SIP Productization Status Update for TD 29th April

7
SIP PRODUCTIZATION - 2014

Transcript of SIP Productization Status Update for TD 29th April

Page 1: SIP Productization Status Update for TD 29th April

SIP PRODUCTIZATION - 2014

Page 2: SIP Productization Status Update for TD 29th April

BACKGROUND

• Challenges of SIP Stability, Capacity & Performance• Challenges of Operational Maintenance• Lacking standard Application Architecture

• Improve Capacity & Performance• Develop Operational Excellence• Attain Product Maturity• Standard Application Architecture

• Business Continuity• Time to Market• High Availability

BACKGROUND

GOALS

OUTCOME

Page 3: SIP Productization Status Update for TD 29th April

• Web Server Replication(Delivered)

• Web Server Replication(Delivered)

• DB rationalization(Delivered)

• DB rationalization(Delivered)

• Traffic Relieve SIP -> CBS• 20% traffic

• Reduced data entry • XML Removal

• Housekeeping• Transaction Tables (done)• Customer Profile (pending)

• Expire Revamp• phase I & II (done)• phase III (pending)

• Admin Consoles• Configuration• user management

• User Interface• Provisioning• Bulk Execution

Information Security Controls

Capacity &Performance

ArchitectureStandardizati

on

ProductMaturity

• Separate Application Layer

• Hardware Expansion (application servers)

• Standardized Mechanism for Parallel Processing (Jobs Alternate)

• Architecture Revamp

ProductizationPhase I-A (Q1)

ProductizationPhase I-B (Q2)

ProductizationPhase II (Q3)

• Admin Consoles• Configuration• user management

• User Interface• Provisioning• Bulk Execution

Information Security Controls

ProductizationPhase I-A (Q1)

ProductizationPhase I-B (Q2)

ProductizationPhase II (Q3)

Capacity & PerformanceCapacity &

Performance

Architecture Standardizati

on

Product Maturity

ArchitectureStandardizati

on

ProductMaturity

ProductizationPhase I-A (Q1)

Capacity & Performance

Architecture Standardizati

on

Product Maturity

• Separate Application Layer

• Hardware Expansion (application servers)

• Standardized Mechanism for Parallel Processing (Jobs Alternate)

• Architecture Revamp

ProductizationPhase I-B (Q2)

Capacity &Performance

ArchitectureStandardizati

on

ProductMaturityProduct MaturityProductMaturity

ProductizationPhase II (Q3)

• Traffic Relieve SIP -> CBS• 20% traffic

• Reduced data entry • XML Removal

• Housekeeping• Transaction Tables (done)• Customer Profile (pending)

• Expire Revamp• phase I & II (done)• phase III (pending)

Aspects

• Operational Excellence• Immediate relief in

system processes (80%~)• Daily Expiry time

reduced to 20 min from 4 hrs

Targeting

• 500 TPS• High Availability• Standardized

Architecture

Page 4: SIP Productization Status Update for TD 29th April

SIP Server

Existing Architecture

Data Base

Presentation

BusinessPresentation

Business

Persistence

Data

Target Architecture

ARCHITECTURE REVAMP

Page 5: SIP Productization Status Update for TD 29th April

Q1 Q2 Q3JAN FEB MAR APR MAY JUN JUL AUG SEP

Phase I-BApproval

DEVStartI-B

FunctionalDesign

I-B

ProcurementRequest I-B

I-B DEVComplete

TestingI-B

Phase I-ADelivered

Phase I-BGo-Live

Phase II DEV Start

Phase II DEVComplete

Phase I-AInitiated

Phase I-BProposal

Phase IIGo-Live

HardwareDelivery

I-B

Scopingof Phase II

PROJECT TIMELINES

• Freeze on SIP Release (Q2 & Q3)• Hardware Delivery Delay• Product Development Delay

• Critical business CRs will be delivered• Infrastructure will timely deliver• SED will ensure timelines

RISKS MITIGATION

Page 6: SIP Productization Status Update for TD 29th April

Impact on Business CRs/Projects for Q2

Objective Change Requests/Project Customer Centricity Notifications to Customers on degraded performance/Outage of SIP

Revenue My Status mutual exclusivity with IR feature in SIP

Further Analysis of Business Impact is in process as we are in requirement gathering phase