Minutes of 136 th OCC Meeting Date: 18.09.2017 Eastern Regional Power Committee 14, Golf Club Road, Tollygunge Kolkata: 700 033

Transcript of th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4)...

Page 1: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes

of

136th OCC Meeting

Date: 18.09.2017 Eastern Regional Power Committee

14, Golf Club Road, Tollygunge Kolkata: 700 033

Page 2: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Eastern Regional Power Committee

List of participants is at Annexure-A.

PART A

Item no. 1: Confirmation of minutes of 135th OCC meeting of ERPC held on 24.07.2017 The minutes of 135th OCC meeting were uploaded in ERPC website and circulated vide letter dated 09.08.2017 to all the constituents. Members may confirm the minutes. Deliberation in the meeting Members confirmed the minutes of 135th OCC meeting.

PART B: ITEMS FOR DISCUSSION

Item No. B.1: Commissioning of new transmission elements in Eastern Region

In 118th OCC, it was informed that the network diagram of eastern region needs to be updated on regular basis on account of commissioning of new elements in the CTU as well as STU networks. OCC advised all the constituents to update the list of newly commissioned power system elements to OCC on monthly basis so that ERLDC/ERPC can update the network diagram on regular basis. New Generators/Transmission Elements commissioned/charged during July, 2017 as follows:

1. 400kV Kolaghat- New Chanditala (LILO of 400kV Jeerat- Kolaghat SC at New Chanditala) charged for the first time at 14:46Hrs of 03.07.17.

2. 400kV Jeerat-New Chanditala (LILO of 400kV Jeerat- Kolaghat SC at New Chanditala) charged for the first time at 16:42Hrs of 03.07.17.

3. New PPSP-Arambag Ckt-1 (LILO of 400kV PPSP-Arambag Ckt-1 at New PPSP) charged for the first time at 19:13Hrs of 15/07/17.

4. PPSP-New PPSP Ckt-1 (LILO of 400kV PPSP-Arambag Ckt-1 at New PPSP) charged for the first time at 18:49Hrs of 15/07/17.

5. 50MVAR Bus Reactor-1 at New PPSP Substation charged for the first time at 19:00Hrs of 15/07/17.

6. 400kV New Ranchi-New PPSP-DC charged for the first time as follows: a. Ckt-1: 20:08Hrs of 24/07/17. b. Ckt-2: 20:50Hrs of 24/07/17.

7. 400kV Gorakhpur-Motihari (DMTCL) ckt-2 (LILO of 400kV Barh-Gorakhpur ckt-2) charged for the first time at 22:54Hrs of 31/07/17.

List of newly commissioned elements of WBSETCL in July 2017 is enclosed at Annexure-B1. Constituents may update.

Minutes of 136th OCC Meeting held on 30th August, 2017 at ERPC, Kolkata

Page 3: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 2

Deliberation in the meeting Members noted. Item No. B.2: Status of projects funded under PSDF schemes In the PSDF review meeting, it was advised to RPCs to monitor the status of all the projects funded by PSDF. Therefore, constituents are requested to update the status of projects which are being funded by PSDF in the desired format.

SN Name of Constituent

Name of Project Date of approval from PSDF

Target Date of Completion

PSDF grant approved (in Rs.)

Amount drawn till date (in Rs.)

Status as updated in 135th OCC

1 WBSETCL Renovation & up-gradation of protection system of 220 kV & 400 kV Substations in W. Bengal

31-12-14 120.67 Cr 11.04 Cr. 95 % Supply Completed

2 WBSETCL Transmission System improvement of WBSETCL

3 OPTCL Renovation & Up-gradation of protection and control systems of Sub-stations in the State of Odisha in order to rectify protection related deficiencies.

10.05.15 10.05.17 162.5 Cr. 16.25 Cr + 8.91 Cr

Total contract awarded for Rs. 51.35 Cr

4 ERPC Creation & Maintenance of web based protection database and desktop based protection calculation tool for Eastern Regional Grid

17.03.16 20 Cr. 4.94 Cr. + 9.88 Cr.

1) Hardware supplied and installed. 2) SAT completed for pilot state 3) Protection database management software (PDMS) put in live w.e.f. 30.03.17. 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

5

BSPTCL

Renovation and up-gradation of 220/132/33 KV GSS Biharsharif, Bodhgaya, Fatuha, Khagaul, Dehri -on-sone & 132/33 kV GSS Kataiya

11/5/2015

Feb’2017

64.22 crore

23.68 crore

Project is on going. Contract awarded for Rs.71.37 Cr till date.

6 Installation of capacitor bank at different 35 nos. of GSS under BSPTCL

5/9/2016

18.88 crore

Approved (triparty agreement among NLDC, Govt. of Bihar & BSPTCL is in under process)

7 Renovation & up-gradation of protection and control system of 12 nos. 132/33 KV GSS under BSPTCL.

Recommendation of appraisal committee is awaited. Estimated cost 54.69 crore.

8 DVC Renovation and upgradation of control & protection system and replacement of Substation Equipment of 220/132/33 kV Ramgarh Substation

25.96 Tendering in process.

9 Renovation and upgradation of control & protection system including replacement of substation equipment at Parulia, Durgapur, Kalyaneshwari, Jamshedpur, Giridih, Barjora, Burnpur, Dhanbad and Burdwan Substation of DVC

140 Appraisal committee has recommended. It will be placed in next monitoring Committee meeting.

10 WBPDCL Implementation of Islanding scheme at Bandel Thermal Power Station

1.39 Cr Award placed to ABB. Material delivery by Dec, 17.

Upgradation of Protection and SAS

26.09 Approved by Ministry of Power

Page 4: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 3

11 OHPC Renovation and up-gradation of protection and control system of 4 nos OHPC substations.

22.35 Cr Tendering unde progress.

12a ERPC Training for Power System Engineers

The proposal was approved by Appraisal Committee. The approval from MoP, GOI is awaited.

12b Training on Power market trading at NORD POOL Academy for Power System Engineers of Eastern Regional Constituents

In 35th ERPC meeting, CE-NPC, CEA informed that grant has been allotted to Powergrid for installation of STATCOM but no update on the progress have been received from Powergrid. Powergrid informed that project has already been awarded and they will submit the details to PSDF Nodal Agency and NPC. In 131st OCC, Powergrid informed that they will submit the details shortly. In 134th OCC, it was informed that MoP has issued the letter for sanction of grant for Bandel islanding scheme and renovation & up-gradation of OHPC substations. In 135th OCC, WBSETCL informed that two schemes (installation of switchable reactor & shunt capacitor for improvement of voltage profile and Improvement of State Transmission System by Renovation & Modernisation of Transmission System for relieving congestion) have been approved by the PSDF monitoring committee. Respective constituents may update. Deliberation in the meeting Members updated the status as mentioned in above table. WBSETCL placed the details of two schemes approved by the PSDF monitoring committee as follows:

SN Name of Constituent

Name of Project Date of approval from PSDF

Target Date of Completion

PSDF grant approved (in Rs.)

Amount drawn till date (in Rs.)

Status as updated in 136th OCC

1 WBSETCL Renovation & modernisation of transmission system for relieving congestion in Intra-State Transmission System.

22-05-17

2 WBSETCL Installation of switchable reactor & shunt capacitors

22-05-17

Item No. B.3: OPERATIONAL LOAD FLOW STUDY FOR OFF-PEAK PERIOD (WINTER

LEAN PERIOD) In 128th OCC for lean off-peak load flow study, OCC finalized the date and time as follows

13.00 Hrs of 28th December,2016. 02:00 Hrs of 29th December,2016

In 130th OCC, PRDC informed that they will submit the report by end of March, 2017. The report is available at ERPC website (www.erpc.gov.in) Further OCC advised PRDC to carry out another load flow study in the first week of May, 2017 tentatively for 4th and 5th May, 2017 for 19:00 and 20:00 Hrs. Therefore, all utilities have to record data for four instances.

Page 5: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 4

OCC advised all the constituents to note the date and timings for recording the data and send it to ERPC/PRDC. In 133rd OCC, PRDC informed that load flow studies of Summer Peak Condition (4th and 5th May, 2017) for 19:00 and 20:00 hrs, they have received data from BSPTCL and CESC. In 134th OCC, PRDC informed that as per the data received from ER constituents and ERLDC SCADA snapshot the demand of 20 Hrs of 4thMay, 2017 is observed as more appropriate for Peak load flow analysis. OCC advised PRDC to carry out Peak load flow studies with the above data. Further, it was informed that the login ID and Password for access of PDMS has been issued to the respective members as nominated by the authorities. OCC advised constituents to verify their respective data and give their feedback. In 135th OCC, PRDC informed that load flow studies of Summer Peak Condition (4th and 5th May, 2017) for 19:00 and 20:00 hrs, some data is still pending from PGCIL and OPTCL. OCC advised DVC, PGCIL and OPTCL to submit the pending data to PRDC with a copy to ERPC at the earliest. Subsequently, PRDC informed that data from DVC and OPTCL has been received however; Powergrid data is yet to be received. PRDC may update. Deliberation in the meeting PRDC informed that the data is still pending from few substations. OCC advised PRDC to consider SCADA data for pending substations and advised to finalize and submit the report at the earliest. Item No. B.4: Status of UFRs healthiness installed in Eastern Region UFR Healthiness Certification for the month of July, 2017 has been received from OPTCL, CESC, JUSNL, WBSETCL, DVC, and BSPTCL. Members may note. Deliberation in the meeting Members noted. Item No. B.5: Healthiness of SPS existing in Eastern Region GMR, Vedanta, CESC, Chuzachen, Powergrid-Odisha & NTPC (TSTPS) have submitted the healthiness certificate for the month of July, 2017. Teesta-III, Jorethang, Dikchu, Chuzachen & Powergrid may submit the healthiness certificate for Rangpo SPS as decided in special meeting of 21.06.2017. JITPL, Powergrid (ER-II) may submit the healthiness certificate for July 2017. Deliberation in the meeting

Page 6: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 5

OCC advised Teesta-III, Jorethang, Dikchu, Chuzachen, JITPL & Powergrid to submit the healthiness certificate. OCC felt that healthiness certificate for SPS of 132 kV Muzaffarpur-Dhalkebar D/C line may also be submitted on monthly basis and advised Powergrid to submit the healthiness certificate in every OCC meeting. Item No. B.6: Furnishing of data for Merit Order Web Portal – CEA During the Power Minister’s Conference held on 3rd and 4th May 2017, at New Delhi, it was decided to develop a web portal/mobile app in about a month’s time with a view to having transparency in Merit order scheduling & dispatch and ensuring most economic system operation. In the conference Hon’ble Union Minister for Power requested all the States/UTs to submit the requisite data to CEA immediately. On this regard, it is to inform that POSOCO has developed the facility for online uploading of monthly & daily data related to Merit Order Dispatch Portal, by the SLDCs. NLDC (POSOCO) has already communicated via email to all the SLDCs, their respective User IDs & Passwords and the procedure for online filling & uploading of data. All the SLDCs to start submitting the above data to NLDC online immediately. In case of any doubt / clarification, Shri Harish Kr Rathour (NLDC) may be contacted at his Mobile No.9873918443. The procedure for online uploading of data for the portal is available in ERPC website. Subsequently, CEA vide mail dated 4th July 2017 informed that for the ease of user, import from excel (in a predefined format) facility have also been implemented. Users are requested to follow following steps to upload data through excel:

1) Login to MERIT web portal (www.meritindia.in/login). 2) Select any date and click on “GO” button. After this, list of all station will be visible for that

date with other information’s, if already filled. 3) Click on “Export Data in Excel” to export the file in excel. This would be a template file

which is to be used for uploading the data. a. Once you do not have any changes in the list of plants, this file can be used for

data uploading and on daily basis user need not to download excel format again. b. In case updation in list of station is required (State owned stations), same can be

modified through monthly page. At present this feature is disabled and very shortly it will be enabled.

c. Initial two row has station ID and name of station, which should not be disturbed and data will be uploaded based on these only. Any changes in it may lead to wrong data uploading.

d. User can select any file name to save and upload the data. e. Once you filled data click on “If you have data ready in Excel, CICK HERE to

upload”, select date for which you want to upload data, browse for the desired file and click on UPLOAD.

f. If entire file has not been uploaded, you will get the file which will show list of stations not uploaded.

4) If new station to be added for state, user can add through monthly data upload pages. Once, it has added new EXCEL template to be downloaded again in order to fill data for new station.

5) User who wants to fill data directly through web-portal, would now have option to sort based on the various fields, which will help in filling data. Users who wants to fill on-line need not to click on “If you have data ready in Excel, CICK HERE to upload”, they only select the date and simply click on “GO” button.

After submission of data, user can check directly on www.meritindia.in. It is once again requested to all to fill the monthly data (variable and fixed cost) because all visualization in first page is based

Page 7: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 6

on variable costs of the plants. In case of any doubt / clarification, Shri Harish Kr Rathour (NLDC) may be contacted at his Mobile No.9873918443. Members may comply. Deliberation in the meeting Members noted for compliance. Item No. B.7: Status of Islanding Schemes of Eastern Region

B.7.1. Status of commissioned Islanding Schemes in Eastern Region

At present, the following islanding schemes are in service:

1. CESC as a whole Islanding Scheme, CESC 2. BkTPS Islanding Scheme, WBPDCL 3. Tata Power Islanding Scheme, Haldia 4. Chandrapura TPS Islanding Scheme, DVC 5. Farakka Islanding Scheme, NTPC

In 108th OCC meeting, respective constituents agreed to certify that the islanding schemes under their control area are in service on monthly basis. In 134th OCC, JUSNL was advised to submit the healthiness certificate of the UFR and PLCC system related to Farakka islanding scheme at their end. The healthiness certificate for Islanding Scheme for July, 2017 has been received from CTPS, DVC, NTPC, JUSNL, BkTPS, Tata Power and CESC. Members may note. Deliberation in the meeting Members noted.

B.7.2. Bandel Islanding Scheme, WBPDCL As per the latest status available in PSDF web site the scheme was approved for an amount of Rs.1.39 crore by the Monitoring Committee on 10.04.2017. In 134th OCC, WBPDCL informed that MoP has issued the sanction letter for grant of PSDF. In 135th OCC, WBPDCL informed that order has been placed to ABB for implementation of Bandel islanding scheme. WBPDCL may update the latest status. Deliberation in the meeting Members noted. Item No. B.8: Request for LILO arrangement in 132kV Lalmatia-Dumka D/C line at loc.

89 for supplying construction power at 132kV level to 2x800 MW Thermal power plant at Godda by M/s Adani power--JUSNL

JUSNL vide letter dated 18-08-2017 informed that M/s Adani Power Jharkhand Ltd. (APJL) is setting up 2x800 MW thermal power plant at Godda. Availing power supply for construction M/s

Page 8: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 7

Adani Power has requested for construction of LILO of 132kV Dumka-Lalmatia D/c line at loc. 89 on cost deposit basis. Details are enclosed at Annexure-B8. 132kV Lalmatia-Dumka D/C line is covered under Farakka islanding scheme. Members may discuss. Deliberation in the meeting It was informed that the PLCC of 132kV Lalmatia-Dumka D/C line is being used under Farakka islanding scheme, so the LILO of both ckts might reduce the reliability of PLCC system and hamper the operation of Farakka islanding scheme. In view of above, OCC decided that LILO of one ckt of 132kV Dumka-Lalmatia D/c line may be done for meeting the requirement of construction power of 2x800 MW power plant of M/s Adani Power. Item No. B.9: Flexible jumpering arrangement for bypassing substations, prone to

inundation during monsoon, for ensuring continuity of important corridors and power evacuation from power stations--ERLDC

During the current monsoon season, quite a few substations in Eastern Region viz. Alipurduar(PG), Kishanganj(PG), Dalkhola(PG) and Motihari(DMTCL) had to be completely shutdown, due to massive waterlogging. Outage of Kishanganj S/Stn posed constraint in power evacuation of Sikkim generators and surplus power of NER while outage of Alipurduar S/stn weakened the inter-regional connectivity between ER and NER. Such substations typically have 2 nos incoming and 2 nos outgoing lines and lie either along a major intra/inter-regional corridor or along the evacuation route of a major power station. Under the above mentioned situation, it is desirable that continuity of the transmission corridor be maintained by directly connecting the incoming and outgoing lines, bypassing the inundated substation. However, such network re-configuration is possible only if facility for jumpering conductors at appropriate locations is already in place. This practice is already being followed at a number of locations in Western Region. Members may please identify the substations where the above proposed arrangement can be utilised for maintaining grid security under flood situations. Members may discuss. Deliberation in the meeting ERLDC explained that the flexible jumpering arrangement may be done for 400 kV Binaguri-Kisheenganj-N.Purnea D/C and 400kV Binaguri-Alipurduar-Bongaigaon D/C lines for bypassing the LILO points i.e. 400kV Kishanganj(PG) and Alipurduar(PG) S/s so that the same lines may be directly connected during the emergencies like flood situations at LILO points. The possibility may be explored as these elements are very important in terms of hydro power evacuation and long outages of these elements may endanger the grid security. The details are enclosed at Annexure-B9. The other such elements (LILOed at Dalkhola, Motihari (DMTCL) etc) may also be explored which are under threat during flood and other emergencies. OCC felt that such kind of bypassing arrangement will help the grid to improve the reliability during emergencies when substation is not available in service. OCC advised Powergrid to explore the possibilities of implementing such bypassing arrangement for above elements and for other important elements, if any. Powergrid agreed to do the survey and explore the possibilities.

Page 9: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 8

Item No. B.10: Concerned members may update the latest status.

B.10.1. Status of construction of 400 kV Sterlite-Jharsuguda D/C sections In 134th OCC, OPTCL updated the status as follows:

Activities Nos Status as updated in 35th TCC

Status as updated in 134th OCC Remarks

Tower Foundation 64 64 64 Completed Tower Erection 64 59 64 Completed

Stringing /OPGW Cabling & Testing

20.5 Km 9 km completed 16 km completed

Sub station Bay 2 Bay construction completed Testing going on

OPTCL informed that the construction of the dedicated line would be completed by 15th July, 2017 in all respects. Further, GRIDCO/OPTCL added that 7 No. of towers of 400KV Vedanta-Meramundali D/C line have been severely damaged due to whirlwind and cyclonic storm on 15-06-2017 night between Location No.7-0 to 8-0. As a result, GRIDCO could not avail State share of power through the said line and is solely dependent on LILO connectivity to avail IPP power from M/s. Vedanta Limited. In view of the above, GRIDCO/OPTCL requested that the disconnection of interim LILO connectivity scheduled on 01-07-2017 for M/s. Vedanta Ltd may please be deferred until the restoration work of Vedanta-Meramundali line and commencement of power supply to the State through this line.

After detailed deliberation, OCC agreed to extend the LILO connectivity till 15th July, 2017. It was also decided that the removal of LILO could be reviewed subject to the completion of dedicated line as per the latest schedule i.e. by 15th July, 2017. Accordingly, a special meeting to review the removal of LILO connectivity was held at ERPC on 14th July 2017 and the minutes are available at ERPC website. In 135th OCC, OPTCL updated the status as follows:

Activities Nos Status as updated in 35th TCC

Status as updated in 135th OCC Remarks

Tower Foundation 64 64 64 Completed Tower Erection 64 59 64 Completed

Stringing /OPGW Cabling & Testing

20.5 Km 9 km completed 17.8 km completed

Sub station Bay 2 Bay construction completed Testing going on

After detailed discussion, it was decided that Vedanta should complete the line construction and bay works by 30th July, 2017. It was also decided that the LILO of Vedanta Ltd may be disconnected from 16th August, 2017. OCC advised OPTCL to complete the line by 1st week of August 2017. Members may discuss.

Page 10: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 9

Deliberation in the meeting OPTCL informed that construction of dedicated 400 kV Vedanta- Jharsuguda line has been completed except 800m stringing which involves crossing of two 400 kV lines. The stringing work is being done manually because of severe rains. However, OPTCL assured that the line would be commissioned by September, 2017 in all respects.

OPTCL requested to extend the deadline for removal of LILO till the restoration of 400 kV Vedanta-Meramundali D/C line which is expected by 2nd week of September, 2017.

OCC advised OPTCL not to link the restoration of 400 kV Vedanta-Meramundali D/C line and stressed for early commissioning of 400 kV Vedanta-Jharsuguda line at least by ensuing TCC/ERPC meetings. With above view OCC referred the issue to TCC for further guidance. Special Protection Scheme(SPS) of Sterlite (VAL) –ERLDC Sterlite has installed capacity of 4X600MW (2400MW) with smelter load of More than 1000MW grid-connected plant. In case of loss of smelter load or evacuation path units might trip due to mismatch of load and generation. Sterlite had already implemented SPS to minimize the impact of such major load generation mismatch on the grid. In an earlier OCC meeting VAL agreed to share their presently implemented SPS details. But thereafter, VAL did not submit anything to ERLDC/ERPC. In 135th OCC, OPTCL was advised to submit the present SPS settings to ERPC and ERLDC within a week. SLDC OPTCL and Vedanta may update. Deliberation in the meeting OPTCL was advised to submit the present SPS settings to ERPC and ERLDC within a week.

B.10.2. Enabling of 3-Phase Auto Reclose at 132 kV North Bengal and Sikkim areas to minimize element outages due to transient faults -- Powergrid

During rainy season In North Bengal and Sikkim area, high element outages observed of 132 KV level. Mainly from past experience it is observed that 90% of the fault is of Single Phase to Ground fault and transient in nature. However as per general practice 132 KV level CB’s are of mechanically ganged and any single phase fault also causing tripping of all three phases. To make system more dynamic it is prudent to go for, three phase auto reclosure for any single phase Fault in the 132 KV lines. Only by introduction of A/R facility line availability may be increased in the tune of 90% i.r.o present situations. POWERGRID proposed to implement the same however other constituents as well as ERLDC may give respective views. Upon concurrence detailed road map for Implementation will be given. In 132nd OCC, Powergrid informed that in North Bengal and Sikkim area most of the time the 132 kV lines were tripping on transient fault and the system can be saved by implementing 3-phase auto-reclosure scheme. OCC discussed the matter in detail and agreed in principle for implementation of 3-pase auto-reclosure scheme for 132 kV lines. Further, it was decided that the implementation would start with North Bengal and Sikkim area. Further, OCC advised Powergrid to submit a report on the status of PLCC/telemetry, A/R facility etc. for both ends of each 132 kV lines of North Bengal and Sikkim area.

Page 11: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 10

In 134th OCC, Powergrid informed that the 3-phase auto-reclosure scheme for 132kV Rangpo-Gantok line will be implemented by July 2017. In 135th OCC, Powergrid informed that Rangpo end relay will be installed within a week and replacing the relay at Gangtok end will take time. OCC advised Powergrid to submit a report on the status of PLCC/telemetry, A/R facility etc. for both ends of each 132 kV lines of North Bengal and Sikkim area. Powergrid may update. Deliberation in the meeting OCC advised Powergrid to submit a report on the status of PLCC/telemetry, A/R facility etc. for both ends of each 132 kV lines of North Bengal and Sikkim area.

B.10.3. Status of Installation of STATCOM in Eastern Region In the 15th meeting of SCM it was agreed to install STATCOM in combination with mechanically switched Reactors (MSR) and Capacitors (MSC) and co-ordinated control mechanism of MSCs and MSRs at Ranchi, Rourkela, Jeypore and Kishanganj substations in Eastern Region as given below

The matter was again discussed in the 28th ERPC/TCC meeting held on 12th -13th September, 2014 at Goa, wherein, it was decided that POWERGRID may go ahead with implementation of the STATCOM project in Eastern Region with debt – equity ratio of 70:30 funding. The debt part should be refunded through PSDF and Equity Component (30%) to be funded by POWERGRID to be recovered through regulated tariff mechanism. CTU should initiate the process of availing fund from PSDF. POWERGRID may kindly inform tentative dates for commissioning of STATCOMs at the above mentioned locations. Deliberation in the meeting Powergrid updated the status as follows:

Sl No Location /Sub-Station of POWERGRID in ER

STATCOM -Dynamic Shunt Controller (MVAr)

Mechanically Switched Compensation Sl. (MVAr) Reactor (MSR)

Capacitor(MSC)

1 Rourkela ±300 2x125 2 Kishanganj ±200 2x125 3 Ranchi(New) ±300 2x125 4 Jeypore ±200 2x125 2x125

Sl No

Location /Sub-Station

of POWERGRID in ER

STATCOM -Dynamic Shunt

Controller (MVAr)

Mechanically Switched Compensation Sl.

(MVAr) Latest status Reactor

(MSR) Capacitor (MSC)

1 Rourkela ±300 2x125 Expected to complete by Mar 2018

2 Kishanganj ±200 2x125 Expected to complete by Jan 2018 3 Ranchi(New) ±300 2x125

4 Jeypore ±200 2x125 2x125 Expected to complete by Jun 2018

Page 12: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 11

It was informed that Powergrid is not placing any details about PSDF grant taken for this scheme in monthly OCC meetings. OCC advised Powergrid send the details to ERPC Secretariat within three days so that the same can be placed before 7th NPC meeting scheduled to be held on 8th September, 2017. Powergrid agreed.

B.10.4. Bus Splitting of Kahalgaon STPS Stage I&II, NTPC In 24th ERPC meeting held on 27.04.2013, ERPC advised NTPC to go ahead with the bus-splitting scheme as it is a technical requirement for safe, secure operation of the grid. In 32nd TCC, NTPC informed that they are going ahead with the implementation of Bus Splitting of Kahalgaon STPS Stage I&II and the implementation is expected to be completed by December, 2018. In 126th OCC, NTPC has given the present status as follows: 400/132kV Switchyard package - bid opened on 14.03.16. Awarded on 04.05.2016. Site levelling – Site levelling work has been completed. Transformer package and Shunt reactor– have been awarded.

In 35th TCC, NTPC informed that the work is in progress as per the schedule and the bus splitting will be completed by December, 2018. In 135th OCC, NTPC informed that the bus splitting will be implemented by December, 2018. NTPC may update. Deliberation in the meeting NTPC informed that the bus splitting will be implemented by December, 2018.

B.10.5. 220 kV inter-connecting lines of OPTCL with 400/220 kV Bolangir (PG), Keonjhar & Pandiabil S/s

PGCIL has already commissioned the 2x315MVA 400/220kV Bolangir S/s by LILOing of 400kV Meramandali-Jeypore S/C line and 400/220 kV Keonjhar S/s with an objective of supplying power from ER grid to its adjoining areas in Odisha. In 135th OCC, OPTCL updated the completion schedule of inter-connecting system as follows:

Sl. No. Name of the transmission line Completion schedule 1. 2x315MVA 400/220kV Bolangir S/s a. LILO of one circuit of Sadeipalli-Kesinga220 kV D/C

line at Bolangir S/S Only 7 towers left (Severe ROW problem). By Oct, 2017.

2. 400/220 kV Keonjhar S/S a. Keonjhar (PG)-Keonjhar (OPTCL) 220 kV D/C line By 2017. b. Keonjhar (PG)-Turumunga(OPTCL) 220kV D/C line By 2019. 3. 400/220kV Pandiabil Grid S/s: a. Pratapsasan(OPTCL)-Pandiabil(PG) 220 kV D/C line Dec, 2017.

OPTCL may update. Deliberation in the meeting Members noted.

Page 13: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 12

B.10.6. 220 kV inter-connecting lines of JUSNL with 2x315 MVA, 400/220 kV sub-stations at Chaibasa, Daltonganj & Dhanbad

In 135th OCC, JUSNL updated the latest status as follows: Sl. No. Name of the transmission line Completion schedule 1. Chaibasa 400/220kV S/s a. Chaibasa (POWERGRID) – Ramchandrapur (JUSNL) 220kV D/c commissioned on 25th

August, 2017 2. Daltonganj 400/220/132kV S/s: a. Daltonganj (POWERGRID) – Latehar 220kV D/c By Dec, 2017. b. Daltonganj (POWERGRID) – Garhwa 220kV D/c May, 2018 C Daltonganj (POWERGRID) – Daltonganj (JUSNL) 132kV D/c Dec, 2018 d Daltonganj (POWERGRID) – Chatarpur/Lesliganj 132kV D/c Matching with S/s 3. Dhanbad 400/220 kV S/s: Awarded under TBCB a. Dhanbad – Dhanbad (Govindpur) (JUSNL) 220kV D/c Matching with S/s

JUSNL may update. Deliberation in the meeting JUSNL updated the status as mentioned in above table.

B.10.7. 220 kV inter-connecting lines of WBSETCL with 400/220 kV, 2x315 MVA Alipurduar & 2x500 MVA Rajarhat sub-stations

In 135th OCC, WBSETCL updated the latest status as follows:

Sl. No. Name of the transmission line Completion schedule 1. 2x315MVA, 400/220kV Alipurduar sub-station a. Alipurduar (POWERGRID) – Alipurduar (WBSETCL)

220kV D/c (Twin moose) October 2017

2. 2x500MVA, 400/220kV Rajarhat --- a. Rajarhat-N. Town-3 (WBSETCL) 220 kV D/C line Matching b. Rajarhat-N. Town-2 (WBSETCL) 220 kV D/C line June, 2018 c. Rajarhat- Barasat (WBSETCL) 220 kV D/C line June, 2018

WBSETCL may update. Deliberation in the meeting Members noted. Item No. B.11: Restoration of PLCC system of important JUSNL ties

I) 220 KV Chandil –Santaldih line WBPDCL vide mail dated 24.07.2017 informed that single phase Auto Reclose feature has been put into service at 220 KV STPS-Chandil feeder at STPS end at 14:02 hrs. on 14.07.17.

II) 220 KV Ramchandrapur-Joda line In 130th OCC meeting, OPTCL informed that PLCC panels at 220kV Joda end will be commissioned within a week. JUSNL informed that the Ramchandrapur end is ready in all respect for implementation of PLCC. In 35th TCC, OPTCL informed that PLCC panels at 220kV Joda end will be commissioned by March 2017.

Page 14: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 13

In 131st OCC, WBPDCL informed that shutdown was proposed on 31st March, 2017 to complete the work. In 132nd OCC, OPTCL informed that the PLCC panels have been commissioned and will be put in service after completion of testing. In 133rd OCC, OPTCL informed that the panels will be commissioned by June, 2017. In 134th OCC, OPTCL informed that the panels will be commissioned by June, 2017. OCC advised OPTCL and WBPDCL to take the issue seriously and implement the auto reclose scheme at the earliest as CERC may take some suo motu action against non-completion of said PLCC links. In 135th OCC, OPTCL informed that the auto reclose scheme will be implemented within 10 days. JUSNL/WBPDCL/OPTCL may update. Deliberation in the meeting It was informed that the PLCC of 220 KV STPS-Chandil line was put into service w.e.f 14.07.2017. OPTCL informed that the PLCC system has been implemented on 27th July 2017. Item No. B.12: Third Party Protection Audit 1. Status of 1st Third Party Protection Audit:

The compliance status of 1st Third Party Protection Audit observations is as follows:

Name of Constituents Total Observations Complied % of

Compliance Powergrid 54 37 68.52 NTPC 16 14 87.50 NHPC 1 1 100.00 DVC 40 26 65.00 WB 68 27 39.71 Odisha 59 38 64.41 JUSNL 34 16 47.06 BSPTCL 16 5 31.25 IPP (GMR, Sterlite and MPL) 5 5 100.00

The substation wise status of compliance are available at ERPC website (Observations include PLCC rectification/activation which needs a comprehensive plan). In 118th OCC, all the constituents were advised to comply the pending observations at the earliest. All the STUs informed that most of the observations are related to funding from PSDF. DPRs have been submitted to PSDF committee. OCC advised all specially JUSNL and BSPTCL to send the revised DPRs at the earliest after clarifying the queries if any. Members may comply.

Page 15: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 14

Deliberation in the meeting Members noted. 2. Schedule for 2nd Third Party Protection Audit:

The latest status of 2nd Third Party Protection audit is as follows:

1) Jeerat (PG) Completed on 15th July 2015 2) Subashgram (PG) Completed on 16th July 2015 3) Kolaghat TPS (WBPDCL)- Completed on 7th August 2015 4) Kharagpur (WBSETCL) 400/220kV - Completed on 7th August 2015 5) Bidhannagar (WBSETCL) 400 &220kV Completed on 8th September, 2015 6) Durgapur (PG) 400kV S/s Completed on 10th September, 2015 7) DSTPS(DVC) 400/220kV Completed on 9th September, 2015 8) Mejia (DVC) TPS 400/220kV Completed on 11th September, 2015 9) 400/220/132kV Mendhasal (OPTCL) Completed on 2nd November, 2015 10) 400/220kV Talcher STPS (NTPC) Completed on 3rd November, 2015 11) 765/400kV Angul (PG) Completed on 4th November, 2015 12) 400kV JITPL Completed on 5th November, 2015 13) 400kV GMR Completed on 5th November, 2015 14) 400kV Malda (PG) Completed on 23rd February, 2016 15) 400kV Farakka (NTPC) Completed on 24th February, 2016 16) 400kV Behrampur(PG) Completed on 25th February, 2016 17) 400kV Sagardighi (WBPDCL) Completed on 25th February, 2016 18) 400kV Bakreswar (WBPDCL) Completed on 26th February, 2016 19) 765kV Gaya(PG) Completed on 1st November, 2016 20) 400kV Biharshariff(PG) Completed on 3rd November, 2016 21) 220kV Biharshariff(BSPTCL) Completed on 3rd November, 2016 22) 400kV Maithon (PG) Completed on 18th May, 2017 23) 132kV Gola (DVC) Completed on 17th May, 2017 24) 132kV Barhi (DVC) Completed on 18th May, 2017 25) 132kV Koderma (DVC) Completed on 18th May, 2017 26) 132kV Kumardhubi (DVC) Completed on 19th May, 2017 27) 132kV Ramkanali (DVC) Completed on 19th May, 2017 28) 220kV Ramchandrapur (JUSNL) Completed on 1st June, 2017 29) 400kV Jamshedpur (PG) Completed on 1st June, 2017 30) 132kV Patherdih (DVC) Completed on 31st May, 2017 31) 132kV Kalipahari (DVC) Completed on 30th May, 2017 32) 132kV Putki (DVC) Completed on 31st May, 2017 33) 132kV ASP (DVC) Completed on 30th May, 2017 34) 132kV Mosabani (DVC) Completed on 2nd June, 2017 35) 132kV Purulia (DVC) Completed on 1st June, 2017

The list of observations for the above sub-stations is already available at ERPC website (www.erpc.gov.in). Respective constituents are requested to comply and submit the report to ERPC for regular update. Members may note. Deliberation in the meeting Members noted. Item No. B.13: Inspection of Under Frequency Relays (UFR) The proposed UFR audit schedule is placed below:

Page 16: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 15

Sl No Proposed Date Substation/feeder inspected by the sub-group 1

Sep, 2017 220/132/33 KV Kalyaneswari of DVC

2 220/132/33 KV New Bishnupur of WBSETCL 3 132/33 KV Old Bishnupur of WBSETCL 4 Oct, 2017 BRS (Liluah S/Stn.) of CESC

Members may decide. Deliberation in the meeting Members noted. Item No. B.14: Preparation of crisis management plan for Cyber Security in Power Sector

in line with CERT-IN. The activity of the preparation of Crisis Management Plan for countering the cyber attacks and its implementation including the Mock Drills, audits etc. is being monitored by CEA regularly in line with crisis management plant of Ministry of Power. Power Utilities (including generation, transmission & distribution utilities) of eastern region are to furnish regularly the updated status to on the same to Chief Engineer, Distribution Planning & Development Division, CEA. NTPC communicated their activity of the preparation of Crisis Management Plan for countering the cyber attacks vide letter dated 2nd August, 2013. In 113th OCC, Member Secretary informed that during interaction with consultants of Grid Study Committee, NLDC agreed that they will plan for conducting workshops on crisis management plan for Cyber Security and few workshops will also be held in Eastern Region. CESC vide letter dated 22.08.15 had furnished their status of the preparation of Crisis Management Plan (CMP) for Cyber attacks in their system. Constituents may nominate. Deliberation in the meeting Members noted. Item No. B.15: Certification through BIS as per IS 18001:2007 to all generating/

transmission units. In 84th OCC meeting all constituents were requested to interact with BIS with intimation to ERPC and get certified as per CEA direction. As per the information received from the constituents the following generators certified with IS 18001:

All NTPC stations in Eastern Region Teesta, NHPC All OHPC generating units All CESC generating units Bandel TPS, WBPDCL Kolaghat Generating station, WBPDCL Bakreswar Generating station, WBPDCL Sagardighi Thermal Power Project, WBPDCL DGPC units

Members may note and update the status.

Page 17: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 16

Deliberation in the meeting Members noted. Item No. B.16: Data of Peak Demand – Submission of hourly power cut data The peak demand met figure calculated by CEA is a part of the monthly Power Supply Postion Report prepared by CEA, based on the data provided by five Regional Power committee (RPCs), who in turn collect the data from State / UTs and RLDCs. As per the present methodology being adopted for calculation of States /Regional peak demand met, the figure of peak demand met at any time in the month is taken as peak demand met for the month. For all India monthly peak demand met, the sum of five regional peaks met, which may occur at different points of time is taken. The above methodology has been reviewed and it has been decided with the approval of Chairperson, CEA that Peak demand Met and Peak Demand in the country should be based on hourly all India demand data. The matter was taken up with POSOCO for getting the hourly data of peak demand met for each month in respect of all the regions in the country in the first week of following month and they have assured to furnish the same. To calculate the demand, data of hourly scheduled and unscheduled power-cuts / load shedding is also required, which is not available with POSOCO. It is, therefore, requested that hourly figures of scheduled/ unscheduled power cuts/load shedding data may be collected from States / UTs and the same may be sent to CEA every month as per above schedule in the enclosed format, in spread sheet, so that hourly figures of peak demand can be calculated and incorporated in Power Supply Position report. This data for a month may kindly be sent in the first week of each month, along with PSP data, starting from the data for the month of February, 2015. The format for sending the data of hourly scheduled and unscheduled power-cuts / load shedding has already been circulated. In 110th OCC meeting, OCC advised all the concerned utilities (BSPTCL, JUSNL, OPTCL, WBSETCL & Sikkim) to send the data of hourly scheduled and unscheduled power-cuts / load shedding by mail to [email protected] latest by first week of each month. OCC advised all constituents to submit the data also to ERLDC ([email protected]). For the month of July, 2017 data has been received from OPTCL, CESC, DVC, WBSETCL, BSPTCL. JUSNL may submit. Deliberation in the meeting JUSNL submitted the data. Item No. B.17: Transfer capability determination by the states -- Agenda by NPC In order to ensure, safe and secure operation of the grid, the states should carry out the power system study for operational planning and power transfer capability through their respective transmission links with the rest of the grid. It was decided in the NPC meeting that to begin with, power system study for assessment of operational limits / power transfer capability for each state will be done by the concerned RLDC in association with concerned SLDC. Monthly TTC /ATC will be uploaded by the SLDCs at their respective websites and also communicated to concerned RLDC & NLDC subsequently. ATC/TTC declared by states for the month of August-2017 is given below:

Page 18: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 17

Sl No State/Utility TTC import(MW) RM(MW) ATC (Import) MW 1 BSPTCL 4395 91 4304 2 JUSNL 842 100 742 3 DVC 603 52 551 4 OPTCL 1000 72 928 5 WBSETCL 3660 300 3360 6 Sikkim

In 135th OCC, ERLDC informed that the ATC figure of WBSETCL will differ as the RM should be maximum unit size of WBPDCL which is 500 MW. Also the TTC figure will depend upon the inter-tripping schemes of Jeerat and Subhasgram S/s of WBSECTL. OCC advised WBSETCL to share the details of inter tripping scheme at Jeerat and Subashgram. Members may update. Deliberation in the meeting WBSETCL informed that details of inter tripping scheme at Jeerat have been sent to ERLDC. WBSETCL added that inter tripping scheme at Subashgram has been disabled. OCC advised WBSETCL to share the details of inter tripping schemes at other substations, if any. WBSETCL informed that they are having one more inter tripping scheme at Arambag the details of the same would be furnished to ERLDC. Item No. B.18: Long outage of important transmission elements

a) Non availability of Line Reactor of 400KV Malda-Purnea-I

In 123rd OCC, Powergrid informed that order has been placed for Reactor-1 and it will be commissioned by September, 2016. In 133rd OCC, Powergrid informed that the dispatch got delayed due to commercial issues and it will be dispatched by May, 2017 & commissioned by end of June, 2017. In 134th OCC, Powergrid informed that the reactor is reached at site and will be commissioned by end of July, 2017 subject to availability of shutdown. In 135th OCC, Powergrid informed that they are taking shutdown from today and the reactor will be commissioned by 15th August, 2017. Powergrid may update. Deliberation in the meeting Powergrid informed that the reactor will be commissioned by 10th September, 2017.

b) 400kV Patna-Kishengunj D/C

Tower collapsed at Loc.51 in Kankai river on 26.07.2016 and three nos towers at Loc no 128F/0, 128 G/0 and 128E/0 in Ganga riveron 01.09.2016. In 134th OCC, Powergrid informed that line will be restored by 15th July, 2017. OCC advised Powergrid to submit weekly progress to ERPC and ERLDC.

Page 19: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 18

In 135th OCC, Powergrid informed that line will be restored by 15th August, 2017. OCC advised Powergrid to submit weekly progress to ERPC and ERLDC. Powergrid may update. Deliberation in the meeting Powergrid informed that the line has been restored on 4th August, 2017.

c) 220 kV Waria – Bidhannagar-II The line is under outage wef 20.08.16 due to collapse of one no of tower collapse. In 133rd OCC, DVC informed that the line will be restored by 15th June, 2017. In 135th OCC, DVC informed that the line will be restored by 20th August, 2017. DVC may update. Deliberation in the meeting DVC informed that because of sever rains and difficult site conditions the restoration of the line would be delayed by another one month.

d) 50MVAR Bus Reactor-I at Farakka (alongwith main and tie bays) Under shutdown wef 31/05/16 for dismantling from old bay and re-installation in new bay in the dia of FSTPP GT#3. In 133rd OCC, Powergrid informed that the reactor will be in service by second week of June, 2017. In 134th OCC, Powergrid informed that the reactor will be in service within a week. In 135th OCC, Powergrid informed they are taking shutdown on 31st July 2017 to complete the work. Powergrid may update. Deliberation in the meeting Powergrid informed that the reactor has been put in service but differential protection is getting operated because of some problem in the scheme. Powergrid informed that the reactor would be brought into service after the rectification of the same which is expected by 10th September 2017. Item No. B.19: Replacement of old RTU in Eastern Region for reporting of RTU / SAS to

back-up control centre The matter for replacement of old RTU in Eastern Region for reporting to back up control centre has been discussed in a special project review meeting held on 14th February 2017 at ERPC & also on 35th TCC/ERPC meeting held on 24th / 25th February 2017, It was also mentioned that there would not be any service support for the old RTUs from POWERGRID after 15 years of operation period. It was accordingly advised to ERLDC to form a committee with POWERGRID as a nodal agency for assessment of such old RTUs vis-a-vis further action plan on replacement. It was also advised to submit a report in the next TCC/ERPC meeting.

Page 20: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 19

The matter for replacement of old RTU in Eastern Region for reporting to back up control centre has been discussed again in 19th SCADA O&M meeting held at ERLDC, Kolkata on 07th April 2017, wherein nomination of nodal person name from OPTCL, WBSETCL, DVC, BSPTCL, JUSNL, POWERGRID ERTS-1, POWERGRID ERTS-2, ERLDC, MPL &Jorethang has been collected. Nomination from NTPC all stations including Nabinagar, NHPC all stations, Dikchu, Teesta-III, Chuzachen, JITPL, GMR, Ind Bharat & APNRL are yet to be provided. ERLDC has already issued letter ref no: ERLDC / SCADA O&M / 2017/ dated 11.04.2017 for the same. It is requested to provide the nomination from these stations. OCC requested all the respective members to nominate their representatives at the earliest. In 133rd OCC, OCC advised NHPC to submit the nomination list at the earliest. ERLDC informed that a meeting has been scheduled on 09th June 2017 to discuss the above matter and requested all the constituents to send their nominated members to attend the meeting. In 134th OCC, ERLDC informed that the next meeting will be held in end of July 2017 and the report will be placed in August, 2017. In 135th OCC, ERLDC informed that the second meeting will be held on 4th August 2017 and the report will be placed by 10th August, 2017. As advised by TCC, a committee with POWERGRID as a nodal agency has been formed in Eastern Region for assessment of old RTUs and further action on replacement. Subsequently, two meetings were held at ERLDC, Kolkata on 09th June 2017 & 04th August 2017. A report has been finalized based on the suggestions received from the various committee members and the report is available in ERPC website (http://erpc.gov.in/report/). Members may note. Deliberation in the meeting Members noted and referred to TCC. Item No. B.20: Failure of RTU data with the outage of ICTs of Patna and Biharshariff

station --ERLDC It has been observed on several occasions that with the tripping of all the ICTs at Patna and Biharshariff station, RTU stopped reporting to ERLDC, after restoring these ICTs, data again started reporting. It is to be appreciated that real time SCADA data should not be getting interrupted for any eventuality of the grid. The same was informed to POWERGRID several times but it is yet to be implemented and confirmed by them. In 135th OCC, Powergrid informed that at Biharshariff the ULDC battery bank is under replacement. At Patna, the reason is yet to be identified. ERLDC informed that the same problem has been observed in other substations also and requested Powergrid to ensure uninterrupted power supply to RTUs. OCC advised ERLDC to submit the list of such substations to Powergrid. OCC advised Powergrid to ensure uninterrupted power supply to RTUs and send the updated status to ERPC.

Page 21: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 20

Members may update. Deliberation in the meeting ERLDC placed the details of substations where the communication and telemetry is getting effected due to power supply failures. The list is enclosed at Annexure-B20. Powergrid agreed to look and resolve. Item No. B.21: Shifting of communication links for PMUs reporting to ERLDC--ERLDC Presently, PMUs locations at Farakka, Talcher, Jamshedpur, Ranchi, Binaguri, Durgapur, Rourkela & Jeypore are reporting through Alcatel Mux using E1 – Ethernet convertor at both end. In case of fibre cut between Kasba to ERLDC, all the 8 nos PMUs data stopped reporting to ERLDC (happened on 16/May/2017 from 04:25 Hrs to 12:49 Hrs). There is no redundant path provided for these communication links. So, it is requested POWERGRID to shift these PMUs’ communication path / equipment so that the protection path of ULDC network would be used and this type of outage could be avoided. Communication link for Patna PMU is taken from PowerTel. It is also requested to POWERGRID that communication path may also be shifted for Patna PMU so that PowerTel communication could be removed. In 134th OCC, ERLDC informed that work is not yet completed. Powergrid informed that 8 PMUs communication system have been shifted to ULDC network. OCC advised ERLDC to send the details of requirement to Powergrid. Accordingly, ERLDC has sent the detailed requirement for shifting of communication link to POWERGRID ULDC on 14-07-2017. The same is attached at Annexure – B.21. In 135th OCC, Powergrid agreed to complete the work within a month. PGCIL may update. Deliberation in the meeting ERLDC has placed the updated status. The status is enclosed at Annexure-B21. Powergrid agreed to complete the work at the earliest. Item No. B.22: Update on status of telemetry CERC vide order dated 28.02.2016 on Petition No. 007/SN/2014 directed NLDC and respective RLDCs to update the status of telemetry every month at their respective websites and take up the issue of persistent non-availability of data from Generating Stations/substations at RPC meetings for appropriate action. In 120th OCC, ERLDC informed that every month they were updating the status and posting at ERLDC website. 134th OCC advised all the respective constituents to ensure the availability of telemetry data to ERLDC. Members may update. Deliberation in the meeting

Page 22: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 21

ERLDC presented the status of telemetry data availability. The latest status is enclosed at Annexure-B22. OCC advised all the respective constituents to ensure the availability of telemetry data to ERLDC.

a) Frequent failure of JITPL data to ERLDC: Real time SCADA data from JITPL is frequently failing (May-17: 24% & June-17 (up to 18th): 62%). It was observed that

Microwave terminal equipment at Talcher HVDC end is getting hanged quite frequently causing failure of real time data to ERLDC.

The direct line from JITPL to Angul 765/400 kV pooling station is available but real time SCADA data is yet to be diverted through this path.

The voice connectivity from JITPL to ERLDC is yet to be provided / integrated with Hot Line Voice Communication installed by M/s Orange.

The same was informed to JITPL several times verbally and through a letter vide ref no: ERLDC/SL/2017-18/621 dated: 3rd May 2017 but it is yet to be diverted / provided. In 134th OCC, JITPL representative was not available in the meeting. ERLDC informed that SCADA data from JITPL is frequently failing and JITPL is not responding even with repeated persuasions. OCC advised ERLDC to take suitable action against JITPL and stop entertainment of STOA application till SCADA data is restored. ERLDC informed that they will be constrained to stop all STOA transactions with effective from 00:00 Hrs of 01st August, 2017, upon unavailability of SCDA data at ERLDC. In 135th OCC, it was informed that the data is coming through Powergrid substations via PLCC link. Because of some commercial issues between JITPL and Powergrid the direct link is yet to be restored. OCC advised JITPL and Powergrid to settle the commercial issues bilaterally and restore the JITPL data availability to ERLDC. JITPL may update about the action plan for restoration of real time SCADA data, route diversion of data flow through POWERGRID Angul pooling station & voice connectivity integration with Orange exchange. JITPL and ERLDC may update. Deliberation in the meeting JITPL informed that presently they are communicating ERLDC with a radio link, which is an interim arrangement and is not reliable and they are trying hard to maintain it. However, they had planned to make PLCC system operational for uninterruptable communication to ERLDC. But Powergrid is not allowing them to shift NSK modem of PLCC system from Bolangir(PG) S/s which is the property of JITPL. JITPL added that they were in process of settling the commercial issues with Powergrid and requested Powergrid to cooperate. OCC took serious note of the issue and felt Powergrid should not interrupt in establishing the proper communication system for SCADA/telemetry data to ERLDC. OCC felt that Powergrid

Page 23: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 22

should not take up commercial issue by staking the grid security and advised Powergrid to take up the commercial issue separately.

b) Delay in restoration of 400kV JITPL-Angul line II on 04-08-2017 JITPL vide letter dated 09.08.2017 informed that they have received the charging code from ERLDC at 23:39 hrs on 04.08.2017. But the line could not be charged due to no communication from Angul S/s. After repeated pursuation the line was charged at 11:19 hrs on 05.08.2017. JITPL and Powergrid-Odisha may explain. Deliberation in the meeting JITPL informed that this is the third time Powergrid has delayed to charge the JITPL line because of pending commercial issues. ERLDC informed that till date no information was made available by Powergrid on delayed charging of the line. In OCC meeting also Powergrid failed to give satisfactory explanation on delayed charging of the line. OCC took serious note of delayed charging of the line and endangering the grid security by forcing a 2x600 MW power plant of JITPL connectivity through a single line. After detailed deliberation, OCC felt that at the stake of grid security, Powergrid should not take up the commercial issues. Further, OCC advised Powergrid to submit the reason for delayed charging at the earliest and decided to refer the issue to TCC. Item No. B.23: Less Generation/ Pumping at PPSP, WBSEDCL --ERLDC Since last few days, two units of PPSP were not running either in PUMP mode or Generation mode due to leakage in pipe lines between upper and lower dams. Due to outage of units of PPSP and lower side generation in other state generator, West Bengal is over drawing around 200 to 300 MW during peak hour. WBSEDCL, may please inform the status of the PPSP generation revival plan and their planning of load management during PUJA days if PPSP problem would not solved. Deliberation in the meeting WBSEDCL informed that the issue has been resolved and PPSP generators are in service. Item No. B.24: Despatch of power from Farakka-III under RRAS--ERLDC The matter of participation of Farakka – III under RRAS was deliberated and discussed in 35th Commercial Committee Meeting of ERPC, Where in NTPC, Farakka – III sought some time to sort out the commercial implications with their corporate office. NTPC, Farakka – III may please update the status. Deliberation in the meeting NTPC informed that Farakka Stage-III is ready to participate in RRAS.

Page 24: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 23

OCC advised FSTPS Stage-III to furnish the necessary formats (AS-1, AS-2 & AS-3) at the earliest to commence the participation in RRAS. Item No. B.25: Trans-National Exchange of Power ( NLDC Agenda) National Load Despatch Centre (NLDC) has been constituted as per Ministry of Power (MOP) notification, New Delhi dated 2nd March 2005 and is the apex body to ensure integrated operation of the national power system. One of the important function of NLDC as per clause 3(2) (i) of NLDC Rules, 2005 is to coordinate for trans-national exchange of power. This coordination function includes following activities:

1) First time charging 2) Operational Planning 3) Outage Coordination 4) Real Time Monitoring 5) Switching Coordination 6) Tripping Analysis 7) Maintaining records of power transfer

In this regard, it is to bring to the kind notice of the members that, NLDC is coordinating for trans-national exchange of power with Bhutan, Nepal and Bangladesh for 132 kV and above lines. However, in case of 132 kV lines between India and Nepal which are owned by erstwhile Bihar State Electricity Board (BSEB) are being operated without involving NLDC and ERLDC. These lines include 132 kV Balmiknagar (BSEB)-Surajpura S/C and 132 kV Kataiya (BSEB)-Duhabi S/C. 132 kV Raxaul – Parwanipur D/C is also expected to be commissioned shortly. In this regard, it is pertinent to mention here that 132 kV Rangia (Assam) – Motanga (Bhutan) line owned by AEGCL is also being operated by NLDC in coordination with Bhutan, Assam SLDC and NERLDC. Therefore, all the states of Eastern Region are requested to take following actions with reference to the 132 kV & above lines with neighbouring countries:

1) Provide first time charging documents and take consent from ERLDC/NLDC before first time charging in accordance with NLDC procedure for interconnection of new transmission element.

2) Provide real time data of the lines and all other elements impacting power transfer on these lines.

3) Take real time code from NLDC/ERLDC for switching. 4) Inform NLDC/ERLDC regarding the quantum and limit of power flow. 5) Inform OCC and take approval from OCC for all planned outages. 6) Inform and take consent/approval from NLDC/ERLDC regarding the planned and

emergency outages in accordance with NLDC Outage Planning procedure. 7) Inform NLDC/ERLDC regarding the details of tripping (including lines below 132 kV as

well). 8) Inform NLDC/ERLDC regarding the power transfer on all lines (including lines below 132

kV as well) with neighboring countries on daily basis. Members may discuss. Deliberation in the meeting OCC advised all the respective constituents to comply the above and share the above listed information to ERLDC and NLDC on regular basis. Item No. B.26: Installation of PMUs in Eastern Region under URTDSM project LOA for installation of PMUs in Eastern Region under URTDSM project was awarded to M/s Alstom on 15th January 2014. The contract has to be completed in all respect within 24 months

Page 25: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 24

from the award. The status of implementation may be informed since PMU data is very much important to real time shift operator for analyzing the security of the grid. OCC advised Powergrid to submit a report on latest status of implementation and advised to update the status on every OCC. In 131st OCC, Powergrid submitted the latest status of PMU installation. The updated status as furnished in 132nd OCC by Powergrid is given at Annexure-B.26. POWERGRID may update the status. Deliberation in the meeting Powergrid informed that space provided for PMU installation at Farakka is already occupied and requested NTPC to allot space for installation of PMU. NTPC agreed to look into. Powergrid pointed that they are facing some problem at 400 kV FSTPS & Kolaghat S/s for installation of PMUs. NTPC and WBPDCL agreed to co-operate with Powergrid for installation of PMUs. Item No. B.27: Status of Disturbance Recorder, Stand alone Event Logger and Time

Synchronization equipment. The status of DR/EL and GPS as updated in previous OCCs is enclosed at Annexure-B.27. Constituents are also requested to furnish their list of new DR/EL which are not included in the list. Members may update. Deliberation in the meeting Members noted. Item No. B.28: Status of Emergency Restoration System (ERS Towers) for Eastern

Region constituents

The latest status of Emergency Restoration System (ERS towers) as well as the future plan of procurement was given at Annexure- B.28. CEA vide letter dated 21.07.2017 requested to send the status of state-wise availability of ERS towers and requirement of ERS towers. Members may update the latest status. Deliberation in the meeting MS informed that CEA vide letter dated 21.07.2017 has sought the latest status on ERS. Therefore, OCC advised all constituents to send the updated status to ERPC secretariat vide mail ([email protected]). Item No. B.29: Time correction of SEMs in Eastern Region – Replacement of heavily

drifted SEMs

Page 26: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 25

The issue was discussed in 35th TCC/ERPC meetings and it was felt that the meters with severe drift greater than 10 min need to be replaced first and if replacement is done with Genus then readings are to be collected manually using Laptop till interfacing with AMR is completed. 35th ERPC advised Powergrid to replace the 10% of the heavily drifted SEMs with new Genus make meters and monitor the performance of the Genus meters. Powergrid should present this performance before constituents and subsequently the decision on replacement of the other time drifted meters will be taken up. Subsequently, ERLDC has prepared a list of such SEMs. In 133rd OCC, Powergrid informed that 22 meters were replaced except Purnea. ERLDC informed that the performance of 22 newly installed meters are satisfactory and suggested that all other meters can be replaced. OCC advised Powergrid to replace next 10% of heavily drifted meters as per the list. The list as shared by ERLDC is attached at Annexure-B.29. In 134th OCC, Powergrid informed that SEM at Purnea has been replaced and the replacement of SEMs as per the Annexure will be completed within 2 months. OCC advised Powergrid to give the schedule for replacement of SEMs to ERPC and ERLDC. In 135th OCC, Powergrid ER-II, and Powergrid-Odisha informed that they will replace the SEMs by 15th August, 2017. Powergrid ER-I informed that they are doing the time correction and SEMs are not required to be replaced. Powergrid/ ERLDC may update. Deliberation in the meeting Powergird informed that they will replace all the time drifted SEMs as prepared by ERLDC by September, 2017. Item No. B.30: Integration of Genus Make meter in AMR-- ERLDC In Eastern Region, order for procurement of 965 no of SEM’s was placed with M/s Genus Power. First Lot of the meters have already been delivered by Genus and 24 meters of Genus make meter has been installed in different substation in ER. Issue of Integration of Genus make meters in AMR system was discussed in meeting held with PGCIL, ERLDC, M/s Genus, & M/s TCS on 02.03.17 at ERLDC. M/s TCS informed that they have done the AMR integration test with Genus meter and informed that communication with existing Genus meter for AMR integration couldn’t be established. Moreover M/s TCS had informed that they will try the subsequent steps for communication with Genus meter and update ERLDC & PGCIL accordingly. In 132nd OCC, Powergrid informed that as per their communication with M/s TCS, integration of Genus meters in AMR system is possible, but it will take some more time to establish the communication. In 133rd OCC, Powergrid informed that it will take some more time and asserted it will be done by June, 2017.

Page 27: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 26

In 134th OCC, Powergrid informed that TCS is able to read the Genus make meter data however there are some issues related to baud rate of communication. Testing is in progress at Subashgram. It is expected to be completed by July, 2017. In 135th OCC, Powergrid informed that integration with Genus make meter is successful and some observations were found. TCS has resolved the observations related to software but issues related to Genus are still pending and is expected to be resolved shortly. Powergrid may please update the status. Deliberation in the meeting Powergrid informed that firmware needs to be upgraded which is under progress. After the firmware upgradation the integration of Genus make meters with AMR will be established by September 2017. Item No. B.31: Accounting of Tertiary Loading Arrangement at PGCIL s/station in ER Auxiliary consumption of PGCIL EHV AC sub stations are usually met from HT feeders of the state Discom. In few substations of PGCIL, auxiliary consumption is met through tertiary winding (as alternate supply for reliability). In 35th CCM, It was decided that the drawal of auxiliary power from tertiary winding by Powergrid substations would be treated as state drawl for inter-regional accounting. Powergrid and the states would make back to back commercial arrangements for this power. ERLDC requested Powergrid to submit the requisite information such as meter no, CTR, PTR, etc in respect of those meters and also make meter readings available ontime. Status of meter details and receipt of their data at ERLDC from Powergrid ER-I, ER-II and Odisha project is as below: ER-IS. No S/Station Loc ID Meter No Make CTR PTR Remarks Data Receipt

1 Banka ES-88 NP-7458-A L&T 50 33000/110 Yes2 Lakhisarai ES-94 NP-8870-A L&T 50 33000/110 Yes3 New Ranchi(765) ES-87 NP-8752-A L&T 50 33000/110 Yes4 Ara(220) ES-99 NP-8893-A L&T 50 33000/110 Yes5 Muzaffarpur ET-02 NP-5231-A L&T 1000 415/110 Yes6 New Purnea ES-98 NP-5249-A L&T 50 33000/110 Yes7 Pusauli ET-06 NP-8646-A L&T 50 33000/110 Yes8 Gaya(765) EM-99 NP-7472-A L&T 50 33000/110 No9 Kishanganj ES-90 NP-8876-A L&T 50 33000/110 No

10 Patna ES-89 ER-1285-A Genus 50 33000/110 No11 Biharshariff ET-01 NP-2355-A SECURE 1000 415/110 No12 Chaibasa Detail not rcvd No13 Jamshedpur Detail not rcvd No14 Ranchi(400/220) Detail not rcvd No

1 Angul ES-95 NP-5942-A L&T 1000 415/110 Yes3 Pandiabili ES-39 NP-7462-A L&T 1000 415/110 Yes4 Rangpo (33 kv TRF) ES-96 NP-7940-A L&T 1000 415/110 Yes5 Rangpo (11 KV AUX TRF) ES-97 NP-7941-A L&T 1000 415/110 Yes8 Sundergarh ES-93 ER-1019-A Genus 50 33000/110 Yes9 Baripada EM-69 NP-5909-A L&T 1200 400/110 Yes2 Bolangir ET-03 NP-7951-A L&T 50 33000/110 No6 Durgapur ET-04 NP-6024-B L&T 200 400/110 No7 Rengali ET-05 NP-0629-B Secure 200 415/110 No

10 Jeypore NP-5695-A L&T Detail not rcvd No11 Keonjhar NP-7921-A L&T Detail not rcvd No12 Maithon Detail not rcvd No13 Birpara Detail not rcvd No14 Siliguri Detail not rcvd No15 Subhashgram Detail not rcvd No

ER-II & Odhisa Project

Page 28: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 27

Powergrid may update. Deliberation in the meeting ERLDC informed that for Ara and Muzaffarpur they have received only two months data thereafter they are not receiving the SEM data. Powergrid was advised to check and resolve it. Powergrid updated that tertiary at Birpara and Siliguri were not in charged condition. The meter at Subashgram is defective and the same will be changed. Item No. B.32: Non scheduling of MTPS Stage-ll (2x195 MW) KBUNL vide letter dated 11-07-2017 informed that in special meeting held on 25.01.2017 at ERPC, Kolkata, it was agreed by all the parties that schedulirrg of MTPS Stage-ll shall be done by SLDC, Patna. ln this regard, KBUNL is sending daily declaration of availability, for MTPS Stage-ll, to SLDC, Patna with a specific remark as mentioned below: "Kindly forward this DC to ERLDC also for scheduling purpose of other eastern region beneficiaries of MTPS Stage-lI of KBUNL namely Jharkhand, West Bengal, DVC, GRIDCO & Sikkim". However, it is learned that SLDC, Patna is not co-ordinating with ERLDC to enable scheduling of other Eastern Region beneficiaries of MTPS Stage-ll. It is also pertinent to mention that JBVNL (Jharkhand) has signed LTA agreement with CTU. Further, JBVNL vide their letter ref. no. 909/ C.E. (C&R)/ Ranchi dtd. 22.06.2017 have contended that even after signing of LTA agreement their power is not getting scheduled i.e. they are not getting intimation from SLDC, Patna/ ERLDC regarding scheduling of MTPS Stage-ll. Moreover, other Beneficiaries of MTPS Stage-ll have also raised similar issues. ln view of the above, and in order to discharge the functions/duties assigned to SLDC under Electricity Act, 2003, BSPTCL was requested to co-ordinate with ERLDC for scheduling other Eastern Region beneficiaries of MTPS Stage-ll. In 135th OCC, JUSNL was advised to pursue with CTU for issuing the letter for LTA operationalisation for enabling the scheduling of JUSNL share from MTPS Stage-ll. JUSNL and KBUNL may update. Deliberation in the meeting It was informed that a petition (Petition No. 20/MP/2017) on a related issue was heard before CERC on 09.05.2017 and the final order is reserved till filling of additional information by the respondents. Item No. B.33: Non Receipt of meter Data -- ERLDC

1. Motipur & Samastipur in BSPTCL 220 KV Darbhanga(DMTCL)-Motipur (BSPTCL) D/C Line & 220 KV Darbhanga(DMTCL)-Samastipur (BSPTCL) S/C Line has already been charged and synchronized in April’17. Meter has been installed at BSPTCL end. BSPTCL was requested to send SEM data to ERLDC by every Tuesday. It has been seen that in spite of ERLDC request BSPTCL is not sending the data of Genus Meter installed at Motipur & Samastipur.

Page 29: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 28

In 133rd OCC, ERLDC informed that the Genus meter software is available in ERLDC website and it can be installed in Laptop. The SEM data can be downloaded through Laptop. BSPTCL agreed to send the SEM data after downloading the software. ERLDC informed that BSPTCL is sending data of Motipur end but Samastipur end data is still pending. In 134th OCC, BSPTCL requested for a Laptop for downloading the meter data. Powergrid informed that the software can be downloaded in desktop available at Substation. OCC advised Powergrid to allocate the Laptops to constituents. In 135th OCC, BSPTCL informed that Samastipur data would be send from tomorrow. BSPTCL may update. Deliberation in the meeting BSPTCL informed that the issue has been resolved. . Item No. B.34: Pollution mapping for Eastern Region

The Pollution Mapping work in ER was started with on-site measurement of ESDD and NSDD. OCC advised all the respective constituents to coordinate with Powergrid for online filling of measurement data. Powergrid updated the latest status as follows:

Scope (no. of locations)

Installed Locations

1st set of Measurements submitted

2nd set of Measurements submitted

3rd set of Measurements submitted

4th set of Measurements submitted

5th set of Measurements submitted

JUSNL 67 27 17 17 13 15 24 BSPTCL 59 52 40 29 4 3 0 WBSETCL 73 68 43 4 3 1 1 OPTCL 164 102 100 90 79 78 24 SIKKIM POWER 12 9 6 6 0 0 9 POWERGRID ER1 99 99 99 47 0 15 0 POWERGRID ER2 40 40 40 40 24 0 0 POWERGRID ODISHA 42 42 42 42 40 40 0 Powergrid added that they prepared an online format to submit the details of measurements. Powergrid requested to fill the Google form(https://goo.gl/6375HJ) for onward submission of measurements for better analysis of results. It is also requested to send the onward measurement results to following emails in addition to current email ids 1. [email protected] 2. [email protected] Members may update.

Page 30: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 29

Deliberation in the meeting Members noted. Item No. B.35: Mock Black start exercises in Eastern Region – ERLDC

i) The status of black start exercises The tentative schedule of black-start exercises for F.Y 2017-18 is as follows :

Sl no Name of Hydro Station

Schedule Tentative Date Schedule Tentative Date

Test-I Test-II 1 U.Kolab Last week of

May, 2017 30th May 2017 Last Week of

January2018

2 Maithon

1stweek of June 2017

Completed on 04.04.17

1stWeek of February2018

3 Rengali 2ndweek of June 2017

November 2017 Last week of November 2017

4 U. Indarvati 3rdweek ofJune 2017

November 2017 2ndweek of February2018

5 Subarnarekha 1stweek of October 2017

1stweek of January2018

6 Balimela 3rdweek of October 2017

1stweek of March 2018

7 Teesta-V 2ndweek of Nov 2017

Last week of February2018

8 Chuzachen Last Week of May2017

May, 2017 January2018

9 Burla Last Week of June 2017

1st week of July, 2017

Last week of February2018

10 TLDP-III 1stWeek of June 2017

After Mansoon 2ndWeek of January2018

11 TLDP-IV Last Week of June 2017

After Mansoon 1stWeek of February2018

12 Teesta-III

Members may update. Deliberation in the meeting Members noted. Black start and FGMO/RGMO operation of Purulia Pump Storage Project (PPSP) units of WBSEDCL – ERLDC In the 130th OCC Meeting held on 17th February, 2017 WBSEDCL informed that they had contacted OEM Toshiba for feasibility of black start and OEM required to conduct a simulation with CEA recommendations. OCC advised WBSEDCL to expedite the process as the time extension granted by CERC for making black-start and FGMO/RGMO operational in PPSP units, was going to lapse by March.2017. In 135th OCC, WBSEDCL informed that they have not received any comments from OEM.

Page 31: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 30

ERLDC informed that making black-start functional at PPSP has therefore become uncertain as it is completely dependent on the OEM, who is not responding to the requirement of WBSEDCL. It may be noted that WBSEDCL had already sought 6 month time from CERC and no progress could be made even after expiry of 11 months. Since such delay and uncertainty in execution of the work is ultimately affecting the security of Eastern Regional grid, matter may escalated to MOP / CEA for hiring the professional service of competent vendors / consultants so that black-start capability at PPSP could be operationalised within a definite target date. WBSEDCL may update. Deliberation in the meeting WBSEDCL informed that they are putting all the efforts to implement the black start facility for PPSP. Testing of DG sets meant for Black start

Test run report of DG sets for blackstart has been received only from Odisha hydro units. The test run reports of other machines may be sent to [email protected] and [email protected]. Constituents may kindly ensure compliance. Deliberation in the meeting Members noted. Item No. B.36: Restricted Governor /Free Governor Mode Operation of generators in ER The latest status of units of ER under RGMO is available at ERPC website (http://www.erpc.gov.in/) under Operation>Important data. In 126thOCC requested all the generators to share their governor response with ERLDC in the group (https://in.groups.yahoo.com/neo/groups/ er_gov_respons/info). Members may also send their request for joining the group to [email protected]. ERLDC had uploaded the unit wise responses in the group “[email protected].” i.r.o the following events for monitoring of RGMO response of generator:

(1) On 21.07.17, at 21:26 Hrs Genration loss of about 1031 MW Occurred at Korba STPS due to tripping of evacuation lines.

(2) On 02-03-17, 01:58 hrs, Unit I & II at Krishnapattanam tripped. Generation loss 1085 MW ERLDC may update. Deliberation in the meeting ERLDC informed that as per CERC order dated 31st July 2017 in Petition No. 84/MP/2015, the commission shall closely watch the primary response of ISGSs as reported by POSOCO/NLDCs from September, 2017. ERLDC presented the details, which is enclosed at Annexure-B36A. CERC vide their letter dated 05-06-17 desired to know the present status of RGMO/FGMO response of all eligible thermal and hydro units. Accordingly ERLDC vide letter no.ERLDC/SS/FGMO/2017 dated 07-06-17 requested all concerned power stations and SLDCs to provide updated status of FGMO/ RGMO of units under their control. 134th OCC advised all the constituents to go through the list and update the latest status vide mail to ERPC/ERLDC.

Page 32: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 31

ERPC vide letter dated 6th July 2017 advised all the generators to update the latest status of RGMO/FGMO. Updated status of the RGMO/FGMO of ER generators are enclosed in Annexure-B36B. The list is also available in ERPC website. Members may update. Deliberation in the meeting Members noted for compliance. Item No. B.37: Status of state owned units under long outage --ERLDC Numbers of units of state sector were decommissioned during recent days/months. As per the letter received from DVC on date 08th August, 2017, CTPC U#2, BTPS U#1&2 are under the process of de-commissioning as they have crossed their useful life and compliance of prevailing pollution norms is not feasible and CTPS U#1 is already de-commissioned. All state sectors may update the latest status of units under de-commissioned or in the process of de-commissioning. Deliberation in the meeting It was informed that DVC has already furnished their status. OCC advised West Bengal and Odisha generating units to submit their status to ERLDC and ERPC. Item No. B.38: Reactive Power performance of Generators and optimisation of

Transformer tap Generating stations have been monitored for certain sample dates in the month of June,17.

Power Plant Max and Min Voltage observed for July 17 (KV)

Date for monitoring (July 17)

Farakka STPS 424,400 1,2

Khalgaon STPS 423,404 9,27

Talcher STPS 409,396 2,21

Teesta 416,393 3,11

Bakreshwar TPS 413,400 2,16

Kolaghat TPS 427,398 2,16

Sagardighi TPS 425,406 2,27

MPL 420,407 1,27

Mejia-B 423,411 1,27

DSTPS 428,412 16,18

Adhunik TPS 426,410 2,21

Barh 439,411 9,27

JITPL 415,404 21,23

GMR 415,405 13,28

HEL 434,397 9,27

Kodarma 425,402 9,27

Page 33: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 32

ERLDC may present the reactive performance. Deliberation in the meeting ERLDC presented the performance of the generators for July, 2017 and informed that the performance of Mejia #7&8, Barh unit #4&5 and Haldia unit #1&2 were not satisfactory. Presentation is enclosed at Annexure-B38. OCC advised NTPC and CESC to take the corrective actions to improve the performance. a) Schedule for reactive capability tests The following was status of regarding reactive capability testing:

a. Adhunik TPS(both units) –Yet to be confirmed by Adhunik b. JITPL(both units) – After the emergent inspection of OEM(BHEL) c. Barh TPS – December 2017 d. Raghunatpur – by December 2017 e. GMR (Three units) f. Haldia TPS

Members may update. Deliberation in the meeting Members updated the status as mentioned above. b) Transformer tap optimisation of Eastern Region :

1. Present tap position of 220/132KV, ICTs at Malda is 10(ten). Based on operational study, the voltage may be optimised by changing transformer tap from 10 to 8.

2. Tap position of 220/132KV, 160MVA ICT at Lalmatia is set to 5(five). For improvement of 132kV voltage, the tap position may be changed from 5 to 7(Seven).

Members may discuss. Deliberation in the meeting After detailed deliberation OCC advised to change the tap of 220/132 kV Malda ICTs from 10 to 8 and Lalmatia ICT tap on later stage.

PART C:: OPERATIONAL PLANNING Item no. C.1: ER Grid performance during July, 2017 The average consumption of Eastern Region for July - 2017 was 394 Mu. Eastern Region has achieved record maximum energy consumption of 429 Mu on 17th July-17. Total Export schedule of Eastern region for July - 2017 was 2529 Mu, whereas actual export was 2399 Mu. ERLDC may present. Deliberation in the meeting ERLDC has presented the performance of the Eastern Region grid during July 2017. Presentation is enclosed at Annexure- C1.

Page 34: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 33

Item no. C.2: OPERATION OF HYDRO POWER PROJECTS IN PEAKING MODE

CEA vide letter dated 18.07.17 informed that POSOCO has carried out operational analysis of various hydro stations in the country and observed that despite 40.6 GW of peaking hydro capacity only about 33 GW peak generation is carried out on all India basis. According to POSOCO, this is on account of a number of hydro stations, particularly in state sector, which are not being operated in peaking mode. In order to examine the above observation, a Sub-committee has been constituted by the MoP under Chiarperson, CEA with heads of POSOCO, NHPC, SJVN & THDC as members and Director (H), MoP as the Member Convenor. The Sub-Committee has held three meetings with the concerned hydro generating stations and concluded that there is scope for about 2000 MW additional power generation from hydro stations during peak hours. It has been desired by the Chairperson that the matter of utilization of hydro stations in peaking mode be made a regular agenda item for discussion at the monthly OCC meetings while discussing operational planning for the month ahead and analyzing the operation in the previous month. In 135th OCC, ERLDC presented the performance in peaking mode for hydro generations in Eastern Region. OCC decided to review the performance of hydro generators in peaking mode in monthly OCC meetings As informed by ERLDC, during review it was observed numbers of hydro units of state sectors were under outage due to various reasons and also some units were running at de-rated capacity compare to their installed capacity. In this regards, it is requested to all State (through SLDC), ISGS and IPP owned hydro generators to update the status of the hydro units on bar, hydro units under outage along with reason to ERLDC and ERPC on daily basis in the following format. Hydro units which are unable to generate as per installed capacity may be intimated to RLDC and RPC on monthly basis. Hydro unit outage status: S.No Station Location Owner Unit No Capacity Reason(s)

of Outage Outage Date

Outage Time

Expected Revival Date

1. 2. n.

Hydro Units running at De-rated Capacity: S.No Station Location Owner Unit No Capacity De-Rated

capacity Reason of operation at De-rated

1. 2. n.

Members may update.

Deliberation in the meeting ERLDC presented the performance of Hydro generators for July 2017. Presentation is enclosed at Annexure-C2.

Page 35: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 34

OCC advised all the hydro generators to submit the requisite data to ERLDC and ERPC in the prescribed format on regular basis. Item no. C.3: Anticipated power supply position during September’17 The abstract of peak demand (MW) vis-à-vis availability and energy requirement vis-à-vis availability (MU) for the month of September’17 were prepared by ERPC Secretariat on the basis of Provisional LGBR for 2015-16 and feedback of constituents, keeping in view that the units are available for generation and expected load growth etc. is at Annexure-C.3. Members may confirm. Deliberation in the meeting Modified anticipated power supply position for the month of September, 2017 after incorporating constituents’ observations is given at Annexure-C.3. Item no. C.4: Shutdown proposal of transmission lines and generating units for the

month of September’17 Members may finalize the Shutdown proposals of transmission lines and generating stations for the month of September’17 as placed at Annexure-C.4. ERLDC may place the transmission line shutdown. Members may confirm. Deliberation in the meeting Approved maintenance programme of generators and transmission elements for the month of September, 2017 is given at Annexure-C.4. As informed by NTPC, unit 5 shutdown of NTPC Barh was scheduled from 17/8/2017. During this shutdown, originally boiler and generator works were to be undertaken. But based on failure experience in some latest 660 MW turbines of BHEL recently, they have recommended for overhauling and inspection of LP turbine also. As this recommendation was received very late, despite our best effort, the necessary logistic arrangement is delayed by 3-4 days. Now we propose to shutdown this unit on 20/08/2017, 24:00 hrs. The shutdown duration will be for one month (30 days). Unit is planned to be brought back on 20/09/2017. Members may note. Deliberation in the meeting Members noted. Item no. C.5: Prolonged outage of Power System elements in Eastern Region

(i) Thermal Generating units: Sr No Generating Station UNIT

NO CAP(MW) REASONS FOR OUTAGE OUTAGE DATE

1 APNRL 1 270 PA FAN TRIPPED 18-Aug-17 2 JITPL 1 600 COAL SHORTAGE 5-May-17 3 RAGHUNATHPUR 2 600 FURNACE PRESSURE

HIGH 9-Aug-17

4 PATRATU TPS 10 110 OVER HAULING 26-Jan-17 5 KOLAGHAT 6 210 STATOR EARTH FAULT 11-Jun-17

Page 36: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 35

6 BOKARO B 3 210 COAL SHORTAGE 24-Jun-17 7 MEJIA 4 210 COAL SHORTAGE 23-Jul-17 8 MEJIA 2 210 COAL SHORTAGE 25-Aug-17 9 BOKARO A 1 500 STATION TRANSFORMER

TRIPPED 15-Aug-17

10 TENUGHAT 1 210 COAL SHORTAGE 25-Jul-17 11 SANTALDIH 5 250 ROTOR EARTH FAULT 30-Apr-17 12 DSTPS 1 500 TESTING OF HOUSE LOAD

OPERATION 11-Jul-17

13 SAGARDIGHI 4 300 AUXILIARY FAILURE 17-Jul-17

(ii) Hydro Generating units: Sr No Generating Station UNIT

NO CAP(MW) REASONS FOR OUTAGE OUTAGE DATE

1 BALIMELA 2 75 Due to flood 18-08-17 2 BALIMELA 8 75 Due to flood 18.08.2017 3 BALIMELA 7 75 Generator Stator Problem 16.04.2017 4 RENGALI 5 50 Hoist gate problem 21.03.2017 5 U.KOLAB 3 80 Generator interturn fault 19.04.2017 6 TLDP-III 1 33 agitation / law and order issue 12.07.2017 7 TLDP-III 2 33 agitation / law and order issue 12.07.2017 8 TLDP-III 3 33 agitation / law and order issue 12.07.2017 9 TLDP-III 4 33 agitation / law and order issue 12.07.2017 10 TLDP-IV 1 40 agitation / law and order issue 13.07.17 11 TLDP-IV 2 40 agitation / law and order issue 13.07.17 12 TLDP-IV 3 40 agitation / law and order issue 13.07.17 13 TLDP-IV 4 40 agitation / law and order issue 13.07.17

(iii) Transmission elements Transmission Element / ICT Outage

Date Reasons for Outage 220 KV BALIMELA - U' SILERU 27.04.15 LINE IDLE CHARGED FROM UPPER SILERU

END AT 12:42 HRS OF 25.01.17 220KV WARIA - BIDHANNAGAR-II 10.09.16 LINE UNDER B/D, TOWER COLLAPSED AT LOC

NO 28 400 KV STERLITE - MERAMUNDALI D/C 15.05.17 TOWER CROSS ARM DAMAGED

220 KV THERUVALI-INDRAVATI-III 16.07.17 TOWER COLLAPSE At loc 69 and loc70 due to

flood 220 KV THERUVALI-INDRAVATI-IV 16.07.17 TOWER COLLAPSE At loc 69 and loc70 due to

flood 220 KV Kishanganj(PG)-Kishanganj (B) I 13.08.17 HAND TRIPPED DUE TO FLOOD IN

KISHANGANJ SWITCHYARD 220 KV Kishanganj(PG)-Kishanganj (B) IV 13.08.17 HAND TRIPPED DUE TO FLOOD IN

KISHANGANJ SWITCHYARD 400KV MOTIHARI-BARH-I & II 14.08.17 24 NO OF TOWERS IN GANDAK RIVER WHERE

WATER LEVEL IS HIGH (Reported as per Clause 5.2(e) of IEGC)

Members may update.

Page 37: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 36

Deliberation in the meeting Members noted. Item no. C.6: Status of commissioning of generating station and transmission elements New generating units:

S.No. Power Plant Plant Size Expected date

New transmission elements:

Sl No. Name of Element Expected date 1 400kV Rajarhat-Purnea D/C (with LILO of one circuit each at

Farakka and Gokarno)

2 Augmentation of 400kV Farakka-Malda D/C with HTLS conductor 3 400kV Ind-Bharath-Jharsuguda D/C 4 400kV Talcher-Bramhapur-Gazuwaka D/C 5 400kv Talcher-Rourkella(2nd D/C-Quad) 6 400kV Sterlite-Jharsuguda D/C 7 765kv Anugul-Srikakulum D/C 8 400kV Sasaram-Daltonganj D/C &Daltonganj S/Stn 9 400 kV Ranchi-Raghunathpur D/C 10 220 kV TLDP-IV – NJP ckt-2 11 220 kV Bidhansai-Cuttack D/C 12 220kV Gola- Ranchi

Members may update. Deliberation in the meeting Members noted.

PART D:: OTHER ISSUES

Item no. D.1: UFR operation during the month of July’17 System frequency touched a maximum of 50.23 Hz at 08:00 Hrs of 06/07/17 and a minimum of 49.69 Hz at 20:56 Hrs of 08/07/17 and 18:59 Hrs of 19/07/17. Hence, no report of operation of UFR has been received from any of the constituents. Members may note. Deliberation in the meeting Members noted. Item no. D.2: Non-compliance of directions issued by SLDC

Page 38: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 37

Vide clause no 5.5.1.(c)(h) of IEGC, non-compliance of SLDC directions by SEB/Distribution licenses/bulk consumers to curtail overdrawal are to be reported to ERLDC for incorporating the same in weekly report to be prepared and published by ERLDC. All SLDCs are to inform ERLDC the instances of non–compliance of SLDC directions by SEB/Distribution licenses/bulk consumers to curtail overdrawal, within two days after the day of operation. No report from any constituent has yet received. Hence, ERLDC would be considering ‘Nil’ report for all constituents for July’17. Members may note. Deliberation in the meeting Members noted. Item no. D.3: Grid incidences during the month of July, 2017 Sr No

GD/ GI

Date Time S/S involved

Affected System

Summary Load loss (MW)

Gen loss (MW)

1 GD-I

03/07/2017

18:32 Lalmatia JUSNL Total loss of power supply occurred at Sahebgunj and Lalmatia after

hand tripping of all 132 kV & 220 kV lines connected to Lalmatia S/S due

to DC failure at Lalmatia.

76 0

2 GD-I

03/07/2017

18:53 Patna ISTS On mal-operation of Bucholtz relay due to ingress of moisture through cables during rain, 400/220 kV 500

MVA ICT - I at Patna tripped at 18:53 hrs. Prior to the tripping, total loading of the ICTs was 571 MW. After tripping of ICT - I, loading at

other 400/220 kV ICT (315 MVA) at Patna increased to 430 MW. At 19:14 hrs, 400/220 kV ICT - II

tripped due to overload resulting load loss at surrounding area.

536 0

3 GD-I

13/07/2017

20:18 Bokaro-B DVC At 20:18 hrs, all 220 kV feeders along with 400/220 kV ICTs

(connected to 400 kV Bokaro A bus) and 220/132 kV ATRs at

Bokaro B tripped due to bus bar protection operated for R phase PT

failure at 220 kV Bokaro B main bus. Heavy thundering was

reported at Bokaro end.

201 0

4 GD-I

15/07/2017

09:40 Lalmatia JUSNL 132 kV Kahalgaon(BSPTCL) - Lalmatia S/C tripped at 09:50 hrs on E/F causing load loss of 22 MW at

Sahebgunj. 132 kV Kahalgaon(NTPC) - Lalmatia S/C also tripped at the same time from

Lalmatia on E/F. 132 kV Kahalgaon(BSPTCL) - Lalmatia S/C

& 132 kV Kahalgaon(NTPC) - Lalmatia S/C tripped again at 13:54

hrs on E/F.

22 0

5 GD-I

16/07/2017

00:30 Teesta III ISTS 400 kV Teesta III - Dikchu S/C (tripped only from Teesta III end)

and Unit #I at Dikchu tripped due to operation of cable differential

protection (B phase current 1.1 kA at Teesta III) resulting generation

0 100

Page 39: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 38

loss at Unit # II at Dikchu due to loss of evacuation path.

6 GD-I

24/07/2017

15:56 Teesta III ISTS 400 kV B/C at Teesta III tripped on receipt of SPS signal resulting in tripping of unit I, II & IV. However both circuits of 400 kV Rangpo -

Binaguri D/C were in service. Flow in 400 kV Rangpo - Binaguri D/C was around 800 MW/Ckt. Rangpo personnel verbally confirmed non increment of TX counter dedicated

for transmitting SPS signal.

0 670

7 GD-I

24/07/2017

19:11 Teesta III ISTS Due to Rotor Earth Fault in Unit #5, there was a dip in DC Voltage

during Unit 5 Start-up (DC Field Flushing) leading other

synchronized units to No Load Operation.

0 420

8 GD-I

27/07/2017

10:08 Teesta III ISTS At 10:08 hrs 400 kV Rangpo – Binaguri – II tripped due to B-N fault. (DEF, F/C at Rangpo and DT received at Binaguri). After tripping of circuit – II, power flow in 400 kV Rangpo – Binaguri – I became more than 850 MW (1700 MW approx.) and SPS – I (generation reduction at Teesta III, Dikchu, JLHEP and Chujachen.) got activated resulting tripping of one unit at each power plant at Chujachen, JLHEP and Dikchu. Due to non-tripping of any unit at Teesta III, power flow in 400 kV Rangpo – Binaguri – I remained more than 850 MW for more than 500 ms and SPS – II got activated resulting tripping of 400 kV Teesta III – Rangpo S/C followed by tripping of remaining units at Teesta III and Dikchu due to loss of evacuation path.

0 1070

9 GD-I

31/07/2017

11:24 Tarkera OPTCL B phase isolator drop jumper of 220 kV Tarkera - Chandiposh - Rengali snapped at Tarkera end at 11:24

hrs. But relay at Tarkera end failed to operate due to DC failure in relay panel of same line resulting tripping of all elements connected to 220 kV

Bus at Tarkera due to LBB operation.

150 0

Multiple elements tripping without load loss 1 GI-I 19/07

/2017 10:50 Dalkhola ISTS Due to operation of bus bar

protection of bus - I, 220 kV Dalkhola - Kishangunj D/C and 220 kV Dalkhola - Purnea D/C tripped.

0 0

Members may note. Deliberation in the meeting Members noted.

Page 40: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 39

Item no. D.4: Reporting of voltage deviation indices (VDl) for select S/Stns in ER ERLDC submitted the Voltage Deviation Index (VDI) of selected 400 kV Sub-stations for July, 2017 of Eastern Region which is enclosed at Annexure- D.4. Members may note. Deliberation in the meeting Members noted. Item no. D.5: Additional agenda

1. Sustain Under-injection by ISGS generators during RRAS—ERLDC During July and August 2017, NLDC triggered RRAS UP for ISGSs generators of Easter Region on several occasions. However it is observed that some of the ISGS failed to maintain their generation as per schedule and continuous under-injection was observed during the above mentioned period. As per section 5.4 of Detailed Operating procedure of RRAS, “The continuity of the RRAS shall be ensured by the RRAS provider over the period of the despatch”. However, this was continuously violated by ISGS stations of ER. As per clause 9.13 of Detailed Operating procedure of RRAS Quote - Sustained failure, i.e. failure to provide the RRAS (barring unit tripping) by RRAS Provider(s) more than three (3) times during a month shall be brought to the notice of the CERC

- Unquote

Detailed performance of ER ISGS from RRAS point of view would be presented during the meeting. ISGSs are therefore requested to exercise due care while declaring their respective DCs, so that actual generation as per the total schedule issued, can be maintained by them.

Deliberation in the meeting ERLDC presented the performance of the RRAS provider generators during July & August 2017 and informed that in real time Barh, FSTPP stage I & II and KhSTPP stage I & II generators were failed to maintain their generation as per schedule. Presentation is enclosed at Annexure-D5.1. OCC advised NTPC to follow the RRAS schedule strictly. OCC advised ERLDC to monitor the status for one week and even if there is no improvement, the acion may be initiated as per the provisions of IEGC. Further, OCC advised ERLDC to place the status in next OCC meeting.

2. Delineation of O&M responsibilities of various assets of the ISTS--ERLDC With opening up of transmission sector for private participation and rapid addition of new ISTS elements through TBCB route, multiple transmission licensees are now involved, in so far as ownership and maintenance of the regional ISTS is concerned. A single transmission line may be partly owned by one licensee and partly by the other, while the bay equipment, panels etc. at each of the ends may be owned / maintained by two different transmission licensees. In the above backdrop, as the apex body to ensure integrated operation of the regional power system, it becomes essential for RLDCs to be accurately aware of the scope

Page 41: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 40

of responsibilities of each of the licensees, in order to discharge its responsibilities in a smooth and efficient manner. A list of transmission elements in Eastern Region together with their ownerships as per information available with ERLDC is enclosed at Annexure-D5.2. It is requested to kindly go through the list and indicate the agencies responsible for maintenance of line, ensuring real time data, furnishing relay indication, DR etc. in respect of each of the elements and inform ERLDC wherever necessary updating / correction is required to be incorporated.

Deliberation in the meeting

OCC advised all the constituents to update the status as given in the annexure and send it to ERPC and ERLDC within a week. 3. Trail operational certificate for underground fiber optic link from Jakkanpur to SLDC, Patna-

BSPTCL End to end testing of UGFO link between Jakkanpur to SLDC, Patna has been carried out on 03-10-16. Route survey with M/S KEC was carried out on 31-05-17. It was observed that no marking to identify route, location of splice chamber and pits. No provision of clause of standard technical specification of UGFO of PGCIL was followed either regarding the route markers, constrcution of manholes, warning bricks etc. BSPTCL repeatedly requested PGCIL authorities to furnish the technical specification and the SAT procedure of UGFO, but the same has not been provided yet. This may affect the maintenance of UGFO link further. Details are enclosed at Annexure-D5.3.

Deliberation in the meeting

It was agreed that Powergrid and BSPTCL will do the joint inspection. Powergrid agreed to provide the technical specification and SAT procedure of UGFO to BSPTCL. 4. Ethernet link for integration of Kishanganj SAS GSS with SLDC, Patna - BSPTCL Synchronous Digital Hierarchy (SDH) has been installed in Kishanganj (PG)and approach cable laid out up to connecting SDH for integration of SDH of Kishanganj (New) GSS. Ethernet link for integration of SDH of Kishanganj SAS GSS with SLDC, Patna for monitoring of real time data and voice of 220/132/33 kV Kishanganj (New) GSS as well as connecting GSS for ULDC purpose is required on priority basis. Details are enclosed at Annexure-D5.4.

Deliberation in the meeting

Powergrid agreed to resolve the issue.

5. CONSTRUCTION OF BIRPARA GIS UNDER ERSS-XIV --Powergrid UNDER ERSS-XIV PACAKAGE, 132 KV AIS PART OF BIRPARA SS HAVING SMT SCHEME IS TO

BE UPGRADED TO 132 KV DOUBLE MAIN SCHEME OF GIS SYSTEM. PRESENTLY GIS BUIDING WORK COMPLETED AND ALL THE GIS ACCESSORIES ARE

ERECTED. NOW WE REQUIRE SHUT DOWN OF INDIVIDUAL FEEDERS OF 132 KV SYSTEM AND ALSO COMPLETE 132 KV SYSTEM (01 DAY) FOR COMMISSIONING OF GIS.

1 132KV BIRPARA(PGCIL)-BIRPARA(WBSETCL)-II 01.09.17 08:00

Hrs 01.09.17 17:00 Hrs ODB

GIS DUCT (OUT SIDE) ERECTION WORK OF BIRPARA(PGCIL)-BIRPARA (WBSETCL)-I & BIRPARA(PGCIL)-BIRPARA (WBSETCL)-II

2 160MVA ICT-I (BIRPARA-PGCIL) 02.09.17 08:00

Hrs 02.09.17 15:00 Hrs ODB GIS BUSHING ERECTION WORK 132KV

SIDE ICT-1 (160MVA ICT-1)

Page 42: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 41

3 132KV BIRPARA(PGCIL)-BIRPARA(WBSETCL)-II 03.09.17 08:00

Hrs 03.09.17 15:00 Hrs ODB GIS BUSHING ERECTION WORK

BIRPARA(PGCIL)-BIRPARA(WBSETCL)-II

4

BOTH 132KV BIRPARA (PGCIL)-BIRPARA (WBSETCL) -I & 132KV BIRPARA (PGCIL)-BIRPARA (WBSETCL)-II

04.09.17 08:00 Hrs 04.09.17 12:00

Hrs ODB GIS DUCT (OUT SIDE) ERECTION WORK OF BIRPARA(PGCIL)-BIRPARA(WBSETCL)-I

5 132KV BIRPARA(PGCIL)-BIRPARA(WBSETCL)-I 05.09.17 08:00

Hrs 05.09.17 15:00 Hrs ODB

GIS DUCT (OUT SIDE) ERECTION WORK OF BIRPARA(PGCIL)-BIRPARA(WBSETCL)-I

6 132KV BIRPARA(PGCIL)-BIRPARA(WBSETCL)-I 06.09.17 08:00

Hrs 06.09.17 15:00 Hrs ODB

GIS BUSHING ERECTION WORK OF 132KV BIRPARA(PGCIL)-BIRPARA(WBSETCL)-I

7 132KV BIRPARA(PGCIL)-BIRPARA(WBSETCL)-II 07.09.17 08:00

Hrs 07.09.17 15:00 Hrs ODB

GIS DUCT (OUT SIDE) ERECTION WORK OF 132KV SIDE ICT-2 (160MVA ICT-2)

8 132KV BIRPARA(PGCIL)-BIRPARA(WBSETCL)-I 08.09.17 08:00

Hrs 08.09.17 15:00 Hrs ODB

GIS DUCT (OUT SIDE) ERECTION WORK OF 132KV SIDE ICT-2 (160MVA ICT-2)

9 160MVA ICT-II (BIRPARA-PGCIL) 09.09.17 08:00

Hrs 09.09.17 15:00 Hrs ODB GIS BUSHING ERECTION WORK OF

132KV SIDE ICT-2 (160MVA ICT-2)

10 ALL BAYS OF 132KV SIDE 18.09.17 08:00 Hrs 18.09.17 17:00

Hrs ODB FOR HV TESTING & PD TEST

11 160MVA ICT-I (BIRPARA-PGCIL) 20.09.17 07:00

Hrs 20.09.17 11:00 Hrs ODB FOR JUMPERING & CHARGING

12 132KV BIRPARA(PGCIL)-BIRPARA(WBSETCL)-I 20.09.17 12:00

Hrs 20.09.17 16:00 Hrs ODB FOR JUMPERING & CHARGING

13 160MVA ICT-II (BIRPARA-PGCIL) 21.09.17 07:00

Hrs 21.09.17 11:00 Hrs ODB FOR JUMPERING & CHARGING

14 132KV BIRPARA(PGCIL)-BIRPARA(WBSETCL)-II 21.09.17 12:00

Hrs 21.09.17 16:00 Hrs ODB FOR JUMPERING & CHARGING

Deliberation in the meeting WBSETCL agreed to allow all the shutdowns during the morning periods and holidays except sl No 4 & 10. OCC advised Powergrid to take the Shutdowns in consultation with WBSETCL.

6. SHUTDOWN REQUIREMENT FOR COMMISSIONING OF 2ND 500 MVA ICT AT MAITHON --Powergrid

EXISTING 500 MVA ICT IS NOW CONNECTED THROUGH ERS WITH 220 KV

SIDE BAY NO: 206. AFTER FINAL COMMISSIONING OF 2ND 500 MVA ICT THE BAY

CONFIGURATION WILL BE AS FOLLOWS:

ICT IDENTIFICATION BAY NO (400 KV) BAY NO (220 KV)

500 MVA (EXISTING) 428 & 429 213 500 MVA (UPCOMING) 423 & 424 206

Name of Element

From To Reason

Date Time Date Time

Page 43: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 42

500MVA ICT-1

Existing 17.09.2017 09:00 19.09.2017 17:30

1. Dismantling of Jumper of 500MVA ICT-1 (Existing) and connection of Jumper of 500MVA ICT(new) in

220kV side, Removal of ERS Tower

2. Shifting of protection scheme for 220kV side for 500MVA ICT (New), since the said bay is being used by

existing 500MVA ICT-1. Testing activity like differential stability etc.

315MVA ICT-2 22.09.2017 09:00 24.09.2017 17:30

1. Erection of BPI, Connection of Jumper of 500MVA ICT-1 to 220kV bay of 315MVA ICT-2 (213). After that 315MVA ICT-2 will be taken

out of service. 2. Shifting of protection scheme for

220kV side for 500MVA ICT-1, since the said bay is being used by

existing 315MVA ICT-2. Testing activity like differential stability etc.

Deliberation in the meeting OCC advised Powergrid to take the Shutdowns in consultation with DVC.

7. SHUTDOWN REQUIREMENT OF 220 KV ALIPURDUAR-SALAKATI-D/C FOR SHIFTING OF TOWER FROM LOC NO: 196. --Powergrid

220kV D/C Alipurduar-Salakati TL was switched off on 13.08.2017 at 16:58 Hrs due to bending of tower location no.-196 due to extreme flood in Kaljani River in an around Alipurduar Area. Anticipating further tower bending may lead to collapse of tower and may raise safety concern, the line was switched off.

FOR RESTORATION OF SUBJECT LOCATION 02 NO’S FOUNDATION WITH 400 KV TOWERS (DD+18) ENVISAGED.

TENTAIVE S/D REQUIREMENT FOR RESTORATION OF THE LINE SL NO

NAME OF ELEMENT

FROM DATE

FROM TIME

TO DATE TO TIME

NATURE

REMARKS

01. 220 KV APD-SKT-D/C

30.09.17 09:00 20.11.17 15:00

OCB

FOR PERMANENT RESTORATION OF LOC NO: 196.

Deliberation in the meeting OCC decided to defer this shutdown to winter season.

8. REQUIREMENT FOR SHIFTING OF DAMAGED ANCHOR TOWER-2 (MC) CARRYING: LILO IN & OUT PORTION OF 400 KV BINAGURI-PURNEA (Ckt: 3 & 4) & ANCHOR TOWER-1 (MC) CARRYING LILO IN & OUT PORTION OF 220 KV SILIGURI-DALKHOLA-D/C AT KISHANGANJ. --Powergrid

Page 44: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Minutes of 136th OCC Meeting Page 43

DURING CONSTRUCTION THE TOWERS ARE ALMOST 250 METERS AWAY FROM

RIVER COURSE BUT DUE TO RAPID COURSE CHANGE OF MAHANANDA RIVER ALONG WITH TREMENDOUS SOIL EROTION FROM RIVER BANKS NEAR AREA BARMASIA VILLAGE/BIHAR NEAR POWERGRID KISHANGANJ S/S.

DUE TO RECENT FLOOD IN BIHAR THE SUBJECT TOWERS HAVE BECOME MORE VULNARABLE AND RECENT INSPECTION SHOWS HEAVY SOIL EROSION FROM BOTTOM OF FOUNDATION RESULTING IN SINKING OF EXISTING FOUNDATION (01 LEG).

Deliberation in the meeting OCC advised Powergrid to keep a close watch in the scenario and take necessary action.

9. SHUTDOWN REQUIREMENT OF 400 KV ANDAL-JAMSHEDPUR-D/C FOR PORCEALIN INSULATOR DAMAGED BY MISCREANTS. --Powergrid

NEAR BORDER AREA OF BENGAL & JHARKHAND, NAMELY “DALMA WILDLIFE

SANCTUARY & MANIQUE FOREST” 400 KV ANDAL-JAMSHEDPUR-D/C & MAITHON-MEJIA-D/C PASS THROUGH.

THE AREA CONSISTS OF FORESTS AS WELL AS HILLY AREA CORRIDOR AND ALSO A KNOWN HABITAT FOR LOCAL TRIBALS. WE ARE FACING INSULATOR BROKEN INCIDENTS IN THE SUBJECT CORRIDOR MAY BE DUE TO SOME ACTIVITY BY THE HABITATS.

Deliberation in the meeting OCC agreed to allow shutdown and advised Powergrid to replace the damaged insulators.

Meeting ended with vote of thanks to the chair

***********

Page 45: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Venue: ERPC Conference Room, Kolkata

Participants in 136th gCC Meetin R Of ERPC

neflqF= - lr

Date: 30.08.2017 (Wed nesday)Time: 11:00 hrs

SINo

Name

-FCnttor",

2

I k Lo-Jy

?rltr

P.

6

I

;

3

10

72

13

1,1

I S. k. SLq'"-.q

RT

Md,\u,s

V31 en Tst"r, 15

M. l(.lh^\qr^-

)gL-a l)o tvo JeG)Dap.'

"Coming together is a beginning, staying together is progress, and working together is success." -Henry tord

IPage 1]

Designa tion /Organization

ContactNumber

Em aiI Siqnature

n+e f e (/" l4fiotazs nterfc-/ot tt*@zi<.,"*"'rr{^

llt eb/*rt, ffaltwTt 9nrlhoW)tv+ U' paurl,.;' t hM"

DCn, 6pcp1 g8l lrg?3 tL lotJ^:l^ c, @ PoSo(0.; \ 4hry6.3A{'ERTEE p6Yr/ ERLre

3

414"".o\tg,)3 3ur ad\f . bd ax{c a Gaptoco 1r

,bA,y

DN^, P(-o 3q3q?\82{? p"sdl-a.'. 11.*nrO,' trt3i:.

B, P^.^_ c+lsce,-lrt*- a1o 319)tot- bPb,*.

a^- , J,,zo- @7tw4. h.,__&f,qqq t9

tts Z *1t"::"'^":-ih* €) x4.1 s

a gu Q<-rec)

48\(o\).il-tNl IL sf 7oo&9Yq I4j'1,r"".a^q a-aArft. ." L w

46u (coq.r)lz(. Bu r.t U- {q3rorrs66

rra.nparix etA@re&f1. -.'1. c-o ^

Gy !C,1Iwi[^^a V\r*a4rLGal.NHpa L+l - 4+rqAuw i Khn t.l@d,'{+n4il.&"

AAcl ,vlaha#4{DNFtPc.' S6soolor-ss Y.il'r<tt ,4t1e+@7"*'t 4-

\(//9r'kat<P t. rauaififfi*l,,- 1 ,fL,

e e Ce) ,DhN,,

VNP176to421 U.lsh<?r^) zlo e d,"L

,r-<<n.4o.n %tfi4^*4(!180(,^.v Ea.!(Y

q!.3zsJ-l632- nung.fiikq@(osoo.h nq\r4-9a e,v+Ug[ot) 91ot92J sr l n^j?^.6iC Plos"fl. /.-

\^#^afr**\*"15 VIlii

L/

dob^3

R

Itl'e"'DE?G)DG?CI;*ch, Wlz^ t+qzoslL

N\4?aC4+L p. cl, il " n 4q 6 6Jru Lg...,r.ll Pd)h c^"Ao, aeG) / cW-

D G( C 1t ;"ad\l

-1418 Qa,So*n e*"1" 50(E)., (-"1? ',

PhlC/ l"t,ag\,.u

9t.*lfl/Y+.Gn6Rt-oc

q\teotrta)L

9o-tt."o lai of@,*<i\. o '.^

3f lr\19 5-l-$,.n'';J

JDJ' d.l;,-5* Nl @4,!aYeLooqB. t) 69q1.1

)()

t"

D. S+tru

11

1r. }'t rrn+

B*'z--

CA---------J

1td14{tT),0

fuCn -

1718s('%

Page 46: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

P a rt icipants in 136th PCC Meetine of ERPC

Venue: ERPC Conference Room, Kolkata Time: 11:00 hrs Date: 30.08.2017 (Wed nesd ay)

"Coming together is a beginning, staying together is progress, and working together is success." -Henry Ford

lPage 2 l

Na me Designation /Orqan jza tion

ContactN um ber

Email SignatureSINo

|.qJ l,; ba, itnQ4aQt.." .b W!---TeL N<l\ A) ["L-t b1 r E fbarcaLk4

+115 lTLt I l8 \s21

K'r(-l-t++<-.,rL )fttr pt-l) f-4 ML"t34/-A

3q e6a{8! 22 ,***1,,an<.pzr o L n 4 L. @' i i ,4i,--"22

q14)Ezrzx 9x-n^,cL.-q oiec*lT a,r)=-23 I.i< rvrt<irn4.

D(nLrIJ vrpceslRa M.qr

>hhb}"?. titt@d'-r...'1. r-:'.24 s./4. 41,,-'\' €R-t , (hcf L 9 q lrraD }s1 sr,--25 S,(, snup */r?"*,ltd qoTssv3643 S qsahu g fx-,"x -*,J1" .

Y -o"n

7 ( 36J 353/.26 3, r<rno't' (4, EzlD C- L-t^e-'-s a/"^..o27 r4' Nr. f.0 a-.,14, $-ttt-De- 1?34331sn e-h - !^re-hst--;f-G,

€,,1t.r€Rco c- 1fiTns, (to28 C, ,y,r4t I tCK

29 B B- qrr.'

30 Q"u(nui"-a,

qlx E+e

?.RD C

1t1,5%4Ko

StLglsbstL

wr,-I

.nl-tgrac-,?+* 8s Pra31

Br 0rtq Kt n-r ,.R 9 u p31r51tl *rr, s;lier6rr-ll1 . ro.r IW

x, a, ao Q fltsq bL32

33 pLt?f* \'taqLZ, E*9I

4Le f DC/?dv'^-

e-x'eL-c@Qyab. @,)a

kqw,aaz|/o7@6wd('tn - t^rr_

A.et.G, st,a.,felt34 qr^ti Rrtr':.^t' TugtnAa e^.1.4il4t A6ru''t'tz.

35

fvln.t \r,^* c €, Plfr'4(*, 77Cr8't?7t / 5 rlc- btet>@ dt' u*'

1

4.,.36 't^shrv (enjc'r '\€t, Scpc, .

Panc b,q324?Y221 -bL

3l gc+lc*w-$usn- 7+tsurtssL

va"i+aSLtre7..ait.c-

etori+!,tual@ nA trrK.i Q. c r'.1

Y.t( Blri

l\Kar*"-9a*- <+.,<Iofw5errc 9+3<otr^t9 ctdc dbs.e*J,G39 f- K,(,r,S,^ QEtM<LL<-- q|947( ooro pa, ue.ba"[email protected] ,^, lp40 N-7 &L DQnt t wgtp.t e3 vL7r1/-. nXnaLaQ a>afl-t- c -,"4

/@N,har;r.^. ?in i ca @Px'aco. lr^- l{re-6--rr,a.6e* a?a'rlt.

W

tfu3*1 l1v7

.Y

C4-38 *&.--

Page 47: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

,19

Participants in 136!h 9CC Meeting of ERPC

Venuc: ERPC Conference Room, Kolkata Time: 11:00 hrs Date: 30.08.2017 (Wednesday)

"Coming together is a beginning, staying together is progress, and working together is success." -Henry Ford

IPage 3 ]

SINo

Name Designation /Organrzation

ContactN um ber

Em aiI Signature

c\4l U, K, P^I <-/"v) gDt73e1t2- a+"ur'@fZ* )L4)

A.5r .'-.t /.,tpj A D^H 1sc)cl83t862 682 axA rt -,1 ,i'.3, |'1..G'

.!ra..b l'9.(Aq-

qq391u7V+\ W.??QA.;d@,,'i"q_43

U'N.t'{ilf"* C3'"* tl)1a{1,6>to

<)<.la-l-qsr+J. t".L &b44

l, o. eA^ Clp,gf,o olrrf 1\leqo >a)x

45PK Mi sltrc, qM. gLD c . \dt ** gY39go7v'rz e.lt.ll<rni ilra p sllto'r{tte -

br), )o Nzhpn, rl'qt9y,.a'ar '-v/

46h Lu^+^*a rtlrl,, eqN vfi$rqnbekipd"f'c*4 A(u,a6]crt 6,otGoqqqll <t"^\ed"-5fuG,.S,'8^*

---t-.-47

vP,1(? L 8t4o6B16) Nd,vrr',r\,nfit^W)\inAaLnoto.c.ot t 'fr'"-

,18 o,S;Aobc,,Aa-

u4o€A, M,NVs-f4 (-jot 51-(?L 1816sa\b+

?Whh?E e"'1,'7O{;'yAA y-50 c.6VY_ w,(6'l xr\

oooso'..t"fl;4aI tv- c ^-;) tn)ta 4^/t<51 P.v.w\ \' t^(r (^ 9t-t]+TtZsez

rlr*^({lEwl ltLu "ttztr0 ["q-y?

- Ou491o3l9 dJ,.M*@ YLa o; e"!/1ftce,wt3sLbC

11311ro3ot- -a.beyAr.arroy-€ i e ne'lfrel:3 €T .-L<r.D L/Aq,

v-! l,

\

A (E, I LDCtngS,StL ?4tUDuilq sh;u"rr,"oilrvO f?.' Y--

. j'^8lPq\34\0,+L(

\2

5l

?. Ao.'|.a,

56

5

r

,K l+.1

4Ff@stotc F,<"1'o,.1@A**''" \v-\7 e-no^.[ ,q\ 0_E 8""!I )'lt gewrKE 9€-r;.CRo*.{A@dMtu apv..1/ \4,+<;58 (,X i'-,, (n/Aur.iulr - \tttBgrgj .Ul)..-A.rps 9y)l59 Sr. :-,.1!{-

PO90C-a ?EJr(t{}) b66"gtt-uro"rdif, @p, (oo. I !A G},IS-

6[)

b.Mo^ArlD.u. Bau,rl ee.e0-P( s 86)6r?2e6 e-e-o! .<.alc o

2o-t',1"

a.,*-^Ji.w;+v-- @.idaQfw,+.c4*

/\.a.PL-alytM

;rf-r,a*h"^}t55

M-r-

W,+

Page 48: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Annexure-B1

Page 49: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Scanned by CamScanner

Annexure-B8

Page 50: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Scanned by CamScanner

Page 51: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Proposal to avoid difficulties at Kishanganj S/S • 400kV Binaguri - Purnea 3 &4 were made LILO in Kishanganj S/S. At Kishanganj S/S

both Binaguri – 1&2 and Purnea – 1&2 line are in the same dia.

• In case of the emergency situation as discussed, the continuity Binaguri – Purneacould not be made by suitable switching arrangement at Kisanganj S/S.

• Continuity of 400 kV Binaguri – Purnea direct ckt in case of exigency could bemade by either make a temporary arrangement to directly connecting theincoming and outgoing lines within S/S, bypassing the substation or Makesuitable bay arrangement at Kishanganj so that Binaguri – Purnea to be locatedat same DIA. Kishanganj S/S

Binaguri 1 New Purea 1 ICT 3 (Future)

Patna 1 Patna 2 Future Future

Binaguri 2 New Purea 2

ICT 2 SPAREB/R 2

Powergrid may explore and suggest suitable plan in next OCC

Annexure-B9

Page 52: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Proposal to avoid difficulties at Alipurduar S/S • 400kV Binaguri - Bongaigaon 3 &4 were made LILO in Alipuduar S/S.

• Continuity of 400 kV Binaguri – Bongaigaon direct ckt in case of exigency could bemade by either make a temporary arrangement to directly connecting theincoming and outgoing lines within S/S, bypassing the substation or Makesuitable bay arrangement at Kishanganj so that Binaguri – Purnea to be locatedat same DIA.

Alipurduar S/S Powergrid may explore and suggest

suitable plan in next OCC Pole 4 Future Pole

Bus 2A

Bus 2B

Bus 1B

Bus 1A

Future Future

Binaguri 2 Bongaigaon2

Binaguri 1 Bongaigaon1

Page 53: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Item No:B20 Failure of RTU data with the outage of ICTs of Patna and Biharshariff station

• POWERGRID may update the status of extending UPS to RTUS forPatna and Biharshariff station.

• As per input from POWERGRID ,for following listed 17 nos of stations( having communication equipments ) DCPS need to be replaced.

1. RSCC, Kolkata

2. CPCC, Durgapur

3. Kanchanpur

4. Barkot

5. Jamui

6. Maldah

7. Siliguri 400 kV

8. Jamshedpur 400 kV

9. Siliguri 220 kV

10. Rengali

11. Birpara

12. Rourkela

13. Purnea 220 kV

14. Indravati

15. Muzaffarpur 400 kV

16. Biharsharif 400 kV

17. Sasaram HVDC

– The above list is also available in Report of RTU / SAS replacement in Eastern Region dated 10-08-2017.

ERLDC,POSOCO

Annexure-B20

Page 54: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Item No B21: Shifting of communication linksfor PMUs reporting to ERLDC

• Updated status as on 29-08-2017

• POWERGRID is requested to update the status and action plan.

ERLDC,POSOCO

S/N Location Station type Commmunicatio channel

1 Binaguri 400/220KV Substation Shifted to POWERGRID ULDC wideband on 16 June,2017

2 Biharshariff 400/220KV Substation Shifted to POWERGRID ULDC wideband on 24th November ,2015

3 Patna 400/220KV Substation 2 MBPS PDT link from Patna to ERLDC , Kolkata

4 Farakka 400 kV Generating Station. E1 link

5 Ranchi 400/220KV Substation E1 link

6 Rourkela 400/220KV Substation E1 link ( In progress)

7 Talcher 400 kV Generating Station. E1 link

8 Jeypore 400/220KV Substation E1 link

9 Durgapur 400/220KV Substation E1 link (In Progress)

10 Jamshedpur 400/220KV Substation E1 link

11 Sasaram 765/400/220 kV SubStation Shifted to POWERGRID ULDC wideband on 24th November ,2015

12 Rengali 400/220KV Substation Shifted to POWERGRID ULDC wideband on 17 April,2017

Annexure-B21

Page 55: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Overview of real time telemetry of Eastern region for month

July, 2017

Reason for such poor availability:- A) Non availability of stand by link.B) Melli New, BHVDC not available

since 19th June, 17. C) JITPL not reporting since 20th June, 17. ERLDC,POSOCO

Availability 100 %,

33

Availability 80%-

99.99%, 23

Availability below

80.00%, 6

Dh

arb

anga

Talc

he

rH

VD

C

Ste

rlit

e

JITP

L

BH

VD

C

Me

lli N

ew

79

%

74

%

74

%

0%

0%

0%

21

%

26%

26%

100%

100%

100%

Availability

Annexure-B22

Page 56: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

1%

1%

1%

1%

1%

1%

1%

1%

2%

2%

2%

2%

3%

3%

3%

4%

4%

5%

6

%

7%

8%

9%

9%

9%

10

% 2

6%

70

%

10

0%

1

00

%

10

0%

0%

20%

40%

60%

80%

100%

120%B

ahar

amp

ur

IBEU

LLa

khis

arai

Ban

kaR

angp

oFa

rakk

a N

TPC

Pan

dia

wili

Pat

na

Ind

rava

ti (

PG

)Ta

lch

er

HV

DC

Ran

git

Mai

tho

nJa

msh

edp

ur

(PG

)Sa

sara

mB

arh

NTP

CC

han

dw

aka

Kah

alga

on

NTP

CTe

esta

VN

abin

agar

Ga

ngt

akSi

ligu

ri 2

20B

irp

ara

Bih

arsh

arif

fA

rrah

Bo

lan

gir

Mu

zaff

arp

ur

Talc

he

r N

TPC

Mal

da

Tees

ta II

IP

urn

ea 2

20K

ish

anga

nj

Aip

urd

uar

Silig

uri

440

Ch

aib

asa

Ran

chi

Jeyp

ore

Gay

aP

urn

ea N

ew

Ne

w S

asar

amC

hu

zach

en

HEP

MP

LLa

lmat

iaD

urg

apu

rJo

reth

ang

HEP

Ro

urk

ella

Ren

gali

Kal

abad

iaK

eo

njh

or

An

gul

Dik

chu

New

Ran

chi

Jhar

sugu

da

Ne

w F

arak

ka N

TPC

Ster

lite

Dh

arb

anga

AP

NR

LM

oti

har

iSu

bh

asgr

amD

alkh

ola

KB

UN

L St

#2

JITP

LB

HV

DC

Mel

li N

ew

Percentage Failure(in average) of real time telemetry upto 27th August,2017.

Overview of real time telemetry of Eastern region upto 27th August,2017

All users has to provide stand by

communication link to backup ERLDC located

at New Delhi at the earliest.

POWERGRID has to restore SCADA data of

New Melli (down since 19-06-17, SAS

configuration issue at New Melli end).

ERLDC,POSOCO

Availability 100 %, 40

Availability 80%-

99.99%, 18

Availability below

80.00%, 5

Page 57: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

VOIP Status

ERLDC,POSOCO

Site name 01-Aug 02-Aug 03-Aug 04-Aug 05-Aug 06-Aug 07-Aug 08-Aug 09-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug

Jaipur 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

Daltonganj 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

Indrabati 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

Pandiavil 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

Purnia 220 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

Bolangir 0% 33% 100% 100% 100% 100% 100% 100% 83% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

Patna 0% 0% 0% 0% 0% 0% 0% 0% 0% 53% 100% 100% 100% 100% 78% 55% 100% 60% 100% 95% 13%

kanthi 100% 99% 100% 100% 77% 97% 36% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 44% 100% 100% 100%

MALDA 0% 0% 0% 0% 0% 0% 0% 0% 55% 100% 99% 98% 97% 100% 98% 91% 100% 100% 99% 100% 73%

Dalkhola 99% 97% 99% 99% 100% 100% 99% 100% 99% 100% 99% 97% 63% 0% 0% 0% 0% 0% 0% 0% 0%

Kisanganj 100% 97% 100% 100% 100% 100% 99% 100% 100% 100% 99% 98% 49% 58% 0% 0% 0% 0% 0% 0% 0%

Kusai Colony 100% 99% 100% 100% 100% 100% 100% 100% 100% 48% 0% 0% 0% 0% 0% 36% 100% 100% 99% 100% 100%

Gangtok 100% 97% 100% 100% 43% 0% 0% 0% 0% 47% 99% 98% 98% 99% 76% 55% 100% 100% 100% 100% 100%

FSTPP 70% 68% 77% 96% 97% 94% 92% 73% 70% 70% 71% 72% 53% 49% 72% 59% 65% 80% 80% 90% 85%

Keonjhar 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 75% 0% 0% 0% 0% 33% 100% 100% 100% 100% 100%

Rengali 0% 0% 23% 100% 100% 100% 100% 74% 64% 100% 67% 100% 100% 100% 77% 53% 100% 99% 100% 100% 100%

Siliguri 90% 85% 89% 90% 90% 92% 90% 94% 91% 85% 85% 85% 85% 90% 67% 45% 87% 90% 90% 89% 89%

SRLDC 100% 100% 100% 100% 100% 100% 100% 100% 100% 99% 27% 100% 100% 100% 74% 5% 38% 100% 98% 100% 100%

WRLDC 100% 100% 100% 100% 100% 100% 100% 100% 100% 99% 27% 100% 100% 100% 74% 5% 39% 100% 98% 100% 100%

Teesta NHPC 0% 34% 100% 100% 100% 100% 99% 100% 100% 100% 99% 98% 98% 100% 76% 54% 99% 100% 100% 100% 100%

NLDC 100% 100% 100% 100% 100% 100% 100% 100% 98% 99% 100% 100% 100% 99% 75% 5% 38% 100% 98% 100% 100%

Ranchi 765 100% 64% 100% 100% 100% 100% 100% 100% 80% 100% 100% 100% 100% 100% 76% 53% 100% 100% 100% 100% 100%

Angul 100% 91% 69% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 75% 53% 100% 99% 100% 100% 100%

Talcher NTPC 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 47% 53% 100% 99% 100% 100% 89%

Darlipalli 100% 91% 69% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 78% 55% 100% 99% 100% 100% 100%

Restoration/integration of VOIP for Jeypore, Kishanganj, Indravati, Pandiabili station

by POWERGRID at the earliest.

Page 58: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Frequent failure of JITPL SCADA data to ERLDC

• Real time SCADA data from JITPL is frequently failing (May-17: 24% & June-17 (up to 18th): 62%).

• JITPL SCADA server stopped reporting to ERLDC since 20th June2017. 71 days passed but data yet to be restored.

• JITPL is requested to update OCC regarding— – Action plan and tentative date of restoration of SCADA

data. – Route diversion. – VOIP integration. – Measures being taken to extend SCADA data to Back

up ERLDC , New Delhi.

ERLDC,POSOCO

Page 59: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

• Major concern:- – Long outage of real time data

• JITPL

• New Melli

• Bheramara HVDC.

– Non availability of VOICE • Patna, Jeypore, Kishanganj, Indravati, Pandiabili and

Rengali

– Provision of stand by communication link.

– Non availability of Unit side data Farakka STPS (Unit #6).

Teesta V HPS all unit (LV).

IBEUL (Unit #1 and Unit #2).

Rangit HPS (GT i.e. HV side data)

ERLDC,POSOCO

Page 60: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Elementary Data non availability at 400 kV Level:

WBSETCL

Kolaghat TPS: Kharagpur #1 MW/MVAR not available since 06-07-2016.

OPTCL MW/MVAr flow of Meeramandali – GMR line at Meeramundali

end since 29-11-2016.

ERLDC,POSOCO

Page 61: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

POWERGRID Data Intermittent :

Malda,Ranchi 400kV, Baripada, Gaya, Jharsuguda, Angul, Chaibasa ,Banka.

VOIP for following station not yet provided:

Indravati , Jeypore, Bolangir

VOIP not Working:

Purnea 220 , Baharampur 400kV , Rourkela , Rengali, Dalkhola , Kishanganj, ,Pandiabili.

ERLDC,POSOCO

Page 62: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

IPP

IBEUL : Stand by channel upto Back up ERLDC not yet provided.

JITPL : No voice communication available between JITPL and ERLDC.

ERLDC,POSOCO

Page 63: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Important Stations with out real time telemetry:

WBSETCL Dharampur 220,Krishnanagar 220, Hura 220,Foundry Park, 220

Dalkhola,Bantala ,Lakshmikantapur ,New Town.

DVC: 220 kV Giridhi, 132 kV Kolaghat.

OPTCL: 220kV Samangara, 220 kV Lapanga.

JSUNL: Hatia New 220, Patratu ,Deoghar, Garwh ,Goelkera ,Jamtarta,

Kendoposi.

ERLDC,POSOCO

Page 64: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

PMU Installation and commissioning status of ER as on 20.04.2017

S.No Region State Sub-StationOwner/

UtilityS/S type PMU

TOTAL

PANEL

QTY

PMU

Delivery

status

Cable

Delivery

status

ErectionCable

laying

CT/PT/DI

termination

Commiss

ioningIntegration SAT Remarks

78 286 175 73 61 51 45 40 40 24 37

1 ER-II West Bengal Arambagh WBSETCL CR 3 1 Yes Yes done done pending pending Pending pending CT/ PT/ DI interfacing pending due to permission issue.

2 ER-II West Bengal BAKRESHWAR TPS WBSETCL CR 4 1 Yes Yes done pending pending pending Pending pending Panel erected. Cable laying pending due to permission

issue.

3 ER-II West Bengal Bidhannagar WBSETCL CR 3 1 Yes Yes done done pending pending Pending pending Panel erected. Cable laying and termination at PMU panel

completed. CT/ PT/ DI interfacing pending due to

permission issue.

4 ER-II West Bengal JEERAT WBSETCL CR 2 1 Yes Yes done done done done done pending SAT pending as customer didn't agree to witness SAT.

5 ER-II West Bengal Kolaghat TPS WBSETCL CR 4 1 Yes Yes N/A N/A N/A N/A N/A N/A

6 ER-II West Bengal KASBA WBSETCL CR 3 1 Yes Yes done done done done done pending SAT pending as customer didn't agree to witness SAT.

7 ER-II DVC DSTPS DVC CR 2 1 Yes Yes done done done done Pending done Communication Link not available.

8 ER-II DVC Kodarma TPS DVC CR 3 1 Yes Yes done done done done Pending done Communication panel does not exist.

9 ER-II DVC MEJIA-B DVC CR 2 1 Yes Yes done done done done done done Integrated on 07.12.2016

10 ER-II DVC Maithon RB TPS DVC CR 2 1 Yes Yes pending pending pending pending Pending pending

Work started on 04.07.2016. Panel shifted. Team

demobilised due to access issue and panel location issue.

11 ER-II DVC Raghunathpur TPS DVC CR 3 1 Yes Yes done done done done Pending done Communication link was not available during work.

12 ER-II DVC MEJIA DVC CR 5 2 Yes Yes done done done done Pending done S/S couldn't be integrated because distance between PMU

panel and SDH is more than 100 mtrs. Will be integrated on

Mar 2017.

13 ER-II DVC Bokaro DVC CR 2 1 Yes Yes done done done done done done PMU integrated on 24.06.2016

14 ER-II DVC CTPS(Chanderpura) DVC CR 2 1 Yes Yes done done done done Pending done S/S couldn't be integrated because distance between PMU

panel and SDH is more than 100 mtrs. Will be integrated on

Mar 2017.

15 Odisha Orissa Budhipadar OPTCL CR 0 0 No No N/A N/A N/A N/A N/A N/A BOQ not finalized.

16 Odisha Orissa MENDHASAL OPTCL CR 2 1 Yes Yes done done done done Pending done OPTCL is not providing CT/ PT connection for

Meeramundali-2 feeder.

17 Odisha Orissa MERAMANDALI OPTCL CR 6 2 Yes Yes done under

progress

pending pending Pending pending

18 Odisha Orissa RENGALI OPTCL CR 2 1 Yes Yes done done done done Pending done Integration delayed because CAT-6 cable is faulty.

19 Odisha Orissa U.KOLAB OPTCL CR 2 1 Yes Yes done done done done Pending done

20 Odisha Orissa BALIMELA(H) OPTCL CR 3 1 Yes Yes done done partially done pending Pending done OPTCL denied to provide DC connection. CT/PT/DI

interfacing pending due to permission issue.

21 ER-II West Bengal Durgapur Powergrid CR 5 2 Yes Yes done done done done done done PMU integrated on 30.05.2016.

22 ER-II West Bengal FARRAKA NTPC CR 5 2 Yes Yes N/A N/A N/A N/A N/A N/A

23 Odisha Orissa Indrawati Powergrid CR 2 1 Yes Yes done done done done Pending done Communication Link not available.

24 Odisha Orissa Indrawati HPS OPTCL CR 1 1 Yes Yes N/A N/A N/A N/A N/A N/A OPTCL denied to provide DC connection.

25 Odisha Orissa JEYPORE Powergrid CR 2 1 Yes Yes done done done done Pending done Communication Link not available.

26 ER-II West Bengal MAITHON Powergrid CR 7 2 Yes Yes done done done done done done PMU integrated on 21.06.2016.

27 ER-II West Bengal MALDA Powergrid CR 2 1 Yes Yes done done done done done done PMU integrated on 24.06.2016

28 Odisha Orissa Rengali Powergrid Kiosk 2 1 Yes Yes done done done done done done PMU integrated on 04.05.2016

29 Odisha Orissa ROURKELA Powergrid Kiosk 5 2 Yes Yes done done done done done done PMU integrated on 21.04.2016

30 ER-II West Bengal Binaguri Powergrid CR 7 2 Yes Yes done done done done done done PMU integrated on 28.07.2016

31 ER-II West Bengal SUBHASHGRAM Powergrid Kiosk 2 1 Yes Yes done done done done done done PMU integrated on 22.06.2016

32 Odisha Orissa Baripada Powergrid CR 3 1 Yes Yes done done done done done done PMU integrated on 30.01.2017.

33 Odisha Orissa Bolangir Powergrid CR+Kiosk 2 3 Yes Yes done done done done Pending done Communication Link not available.

34 Odisha Orissa ANGUL Powergrid Kiosk 10 11 Yes Yes done done done done done done PMU integrated on 24.03.2017.

Page 1 of 4

Annexure- B.26

Page 65: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

PMU Installation and commissioning status of ER as on 20.04.2017

S.No Region State Sub-StationOwner/

UtilityS/S type PMU

TOTAL

PANEL

QTY

PMU

Delivery

status

Cable

Delivery

status

ErectionCable

laying

CT/PT/DI

termination

Commiss

ioningIntegration SAT Remarks

35 Odisha Orissa Keonjhar Powergrid CR 2 3 Yes Yes done done done done done done PMU integrated on 18.01.2017.

36 Odisha Orissa Jharsuguda Powergrid Kiosk 8 9 Yes Yes done done done done done done PMU integrated on 29.07.2016

37 Odisha Orissa GMR GMR Kiosk 3 4 Yes Yes N/A N/A N/A N/A N/A N/A

38 ER-II Sikkim RANGPO Powergrid CR 4 1 Yes Yes done done done done Pending done S/S couldn't be integrated because distance between PMU

panel and SDH is more than 100 mtrs. Will be integrated on

Mar 2017.

39 ER-II West Bengal Baharampur Powergrid CR 2 3 Yes Yes done done done done done done PMU integrated on 10.05.2016

40 ER-II West Bengal Birpara Powergrid CR 4 1 Yes Yes done done done done done done PMU integrated on 15.07.2016.

41 ER-II DVC CTPS B DVC CR 3 1 Yes No N/A N/A N/A N/A N/A N/A

42 ER-II DVC KALYANESWARI DVC CR 4 1 Yes Yes done done done done done done PMU integrated on 02.01.2017.

43 ER-II DVC PARULIA DVC CR 5 2 Yes Yes done done done done done done PMU integrated on 21.02.2017.

44 ER-II West Bengal Purulia PSP WBSETCL CR 2 1 Yes No N/A N/A N/A N/A N/A N/A

45 ER-II Jharkhand Bokaro TPS DVC CR 1 1 Yes Yes done pending pending pending Pending pending

46 ER-II West Bengal Durgapur TPS DVC CR 3 1 Yes No N/A N/A N/A N/A N/A N/A

47 Odisha Orissa TTPS(Talcher) OPTCL CR 3 1 Yes No N/A N/A N/A N/A N/A N/A

48 Odisha Orissa TALCHER NTPC CR 5 2 No No N/A N/A N/A N/A N/A N/A NTPC is not allowing to deliver mterial.

49 ER-II Sikkim TEESTA Powergrid CR 1 1 Yes No N/A N/A N/A N/A N/A N/A

50 Odisha Orissa Uttara Powergrid CR 2 1 Yes Yes done done done done Pending pending Communication link from s/s to ERLDC and NTAMC to be

provided by PGCIL.

51 Odisha Orissa Jindal JITPL CR 2 1 Yes No N/A N/A N/A N/A N/A N/A

52 Odisha Orissa Monnet Monnet CR 1 1 Yes No N/A N/A N/A N/A N/A N/A

53 Odisha Orissa Strelite Strelite CR 3 1 Yes No N/A N/A N/A N/A N/A N/A

54 Odisha Orissa Ind barath Ind barath Kiosk 1 1 Yes No N/A N/A N/A N/A N/A N/A

55 ER-II Sikkim New Melli Powergrid CR 0 0 No No N/A N/A N/A N/A N/A N/A BOQ not finalized.

56 ER-II Sikkim TT Pool Powergrid CR 0 0 No No N/A N/A N/A N/A N/A N/A BOQ not finalized.

57 ER-II West Bengal Alipurduar Powergrid CR 6 7 Yes Yes partially

done

partially

done

pending pending Pending pending

Work started on 22.12.2016. 4 PMU panels and network

panel installed. Rest 2 PMU panels could not be erected

because location not finalised. Cable laying and

termination at PMU panel completed for 6 feeders. CT/PT

interfacing pending due to unavailability of shutdown.

PGCIL is asking to take DI points from field, which is not in

scope. Work is held up. Team demobilised.

58 ER-II West Bengal Rajarhat Powergrid CR 2 1 Yes Yes done pending pending pending Pending pending Work withheld due to localite agitation issue.

59 ER-I Jharkhand JAMSHEDPUR Powergrid CR 6 2 Yes Yes done done done done done done PMU integrated on 14.02.2017

60 ER-I BIHAR Kahalgaon(KHSTPP) NTPC CR 6 2 Yes Yes done done pending pending Pending pending Work withheld due to gate pass issue.

61 ER-I BIHAR Purnea Powergrid CR 6 2 Yes Yes done done pending pending done pending PMU integrated on 13.04.2017

62 ER-I BIHAR PATNA Powergrid Kiosk 6 7 Yes Yes done done done done done done PMU integrated on 11.04.2017

63 ER-I Jharkhand RANCHI Powergrid Kiosk 12 13 Yes Yes done under

progress

pending pending Pending pending

64 ER-I BIHAR SASARAM(Pusauli) Powergrid CR+Kiosk 9 3 Yes Yes N/A N/A N/A N/A N/A N/A

65 ER-I BIHAR BARH NTPC CR 4 1 Yes Yes N/A N/A N/A N/A N/A N/A

66 ER-I BIHAR LakhiSarai Powergrid Kiosk 4 5 Yes Yes done done done done Pending done SAT completed. PMU not integrated because FO cable was

not delivered due to road permit issue.

67 ER-I BIHAR BANKA Powergrid Kiosk 4 5 Yes Yes done done done done Pending pending SAT pending. PMU not integrated because switch was not

delivered to site. Switch in transit.

Page 2 of 4

Page 66: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

PMU Installation and commissioning status of ER as on 20.04.2017

S.No Region State Sub-StationOwner/

UtilityS/S type PMU

TOTAL

PANEL

QTY

PMU

Delivery

status

Cable

Delivery

status

ErectionCable

laying

CT/PT/DI

termination

Commiss

ioningIntegration SAT Remarks

68 ER-I Jharkhand Chaibasa Powergrid Kiosk 4 5 Yes Yes done under

progress

pending pending Pending pending

69 ER-I BIHAR 765kv Gaya Powergrid Kiosk 11 12 Yes Yes done done done done done done PMU integrated on 24.02.2017

70 ER-I Jharkhand 765/400kV Ranchi (N) Powergrid Kiosk 8 9 Yes Yes done done done done done done PMU integrated on 24.02.2017

71 ER-I Bihar Biharshariff Powergrid CR 9 3 Yes Yes N/A N/A N/A N/A N/A N/A

72 ER-I Bihar MUZAFFAPUR Powergrid CR 5 2 Yes No N/A N/A N/A N/A N/A N/A

73 ER-I Jharkhand Daltonganj Powergrid Kiosk 2 3 Yes Yes N/A N/A N/A N/A N/A N/A Road permit for Switch is pending.

74 ER-I Bihar Kishanganj (karandeghi)Powergrid CR 4 1 Yes Yes done done done done Pending done S/S couldn't be integrated because distance between PMU

panel and SDH is more than 100 mts.

75 ER-I Jharkhand Jharkhand Pool (Chandwa)Powergrid Kiosk 4 1 Yes Yes done done done done Pending done S/S couldn't be integrated because distance between PMU

panel and SDH is more than 100 mts.

76 ER-I Jharkhand Patratu Jharkhand CR 3 1 Yes No N/A N/A N/A N/A N/A N/A

77 ER-I Jharkhand Tenughat Jharkhand CR 2 1 Yes No N/A N/A N/A N/A N/A N/A

78 ER-I Bihar Barauni PP Bihar CR 0 0 No No N/A N/A N/A N/A N/A N/A BOQ not finalized.

ER PMU site activity Summary:

No. of Substations No. of PMU S/S PMU S/S PMU S/S PMU S/S PMU

1 ER-I Powergrid 15 94 15 94 11 69 8 47 5 37

2 ER-I NTPC 2 10 2 10 1 6 0 0 0 0

3 ER-I Jharkhand 2 5 2 5 0 0 0 0 0 0

4 ER-I Bihar 1 0 0 0 0 0 0 0 0 0

ER-I Total 20 109 19 109 12 75 8 47 5 37

1 ER-II Powergrid 13 42 11 42 10 39 8 33 7 29

2 ER-II NTPC 1 5 1 5 0 0 0 0 0 0

3 ER-II DVC 13 37 13 37 10 29 9 28 4 13

4 ER-II WBSETCL 7 21 7 21 5 15 2 5 2 5

ER-II Total 34 105 32 105 25 83 19 66 13 47

1 Odisha Powergrid 10 38 10 38 10 38 10 38 6 30

2 Odisha OPTCL 8 19 6 16 5 15 3 6 0 0

3 Odisha NTPC 1 5 1 5 0 0 0 0 0 0

4 Odisha IPP 5 10 5 10 0 0 0 0 0 0

Odisha Total 24 72 22 69 15 53 13 44 6 30

ER Total 78 286 73 283 52 211 40 157 24 114

Commissioned Integrated to ERLDC/ SLDCSl. No. Region Utility

As per approved BOQ Supplied Installed

Page 3 of 4

Page 67: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Sl. No. Site Name Work Progress

1 ERLDC

Installed, powered up, functioning and integrated with DVC,

WBSETCL and OPTCL PDS system.

2 Backup-NLDC POSOCO did not provide space for PDS system installation.

3 SLDC, Maithon

Installed, powered up, functioning and integrated with ERLDC

PDS system.

4 SLDC, Bhubaneswar

Installed, powered up, functioning and integrated with ERLDC

PDS system.

5 SLDC, Howrah (WBSETCL)

Installed, powered up, functioning and integrated with ERLDC

PDS system.

Status of PDS system Installation and commissioning at ER as on 20.04.2017

Page 4 of 4

Page 68: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Annexure – B.27

AVAILABILITY STATUS OF EVENT LOGGER, DISTURBANCE RECORDER & GPS

Sl. NO

Substation Protection & Control System

Remarks Availability Time Synchronization EL DR GPS Relay DR EL

1 Subhasgram Yes Yes Yes Yes Yes Yes 2 Maithon Yes Yes Yes Yes Yes Yes 3 Durgapur Yes Yes Yes Yes Yes Yes 4 Malda Yes Yes Yes Yes Yes Yes 5 Dalkhola Yes Yes Yes Yes Yes Yes 6 Siliguri Yes Yes Yes Yes Yes Yes 7 Binaguri Yes Yes Yes Yes Yes Yes 8 Birpara Yes Yes Yes Yes Yes Yes 9 Gangtok Yes Yes Yes Yes Yes Yes

10 Baripada Yes Yes Yes Yes Yes Yes 11 Rengali Yes Yes Yes Yes Yes No New EL would be implemented

in BCU under NTAMC project by March'2015

12 Indravati (PGCIL) Yes Yes Yes Yes Yes No EL is old one(model-PERM 200), provision for time synchronisation is not available. New EL would be implemented in BCU under NTAMC project by March'2015

13 Jeypore Yes Yes Yes Yes Yes Yes EL is old and not working satisfactorily. New EL would be implemented in BCU under NTAMC project by March, 2015

14 Talcher Yes Yes Yes Yes Yes Yes 15 Rourkela Yes Yes Yes Yes Yes Yes 16 Bolangir Yes Yes Yes Yes Yes Yes 17 Patna Yes Yes Yes Yes Yes Yes 18 Ranchi Yes Yes Yes Yes Yes Yes 19 Muzaffarpur Yes Yes Yes Yes Yes Yes 20 Jamshedpur Yes Yes Yes Yes Yes Yes 21 New Purnea Yes Yes Yes Yes Yes Yes 22 Gaya Yes Yes Yes Yes Yes Yes 23 Banka Yes Yes Yes Yes Yes Yes 24 Biharsariif Yes Yes Yes Yes Yes Yes 25 Barh Yes Yes Yes Yes Yes Yes 26 Sagardighi No Yes Yes Yes Yes No EL is under process of restoration with

help from OEM, China

27 Kahalgaon Yes Yes Yes Yes Yes Yes 28 Farakka Yes Yes No No No No Time synchronization available for

Farakka-Kahalgaon line-III & IV. The same will be implemented in rest of the

lines by December, 2014.

29 Meramundali Defunct Yes Yes Yes Yes Yes 30 Tisco Yes Yes Yes Yes Yes Yes 31 Bidhannagar No Yes Yes No No No Using DR & EL available in Numerical

Page 69: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

relays. GPS will be put in service by January, 2015.

32 Indravati (OHPC) Yes Faulty No No No No Time synchronization will be done by Feb, 2015. ICT-I feeders using DR & EL available in Numerical relays. 400 kV ICT-II feeder is being maintained by

PGCIL, Mukhiguda.Status may confirm from PGCIL

33 Kharagpur No Yes Yes No No No Using DR & EL available in Numerical relays.

34 DSTPS Yes Yes Yes Yes Yes Yes 35 Sterlite Yes Yes Yes Yes Yes Yes 36 Mejia ‘B’ Yes Yes Yes Yes Yes Yes 37 Mendhasal Defunct Yes Yes Yes Yes No EL will be restored by March, 2015.

38 Arambagh No Yes Yes No No No Using DR & EL available in Numerical relays

39 Jeerat No Yes No No No No Using DR & EL available in Numerical relays. Procurement of new GPS is in

progress. 40 Bakreswar Yes Yes Yes Yes Yes Yes 41 GMR Yes Yes Yes Yes Yes Yes 42 Maithon RB Yes Yes Yes Yes Yes Yes 43 Raghunathpur Yes Yes Yes Yes Yes Yes 44 Kolaghat Yes Yes Yes Yes Yes Yes 45 Teesta V Yes Yes Yes Yes Yes Yes 46 Koderma Yes Yes Yes Yes Yes Yes 47 Sasaram Yes Yes Yes Yes Yes Yes 48 Rangpo Yes Yes Yes Yes Yes Yes 49 Adhunik Yes Yes Yes Yes Yes Yes 50 JITPL Yes Yes Yes Yes Yes Yes 51 765kV Angul Yes Yes Yes Yes Yes Yes 52 Chuzachen Yes Yes Yes No Yes Yes 53 New Ranchi

765kV Yes Yes Yes Yes Yes Yes

54 Lakhisarai Yes Yes Yes Yes Yes Yes 55 Chaibasa 56 765kV

Jharsuguda Yes Yes Yes Yes Yes Yes All are in working condition.

However a dedicated DR for 765KV Lines; make TESLA is not working.

M/s Siemens has assured to commission the same by 31.01.15

57 Beharampur Yes Yes Yes Yes Yes Yes 58 Keonjhar Yes Yes Yes Yes Yes Yes

Page 70: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Annexure- B.28

Eastern Regional Power Committee

The status of ERS towers in Eastern Region as submitted during ERS meeting held on 10.11.14 taken by Member (Power System), CEA is given below:

1) As per 100th OCC meeting held on 22.08.2014, the status of ERS towers asavailable in Powergrid is as given below:

Sl. No.

Name of S/S No. of ERS towers available

ERS towers in use

1 Durgapur, ER-II 1 Set (8 towers)

2 Rourkela, ER-II 3 towers incomplete shape

3 ER-I (located at Jamshedpur)

15 towers (10 nos Tension tower and 5 nos suspension tower)

2) As informed by OPTCL, the present status of ERS towers in OPTCL system isas follows:

220 kV ERS towers: 42 nos located at Mancheswar, Chatrapur & Budhipadar

400 kV ERS towers: 2 nos located at Mancheswar.

12 nos. of new 400 kV ERS towers have been approved by Board of Director forprocurement in the current financial year. Purchase order has been placed.

Another, 16 nos of 400 kV towers accompanied with 6 sets of T&P are required.

3) WBSETCL informed that they have placed order for 2 sets of ERS towers on31.10.2014 and expected by June, 2015.

4) The 25th ERPC meeting held on 21.09.2014, the board concurred to theproposal of procurement of four sets of ERS and it was also informed that, theproposed four sets of ERS will be kept at Sikkim, Siliguri, Ranchi and Gayaand will be used by all constituents of ER during emergencies.

Powergrid informed that four sets of ERS for Eastern Region will be procured.

5) Bihar informed that they have 10 sets of 220 kV ERS towers and 2 setsare under process of procurements.

6) DVC informed that they are in process of procuring two (2) sets of 400 kVERS towers.

Page 71: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Annexure-B29

List of drifted meters to be replaced in Phase-IISNO LOCATION METER SNO FEEDER NAME1 MUZAFFARPUR(PG) NP-5074-A 400 KV MUZAFARPUR (PG)-GORAKHPUR(NR)-1

2 MUZAFFARPUR(PG) NP-9981-A 400 KV MUZAFARPUR (PG)-GORAKHPUR(NR)-2

3 MEJIA(DVC) NP-5226-A MEJIA END OF MAITHON(PG)-1

4 MEJIA(DVC) NP-5227-A MEJIA END OF MAITHON(PG)-2

5 RANCHI(PG) NP-5835-A 400 KV RANCHI-SIPAT-1 (WR)

6 RANCHI(PG) NP-5836-A 400 KV RANCHI-SIPAT-2 (WR)

7 BINAGURI(PG) NP-5884-A BINAGURI END OF BONGAIGAON (NER)-1

8 BINAGURI(PG) NP-5885-A BINAGURI END OF BONGAIGAON (NER)-2

9 ROURKELLA(PG) NP-5933-A ROURKELA END OF TARKERA (GRIDCO)-2

10 KHARAGPUR(PG) NP-7563-A 400 KV KHARAGPUR -BARIPADA(PG)

11 MPL NP-7970-A MAITHON RB END OF RANCHI (PG)-1 (MAIN)

12 MPL NP-7971-A MAITHON RB END OF RANCHI (PG)-2 (MAIN)

13 MPL NP-7564-A MAITHON RB END OF MAITHON (PG)-1 (MAIN)

14 MPL NP-6518-A MAITHON RB END OF MAITHON (PG)-2 (MAIN)

15 RANCHI NEW(PG) NP-7847-A 765 KV RANCHI NEW -DHARAMJAYGARH-1

16 RANCHI NEW(PG) NP-8753-A 765 KV RANCHI NEW -DHARAMJAYGARH-217 STERLITE NP-7572-A 400 KV STERLITE - RAIGARH(WR)-II(MAIN)18 STERLITE NP-7372-A 400 KV STERLITE - ROURKELLA(PG)-II(MAIN)19 ROURKELLA(PG) NP-5928-A 400 KV ROURKELLA(PG)-RAIGARH(WR)20 MIRAMUNDALI(OPTCL) NP-5977-A 400 KV MIRAMUNDALI-ANGUL-121 MIRAMUNDALI(OPTCL) NP-5976-A 400 KV MIRAMUNDALI-ANGUL-222 SUNDERGARH(PG) NP-7634-A 765 KV SUNDERGARH-DHARAMJAYGARH-123 SUNDERGARH(PG) NP-7638-A 765 KV SUNDERGARH-DHARAMJAYGARH-2

Page 72: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

CERC order regarding FGMO/RGMO response of generators

Annexure-B36A

Page 73: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

CERC order

• Petition No. 84/MP/2015, Date of order: July 31, 2017 section 23 (a):

– “… the Commission, starting from the month of September, 2017 shall be closely watching the primary response of ISGSs as reported by POSOCO/NLDCs.

– At the State level, SLDCs shall report the frequency response of intra-State generators to the concerned SERCs.”

Page 74: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Section 23(b)

• “… SLDCs through the assistance of POSOCO shall start the process of selecting independent third parties capable of undertaking periodic checkups to monitor the RGMO/FGMO response.

• To start with selected independent third parties shall be sent to the generating stations which are not providing the desired RGMO/FGMO response….”

Page 75: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Section 23(b) contd.

• “…Independent Third Parties shall ensurethat the generator has not, in any way,prevented/disabled the governor fromproviding the desired response.

• In case, even after enabling the governors,units are not able to provide the desiredresponse as per the provisions of the GridCode, third parties, based on thesubmissions of the generators, shall bringout the technical constraints, if any, whichlimit the primary response of the units.”

Page 76: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Section 23(c)

• “All ISGSs are directed to provide primaryresponse compulsorily in terms ofRegulation 5.2 (f), (g), (h) and (i) of theGrid Code failing which we would nothesitate in initiating action under Section142 of Electricity Act, 2003 for notproviding desired RGMO/FGMO responsewithout any valid reasons.”

N.B. All ISGSs have been communicated about Hon’ble Commission’s order vide letter no ERLDC/SS/FGMO/2017/2505 dated 25-08-17.

Page 77: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Section 24• “….. The Committee (on implementation of FGMO /

primary response) has also recommended thatthere is no requirement for granting anyexemption even to LMZ units from operationunder RGMO/FGMO with manual intervention

• … has the option of either expediting the R&M ofold units which shall include installation of newEHG governors capable of providing adequateprimary response or

• to go in for retrofit of mechanical governors foradopting RGMO features or

• to operate on FGMO with manual intervention…”

Page 78: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

• Primary response of ER ISGS units in terms of Regulation 5.2 (f), (g), (h) and (i) of the Grid Code, calculated based on ERLDC SCADA data will be uploaded to a web group called https://in.groups.yahoo.com/neo/groups/ er_gov_respons/info

– Members are requested to validate the response recorded at ERLDC with DCS data and to provide reason for not providing desired FGMO/RGMO response (if any)

– Request for joining the group can be sent to [email protected].

Page 79: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Annexure-B36B

Whether operating

under RGMO

indicate in case of status is not available

Name of State Type Name of Uitlity

Sector (CS/SS/Private)

Name of Station Name of Stage/ Unit

Installed capacity (MW)

SS 1 210 NoSS 2 210 NoSS 1 65 YesSS 2 65 YesSS 1 82.5 NoSS 2 82.5 NoSS 3 82.5 NoSS 4 82.5 NoSS 5 210 No

Details of stations/Units required to operate under RGMO/FGMO as per IEGC

JHARKHANDThermal TVNL Tenughat

Hydro JSEB Subarnrekha

Bandel TPS

Difficulties in implementing RGMO & exemption not applied

SS 5 210 NoSS 5 250 No

SS 6 250 No

SS 1 210 No NilSS 2 210 No NilSS 3 210 No NilSS 4 210 No NilSS 5 210 No NilSS 6 210 No NilSS 1 210 YesSS 2 210 YesSS 3 210 YesSS 4 210 YesSS 5 210 YesSS 1 300 No

SS 2 300No

SS 1 12.5 NoSS 2 12.5 NoSS 3 12.5 NoSS 4 12.5 NoSS 1 225 Yes

Raman Hydel

Santaldih

Kolaghat

Bakreshwar

Sagardighi

WEST BENGAL

Termal WBPDCL

Hydro

Unit#6 could not be implemented because of some technical problem

Without OEM support it is not possible to put in FGMO/RGMO. At present OEM support is not Station is not in RGMO. WBSETCL is pursuing with Rammam

SS 1 225 YesSS 2 225 YesSS 3 225 YesSS 4 225 YesSS 1 250 YesSS 2 250 YesSS 3 250 YesSS 1 300 YesSS 2 300 Yes

Thermal DPL SS DPL 7 300 YesSS 1 210 NoSS 2 210 NoSS 1 49.5 NoSS 2 49.5 NoSS 3 32 NoSS 4 32 NoSS 5 37.5 NoSS 6 37.5 NoSS 7 37.5 NoSS 1 24 NoSS 2 24 NoSS 3 24 NoSS 1 60 No

PPSP

Budge-BudgeThermal CESC

Haldia

OPGC

Hydro

IB TPS

Burla

Chiplima

Not adequate response in RGMO

In 134th OCC WBPDCL informed that the units are

in RGMO/FGMO mode

SS 1 60 NoSS 2 60 NoSS 3 60 NoSS 4 60 NoSS 5 60 NoSS 6 60 NoSS 7 75 NoSS 8 75 NoSS 1 50 NoSS 2 50 No

OrissaHydro OHPC

Balimela

Page 80: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Annexure-B41

SS 3 50 NoSS 4 50 NoSS 5 50 NoSS 1 80 NoSS 2 80 NoSS 3 80 NoSS 4 80 NoSS 1 150 NoSS 2 150 NoSS 3 150 NoSS 4 150 No

71CS 1 210 No

CS 2 210 No

CS 3 210 No

CS 2 140 No

CS 3 140 NoCTPS

Rengali

Upper Kolab

Indravati

Bokaro-B

RGMO mode of operation would not be possible for units1, 2 and 3. Because of non-availability of electro-hydraulic governor, digital voltage recorder and CMC.

Machines are very old (under consideration for

phase wise decommissioning)

CS 7 250 YesCS 8 250 YesCS DTPS 4 210 NoCS 1 210 NoCS 2 210 No

CS 3 210 No

CS 4 210 NoFinal tuning of RGMO is in progress

CS 5 250 Yes

CS 6 250 YesCS 7 500 YesCS 8 500 YesCS 1 500 YesCS 2 500 YesCS 1 500 YesCS 2 500 YesCS 1 600 YesCS 2 600 YesCS 1 20 NoCS 2 20 No

No

DVC

Thermal

Mejia

Mejia - B

DSTPS

KODERMA

Maithon

Central Sector

RGMO mode of operation would not be possible for

decommissioning)

there is no DCS for SG/TG package the possibility of implementing RGMO is to

be explored

RTPS

CS 2 20 NoCS 3 23.2 NoCS 1 40 NoCS 2 40 NoCS 1 200 YesCS 2 200 YesCS 3 200 YesCS 1 500 YesCS 2 500 Yes

CS Farakka-U#6 500 YesKept in RGMO mode from April, 2014

CS 1 210 YesCS 2 210 YesCS 3 210 YesCS 4 210 YesCS 5 500 YesCS 6 500 YesCS 7 500 YesCS 1 500 YesCS 2 500 YesCS Barh 5 660 YesCS Barh 6 660 YesCS 1 20 NoCS 2 20 No

Thermal NTPC

Hydro

Farakka STPP-I

Farakka STPP-II

Kahalgoan STPP

Talcher STPP Stg-I

Maithon

Panchet

* RangitPondage capacity is to generate power upto 3

would not be possible for units1, 2 and 3. Because of RGMO mode of operation would not be possible for

CS 2 20 NoCS 3 20 NoCS 1 170 YesCS 2 170 YesCS 3 170 Yes

50PS 1 525 YesPS 2 525 YesPS 1 600 Yes

Hydro NHPC

* Rangit

Maithon RB TPP

generate power upto 3 hours only.Hence not under

Teesta HEP

Page 81: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Annexure-B41

PS 2 600 YesPS 3 600 YesPS 4 600 YesPS 1 270 YesPS 2 270 YesPS 1 48 NoPS 2 48 NoPS 1 49.5 NoPS 2 49.5 NoPS 1 200 NoPS 2 200 NoPS 3 200 NoPS 4 200 NoPS 5 200 NoPS 6 200 NoPS 1 48 NoPS 2 48 No

20

could be put in RGMO mode but because of

transmission evacuation constraint RGMO/FGMO is

disabled

IPP

Hydro IPP

Thermal IPP Sterlite

JLHEP

Chujachen HEP

Dikchu

Teesta Urja

(RoR project with 3 hours pondage)

Adhunik Power

(RoR project with 3 hours pondage)

(RoR project with 3 hours pondage)

Page 82: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Reactive power performances of various units in the month of June,

2017

Annexure-B38

Page 83: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Voltage & reactive power injection (Unit MVArinjection-MVAr absorption in GT) at terminal point of generating units are compared for various generating units in ER.

– Scatter plot is plotted with taking

• Terminal voltage across x axis

• Reactive power injection across y axis

• (Nominal terminal voltage (kV), 0 MVAr) as origin

• MVAr injection should reduce with increase in terminal voltage

Page 84: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Response of the units whose MVArinjection increases with increase in

voltage

Page 85: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

The units whose MVAr injection increases with increase in voltage

• Mejia B #7 & #8

*Based on available SCADA data at ERLDC

Page 86: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.
Page 87: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.
Page 88: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Response of the units whose MVAr injection decreases with increase in voltage but does not absorb reactive

power even in high voltage period

Page 89: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.
Page 90: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.
Page 91: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.
Page 92: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.
Page 93: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Power System Operation Corporation Ltd.

ERLDC POSOCO

At ERPC, Kolkata

30th August, 2017

ER Grid Performances

136th OCC Meeting

Annexure-C1

Page 94: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Highlights for the month of July-17

Peak Demand ER: 20274 MW on 17th July

2017 at 21:30 hrs % Growth in Average Demand

Met w.r.t. last year- 4.26%

BSPHCL : 4132 MW ; ON 17/07/17

JUVNL: 1222 MW; ON 21/07/17

DVC: 2765 MW; ON 21/07/17

GRIDCO: 4246 MW; ON 05/07/17

WB: 8282 MW; ON 18/07/17

SIKKIM: 108 MW; ON 22/07/17

Frequency Profile Average Freq:- 50.00 Hz

Avg FVI: - 0.0376 Lowest FVI:- 0.023

Max- 50.23Hz on 06th

July 17 Min- 49.69 Hz on 08th &

19th July 17

76.15% of the time freq was with in IEGC Band

On 17/07/17 frequency within IEGC band was 88.18 % which was maximum so far.

New Element Generating Units- 195

MW Transmission Lines-15

CKM

Open Access STOA transactions

approved -347 nos.

Energy Approved- 881.41 MUs

Energy met

Max. 429 MU on 17th July 2017 %Growth w.r.t. last year on Max

energy – 4.6% Avg. 394 MU in July 2017

%Growth w.r.t. last year on Avg. energy – 1.8%

Page 95: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

1. Achievements during the month

a. New generating units synchronized:

1) MTPS Unit#2 (Stage-II) of 195 MW has been declared under COD w.e.f 01/07/17

b. New transmission elements charged:

1. 400kV Kolaghat- New Chanditala (LILO of 400kV Jeerat- Kolaghat SC at New Chanditala) chargedfor the first time at 14:46Hrs of 03/07/17.

2. 400kV Jeerat-New Chanditala (LILO of 400kV Jeerat- Kolaghat SC at New Chanditala) charged for the first time at 16:42Hrs of 03/07/17.

3. New PPSP-Arambag Ckt-1 (LILO of 400kV PPSP-Arambag Ckt-1 at New PPSP) charged for the firsttime at 19:13Hrs of 15/07/17.

4. PPSP-New PPSP Ckt-1 (LILO of 400kV PPSP-Arambag Ckt-1 at New PPSP) charged for the firsttime at 18:49Hrs of 15/07/17. 5. 50MVAR Bus Reactor-1 at New PPSP Substation charged for the first time at 19:00Hrs of 15/07/17.

6. 400kV New Ranchi-New PPSP-I & II charged for the first time at 20:08 hrs and at 20:50 hrsrespectively of 24/07/17.

7. 400kV Gorakhpur-Motihari (DMTCL) ckt-2 (LILO of 400kV Barh-Gorakhpur ckt-2) charged for thefirst time at 22:54Hrs of 31/07/17.

Page 96: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Elements charged for the first time in the month of August 2017

• 80MVAR Bus Reactor at New Chanditala SS charged for the first time at 19:07Hrs of18/08/17.

• 400kV Gorakhpur- Motihari ckt-2 (LILO of 400kV Barh GorakhPur 2 at Motihari) charged forthe first time at 22:54Hrs of 31/07/17

• 400kV Barh- Motihari ckt-2 (LILO of 400kV Barh GorakhPur 2 at Motihari) charged for thefirst time at 19:20Hrs 01/08/17.

• 315MVA ICT I at Motihari SS Charged for the first time at 20:52Hrs of 01/08/17.

• 315MVA ICT II at Motihari SS Charged for the first time at 18:09Hrs of 06/08/17.

• Bus Reactor I at Motihari SS Charged for the first time at 00:08Hrs of 02/08/17.

• Bus Reactor II at Motihari SS Charged for the first time at 16:35Hrs of 03/08/17.

Page 97: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Elements charged for the first time in the month of August 2017

• 125 MVAR BR I & II at Rengali Charged for the first time at 20:40Hrs and 21:12Hrsrespectively of 01/08/17.

• 132kV Motihari-bettiah I & II Charged for the first time at 12:20Hrs and 12:21Hrs of04/08/17.

• 132Kv Motihari-Motihari(BSEB) II Charged for the first time at 15:41hrs of 04/08/17.

• 400kV Gorakhpur- Motihari ckt-1 (LILO of 400kV Barh GorakhPur 1 at Motihari) charged forthe first time at 12:14Hrs of 07/08/17

• 400kV Barh- Motihari ckt-2 (LILO of 400kV Barh GorakhPur 2 at Motihari) charged for thefirst time at 15:55hrs of 07/08/17.

• 80MVAR Bus Reactor at New Chanditala SS charged for the first time at 19:07Hrs of18/08/17.

• 400kV DC RTPS-Ranchi DC (Ckt.- II & III) from DVC-RTPS to PGCIL Ranchi SS charged for thefirst time at 19:37hrs and 19:40Hrs of 28/08/17.

Page 98: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

3.81% increase in IEGC band on July-17,

w.r.t last year

2.62% increase in f<49.9 Hz band on

July-17, w.r.t last year

6.43% decrease in f>50.05 Hz band on

July-17, w.r.t last year

In Aug-17 (Up to 27th): Max Freq: 50.20 Hz Min Freq: 49.65 Hz

Page 99: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

So Far Highest Demand

Constitute Demand (in MW) Date Time Dmd met on 21st

Aug’17(max dmd met day)

Bihar 4238 23-Aug-17 20:30 4172

DVC 3333 10-Apr-16 20:57 2569

Jharkhand 1262 10-Jun-17

19:54 1203

Odisha 4412 22-Aug-17 19:37 4282

W. Bengal 8605 12-Apr-17

19:56 7818

Sikkim 117 28-Oct-16 18:59 83

ER 20621 28-Apr-17 19:36 20164

So Far Highest Energy Consumption

Constitute Energy consumption

(in MUs) Date

Dmd met on 21st Aug’17(max dmd met day)

Bihar 85.8 18-June-17 78.6

DVC 75 23-Mar-17 57

Jharkhand 26 20-Apr-16 23.5

Odisha 88.5 23-May-17 84.5

West Bengal 181 27-Apr-16 151.4

Sikkim 2 24-Mar-17 1.3

ER 434 25-May-17 412

Page 100: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Max. 86 MU on 17th July 2017 %Growth w.r.t. last year : 15.98%

Max. 24 MU on 16th July 2017 %Growth w.r.t. last year : (-)2.63%

Max. 429 MU on 17th July 2017 % Growth w.r.t. last year : 4.59%

Page 101: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Record Max. 87 MU on 06th July 2017 %Growth w.r.t. last year: 4.93%

Max. 175 MU on 18th July 2017 %Growth w.r.t. last year: 3.11%

Max. 67 MU on 16th July 2017 %Growth w.r.t. last year: 6.29%

Max. 1.3 MU on 28th July 2017 %Growth w.r.t. last year: 3.73%

Page 102: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

3D VIEW OF ER DEMAND PATTERN (APR-17 TO JUL-17)

Page 103: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

3D CURVES ( APRIL-JULY’17)

EASTERN REGION DEMAND

Page 104: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

BSPHCL Demand pattern

JUVNL Demand pattern

DVC Demand Pattern Odisha Demand Pattern

( APRIL-JULY’17)

Page 105: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

WBSEDCL Demand pattern

Sikkim Demand pattern

( APRIL-JULY’17)

Page 106: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

0

500

1000

1500

2000

2500

3000

3500

4000

4500

0%

10

%

20

%

30

%

40

%

50

%

60

%

70

%

80

%

90

%

10

0%

MW

--->

% of Time--->

BSPHCL Load duration curve -Aug-17

0

200

400

600

800

1000

1200

1400

0%

10

%

20

%

30

%

40

%

50

%

60

%

70

%

80

%

90

%

10

0%

MW

--->

% of Time--->

JUVNL Load duration curve -Aug-17

50 % of the time load was above 16000 MW

Data upto 24th Aug’17

20 % of the time load was above 3600 MW

Around 20 % of the time load was above

1000 MW

Page 107: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

0

500

1000

1500

2000

2500

3000

35000

%

10

%

20

%

30

%

40

%

50

%

60

%

70

%

80

%

90

%

10

0%

MW

--->

% of Time--->

DVC Load duration curve -Aug-17

0

500

1000

1500

2000

2500

3000

3500

4000

4500

5000

0%

10

%

20

%

30

%

40

%

50

%

60

%

70

%

80

%

90

%

10

0%

MW

--->

% of Time--->

Gridco Load duration curve -Aug-17

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

0%

10

%

20

%

30

%

40

%

50

%

60

%

70

%

80

%

90

%

10

0%

MW

--->

% of Time--->

WB Load duration curve -Aug-17

0

20

40

60

80

100

120

0%

10

%

20

%

30

%

40

%

50

%

60

%

70

%

80

%

90

%

10

0%

MW

--->

% of Time--->

Sikkim Load duration curve -Aug-17

Data upto 24th Aug’17

50 % of the time load was above 6000 MW 40 % of the time load

was above 60 MW

20 % of the time load was above 3500 MW

10 % of the time load was above 2500 MW

Page 108: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

FrequencyActual

DATE : 28 Aug 2017 Monday Schedule

Act

MUMAX MIN Min/Max UI SCHEDULE Act MU MAX MIN Min/Max UI SCHEDULE

71.0 3767 2246 0.60 -0.95 71.99 -18.7 -404 -1140 0.35 2.75 -21.42

Time: 21:00 16:26 Time: 15:13 11:41

Act

MUMAX MIN Min/Max UI SCHEDULE Act MU MAX MIN Min/Max UI SCHEDULE

28.8 1987 714 0.36 0.67 28.11 50.7 3388 1017 0.30 2.02 48.66

Time: 22:14 4:08 Time: 20:12 7:08

49.6

49.8

50.0

50.2

50.4

50.6

50.8

51.0

-1000-500

0500

1000150020002500300035004000

00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23

BIHAR

49.6

49.8

50.0

50.2

50.4

50.6

50.8

51.0

-1400

-1200

-1000

-800

-600

-400

-200

0

200

400

600

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

DVC

49.6

49.7

49.8

49.9

50.0

50.1

50.2

50.3

-1500

-1000

-500

0

500

1000

1500

2000

2500

3000

3500

4000

00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23

WEST BENGAL

48.6

49.1

49.6

50.1

50.6

-1500

-1000

-500

0

500

1000

1500

2000

2500

00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23

ODISHA

CONSTITUENTWISE SCHEDULE & ACTUAL EXCHANGE

Page 109: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

FrequencyActual

DATE : 28 Aug 2017 Monday Schedule

MU MAX MIN Min/Max UI SCHEDULE Act MU MAX MIN Min/Max UI schd MU

1.0 77 16 0.20 -0.16 1.19 15.53 843 443 0.53 -0.93 16.46

Time: 18:54 2:07 Time: 19:35 16:45

CONSTITUENTWISE SCHEDULE & ACTUAL EXCHANGE

49.6

49.7

49.8

49.9

50.0

50.1

50.2

50.3

-40

-20

0

20

40

60

80

100

00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23

SIKKIM

49.6

49.8

50.0

50.2

50.4

50.6

50.8

51.0

-400

-200

0

200

400

600

800

1000

00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23

JHARKHAND

Page 110: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

DC

ActualDATE : Schedule

Act MU MAX MIN Min/Max UI schd MU Act MU MAX MIN Min/Max UI schd MU

24.21 1315 714 0.54 -0.87 25.07 7.3 453 259 0.57 -0.03 7.33

Time: 19:15 8:45 Time: 0:15 8:45

Act MU MAX MIN Min/Max UI schd MU Act MU MAX MIN Min/Max UI schd MU

15.8 738 562 0.76 -0.74 16.56 26.2 1401 775 0.55 -0.34 26.53

Time: 19:45 5:45 Time: 22:30 5:45

28 Aug 2017 Monday

-400

-200

0

200

400

600

800

1,000

1,200

1,400

0:15

1:00

1:45

2:30

3:15

4:00

4:45

5:30

6:15

7:00

7:45

8:30

9:15

10:0

010

:45

11:3

012

:15

13:0

013

:45

14:3

015

:15

16:0

016

:45

17:3

018

:15

19:0

019

:45

20:3

021

:15

22:0

022

:45

23:3

0

-100

0

100

200

300

400

500

0:15

1:00

1:45

2:30

3:15

4:00

4:45

5:30

6:15

7:00

7:45

8:30

9:15

10:0

010

:45

11:3

012

:15

13:0

013

:45

14:3

015

:15

16:0

016

:45

17:3

018

:15

19:0

019

:45

20:3

021

:15

22:0

022

:45

23:3

0

FSTPP ST 3

-200

-100

0

100

200

300

400

500

600

700

800

0:15

1:00

1:45

2:30

3:15

4:00

4:45

5:30

6:15

7:00

7:45

8:30

9:15

10:0

010

:45

11:3

012

:15

13:0

013

:45

14:3

015

:15

16:0

016

:45

17:3

018

:15

19:0

019

:45

20:3

021

:15

22:0

022

:45

23:3

0

KHSTPP ST 1

-400

-200

0

200

400

600

800

1,000

1,200

1,400

1,600

0:15

1:00

1:45

2:30

3:15

4:00

4:45

5:30

6:15

7:00

7:45

8:30

9:15

10:0

010

:45

11:3

012

:15

13:0

013

:45

14:3

015

:15

16:0

016

:45

17:3

018

:15

19:0

019

:45

20:3

021

:15

22:0

022

:45

23:3

0

KHSTPP ST 2

ISGS (THERMAL) DC, SCHEDULE & ACTUAL GENERATION

FSTPP ST 1& 2

Page 111: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

DC vs Schedule vs Actual of Nabinagar

14th August 2017 19th August 2017

22nd August 2017 25th August 2017

DC Schedule Actual

• Nabinagar U-1(250 MW) scheduling start from 00:00 Hr of 02/08/17.• Beneficiaries are Eastern Railway through DVC (75 MW), Western Railway through

Maharashtra(120 MW), BSPHCL (25 MW:10 % share allocation).• All contract amount are maximum schedule limit to beneficiary at generator Ex-bus

boundary.

Declaring less DC of around 150 MW compare to Normative DC is 227.5 MW.

Page 112: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.
Page 113: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

DETAILS OF BANGLADESH DRAWL AUGUST-2017

DETAILS OF TALA + CHUKHA Generation AUGUST-2017

Page 114: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Sikkim IPP generation curtailed due to

outage of KISHANGANJ s/s

Teesta – V was under shutdown due to high silt content

Rangpo – Binaguri D/C loading & Sikkim IPP generators Gen. pattern15/07/17 to 15/08/17

Page 115: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

State Hydro Generators Performance

Annexure-C2

Page 116: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Unit No

Date of Outage Reason

U - 5 25.10.2016 R & M Work

U - 6 16.10.2015 R & M Work

U - 7 21.02.2017 GT Problem

Effective Installed Capacity :- 163 MW

Page 117: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Unit No

Date of Outage

Reason

U - 5 21.03.2017 Hoist Gate Problem

Effective Installed Capacity :- 200 MW

Page 118: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Unit No

Date of Outage

Reason of Outage

U – 1 (60)

05.08.2016 R & M Work

U – 7 (75)

16.04.2017 Gen. Stator Problem

Units were taken out due to Flood in Down stream Area

Effective Installed Capacity :- 375 MW

Page 119: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Unit No

Date of Outage

Reason of Outage

U – 2 (80)

22.06.2017 Annual Maintenance

U – 3 (80)

19.04.2017 Gen. Internal fault

Effective Installed Capacity :- 160 MW

Page 120: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Units were taken out due to Flood in Down stream Area

Page 121: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Two units of PPSP were not running either in PUMP mode or Generation mode due to leakage in pipe lines between upper and lower dams

Page 122: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Annexure-C.3

P A R T I C U LA R S PEAK DEMAND ENERGYMW MU

1 BIHARi) NET MAX DEMAND 4300 2250ii) NET POWER AVAILABILITY- Own Source (including bilateral) 700 158

- Central Sector 2835 1710iii) SURPLUS(+)/DEFICIT(-) -765 -382

2 JHARKHANDi) NET MAX DEMAND 1200 760ii) NET POWER AVAILABILITY- Own Source (including bilateral) 450 287

- Central Sector 700 357iii) SURPLUS(+)/DEFICIT(-) -50 -116

3 DVCi) NET MAX DEMAND (OWN) 2720 1631ii) NET POWER AVAILABILITY- Own Source 4822 2599

- Central Sector 473 342Long term Bi-lateral (Export) 1500 936

iii) SURPLUS(+)/DEFICIT(-) 1075 374

4 ORISSAi) NET MAX DEMAND 4100 2484ii) NET POWER AVAILABILITY- Own Source 3350 2212

- Central Sector 1215 748iii) SURPLUS(+)/DEFICIT(-) 465 476

5 WEST BENGAL5.1 WBSEDCL

i) NET MAX DEMAND (OWN) 6225 3423ii) CESC's DRAWAL 0 0iii) TOTAL WBSEDCL's DEMAND 6225 3423iv) NET POWER AVAILABILITY- Own Source 3566 1980

- Import from DPL -64 0 - Central Sector 2732 1626

v) SURPLUS(+)/DEFICIT(-) 9 182vi) EXPORT (TO B'DESH & SIKKIM) 10 7

DPL

Sep-17

SL.NO

Anticipated Power Supply Position for the month of

5.2 DPLi) NET MAX DEMAND 490 178ii) NET POWER AVAILABILITY 426 181iii) SURPLUS(+)/DEFICIT(-) -64 3

5.3 CESCi) NET MAX DEMAND 1990 1027ii) NET POWER AVAILABILITY - OWN SOURCE 750 473

FROM HEL 540 328FROM CPL/PCBL 0 0Import Requirement 700 226

iii) TOTAL AVAILABILITY 1990 1027iv) SURPLUS(+)/DEFICIT(-) 0 0

6 WEST BENGAL (WBSEDCL+DPL+CESC)(excluding DVC's supply to WBSEDCL's command area)

i) NET MAX DEMAND 8705 4628ii) NET POWER AVAILABILITY- Own Source 4742 2634

- Central Sector+Others 3972 1954iii) SURPLUS(+)/DEFICIT(-) 9 -40

7 SIKKIMi) NET MAX DEMAND 85 34ii) NET POWER AVAILABILITY- Own Source 10 7

- Central Sector+Others 152 99iii) SURPLUS(+)/DEFICIT(-) 78 72

8 EASTERN REGION At 1.03 AS DIVERSITY FACTOR

i) NET MAX DEMAND 20495 11787Long term Bi-lateral by DVC 1500 936EXPORT BY WBSEDCL 10 7

ii) NET TOTAL POWER AVAILABILITY OF ER 23421 13107(INCLUDING C/S ALLOCATION)

iii) PEAK SURPLUS(+)/DEFICIT(-) OF ER 1416 377(ii)-(i)

Page 123: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Annexure- C.4

From To

KTPS 2 500 15.09.17 10.10.17 26AOH (Blr, TG Brgs, LPT Gen), deferred to

Nov 20174 60 05.09.17 19.09.17 15 Boiler Overhaul5* 110 22.09.17 26.10.17 35 Boiler Overhaul + HPT + IPT

* Odisha requested Talcher to take the shutdown after Puja

Proposed Maintenance Schedule of Thermal Generating Units of ER during September, 2017(as finalised in LGBR meeting )

System Station Unit Size (MW) Period No. of Days Reason

DVC

TTPSODISHA

Page 124: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Sr. No NAME OF THE ELEMENTS DATE TIME DATE TIME REMARKS S/D availed BY ReasonSUBJECT TO CONSENT FROM AGENCY

1 400KV Berhampore Bheramara Ckt-II Main Bay (401 bay) 01/09/17 09:00 01/09/17 16:00 ODB ER-II AMP works

2 400 KV Maithon-Durgapur I & II 01/09/17 08:00 12/09/17 18:00 OCB ER-IIDiversion of MD Line by M/S Suhara Power for dedicated freight coridor.

3 z 01/09/17 09:00 01/09/17 17:30 ODB ER-II Insulator Replacement at MD Line JSEB

4 50 MVAR Line Reactor AT SUBHASGRAM 01/09/17 08:00 30/09/17 17:30 OCB ER-IIImplementation of Switching Scheme in existing 50 MVAR Sgram-S'dighi Line Reactor at Subhasgram

5220kV SLG-Kishanganj Ckt-I

01/09/17 9.00 hrs 01/09/17 17.00 hrs ODB ER-II Jumper tightening & defect insulator replacement

6 132kV Rangpo-Melli 01/09/17 09:00 05/09/17 17:00 ODB ER-II PORCEALIN INSULATOR REPLACEMENT BY POLYMER INSULATOR. SIKKIM

7 50 MVAR X 2 BUS REACTOR AT JEERAT 01/09/17 09:00 01/09/17 17:00 ODB ER-II FOR FREQUENCY DOMAIN SPECTROCHEM MEASURMENT. WB

8 315MVA ICT-II AT PATNA 01/09/17 08:00 01/09/17 18:00 ODB POWERGRID ER-I Application of insulation sleeve on tertiary BSEB

9 220 KV MAIN BAY OF ICT#1 AT PURNEA 01/09/17 09:00 02/09/17 17:00 OCB POWERGRID ER-IDEW POINT MEASUREMENT DONE OF Y & B POLE. RESULT IS BELOW EXPECTED LEVEL, POLE RECONDITIONING TO BE DONE.

BSEB

10 132 KV PURNEA - PURNEA( BSPTCL)#3 LINE 01/09/17 09:00 23/09/17 17:00 OCB POWERGRID ER-I GIS WORK BSEB

11 132kv NBU-Siliguri(PGCL) 01/09/17 09:00 02/09/17 15:00 ODB WB PrePuja Maintenance

12 400 kV Bus-II at Baripada 01/09/17 08:30 01/09/17 17:30 ODB ER-II/Odisha/BARIPADA S/S For GIS bay EXTN works(for isolation of GIS Bus-II)

EASTERN REGIONAL LOAD DESPATCH CENTRE

KOLKATA

TRANSMISSION ELEMENTS OUTAGE APPROVED IN 136TH OCC MEETING OF ERPC

13 400 kV Bay 415 CB(GIS) at Baripada 01/09/17 08:30 06/09/17 17:30 OCB ER-II/Odisha/BARIPADA S/S For GIS Bus-II ext. works

14

50MVAR BUS REACTOR at Rourkela

01/09/17 09:00 30/11/17 18:00 OCB ER-II/Odisha/ROURKELA

Replacement of existing 50MVAR Bus Reactor by 125MVAR Bus Reactor for extension of 400KV Rourkela S/S under ERSS-IX Package.

AFTER RETURN OF JAMSHEDPUR BR

15Auto Reclose to be kept in Manual mode 400 KV Rengali-Indravati Line

01/09/17 08:00 30/09/17 18:00 ODB ER-II/Odisha/BOLANGIR For Carrying out PID of line , No Power Interuption will be there.

16 400 kV JSR-mejia Line 01/09/17 08:00 01/09/17 18:00 ODB POWERGRID ER-I Fo rmain bay CB replacement work under Addcap

Page 125: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

17 50 MVAR BR-I at JSR 01/09/17 08:00 11/09/17 18:00 ODB POWERGRID ER-I Bus Reactor-III bay construction work.

18 132KV BIRPARA(PGCIL)-BIRPARA(WBSETCL)-II 01/09/17 08:00 01/09/17 17:00 ODB ER-IIGIS DUCT (OUT SIDE) ERECTION WORK OF BIRPARA(PGCIL)-BIRPARA(WBSETCL)-I & BIRPARA(PGCIL)-BIRPARA(WBSETCL)-II

WB

19 400 KV Maithon-Kahalgoan I & II 02/09/17 09:00 03/09/17 17:30 ODB ER-II Insulator Replacement at MD Line

20 ICT-IV AT SUBHASGRAM & Haldia Line -1 02/09/17 08:00 02/09/17 17:30 ODB ER-II Joint Inspection of POWERGRID & CESC for simultenous Tripping WB

21 220kV SLG-Kishanganj Ckt-II 02/09/17 9.00 hrs 02/09/17 17.00 hrs ODB ER-II Jumper tightening & defect insulator replacement

22 80 MVAR Alipurduar-I L/R AT BONGAIGAON 02/09/17 9.00 hrs 02/09/17 17.00 hrs ODB ER-II AMP

23 132kV Siliguri-Kurseong 02/09/17 09:00 06/09/17 17:00 ODB ER-II PORCEALIN INSULATOR REPLACEMENT BY POLYMER INSULATOR. WB

24 132 kV LKR-LKR (BSPTCL) Line-1 02/09/17 10:00 02/09/17 14:00 ODB POWERGRID ER-I AMP BSEB

25 400KV ABG-KTPP# 02/09/17 06:00 02/09/17 15:00 ODB WB PrePuja Maintenance

26 160MVA ICT-I (BIRPARA-PGCIL) 02/09/17 08:00 02/09/17 15:00 ODB ER-II GIS BUSHING ERECTION WORK 132KV SIDE ICT-1 (160MVA ICT-1) WB

27 315MVA ICT-I AT PATNA 03/09/17 08:00 03/09/17 18:00 ODB POWERGRID ER-I Attending commissioning punch point & Pre-warranty Test BSEB

28 400KV ABG-PPSP# 03/09/17 06:00 03/09/17 15:00 ODB WB PrePuja Maintenance

29 220KV Birpara-Birpara(PG)#1 03/09/17 07:00 03/09/17 15:00 ODB WB PrePuja Maintenance

30 132kv NJP-Siliguri(PGCL)# 03/09/17 07:00 04/09/17 15:00 ODB WB PrePuja Maintenance

31 315MVA ICT #3 at Baripada 03/09/17 00/01/1900 03/09/17 00/01/1900 ODB ER-II/Odisha/BARIPADA S/S CSD Commissioning,amp work &calibration of OTI&WTI GRIDCO

32 220KV BUS COUPLER BAY (BAY NO.- 202) at Rourkela 03/09/17 09:00 03/09/17 18:00 ODB ER-II/Odisha/ROURKELA AMP

33 132KV BIRPARA(PGCIL)-BIRPARA(WBSETCL)-II 03/09/17 08:00 03/09/17 15:00 ODB ER-IIGIS BUSHING ERECTION WORK BIRPARA(PGCIL)-BIRPARA(WBSETCL)-II

WB

34 400KV Berhampore Bheramara Ckt-II Line 04/09/17 09:00 05/09/17 16:00 ODB ER-II FOX-515 COMMUNICATION CHECKING WITH BANGLADESH. NLDC

35 125 MVAR BR#2 at DURGAPUR 04/09/17 10:00hrs 04/09/17 17:00hrs ODB ER-II for fire fighting commissioning of BR#2

36 400 KV Maithon-Jamshedpur 04/09/17 09:00 05/09/17 17:30 ODB ER-II Insulator Replacement at MD Line

37 220 kv Maithon-Kalyanswari I&II 04/09/17 09:00 04/09/17 17:30 ODB ER-II Insulator Replacement at MD Line DVC

38 220 kv Maithon-Dhanbad I&II 04/09/17 09:00 04/09/17 17:30 ODB ER-II Insulator Replacement at MD Line DVC

39 Sagardihgi - ICT#1 Tie bay (402) AT SUBHASGRAM 04/09/17 08:00 06/09/17 17:30 OCB ER-II Yph Interrupter Unit repalcement for SF6 Leakage WB

Page 126: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

40 400KV ICT-I main Bay( BAY NO.-407) 04/09/17 9.00 hrs 09/09/17 17.00 hrs OCB ER-II CB (BHEL make) overhauling

41 400 KV ANDAL-JAMSHEDPUR-I 04/09/17 09:00 06/09/17 17:00 ODB ER-II FOR DAMAGED INSULATOR REPLACEMENT BY MISCREANTS. DVC

42132 kV LKR-LKR (BSPTCL) Line-2

04/09/17 10:00 04/09/17 14:00 ODB POWERGRID ER-I AMP BSEB

43 765/400 KV ICT-I AT NEW RANCHI 04/09/17 08:00 09/09/17 18:00 ODB POWERGRID ER-I Erection of Gantry tower under STATCOM project NLDC

44 Main bay 400KV 125MVA B/R-2 04/09/17 08:00 04/09/17 18:00 ODB POWERGRID ER-I AMP ( 17-18 )

45 BSF-Banka-1 main Bay No-428 at Biharsarif 04/09/17 10:00 08/09/17 18:00 OCB POWERGRID ER-I CB Overhauling Work

46 220 kV Patna-Sipara-1 04/09/17 10:00 05/09/17 18:00 ODB POWERGRID ER-I Isolator alignment work & other AMP works BSEB

47 400 kV PTN-BRH CKT – I 04/09/17 08:00 04/09/17 18:00 ODB POWERGRID ER-Ifor replacement of prcelain insulator with polymer insulator at varoius locations

48 220 KV BUS -1 AT MUZ 04/09/17 09:00 04/09/17 18:00 ODB POWERGRID ER-IErection of BPI & IPS tube for GIS bay extension work at Muzaffarpur substation.

BSEB

49 400KV ABG-NEW PPSP# 04/09/17 06:00 04/09/17 15:00 ODB WB PrePuja Maintenance

50 765kV ICT-2 Main Bay (707) at Angul 04/09/17 10:00 04/09/17 18:00 ODB ER-II/Odisha/Angul SS C & Tan delta testing of Grading Capacitor of 707CB. NLDC

51 400 KV Indravati-Rengali Main Bay at Indravati 04/09/17 09:00 04/09/17 16:00 ODB ER-II/Odisha/Indravati AMP Work

52 220 kV Jeypore-Jayanagar-2 Line 04/09/17 09:30 04/09/17 15:30 ODB ER-II/Odisha/JeyporeFor Changing B-Ph CVT of Jayanagar-II Line due to Oil Leakage (If Not available in the month of Aug 2017)

GRIDCO

53 765 KV Bus-II at Sundargarh 04/09/17 08:00 05/09/17 18:00 OCB ER-II/Odisha/SundergarhExtension of 4.5" Al Tube & stability checking for commissiong of 765KV Angul Line-3&4 main bay(713 & 716)for new bays construction work

NLDC

54 315MVA ICT-II at Keonjhar 04/09/17 09:00 30/09/17 18:00 OCB ER-II/Odisha/Keonjhar Construction of Firewall for 125MVAR Reactor

55 400KV Keonjhar- Rengali line 04/09/17 09:00 04/09/17 18:00 ODB ER-II/Odisha/Keonjhar 01 no. bundle spacer and VD tightening work.

56 400Kv Rourkela-Raigarh -II line (direct) 04/09/17 08:00 14/09/17 18:00 OCB ER-II/Odisha/Sundergarh TLMErection and stringing of 400kv Rourkela-Raigarh Fdr - II (direct) and Sundargarh -Raigarh fdr-I due to diversion Railway line on behalf of OPGC

NLDC

57 400Kv Sundargarh- Raigarh-I 04/09/17 08:00 14/09/17 18:00 OCB ER-II/Odisha/Sundergarh TLMErection and stringing of 400kv Rourkela-Raigarh Fdr - II (direct) and Sundargarh -Raigarh fdr-I due to diversion of Railway line on behalf of OPGC .

NLDC

behalf of OPGC .

58 400KV Sundergarh-Raigarh-I 04/09/17 08:00 05/09/17 18:00 ODB ER-II/Odisha/Sundergarh TLMFor replacement of Porcelein Insulator at various crossing span by CLR polymer (proposed crossing span 624-625 & 675-676)

NLDC

59 400KV Bus I at bolangir 04/09/17 08:00 11/09/17 18:00 ODB ER-II/Odisha/BOLANGIR BPI Erection and Stringing in Reactor Bay construction ERSS-XIV

60BOTH 132KV BIRPARA(PGCIL)-BIRPARA(WBSETCL)-I & 132KV BIRPARA(PGCIL)-BIRPARA(WBSETCL)-II

04/09/17 08:00 04/09/17 12:00 ODB ER-IIGIS DUCT (OUT SIDE) ERECTION WORK OF BIRPARA(PGCIL)-BIRPARA(WBSETCL)-I

WB

61 400/220/33kV, 315MVA ICT - 1 at ALIPURDUAR 05/09/17 09:00 07/09/17 18:00 OCB ER-II Rectification work of ICT - I 220kV side CB alignment problem.

62 125 MVAR Bus Reactor-1 AT MAITHON 05/09/17 09:00 10/09/17 17:30 ODB ER-II Construction of Fire wall under ERSS-IX

Page 127: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

63 400 KV PPSP-DURGAPUR 05/09/17 09:00 05/09/17 17:30 ODB ER-II Insulator Replacement at MD Line WB

64 160 MVA ICT-1 220/132 KV AT MALDA 05/09/17 8-00 A.M. 05/09/17 4-00 P.M. ODB ER-II AMP WB

65 132kV Siliguri - Melli 05/09/17 09:00 13/09/17 17:00 ODB ER-II PORCEALIN INSULATOR REPLACEMENT BY POLYMER INSULATOR. SIKKIM

66 400 kV PTN-BRH CKT – II 05/09/17 08:00 05/09/17 18:00 ODB POWERGRID ER-Ifor replacement of prcelain insulator with polymer insulator at varoius locations

67 400kv DGP: 400KV Reactor Bay 05/09/17 09:00 05/09/17 15:00 ODB WB PrePuja Maintenance

68 400KV ABG-BKTPP# 05/09/17 06:00 05/09/17 15:00 ODB WB PrePuja Maintenance

69 765kV Bus Reactor-2 Main Bay (715) at Angul 05/09/17 10:00 05/09/17 18:00 ODB ER-II/Odisha/Angul SS C & Tan delta testing of Grading Capacitor of 715CB. NLDC

70 160 MVA ICT#1 at Baripada 05/09/17 09:00 05/09/17 17:30 ODB ER-II/Odisha/BARIPADA S/S AMP work GRIDCO

71 400KV D/C IB-Meramundali TL (OPTCL) 05/09/17 08:00 06/09/17 18:00 OCB ER-II/Odisha/Sambalpur TLCStringing work of 765KV Angul-Jharsuguda D/C (Ckt-III & IV) transmission line

GRIDCO

72 400KV GT # 4 Bay No:29 Main Bay 05/09/17 09:30hrs 07/09/17 18:00 hrs OCB BARH PM job of Bay & relay test

73 400KV GT # 5 TIE Bay No:28 TIE Bay 05/09/17 09:30hrs 07-Sep-17 18:00 hrs OCB BARH PM job of Bay & relay test

74 132KV BIRPARA(PGCIL)-BIRPARA(WBSETCL)-I 05/09/17 08:00 05/09/17 15:00 ODB ER-IIGIS DUCT (OUT SIDE) ERECTION WORK OF BIRPARA(PGCIL)-BIRPARA(WBSETCL)-I

WB

75 400 KV S/C Farakka-Durgapur-II TL 06/09/17 11:00 06/09/17 15:00 ODB ER-II For replacement of Insulator due to damage by miscreant

76 400kV Bus-I AT BINAGURI 06/09/17 07.00 hrs 06/09/17 17.00 hrs ODB ER-II To facilitate hot spot rectification in Purnea-3 & 4 Line.

77 50MVAR L/R OF 400KV Maithan RB AT RANCHI 06/09/17 10:00 06/09/17 17:00 ODB POWERGRID ER-I AMP WORK

78 Tie bay of 400KV B/R-2 & NRNC-RNC Ckt-1 AT NRNC 06/09/17 08:00 06/09/17 18:00 ODB POWERGRID ER-I AMP ( 17-18 )

79 400/220 kV ICT- 1 AT GAYA 06/09/17 10:00 06/09/17 14:00 ODB POWERGRID ER-I AMP work BSEB

80 400 kV PTN-BRH CKT – III 06/09/17 08:00 07/09/17 18:00 ODB POWERGRID ER-Ifor replacement of prcelain insulator with polymer insulator at varoius locations

81400KV DGP-Arambag#

06/09/17 09:00 06/09/17 15:00 ODB WB PrePuja Maintenance

82 400 kV Bus-II at Baripada 06/09/17 08:30 06/09/17 17:30 ODB ER-II/Odisha/BARIPADA S/S For GIS bay EXTN works(for recoonecting jumpers to GIS Bus-II)

83 765/400kV ICT-1 at Angul 06/09/17 10:00 06/09/17 18:00 ODB ER-II/Odisha/Angul SS CSD commissioning at 400kV side of ICT. NLDC

84 125MVAR B/R - UIHEP Tie Bay (411) at Indravati 06/09/17 09:00 06/09/17 16:00 ODB ER-II/Odisha/Indravati Installation of CSD & online testing in Tie CB

85 220KV Rengali(PG)- Rengali(OPTCL)-2 Line 06/09/17 10:00 06/09/17 13:00 ODB ER-II/Odisha/Rengali For attending hotspot in Line isolator GRIDCO

Page 128: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

86 400KV Kahalgaon-Banka Line-1 06/09/17 09:30hrs 06-Sep-17 17:30 hrs ODB KAHALGAON PM works & relay testing

87 400 kV JSR-mejia Line 06/09/17 08:00 06/09/17 18:00 ODB POWERGRID ER-I For main bay CB replacement work under Addcap DVC

88 132KV BIRPARA(PGCIL)-BIRPARA(WBSETCL)-I 06/09/17 08:00 06/09/17 15:00 ODB ER-IIGIS BUSHING ERECTION WORK OF 132KV BIRPARA(PGCIL)-BIRPARA(WBSETCL)-I

WB

89 400KV Berhampore Bheramara Ckt-I Line 07/09/17 09:00 08/09/17 16:00 ODB ER-II FOX-515 COMMUNICATION CHECKING WITH BANGLADESH. NLDC

90 132kV Melli-Rangit 07/09/17 09:00 14/09/17 17:00 ODB ER-II PORCEALIN INSULATOR REPLACEMENT BY POLYMER INSULATOR. SIKKIM

91 400 KV ANDAL-JAMSHEDPUR-II 07/09/17 09:00 09/09/17 17:00 ODB ER-II FOR DAMAGED INSULATOR REPLACEMENT BY MISCREANTS. DVC

92 200 MVA ICT-1 AT LAKHISARAI 07/09/17 08:00 08/09/17 18:00 ODB POWERGRID ER-I Checking of Air Cell. BSEB

93 400 KV NEW RANCHI -RANCHI Ckt - 1 07/09/17 09:00 07/09/17 18:00 ODB POWERGRID ER-I TL Maintenance works

94 400 KV BSF - BALIA Ckt. I 07/09/17 08:00 08/09/17 18:00 ODB POWERGRID ER-I for replacement of prcelain insulator with polymer insulator

95 400/220 kV ICT- 2 AT GAYA 07/09/17 10:00 07/09/17 18:00 ODB POWERGRID ER-I Bay extension work for Gaya Navinagar Line BSEB

96 400KV Ranchi -Rourkela Ckt-I 07/09/17 09:00 07/09/17 17:00 8 hrs POWERGRID ER-IInsulator replacement at Location no 333 & 332 damage by miscreants

97 400KV DGP-PPSP#2 07/09/17 09:00 07/09/17 15:00 ODB WB PrePuja Maintenance

98 JEERAT: 400/220KV 315MVA TR#1 07/09/17 07:00 07/09/17 15:00 ODB WB PrePuja Maintenance

99 765/400kV ICT-2 at Angul 07/09/17 10:00 07/09/17 18:00 ODB ER-II/Odisha/Angul SS CSD commissioning at 400kV side of ICT. NLDC

100 765KV 240 MVAr Bus reactor-II at Sundargarh 07/09/17 09:00 07/09/17 12:00 ODB ER-II/Odisha/SundergarhShifting of spare Reactor to B-Ph reactor of 765KV B/R-II after attending oil leakage of the Reactor.

NLDC

101 400 kV Bus-I at Baripada 07/09/17 08:30 07/09/17 17:30 ODB ER-II/Odisha/BARIPADA S/S For GIS bay EXTN works(for isolation of GIS Bus-I)

102 400 kV Bay 413CB(GIS) at Baripada 07/09/17 08:30 12/09/17 17:30 OCB ER-II/Odisha/BARIPADA S/S For GIS Bus-I ext. works

For attending the oil mix up problem of OLTC in 315 MVA ICT#1 and 103 315MVA ICT#1 at Rourkela 07/09/17 09:00 11/09/17 18:00 OCB ER-II/Odisha/ROURKELA

For attending the oil mix up problem of OLTC in 315 MVA ICT#1 and to arrest oil lekage problem from tan delta test tap assemblies of its bushings.

GRIDCO

104 132KV BIRPARA(PGCIL)-BIRPARA(WBSETCL)-II 07/09/17 08:00 07/09/17 15:00 ODB ER-IIGIS DUCT (OUT SIDE) ERECTION WORK OF 132KV SIDE ICT-2 (160MVA ICT-2)

WB

105 160 MVA ICT-2 220/132 KV AT MALDA 08/09/17 8-00 A.M. 08/09/17 4-00 P.M. ODB ER-II AMP WB

106 132kV Kurseong - Rangit 08/09/17 09:00 14/09/17 17:00 ODB ER-II PORCEALIN INSULATOR REPLACEMENT BY POLYMER INSULATOR. WB

107 Main bay 765/400 KV ICT-2 AT NRNC 08/09/17 08:00 08/09/17 18:00 ODB POWERGRID ER-I AMP ( 17-18 ) NLDC

108 400 KV NEW RANCHI -RANCHI Ckt - 2 08/09/17 09:00 08/09/17 18:00 ODB POWERGRID ER-I TL Maintenance works

Page 129: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

109 400 kV PTN-BRH CKT – IV 08/09/17 08:00 09/09/17 18:00 ODB POWERGRID ER-Ifor replacement of prcelain insulator with polymer insulator at varoius locations

110 400kV BUS - 1 AT JSR 08/09/17 09:30 08/09/17 17:30 8 hrs POWERGRID ER-I Bay construction work of 125 MVAR B/R

111 400KV DGP-PPSP#1 08/09/17 09:00 08/09/17 15:00 ODB WB PrePuja Maintenance

112 220KV DGP-Waria#1 08/09/17 09:00 08/09/17 15:00 ODB WB PrePuja Maintenance DVC

113 765KV 240 MVAr Bus reactor-I at Sundargarh 08/09/17 09:00 08/09/17 12:00 ODB ER-II/Odisha/SundergarhShifting of Y-Ph Reactor to Spare Reactor to attend oil leakage in Y-Ph Reactor.

NLDC

114 765/400kV ICT-3 at Angul 08/09/17 10:00 08/09/17 18:00 ODB ER-II/Odisha/Angul SS CSD commissioning at 400kV side of ICT. NLDC

115 132KV S/C Sambalpur-Rairakhol TL (OPTCL) 08/09/17 08:00 09/09/17 18:00 OCB ER-II/Odisha/Sambalpur TLCStringing work of 765KV Angul-Jharsuguda D/C (Ckt-III & IV) transmission line

GRIDCO

116 400KV GT # 5 08/09/17 09:30hrs 15-Sep-17 18:00 hrs OCB BARH PM job of Generator Transformer

117 400KV Fkk-Kahalgaon Line-408/09/17 09:30hrs 08-Sep-17 17:30 hrs OCB

FARAKKACB testing

118 132KV BIRPARA(PGCIL)-BIRPARA(WBSETCL)-I 08/09/17 08:00 08/09/17 15:00 ODB ER-IIGIS DUCT (OUT SIDE) ERECTION WORK OF 132KV SIDE ICT-2 (160MVA ICT-2)

WB

119 160MVA ICT-II OF BIRPARA. 09/09/17 07:00 Hrs 09/09/17 14:00 Hrs ODB ER-II132KV GIS DUCT (OUT SIDE) ERECTION WORK under ERSS-XIV Pacakage.

WB

120 500MVA ICT# V AT SUBHASGRAM 09/09/17 08:00 09/09/17 17:30 ODB ER-II PSD Commissioning work WB

121 400kV Tala-I L/R along with Line 09/09/17 9.00 hrs 09/09/17 17.00 hrs ODB ER-II Repeat tan delta of 400kV R Phase Bushing & Neutral Bushing. NLDC

122 BSF-Banka-2 main Bay No-430 at Biharsarif 09/09/17 10:00 13/09/17 18:00 OCB POWERGRID ER-I CB Overhauling Work

123 220 kV Patna-Sipara-2 09/09/17 10:00 09/09/17 18:00 ODB POWERGRID ER-I Isolator alignment work & other AMP works BSEB

124 400kV BUS -2 AT JSR 09/09/17 09:30 09/09/17 17:30 8 hrs POWERGRID ER-I Bay construction work of 125 MVAR B/R

125 400KV DGP-PGCIL#1 09/09/17 09:00 09/09/17 15:00 ODB WB PrePuja Maintenance

126 Arambag: 400/220KV 315MVA TR#1 09/09/17 06:00 09/09/17 15:00 ODB WB PrePuja Maintenance

127 765/400kV ICT-4 at Angul 09/09/17 10:00 09/09/17 18:00 ODB ER-II/Odisha/Angul SS CSD commissioning at 400kV side of ICT. NLDC

128 160MVA ICT-II (BIRPARA-PGCIL) 09/09/17 08:00 09/09/17 15:00 ODB ER-II GIS BUSHING ERECTION WORK OF 132KV SIDE ICT-2 (160MVA ICT-2) WB

129 400 kv Maithon-Mejia 3 10/09/17 09:00 11/09/17 17:30 ODB ER-II Insulator Replacement at MD Line DVC

130 132 KV RANGPO-RANGIT 10/09/17 09:00 14/09/17 17:00 ODB ER-II PORCEALIN INSULATOR REPLACEMENT BY POLYMER INSULATOR.

131 220 KV MALDA-DALKHOLA-I 10/09/17 09:00 10/09/17 17:00 ODB ER-II PORCEALIN INSULATOR REPLACEMENT BY POLYMER INSULATOR.

Page 130: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

132 400 KV MALDA-PURNEA-I & II 10/09/17 09:00 10/09/17 17:00 ODB ER-II FOR LINE IMPEDANCE MEASURMENT.

133 220 kV Patna-Khagaul 10/09/17 10:00 11/09/17 18:00 ODB POWERGRID ER-I Isolator alignment work & other AMP works BSEB

134 132 KV PURNEA - KISHANGANJ LINE 10/09/17 09:00 23/09/17 16:00 OCB POWERGRID ER-I GIS WORK BSEB

135 400KV BUS-II AT CHAIBASA 10/09/17 08:00 10/09/17 17:00 ODB POWERGRID ER-I FOR BAY EXTENSION WORK UNDER ERSS-14

136 400KV JRT-NewChanditala 10/09/17 07:00 10/09/17 15:00 ODB WB PrePuja Maintenance

137 220KV Birpara-Birpara(PG)#2 10/09/17 07:00 10/09/17 15:00 ODB WB PrePuja Maintenance

138 400KV Talcher -II ine 10/09/17 10:00 10/09/17 12:00 ODB ER-II/Odisha/Rengali For attending hotspot in Line isolator

139 400 kv Tie bay og Mejia Durgapur Line at JSR 10/09/17 08:00 17/09/17 18:00 OCB POWERGRID ER-I For CB replacement work under Addcap

140 125MVAR Bus Reactor - 2 at ALIPURDUAR 11/09/17 09:00 11/09/17 18:00 ODB ER-II Oil leakage rectification of Radiator Tank (Gasket replacement)

141 400KV Berhampore Jeerat Line 11/09/17 09:00 11/09/17 16:00 ODB ER-IIEarthwire rectification work required for POWERLINE crossing of 400 KV Sagrdighi-Gokarna-D/C.

WB

142 132KV BIRPARA(PGCIL)-BIRPARA(WBSETCL)-I 11/09/17 07:00 Hrs 11/09/17 14:00 Hrs ODB ER-II132KV GIS DUCT (OUT SIDE) ERECTION WORK under ERSS-XIV Pacakage.

WB

143 400 KV Subhasgram- Jeerat Line 11/09/17 08:00 13/09/17 17:30 ODB ER-II PID test & Insulator replacement work at Line WB

144 220kV NSLG-BRP Ckt-I 11/09/17 9.00 hrs 11/09/17 17.00 hrs ODB ER-II Jumper tightening & defect insulator replacement

145 400KV ICT-I & Tala-I Tie Bay( BAY NO.-408) 11/09/17 9.00 hrs 16/09/17 17.00 hrs OCB ER-II CB (BHEL make) overhauling

146 132kV Rangit -Rammam 11/09/17 09:00 20/09/17 17:00 ODB ER-II PORCEALIN INSULATOR REPLACEMENT BY POLYMER INSULATOR. WB

147 220 KV MALDA-DALKHOLA-II 11/09/17 09:00 11/09/17 17:00 ODB ER-II PORCEALIN INSULATOR REPLACEMENT BY POLYMER INSULATOR.

148200 MVA ICT-2 AT LAKHISARAI

11/09/17 08:00 12/09/17 18:00 ODB POWERGRID ER-I Checking of Air Cell. BSEB

149 Main bay 400KV 125MVAR B/R-1 AT NRNC 11/09/17 08:00 11/09/17 18:00 ODB POWERGRID ER-I AMP ( 17-18 ) NLDC

150 400 kV PTN-BAL CKT I 11/09/17 08:00 11/09/17 18:00 ODB POWERGRID ER-Ifor replacement of prcelain insulator with polymer insulator at varoius locations

NLDC

151 50 MVAR BR1 AT JSR 11/09/17 09:30 11/09/17 17:30 8 hrs POWERGRID ER-I Bay construction work of 125 MVAR B/R

152400KV DGP-PGCIL#2

11/09/17 09:00 11/09/17 15:00 ODB WB PrePuja Maintenance

153 Arambag: 400/220KV 315MVA TR#2

11/09/17 06:00 11/09/17 15:00 ODB WB PrePuja Maintenance

154765kV, 80*3 MVAR Line Reactor-1 at Angul

11/09/17 08:00 11/09/17 18:00 ODB ER-II/Odisha/Angul SS For attending Oil Leakage problem under TBEA Punch Points. NLDC

Page 131: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

155 400 KV Indravati-Jeypore Main Bay at Indravati 11/09/17 09:00 14/09/17 18:00 OCB ER-II/Odisha/Indravati Overhauling of Main Bay (401) CB Mechanism

156 400KV Bus-I at Sundargarh 11/09/17 08:00 11/09/17 18:00 ODB ER-II/Odisha/SundergarhErection of SF6 to AIS Bushing for extension of Bus bar for GIS extn work under construction head.

157 400KV ROURKELA-SEL#2 by RKL 11/09/17 09:00 11/09/17 18:00 ODB ER-II/Odisha/ROURKELAFor fixing of Counter weight at loc 193 & fixing of Dislocated VD ,spacers at other locations.

GRIDCO

158 765 KV Angul-Srikakulam TL CKT-II 11/09/17 07:00 12/09/17 17:00 ODB ER-II/Odisha/BerhampurReplacement of Glass Insulatos by Long Rod Polymer Insulators at loc no. 681, 715, 722,723, 727 and 728. (Already approved in 135th OCC, in case of non availability, the S/D will be taken in the month

NLDC

159 765kV Angul-Srikakulam Line-2 11/09/17 08:00 11/09/17 18:00 ODB ER-II/Odisha/Angul TLAMImprovement & strenghthening of line jumpers to prevent swing during high speed wind to avoid tripping in future & improvement of line availability & reliability and NTAMC Validation Work

NLDC

160 400KV Fkk-Sagardighi Line11/09/17 09:30hrs 12-Sep-17 17:30 hrs ODB

FARAKKACT & Relay testing

WB

161 50 MVAR BR-I at BSF 11/09/17 08:00 13/09/17 18:00 OCB POWERGRID ER-I For commissioning of 125 mVAR BR-I in parallel with existing BR

162400KV TIE BAY OF MAITHON(RB)-I & Future Bay (408) AT RANCHI

12/09/17 10:00 12/09/17 17:00 ODB POWERGRID ER-I AMP WORK

163 765kV Gaya-Balia line 12/09/17 08:00 12/09/17 18:00 ODB POWERGRID ER-I For replacement of insulators at loc 135 & 169 NLDC

164 132KV BIRPARA(PGCIL)-BIRPARA(WBSETCL)-II 12/09/17 07:00 Hrs 12/09/17 14:00 Hrs ODB ER-II132KV GIS DUCT (OUT SIDE) ERECTION WORK under ERSS-XIV Pacakage.

WB

165 400kV D/C Siliguri-Purnea T/L 12/09/17 09:00 15/09/17 17:00 ODB ER-II For line maintenance work

166 220kV NSLG-BRP Ckt-II 12/09/17 9.00 hrs 12/09/17 17.00 hrs ODB ER-II Jumper tightening & defect insulator replacement

167220 KV B/C BAY AT MALDA

12/09/17 8-00 A.M. 12/09/17 4-00 P.M. ODB ER-II AMP

168400/220KV 315MVA ICT-II 220KV side Bay (209) AT RANCHI

12/09/17 10:00 12/09/17 17:00 ODB POWERGRID ER-I AMP WORK JSEB

169 200MVA ICT-1 AT BANKA 12/09/17 10:00 12/09/17 18:00 ODB POWERGRID ER-I Providing insulation sleeves on tertiary conductor BSEB

170400 KV BSF - BALIA Ckt. II

12/09/17 08:00 12/09/17 18:00 ODB POWERGRID ER-I for replacement of prcelain insulator with polymer insulator

171 400 kV PTN-BAL CKT II 12/09/17 08:00 12/09/17 18:00 ODB POWERGRID ER-Ifor replacement of prcelain insulator with polymer insulator at varoius locations

NLDC

172 400 KV Chandwa-Ranchi -I 12/09/17 09:00 12/09/17 18:00 ODB POWERGRID ER-I To replace LA in R-ph

173 HVDC Back to Back System including AC Bypass@ Pusauli 12/09/17 09:00 Hrs 15/09/17 18:00HrsHVDC system will be out on

12.09.17 and 15.09.17 on daily basis only for 02

PusauliTo carry out following activities(i) Faulty Thyrister Replacement,(ii) UV Detector Cleaning,

NLDC

174 400KV JEERAT-BKTPP 12/09/17 07:00 12/09/17 15:00 ODB WB PrePuja Maintenance

Page 132: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

175 DGP: 400/220KV 315MVA ICT#1 12/09/17 09:00 12/09/17 15:00 ODB WB PrePuja Maintenance

176 Arambag: 400KV BUS Transfer Bay 12/09/17 06:00 12/09/17 15:00 ODB WB PrePuja Maintenance

177 400KV ROURKELA-RAIGARH#2 by RKL 12/09/17 09:00 12/09/17 18:00 ODB ER-II/Odisha/ROURKELAFor fixing of Counter weight at loc 1013 & fixing of Dislocated VD ,spacers at other locations

NLDC

178 765kV Angul- Srikakulam Line-1 with LR at Angul 12/09/17 08:00 12/09/17 18:00 ODB ER-II/Odisha/Angul SSFor commissioning of Spare Reactor with Line Reactor-1. Isolator switching needs to be done for CB selection scheme checking. During the operation of CB at the time of scheme checking, Reactor

NLDC

179 220 kV Jeypore-Jayanagar-I Line 12/09/17 09:30 12/09/17 17:30 ODB ER-II/Odisha/JeyporeFor Changing R & Y-Ph CT of Jayanagar-I Line due to H2 Violation (If Not available in the month of Aug 2017)

GRIDCO

180 400 kV Bus-I at Baripada 12/09/17 08:30 12/09/17 17:30 ODB ER-II/Odisha/BARIPADA S/S For GIS bay EXTN works(for recoonecting jumpers to GIS Bus-I)

181210 BAY(220kv side 160MVA ICT#1) at Baripada

12/09/17 09;00 12/09/17 17:30 ODB ER-II/Odisha/BARIPADA S/SAMP work

GRIDCO

182400KV Bus II at bolangir

12/09/17 08:00 19/09/17 18:00 ODB ER-II/Odisha/BOLANGIRBPI Erection and Stringing in Reactor Bay construction ERSS-XIV

183 765kV Gaya-VNS-II line 13/09/17 08:00 13/09/17 18:00 ODB POWERGRID ER-I For attending Line Defects NLDC

184 160MVA ICT-I OF BIRPARA 13/09/17 07:00 Hrs 13/09/17 14:00 Hrs ODB ER-II132KV GIS DUCT (OUT SIDE) ERECTION WORK under ERSS-XIV Pacakage.

WB

185125 MVAR BR#3 at DURGAPUR

13/09/17 10:00hrs 13/09/17 17:00hrs ODB ER-II for fire fighting commissioning of BR#3

186 MAIN BAY OF 400KV Ranchi- Rourkela-II AT RANCHI 13/09/17 10:00 13/09/17 17:00 ODB POWERGRID ER-I AMP WORK

187 Main bay 765/400 KV ICT-1AT NRNC 13/09/17 08:00 13/09/17 18:00 ODB POWERGRID ER-I AMP ( 17-18 ) NLDC

188200MVA ICT-2 AT BANKA

13/09/17 10:00 13/09/17 12:00 ODB POWERGRID ER-IProviding insulation sleeves on tertiary bushing

BSEB

189 400 kV 125 MVAR Bus Reactor-1 AT GAYA 13/09/17 10:00 13/09/17 18:00 ODB POWERGRID ER-I Bay extension work for Gaya Navinagar Line

190 400 kV PTN-BAL CKT III 13/09/17 08:00 13/09/17 18:00 ODB POWERGRID ER-Ifor replacement of prcelain insulator with polymer insulator at varoius locations

NLDC

191 400/220kV, 315MVA ICT-1 AT JSR 13/09/17 09:30 13/09/17 17:30 8 hrs POWERGRID ER-I Differential relay replacement work JSEB

192 400 KV Chandwa-Ranchi -II 13/09/17 09:00 13/09/17 18:00 ODB POWERGRID ER-I To replace LA in Y-ph

193 DGP: 400/220KV 3*105 MVA TR#2 13/09/17 09:00 13/09/17 15:00 ODB WB PrePuja Maintenance

194 Arambag: 400KV Main Bus- 2 13/09/17 06:00 13/09/17 15:00 ODB WB PrePuja Maintenance

195 765kV Angul- Srikakulam Line-2 with LR at Angul 13/09/17 08:00 13/09/17 18:00 ODB ER-II/Odisha/Angul SSFor commissioning of Spare Reactor with Line Reactor-2. Isolator switching needs to be done for CB selection scheme checking. During the operation of CB at the time of scheme checking, Reactor

NLDC

196765 KV Angul-Srikakulam TL CKT-I

13/09/17 07:00 14/09/17 17:00 ODB ER-II/Odisha/BerhampurReplacement of Glass Insulatos by Long Rod Polymer Insulators at loc no. 681, 715, 722,723, 727 and 728.(Already approved in 135th OCC, in case of non availability the S/D will be taken in the month of

NLDC

197 765kV Angul-Srikakulam Line-1 13/09/17 08:00 13/09/17 18:00 ODB ER-II/Odisha/Angul TLAMImprovement & strenghthening of line jumpers to prevent swing during high speed wind to avoid tripping in future & improvement of line availability & reliability and NTAMC Validation work

NLDC

Page 133: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

198 400KV Bus-II at Sundargarh 13/09/17 08:00 13/09/17 18:00 ODB ER-II/Odisha/SundergarhErection of SF6 to AIS Bushing for extension of Bus bar for GIS extn work under construction head.

199 400KV Kahalgaon-Banka Line-2 13/09/17 09:30hrs 13-Sep-17 09:30 hrs ODB KAHALGAON PM works & relay testing

200 400KV Fkk-Bahrampore Line 13/09/17 09:30hrs 14-Sep-2017 17:30 hrs ODB FARAKKA CVT Replacement, CB & Relay Testing

201 765kV Gaya-VNS-I line 14/09/17 08:00 14/09/17 18:00 ODB POWERGRID ER-I For replacement of insulators at loc 181 & 183 NLDC

202 400 KV BSF - KOD Ckt. I 14/09/17 08:00 14/09/17 18:00 ODB POWERGRID ER-I for replacement of prcelain insulator with polymer insulator DVC

203 ICT-3 Main bay no.-410 at Biharsarif 14/09/17 10:00 18/09/17 18:00 OCB POWERGRID ER-I CB Overhauling Work

204 400 kV 125 MVAR Bus Reactor-2 AT GAYA 14/09/17 10:00 14/09/17 18:00 ODB POWERGRID ER-I Bay extension work for Gaya Navinagar Line

205 400 kV PTN-BAL CKT IV 14/09/17 08:00 14/09/17 18:00 ODB POWERGRID ER-Ifor replacement of prcelain insulator with polymer insulator at varoius locations

NLDC

206 400/220kV, 315MVA ICT-2 AT JSR 14/09/17 09:30 14/09/17 17:30 8 hrs POWERGRID ER-I Differential relay replacement work JSEB

207 Arambag: 400/220KV 315MVA TR#3 14/09/17 06:00 14/09/17 15:00 ODB WB PrePuja Maintenance

208 DGP: 400KV BUS Transfer Bay 14/09/17 09:00 14/09/17 15:00 ODB WB PrePuja Maintenance

209 765kV Main Bus-I at Angul 14/09/17 08:00 15/09/17 18:00 OCB ER-II/Odisha/Angul SSChecking of Bus-bar Stability of 765kV Angul-Sundargarh Line-3&4 for connection with existing system under Construction Head.

NLDC

210 400 kV Jeypore-Gajuwaka-I Line 14/09/17 09:30 14/09/17 13:30 ODB ER-II/Odisha/JeyporeFor Relay testing after Retrofitting of Main-II Relay of Gajuwaka-I Line (If Not completed in the month of Aug 2017)

NLDC

211 400 kV Jeypore-Gajuwaka-II Line 14/09/17 13:30 14/09/17 17:30 ODB ER-II/Odisha/JeyporeFor Relay testing after Retrofitting of Main-II Relay of Gajuwaka-II Line (If Not completed in the month of Aug 2017)

NLDC

212 104 BAY(132kv side 160MVA ICT#1) at Baripada 14/09/17 09;00 14/09/17 17:30 ODB ER-II/Odisha/BARIPADA S/S AMP work

213 500MVA ICT-1 AT MAITHON 15/09/17 09:00 16/09/17 17:30 OCB ER-II1. Dismantling of Jumper of 500MVAV ICT-1 and connection of Jumper of 500MVA ICT(new) in 220kV side and other work related to commissioning & first time charging of 500MVA ICT. 2.

DVC

214 132kV Rangpo-Gangtok 15/09/17 09:00 20/09/17 17:00 ODB ER-II PORCEALIN INSULATOR REPLACEMENT BY POLYMER INSULATOR. SIKKIM

215 132kV Rangpo-Chuzachen 15/09/17 09:00 20/09/17 17:00 ODB ER-II PORCEALIN INSULATOR REPLACEMENT BY POLYMER INSULATOR. SIKKIM

216 Main bay 400KV RNC-Chadwa ckt-II AT NRNC 15/09/17 08:00 15/09/17 18:00 ODB POWERGRID ER-IAMP ( 17-18 )

217 160 MVA ICT#2 AT PURNEA 15/09/17 09:00 23/09/17 16:00 OCB POWERGRID ER-I GIS WORK BSEB

Page 134: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

218 500 MVA ICT-3 AT MUZ 15/09/17 09:00 20/09/17 18:00 OCB POWERGRID ER-IREPLACEMENT OF GASKET/ORINGS OF ALL TURRET BUSHINGS FOR ARRESTING LEAKAGE & ATTENDING COMMISSIONING PUNCH POINT.

BSEB CONSENT REQUIRED

219 DGP: 400KV Bus-Coupler Bay 15/09/17 09:00 15/09/17 15:00 ODB WB PrePuja Maintenance

220 JEERAT: 400/220KV 315MVA TR#2 15/09/17 07:00 15/09/17 15:00 ODB WB PrePuja Maintenance

221400 KV Rourkela-Sterlite-II & Rourkela - Sundargarh-II (both circuits together)

15/09/17 08:00 16/09/17 17:00 OCB ER-II/Odisha/Sundargarh TLCStringing work of 765KV Angul-Jharsuguda D/C (Ckt-III & IV) transmission line

GRIDCO

222 400KV Rourkela-Sundergarh-II 15/09/17 08:00 15/09/17 18:00 ODB ER-II/Odisha/Sundergarh TLMFor replacement of Porcelein Insulator at single crossing span (317-318, 7 & 236. ) by CLR polymer (Already approved in 135th OCC, in case of non availability the S/D will be taken in the month of Sept-

223 220 KV S/C Budhipada-Korba Line 15/09/17 08:00 31/10/17 18:00 OCB ER-II/Odisha/Sundergarh TLM Erection and stringing of M/C (Multi Ckt) tower of diversion work NLDC

224 400 kV BSF-Sasaram -II Line 15/09/17 08:00 15/09/17 18:00 ODB POWERGRID ER-I For rectification of Y-phaseline isolator at BSF.

225 765 KV BUS-I at Gaya S/S 16/09/17 08:00 16/09/17 18:00 ODB POWERGRID ER-I For isolator rectification work under S/S extn. Package NLDC

226 400 KV Subhasgram-Haldia Line-1 16/09/17 08:00 16/09/17 17:30 ODB ER-II Jumper Tightning of Haldia Line-1 WB

227 200 MVA ICT-2 & 80 MVAR Bus Reactor AT LAKHISARAI 16/09/17 08:00 19/09/17 18:00 ODB POWERGRID ER-I Fire wall Construction. BSEB

228 400kV JSR- Andal-II 16/09/17 09:30 16/09/17 17:30 8 hrs POWERGRID ER-I AMP Work DVC

229 JEERAT: 400/220KV 315MVA TR#3 16/09/17 07:00 16/09/17 15:00 ODB WB PrePuja Maintenance

230 Arambag: 400KV Main Bus- 1 16/09/17 06:00 16/09/17 15:00 ODB WB PrePuja Maintenance

231400KV Rourkela-Sterlite-II

16/09/17 08:00 16/09/17 18:00 ODB ER-II/Odisha/Sundergarh TLMFor replacement of Porcelein Insulator at single crossing span (317-318) by CLR polymer . Insulator replacement at Location No.- 57 & rectification of bundle spacer in span 195-196 (Already approved in

GRIDCO

232 400kV Angul-Bolangir Line. 16/09/17 08:00 16/09/17 18:00 ODB ER-II/Odisha/Angul TLAMImprovement & strenghthening of line jumpers to prevent swing during high speed wind to avoid tripping in future & improvement of line availability & reliability and NTAMC Validation work

NLDC

233 400 KV Indravati-Jeypore Tie Bay at Indravati 16/09/17 09:00 20/09/17 18:00 OCB ER-II/Odisha/Indravati Overhauling of Tie Bay (402) CB Mechanism

234401BAY (Keonjhar main Bay) at Baripada

16/09/17 09;00 16/09/17 17:30 ODB ER-II/Odisha/BARIPADA S/SGas arresting works

235 400KV ROURKELA-TACHER#2 16/09/17 09:00 18/09/17 18:00 ODB ER-II/Odisha/ROURKELAFor replacement of disc insulators with polymer insulators (Already approved in 135th OCC, in case of non availability, the S/D will be taken in the month of Sept-17)

236400 KV Rengali Indravati Line (Rescheduled Shutdown proposal, already approved in 135th OCC)

16/09/17 07:00 26/09/17 18:00 ODB ER-II/Odisha/Bolangir Replacement of Porcelain insulators with Polymer insulators in major crossings at Locations 1121-1122,929-930,773-774,931-932,1078-1079,1081-1082,913-914,1036-1037,1061-1062,1074-

NLDC

Page 135: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

237 220 kV Patna- Fatuha 17/09/17 10:00 18/09/17 18:00 ODB POWERGRID ER-I Isolator alignment work & other AMP works BSEB

238 765 KV BUS-II at Gaya S/S 18/09/17 08:00 18/0917 18:00 ODB POWERGRID ER-I For isolator rectification work under S/S extn. Package NLDC

239 400/220/33kV, 315MVA ICT - 2 at ALIPURDUAR 18/09/17 09:00 20/09/17 18:00 OCB ER-II Air cell replacement (Aircell found defective)

240 132KV BIRPARA(PGCIL)-BIRPARA(WBSETCL)-I 18/09/17 10:00 Hrs 18/09/17 14:00 Hrs ODB ER-II132KV GIS DUCT (OUT SIDE) ERECTION WORK under ERSS-XIV Pacakage.

WB

241 160MVA ICT-I OF BIRPARA 18/09/17 10:00 Hrs 18/09/17 14:00 Hrs ODB ER-II132KV GIS DUCT (OUT SIDE) ERECTION WORK under ERSS-XIV Pacakage.

WB

242 400 KV Jeerat- Baharampur Line 18/09/17 08:00 20/09/17 17:30 ODB ER-II For increasing CT Ratio as requseted by SLDC (WBSETCL Jeerat) WB

243 132kV Siliguri - Melli 18/09/17 9.00 hrs 18/09/17 17.00 hrs ODB ER-II Jumper tightening SIKKIM

244 400KV TALA-I main Bay( BAY NO.-409) 18/09/17 9.00 hrs 23/09/17 17.00 hrs OCB ER-IICB (BHEL make) overhauling

245 L/R OF 765KV Dharamjaygarh -1 AT NEW RANCH 18/09/17 08:00 19/09/17 18:00 ODB POWERGRID ER-I AMP ( 17-18 ) NLDC

246 400KV Tie Bay of ICT2 & B/R2 AT JSR 18/09/17 09:30 19/09/17 17:30 8 hrs POWERGRID ER-I Pnumatic Drive unit overhauling work

247 Arambag: 400/220KV 315MVA TR#4 18/09/17 06:00 18/09/17 15:00 ODB WB PrePuja Maintenance

248 765kV Main Bus-II at Angul 18/09/17 08:00 19/09/17 18:00 OCB ER-II/Odisha/Angul SSChecking of Bus-bar Stability of 765kV Angul-Sundargarh Line-3&4 for connection with existing system under Construction Head.

NLDC

249 403 BAY(315MVA ICT#1 main bay) at Baripada 18/09/17 09;00 18/09/17 17:30 ODB ER-II/Odisha/BARIPADA S/S AMP work

250 ALL BAYS OF 132KV SIDE 18/09/17 08:00 18/09/17 17:00 ODB ER-II FOR HV TESTING & PD TEST WB

251 500 MVA ICT-I OF MAITHON SS 18/09/17 08:00 20/09/17 17:00 OCB ER-II FOR COMMISSIONING OF 2ND 500 MVA ICT DVC

252 220 KV BUS-I at Gaya S/S 19/09/17 08:00 19/09/17 18:00 ODB POWERGRID ER-I For KHIJARSARAI bay commisioning work BSEB

253 132KV BIRPARA(PGCIL)-BIRPARA(WBSETCL)-II 19/09/17 10:00 Hrs 19/09/17 14:00 Hrs ODB ER-II132KV GIS DUCT (OUT SIDE) ERECTION WORK under ERSS-XIV Pacakage.

WB

254 160MVA ICT-II OF BIRPARA 19/09/17 10:00 Hrs 19/09/17 14:00 Hrs ODB ER-II132KV GIS DUCT (OUT SIDE) ERECTION WORK under ERSS-XIV Pacakage.

WB

255 315MVA ICT-2 AT MAITHON 19/09/17 09:00 20/09/17 17:30 OCB ER-IIErection of BPI, Connection of Jumper of 500MVA ICT-1 to existing 220kV bay of 315MVA ICT-2. After that 315MVA ICT-2 will be taken out of service.

DVC

256 132kV Siliguri - Kurseong 19/09/17 9.00 hrs 19/09/17 17.00 hrs ODB ER-II Jumper tightening WB

257 400KV Tie BAY OF RKL-I & RGP-2 AT RANCHI 19/09/17 10:00 19/09/17 17:00 ODB POWERGRID ER-I AMP WORK

258 Main Bay of 400 KV Ranchi-NPPSP-I AT NRCN 19/09/17 08:00 19/09/17 18:00 ODB POWERGRID ER-I AMP ( 17-18 )

259 ICT-3 & BR-2 Tie bay no.-411 at Biharsarif 19/09/17 10:00 23/09/17 18:00 OCB POWERGRID ER-I CB Overhauling Work

Page 136: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

260 408 BAY(dubari &jamshedpur line tie bay) at Baripada 19/09/17 09;00 19/09/17 17:30 ODB ER-II/Odisha/BARIPADA S/S AMP work

261 220 KV BUS-II at Gaya S/S 20/09/17 00/01/1900 20/09/17 00/01/1900 ODB POWERGRID ER-I For KHIJARSARAI bay commisioning work BSEB

262 400KV Tie of RKL-II & RGP-3 AT RANCHI 20/09/17 10:00 20/09/17 17:00 ODB POWERGRID ER-I AMP WORK

263 Main Bay of 400 KV Ranchi-NPPSP-II AT NRCN 20/09/17 08:00 20/09/17 18:00 ODB POWERGRID ER-I AMP ( 17-18 )

264 400KV Tie Bay of ICT2 & B/R2 AT JSR 20/09/17 09:30 21/09/17 17:30 8 hrs POWERGRID ER-I Pnumatic Drive unit overhauling work

265 132 KV MAIN BUS AT 220/132 KV PURNEA SS 20/09/17 09:00 20/09/17 10:00 ODB POWERGRID ER-I GIS WORK BSEB

266 160 MVA ICT#1 AT PURNEA 20/09/17 09:00 23/09/17 16:00 OCB POWERGRID ER-I GIS WORK BSEB

267400kV, 125MVAR Bus Reactor-3 at Angul

20/09/17 10:00 20/09/17 18:00 ODB ER-II/Odisha/Angul SSAMP work.

268400 kV Jeypore-Indravati S/C Line

20/09/17 06:00 21/09/17 18:00 ODB ER-II/Odisha/JeyporeFor Replacement of PID Defective Insulators in Jey-Ivt Line (If Not available in the month of Aug 2017) at Locations Loc.No. 27,34,48,71,107,109,111,121, 124,125,126,127,128,129,130,

NLDC

269400 KB Rourkela-Raigarh -I & Rourkela - Sundargarh-I (both circuits together)

20/09/17 08:00 24/09/17 17:00 OCB ER-II/Odisha/Sundargarh TLCErection of tower under line and Stringing work of LILO of 400 KV D/C Rourkela-Raigarh (Ckt- I)

NLDC

270765 KV D/C Jharsuguda- Dharamjaygarh Transmission line (Ckt-I & II)

20/09/17 08:00 22/09/17 17:00 OCB ER-II/Odisha/Sundargarh TLCSwapping arrangement :Stringing work of 765KV Jharsuguda - Dharamjaygarh  TL, Ckt-III & IV with Ckt-I & II

NLDC

271 400 kV Bus-I at Baripada 20/09/17 08:30 20/09/17 17:30 ODB ER-II/Odisha/BARIPADA S/S For GIS bay EXTN works(for isolation of GIS Bus-I)and HV testing

272 400 kV Bay 413 CB(GIS) at Baripada 20/09/17 08:30 25/09/17 17:30 OCB ER-II/Odisha/BARIPADA S/S For GIS Bus-II ext. works

273 400KV Kahalgaon-Barh Line-2 20/09/17 09:30hrs 20-Sep-2017 17:30 hrs ODB KAHALGAON PM works & relay testing

274 400KV Fkk-Durgapur Line-2 20/09/17 09:30hrs 21-Sep-2017 17:30 hrs ODB FARAKKA CVT Replacement, CB & Relay Testing

275 400 kV main bay of BR-II 20/09/17 08:00 21/09/17 18:00 OCB POWERGRID ER-I For Pneumatic drive Overhauling work.

276 160MVA ICT-I (BIRPARA-PGCIL) 20/09/17 07:00 20/09/17 11:00 ODB ER-II FOR JUMPERING & CHARGING WB

Page 137: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

277 132KV BIRPARA(PGCIL)-BIRPARA(WBSETCL)-I 20/09/17 12:00 20/09/17 16:00 ODB ER-II FOR JUMPERING & CHARGING WB

278 125MVAR Bus Reactor - 1 at ALIPURDUAR 21/09/17 09:00 23/09/17 18:00 OCB ER-II Change of Radiator (01 no) - Oil leakage from radiator

279 125 MVAR B/R -1 AT PATNA 21/09/17 09:00 31/09/17 18:00 ODB POWERGRID ER-I Fire fighting work , construction activity

280 400 KV Indravati-Jeypore Main Bay at Indravati 21/09/17 09:00 25/09/17 18:00 OCB ER-II/Odisha/Indravati Overhauling of Main Bay (403) CB Mechanism

281 410 BAY(pandiabilli line main bay) at Baripada 21/09/17 09:00 21/09/17 17:30 ODB ER-II/Odisha/BARIPADA S/S AMP work

282 400KV BUS-I AT GAYA 21/09/17 08:00 21/09/17 18:00 ODB POWERGRID ER-I Bay extension work for Gaya Navinagar Line

283 160MVA ICT-II (BIRPARA-PGCIL) 21/09/17 07:00 21/09/17 11:00 ODB ER-II FOR JUMPERING & CHARGING WB

284 132KV BIRPARA(PGCIL)-BIRPARA(WBSETCL)-II 21/09/17 12:00 21/09/17 16:00 ODB ER-II FOR JUMPERING & CHARGING WB

285 400 KV Subhasgram-Haldia Line-2 22/09/17 08:00 22/09/17 17:30 ODB ER-II Jumper Tightning of Haldia Line-2 WB

286 MAIN BAY OF JSR -II AT CHAIBASA 22/09/17 08:00 22/09/17 17:00 ODB POWERGRID ER-I AMP

287 BkTPP: Diversion of 400KV JEERAT Bay 22/09/17 08:00 22/09/17 12:00 ODB WB Thermography survey

288 400KV Fkk-Durgapur Line-1 22/09/17 09:30hrs 23-Sep-2017 17:30 hrs ODB FARAKKA CB & Relay Testing

289 400KV BUS-II AT GAYA 22/09/17 08:00 22/09/17 18:00 ODB POWERGRID ER-I Bay extension work for Gaya Navinagar Line

290 220 Kv bus-I AT Ramchandrapur 22/09/17 08:00 22/09/17 18:00 ODB POWERGRID ER-I For commissioning of 315 MVA Ict-III at Jamshedpur JSEB

291 400kV JSR-Maithon Line 22/09/17 08:00 22/09/17 18:00 OCB POWERGRID ER-I Fror line bay AMP

292 315 MVA ICT-II OF MAITHON 22/09/17 08:00 24/09/17 17:00 OCB ER-IIFOR CHARGING OF 1ST 500 MVA ICT IN PLACE OF EXISTING 315 MVA ICT.

DVC

293 132 kV LKR-LKR-II 23/09/17 08:00 27/09/17 18:00 ODB POWERGRID ER-I For Erection of LM Tower-1 BSEB

294 132 kV LKR-Jamui-1 23/09/17 08:00 27/09/17 18:00 ODB POWERGRID ER-I For Erection of LM Tower-2 BSEB

295 132KV BAY OF 400/132KV 200MVA ICT-I AT LAKHISARAI 23/09/17 08:00 27/09/17 18:00 ODB POWERGRID ER-I For Erection of LM Tower-3 BSEB

296 220 Kv bus-II AT Ramchandrapur 23/09/17 08:00 23/09/17 18:00 ODB POWERGRID ER-I For commissioning of 315 MVA Ict-III at Jamshedpur JSEB

Page 138: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

297 400 kv Maithon-Ranchi 24/09/17 09:00 24/09/17 17:30 ODB ER-II Insulator Replacement at MD Line

298 400 kv Maithon-RTPS 25/09/17 09:00 25/09/17 17:30 ODB ER-II Insulator Replacement at MD Line DVC

299 400kV Subhasgram- Sagardighi Line 25/09/17 08:00 27/09/17 17:30 ODB ER-II PID Test & Insulator replacement work at Line WB

300 400kV NSLG-Purnea Ckt-1 25/09/17 07.00 hrs 26/09/17 17.00 hrs ODB ER-II Defect Insulator replacements & jumper tightening

301 400KV RANGPO-I & BONG-I Tie Bay( BAY NO.-411) 25/09/17 9.00 hrs 30/09/17 17.00 hrs OCB ER-II CB (BHEL make) overhauling

302 400 KV BUS COUPLER AT MALDA 25/09/17 09:00 25/09/17 17:00 ODB ER-II AMP

303 765kV Angul-Sundargarh Line-1 by Angul TLM 25/09/17 08:00 25/09/17 18:00 ODB ER-II/Odisha/Angul TLAMImprovement & strenghthening of line jumpers to prevent swing during high speed wind to avoid tripping in future & improvement of line availability & reliability. And NTAMC Validation work

NLDC

304 400KV Bus-I at Sundargarh 25/09/17 08:00 26/09/17 18:00 OCB ER-II/Odisha/SundergarhFor Jumpring, Checking of Bus stability, Busbar & LBB Protection for 400KV GIS extn work under construction head.

305 400 kV Bus-I at Baripada 25/09/17 08:30 25/09/17 17:30 OCB ER-II/Odisha/BARIPADA S/S For reconnection of jumpers of GIS BUS-I

306 132 KV PURNEA - PURNEA BSPTCL#2 LINE 26/09/17 09:00 08/10/17 16:00 OCB POWERGRID ER-I GIS WORK BSEB

307 400 kV Bus-II at Baripada 26/09/17 08:30 26/09/17 17:30 ODB ER-II/Odisha/BARIPADA S/S For GIS bay EXTN works(for isolation of GIS Bus-II)and HV testing

308 400 kV Bay 415 CB(GIS) at Baripada 26/09/17 08:30 30/09/17 17:30 OCB ER-II/Odisha/BARIPADA S/S For GIS Bus-Iext. Works

309 765kV Angul-Sundargarh Line-2 26/09/17 08:00 26/09/17 18:00 ODB ER-II/Odisha/Angul TLAMImprovement & strenghthening of line jumpers to prevent swing during high speed wind to avoid tripping in future & improvement of line availability & reliability and NTAMC Validation Work

NLDC

3103X105MVA ICT #1 & 125MVAR Reactor TIE Bay (408) at Jeypore

26/09/17 09:30 26/09/17 17:30 ODB ER-II/Odisha/Jeypore AMP of TIE Bay (408) NLDC

311 400kV NSLG-Purnea Ckt-2 27/09/17 07.00 hrs 28/09/17 17.00 hrs ODB ER-II Defect Insulator replacements & jumper tightening

312 400kV Angul-Meramundali Line-1 27/09/17 08:00 27/09/17 18:00 ODB ER-II/Odisha/Angul TLAMImprovement & strenghthening of line jumpers to prevent swing during high speed wind to avoid tripping in future & improvement of line availability & reliability and NTAMC Validation work

GRIDCO

313 400KV Bus-II at Sundargarh 27/09/17 08:00 28/09/17 18:00 OCB ER-II/Odisha/SundergarhFor Jumpring, Checking of Bus stability, Busbar & LBB Protection for 400KV GIS extn work under construction head.

314 132KV TBC & 132 kV Main Bus AT LAKHISARAI 28/09/17 08:00 30/09/17 18:00 ODB POWERGRID ER-I For Erection of LM Tower-3 BSEB

315 ICT-I (3x 105 MVA) at Jeypore 28/09/17 10:30 28/09/17 11:30 ODB ER-II/Odisha/JeyporeFor changing ICT-I combination form Unit-I,II,III, to Unit-II , III & IV for charging Unit-IV after Oil Refilling Works due to H2 violation

GRIDCO

316 315 MVA ICT-I AT SUBHASGRAM 30/09/17 08:00 30/09/17 17:30 ODB ER-II Tertiary CT- Bph Replacement Work WB CONSENT REUQIRED

317 400 kV Bus-II at Baripada 30/09/17 08:30 30/09/17 17:30 OCB ER-II/Odisha/BARIPADA S/S For reconnection of jumpers of GIS BUS-II

318 220 KV ALIPURDUAR-SALAKATI-D/C 30/09/17 09:00 15/11/17 17:00 OCB ER-IIFOR SHIFTING OF EXISTING TOWER LOC: 196 TO UPCOMING DD+18 TOWERS, DUE TO RECENT FLOOD AT NORTH BENGAL

NLDC

319 220kV Bus Coupler at Rengali 30/09/17 09:00 30/09/17 17:00 ODB ER-II/Odisha/Rengali Replacement of Tan delta violated CT (R&B Ph.)

Page 139: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Date Time Date Time

1 Sipat-Ranchi Ckt-2 04-Sep-17 07:30 hrs 06-Sep-17 19:00 Hrs. Continuous NTPC For Annual maint works WRPC

2 765kV D'JAIGARH-RANCHI I 18-Sep-17 10:00 18-Sep-17 13:00 Daily POWERGRIDTO ATTEND CORONA ISSUES INSIDE THE WAVETRAP WHICH IS CAUSING FREQUENT PLCC ALARAMS

WRPC

3 765kV D'JAIGARH-RANCHI II 19-Sep-17 10:00 19-Sep-17 13:00 Daily POWERGRIDTO ATTEND CORONA ISSUES INSIDE THE WAVETRAP WHICH IS CAUSING FREQUENT PLCC ALARAMS,ROTATION OF SPARE REACTOR WITH LINE REACTOR FOR ATTENDING OIL

WRPC

4 400kV RANCHI-SIPAT I 19-Sep-2017 8:00 24-Sep-2017 18:00 Continious POWERGRID For Rectification of Bend C-leg at Tower No 664, on permanent basis WRPC

5 400kV RANCHI-SIPAT II19-Sep-17 08:00 24-Sep-17 18:00

Continious POWERGRID For Rectification of Bend C-leg at Tower No 664, on permanent basis WRPC

6 765kV D'JAIGARH-RANCHI I25-Sep-17 08:00 28-Sep-17 18:00

Daily POWERGRID For Replacement of Quad spacer Cap against Damage/Open WRPC

7 400 kV Bongaigaon-Balipara # 1 18-Sep-2017 10:00 18-Sep-2017 12:00 Daily POWERGRID For AMP of Line Reactor and Line equipments NERPC

8 Balia-Patna Ckt- 3(400 kV) 20-Sep-2017 9:00 22-Sep-2017 17:00 Daily POWERGRID For Fire Fighting erection works of Line Reactor , at Balia NRPC

9 Balia-Patna Ckt- 4(400 kV) 25-Sep-2017 9:00 27-Sep-2017 17:00 Daily POWERGRID For Fire Fighting erection works of Line Reactor , at Balia NRPC

Name of Requesting Agency outages proposed in

Outages proposed in other RPCs requiring ERPC approval

Sl No Name of Elements To

Reason From

Basis

Page 140: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Annexure-D4

Page 141: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.
Page 142: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

UNDER-INJECTION OF RRAS PROVIDER DURING RRAS UP PERIOD

Annexure-D5.1

Page 143: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

RRAS DEVIATION CLAUSE • As per CERC Ancillary Services Operations Regulation 2015, clause no 7.2

“The RRAS Provider shall inject or back down generation as per the instruction of the Nodal Agency for Regulation Up and Regulation Down respectively”

• As per clause 5.3 of DOP of RRAS

“The RRAS Provider shall increase or decrease the generation as per the instruction of the Nodal Agency given through the respective RLDC for Regulation Up and Regulation Down respectively.”

• As per clause 5.4 of DOP of RRAS

“The continuity of the RRAS shall be ensured by the RRAS provider over the period of the despatch.”

• Above mentioned clause clearly mentioned that RRAS provider have to maintain their generation as per schedule during RRAS period, however in real time It is observed that Maximum ER RRAS provider failed to maintain their generation as per schedule.

Page 144: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Performance of Barh

Page 145: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Performance of Barh

Page 146: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Performance of Barh

Page 147: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Performance of FSTPP I & II

Page 148: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Performance of FSTPP I & II

Page 149: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Performance of FSTPP I & II

Page 150: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Performance of KHSTPP I

Page 151: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Performance of KHSTPP I

Page 152: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Performance of KHSTPP I

Page 153: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Performance of KHSTPP II

Page 154: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Performance of KHSTPP II

Page 155: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Performance of KHSTPP II

Page 156: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

• As per CERC Ancillary Services Operations Regulation 2015, clause no 13.7

“Sustained failure to provide the RRAS (barring unit tripping) by RRAS Provider(s) shall attract penalties on account of gaming. Violation of directions of RLDC for RRAS shall also make the RRAS Provider(s) liable for penalties in terms of section 29 of the Act.”

• As per 9.13 clause of Detail Operating Procedure of RRAS

“Sustained failure, i.e., failure to provide the RRAS (barring unit tripping) by RRAS Provider(s) more than three (3) times during a month shall be brought to the notice of the CERC.”

Page 157: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

SL.NO TIE-LINE LINE OWNED BY

Bay equip Ownership

Responsibility of maintaining bay eqp.

Responsibility of ensuring Real Time data

Responsibility of sending RI/DR/EL

Bay equip Ownership

Responsibility of maintaining bay eqp.

Responsibility of ensuring Real Time

data

Responsibility of sending RI/DR/EL

1 GAYA-VARANASI POWERGRID POWERGRID(ER) POWERGRID(NR)2 GAYA-BALIA POWERGRID POWERGRID(ER) POWERGRID(NR)3 PUSAULI-FATEHPUR POWERGRID POWERGRID(ER) POWERGRID(NR)4 RANCHI(NEW)-DHARAMJAYGARH POWERGRID POWERGRID(ER) POWERGRID(WR)5 JHARSUGUDA-DHRAMJAYGARH POWERGRID POWERGRID(ER) POWERGRID(WR)6 ANGUL-SRIKAKULAM POWERGRID POWERGRID(ER) POWERGRID(SR)

7 ANGUL-JHARSUGUDA POWERGRID POWERGRID POWERGRID

7 MUZZFARPUR-GOROKHPUR POWERLINKS POWERGRID(ER) POWERGRID(NR)8 PATNA-BALIA POWERGRID POWERGRID(ER) POWERGRID(NR)9 BIHARSHARIFF-BALIA POWERGRID POWERGRID(ER) POWERGRID(NR)

10 BIHARSHARIFF-VARANASI POWERGRID POWERGRID(ER) POWERGRID(NR)BARH-MOTIHARI L(LILO) POWERGRID(ER) DMTCLMOTIHARI-GOROKHPUR L(LILO) DMTCL POWERGRID(NR)

12 SASARAM(N) -SARNATH POWERGRID POWERGRID(ER) POWERGRID(NR)14 SASARAM(N) -ALLAHABAD POWERGRID POWERGRID(ER) POWERGRID(NR)15 BINAGURI-BONGAIGAON-I, II POWERGRID POWERGRID(ER) POWERGRID(NER)16 AILPURDUAR-BONGAIGAON-I, II PGCIL(LILO) POWERGRID(ER) POWERGRID(NER)20 TEESTA V-RANGPO POWERGRID NHPC POWERGRID21 SEL-RAIGARH POWERGRID & SEL SEL POWERGRID(WR)22 JHRASUGUDA-IBEUL IBEUL POWERGRID IBEUL23 JHRASUGUDA-RAIGARH IBEUL POWERGRID(ER) POWERGRID(WR)24 ROURKELA-RAIGARH POWERGRID POWERGRID(ER) POWERGRID(WR)25 ROURKELA-SEL POWERGRID & SEL POWERGRID SEL26 RANCHI -SIPAT POWERGRID POWERGRID(ER) POWERGRID(WR)28 FARAKKA-BEHRAMPUR POWERGRID NTPC POWERGRID29 FARAKKA-SAGARDIGHI POWERGRID NTPC WBPDCL30 FARAKKA - MALDA POWERGRID NTPC POWERGRID31 FARAKKA - PARULIA POWERGRID NTPC POWERGRID32 KAHALGAON -BANKA POWERGRID NTPC POWERGRID34 SAGARDIGHI-BEHRAMPUR POWERGRID WBPDCL POWERGRID35 SAGARDIGHI-SUBHASGRAM POWERGRID WBPDCL POWERGRID36 SAGARDIGHI-PARULIA WBSETCL WBPDCL POWERGRID(ER)38 JEERAT-SUBHASGRAM POWERGRID WBSETCL POWERGRID39 SUBHASGRAM(PG)-HALDIA HEL POWERGRID HEL40 PARULIA-BIDHANAGAR WBSETCL POWERGRID WBSETCL41 KHARAGPUR-BARIPADA WBSETCL & OPTCL WBSETCL POWERGRID(ER)45 DSTPS - JAMSHEDPUR POWERGRID DVC POWERGRID46 KODERMA-BIHARSARIFF POWERGRID DVC POWERGRID51 RAGUNATHPUR-MAITHON POWERGRID DVC POWERGRID52 JAMSEDPUR-AHUNIK APNRL POWERGRID APNRL53 JAMSHEDPUR-TISCO POWERGRID DVC POWERGRID55 JEYPORE-GAZUWAKA POWERGRID POWERGRID(ER) POWERGRID(SR)

OWNERSHIP DETAILS

A) 765 KV LINES

B) 400 KV LINES

FROM END TO END

Annexure-D5.2

Page 158: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

58 INDRAVATI-INDRAVATI OPTCL POWERGRID(ER) OPTCL59 TSTPP-MERAMUNDALI POWERGRID NTPC OPTCL61 BARIPADA-NEW DUBURI POWERGRID POWERGRID(ER) OPTCL62 MENDHASAL-NEW DUBURI OPTCL POWERGRID(ER) OPTCL64 TSTPP - RENGALI POWERGRID NTPC POWERGRID65 KHARAGPUR-CHAIBASA PKTCL WBSETCL POWERGRID66 MENDHASAL-PANDIABILI POWERGRID OPTCL POWERGRID67 BARIPADA – PANDIABILI POWERGRID WBSETCL POWERGRID

NEW RANCHI-NEW PPSP PKTCL POWERGRID WBSETCL71 FARAKKA-GOKARNO POWERGRID NTPC WBSETCL72 DIKCHU-TEESTA-III SKPPL+TPTL DIKCHU TEESTA-III73 RANGPO-TEESTA-III POWERGRID+TPTL POWERGRID TEESTA-III2 BANKA-BIHARSARIFF POWERGRID POWERGRID POWERGRID3 LAKHISARAI-BIHARSARIFF POWERGRID POWERGRID POWERGRID4 KAHALGAON -LAKHISARAI POWERGRID NTPC POWERGRID5 BIHARSHARIFF-PURNEA ENICL POWERGRID POWERGRID6 MAITHON-GAYA POWERGRID POWERGRID POWERGRID7 KAHALGAON -BARH POWERGRID NTPC NTPC8 BARH -PATNA POWERGRID NTPC POWERGRID9 PATNA- KISHANGANJ POWERGRID POWERGRID POWERGRID

10 PURNEA - BINAGURI I & II POWERGRID POWERGRID POWERGRID11 PURNEA-KISHANGANJ POWERGRID POWERGRID POWERGRID12 BINAGURI-KISHANGANJ POWERGRID POWERGRID POWERGRID13 PURNEA - MUZAFFARPUR POWERLINKS POWERGRID POWERGRID14 BIHARSHARIFF-MUZAFFARPUR POWERGRID POWERGRID POWERGRID15 BIHARSHARIFF- PUSAULI POWERGRID POWERGRID POWERGRID16 FARAKKA - KAHALGAON I & II POWERGRID NTPC NTPC17 FARAKKA-KAHALGAON III & IV POWERGRID NTPC NTPC18 BOKARO-KODERMA POWERGRID DVC DVC19 MALDA - PURNEA POWERGRID POWERGRID POWERGRID20 MERAMUNDALI - MENDASAL OPTCL OPTCL OPTCL21 RENGALI-KEONJHAR OPTCL POWERGRID OPTCL22 KEONJHAR- BARIPADA OPTCL POWERGRID POWERGRID23 JEYPORE - INDRAVATI POWERGRID POWERGRID POWERGRID24 INDRAVATI - RENGALI POWERGRID POWERGRID POWERGRID25 TSTPP - ROURKELA POWERGRID NTPC POWERGRID26 ROURKELA- JHARSIGUDA POWERGRID POWERGRID POWERGRID27 JAMSHEDPUR - CHAIBASA POWERGRID POWERGRID POWERGRID28 CHAIBASA- ROURKELA POWERGRID POWERGRID POWERGRID29 KTPS - CHANDITALA WBSETCL WBPDCL WBSETCL29 CHANDITALA - JEERAT WBSETCL WBSETCL WBSETCL30 BAKRESWAR - JEERAT WBSETCL WBPDCL WBSETCL31 BAKRESWAR - ARAMBAGH WBSETCL WBPDCL WBSETCL

NEW PPSP - ARAMBAGH WBSETCL WBSETCL WBSETCLNEW PPSP - PPSP WBSETCL WBSETCL WBSEDCL

33 PPSP - BIDHANAGAR WBSEDCL WBPDCL WBSETCL34 KTPS - ARAMBAGH WBSETCL WBPDCL WBSETCL35 KTPS-KHARGPUR WBSETCL WBPDCL WBSETCL36 KTPS-KHARGPUR WBSETCL WBPDCL WBSETCL37 PARULIA - JAMSHEDPUR POWERGRID POWERGRID POWERGRID38 MAITHON - JAMSHEDPUR POWERGRID POWERGRID POWERGRID39 MAITHON - RANCHI POWERGRID POWERGRID POWERGRID40 DSTPS-RAGHUNATHPUR I & II DVC DVC DVC41 JAMSHEDPUR-BARIPADA POWERGRID POWERGRID POWERGRID42 RANCHI-RANCHI NEW POWERGRID POWERGRID POWERGRID43 RANCHI-ROURKELA-I&II POWERGRID POWERGRID POWERGRID44 BINAGURI-RANGPO POWERGRID POWERGRID POWERGRID

Page 159: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

45 NEW RANCHI-CHANDWA POWERGRID POWERGRID POWERGRID46 GAYA- CHANDWA POWERGRID POWERGRID POWERGRID47 AILPURDUAR-BINAGURI-I,II PGCIL(LILO) POWERGRID(ER) POWERGRID(ER)48 MUZAFFARPUR-DARBHANGA DMTCL POWERGRID(ER) DMTCL49 SEL- MEERAMANDALI POWERLINKS SEL OPTCL50 BARIPADA-PANDIABILI POWERGRID POWERGRID POWERGRID51 MEERAMUNDALI- NEW DUBURI POWERGRID OPTCL POWERGRID

74 PATNA-SIPARA BSPHCL POWEGRID BSPHCL76 PUSUALI-SAHUPURI BSPHCL & UPPCL POWERGRID UPPCL78 PATNA-KHAGUAL BSPHCL POWERGRID BSPHCL80 NEW SASARAM- ARRAH POWERGRID BSPHCL POWERGRID81 BODHGAYA-GAYA(PG) BSPHCL & PG BSPHCL POWERGRID82 DEHRI-GAYA(PG) BSPHCL & PG BSPHCL POWERGRID83 MUZZFARPUR-KANTI POWERLINKS POWERGRID BSPHCL84 MUZZAFFARPUR-HAZIPUR-I & II BSPTCL POWERGRID BSPTCL87 BALIMELA-U.SILLERU APTRANSCO OPTCL APTRASCO88 JINDAL-JAMSHEDPUR OPTCL & DVC OPTCL DVC89 JODA-RAMCHANDRAPUR OPTCL & JUSNL OPTCL JUSNL90 BUDHIPADAR-KORBA II & III OPTCL & CSEB OPTCL CHATTISGARH91 BUDHIPADAR-RAIGARH I POWERGRID OPTCL CHATTISGARH92 TSTPP-MERAMUNDALI OPTCL NTPC OPTCL93 TSTPP-RENGALI HPS OPTCL NTPC OPTCL94 BISRA(PG)-TARKERA(OPTCL) OPTCL POWERGRID OPTCL95 JEYPORE(PG)-JAYNAGAR(OPTCL) OPTCL POWERGRID OPTCL96 TSTPP-TALCHER OPTCL NTPC OPTCL97 FARAKKA-LALMATIA ECL NTPC NTPC98 RENGALI-RENGALI OPTCL POWERGRID OPTCL99 BARIPADA-BALASORE OPTCL POWERGRID OPTCL100 MAITHON(PG)-K'SWARI(DVC) DVC POWERGRID DVC102 CHANDIL-SANTALDIH WBSETCL & JUSNL JUSNL WBSETCL103 RANCHI-HATIA JUSNL POWERGRID JUSNL105 TENUGHAT-BIHARSHARIF BSPHCL & JUSNL JUSNL BSPHCL106 JAMSHEDPUR-RAMCHANDRAPUR POWERGRID POWERGRID JUSNL107 MAITHON(PG)-DHANBAD(DVC) DVC POWERGRID DVC108 PARULIA(PG)-PARULIA(DVC) DVC POWERGRID DVC109 WARIA-BIDHANNAGAR DVC & WBSETCL DVC WBSETCL112 SUBH'GRM(PG) - NEWTOWN WBSETCL POWERGRID WBSETCL113 SUBH'GRM(PG) - SUBH'GRM (WB) WBSETCL POWERGRID WBSETCL114 SUBH'GRM(PG) - EMSS(CESC) CESC POWERGRID CESC115 SUBH'GRM(PG) - BANTALA WBSETCL POWERGRID WBSETCL118 BIRPARA- CHUKHA POWERGRID POWERGRID POWERGRID119 BIRPARA-MALBASE POWERGRID POWERGRID POWERGRID120 ALIPURDUAR-SALAKATI POWERGRID POWERGRID(ER) POWERGRID(NER)122 NEW MELLI- JLHEP DANS POWERGRID DANS124 DARBHANGA-MOTIPUR BSPTCL DMTCL BSPTCL125 DARBHANGA-SAMASTIPUR(UJIYARPUR) BSPTCL DMTCL BSPTCL127 BOLANGIR-KATAPALLI OPTCL POWERGRID OPTCL128 BOLANGIR-SADHEPALLI OPTCL POWERGRID OPTCL129 PANDIABILI-ATRI OPTCL POWERGRID OPTCL130 PANDIABILI-SAMANGARA OPTCL POWERGRID OPTCL52 BIHARSHARIFF-FATUAH BSPHCL BSPHCL BSPHCL53 BIHARSHARIFF-BODHAGYA BSPHCL BSPHCL BSPHCL54 BIHARSHARIFF-BEGUSARAI BSPHCL BSPHCL BSPHCL55 MTPS-BEGUSARAI BSPHCL BSPHCL BSPHCL56 MTPS-DARBHANGA BSPHCL BSPHCL BSPHCL57 MTPS-GOPALGANJ BSPHCL BSPHCL BSPHCL

C) 220 KV LINES

Page 160: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

58 SASARAM-ARRAH POWERGRID POWERGRID POWERGRID60 WARIA-PARULIA DVC DVC DVC61 WARIA-MEJIA DVC DVC DVC62 CTPS A-DHANBAD DVC DVC DVC63 CTPS B-DHANBAD DVC DVC DVC64 DHANBAD-GIRIDIH DVC DVC DVC65 BOKARO-JAMSHEDPUR DVC DVC DVC66 KASBA-EMBYPASS CESC WBSETCL CESC67 KASBA-SUBHASGRAM(WB) WBSETCL WBSETCL WBSETCL69 BOKARO-CTPS B DVC DVC DVC70 KALYANESHWARI-MEJIA DVC DVC DVC71 KALYANESHWARI-BURNPUR DVC DVC DVC72 BURNPUR-MEJIA DVC DVC DVC73 MEJIA-MUCHIPARA DVC DVC DVC74 MEJIA-BARJORA DVC DVC DVC75 PARULIA-MUCHIPARA DVC DVC DVC76 BOKARO-RAMGARH DVC DVC DVC77 PTPS -TENUGHAT JUSNL JUSNL TVNL78 PATRATU-HATIA JUSNL JUSNL JUSNL79 CHANDIL-RAMCHANDRAPUR JUSNL JUSNL JUSNL80 JEYANAGAR-U.KOLAB OPTCL OPTCL OHPC81 MERAMANDALI-NALCO OPTCL NTPC NALCO82 MERAMUNDALI - BIDANASI OPTCL OPTCL OPTCL83 MERAMUNDALI - DUBURI(OLD) OPTCL OPTCL OPTCL84 KATAPALLI-BUDHIPADAR OPTCL OPTCL OPTCL85 IBTPS - BUDHIPADAR OPTCL OPGC OPTCL86 TARKERA-BUDHIPADAR OPTCL OPTCL OPTCL87 TARKERA-CHANDIPOSH OPTCL OPTCL OPTCL88 TARKERA-BARKOT OPTCL OPTCL OPTCL89 RENGALI-CHANDIPOSH OPTCL OPTCL OPTCL90 RENGALI-BARKOT OPTCL OPTCL OPTCL91 U. KOLAB-THERUVALI OPTCL OHPC OPTCL92 U. KOLAB-JAYANAGAR OPTCL OHPC OPTCL93 BALIMELA-JEYNAGAR OPTCL OHPC OPTCL94 TALCHER-MERAMUNDALI OPTCL NTPC OPTCL95 MERAMUNDALI - BHANJNAGAR OPTCL OPTCL OPTCL96 MENDHASAL -BHANJNAGAR OPTCL OPTCL OPTCL97 MENDHASAL - NAYAGARH OPTCL OPTCL OPTCL98 NAYAGARH - BHANJNAGAR OPTCL OPTCL OPTCL99 THERUVALLI - BHANJNAGAR OPTCL OPTCL OPTCL100 THERUVALLI - LAXMIPUR OPTCL OPTCL OPTCL101 THERUVALLI - NARENDRAPUR OPTCL OPTCL OPTCL102 MENDHASAL - NARENDRAPUR OPTCL OPTCL OPTCL103 MENDHASAL - CHANDAKA OPTCL OPTCL OPTCL104 JAYANAGAR - LAXMIPUR OPTCL OPTCL OPTCL105 UIHEP-THERUVALI OPTCL OHPC OPTCL106 KTPS-HOWRAH WBSETCL WBPDCL WBSETCL107 BISHNUPUR-SANTALDIH WBSETCL WBSETCL WBPDCL108 SANTALDIH-BIDHANNAGR WBSETCL WBDPCL WBSETCL109 BIDHANNAGAR-DPL WBSETCL WBSETCL DPL110 BIDHANNAGAR-BAKRESWAR WBSETCL WBSETCL WBPDCL111 SATGACHIA-BAKRESWAR WBSETCL WBSETCL WBPDCL112 KHARAGPUR- MIDNAPORE I&II WBSETCL WBSETCL WBSETCL113 ARAMBAGH- MIDNAPORE WBSETCL WBSETCL WBSETCL114 ARAMBAGH-N.BISHNUPUR WBSETCL WBSETCL WBSETCL115 ARAMBAGH- DOMJUR WBSETCL WBSETCL WBSETCL116 ARAMBAGH- RISHRA WBSETCL WBPDCL WBSETCL117 JEERAT-NEWTOWN WBSETCL WBSETCL WBSETCL118 JEERAT-SATGACHIA WBSETCL WBPDCL WBSETCL119 SATGACHIA-KRISHNANAGAR WBSETCL WBPDCL WBSETCL120 BAKRESWAR-SADAIPUR WBSETCL WBPDCL WBSETCL120 SADAIPUR-GOKARNO WBSETCL WBPDCL WBSETCL

Page 161: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

121 GOKARNO-SAGARDIGHI WBSETCL WBSETCL WBPDCL122 GOKARNO-KRISHNANAGAR WBSETCL WBSETCL WBPDCL123 SUBHASGRAM (WB)- LAKHIKANTPUR WBSETCL WBSETCL WBSETCL124 DALKHOLA-PURNEA POWERGRID WBSETCL WBSETCL125 BIRPARA-BINAGURI POWERGRID POWERGRID POWERGRID

BINAGURI-SILIGURI POWERGRID POWERGRID POWERGRID126 JEERAT-KASBA WBSETCL WBPDCL WBSETCL127 JEERAT- DHARAMPUR WBSETCL WBPDCL WBSETCL128 DHARAMPUR- RISHRA WBSETCL WBPDCL WBSETCL

SILIGURI-KISHANGANJ POWERGRID POWERGRID POWERGRID129 DALKHOLA-KISHANGANJ POWERGRID POWERGRID POWERGRID130 DALKHOLA-MALDA POWERGRID POWERGRID POWERGRID131 RANGPOO- NEW MELLI POWERGRID POWERGRID POWERGRID132 ALIPURDUAR-BIRPARA POWERGRID POWERGRID(ER) POWERGRID(ER)

131 MUZZAFARPUR- DHALKEBARCross Border Power

Trans. Ltd. POWERGRID NEPAL132 BARHI - B'SHARIFF BSPHCL & DVC DVC BSPHCL133 BARHI-RAJGIR BSPHCL & DVC DVC BSPHCL134 DEOGHAR-SULTANGANJ BSPTCL & JUSNL JUSNL BSPHCL135 KAHALGAON-KAHALGAON POWERGRID BSPHCL NTPC136 ARRAH-ARRAH POWERGRID BSPHCL POWERGRID137 DUMRAON-ARRAH POWERGRID BSPHCL POWERGRID138 PURNEA(PG)-PURNEA(BS) BSPHCL BSPHCL POWERGRID139 PURNEA(PG)-KISANGANJ BSPHCL BSPHCL POWERGRID140 DEHRI--PUSUALI POWERGRID BSPHCL POWERGRID141 KARMANASA--PUSUALI POWERGRID BSPHCL POWERGRID142 KARMANASA-SAHUPURI BSPHCL & UPPCL BSPHCL UPPCL143 KARMANASA-CHANDAULI BSPHCL & UPPCL BSPHCL UPPCL144 SONENAGAR - RIHAND BSPHCL & UPPCL BSPHCL UPPCL145 MAITHON-JAMTARA DVC & JUSNL DVC JUSNL146 KHARAGPUR-KHARAGPUR DVC DVC WBSETCL147 KOLAGHAT-KOLAGHAT DVC DVC WBSETCL148 MACHKUND-VIZAG APTRANSCO OPTCL APTRANSCO149 JODA-KENDPOSI OPTCL & JUSNL OPTCL JUSNL150 BARIPADA-BANGIRIPOSI OPTCL POWERGRID OPTCL151 BARIPADA-BARIPADA OPTCL POWERGRID OPTCL152 GARWA-SONENAGAR BSPHCL & JUSNL JUSNL BSPHCL153 LALMATIA-SABOUR BSPHCL & JUSNL JUSNL BSPHCL154 CHANDIL-MANIQUE JUSNL & DVC JUSNL DVC155 PATRATU-PATRATU JUSNL & DVC JUSNL DVC156 GARWA-RIHAND JUSNL & UPPCL JUSNL UPPCL157 RANGIT-RAMMAM POWERGRID NHPC WBSETCL158 KAHALGAON-SABOUR POWERGRID NTPC BSPHCL159 KAHALGAON-LALMATIA POWERGRID NTPC JUSNL160 BIRPARA-BIRPARA WBSETCL POWERGRID WBSETCL161 MALDA-MALDA WBSETCL POWERGRID WBSETCL162 SILIGURI-NBU WBSETCL POWERGRID WBSETCL

SILIGURI - NJP WBSETCL POWERGRID WBSETCL163 RANGIT -SAGBARI SIKKIM NHPC SIKKIM164 ARHA-JAGDISHPUR BSPHCL POWERGRID BSPHCL165 RANGIT-RANGPO POWERGRID NHPC POWERGRID166 RANGIT-KURSEONG POWERGRID NHPC WBSETCL167 RANGIT-SAGBARI SIKKIM NHPC SIKKIM168 CHUJACHEN-GANGTOK POWERGRID & GATI GATI INFRA POWERGRID169 BANKA-SABOUR BSPTCL POWERGRID BSPTCL170 BANKA-BANKA BSPTCL POWERGRID BSPTCL

C) 132 KV LINES

Page 162: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

171 RANGPO-CHUJACHEN GATI INFRA POWERGRID GATI INFRA172 NJP-MELLI POWERGRID POWERGRID SIKKIM

173 RANGPO- MELLIPOWERGRID+GATI

INFRA POWERGRID SIKKIM174 NJP-MELLI POWERGRID POWERGRID SIKKIM175 LAKHISARAI - JAMAUI BSPHCL POWERGRID BSPHCL176 RANGIT - RABANGLA POWERGRID NHPC SIKKIM177 KALINGPONG-MELLI WBSETCL & SIKKIM WBSETCL SIKKIM178 BANKA-SULTANGUNJ BSPTCL POWERGRID BSPTCL

Page 163: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Annexure-D5.3

Page 164: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.
Page 165: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.

Annexure-D5.4

Page 166: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.
Page 167: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.
Page 168: th OCC Meeting - ERPCerpc.gov.in/.../uploads/2017/03/136OCCMINUTES_1-min.pdf · 2017. 9. 18. · 4) Training on PDMS organised at ERPC, Odisha, Bihar, WBSETCL, Jharkhand and DVC.