Terminal four wharf, warehouse, and debris removal project
Transcript of Terminal four wharf, warehouse, and debris removal project
TERMINAL FOUR WHARF, WAREHOUSE, AND DEBRIS REMOVAL PROJECTANNIKEN LYDONSEPTEMBER 2, 2021 COMMISSION MEETINGAPPLICANT: CITY OF RICHMOND WITH SUPPORT FROM THE STATE COASTAL CONSERVANCY
2
PROJECT LOCATION
September 2, 2021
3
PROJECT SITE PLAN
September 2, 2021
4
RELEVANT MCATEER-PETRIS ACT SECTIONS
• Section 66632• Permit required for fill and extraction
of materials• Section 66605
• Water-oriented use• No alternative upland location• Minimum fill necessary• Minimize harmful effect on Bay
resources• Fill is constructed accordance with
sound safety standards• Valid title to the property
September 2, 2021
5
PROPOSED REGULATION SECTIONS
• Work in the Bay• 10601(a)(6) – removal that involves no
substantial enlargement or change in use.• 10601(a)(2) – installation of new
shoreline protection
• 100-foot Shoreline Band• 10601(b)(5) – removal that involves no
substantial enlargement or change in use.• 10601(b)(1) – placement of fill that
does not have significant adverse impacts on future public access.
September 2, 2021
RELEVANT BAY PLAN POLICIES• Fish, Other Aquatic
Organisms and Wildlife• Subtidal Areas• Water Quality• Shoreline Protection• Safety of Fills• Climate Change• Public Access
6September 2, 2021
Terminal Four
Pt. Molate
Pt. San Pablo
San Francisco Bay