide this link below to the SPP Compliance Filing with FERC, filed 16 April 2019.
https://www.spp.org/documents/59793/20190416_revisions%20to%20implement%20gi%20three-stage%20study%20process_er19-1579-000.pdf
Tariff Services Team
31 May 2019
3
Benefits
• Streamlined, simplified, less confusing. Easier for SPP to administer
Easier for customers to understand and navigate
• Majority of upgrades are identified in Stage 1 which permits customers to make an informed decision prior to committing to a lengthy and expensive stability analysis.
• Tying financial security to upgrade cost allocation encourages customers to weigh the risks of proceeding at an earlier stage.
• Reduce the number of requests withdrawing late in the process, which reduces re-studies and uncertainty. 4
Tariff Filing
• FERC Docket: ER19-1579
• Filed: April 16, 2019
• Requested effective date: July 1, 2019
• Current status: Awaiting FERC Order
5
6
DISIS Phase 2Stability and
Short-Circuit
Entry
Withdraw
SPP GI Study Process(Three-Stage)
DISIS Phase 1Steady-State
Analysis
Facilities
Study
Study
Deposit*
and Financial
Security 1†
Financial
Security 2 †
Financial
Security 3 †
SPP
Generator
Interconnection
Agreement
Decision
Point 1
Decision
Point 2
Decision
Point 3
*Study Deposit Schedule
• 0-2 MW: $25,000
• >2-20 MW: $35,000
• >20-74 MW: $50,000
• 75 MW+: $90,000
† Financial Security Deposits
• Financial Security 1: $2000/MW
• Financial Security 2: 10% of allocated upgrade
costs or $2000/MW (minimum)
• Financial Security 3: Additional 10% of allocated
upgrade costs (total of 20%)
7
Stage 1
Application
Application and
Study Agreement
Technical Data
Evidence of Site Control
Financial Security
Deposit 1 = $2,000/MW
Application Fee and
Study Deposit
Open Season Stage 1Decision Point 1
Stage 2Decision Point 2
Stage 3Decision Point 3
GIA
5 Months + 1 Month Review Period
8
• Steady-State Thermal and Voltage Analysis
• Short-Circuit Ratio
• Cost Estimates (+/-30%) for each new upgrade
• Initial Interconnection Facilities and Network Upgrades required
• Available affected system impacts, upgrades, and estimated costs
Stage 1 Deliverables
Open Season Stage 1Decision Point 1
Stage 2Decision Point 2
Stage 3Decision Point 3
GIA
90 Days
STAGE
Open Season Stage 1Decision Point 1
Stage 2Decision Point 2
Stage 3Decision Point 3
GIA
9
Refund Stage 1 Financial Security Deposit
Pay Financial Security Deposit 2
$2,000/MW
10% of SPP upgrade costs x cost allocation factor2 less FS1
Withdraw
Continue
Optional Changes
Reduce request by up to 50%
Drop from NRIS to ERIS
Turbine/Inverter Change
Gre
ate
r o
f:
15 Business Days
Financial
Security 1
is at risk
10
• Dynamic and Transient Stability Analysis
• Short-Circuit Analysis
• Refresh of the Stage 1 thermal and voltage analysis as needed
• Cost Estimates (+/-30%) for each new upgrade allocated to a request in the study.
• Available affected system impacts, upgrades, and estimated costs
Stage 2 Deliverables
Open Season Stage 1Decision Point 1
Stage 2Decision Point 2
Stage 3Decision Point 3
GIA
120 Days
STAGE
Open Season Stage 1Decision Point 1
Stage 2Decision Point 2
Stage 3Decision Point 3
GIA
11
• Stage 2 Financial Security Deposit is refunded
• Stage 1 Financial Security is refundable if
costs exceed “penalty-free” threshold
Pay Financial Security Deposit 3
20% of SPP upgrade costs less FS1 and FS2
Withdraw
Continue
Optional Changes
Reduce request by up to 10%
15 Business Days
Financial
Security 1
and 2 are at
risk
12
• Refresh analysis as needed
• Facilities Study-level Cost Estimates (+/-20%) for each new upgrade allocated to a request in the study.
• Construction Lead Time Estimates
• Available affected system impacts, upgrades, and estimated costs
Stage 3 Deliverables
Open Season Stage 1Decision Point 1
Stage 2Decision Point 2
Stage 3Decision Point 3
GIA
135 Days
STAGE
Open Season Stage 1Decision Point 1
Stage 2Decision Point 2
Stage 3Decision Point 3
GIA
13
Review Report
Provide comments on Stage 3 report
Begin negotiations on GIA with TO
Withdraw
Continue
15 Business Days
• Financial Security 1, 2, and 3 are refundable if
costs exceed “penalty-free” threshold
Financial
Security 1, 2,
and 3 are at
risk
Penalty-Free Withdrawal• If estimated costs increase between stages, the
customer can withdraw without risking financial security if the increase meets these requirements Costs of Stage 2 compared with Stage 1 increase by
25% or greater, and
$10,000/MW or greater
Costs of Stage 3, or any Stage 3 revision, compared with Stage 2 increase by
35% or greater, and
$15,000/MW or greater
• Known affected-system upgrade costs are included for purposes of determining if penalty-free withdrawal applies.
14
Security Refund
15
Open Season DRP DISIS Stage 1 DP1 DISIS Stage 2 DP2 Facilities Study DP3
Full Refund
Full Refund Refund Subject to Adverse Impact Test
Refund Subject to Adverse
Impact Test
FullRefund Subject to Adverse
Impact Test
Exc1
FS-1 paid FS-2 paid FS-3 paid
Disposition of
FS-1 if request
is withdrawn
during the
period shown
above
Exc2
Exc2
Exc2
Disposition of
FS-2 if request
is withdrawn
during the
period shown
above
Disposition of
FS-3 if request
is withdrawn
during the
period shown
above
FS = Financial Security
Deposit
DRP = DISIS Review Period
DP = Decision Point
Exc1 = Exception to Adverse Impact Test: Full
refund if cost increases by 25% and $10k/MW
Exc2 = Exception to Adverse Impact Test: Full
refund if cost increases by 35% and $15k/MW
Study Cycle
GI Process Timeline
FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JANJANDECNOV FEB APR
16
DISIS
Review
Period 1 month
Decision
Point 115 bus. days
Decision
Point 215 bus. days
Decision
Point 315 bus. days
DISIS Phase 1 DISIS Phase 2 Facilities Study
90 days 120 days 135 days
GIA
Negotiation
and Filing
75 days
Approx. 485 days
TransitionOn the effective date of the new process:
• Feasibility and PISIS Queues
Studies that are in progress will continue to completion under the legacy process
Requests in studies that have not begun will be terminated and can be entered in the open season for Stage 1
• DISIS Queue
The cluster study currently under way will continue to completion under the legacy process, then enter Decision Point 1 of the new process
Clusters that have been queued, but have not commenced, will enter Stage 1 by satisfying the Stage 1 requirements within 20 Business Days after the previously-queued Stage 2 DISIS study is posted
• Facilities Study Queue
Requests having signed Facilities Study Agreements will continue under the legacy process to a signed GIA
• Open Seasons will be paired until the last DISIS cluster posts its Stage 1 report. Paired open season requests will comprise one Stage 1 study and will have the same queue priority.
17
Stakeholder Approval Process
• GIITF developed a whitepaper describing the three-stage process for MOPC
• MOPC approved the GIITF whitepaper at the April 2018 meeting
• Tariff changes were drafted in RR335 and were approved by Regional Tariff Working Group on Nov. 29, 2018
Reliability Coordination Working Group on Dec. 12, 2018
Transmission Working Group on Dec. 19, 2018
MOPC on January 15, 2019 (unanimously)
18
19
Questions?
If you have any questions, please submit a ticket on RMS.