T H E B A N K S P R O J E C T M O N T H L Y R E P O R T : J A N U A R Y / F E B R U A R Y 2 0 1 7
Aerial view of The Banks in February 2017. Photo credit: McKendrick-Lee Photography.
2THE BANKS PROJECT MONTHLY REPORT: January/February 2017
PUBLIC PARTIES CONSTRUCTION
Public Services crew maintains Freedom Way.Snow plow clears January’s dusting of snow from surface recreation areas.
Daily commuters park their vehicles in the Block 24 garage. The Variable Message Signage project continues in Phase I design.
3THE BANKS PROJECT MONTHLY REPORT: January/February 2017
ECONOMIC INCLUSION: PHASE IIIA
Economic Inclusion information is available here: http://thebankspublicpartnership.com/wp-content/uploads/economic-inclusion-janfeb2017.pdf
Goal
Actual
30%
10%
30%
10%
85.6%
paid to SBE contractors
5,479,393
Minority workforce participation is 14.82% including minority female hours
Total female participation is
0.53%
SBE Participation
SBE Professional
Services Participation
26-county Consolidated Metropolitan
Statistical Area employee
residency
4THE BANKS PROJECT MONTHLY REPORT: January/February 2017
DEVELOPERView of the AC Hotel in February, corner of Freedom Way and Joe Nuxhall Way.
View of Developer’s Phase IIA and Public Parties’ Phase IIIA.
5THE BANKS PROJECT MONTHLY REPORT: January/February 2017
SAFETY
SCHEDULE
BUDGET
All Public Parties work remained on schedule.
The Public Parties project work remained within budget.
Phase IIIA budget expended totaled 82.9% of the $29.3 million total through February 28, 2017.
Since the Project’s inception in 2008 through December 31, 2016, The Banks Public Parties construction crews recorded 489,163 work-hours without a lost-time incident.
Developer’s Phase IIA construction crews worked a total of 682,241 hours without a lost-time incident from April 28 through December 31, 2016.
AC Hotel construction logged a total of 46,932 hours without a lost-time incident through February 28, 2017.
Public Parties’ Phase IIIA construction crews recorded a total of 48,645 work-hours without a lost-time incident July 1–February 28, 2017.
Budget information is available here: http://thebankspublicpartnership.com/ wp-content/uploads/budget-janfeb2017.pdf
6THE BANKS PROJECT MONTHLY REPORT: January/February 2017
PARKSCrossing the foot bridge in AdventurePlay area.
Ohio River stage at 44-feet. Cincinnati Parks team continues selection of a consultant for the marina project.
7THE BANKS PROJECT MONTHLY REPORT: January/February 2017
COMMUNICATIONS
@IBackTheBanks
Followers
1,319
43
Tweets
10
Development Media Mentions
14,225
Impressions
Media information is available here: http://thebankspublicpartnership.com/wp-content/uploads/media-summary-janfeb2017.pdf
118
Engagements
8THE BANKS PROJECT MONTHLY REPORT: January/February 2017
WHAT’S NEXT
Unseasonably warm winter weather? People enjoy the Rosenberg swings in Smale Park!
For more information: Phil Beck The Banks Project Executive (513) 946-4434 www.thebankspublicpartnership.com Published 3/20/17