Sloan Corporate Finance Tutorial i308[2]
-
Upload
lindsey-joseph -
Category
Documents
-
view
216 -
download
0
Transcript of Sloan Corporate Finance Tutorial i308[2]
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
1/36
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
2/36
2
Todays Topic
NPVA Simple Case Study
Eagle Industry
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
3/36
3
NPV (Net Present Value)
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
4/36
4
NPV
NPV = Discounted Cash Flow (Inflow outflow)
In other words, it is the fundamental value of
an asset at current period. Note: NPV is not necessarily equal to marketvalue! (Market value is determined by supplyand demand in the market. If the market is
efficient, NPV is equal to market value.)
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
5/36
5
Investment Decision and NPV
What is the goal of a firm? Maximizingshareholders value
NPV = shareholders value
Therefore, Investment decisions should bebased on the NPV of the project.
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
6/36
6
NPV
NPV of cash on hand = amount of cash Ex) NPV of 100 on hand = 100
Suppose annual interest rate is rf= 10% Ex 1) NPV of 100 of next year?
Ans) 100/(1+rf) = 100/1.1 = 90.91 Ex 2) NPV of the following cash flow: 100(year 1), 100(year 2), 200(year 3) Ans) 100/1.1 + 100/1.12 + 200/1.13 = 323.82
In general, you have NPV formula such that
NPV = where Ct is cash flow at time t= +
N
t
t
t
r
C
0 )1(
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
7/36
7
NPV of Uncertain Cash Flow
Calculating NPV is that simple! But, what ifyou have uncertain cash flow?
Can we just use expected cash flow like the
following? NPV = where E(C) is expectation of C
The answer is no. Lets look at an example!
= +
N
t
t
t
r
CE
0 )1(
)(
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
8/36
8
Example: A Coin Tossing
Consider a gamble where you pay a certain amountnow, and receive money next year. Next year youwill toss a coin, and you will get 100 if it is head,0 if it is tail.
Expected cash flow (C) in the next year is E(C) =
0.5*100+0.5*0 = 50Suppose annual interest rate is rf= 7%
Are you willing to pay 50/(1+rf) = 50/1.07 = 47 forthis betting? Probably not!
Probably, you want to pay somewhat lower than 47.Suppose you want to pay P = 35 for the gamble.
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
9/36
9
Return on Coin Tossing
The expected return on this betting is E(r) = E(C)/P 1 = 50/35 1 = 43%
You want to ask for higher return than the interestrate because this is a risky choice. We call it riskpremium! E(r) = rf+ risk premium = 7% + 36%
In general, this is decided by the risk of an asset. ex) CAPM: E(r) = rf+ (rM rf)
Therefore, we can calculate NPV of uncertain cash
flow by using an appropriate discount factorconsidering the risk of investment. (We will coverthis later in the cost of capital part.)
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
10/36
10
A Simple Case Study
Ginos Trattoria Case
(Adapted from Brealey and Myers)
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
11/36
11
Sample Problem
Ginos Trattoria is considering a new project, which requires
an investment of 2 million. The project is expected togenerate sales revenue of 1 million in the first year, 2million in the second year and 3 million each for year 3, 4and 5. The cost of goods sold is expected to be 75 percentof sales revenue. Other costs are expected to be 7 percentof sales in the first year and 5 percent of sales thereafter.
The project will need working capital investment of 200,000 in the first year and an additional 100,000 in thesecond year. The investment in plant ( 2 million) will bedepreciated using 25% declining balance over 5 years. Ifthe companys opportunity cost of capital is 10 percent,calculate the NPV for the project. Assume that the plant willoperate for 5 years, and at the end of 5 years, the plant canbe sold for a salvage value of 600,000. The tax rate forthe company is 36 percent.
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
12/36
12
Approach for the Case
We need to calculate NPV to evaluate theproject
Remember NPV is discounted cash flows
Thus, all the information you will need is cashflowThe paragraph looks a bit too messy, and
very boring. Instead of trying to read it, we
can just pick up necessary information fromthe paragraph
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
13/36
13
Cash Flow ?
Cash Flow = Cash Flow from Operation + Cash Flow from Investment + Cash Flow from Financing
= Net Income + Changes in WC + Capital Expenditure
+ Raising and Paying Debt orEquity
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
14/36
14ash Flow
CF fromInvestmentCF fromOperation
CF fromFinancing
Investment
Salvage
Value
Tax on differencebetweensalvage value andending book value=
-
+Cost
Tax SavingsFrom
Depreciation
=
Sales-
Tax EffectofSales &Cost+-
Change inWorking Capital
+
We wont havethis part in our
simple example
Ginos TrattoriaCase
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
15/36
15
Necessary Information
All the information you will need will be thefollowing blocks from the case:
Investment SalvageValue
Tax on differencebetweensalvage value andending book value
Cost
Tax SavingsFrom
Depreciation
Sales
Tax EffectofSales &Cost
lso, you will need to know tax rate, discount rate,nd depreciation rule.
Change inWorkingCapital
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
16/36
16
Step 1. Find Necessary Information
1.1 Find Investment and salvage value Ginos Trattoria is considering a new project, which requires an investment of 2
million. Assume that the plant will operate for 5 years, and at the end of 6 years, the plant can
be sold for a salvage value of 600,000.
1.2 Find Revenue (or Sales)
The project is expected to generate sales revenue of 1 million in the first year, 2million in the second year and 3 million each for year 3, 4 and 5.
1.3 Find Cost The cost of goods sold is expected to be 75 percent of sales revenue. Other costs
are expected to be 7 percent of sales in the first year and 5 percent of sales thereafter.
YearsInvestmentYearsSales
Years 0 1 2 3 4 5 6COGS 750 1500 2250 2250 2250
Other Costs 70 100 150 150 150
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
17/36
17
Step 1. Find Necessary Information (2)
1.4 Find Working Capital
The project will need working capital investment of 200,000 in the first year and an additional$100,000 in the second year.
1.5 Find Depreciation Rule The investment in plant ( 2 million) will be depreciated using 25% declining balance over
schedule for the 5-year class.
1.6 Find Tax Rate The tax rate for the company is 36 percent.
1.7 Find Cost of Capital If the companys opportunity cost of capital is 10 percent, calculate the NPV for the project.
1.8 Duration of the project Assume that the plant will operate for 5 years, and at the end of 5 years, the plant can be sold
for a salvage value of 600,000.
YearsChange in Work
Capital
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
18/36
18
Step 2. Calculate Profit, Tax effect of Sales&Costs,Depreciation, and Tax Savings
2.1 Profit = Sale
Years
Sales2.2 Tax = tax rYears
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
19/36
19
Step 2. Calculate Profit, Tax effect of Sales&Costs,Depreciation, and Tax Savings (2)
2.4 Tax Saving
YearsDepreciation
Depreciation (25% Declining Rule) UK Tax Depreciationreciation in the first year = 25% of Value = .25 * 2000 = 500reciation after the second year = 75% of previous years depreciation = .75*500
2.5 Thus, we caYears
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
20/36
20
Step 3. Calculate Cash Flow
Total Cash Flo
Years
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
21/36
21
Step 4. Calculate NPV, IRR, Payback,and so on..
Using 10% cost of capital, we derive NPV = -220,962.07 IRR = 6.84%
Payback Period = 5 yearsThen, we can evaluate the project by given
criteria.
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
22/36
22
Graham & Harvey (2007)s Survey
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
23/36
23
NPV Criteria
Investment Decision using NPV: accept the project if NPV > 0
Strength
Consistent with the goal of shareholder valuemaximization
Weakness
Relies on cash flow forecasts, which tend to beinaccurate and biased upwards.
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
24/36
24
IRR Criteria
Investment Decision using IRR: accept the project if IRR > opportunity costs of capital
Strength
IRR gives the same answer as NPV if used properly More intuitive (summarized to one number)
Weakness
Multiple solutions Easily misleading: timing, scale, etc
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
25/36
25
Payback Period Criteria
Investment Decision using Payback: accept the project if it pays back its initial investment within the
cutoff period
Strength
Does not use distant cash flows which could be inaccurate ingeneral Make sure the initial investment is recovered within short term
Weakness
The payback rule ignores all cash flows after the cutoff date. The payback rule gives equal weight to all cash flows before thecutoff date. (It ignores the timing of cash flows within thepayback period)
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
26/36
26
Quiz!
The Campbell-Graham survey shows thatover half of their CFOs use payback period(in conjunction with NPV) to assess projects.
Why do they use payback period?Payback period has its own strengths which
NPV does not have although it is a bitoversimplified.
Thus, payback period could provide a bettercriteria together with NPV.
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
27/36
27
Best Criteria?
In an ideal world (where forecasting isunbiased and accurate), NPV is the bestrule as we have seen.
In reality, there is always the possibility of
having optimistic bias, and other biases inforecasting. Given that, using other criteria(payback) together with NPV will give youmore effective way of investment decision
making.
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
28/36
28
A Review on Eagle Industry
C Mi t k i E l I d t
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
29/36
29
Common Mistakes in Eagle IndustryCase
Tax savingsSunk Cost
Opportunity Cost
Minor mistakes
Tax Savings
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
30/36
30
Tax Savings(Straight-line Depreciation)
Building (25 years straight line depreciation) Initial value: 1000, salvage value: 0
After 5 years, the book value is still 800 although thesalvage value is 0. Therefore, the difference between theending book value and the salvage value could be usedfor tax savings.
Tax Savings in year 6: 30%*(800)=240
0 1 2 3 4 5 6
Book Value 1000 960 920 880 840 800
Depreciation 40 40 40 40 40 800
Tax Savings 12 12 12 12 12 240
Tax Savings
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
31/36
31
Tax Savings(25% declining balance)
Plant and machinery (25% declining balance) Initial value: 1200, salvage value: 100
After 5 years, the book value is still 285 although the salvagevalue is 100. Therefore, the difference between the endingbook value and the salvage value could be used for taxsavings.
Tax Savings in year 6: 30%*(285-100)=55
Book Value 1200 900 675 506 380 285
Depreciation 300 225 169 127 95 185
Tax Savings 90 68 51 38 28 55
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
32/36
32
Opportunity Cost
Opportunity Cost of Land should be included in theanalysisThe criteria whether its a positive NPV project will be
NPV > 0
In case you dont include the opportunity cost Option 1: Run the project (Opportunity cost is not included)
Option 2: Sell the land at 100,000
The criteria whether its a positive NPV project will be NPV > 100,000
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
33/36
33
Sunk Cost
Sunk cost shouldnt be included R&D cost (500,000) over the past two years is
a sunk cost, thus its not included in theanalysis
How to decide whether to include or notIf something can be affected by the decision to
accept or reject the project, it should beincluded.
Otherwise, it should be ignored.
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
34/36
34
Working Capital
Working Capital = Current Asset Current Liability = Inventory + Account Receivable Account Payable
Use change in working capital, not working capital
itself to calculate cash flowThere is no tax effect on change in working capitalWith reasonable assumptions, working capital should
be recovered after the projects duration
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
35/36
35
Minor Mistakes
Tax-free Grant In a development area, there is a tax free grant of 15%
on the value ofinvestment in buildings, plant, andmachinery. (only in the first year!)
15%*(1000+1200) = 330
There are launching costs of 200 and 100 in eachof the first two years respectively:
year 0 1 2 3 4 5
launching costs 200 100
-
8/6/2019 Sloan Corporate Finance Tutorial i308[2]
36/36
36
Next Time (Tentative)
Valuation with InflationSensitivity Analysis
Capital Structure
Fixed Income
You can download materials from
http://phd.london.edu/jhan.phd2005
http://phd.london.edu/jhan.phd2005http://phd.london.edu/jhan.phd2005