Supervision of piling works, ACES, 2011, Singapore

39
RE & RTO Seminar cum Awards Night Supervision of Foundation Works Chua Tong Seng 14 th December 2011 1

Transcript of Supervision of piling works, ACES, 2011, Singapore

Page 1: Supervision of piling works, ACES, 2011, Singapore

RE & RTO Seminar cum Awards Night

Supervision of Foundation Works

Chua Tong Seng14th December 2011

1

Page 2: Supervision of piling works, ACES, 2011, Singapore

Teamwork: QP-RE-RTO

2

DTL

MCEKPE

KPE-C424KPE-C423LTA

Page 3: Supervision of piling works, ACES, 2011, Singapore

Understanding Soil Condition

DSTA,2009

3

Page 4: Supervision of piling works, ACES, 2011, Singapore

Bukit Timah Granite Formation

4

Bkt Timah

Granite

Page 5: Supervision of piling works, ACES, 2011, Singapore

Kallang FormationMarine Clay

UMC

LMC

Dr.Poh, TY

5

UMC

LMC

6000 years ago

Page 6: Supervision of piling works, ACES, 2011, Singapore

E , F1 and F2

Fluvial Clay, F2

Estuarine Deposit, E

Estuarine Deposit, E

6

Fluvial Sand, F1

Page 7: Supervision of piling works, ACES, 2011, Singapore

Old Alluvium Formation

K.W.Lee,2010

7

Sandy CLAY

Clayey SAND

Page 8: Supervision of piling works, ACES, 2011, Singapore

Jurong Formation

Syncline

JF@Buona Vista

Geological Time, Kimura, 2011

8

Page 9: Supervision of piling works, ACES, 2011, Singapore

Limestone Formation

Jeyatharan et al, 2003

Vietnam,Yashuda, 2011

9

?

Page 10: Supervision of piling works, ACES, 2011, Singapore

Fort Canning Boulder Bed, FCBB

Shirlaw et al, 2003

10

LONGITUDINAL SECTION

Page 11: Supervision of piling works, ACES, 2011, Singapore

Types of Foundation

11

Page 12: Supervision of piling works, ACES, 2011, Singapore

Classification of Piles

End Bearing and Friction Piles Replacement,

Displacement or Low-displacement?

12

Page 13: Supervision of piling works, ACES, 2011, Singapore

Bored Piles in Singapore

GBH

13

Page 14: Supervision of piling works, ACES, 2011, Singapore

Sequence of Construction

14

B

Page 15: Supervision of piling works, ACES, 2011, Singapore

Keep Accurate Installation Records

• Soil Description

• Dry hole or tremie concreting

• Stabilisation method

• Length of temporary steel casing

• Duration of drilling

• Record of anomaly, like hole

collapse

• Pile concreting record

15

Page 16: Supervision of piling works, ACES, 2011, Singapore

Collection of Representative Samples

Collection of samples for various depths and different soil/rock layers Which sample do you choose?

16

Page 17: Supervision of piling works, ACES, 2011, Singapore

Construction Problems

17

Chua, 1999

Page 18: Supervision of piling works, ACES, 2011, Singapore

Stabilising Fluids

Bentonite suspension

Polymer suspension

18

Marsh Funnel

Mud Balance

Page 19: Supervision of piling works, ACES, 2011, Singapore

Construction tolerance: VerticalityCaliper Logging (Koden)

• Singapore Standard

CP4:2003, Code of

Practice for

Foundations

1:75

Kelly Bar

Loadtest,2011

Bauer,2011

19

Page 20: Supervision of piling works, ACES, 2011, Singapore

Eccentricity

20

Where is the centre of pile ?

75mm

Page 21: Supervision of piling works, ACES, 2011, Singapore

Time-Lag before Concreting

CP4:2003 Code of Practice for Foundation

• The time interval between completion of the

formation of the borehole and commencement

of concreting should be minimised as ground

will deteriorate with time

21

Page 22: Supervision of piling works, ACES, 2011, Singapore

Checking Base of Pile

LCH,2011

22

Page 23: Supervision of piling works, ACES, 2011, Singapore

Imperfection: Soft Toe of Pile

23

Page 24: Supervision of piling works, ACES, 2011, Singapore

Type of Rock at Founding Depth

24

Page 25: Supervision of piling works, ACES, 2011, Singapore

Slake Tests

Case 1 Case 2

25

Page 26: Supervision of piling works, ACES, 2011, Singapore

Reinforcements of Bored Pile

CP4: 2003, Foundations

• CP4: compression min main

reinforcement 0.5% of Ac

and not less than 10m long

below pile cut-off level

• For tension , full cage

• For pile within excavation,

reinforcement should be

adequately provided for

bending moment.

BS EN 1536:2000, Bored Piles

• Piles should be reinforced

over any length through

soft or loose soil

26

Page 27: Supervision of piling works, ACES, 2011, Singapore

Barrette Piles

BS EN 1536:2000

Dr. Yet,N.S., 2010

27

Page 28: Supervision of piling works, ACES, 2011, Singapore

Driven Piles

Pile Driver Pile Segments

28

Page 29: Supervision of piling works, ACES, 2011, Singapore

Common Problems with Driven Piles

Piles shorter than design

• Driving energy less than

required i.e. low hammer

efficiency or soft cushion

• Soil strength higher than

anticipated

Piles longer than design

• Driving energy higher than required

• Soil resistance lower than anticipated

• Additional piles to compensate weaker soil i.e. due higher negative skin friction, nsf ?

• Overstressing, yielding of piles?

29

Page 30: Supervision of piling works, ACES, 2011, Singapore

Overstressing of Steel Piles

30

HKFellinius, 1986

Page 31: Supervision of piling works, ACES, 2011, Singapore

Type of Pile Load Test

Ultimate Load Test

• Verification of design

• Conducted to 2.5 to 3.0

times working load, or

failure

• Instrumented to determine

skin friction and end

bearing

Working Load Test

• Quality control test for

assessment of workmanship

• Tested to 1.5 to 2.0 times

working load

• Randomly chosen from

among working piles, not

pre-selected

31

(Dr. Yet NS, 2011)

Page 32: Supervision of piling works, ACES, 2011, Singapore

BCA/IES/ACES Advisory Note 1/03 on

Load Tests and Schedule

32

Page 33: Supervision of piling works, ACES, 2011, Singapore

Method of Pile Load Tests

Kentledge Method O-Cell

33

Foo HK,2011

Page 34: Supervision of piling works, ACES, 2011, Singapore

Dynamic Pile Testing

High Strain Pile Dynamic Test, PDA Statnamic Test

34

Page 35: Supervision of piling works, ACES, 2011, Singapore

Pile Intergrity Testing

Cross-hole Sonic Logging Low Strain Hammer Test

35

Page 36: Supervision of piling works, ACES, 2011, Singapore

Guidelines for Pile Load Test using Kentledge

• Key points

� Design by PE

� Kentledge weight at least 110% of max test load

� Supervise by PE and QSS

� Design to Codes and prepare Drawings to communicate design intent

� Construction to follow design Drawings

� Instrumentation and monitor stability

� All to observe WSHA

36

Page 37: Supervision of piling works, ACES, 2011, Singapore

Workplace Safety & Health Act, WSHA

• An ACT relating to safety, health and welfare of persons at work in workplaces

• WSH(Construction) Regulations 2007

– Piling works

– Reg. 129 Stability of adjacent structures

– Reg. 130 Inspection

– Reg. 131 Pile driver not in use

– Reg. 132 Pile testing

– Reg. 133 Footing

Lim Shiyi, 2011

37

Page 38: Supervision of piling works, ACES, 2011, Singapore

Source of Specification

• Projects Technical Specification

• Code of Practice SS CP4:2003 Foundation

• Code of Practice SS515:2005 Supervision of Structural Works

• Code of Practice BS EN– BS EN 1536:2000 Execution of special geotechnical works –

Bored piles

– BS EN 12699:2000 Execution of special geotechnical works –Displacement piles

– BS EN 14199:2000 Execution of special geotechnical works –Micropiles

38

Page 39: Supervision of piling works, ACES, 2011, Singapore

Conclusion

• Good for QP-RE-RTO to cultivate goodcommunication links. QP to disseminate keydesign requirements and RE-RTO to feedback onsite observations i.e. unexpected soil condition atthe site

• RE-RTO contributions are very important

• All should be familiar with relevant Codes

• Works as a Team. If there is any incident, the lineof responsibility will become irrelevant as allmembers in the team will be affected in one wayor another.

39