Status of HTS Projects in the US - superpower-inc.com · Albany HTS Cable Project ... • No...
Transcript of Status of HTS Projects in the US - superpower-inc.com · Albany HTS Cable Project ... • No...
superior performance.powerful technology.
SuperPower, Inc. is a subsidiary of Royal Philips Electronics N.V.
Status of HTS Projects in the US
Chuck WeberDirector, HTS ApplicationsApril 22, 2008
APPA 2008Engineering & Operations Technical ConferenceIndianapolis, Indiana
APPA, April 23, 2008, Indianapolis, IN
HTS Materials Research– Synthesis– Characterization– Microstructure-Property
Relationships– Other
HTS Materials Research– Synthesis– Characterization– Microstructure-Property
Relationships– Other
ScienceScience
CryogenicsDielectrics
CryogenicsDielectrics
Epitaxial Film GrowthApproach single crystal Ic
Epitaxial Film GrowthApproach single crystal Ic
Market-Ready Electric Power Equipment
- Conductor Development- Applications- Strategic Research
SystemsElectric Power Application
Prototypes
SystemsElectric Power Application
Prototypes
DOE HTS Program R&D Activity Flow
Long Wire ProcessingApproach short length IcLong Wire Processing
Approach short length IcMarket-Ready HTS Wires and Coils
APPA, April 23, 2008, Indianapolis, IN
U.S. HTS Cable Installations
Albany, NY
Carrollton, GA
Long Island, NY
Columbus, OH
New Orleans, LA New Project
New York, NY (DHS)
APPA, April 23, 2008, Indianapolis, IN
Albany, NY - Site Location
APPA, April 23, 2008, Indianapolis, IN
• Demonstration of technical and commercial viability of underground HTS cable operation between two National Grid substations
– 350m long - 34.5kV - 800Arms - 48MVA• Cable was energized on July 20, 2006 and serves the equivalent of 25,000 homes• 2006 installation connects two lengths of 1G cable totaling 350
meters with the world's first HTS cable-to-cable joint, required for long cable runs
Albany HTS Cable Project
• Cable operated for more than 9 months (>6,720 hours) before taken-off-line
• 30 m section has been replaced with a 2G cable - world's first use of 2G in any utility device
Cable configuration: 3 phases in 1 common cryostat
34kV, 48MVA
APPA, April 23, 2008, Indianapolis, IN
66
67
68
69
70
71
7/20 8/17 9/14 10/12 11/9 12/7 1/4 2/1 3/1 3/29 4/26
Date (2006-2007)
Tem
pera
ture
[K]
0
4
8
12
16
20
Tran
smitt
ed E
lect
ricity
[MVA
]
Cable Inlet Temperature
Cable Outlet Temperature
Transmitted Electricity
Chiller System ShutdownSupply Voltage Issue
Energizedon July 20,2006
Completedon May 1, 2007
Fault Current Event
7kA
8 cycle
The HTS cable system was checked for damage after the fault eventNo Issues Re-connected to Power Grid
More Than 6,700 Hrs of Reliable Power Transmission
Summary of Phase I Operation
APPA, April 23, 2008, Indianapolis, IN
Excellent overall performance obtained in 2G cable
Ic of conductor layers ~ 2660 –2820A (DC, 77K, 1μV/cm)
Ic of shield layers ~ 2400 – 2500A (DC, 77K, 1μV/cm)
-0.5
0
0.5
1
1.5
2
0 500 1000 1500 2000 2500 3000Current (A, DC)
Elec
trica
l Fie
ld(u
V/cm
)
Core-1Core-2Core-3
Ic Criterion (1uV/cm)
0.001
0.01
0.1
1
100 1000 10000Loading Current (Arms, 60Hz)
AC
loss
(W/m
/pha
se)
Measured value
0.34 W/m/ph @ 800 ArmsAlmost same result as previous
1 meter test 2G cable
No Ic degradation and No defect was found at dismantling inspection when bent to a diameter of 2.4 m
Cable withstood AC 69kV for 10 minutes and Impulse ±200kV, 10 times
APPA, April 23, 2008, Indianapolis, IN
Columbus HTS Cable Project• 200-meter, 3-phase HTS power cable at an American Electric Power
substation in Columbus, OH• Cable was energized August 8, 2006 and serves the equivalent of 36,000
homes, summer peak 2715 Amps• New “triax” cable design – all 3 phases in one cable and uses ½ the
amount of HTS wire compared to other designs• Cable has operated successfully for more than 1 year – 99.8973%
availability (8751/8760 hours)• Pulse tube cryocoolers installed and running as expected
3 Superconducting Phases
13.2kV, 69MVA
APPA, April 23, 2008, Indianapolis, IN
LIPA Project Overview
World’s First Installation of a Transmission Voltage HTS Cable
• Long Island Power Authority – Holbrook Substation• Electrical Characteristics
- Design Voltage/Current – 138kV/2400A ~ 574MVA- Design Fault Current – 51,000A @ 12 line cycles (200ms)
• Physical Characteristics- Length ~ 600m- HTS Conductor Length ~155km- Cold Dielectric Design
• Hardware Deliverables- Three ~600 m Long Phase Conductors- Six 138kV Outdoor Terminations- One Refrigeration System + Laboratory Pulse Tube
System• Installation/Commissioning – Spring 2008
LIPA Cable Project and Project Team
SPI
LIPA Project Status
North End
Terminations
Refrigeration System
StatusSystem is manufactured, installed and will be commissioned in Spring 2008
New Project: AMSC “LIPA 2A” HTS Cable
LIPA 2A Project Scope:• Demonstrate cost-effective 2G cable at transmission voltage
- Use existing system – replace 1G wire with 2G
• Introduce repairable cryostat and cable joint
• Develop low-cost, reliable, and efficient refrigeration system- 65K/20 kW Turbo Brayton refrigerator
• Demonstrate inherent fault current limiting capability at transmission voltage
HV Termination
RedundantCooling & Control
Cold Termination
Heat
Pow
er
SC
AD
A
Supply
Return
HV Termination
RedundantCooling & Control
Cold Termination
Heat
Pow
er
SC
AD
A
Supply
Return
APPA, April 23, 2008, Indianapolis, IN
New Project: New Orleans HTS CableProblem:• Load growth in urban area• Saturated 13 kV distribution• 230/13 substation to north &
south of area• Need new substation at mid-
point
Challenges:• Overhead rights of way for
230 or 13 kV very difficult or impossible
• Small footprint available for new substation dictates gas insulated substation 230 kV equipment or expensive station expansion
• 230 kV solution: placing transformer in dense residential area
• 13 kV conventional: Voltage drop, power quality
Solution:• 13.8 kV HTS cable to transmit 60 MVA into small footprint
station. (2 splices, three sections)• 1700 meters HTS cable• Meets load growth needs• No transformers needed• Leverage reserve transformer capacity at south end• Single point cooling station• 13.8 kV HTS replaces 230 kV underground• Cost-effective with DOE support
HYDRA Project Overview
World’s First Installation of an Inherently Fault Current Limiting HTS Cable
• Sponsored by Department of Homeland Security• Installed in Consolidated Edison Company of New York grid• Inherently Fault Current Limiting HTS cable connecting two substations in
Manhattan• Electrical Characteristics
- Design Voltage/Current – 13.8kV/4,000A- Maximum Fault Current – 40,000A
• Physical Characteristics- Length ~ 300m with cold dielectric design
• Hardware Deliverables- One ~300m Long 3-Phase Cable- Three 13.8kV Outdoor Terminations / Three 13.8kV Indoor Terminations• One Refrigeration System
• Installation/Commissioning – Spring 2010
HYDRA Project Team
AMSCPrime Contractor
Con Edison SouthwireAMSC
Cable and Accessory Design
Cable Manufacturing
Cable and Accessory Installation
Utility Requirements
Project Oversight
FCL Cable System Site
Altran Solutions, Construction Engineering
Technical Oversight
Wire Development
Wire Manufacturing
System Hardware Development
Project Management & System Design
Air Liquide, Refrigeration System
Hydra Project Status
• System design in process
• Two single-phase 3-meter engineering cables fabricated and testing underway
• Three phase 50-meter cable demonstration scheduled for fall 2008
• Cable termination design started
• Refrigeration system requirements established
• Construction drawing package in review with Consolidated Edison
• System installation and commissioning in spring 2010
APPA, April 23, 2008, Indianapolis, IN
Fault Current Limiters
APPA, April 23, 2008, Indianapolis, IN
New Project: SuperPower 138 kV FCL
• “Continuation” of current DOE project: – 1Φ alpha fabrication and test– 3Φ beta design, fabrication, test and
grid installation• Site selected: AEP TIDD substation
– 1,200 Arms, 138 kV– Prospective fault current is 13.8 kArms
(~37 kApeak)• DOE Investment - first period: $2.4M, total
up to $5.8M Single Phase SFCL
Bushings
MatrixAssembly
HTS Elements
Cryostat
• FCL design features matrix design consisting of parallel 2G HTS elements and conventional coils
Nissin Electric Co. Ltd.
APPA, April 23, 2008, Indianapolis, IN
TIDD Substation – One-Line Diagram (Partial)
Proposed SFCL Installation Location
APPA, April 23, 2008, Indianapolis, IN
RUL Description
5 CyclesFault
13kA/7kA
18 Cycles Load Current
15 sec Load Current
135 sec Load Current
5 CyclesFault
13kA/7kA
5 CyclesFault
13kA/7kA
5 CyclesFault
13kA/7kA
Breaker opens and locks-out
Recovery under NO Load Current
5 CyclesFault
13kA/7kA
160 sec Load Current
Recovery Under Load (RUL)
Load current flows through HTS / Shunt circuitry while cooling down from heating during fault transient(s).
Typical AEP reclosure sequence
Shu
nt
2G Elements
APPA, April 23, 2008, Indianapolis, IN
New Project: AMSC 115 kV FCL• Final target specs: SuperLimiter FCL system
– 115 kV, 1200 A nominal rating– Fault current reduction from 80 kA to below 55 kA
• 5 year project – Phase 1a
• 2G wire• Develop optimized wire for HV
FCL• HV system modeling and design
– Phase 1b• Develop switching modules,
cryostat and terminations• Build and lab-test single phase
HV system– Phase 2
• Build full 3-phase HV system• Install and test in SCE grid
• DOE Investment - Phase 1a: $3.2M, total up to $12.7M
APPA, April 23, 2008, Indianapolis, IN
SPE Project Description
APPA, April 23, 2008, Indianapolis, IN
APPA, April 23, 2008, Indianapolis, IN
APPA, April 23, 2008, Indianapolis, IN
Key Technology Component: SuperLimiter Shunt Configuration with Fast Switch (AMSC/Siemens)
APPA, April 23, 2008, Indianapolis, IN
New Project: SC Power Systems 138 kV Class FCC• Features HTS coil and DC power supply in
a saturable reactor in series with AC line • Project Phases (5 years total)
– 15 kV Class w/ 1G HTS wire to be installed at test site
– 15 kV Class replaced with 2G wire and installed at test site
– Development & Demo of 69 kV Class
– Development & Demo of 138 kV Class
• DOE Investment - First phase: $2.4M, total up to $11M
29
Fault Current Limiter – Surge Suppressor for Power Grids» We keep the lights on «
SC Power Systems, Inc. is now Zenergy Power, Inc.
Zenergy has two US contracts for its patented fault current limiter– California Energy Commission grant for $500k to install
13.8kV FCL in the SoCal Edison grid– DOE grant for $11M to develop and install 138kV FCL
First phase to install 13.8kV FCL at utility to be determined
30
Prototype Hardware Testing Program
Successful testing in Q4 2007 under observation of major US utilities
PG&E San Ramon, CA – Oct 2007– 480V and 460A steady state current
Powertech Labs British Columbia – Dec 2007– 13kV and 1100A steady state current
Testing at Powertech – Dec 2007
31
Short Circuit Test ResultsFirst Prototype – 21% fault current reduction
100 200 300 400 500 600ms-30
-20
-10
0
10
20
30
40kA
Line
Cur
rent
[kA]
-s033ias036ia
16 kA rms NO FCL
12.7 kA rms w/ FCL
32
Hardware Schedule for 2008
CEC machine for SoCal Edison– Delivery in Q3-2008– 13.8kV, 1200A, Prospective fault up to 22kA
DOE machine – provisional specification– Delivery in Q3-2008– 13.8kV, 4000A, Prospective fault up to 80kA
APPA, April 23, 2008, Indianapolis, IN
2008 Events
• National Electricity Delivery Forum, Feb 20-21www.electricitydeliveryforum.org
• American Public Power Association Engineering & Operations Conference, April 20-23
www.appanet.org• HTS Peer Review, July 29-31• Applied Superconductivity Conference, August 17-22 (Chicago, IL)• EPRI Superconductivity Conference, Fall • Coated Conductor for Applications Workshop, First week in December,
University of Houston
APPA, April 23, 2008, Indianapolis, IN
For more information… Office of Electricity Delivery and Energy Reliability’s Website
www.electricity.doe.gov
SuperPower, Inc Websitewww.superpower-inc.com