Stephen Tromans QC 39 Essex Chambers, London
Transcript of Stephen Tromans QC 39 Essex Chambers, London
1 © Stephen Tromans QC, 39 Essex Chambers
CAMBRIDGE NUCLEAR WORKSHOP
NUCLEAR LAW IN THE UK: A PRACTITIONER’S PERSPECTIVE
Stephen Tromans QC
39 Essex Chambers, London
The history of designing, constructing and operating new nuclear power stations in the UK
has been described as an “often depressing story” (Simon Taylor, Privatisation and Collapse
in the Nuclear Industry” (Oxford, Routledge, 2007). At the inception of the nuclear
programme there was huge optimism. The White Paper, A Programme of Nuclear Power,
published in 1955 (Cmnd. 6618) described nuclear power as “the energy of the future”, and
thought it might take as much as “five or more years” to complete a nuclear power station,
“including finding the site, designing the station and building it.” At that stage, this was
undertaken by the state, through the Central Electricity Generating Board (CEGB).
Within this framework of publicly promoted and financed projects, the UK’s nuclear fleet
was constructed, comprising the nine Magnox stations in the 1960s, under the second phase
of the programme, the seven Advanced Gas Cooled Reactors (AGRs) in the 1970s and 80s,
and the single Pressurised Water (PWR) reactor at Sizewell B. These plants have provided a
stable baseload contribution to UK energy needs for 5 decades, and look set to continue to
do so for some time yet. Recently (17 February 2016) EDF as the operator of four AGRs at
Heysham 1 and 2, Hartlepool and Torness has obtained safety clearance from the regulator
to continue to operate the first 3 until 2024 and Torness until 2030. EDF has calculated that
this extension has the potential to avoid 80 million tonnes of CO2 emissions, equivalent to
taking all the cars in the UK off the road for three and a half years.
At the same time, the future for nuclear power in the UK does not seem as secure as would
be desirable, despite strenuous efforts by the UK government to create a favourable
legislative, regulatory and economic climate. Pro-nuclear policies have almost invariably
been driven by political, energy security and economic circumstances: the Suez crisis of
1956 provided impetus to the Magnox programme, as did the OPEC oil embargo and oil
price crisis to the 1970s AGR programme and the miners’ strike of 1983-4 to the PWR
2 © Stephen Tromans QC, 39 Essex Chambers
initiative. At the same time, the wider issue of energy economics has been and remains the
key constraint. This is especially so following privatisation of the nuclear generating
industry in 1996. In December 1995, just before privatisation, the state-owned company
Nuclear Electric announced it would not proceed with investment in two further PWRs at
Hinkley Point and Sizewell, on the basis that the future of UK energy prices was not
sufficiently certain. At that point, the investment would have been between £2-3 billion for
each site. That decision has contributed to the energy gap now faced by the UK.
At the start of the 21st century, it did not appear that the nuclear industry had much of a
future in the UK. However, by 2008 the Business Secretary John Hutton was promoting the
goal of the UK becoming “the world’s number one location for new nuclear investment”.
This has entailed a number of steps by the government to promote and ease the path of
developing new nuclear power stations. These include:
1. A strong national policy in favour of nuclear power, underlain in particular by the need
to improve energy security and to reduce greenhouse gas emissions: see the White
Paper, The Future of Nuclear Power – the Role of Nuclear Power in a Low Carbon UK
Economy (Cm. 7124, May 2007).
2. A much more efficient planning regime to fast track major national infrastructure
projects, including nuclear power stations, under the Planning Act 2008. This avoids the
delays caused by monster planning inquiries, such as that for the Sizewell B project in
the 1980s and aims to conclude the examination of projects in a matter of months,
rather than years. This is underpinned by national policy statements, and applications
are to be determined in accordance with such statements, except in narrowly defined
circumstances (see s. 104 of the Planning Act). The process is heavily front loaded, and
in the case of nuclear power projects extends to the assessment and identification of
suitable sites for the period up to 2025: see NPS EN-6 Nuclear Power Generation (July
2011). In the case of Hinkley Point C, development consent (including many linked
items of infrastructure and considerable compulsory purchase powers) was granted on
19 March 2013, the application having been made on 31 October 2011. The
examination by the Panel was completed within 6 months (March – September 2012),
the report to the Secretary of State was issued within a further three months, and the
3 © Stephen Tromans QC, 39 Essex Chambers
decision made within three months thereafter. That is a remarkably swift timescale for
such a massive, potentially controversial and first of its kind project. The consent
survived a legal challenge by the National Trust for Ireland on transboundary
environmental assessment: R (An Taisce (The National Trust for Ireland) v. The Secretary
of State for Energy and Climate Change [2014] EWCA Civ 1111. The Court accepted the
Secretary of State’s argument (para. 40) that “… evidence that the risk of a severe
nuclear accident is not merely unlikely, but extremely remote, is capable of being
‘compelling evidence’ that a proposed nuclear power station is not likely to have
significant transboundary effects, since it is common ground that such effects would be
likely to occur only if there was such an accident”. It has been pointed out by one
commentator that the legal challenge took 509 days since the decision was taken,
whereas the application took 496 days to be decided from when it was made, so that
the challenge more than doubled the time from application to possible implementation
(Angus Walker, Bircham Dyson Bell, 2 August 2014: https://www.bdb-
law.co.uk/blogs/planning-act-2008/570-an-taisce-loses-hinkley-case-at-the-court-of-
appeal-but-may-fight-on/).
3. Efficient systems for the prior justification of the practice of generating electricity from a
particular type of nuclear reactor, and for generic design assessment of reactor types so
as to reduce the time later taken in considering and determining applications for a
nuclear site licence. The Justification of Practices Involving Ionising Radiation
Regulations 2004 have been used to obtain robust decisions justifying generation of
energy from the Areva EPR and the Westinghouse AP 1000 (October 2010) and the
Hitachi-GE ABWR (February 2015). The first decision survived a legal challenge (see R
(Walker) v. Secretary of State for Energy and Climate Change [2011] EWHC 2048
(Admin)) and the ABWR decision was not challenged. Generic design assessment (GDA)
is an administrative process developed by the Office for Nuclear Regulation and the
Environment Agency allowing the regulators to assess the safety, security and
environmental implications of new reactor designs, separately from the applications to
build them at specific sites. It allows them to get involved with designers at the earliest
stage, where they have the most influence. By assessing at the design stage, any
potential issues can be identified and highlighted so that they can be addressed by the
companies who have submitted a design for assessment, before commitments are made
4 © Stephen Tromans QC, 39 Essex Chambers
to construct the reactors. The system has many benefits, both for regulators and
industry. In December 2012 ONR confirmed that EDF and AREVA's UK EPR reactor
design is suitable for construction in the UK and a Design Acceptance Confirmation
(DAC) and Statement of Design Acceptability (SoDA). The Westinghouse AP1000 reactor
design re-entered the GDA process in August 2014 with 51 outstanding issues remaining,
which will need to be resolved before Design Acceptance Confirmation and a Statement
of Design Acceptability can be granted. ONR are currently assessing Hitachi-GE's UK
Advanced Boiling Water Reactor (UK-ABWR ).
4. The UK has managed proactively any negative implications of the Fukushima accident.
This has involved playing a prominent role in international work within the IAEA, G8, G20
and other international fora, to provide an action plan in response; participation in the
EU stress test initiative; revisiting its own arrangements on public contingency planning
for such emergencies and how such arrangements are tested; and implementing
recommendations on planning controls around nuclear sites. The former chief nuclear
inspector, Dr Mike Weightman, published a comprehensive report in September 2011
on the implications for the UK nuclear industry, and this was followed up by a report on
implementation in October 2012: Progress in Implementing the Lessons Learnt from the
Fukushima Accident, which records the responses by operators to the industry-facing
recommendations. It does not appear that the Japanese accident has presented a
serious impediment to the development of new reactors in the UK.
Polls suggest that the majority of the public support nuclear power, largely on the basis
of energy security and job-creation. Those opposing it tend to be more concerned about
long-term waste management than operational safety. There have been a number of
YouGov surveys, but the most thorough is probably the survey conducted in March 2013
by the UK Energy Research Centre (Public Attitudes to Nuclear Power and Climate
Change in Britain Two Years after the Fukushima Accident, Poortinga, Pidgeon, Capstick
and Aoyagi, 19 September 2013). This shows that public support for new nuclear build is
linked to tackling climate change and improving energy security. By contrast to Japan,
and some other European countries, the UK public’s confidence in nuclear power and
those regulating it has been largely unaffected by Fukushima. Indeed, between 2005
and 2013 the public’s attitude to whether the benefits of nuclear power outweighed the
risks reversed. In 2005 around 40% believed risks outweighed benefits and just over 30%
believed the opposite. By 2013 the respective figures were just under 30% and just
5 © Stephen Tromans QC, 39 Essex Chambers
under 40%. As of 2013, more respondents favoured building new nuclear power
stations (42%) than opposed it (32%).
Much has been made in some quarters of e-mails provided to The Guardian in the
immediate aftermath of Fukushima which showed collaboration between officials at the
Department for Business, Innovation and Skills and nuclear industry companies, which it
is said showed an “attempt to draw up a co-ordinated public relations strategy to play
down the Fukushima nuclear accident”. Whether or not this was a storm in a teacup, it
does of course illustrate a serious point, which is that regulation of the nuclear industry
must be rigorously separated from commercial and political interests which support the
industry. This is, or should be, a central tenet of nuclear regulation world-wide, though
unfortunately it was not properly implemented in Japan pre-Fukushima. What is striking
about the position in the UK is that on 14 March 2011, within 3 days of the accident, HM
Chief Inspector of Nuclear Installations, who is entirely independent of BiS, DECC or the
nuclear industry, had been requested to examine the circumstances of Fukushima and
what lessons could be learnt on safety. He had produced an interim report within 2
months, and a comprehensive 288 page report within about 6 months. As Dr
Weightman put it (p. (v)), in the UK the regulator (ONR) “operates independently both of
the industry and of Government, which is important given the Government’s policy of
promoting nuclear power”. BiS is not the regulator, nor is DECC. So long as they do not
mislead the public, they are free to promote nuclear power and if they see fit, manage
the adverse political or opinion consequences of an accident such as Fukushima. What
is much more important is that there is an independent regulator which the public can
trust to apply the highest safety standards and to ensure that operators are accountable
for learning lessons and improving safety in the light of such incidents.
5. The Government has been working to implement changes to the third party liability
regime made by the 2004 Protocols to the Paris and Brussels Conventions. The relevant
order (the Nuclear Installations (Liability for Damage) Order) was finally laid before
Parliament on 23 February 2016, and will come into force once the 2004 Protocols
themselves come into force. This will widen significantly the heads of liability for which
claims can be made and will increase the limit of liability to € 1.2 billion. It is however
fair to say that many types of loss or detriment which might result from a major incident
(e.g. enforced evacuation) would not necessarily be legally eligible for compensation in
6 © Stephen Tromans QC, 39 Essex Chambers
the absence of physical injury or damage to property and nor would € 1.2 billion
approach the potential levels of compensation required in a worst case incident. The
OECD has estimated third party damage ranging up to $100 billion for the most extreme
event, and third party claims for Fukushima could it appears be around half that sum.
6. Finally, the government has attempted to create acceptable financial conditions for the
massive private sector investment necessary to build a new nuclear power station. On
October 22, 2013 the UK notified to the European Commission its proposed measures in
respect of Hinkley Point C in terms of an Investment Contract (the precursor of a
Contract for Difference under its Electricity Market Reforms in what was then the Energy
Bill) and a Credit Guarantee by HM Treasury under the UK Infrastructure Guarantees
Scheme. Essentially the proposal was that the company developing Hinkley Point C
would receive a fixed price (the Strike Price) for the electricity produced up to a
maximum cap, effectively guaranteeing a fixed return. The Strike Price was set at £92.50
per MW hour, indexed to the Consumer Price Index, to be reduced to £89.50 should a
second station be built at Sizewell C. It was the subject of commercial negotiation,
informed by modelling. The duration was 35 years. In addition the Investment Contract
would contain provisions to address the situation where the plant was shut down for
political reasons. It appeared that the UK might be in for a hard time in convincing the
Commission of the merits of its case that the support measures were acceptable under
State Aid rules. However, on October 8, 2014 it was announced that the College of
Commissioners had approved the proposals. This followed what Commission Vice-
President Almunia described as “significant” modifications to the proposals, which
would limit distortions of competition within the EU, as well as benefiting UK taxpayers.
The final decision is (EU) 2015/658. The Commission noted that the final
Investment/CFD Agreement would incorporate new “gain share” mechanisms on
construction costs and return on equity. On the question of whether the proposals
pursued EU objectives of common interest, the UK’s position was that the relevant
objectives were decarbonisation, security of supply and diversity of supply; that other
measures such as energy efficiency and demand side response were important (and
were being deployed) but could not attain their objectives alone; that it would be unduly
7 © Stephen Tromans QC, 39 Essex Chambers
risky to rely on other technologies without nuclear; that in any event the UK had
determined that nuclear should be part of its energy mix, which it was entitled to do;
and that its energy policy was consistent with an objective of common interest under
the Euratom Treaty (promotion of the peaceful uses of nuclear energy). The UK also
clearly devoted considerable effort to explaining the various facets of market failure
which needed to be addressed, both for new and low carbon energy technologies
generally and nuclear energy in particular. These were not purely theoretical, but were
real, as witness the absence of investment in new nuclear power stations since market
liberalisation in the UK. Essentially the Commission accepted this case. The Minutes of
the 2100th meeting of the Commission held on 8 October (PV(2014) 2100 final) at which
the decision was taken indicate its political sensitivity and that it could be regarded as a
very important precedent. It was stressed that the scale of economic analysis to which
the proposals had been subject was enormous, if not unprecedented: the Chief
Economist at the Directorate-General for Competition had applied no less than 24
econometric models to it. A key finding was that the rate of return applied was
reasonable in view of the risks incurred in constructing and operating the plant. Whilst
the Commission was at pains to stress that subsequent proposals for State Aid approval
in the nuclear sector would be assessed individually, the decision will inevitably have
some precedent effect. The decision that the package was compatible with the internal
market under Article 107 TFEU will have been greeted with relief by the UK and no
doubt EDF. However, almost immediately there was speculation about possible legal
challenge to the Commission’s decision. Such challenges have now been formally
instigated by Austria (Case T-356/15 Austria v. Commission) and by a German energy
company founded by Greenpeace (Case T-382/15 Greenpeace Energy v. Commission).
The precise legal basis of the challenges is at present unclear. However, certainly in the
case of Austria it appears to be politically motivated. The decision to take action was
taken by the Council of Ministers on 22 June and subsequently approved by Parliament.
The Austrian Chancellor, Werner Faymann, is reported as having expressly stated that
the action is intended as a "… deterrent to investors, not only in Britain but throughout
Europe" and as "… a further step in [Austria's] anti-nuclear policy, whose long-term
objective is a nuclear-free Europe." It appears to argue that nuclear is not an innovative
technology, that it has an overall negative environmental impact, and opposes the
8 © Stephen Tromans QC, 39 Essex Chambers
reasoning that it contributes to the promotion of an industry: It is of course a puzzling
conundrum that the Euratom Treaty, with its express objective “… to create the
conditions necessary for the development of a powerful nuclear industry which will
provide extensive energy resources …”, now has not only parties who support nuclear
energy but also parties who are ideologically opposed to it.
All this represents an unprecedented Governmental effort to support an industrial
technology. The question still remains however of whether it will be enough. The costs and
risks of building a new nuclear power station which will operate in a liberalised energy
market, constantly competing against other sources of electricity, may be just too great for
even the largest companies. The UK’s existing power stations were built on a very different
economic model, essentially by centrally-planned government utilities, simply seeking to
meet consumer demand at the lowest cost in the long term over the life of the project.
Where new nuclear build is proceeding, it is essentially under that model. In the UK, despite
all the impediments to developing new nuclear power stations having been resolved or
overcome, the front-runner, EDF, has not yet made a firm commitment to proceed with the
£24.5 billion Hinkley Point C project. It is now partnered with China General Nuclear
Corporation, holding a 33.5% share in the project. The delays not only present increasing
risks to the UK’s energy security until the project begins generating electricity – now no
earlier than 2025 – but also will play havoc with the UK’s carbon budget. It has been
estimated by Carbon Brief that each year of delay adds about 8-11 million tonnes of CO2 to
the UK’s emissions. To replace Hinkley Point’s contribution to zero-carbon emissions, it is
estimated that around 3,000-5,500 onshore wind turbines would have to be built, or 800-
1,500 offshore turbines, i.e. roughly doubling current capacity. Even then the intermittent
nature of wind energy means that fossil fuel back up would be needed. It is interesting in
this respect to note that the threat posed by unconstrained carbon emissions has
superseded for many environmentalists the perceived detriments and dangers of nuclear
power. The UK’s Committee on Climate Change regards new nuclear powers stations as
indispensable in reducing the carbon intensity of the energy sector.
Reticence in committing to investment decisions is not unique to the UK: in February 2016
the US federal Nuclear Regulatory Commission approved the construction of two new
reactors at the South Texas Project site near Houston, a process which had taken several
years. However, the costs of the project coupled with currently low power prices in Texas
9 © Stephen Tromans QC, 39 Essex Chambers
mean that the projects promotor, NRG Energy, does not currently plan to implement the
licenses and is seeking other sources of funding for the $14 billion project.
There are three emerging areas which present challenges to new build, aside from these
economic issues. These are (1) security and safeguards; (2) corporate control and structures;
and (3) long term management of sites and wastes.
Security and safeguards
Unfortunately, nuclear terrorism and nuclear proliferation remain growing threats. Security
and safeguards therefore must assume an ever increasing importance in nuclear regulation
and in the design and construction of new reactors. This extends back to the GDA phase. As
the ONR website says:
“Security forms a major part of the Generic Design Assessment process and requires
the power station design company to submit Conceptual Security Arrangements
providing sufficient information to enable ONR to make an informed judgement of
the adequacy of the security aspects of the generic design. ONR Security Inspectors
work as part of the wider ONR regulatory team to ensure the design company
incorporates security by design across the full spectrum of protective security
measures, including physical protection, cyber and information and personnel
security. The Conceptual Security Arrangements will ultimately form the basis of a
Nuclear Site Security Plan for any licensed site using the design.”
Similarly the once recondite area of Export Controls over fissile materials has become a
mainstream area of concern. Its importance is shown by the collaboration in 2015 between
governments and industry in the BOTTICELLI project seeking to enhance and promote best
practices, the first meeting of the parties being held in Brussels in September 2015. They
subscribe to Ten Export Control Principles, which include establishing and implementing an
effective Internal Compliance Programme with commitment at the highest levels of
management.
10 © Stephen Tromans QC, 39 Essex Chambers
Corporate control and financial structures
A key issue for the ONR in the current world of licensing is the management structure and
capabilities of the licensee. In the old world, the operator had all the relevant technical
know-how, and access to government funding. As the then Nuclear Installations
Inspectorate pointed out to the government in 1994 (Health and Safety Commission,
Submission to the Nuclear Review), when the Nuclear Installations Act was drafted the
operators of nuclear installations were government-owned organisations, which had
longevity, financial security and adequate resources. In today’s world these matters cannot
be taken for granted. There will be complex commercial and corporate relationships
underlying the project. All the main projects are the product of joint ventures between non-
UK parties: Hinkley Point C and Sizewell C between EDF (France) and CGN (China), with
Areva providing the reactor system; Wylfa and Oldbury between Hitachi (Japan) as owner of
Horizon and Hitachi-GE Nuclear Energy (Japan and USA) as technology provider; and
Moorside (NuGeneration) between Toshiba (Japan) and GDF Suez (France).
It is a fundamental tenet of nuclear site licensing in the UK that a single corporate body
should have responsibility under the licensing system (both for compliance with the licence
and for the purposes of liability and insurance under the Nuclear Installations Act) and that
there must be no ambiguity as to its identity. This presents novel and potentially difficult
challenges to ONR to ensure through the site licensing process that the licensee has the
intelligent customer capability to control the installation and operation of the reactor, the
corporate structure to ensure a clear chain of command on decisions affecting safety, and
the financial capability to plough in fund where necessary, possibly many years into the
future, to ensure that safety is maintained. Since privatisation of the nuclear industry, the
NII and later the ONR have developed site licence conditions to require approval of
management systems which give due priority to safety (licence condition 17), , the
appointment of suitably qualified and experienced person (licence condition 12), control
and supervision of operations by such persons (condition 26), , organisational capability in
the sense of adequate financial and human resources to ensure safe operation (condition
36(1)) and the making of arrangements for the control of changes to structure or resources
which may have safety implications (condition 36(2)).
11 © Stephen Tromans QC, 39 Essex Chambers
Long term management of the site
One area that has perhaps been neglected in regulatory terms is the long term management
of nuclear sites. Decommissioning is of course an important aspect of site licensing as is the
decision by ONR as to when the site is deemed to have ceased to represent any danger from
ionising radiation (see Nuclear Installations Act 1965, s. 5(3)). That is however only one
aspect of the regulatory scheme. Decommissioning of a nuclear site will result in large
quantities of radioactive waste, subject to environmental permitting by the Environment
Agency, Natural Resources Wales, or SEPA in Scotland. Not all of this material will be
removed for disposal off-site. Buried structures such as foundations, drains and pipework,
may well be sufficiently contaminated to themselves become radioactive waste when no
longer in use, as may excavated soil which is redeposited on the site. When the present
generation of nuclear power stations was built little, or in truth probably no, consideration
was given as to these issues.
The relevant agencies have recently issued a consultation document providing guidance on
these issues: Guidance on Requirements for Release of Nuclear Site from Radioactive
Substances Regulation (February 2016). Under this guidance operators of new facilities will
be expected to have regard right from the outset as to how they intend to design, build,
operate and decommission the facilities so as to meet regulatory standards for release from
regulation. The overarching requirements are the reduction of radiological risk to as low as
is reasonably achievable (ALARA) and the concomitant principle of optimisation. In
particular, operators will need, at the outset, to ensure the site for the reactor is
characterised before construction commences and that an appropriate Waste Management
Plan (WMP) and Site Wide Environmental Safety Case (SWESC) are in place. The WMP
should provide “… a comprehensive description of the current intent for dealing with all the
anthropogenic radioactivity remaining on or adjacent to the site”. The SWESC should be a
set of claims addressing “… the present state and all envisaged future states of the site, both
during its lifetime of the permit and during the indefinite period after the permit has been
surrendered”. This may require the assumption of a period of restricted use pending
radioactive decay and attenuation processes, provided the operator can demonstrate that
12 © Stephen Tromans QC, 39 Essex Chambers
reliable controls can be put in place: such a period is unlikely to exceed 300 years “because
of the major social changes that may take place over long periods of time” (para. 3.3.10).
Conclusions
Over the past decade the UK government has made strenuous and sustained efforts to
promote a nuclear renaissance by putting in place the policy, legal, regulatory and financial
frameworks necessary for new build. Ultimately however, it is probably the market which
will decide whether this takes place and to what extent.
Biography: Stephen Tromans QC is a barrister specialising in energy, infrastructure and environmental law. He
has a particular focus on nuclear law and has worked with both EDF and Horizon in relation to their current
projects in the UK. He is the author of the leading textbook, “Nuclear Law” and is a board member of the UK
arm of the International Nuclear Lawyers’ Association (INLA UK). He represented the Nuclear Industries’
Association in successfully defending the legal challenge to justification of the EPR reactor design.
Further information is available at http://www.39essex.com/barrister/stephen-tromans-qc/