Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create...

45
Subarnarekha Port Private Limited (SPPL) Updated Form-1 January 2019 Prepared By L&T Infrastructure Engineering Limited C1181308 RP001; Rev. 0 Environmental/CRZ Clearance Validity Extension for Subarnarekha Port At Choumukh, Balasore District, Odisha

Transcript of Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create...

Page 1: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

Subarnarekha Port

Private Limited (SPPL)

Updated Form-1

January 2019

Prepared By

L&T Infrastructure Engineering Limited

C1181308 RP001; Rev. 0

Environmental/CRZ Clearance Validity Extension

for Subarnarekha Port

At Choumukh, Balasore District, Odisha

Page 2: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

Form-1

Page 3: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

L&T Infrastructure Engineering Ltd.

Client: Subarnarekha Port Private Limited Project: Environmental/CRZ Clearance Validity

Extension for Subarnarekha Port Project No.:

C1181308 Title:

Updated Form-1 Document No.:

RP001 Rev.:

0 This document is the property of L&T Infrastructure Engineering Ltd. and must not be passed on to any person or body not authorised by us to receive it nor be copied or otherwise made use of either in full or in part by such person or body without our prior permission in writing.

File path: l:\ports\2018\c1181308 - sppl-ec validity extension\working\reports\updated form-1\final updated form -1 04.02.2019.doc

Notes:

1.

Revision Details:

Rev. Date Details Init. Sign. Init. Sign. Init. Sign.

Prepared Checked Approved

Page 4: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing
Page 5: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

Environmental/CRZ Clearance Validity Extension for Subarnarekha Port C1181308 Updated Form-1 RP001 rev. 0

Table of Contents Page i

TABLE OF CONTENTS

1 Basic Information ...........................................................................................................................1

2 Activity .............................................................................................................................................4

3 Environmental Sensitivity ........................................................................................................... 20

LIST OF APPENDICES

Appendix A: Environmental/CRZ Clearance Letter

Appendix B: Approved Layout showing All Weather Multi-Purpose Port

Appendix C: Location Map

Appendix D: Survey Nos. covered under the Project area

Appendix E: Port Limit Declaration by Commerce and Transport, Government of Odisha

Page 6: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing
Page 7: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

Environmental/CRZ Clearance Validity Extension for Subarnarekha Port C1181308 Updated Form-1 RP001 rev. 0

1 Basic Information Page 1

FORM 1

1 Basic Information S. No. Item Details

1. Name of the Project Development of All Weather Multi-Purpose Port at Choumukh Village, Balasore District, Odisha Application is for extension of Environmental/CRZ Clearance Validity upto March 21, 2022 (Three more years) for the facilities as approved for Subarnarekha Port.

2. Project Sector/ S,No in the Schedule

Physical Infrastructure including Environmental Services - Ports, harbours/Breakwaters/Dredging are included as Item 7(e) in the Schedule of the EIA Notification 2006 (as amended)

3. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled

Environmental and CRZ clearance was obtained in March 21, 2012 and copy of CRZ/EC clearance is given as Appendix A.

As per the clearance obtained, the following Project components / facilities have been permitted:

Total handling capacity – 60 MTPA (Phase I: 25 MTPA and Phase II: 35 MTPA)

Port Land Area: 915 Acres (370 Ha) In addition, Area to be reclaimed: 750 Acres (303

Ha) A dedicated Rail/Road Corridor Facilities: Two (2) Barge berths and Seven (7)

berths (Cumulative) for handling dry bulk cargo (such as Iron Ore, thermal Coal, Coking Coal and Lime Stone), containerized and General cargo including timber, food grains, clinkers, steel products and sugar etc.

The project development consists of 2310 m of eastern breakwater and 3155 m of western breakwater.

Phase I: Length of approach channel is 26,000 m, width (inner/outer) will be 175/200 m and depth(inner/outer) will be (-)15.0 m/(-)15.7 m.

Phase II: Length of approach channel is 29,000 m, width (inner/outer) will be 175/220 m and depth(inner/outer) will be (-)18.0 m/(-)19.0 m.

The diameter and depth of turning circle for Phase I: 520 m /(-)15.0 m and for Phase II: 600 m/ (-) 18.0 m

The capital dredging quantity estimated for phase -1 is 47.0 MCM and for Phase II is 60.0 MCM (Cumulative).

Reclamation quantity - 12 MCM (dredge spoil) The total maintenance dredging quantity -

~1,20,000 m3/annum (off shore disposal)

No changes in the Project Configuration/ Activity/Capacity/area/ Handling Tonnage/ Dredging

Page 8: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

C1181308 Environmental/CRZ Clearance Validity Extension for Subarnarekha Port RP001 rev. 0 Updated Form-1

1 Basic Information Page 2

quantity etc. and facilities remain same as for which Environmental/CRZ clearances have been granted. The facilities to be developed will be in line with the clearances granted.

Approved Layout showing All Weather Multi-Purpose Port facilities are given as Appendix B.

4. New/Expansion/Modernisation

Not Applicable Present proposal is for Extension of validity of Environmental and CRZ Clearance only.

5. Existing Capacity/Area, etc. No Port facilities have been developed so far

6. Category of Project i.e., ‘A ‘or ’B’ Category ‘A’

7. Does it attract the general condition? If yes, please specify

Environmental/CRZ Clearances obtained under Category ‘A’ only.

8. Does it attract the specific condition? If yes, please specify

No

9. Location Subarnarekha Port site is located at South-East of Choumukh village in Balasore district of Odisha State. Location map given as Appendix C

Plot/Survey/Khasra No. Survey Nos. covered under the Project area is provided in Appendix D

Village Choumukh village Tehsil Baliapal District Balasore State Odisha

10. Nearest railway station/ airport along with distance in km

Haldipara RS – 42 km W Kolkata Airport - 150 km (NE) Bhubaneswar Air Port - 215 km SW

11. Nearest town, city and district headquarters along with distance in km

Baliapal – 12 km NNW Balasore (district headquarters) – 48 km W

12. Village Panchayats, Zilla Parishad, Municipal Corporation, Local body (complete postal addresses with telephone nos. to be given)

Chaumukh Village, Baliapal Tehsil, Balasore District,

13. Name of the applicant Subarnarekha Port Private Limited 14.

Registered Address MIG-93, Ananthvihar, Phase-1, Pokhariput, Bhubaneswar - 751 020 Odisha, India TF +91 674 2352599

15. Address for correspondence: Name R. Rangarajan Designation (Owner/Partner/CEO) Executive Director

Address New # 84, Dakshin, 1st Avenue, Indira Nagar, Adyar, Chennai, Tamil Nadu, India

Pin code 600020 E-mail [email protected] Telephone No TF: +91 44 4260 7368 Fax No TF: +91 44 4260 7368

Page 9: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

Environmental/CRZ Clearance Validity Extension for Subarnarekha Port C1181308 Updated Form-1 RP001 rev. 0

1 Basic Information Page 3

16. Details of alternative sites examined shown on a topo sheet

Not Applicable Environmental and CRZ Clearance were obtained. This application is for EC/CRZ validity extension only.

17. Interlinked projects Nil 18. Whether part of interlinked

projects? Not Applicable

If yes, date of submission NA If no, reason Not Applicable

19. Whether the proposal involves approval/clearance under the Forest (Conservation) Act, 1980?

Not Applicable/ Project does not attract Forest (Conservation) Act, 1980

20. Whether the proposal involves approval/clearance under the Wildlife (Protection) Act,1972?

Not Applicable/ Project does not attract wildlife (Protection) Act, 1972

21. Whether the proposal involves approval/clearance under the C.R.Z notification, 2011?

This proposal is for extension of validity of Environmental and CRZ clearance only. Environmental and CRZ clearance has been obtained vide MoEF&CC Letter No.: F. No. 10-33/2007-IA.III dated March 21, 2012 (Appendix A).

22. Whether there is any Government Order/Policy relevant/relating to the site?

Proposed port site is located at Chaumukh village,, the port was declared as minor port by Department of Commerce and Transport, Government of Odisha and issued the port limits and the same is given as Appendix E. Land Lease agreement with Government of Odisha signed on 29.01.2018.

Uploaded Order/Policy

23. Forest land involved (hectare) None 24. Whether there is any litigation

pending against the project and/or land in which the project is proposed to be set up?

PIL/ Petition No. 20115/2012 dated December 06, 2012 in HC of Odisha, Cuttack against Port Policy of Odisha State / Subarnarekha Port Pvt Ltd.

HC of Odisha, Cuttack Dismissed PIL/ Petition No. 20115/2012 on December 16, 2016

(a) Name of the Court (b) Name of the Sub court (c) Case No. (d) Orders/directions of the court, if any and relevance with the proposed the land provided project.

Page 10: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

C1181308 Environmental/CRZ Clearance Validity Extension for Subarnarekha Port RP001 rev. 0 Updated Form-1

2 Activity Page 4

2 Activity

1. Construction, operation or decommissioning of the Project involving actions, which

will cause physical changes in the locality (topography, land use, changes in water

bodies, etc.)

S. No.

Information/Checklist confirmation

Yes/No Details thereof (with approximate quantities /rates, wherever possible) with source of information data

1.1

Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan)

Yes

Development of All Weather Multi-Purpose Port will be carried out in 915 Acres (~370 Ha) of land and in addition to the 750 Acres (~303 Ha) of reclaimed land.

The change in land use shall be as per the approved layout

The terrain of the project site is a coastal plain slope towards sea (south-east) with an elevation of about 0-4 m above Chart Datum (CD).

1.2 Clearance of existing land, vegetation and buildings? Yes

Details of project site (Casuarinas, other Plantations, land with and without scrub and Coastal sand) were presented to EAC and Environmental and CRZ clearances were obtained. The area will be developed as per the approved layout.

1.3 Creation of new land uses? No No new land use involved. Development as per approved layout is envisaged.

1.4 Pre-construction investigations e.g. bore houses, soil testing? Yes

All the requisite pre-construction investigations have been carried out as necessary.

1.5 Construction works? Yes Construction activities include development of Port and associated facilities.

1.6 Demolition works? No

1.7 Temporary sites used for construction works or housing of construction workers?

Yes Adequate Temporary facilities (houses, water, power, fuel, sanitation etc.) for construction labour will be at project site.

1.8

Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations

Yes Envisaged as a part of development

and project requirement in compliance with clearances obtained.

Above ground buildings/underground works such as Port operation building/offices Maintenance buildings comprising a central workshop, functional work stations in different port terminal / operational areas and in the central fire station. Substations to provide distribution of

1.9 Underground works including mining or tunneling? Yes

Page 11: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

Environmental/CRZ Clearance Validity Extension for Subarnarekha Port C1181308 Updated Form-1 RP001 rev. 0

2 Activity Page 5

S. No.

Information/Checklist confirmation

Yes/No Details thereof (with approximate quantities /rates, wherever possible) with source of information data

power. Navigational control centre, other operational buildings, customs and security buildings, traffic offices, medical centre and amenity buildings / conveniences, Water Supply and distribution, Power Supply and Distribution and wastewater conveyance etc.

Approved Layout showing All Weather Multi-Purpose Port facilities are given as Appendix B

1.10 Reclamation works? Yes

Reclamation work of port backup area will be carried out and about 12 MCM of the dredged material will be used for reclamation in compliance to the clearance obtained.

1.11 Dredging? Yes

Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing areas. The dredging volume is estimated at about 47 MCM for Phase 1 and 60.0 MCM for Phase II respectively.

The total maintenance dredging quantity is ~1,20,000 m3/annum (off shore disposal)

Dredging would be carried out in compliance to the clearances obtained

1.12 Offshore structures? Yes

Offshore structures of Port (Breakwaters / Berths / Trestle / Creation of navigation channel etc.) in compliance to the clearance obtained.

1.13 Production and manufacturing processes? No

1.14 Facilities for storage of goods or materials? Yes

Cargo Storage Area for dry bulk cargo, general cargo, and container freight station in compliance to clearances obtained.

1.15

Facilities for treatment or disposal of solid waste or liquid effluents?

Yes

Wastewater from toilets, bathrooms, canteen and administrative buildings of Port is estimated at 12 KLD. Sewage from R&R site (36 KLD) will be treated at the R&R site premises itself. Treated sewage will be used for the development of green belt. A separate STP of 200 KLD capacity will be provided in the township to treat the sewage generated. Treated water and Sludge from STP will be used for green belt development.

Page 12: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

C1181308 Environmental/CRZ Clearance Validity Extension for Subarnarekha Port RP001 rev. 0 Updated Form-1

2 Activity Page 6

S. No.

Information/Checklist confirmation

Yes/No Details thereof (with approximate quantities /rates, wherever possible) with source of information data

The oil contaminated water will be sent to oil water separator, separated oil will be sent to OSPCB approved vendors and water will be sent STP for further treatment in compliance to clearances obtained.

Ships / vessels calling at Subarnarekha Port will not be permitted dump the wastes /bilge water during the berthing period. However, during emergency, the reception Facilities will be provided.

1.16 Facilities for long term housing of operational workers? Yes

Housing facilities for operational staff of the port shall be provided in the township area as a part of the project development in compliance to the clearances obtained.

1.17 New road, rail or sea traffic during construction or operation?

Yes

Construction Phase:

Vehicles involved in men and material transportation

Construction equipment/ machinery and material shall be brought to the site by road

Operation Phase:

New road, rail or sea traffic is envisaged as the Cargo from/ to the hinterland will be transported by ships/Rail/conveyer systems/ Trucks/Tractor Trailers etc.

1.18

New road, rail, air waterborne or other transport infrastructure including new or altered routes and stations, ports, airports etc.?

Yes

The road/rail corridor is proposed as a part of development of Subarnarekha Port will be utilised for cargo transportation as per approvals obtained.

1.19

Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements?

No

1.20 New or diverted transmission lines or pipelines? Yes

Required Infrastructure facilities such as power, water lines etc., will be developed in compliance with clearances obtained.

1.21

Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers?

Yes

Locations of Bridges/Cross Drainages proposed as a part of Rail/Road Corridor crossing Nadi/Nallah/Canal areas will be developed in compliance with clearances obtained.

1.22 Stream crossings? Yes The proposed road/rail alignment will

Page 13: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

Environmental/CRZ Clearance Validity Extension for Subarnarekha Port C1181308 Updated Form-1 RP001 rev. 0

2 Activity Page 7

S. No.

Information/Checklist confirmation

Yes/No Details thereof (with approximate quantities /rates, wherever possible) with source of information data

traverse across the Nallah/Canal /Nadi. Adequate provision for cross drainage system will be provided during the implementation of rail & road corridor for safe discharge of flood water during high flood in compliance with clearances obtained..

1.23 Abstraction or transfers of water from ground or surface waters? Yes

Water Requirement during the construction is expected to be around 50m3/ day and during operational phase water requirement is 1.312 MLD (Cumulative) will be met through Subarnarekha River near Baliapal,. Water treatment Plant will be developed as per approvals obtained.

1.24 Changes in water bodies or the land surface affecting drainage or run-off?

No

Adequate storm water drainage system within the Port site will be developed without affecting natural drainage or run-off.

1.25 Transport of personnel or materials for construction, operation or decommissioning?

Yes

Construction Phase:

Movement of construction material including cement, aggregates, rock, sand and reinforcement

Movement of construction workers by vans/buses

Operation Phase:

Movement of workforce from the townships/ habitations to the port

Cargo movements from/to is envisaged via Road/rail/Sea routes.

1.26 Long-term dismantling or decommissioning or restoration works?

No -

1.27

Ongoing activity during decommissioning which could have an impact on the environment?

No -

1.28

Influx of people to an area in either temporarily or permanently? Yes

Temporary and limited during construction phase

Marginal and permanent during operation phase

1.29 Introduction of alien species? No -

1.30 Loss of native species or genetic diversity? No -

1.31 Any other actions? No -

Page 14: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

C1181308 Environmental/CRZ Clearance Validity Extension for Subarnarekha Port RP001 rev. 0 Updated Form-1

2 Activity Page 8

2. Use of Natural resources for construction or operation of the Project (such as land,

water, materials or energy, especially any resources that are non-renewable or in

short supply):

S. No.

Information/checklist confirmation

Yes/No Details thereof (with approximate quantities /rates, wherever possible) with source of information data

2.1 Land especially undeveloped or agricultural land (ha) Yes

Development of port and associated facilities will be carried out within 915 Acres (~370 Ha) of land and in addition to the 750 Acres (~303 Ha) of reclaimed land. The change in land use will be as per the approved layout.

2.2 Water (expected source & competing users) unit: KLD Yes

1.312 MLD (Cumulative) water is required for Port Operations which will be met through Subarnarekha River near Baliapal

2.3 Minerals (MT) No

During Operation Phase only handling dry bulk cargo (such as Iron Ore, thermal Coal, Coking Coal and Lime Stone), containerized and General cargo is envisaged.

2.4 Construction material – stone, aggregates, sand / soil (expected source – MT)

Yes

Soil, sand, gravel, stone and aggregates are required for the construction of breakwaters and berths will be sourced from approved quarries at Nilgiri which is 67 km from the port site. Quantity of quarry stones required is about 2.0 Million Tonnes, which will be transported by road. About 3 MTPA of cargo also planned to be handled during construction phase.

2.5 Forests and timber (source – MT) Yes

As per project requirement timber for construction/operation if any (as building material) will be sourced from licensed suppliers

2.6

Energy including electricity and fuels (source, competing users) Unit: fuel (MT), energy (MW)

Yes

Power requirement during construction phase is around 3 to 5 MW and power will be drawn from DG sets and nearest 33 KVA sub-station at Baliapal (~ 15 km from site).

During operation phase for Phase I - 21.4 MVA and Phase II is 6.1 MVA (Additional) and power will be drawn from 220 KVA sub-station at Jaleswar (30 km).

2.7 Any other natural resources (use appropriate standard units)

No -

Page 15: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

Environmental/CRZ Clearance Validity Extension for Subarnarekha Port C1181308 Updated Form-1 RP001 rev. 0

2 Activity Page 9

3. Use, storage, transport, handling or production of substances or materials, which

could be harmful to human health or the environment or raise concerns about

actual or perceived risks to human health.

S. No.

Information/Checklist confirmation

Yes/No

Details thereof (with approximate quantities /rates, wherever possible) with source of information data

3.1

Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies)

No

No hazardous cargo /will be handled at the port.

Dry bulk cargo (Iron Ore, Thermal Coal, Coking Coal and lime stone), containerized and General cargo including timber, food grains, clinkers, steel products and sugar etc which is non-hazardous in nature will be in compliance to the approvals obtained.

3.2

Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases)

No

3.3 Affect the welfare of people e.g. by changing living conditions?

Yes The project is likely to provide direct employment to ~350 persons during operation phase and ~1500 persons during construction phase.

The aim of the project is to generate beneficial social impacts as a part of the development of the project and all measures required for that shall be planned and implemented.

3.4

Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc.,

No

3.5 Any other causes No

Page 16: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

C1181308 Environmental/CRZ Clearance Validity Extension for Subarnarekha Port RP001 rev. 0 Updated Form-1

2 Activity Page 10

4. Production of solid wastes during construction or operation or decommissioning

(MT/month)

S. No.

Information/Checklist confirmation

Yes/No

Details thereof (with approximate quantities /rates, wherever possible) with source of information data

4.1 Spoil, overburden or mine wastes Yes

Construction Phase:

The dredging volume is estimated at about 47 MCM for Phase 1 and 60.0 MCM for Phase II respectively

Reclamation quantity - 12 MCM (dredge spoil and 48 MCM balance will be disposed to identified offshore location)

The total maintenance dredging quantity - ~1,20,000 m3/annum (off shore disposal)

Capital, maintenance dredging and shoreline management dredged material etc., and disposal of dredged material will be in compliance with Environmental/CRZ Clearances obtained.

4.2 Municipal waste (domestic and or commercial wastes) Yes

Municipal solid waste generated from canteen and administrative areas is estimated at about 1.2 TPD

Proper collection and disposal of solid waste from office establishment and town ship based on the Central Public Health and Environmental Engineering Organization (CPHEEO)/ SWM Rule 2016

The collected biodegradable waste shall be subjected to composting and the compost will be used as manure for the development of green belt within the port.

The non-biodegradable waste like plastic shall be disposed off to approved vendors of OSPCB/CPCB in a scientific manner

4.3 Hazardous wastes (as per Hazardous Waste Management Rules)

Yes Used oil/spent oil, Wastes/Residue containing oil/ Oil soaked rags/Cotton waste, Discarded containers/barrels & Used Battery and Sludge from Oil

Page 17: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

Environmental/CRZ Clearance Validity Extension for Subarnarekha Port C1181308 Updated Form-1 RP001 rev. 0

2 Activity Page 11

S. No.

Information/Checklist confirmation

Yes/No

Details thereof (with approximate quantities /rates, wherever possible) with source of information data

Waste Separator will be collected and disposed to OSPCB approved vendors. Hazardous wastes, if any will be handled as per Hazardous Waste Management Rules (as amended).

4.4 Other industrial process wastes No

4.5 Surplus product No

4.6 Sewage sludge or other sludge from effluent treatment Yes

Wastewater from toilets, bathrooms, canteen and administrative buildings of Port is estimated at 12 KLD. Sewage from R&R site (36 KLD) will be treated at the R&R site premises itself. Treated sewage will be used for the development of green belt. A separate STP of 200 KLD capacity will be provided in the township to treat the sewage generated. Treated water and Sludge from STP will be used for green belt development.

The oil contaminated water will be sent to oil water separator, separated oil will be sent to OSPCB approved vendors and water will be sent STP for further treatment in compliance to clearances obtained

4.7 Construction or demolition wastes Yes

Construction and Demolition wastes will be utilised within the project site for site grading and other filling purposes.

4.8 Redundant machinery or equipment No

4.9 Contaminated soils or other materials No

Soil contamination is not envisaged and if any from accidental spills, shall be mitigated through suitable preventive and control measures Such as (i) Covered conveyors equipped with Spill Guards, (ii) Dust extraction system at Transfer Towers, (iii) Routine Checks (iv) Arrangements to collect the spilled

Page 18: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

C1181308 Environmental/CRZ Clearance Validity Extension for Subarnarekha Port RP001 rev. 0 Updated Form-1

2 Activity Page 12

S. No.

Information/Checklist confirmation

Yes/No

Details thereof (with approximate quantities /rates, wherever possible) with source of information data

material and storage (Oil spill on the land will be properly cleaned using absorbents, cotton waste, sand, saw dust etc.)

4.10 Agricultural wastes No

4.11 Other solid wastes No

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

S. No. Information/Checklist

confirmation Yes/No

Details thereof (with approximate quantities /rates, wherever possible) with source of information data

5.1 Emissions from combustion of fossil fuels from stationary or mobile sources

Yes

Exhaust emissions from diesel run engines, construction machinery and vehicles

Dust suspension during site preparation, construction, and material transport

Emissions from DG Sets at the port, the tugs, launches, diesel operated small boats, dredgers, Power failure, equipments, engines, transport vehicles and machinery during construction and operational phases of master plan facilities etc.

Emission from DG mounted RTGC at port.

Fugitive emissions during coal handling at the berths

Suitable mitigation measures such as water sprinkling, PUC certified vehicles, well maintained construction equipments low Sulphur Diesel Fuel, suitable stack height for DG sets, covered conveyor/Dust suppression measures will be provided in compliance with Environmental and CRZ Clearances obtained.

5.2 Emissions from production processes No

Page 19: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

Environmental/CRZ Clearance Validity Extension for Subarnarekha Port C1181308 Updated Form-1 RP001 rev. 0

2 Activity Page 13

S. No. Information/Checklist

confirmation Yes/No

Details thereof (with approximate quantities /rates, wherever possible) with source of information data

5.3 Emissions from materials handling including storage or transport

Yes

Fugitive dust emissions are envisaged during unloading / loading and storage of dry bulk cargo. Dust Suppression System, Covered conveyor system and mechanised loading/unloading systems will be installed for cargo handling, storage and transport. Suitable control measures including proposed greenbelt development, Covered Conveyor, dust suppression system to minimise the impacts will be implemented.

5.4 Emissions from construction activities including plant and equipment

Yes

Emission from diesel operated pumps, concrete mixers, equipments and excavators during construction activities. These equipments will be maintained properly to ensure minimum emissions, more-over construction activity will be for a short duration of period and restricted within the Project boundary.

5.5 Dust or odours from handling of materials including construction materials, sewage and waste

Yes

Dust due to handling of material during construction and cargo handling

Dust suppression measures like water sprinkling and greenbelt are being implemented at site which will be extended to master plan development

Sewage generated at site will be collected in the septic tank followed soak pit..

5.6 Emissions from incineration of waste No

5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris)

No

5.8 Emissions from any other sources No

Page 20: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

C1181308 Environmental/CRZ Clearance Validity Extension for Subarnarekha Port RP001 rev. 0 Updated Form-1

2 Activity Page 14

6. Generation of Noise and Vibration, and Emissions of Light and Heat

S. No. Information/Checklist

confirmation Yes/No

Details thereof (with approximate quantities /rates, wherever

possible) with source of information data

6.1 From operation of equipment e.g. engines, ventilation plant, crushers

Yes

During Construction activities 70-85 dB(A) will be expected near to the noise generating source such as DG sets, Vehicular movement, heavy equipments, etc. and PPEs will be provided to the workers.

During the operational phase, noise will be generated due to the cargo handling and storage operations by using equipments such as unloaders, mobile harbour crane, trucks, Operation of generators, pumps, engines of boats and ships etc. at port premises.

Equipment will be deployed with noise mitigating devices conforming to applicable standards

Acoustic enclosures will be provided at high noise generating areas.

6.2 From industrial or similar processes No -

6.3 From construction or demolition Yes

Noise is envisaged from Excavators, Dumpers, Welding/Drilling and Trucks etc. Personnel Protection Equipment (PPE) will be provided to workers. Other Mitigation measures will be implemented during construction activities. The measures includes The construction equipment

deployed would be provided with suitable mufflers / Enclosures

Personal protective equipment like earmuffs will be provided to operating personnel

Exercise of route selection as well as measures such as traffic regulation, timings of transportation etc. will be followed

High noise generating activities such as piling and drilling will be scheduled in a day time such as to minimise noise impacts

Procurement of machinery /

Page 21: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

Environmental/CRZ Clearance Validity Extension for Subarnarekha Port C1181308 Updated Form-1 RP001 rev. 0

2 Activity Page 15

S. No. Information/Checklist

confirmation Yes/No

Details thereof (with approximate quantities /rates, wherever

possible) with source of information data

construction equipment will be done in accordance with specifications conforming to source noise levels of 85 dB (A)

Only well-maintained construction equipment, which meets the regulatory standards for source noise levels, will be used

Any equipment emitting high noise, where possible, will be oriented so that the noise is directed away from sensitive receptors

Noise attenuation will be practiced for noisy equipment by employing suitable techniques such as acoustic controls, insulation and vibration dampers. The attenuation devices will be properly maintained throughout the construction period.

Periodic maintenance of equipment for diesel generators units, air compressors, engines, etc. will be undertaken.

Worn out parts will be replaced and rotating parts will be lubricated to minimise noise emissions

6.4 From blasting or piling Yes

No blasting. Piling activities will be carried out with necessary precautionary measures such as High noise generating activities (piling) will be scheduled in a day time such as to minimise noise impacts.

6.5 From construction or operational traffic Yes

Vehicles complying with Standards prescribed under the Motor Vehicles Act will be allowed to operate

Page 22: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

C1181308 Environmental/CRZ Clearance Validity Extension for Subarnarekha Port RP001 rev. 0 Updated Form-1

2 Activity Page 16

S. No. Information/Checklist

confirmation Yes/No

Details thereof (with approximate quantities /rates, wherever

possible) with source of information data

6.6 From lighting or cooling systems Yes

Minor operations such as welding, cutting, electrical lighting, power circuits, drilling etc. produce Sound/lighting but it would be temporary and necessary safety gadgets for noise/light will be provided. Air conditioning and ventilation system generates noise and necessary enclosure shall be provided.

6.7 From any other sources No -

7. Risks of contamination of land or water from releases of pollutants into the ground

or into sewers, surface waters, groundwater, coastal waters or the sea

S. No. Information/Checklist

confirmation Yes/No

Details thereof (with approximate quantities/rates, wherever possible) with source of information data

7.1 From handling, storage, use or spillage of hazardous materials Yes The cargo to be handled are Dry

bulk cargo, Iron Ore (Export), Thermal Coal (Export), Coking Coal (Import), Lime Stone (Import) General cargo (Export/Import) and Container cargo (Export/Import) etc. These cargo will be stored a the designated storage area with necessary ground preparation.

No significant spill of these materials at Port is expected under normal operations. However, during accidental spills if any shall be recovered by adopting appropriate measures.

7.2

From discharge of sewage or other effluents to water or the land (expected mode and place of discharge)

Yes

Sewage will be treated in STP. Treated sewage and the sludge shall be used for gardening/greenbelt development

Page 23: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

Environmental/CRZ Clearance Validity Extension for Subarnarekha Port C1181308 Updated Form-1 RP001 rev. 0

2 Activity Page 17

S. No. Information/Checklist

confirmation Yes/No

Details thereof (with approximate quantities/rates, wherever possible) with source of information data

7.3 By deposition of pollutants emitted to air, onto the land or into water

Yes

Air

Emissions from DG sets during emergency

Fugitive emissions during coal and iron ore handling and transport.

Dust suppression measures like covered conveyor, water sprinkling and greenbelt

Land

Local authorised waste handler will be employed to remove Municipal solid wastes generated in port area and collection bins will be provided.

Water

Sewage generated will be treated in STP. Treated wastewater will be used for Green Belt development after meeting the prescribed standards for land application.

Runoff from cargo storage areas will be directed to settling ponds and the retention time of each settling pond is 3 to 4 hours.

The oil contaminated water if any will be sent to oil water separator, separated oil will be sent to OSPCB approved vendors

The Port will be equipped with necessary modern equipment to contain and recover oil spills proposed as a part Oil Spill Contingency Plan.

7.4 From any other sources No -

7.5

Is there a risk of long term build up of pollutants in the environment from these sources?

No Not envisaged

Page 24: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

C1181308 Environmental/CRZ Clearance Validity Extension for Subarnarekha Port RP001 rev. 0 Updated Form-1

2 Activity Page 18

8. Risk of accidents during construction or operation of the Project, which could affect

human health or the environment

S. No. Information/Checklist

confirmation Yes/No

Details thereof (with approximate

quantities /rates, wherever

possible) with source of

information data

8.1 From explosions, spillages, fires, etc. from storage, handling, use or production of hazardous substances

Yes

Cargo to be handled Type of Cargo Phase I Phase II

Iron Ore (Export)

(MTPA) 4.0 2.0

Thermal Coal

(Export) (MTPA) 3.0 4.0

Coking Coal (Import)

(MTPA) 10.0 14.0

Lime Stone (Import) (MTPA)

2.0 4.0

General cargo (Export/Import) (MTPA)

3.0 3.5

Container cargo (Export/Import) TEUs

250,000 600,000

Dry bulk cargo (Iron Ore, Thermal Coal, Coking Coal and lime stone) which is non hazardous in nature will be handled using mechanical cargo handling equipment such as gantry cranes, unloaders/loaders, conveyor belt, bull dozers, stacker-cum-reclaimer, wagon loaders and wagon tippler etc., on ship berths and in storage/stackyard areas for unloading/loading operations and thereby protecting the land and water from contamination.. These cargos will be stored at the designated storage area with necessary ground preparation. No significant spill of these materials at Port is expected under normal operations. However, during accidental spills if any shall be recovered by adopting appropriate measures Fires due to auto ignition of coal at both Thermal and Coking coal Stockyard are envisaged. Swivelling Type Nozzles will be installed to cover entire stockpile to suppress the auto ignition of coal and ensure the workers safety.

8.2 From any other causes No -

Page 25: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

Environmental/CRZ Clearance Validity Extension for Subarnarekha Port C1181308 Updated Form-1 RP001 rev. 0

2 Activity Page 19

S. No. Information/Checklist

confirmation Yes/No

Details thereof (with approximate

quantities /rates, wherever

possible) with source of

information data

8.3

Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc.)?

Yes

Cyclone/Flood and Earthquake prone area. Planning of the Layout and Structural design has factored these aspects for the facilities developed/ to be developed.

9. Factors which should be considered (such as consequential development) which

could lead to environmental effects or the potential for cumulative impacts with

other existing or planned activities in the locality

S. No. Information/Checklist

confirmation Yes/No

Details thereof (with approximate quantities /rates, wherever possible) with source of information data

9.1

Lead to development of supporting utilities, ancillary development or development stimulated by the project which could have impact on the environment e.g. 1. Supporting infrastructure

(roads, power supply, waste or wastewater treatment, etc.)

2. Housing development 3. Extractive industries 4. Supply industries 5. Other

Yes

Induced development due to the proposed project in the region, which will create better infrastructure and will attract migration of people.

Necessary supportive utilities, infrastructure, housing etc. to cater the requirements of the project would be developed as a part of the project.

9.2 Lead to after-use of the site, which could have an impact on the environment

No This project would be a permanent establishment

9.3 Set a precedent for later developments

Yes The project would increase the Commercial / Industrial activities in the region.

9.4

Have cumulative effects due to proximity to other existing or planned projects with similar effects

No

Page 26: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

C1181308 Environmental/CRZ Clearance Validity Extension for Subarnarekha Port RP001 rev. 0 Updated Form-1

3 Environmental Sensitivity Page 20

3 Environmental Sensitivity

S. No.

Areas Name/Identity

Aerial distance (within 15

km)

1

Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value

- -

2

Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests

Mangroves 2.50 km NE

3

Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration

- -

4 Inland, coastal, marine or underground waters

Subarnarekha River Bay of Bengal

Adjoining N Adjoining S

5 State, National boundaries West Bengal 17.0 km NE

6

Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas

- -

7 Defence installations - -

8 Densely populated or built-up area Baliapal Village 12.0 km NW

9

Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities)

- -

10

Areas containing important, high quality or scarce resources (ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals)

Chandaneswar Temple Talasari Beach Forest mainly with Casuarinas

12.5 km NE 12.5 km NE Abutting and 5.0 km NE

11

Areas already subjected to pollution or environmental damage. (those where existing legal environmental standards

- -

Page 27: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing
Page 28: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

Appendix A

Environmental/CRZ

Clearance Letter

Page 29: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing
Page 30: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing
Page 31: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing
Page 32: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing
Page 33: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing
Page 34: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing
Page 35: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing
Page 36: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

Appendix B

Approved Layout showing

All Weather Multi-Purpose

Port

Page 37: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

10

SCALE IN km

AutoCAD SHX Text
EAST BREAKWATER 2310 LONG
AutoCAD SHX Text
WEST BREAKWATER 3155 LONG
AutoCAD SHX Text
HTL
AutoCAD SHX Text
LTL
AutoCAD SHX Text
34
AutoCAD SHX Text
32
AutoCAD SHX Text
9
AutoCAD SHX Text
11
AutoCAD SHX Text
5
AutoCAD SHX Text
8
AutoCAD SHX Text
1
AutoCAD SHX Text
2
AutoCAD SHX Text
4
AutoCAD SHX Text
6
AutoCAD SHX Text
7
AutoCAD SHX Text
WAGON LOADER POINT (FOR COKING COAL)
AutoCAD SHX Text
WAGON LOADER POINT (FOR LIMESTONE)
AutoCAD SHX Text
WAGON TIPPLER (FOR THERMAL COAL)
AutoCAD SHX Text
3
AutoCAD SHX Text
13
AutoCAD SHX Text
14
AutoCAD SHX Text
15
AutoCAD SHX Text
27
AutoCAD SHX Text
24
AutoCAD SHX Text
23
AutoCAD SHX Text
22
AutoCAD SHX Text
21
AutoCAD SHX Text
20
AutoCAD SHX Text
19
AutoCAD SHX Text
18
AutoCAD SHX Text
116
AutoCAD SHX Text
116
AutoCAD SHX Text
156
AutoCAD SHX Text
156
AutoCAD SHX Text
156
AutoCAD SHX Text
156
AutoCAD SHX Text
156
AutoCAD SHX Text
156
AutoCAD SHX Text
156
AutoCAD SHX Text
156
AutoCAD SHX Text
10
AutoCAD SHX Text
12
AutoCAD SHX Text
16
AutoCAD SHX Text
31
AutoCAD SHX Text
33
AutoCAD SHX Text
43
AutoCAD SHX Text
44
AutoCAD SHX Text
38
AutoCAD SHX Text
2381850 N
AutoCAD SHX Text
2382850 N
AutoCAD SHX Text
2383850 N
AutoCAD SHX Text
2384850 N
AutoCAD SHX Text
28
AutoCAD SHX Text
41
AutoCAD SHX Text
42
AutoCAD SHX Text
FUTURE COKE STOCK PILE
AutoCAD SHX Text
156
AutoCAD SHX Text
156
AutoCAD SHX Text
156
AutoCAD SHX Text
156
AutoCAD SHX Text
156
AutoCAD SHX Text
156
AutoCAD SHX Text
156
AutoCAD SHX Text
156
AutoCAD SHX Text
156
AutoCAD SHX Text
156
AutoCAD SHX Text
156
AutoCAD SHX Text
156
AutoCAD SHX Text
156
AutoCAD SHX Text
156
AutoCAD SHX Text
116
AutoCAD SHX Text
116
AutoCAD SHX Text
36
AutoCAD SHX Text
37
AutoCAD SHX Text
35
AutoCAD SHX Text
FUTURE STOCK PILE
AutoCAD SHX Text
40
AutoCAD SHX Text
OS
AutoCAD SHX Text
OS
AutoCAD SHX Text
OS
AutoCAD SHX Text
OS
AutoCAD SHX Text
OS
AutoCAD SHX Text
OS
AutoCAD SHX Text
OS
AutoCAD SHX Text
OS
AutoCAD SHX Text
OS
AutoCAD SHX Text
WH
AutoCAD SHX Text
WH
AutoCAD SHX Text
2380850 N
AutoCAD SHX Text
2379850 N
AutoCAD SHX Text
530900 E
AutoCAD SHX Text
30
AutoCAD SHX Text
29
AutoCAD SHX Text
40
AutoCAD SHX Text
ALL DIMENSIONS ARE IN METRES. ALL LEVELS ARE IN METRES AND ARE WITH RESPECT TO CHART DATUM (C.D) ALL COORDINATES ARE GIVEN IN METRES REFERRED TO UNIVERSAL TRANSVERSE MERCATOR (UTM) PROJECTION,SPHEROID (WGS 1984), ZONE 45 AS GIVEN BY INDOMER COASTAL HYDRAULICS (P) LTD. BATHYMETRY & SHORE LINE DETAILS ARE BASED ON BATHYMETRY SURVEY CARRIED OUT BY INDOMER COASTAL HYDRAULICS (P) LTD ON JANUARY 2007.
AutoCAD SHX Text
1. 2. 3. 4.
AutoCAD SHX Text
%%UNOTES :
AutoCAD SHX Text
N
AutoCAD SHX Text
SUBSTATION (ADMIN)
AutoCAD SHX Text
WATER TANK (ADMIN)
AutoCAD SHX Text
UG SUMP (ADMIN)
AutoCAD SHX Text
HEALTH CENTRE
AutoCAD SHX Text
OPERATION BUILDING
AutoCAD SHX Text
ADMINISTRATIVE BUILDING
AutoCAD SHX Text
DESCRIPTION
AutoCAD SHX Text
1
AutoCAD SHX Text
2
AutoCAD SHX Text
3
AutoCAD SHX Text
4
AutoCAD SHX Text
5
AutoCAD SHX Text
6
AutoCAD SHX Text
7
AutoCAD SHX Text
STAFF VEHICLE PARKING (ADMIN)
AutoCAD SHX Text
8
AutoCAD SHX Text
9
AutoCAD SHX Text
SECURITY OFFICE (ADMIN)
AutoCAD SHX Text
SL.NO
AutoCAD SHX Text
10
AutoCAD SHX Text
GATE HOUSE (ENTRY)
AutoCAD SHX Text
11
AutoCAD SHX Text
SECURITY OFFICE (ENTRY GATE HOUSE)
AutoCAD SHX Text
12
AutoCAD SHX Text
SECURITY OFFICE (EXIT GATE HOUSE)
AutoCAD SHX Text
GENERAL CARGO-TRANSIT SHED
AutoCAD SHX Text
STAFF VEHICLE PARKING
AutoCAD SHX Text
GENERAL CARGO-OPEN STORAGE
AutoCAD SHX Text
14
AutoCAD SHX Text
TRUCK PARKING-GENERAL CARGO
AutoCAD SHX Text
16
AutoCAD SHX Text
FUEL STATION (CONTAINER)
AutoCAD SHX Text
17
AutoCAD SHX Text
CONTAINER FREIGHT STATION
AutoCAD SHX Text
GATE HOUSE (EXIT)
AutoCAD SHX Text
15
AutoCAD SHX Text
13
AutoCAD SHX Text
18
AutoCAD SHX Text
19
AutoCAD SHX Text
BUS STOP
AutoCAD SHX Text
20
AutoCAD SHX Text
FIRE STATION
AutoCAD SHX Text
21
AutoCAD SHX Text
TRAILER PARKING
AutoCAD SHX Text
22
AutoCAD SHX Text
FUEL STATION (GENERAL CARGO)
AutoCAD SHX Text
23
AutoCAD SHX Text
WORKERS CANTEEN
AutoCAD SHX Text
24
AutoCAD SHX Text
ETP / STP
AutoCAD SHX Text
25
AutoCAD SHX Text
UG SUMP (PORT)
AutoCAD SHX Text
26
AutoCAD SHX Text
WATER TANK (PORT)
AutoCAD SHX Text
29
AutoCAD SHX Text
RTG WASH - PHASE 1
AutoCAD SHX Text
30
AutoCAD SHX Text
REEFER SUBSTATION - PHASE 1
AutoCAD SHX Text
CONTAINER PARKING YARD-PHASE 1
AutoCAD SHX Text
31
AutoCAD SHX Text
EQUIPMENT WORKSHOP
AutoCAD SHX Text
27
AutoCAD SHX Text
RAILWAY YARD
AutoCAD SHX Text
28
AutoCAD SHX Text
CONTROL TOWER
AutoCAD SHX Text
32
AutoCAD SHX Text
TRUCK PARKING - IRON ORE
AutoCAD SHX Text
33
AutoCAD SHX Text
THERMAL COAL STACKYARD
AutoCAD SHX Text
34
AutoCAD SHX Text
IRON ORE STACKYARD
AutoCAD SHX Text
35
AutoCAD SHX Text
LIMESTONE STACKYARD
AutoCAD SHX Text
36
AutoCAD SHX Text
COKING COAL STACKYARD
AutoCAD SHX Text
37
AutoCAD SHX Text
ROAD & CIRCULATION AREA
AutoCAD SHX Text
38
AutoCAD SHX Text
OTHER PORT OPERATIONS
AutoCAD SHX Text
39
AutoCAD SHX Text
LEAKING CONTAINER
AutoCAD SHX Text
42
AutoCAD SHX Text
CONTAINER PARKING YARD - PHASE 2
AutoCAD SHX Text
43
AutoCAD SHX Text
RTG WASH - PHASE 2
AutoCAD SHX Text
40
AutoCAD SHX Text
REEFER SUBSTATION - PHASE 2
AutoCAD SHX Text
41
AutoCAD SHX Text
44
AutoCAD SHX Text
GREEN BELT
AutoCAD SHX Text
OPEN STORAGE & TRANSIT SHED
AutoCAD SHX Text
OS
Page 38: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

Appendix C

Location Map

Page 39: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

N

H

5

N

H

4

2

NH 6

NH 23

N

H

6

N

H

4

2

N

H

6

NH 43

N

H

2

0

1

N

H

5

N

H

6

0

PARADEEP PORT

PROPOSED POSCO's PORT

PROPOSED ASTARANG PORT

PROPOSED GOPALPUR PORT

DHAMRA PORT

BHUBANESHWAR AIR PORT

NH

203

TO VISAKHAPATNAM

TO HOWRAH

TO SARAIP

ALLI

TO BILASPUR

17°46'52"N

81°22'13"E

22°30'42"N

87°41'14"E

22°30'42"N

81°22'13"E

87°41'14"E

17°46'52"N

BALASORE DISTRICT

21°32'58"N& 87°21'58"E

BHUBANESHWAR

ORISSA

SURROUNDING STATE BOUNDARY

RAILWAY LINE

NATIONAL HIGHWAY

SEAPORT

AIRPORT

ORISSA STATE BOUNDARY

ANDAMAN AND

NICOBAR ISLANDS

B A Y O F B E N G A L

A R A B I A N

LAKSHADWEEP

SRILANKA

S E A

INDIAN OCEAN

KEY MAP

I N D I A

LEGEND

SUBARNAREKHA PORT

C H H A T T I S G A R H

A N D H R A

P R A D E S H

W E S T

J H A R K H A N D

B E N G A L

21°32'58"N& 87°21'58"E

B A Y O F B E N G A L

STATE HEADQUARTER

BITTARKANIKA(S&NP)

N

H

2

2

4

N

H

2

1

7

OTHER ROAD

WATER BODY / RIVER / STREAM

0

Scale in Km

50

N

H

5

A

NH

200

N

H

2

1

5

RUSHIKULYA RIVER MOUTH

DEVI RIVER MOUTH

SIMILIPAL(S&NP)

KULDIHA(S)

HADGAD(S)

GAHIRMATHA(MS)

CHANDAKA-DAMPARA(S)

NANDANKANAN(S)

SATKOSIA GORGE(S)

BAISIPALLI (S)

KHALASUNI(S)

BADRAMA(S)

DEBRIGARH(S)

BALUKHAND-KONARK(S)

NALABAN (CHILKA)(S)

LAKHARI VALLEY(S)

KOTGAD(S)

KARLAPAT(S)

SUNABEDA(S)

SANCTURY / NATIONAL PARK

S

NP

MS

SANCTUARY

NATIONAL PARK

MARINE SANCTUARY

TURTLE NESTING CENTRE

SUBARNAREKHA

PORT

LOCATION MAP

AutoCAD SHX Text
Sankh River
AutoCAD SHX Text
Baitarani River
AutoCAD SHX Text
Subarnarekha
AutoCAD SHX Text
River
AutoCAD SHX Text
Mahanadi
AutoCAD SHX Text
Mahanadi
AutoCAD SHX Text
Mahanadi
AutoCAD SHX Text
Indravati River
AutoCAD SHX Text
Sabari River
AutoCAD SHX Text
Sileru River
AutoCAD SHX Text
N
AutoCAD SHX Text
Asana
AutoCAD SHX Text
Bagdihi
AutoCAD SHX Text
Bahalda
AutoCAD SHX Text
Bangriposi
AutoCAD SHX Text
Banki
AutoCAD SHX Text
Bargaon
AutoCAD SHX Text
Betnoti
AutoCAD SHX Text
Bhasma
AutoCAD SHX Text
Birmitrapur
AutoCAD SHX Text
Bonaigarh
AutoCAD SHX Text
Bovinathpur
AutoCAD SHX Text
Chitarda
AutoCAD SHX Text
Damribera
AutoCAD SHX Text
Garpos
AutoCAD SHX Text
Gobindpur
AutoCAD SHX Text
Jaintgarb
AutoCAD SHX Text
Jaleswar
AutoCAD SHX Text
Jharsuguda
AutoCAD SHX Text
Joshipur
AutoCAD SHX Text
Kanika
AutoCAD SHX Text
Kendumundi
AutoCAD SHX Text
Kesaibahal
AutoCAD SHX Text
Baunshapani Koira
AutoCAD SHX Text
Kuchaiburi
AutoCAD SHX Text
Kuchinda
AutoCAD SHX Text
Kumarkera
AutoCAD SHX Text
Kutra
AutoCAD SHX Text
Palasponga
AutoCAD SHX Text
Parsora
AutoCAD SHX Text
Rengali
AutoCAD SHX Text
Samasingha
AutoCAD SHX Text
Saria
AutoCAD SHX Text
Sundargarh
AutoCAD SHX Text
Surgura
AutoCAD SHX Text
Talsara
AutoCAD SHX Text
Baripada
AutoCAD SHX Text
Panposh
AutoCAD SHX Text
Raurkela
AutoCAD SHX Text
Debrigarh(WLS)
AutoCAD SHX Text
Bhajpur
AutoCAD SHX Text
Purunapani
AutoCAD SHX Text
Baljod
AutoCAD SHX Text
Kiriburu
AutoCAD SHX Text
Tensa
AutoCAD SHX Text
Pani
AutoCAD SHX Text
Padamapaharh
AutoCAD SHX Text
Balani Khandan
AutoCAD SHX Text
Barsua
AutoCAD SHX Text
Gurundia
AutoCAD SHX Text
Similipal
AutoCAD SHX Text
Gorumahisani
AutoCAD SHX Text
Champua
AutoCAD SHX Text
Bishra
AutoCAD SHX Text
Banei
AutoCAD SHX Text
Abasingi
AutoCAD SHX Text
Adaba
AutoCAD SHX Text
Altiri
AutoCAD SHX Text
Ampani
AutoCAD SHX Text
Anantpur
AutoCAD SHX Text
Athgarh
AutoCAD SHX Text
Baibali
AutoCAD SHX Text
Balangir
AutoCAD SHX Text
Baliguda
AutoCAD SHX Text
Balikana
AutoCAD SHX Text
Ballipadar
AutoCAD SHX Text
Banda Chhada
AutoCAD SHX Text
Bangalguda
AutoCAD SHX Text
Banigochha
AutoCAD SHX Text
Bankigarh
AutoCAD SHX Text
Banpur
AutoCAD SHX Text
Bansadhara
AutoCAD SHX Text
Banta
AutoCAD SHX Text
Barachana
AutoCAD SHX Text
Barakot
AutoCAD SHX Text
Baramba
AutoCAD SHX Text
Barasai
AutoCAD SHX Text
Bargarh
AutoCAD SHX Text
Barpali
AutoCAD SHX Text
Basudebpur
AutoCAD SHX Text
Baudh
AutoCAD SHX Text
Begunia
AutoCAD SHX Text
Belpara
AutoCAD SHX Text
Bhanjanagar
AutoCAD SHX Text
Bhuban
AutoCAD SHX Text
Bijepur
AutoCAD SHX Text
Bindagura
AutoCAD SHX Text
Binka
AutoCAD SHX Text
Bissamcuttack
AutoCAD SHX Text
Boran
AutoCAD SHX Text
Borigumma
AutoCAD SHX Text
Brahmagiri
AutoCAD SHX Text
Chandotora
AutoCAD SHX Text
Chandpur
AutoCAD SHX Text
Chatia
AutoCAD SHX Text
Chheligada
AutoCAD SHX Text
Chhindipade
AutoCAD SHX Text
Dabugam
AutoCAD SHX Text
Daspalla
AutoCAD SHX Text
Dehurda
AutoCAD SHX Text
Deogan
AutoCAD SHX Text
Deogaon
AutoCAD SHX Text
Deogarh
AutoCAD SHX Text
Dhama
AutoCAD SHX Text
Dhamini
AutoCAD SHX Text
Dhamnagar
AutoCAD SHX Text
Dharamgarh
AutoCAD SHX Text
Dharmsala
AutoCAD SHX Text
Dhenkikot
AutoCAD SHX Text
Digapahandi
AutoCAD SHX Text
Dublabahal
AutoCAD SHX Text
Gadala
AutoCAD SHX Text
Ghatgaon
AutoCAD SHX Text
Gobindpur
AutoCAD SHX Text
Gop
AutoCAD SHX Text
Goppili
AutoCAD SHX Text
Goyagonda
AutoCAD SHX Text
Gudari
AutoCAD SHX Text
Gunupur
AutoCAD SHX Text
Handapa
AutoCAD SHX Text
Hindola
AutoCAD SHX Text
Indipur
AutoCAD SHX Text
Jagatsingpur
AutoCAD SHX Text
Jagdalpur
AutoCAD SHX Text
Jajpur
AutoCAD SHX Text
Jamunkira
AutoCAD SHX Text
Jankia
AutoCAD SHX Text
Jararha
AutoCAD SHX Text
Jarpara
AutoCAD SHX Text
Jatni
AutoCAD SHX Text
Javaguda
AutoCAD SHX Text
Jayapatna
AutoCAD SHX Text
Jorigam
AutoCAD SHX Text
Jujomura
AutoCAD SHX Text
Junagarh
AutoCAD SHX Text
Kabirpur
AutoCAD SHX Text
Kaintragarh
AutoCAD SHX Text
Kalimala
AutoCAD SHX Text
Kalingia
AutoCAD SHX Text
Kamardihi
AutoCAD SHX Text
Kanas
AutoCAD SHX Text
Kaniah
AutoCAD SHX Text
Kantabanji
AutoCAD SHX Text
Kantalai
AutoCAD SHX Text
Kaptipada
AutoCAD SHX Text
Karasingi
AutoCAD SHX Text
Kendrapara
AutoCAD SHX Text
Keonjhargarh
AutoCAD SHX Text
Khaki Hat
AutoCAD SHX Text
Khandpara
AutoCAD SHX Text
Khaparakho
AutoCAD SHX Text
Khariar
AutoCAD SHX Text
Khurda
AutoCAD SHX Text
Kodala
AutoCAD SHX Text
Korapet
AutoCAD SHX Text
Kotagad
AutoCAD SHX Text
Kotapad
AutoCAD SHX Text
Kudumulagumma
AutoCAD SHX Text
Kunda
AutoCAD SHX Text
Kuparj
AutoCAD SHX Text
Kurtamgad
AutoCAD SHX Text
Lanjigarh
AutoCAD SHX Text
Mahidharpur
AutoCAD SHX Text
Malakanagiri
AutoCAD SHX Text
Malda
AutoCAD SHX Text
Maligam
AutoCAD SHX Text
Mannemkonda
AutoCAD SHX Text
Mansada
AutoCAD SHX Text
Marosile
AutoCAD SHX Text
Mattli
AutoCAD SHX Text
Moter
AutoCAD SHX Text
Mundher
AutoCAD SHX Text
Naikulsahi
AutoCAD SHX Text
Nandapur
AutoCAD SHX Text
Narsinghpur
AutoCAD SHX Text
Nayagarh
AutoCAD SHX Text
Norola
AutoCAD SHX Text
Nabarangapur
AutoCAD SHX Text
Padampur
AutoCAD SHX Text
Padwa
AutoCAD SHX Text
Pal Lahara
AutoCAD SHX Text
Pappadahandi
AutoCAD SHX Text
Partap Sasan
AutoCAD SHX Text
Patamundai
AutoCAD SHX Text
Patnagarh
AutoCAD SHX Text
Phulbani
AutoCAD SHX Text
Pipli
AutoCAD SHX Text
Pottasing
AutoCAD SHX Text
Purushottampur
AutoCAD SHX Text
Raighar
AutoCAD SHX Text
Raikia
AutoCAD SHX Text
Raj Kanika
AutoCAD SHX Text
Ramogiri
AutoCAD SHX Text
Rampur
AutoCAD SHX Text
Rasalpur
AutoCAD SHX Text
Ratanpur
AutoCAD SHX Text
Raulapadar
AutoCAD SHX Text
Rayagoda
AutoCAD SHX Text
Raygad
AutoCAD SHX Text
Sakhi Gopal
AutoCAD SHX Text
Salebhatsa
AutoCAD SHX Text
Salimi
AutoCAD SHX Text
Salepur
AutoCAD SHX Text
Sarangagada
AutoCAD SHX Text
Sarankul
AutoCAD SHX Text
Sarapali
AutoCAD SHX Text
Semiliguda
AutoCAD SHX Text
Sikarapai
AutoCAD SHX Text
Sikerkupa
AutoCAD SHX Text
Simanbadi
AutoCAD SHX Text
Sinapali
AutoCAD SHX Text
Sindhekela
AutoCAD SHX Text
Sipur
AutoCAD SHX Text
Sohela
AutoCAD SHX Text
Sonapur
AutoCAD SHX Text
Sorada
AutoCAD SHX Text
Soro
AutoCAD SHX Text
Subarnagiri
AutoCAD SHX Text
Sukinda Khas
AutoCAD SHX Text
Sunakhala
AutoCAD SHX Text
Sungar
AutoCAD SHX Text
Talcher
AutoCAD SHX Text
Tanga Mali
AutoCAD SHX Text
Thakurmunda
AutoCAD SHX Text
Thuamal Rampur
AutoCAD SHX Text
Tikarapara
AutoCAD SHX Text
Tikaraparha
AutoCAD SHX Text
Tikri
AutoCAD SHX Text
Titlagarh
AutoCAD SHX Text
Umarkot
AutoCAD SHX Text
Varanasi
AutoCAD SHX Text
Angul
AutoCAD SHX Text
Balasore
AutoCAD SHX Text
Brahmapur
AutoCAD SHX Text
Bhadrak
AutoCAD SHX Text
Bhawanipatna
AutoCAD SHX Text
Chatrapur
AutoCAD SHX Text
Cuttack
AutoCAD SHX Text
Dhenkanal
AutoCAD SHX Text
Ichchapuram
AutoCAD SHX Text
Puri
AutoCAD SHX Text
Sambalpur
AutoCAD SHX Text
Chitrakonda
AutoCAD SHX Text
Boipariguda
AutoCAD SHX Text
Pattangi
AutoCAD SHX Text
Bariguma
AutoCAD SHX Text
Narayanapatana
AutoCAD SHX Text
Kakariguma
AutoCAD SHX Text
Ramannaguda
AutoCAD SHX Text
Raipanga
AutoCAD SHX Text
Chandrapur
AutoCAD SHX Text
Katiagada
AutoCAD SHX Text
Manigurha
AutoCAD SHX Text
Gunupur
AutoCAD SHX Text
Komatlapeta
AutoCAD SHX Text
Kumbhikota
AutoCAD SHX Text
Paralakhemundi
AutoCAD SHX Text
Ramagiri
AutoCAD SHX Text
Udayagiri
AutoCAD SHX Text
Surangi
AutoCAD SHX Text
Gopalpur
AutoCAD SHX Text
Taptapani
AutoCAD SHX Text
Asika
AutoCAD SHX Text
Ganjam
AutoCAD SHX Text
Tala Hamma
AutoCAD SHX Text
Khalikot
AutoCAD SHX Text
Godapur
AutoCAD SHX Text
Kalyanasingapuram
AutoCAD SHX Text
Lakshmipur
AutoCAD SHX Text
Riamal
AutoCAD SHX Text
Lakich
AutoCAD SHX Text
Nauparha
AutoCAD SHX Text
Baldhiamal
AutoCAD SHX Text
Kesinga
AutoCAD SHX Text
Khajuripada
AutoCAD SHX Text
Gajalbarhi
AutoCAD SHX Text
Galleri
AutoCAD SHX Text
Balugan
AutoCAD SHX Text
Karachuli
AutoCAD SHX Text
Raja Ranapur
AutoCAD SHX Text
Kamakhydnagar
AutoCAD SHX Text
Daitari
AutoCAD SHX Text
Ioranda
AutoCAD SHX Text
Gogua
AutoCAD SHX Text
Khamar
AutoCAD SHX Text
Chandabali
AutoCAD SHX Text
Anantpur
AutoCAD SHX Text
Paradip
AutoCAD SHX Text
Machnagan
AutoCAD SHX Text
Astaranga
AutoCAD SHX Text
Kakatapur
AutoCAD SHX Text
Anandapur
AutoCAD SHX Text
Jayapur Kendujhar
AutoCAD SHX Text
Ahias
AutoCAD SHX Text
Konarka
AutoCAD SHX Text
Ramachandrapur
AutoCAD SHX Text
Udala
AutoCAD SHX Text
Balsinga
AutoCAD SHX Text
Baliapat
AutoCAD SHX Text
Bara Khunta
AutoCAD SHX Text
Karanjia
AutoCAD SHX Text
Bodo Raruan
AutoCAD SHX Text
Jeypore
AutoCAD SHX Text
Dhamra
AutoCAD SHX Text
NOTES: 1. WILD LIFE SANCTURIES, NATIONAL PARKSM AMRINES SANCTURAIES WILD LIFE SANCTURIES, NATIONAL PARKSM AMRINES SANCTURAIES DETAILS OBTAINED FROM : WWW.WILDLIFEORISSA.IN
Page 40: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

Appendix D

Survey Nos. covered under

the Project area

Page 41: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

SUBARNAREKHA PORT LAND DETAILS - CHAUMUKH VILLAGE

Sl No KHATA Nos PLOT Nos

1 879/1 5553 / 7150

5554 / 7151

5555 / 7152

5539 / 5556

4999 / 5557

5505

2 879 1730 / 5551

1815 / 5552

1816

3 875 4903 / 5554 (P)

4999 / 5555 (P)

Page 42: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

Appendix E

Port Limit Declaration by

Commerce and Transport,

Government of Odisha

Page 43: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing
Page 44: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing
Page 45: Subarnarekha Port Private Limited (SPPL) · 2019. 2. 6. · Capital dredging is required to create inner navigation channel, outer navigation channel, turning circle and berthing

6-3-1192/1/1, 5th Floor, Block No.3,

White House, Kundan Bagh, Begumpet, Hyderabad – 500 016

Ph: 91 -040 – 40354444 ; Fax: 91-040-40354430

L&T Infrastructure Engineering Limited