Supervision of piling works, ACES, 2011, Singapore
-
Upload
tong-seng-chua -
Category
Documents
-
view
1.477 -
download
25
Transcript of Supervision of piling works, ACES, 2011, Singapore
RE & RTO Seminar cum Awards Night
Supervision of Foundation Works
Chua Tong Seng14th December 2011
1
Teamwork: QP-RE-RTO
2
DTL
MCEKPE
KPE-C424KPE-C423LTA
Understanding Soil Condition
DSTA,2009
3
Bukit Timah Granite Formation
4
Bkt Timah
Granite
Kallang FormationMarine Clay
UMC
LMC
Dr.Poh, TY
5
UMC
LMC
6000 years ago
E , F1 and F2
Fluvial Clay, F2
Estuarine Deposit, E
Estuarine Deposit, E
6
Fluvial Sand, F1
Old Alluvium Formation
K.W.Lee,2010
7
Sandy CLAY
Clayey SAND
Jurong Formation
Syncline
JF@Buona Vista
Geological Time, Kimura, 2011
8
Limestone Formation
Jeyatharan et al, 2003
Vietnam,Yashuda, 2011
9
?
Fort Canning Boulder Bed, FCBB
Shirlaw et al, 2003
10
LONGITUDINAL SECTION
Types of Foundation
11
Classification of Piles
End Bearing and Friction Piles Replacement,
Displacement or Low-displacement?
12
Bored Piles in Singapore
GBH
13
Sequence of Construction
14
B
Keep Accurate Installation Records
• Soil Description
• Dry hole or tremie concreting
• Stabilisation method
• Length of temporary steel casing
• Duration of drilling
• Record of anomaly, like hole
collapse
• Pile concreting record
15
Collection of Representative Samples
Collection of samples for various depths and different soil/rock layers Which sample do you choose?
16
Construction Problems
17
Chua, 1999
Stabilising Fluids
Bentonite suspension
Polymer suspension
18
Marsh Funnel
Mud Balance
Construction tolerance: VerticalityCaliper Logging (Koden)
• Singapore Standard
CP4:2003, Code of
Practice for
Foundations
1:75
Kelly Bar
Loadtest,2011
Bauer,2011
19
Eccentricity
20
Where is the centre of pile ?
75mm
Time-Lag before Concreting
CP4:2003 Code of Practice for Foundation
• The time interval between completion of the
formation of the borehole and commencement
of concreting should be minimised as ground
will deteriorate with time
21
Checking Base of Pile
LCH,2011
22
Imperfection: Soft Toe of Pile
23
Type of Rock at Founding Depth
24
Slake Tests
Case 1 Case 2
25
Reinforcements of Bored Pile
CP4: 2003, Foundations
• CP4: compression min main
reinforcement 0.5% of Ac
and not less than 10m long
below pile cut-off level
• For tension , full cage
• For pile within excavation,
reinforcement should be
adequately provided for
bending moment.
BS EN 1536:2000, Bored Piles
• Piles should be reinforced
over any length through
soft or loose soil
26
Barrette Piles
BS EN 1536:2000
Dr. Yet,N.S., 2010
27
Driven Piles
Pile Driver Pile Segments
28
Common Problems with Driven Piles
Piles shorter than design
• Driving energy less than
required i.e. low hammer
efficiency or soft cushion
• Soil strength higher than
anticipated
Piles longer than design
• Driving energy higher than required
• Soil resistance lower than anticipated
• Additional piles to compensate weaker soil i.e. due higher negative skin friction, nsf ?
• Overstressing, yielding of piles?
29
Overstressing of Steel Piles
30
HKFellinius, 1986
Type of Pile Load Test
Ultimate Load Test
• Verification of design
• Conducted to 2.5 to 3.0
times working load, or
failure
• Instrumented to determine
skin friction and end
bearing
Working Load Test
• Quality control test for
assessment of workmanship
• Tested to 1.5 to 2.0 times
working load
• Randomly chosen from
among working piles, not
pre-selected
31
(Dr. Yet NS, 2011)
BCA/IES/ACES Advisory Note 1/03 on
Load Tests and Schedule
32
Method of Pile Load Tests
Kentledge Method O-Cell
33
Foo HK,2011
Dynamic Pile Testing
High Strain Pile Dynamic Test, PDA Statnamic Test
34
Pile Intergrity Testing
Cross-hole Sonic Logging Low Strain Hammer Test
35
Guidelines for Pile Load Test using Kentledge
• Key points
� Design by PE
� Kentledge weight at least 110% of max test load
� Supervise by PE and QSS
� Design to Codes and prepare Drawings to communicate design intent
� Construction to follow design Drawings
� Instrumentation and monitor stability
� All to observe WSHA
36
Workplace Safety & Health Act, WSHA
• An ACT relating to safety, health and welfare of persons at work in workplaces
• WSH(Construction) Regulations 2007
– Piling works
– Reg. 129 Stability of adjacent structures
– Reg. 130 Inspection
– Reg. 131 Pile driver not in use
– Reg. 132 Pile testing
– Reg. 133 Footing
Lim Shiyi, 2011
37
Source of Specification
• Projects Technical Specification
• Code of Practice SS CP4:2003 Foundation
• Code of Practice SS515:2005 Supervision of Structural Works
• Code of Practice BS EN– BS EN 1536:2000 Execution of special geotechnical works –
Bored piles
– BS EN 12699:2000 Execution of special geotechnical works –Displacement piles
– BS EN 14199:2000 Execution of special geotechnical works –Micropiles
38
Conclusion
• Good for QP-RE-RTO to cultivate goodcommunication links. QP to disseminate keydesign requirements and RE-RTO to feedback onsite observations i.e. unexpected soil condition atthe site
• RE-RTO contributions are very important
• All should be familiar with relevant Codes
• Works as a Team. If there is any incident, the lineof responsibility will become irrelevant as allmembers in the team will be affected in one wayor another.
39