The LiCAS FSI Subsystem Current Status and Initial Measurements John Dale for the LiCAS...

13
The LiCAS FSI Subsystem Current Status and Initial Measurements John Dale for the LiCAS Collaboration IOP HEP April 2008

Transcript of The LiCAS FSI Subsystem Current Status and Initial Measurements John Dale for the LiCAS...

Page 1: The LiCAS FSI Subsystem Current Status and Initial Measurements John Dale for the LiCAS Collaboration IOP HEP April 2008.

The LiCAS FSI Subsystem Current Status and Initial

Measurements

John Dale for the LiCAS Collaboration

IOP HEP April 2008

Page 2: The LiCAS FSI Subsystem Current Status and Initial Measurements John Dale for the LiCAS Collaboration IOP HEP April 2008.

Introduction• ILC Alignment Requirements• Linear Collider Alignment and Survey

(LiCAS) Rapid Tunnel Reference Surveyor (RTRS) – concept – prototype current status

• External and Internal FSI Subsystems– Frequency Scanning Interferometry (FSI)– Concept/design– Precision measurements

Page 3: The LiCAS FSI Subsystem Current Status and Initial Measurements John Dale for the LiCAS Collaboration IOP HEP April 2008.

ILC Alignment Requirements

• Alignment of the ILC effects collider luminosity• Main Linac has ~30km tunnel to survey • Needs to be surveyed quickly and effectively

– Reduce down time– Reduce labour cost

• Required Accuracy• 200 μm over 600m vertically (a betatron wavelength)• 500 μm over 600m horizontally

• Difficult using conventional surveying techniques

Page 4: The LiCAS FSI Subsystem Current Status and Initial Measurements John Dale for the LiCAS Collaboration IOP HEP April 2008.

LiCAS RTRS Concept

collider component

Tunnel Wall

Reconstructed tunnel shapes(relative co-ordinates)

wall markers internal FSI external FSISM beam

Page 5: The LiCAS FSI Subsystem Current Status and Initial Measurements John Dale for the LiCAS Collaboration IOP HEP April 2008.

LiCAS RTRS Prototype Current Status

• 3 car prototype under construction at DESY Hamburg

• Design COMPLETED

• Manufacture COMPLETED

• Assembly COMPLETED

• Commissioning COMPLETED

• Currently Entering Calibration Phase

Page 6: The LiCAS FSI Subsystem Current Status and Initial Measurements John Dale for the LiCAS Collaboration IOP HEP April 2008.

Frequency Scanning Interferometry

Tunable Laser

Reference Interferometer: L

Measurement Interferometer: D

Change of phase: ΔΦmeas

Change of phase: ΔΦref

time

IRef

time

Imeas Ref

MEAS

L

D

• Idea is adapted from the Michelson interferometer

• Instead of moving the mirror we change the frequency of the laser

Page 7: The LiCAS FSI Subsystem Current Status and Initial Measurements John Dale for the LiCAS Collaboration IOP HEP April 2008.

Retro Reflector

External FSI Sub-System

• System responsible for measuring wall markers• Unit has 6 FSI Lines• Note: These are bare fibres with no collimators

or beam splitters• All 6 fibres monitor the same retro reflector

LiCAS RTRS Unit

FSI Line

Wall

Retro Reflector

FSI Lines

Page 8: The LiCAS FSI Subsystem Current Status and Initial Measurements John Dale for the LiCAS Collaboration IOP HEP April 2008.

Initial Stability of External FSI Sub-System

RMS 1.71E-6

RMS 1.06E-6

RMS 1.54E-6 RMS 0.78E-6

RMS 1.70E-6

RMS 1.25E-6

Page 9: The LiCAS FSI Subsystem Current Status and Initial Measurements John Dale for the LiCAS Collaboration IOP HEP April 2008.

External Marker Reconstruction Using External FSI Lines

RMS 1.26E-6

RMS 0.57E-6

RMS 3.12E-6

Page 10: The LiCAS FSI Subsystem Current Status and Initial Measurements John Dale for the LiCAS Collaboration IOP HEP April 2008.

Internal FSI Sub-System

• Used to determine the distance from one unit to the next

• First Unit has 6 collimated fibres• Second Unit has 6 retro Reflectors• Each Fibre Monitors a different retro reflector

LiCAS RTRS UnitLiCAS RTRS Unit

Collimated fibreRetro Reflector

Page 11: The LiCAS FSI Subsystem Current Status and Initial Measurements John Dale for the LiCAS Collaboration IOP HEP April 2008.

Initial Stability of Internal FSI Sub-System

Page 12: The LiCAS FSI Subsystem Current Status and Initial Measurements John Dale for the LiCAS Collaboration IOP HEP April 2008.

Initial Stability of Internal FSI Sub-System

1

2 3

4

6 5

0.8 E-6

0.6 E-6

0.25 E-6

0.3 E-6

Units Have Rotated By : 16 μradian

RMS : 61nm

RMS : 45nmRMS : 70nm

RMS : 102nm

Page 13: The LiCAS FSI Subsystem Current Status and Initial Measurements John Dale for the LiCAS Collaboration IOP HEP April 2008.

Summary

• Prototype RTRS is constructed and entering calibration phase

• External FSI System is giving precision of 1-1.5 µm

• We have the ability to reconstruct wall marker positions to a precision of order 1.5µm

• Internal FSI System giving precision of 45 -100 nm