SR A1A North Causeway Bridge Over Intracoastal WaterwaySt Lucie County

Financial Project ID 429936-2-52-1Virtual Public Information Workshop

January 27, 2021

Welcome

www.SRA1ANorthBridge.com

< project logo and/or images >

2

Maurene Sotero BalmasedaModerator

Donovan Pessoa, PEFDOT Project Manager

About the Virtual Meeting Format

COVID-19 pandemic

GoTo Webinar online meeting platform

No cost to the public to log-in or dial-in to the meeting

3

Technical Information

4

Technical Information for Dial-in Attendees

Presenter will say slide #

being shown

Dial-in listeners

Paper copy of meeting presentation

(requested or downloaded prior to meeting)

Now showing slide #5

5

Technical Information (Listen Only mode)

All attendees will be placed in ‘Listen Only’

mode throughout the meeting.

Responses to comments and questions will be provided.

Type your comments or

questions in the control panel

Questions pane.

?

6

Technical Information (Technical Issues)

Type your issue in Questions pane

on the control panel.

?

This meeting is being recorded.

7

Public Notice

www.SRA1ANorthBridge.comEmails to project contacts listProperty owner/tenant letters

Social mediaFlorida Administrative Register

8

Title VI Non-discrimination Statement and Contacts

The Florida Department of Transportation is required to comply with various

non-discrimination laws andregulations, including Title VI of

the Civil Rights Act of 1964.

Public participation is solicited without regard to race, color,

national origin, age, sex, religion, disability, or family status.

Persons wishing to express concerns about Title VI may do so by contacting either:

Sharon SinghHagyan, District Four Title VI Coordinator3400 W. Commercial Blvd. Ft. Lauderdale, FL 33309, (954) 777-4190, [email protected] Free: (866) 336-8435, ext. 4190

Jacqueline Paramore, Statewide Title VI Coordinator605 Suwannee Street Tallahassee, FL 32399, (850) 414-4753, [email protected] Toll Free: 866-374-3368, ext. 4753www.fdot.gov/equalopportunity/titlevicontacts9

Public Comment

(954) 777-4442 or toll free at (866) 336-8435, ext. 4442

Type comments or questions in the

Questions pane on the control panel.

After meeting

?

During meeting

Florida Department of TransportationDistrict Four3400 W Commercial Blvd Ft. Lauderdale, FL 33309Attention: Donovan Pessoa, PE

[email protected]

www.SRA1ANorthBridge.com10

Public Comment (continued)

Responses to comments and

questions will be provided.

All registrants will receive a link to the meeting

recording.

All comments and questions are part of the

Public Record.

Please submit your comments by February 6, 2021

11

Meeting Purpose and Speakers

12

Henri Sinson, PE

Michael Sileno, PE

Project Location

SR A1A North Causeway Bridge

13

Project Background Existing 2100 ft bridge built in 1963 includes a double-leaf bascule span Bridge replacement is required due to: Structural deficiencies Functional obsolescence Vehicular traffic impacts along SR A1A due to frequency of bascule span openings

14

Project Site Plan

15

Zone 3 SR A1A Bridge Observation Deck

Zone 1 US 1 Improvements Old Dixie Hwy Improvements Juanita Ave Extension Sunny Lane Extension

Zone 2 Marina Access Rd East Coast Greenway Ramp Harbortown Dr Improvements

Zone 4 Park Access Road

Indian River Lagoon

North Causeway Island Park

Zone 1Old Dixie Highway & US-1

Shared Use Path

East Coast Greenway

Signalized Intersection

3-Way Stop Intersection

SUNNY LN

16

DrainagePond

St Lucie Inn

Shops

East Coast Packers

Shops

Marine Supply Store

Marine Supply Store

Begin Bridge

3-Way Stop Intersection

Zone 2Marina Access & East Coast Greenway

East CoastGreenway

Ramp

3-Way Stop Intersection

East CoastGreenway

Observation Deck Path

Observation Deck(Beneath Bridge)

17

HarbortownMarina

Day Boat Seafood

Offices

Offices

DrainagePond

ObservationDeck Parking

(Beneath Bridge)

Zone 2 & 3Marina Access, East Coast Greenway, and SR A1A Bridge

18

Observation Deck

Observation Deck Path

East CoastGreenway

Ramp

SR A1A Bridge

Indian River Lagoon

Zone 2 & 3Marina Access, East Coast Greenway, and SR A1A Bridge

19

Observation DeckEast CoastGreenwayRamp

SR A1A Bridge

Indian River Lagoon

New SR A1A Bridge length: 4152.5 ft

Observation Deck Length: 300 ft

East Coast Greenway Ramp Length: 800 ft

Zone 3SR A1A Bridge

20

Observation Deck

East CoastGreenwayRamp

New SR A1A Bridge

New SR A1A Bridge

Zone 3SR A1A Existing Typical Section

11 ft

37 ft - 9 inches

5 ftTraffic LaneSidewalk

Bicycle/Pedestrian/Traffic

Railing

21

4 ftShoulder

4 ft11 ftTraffic Lane Shoulder

Zone 3SR A1A New Bridge Typical Section

12 ft

64 ft - 3 inches

8 ft12 ft 12 ft 8 ft 8 ftTraffic LaneShoulder/Bike LaneEast Coast Greenway Traffic Lane Shoulder/Bike Lane Sidewalk

Traffic Railing

Bicycle/Pedestrian

Railing

22

New Channel Vertical Clearance: 85 ft

Existing 25 ft at center bridge closed, unlimited open

New Channel Horizontal Clearance: 125 ft

Existing 90 ft

Zone 3SR A1A Bridge Navigation Clearance

85 ft

125 ft

Navigation Clearances

85 ft

125 ft

25 ft

90 ft

85 ft

23

Zone 4Park Access

East Coast Greenway

Reconstruct Pedestrian Park Access

DrainagePond

24

North Causeway Island Park

End Bridge

Indian River Lagoon

Zones 1 & 2 – Construction Phase 1

Phase 1 Construction Extend Juanita Ave Extend Sunny Lane Improve US 1 Improve Old Dixie Hwy

Phase 1 Traffic Control Remains in existing Traffic Pattern 2 lanes of traffic on existing bridge

25

Indian River Lagoon

Zones 1 & 2 – Construction Phase 2

Phase 2 Construction Extend Sunny Lane Improve Old Dixie Hwy Construct Marina Access Road

Phase 2 Traffic Control Juanita Ave open to two lane traffic 2 lanes of traffic on existing bridge Sidewalk on the south side of SR A1A will be closed

26

Indian River Lagoon

Zones 1 & 2 – Construction Phase 3

Phase 3 Construction SR A1A bridge approach embankment and walls

Phase 3 Traffic Control Juanita Ave open to two lane traffic Sunny Ln open to westbound traffic SR A1A is closed from US 1 to Old Dixie Hwy Existing bridge accessed from Juanita Ave and Old Dixie Hwy 2 lanes of traffic on existing bridge Temporary pedestrian ramps will provide access from SR A1A to US 1

27

Indian River Lagoon

Construction Phase 1-4 – Zone 3 Phase 1-4 Construction Construct portions of new bridge next to existing bridge Existing bridge is demolished in Phase 4 after completion of new bridge

Phase 1-4 Traffic Control 2 lanes of traffic on existing bridge Phase 1-3 2 lanes of traffic on new bridge in Phase 4

28

Barge Mounted

Cranes

Foundation Piles

Bridge Beams

New SR A1A Bridge

Indian River Lagoon

IntracoastalWaterway

Construction Phase 2 – Zone 4

Phase 2 Construction Construct Park Access Rd

Phase 2 Traffic Control 2 lanes of traffic on existing SR A1A

29

ExtendJuanita Ave

Indian River Lagoon

Construction Phase 3 – Zone 4

Phase 3 Construction SR A1A bridge approach embankment and walls

Phase 3 Traffic Control Shift SR A1A traffic to Park Access Rd 2 lanes of traffic on existing bridge

30

ExtendJuanita Ave

Improve US 1

Indian River Lagoon

Previous Stakeholder EngagementStakeholder Date

PD&E Study Alternatives Public Meeting September 10, 2015

PD&E Study Public Hearing January 31, 2017

Project Kick‐Off Meeting February 2, 2015

Florida East Coast Railway May 24, 2018

Florida East Coast Railway July 18, 2018

Florida East Coast Railway October 10, 2018

St. Lucie County June 12, 2019

St. Lucie County February 4, 2020

St. Lucie County February 11, 2020

St Lucie Transportation Planning Organization April 1, 2020

United States Coast Guard April 2, 2020

United States Army Corps of Engineers April 2, 2020

South Florida Water Management District April 2, 2020

Fort Pierce Utilities Authority May 29, 2020

City of Fort Pierce July 28, 2020

Florida East Coast Railway July 30, 2020

City of Fort Pierce Commission August 8, 2020

Florida Power & Light August 25, 2020

AT&T August 25, 2020

31

Initial Plans (30% Complete)

March 2018

Biddability Submittal (90%

Complete)January 2021

Construction Complete

2026

Constructability Submittal (60%

Complete)May 2020

Plans CompleteJune 2021

Letting (Bid Opening)

October 2021

Construction Begins

January 2022

• Current Cost Estimate: $79 Million• Website: www.SRA1ANorthBridge.com

Project Schedule

32

After meeting, by February 6, 202115 more minutesThank You!

33

(954) 777-4442 or toll free at (866) 336-8435, ext. 4442

Type comments or questions in the

Questions pane on the control panel.

? Florida Department of TransportationDistrict Four3400 W Commercial Blvd Ft. Lauderdale, FL 33309Attention: Donovan Pessoa, PE

[email protected]

www.SRA1ANorthBridge.com