SHASTA COUNTY OFFICE OF EDUCATIONvisualcxcec.com/files/wa155/WA155-8-20180418010428.pdf · Digital...
Transcript of SHASTA COUNTY OFFICE OF EDUCATIONvisualcxcec.com/files/wa155/WA155-8-20180418010428.pdf · Digital...
CONSULTANT REPORT
SHASTA COUNTY OFFICE OF EDUCATION
Shasta COE
Early Childhood Services Oasis Campus Professional Development Center
Prepared for: California Energy Commission Prepared by: Digital Energy, Inc.
Cal i fornia Energy Commiss ion Apri l 17, 2018 Edmund G. Brown Jr . , Governor Contract Number: CEC ‐400‐14‐001 Work Author izat ion Number: 155
Performance Specification – Shasta COE
Prepared by:
Ethan Flyer Vishal Diddi, CEM, CPMP Primary Authors Digital Energy, Inc. 555 Marin St, Suite 230 Westlake Village, CA 91360 805-374-1777 Contract Number: 400-14-001 Work Authorization# 155 Prepared for: California Energy Commission Marites Antonio Contract Agreement Manager Judy Brewster Project Manager Elise Brown Office Manager Local Assistance and Financing Office Dave Ashuckian P. E. Deputy Director Efficiency Division Drew Bohan Executive Director
DISCLAIMER This report was prepared as the result of work sponsored by the California Energy Commission. It does not necessarily represent the views of the Energy Commission, its employees or the State of California. The Energy Commission, the State of California, its employees, contractors and subcontractors make no warrant, express or implied, and assume no legal liability for the information in this report; nor does any party represent that the uses of this information will not infringe upon privately owned rights. This report has not been approved or disapproved by the California Energy Commission nor has the California Energy Commission passed upon the accuracy or adequacy of the information in this report.
Performance Specification – Shasta COE Preface
i
PREFACE
This bid specification document was prepared as a follow up to the energy efficiency report
prepared for Shasta County Office of Education, under the Bright Schools Program. This
California Energy Commission program assists K through 12 schools in identifying measures
that can cut energy use and cost in existing and planned facilities, while concurrently enhancing
building performance. Once the measures are identified, the program can provide additional
assistance to help implement or finance the recommendations. This study was conducted for the
Commission by Digital Energy, Inc., under the direction of Jairam Agaram, P.E. The contract
assignment was directed and managed with the assistance of Judy Brewster, Project Manager
for the Commission. Digital Energy, Inc. and the Commission appreciate the assistance offered
by all Shasta County Office of Education personnel during the study.
School Name Location
Shasta COE 1644 Magnolia Avenue, Redding, CA 96001
Early Childhood Services 43 Hilltop Dr, Redding, CA 96003
Oasis Campus 3711 Oasis Rd, Redding, CA 96003
Professional Development Center 2985 Innsbruck Dr, Redding, CA 96003
Performance Specification – Shasta COE Table of Contents
ii
TABLE OF CONTENTS EXECUTIVE SUMMARY
DIVISION 2 EXISTING CONDITIONS
02 4100 DEMOLITION
02 8416 HANDLING OF BALLASTS AND LAMPS CONTAINING PCBs AND
MERCURY
DIVISION 11 EQUIPMENT
11 2000 COMMERCIAL EQUIPMENT – VENDING MISERS
DIVISION 23 HEATING VENTILATION AND AIR CONDITIONING
23 0000 GENERAL MECHANICAL REQUIREMENTS
23 0700 HVAC INSULATION
DIVISION 26 ELECTRICAL
26 0160 ELECTRICAL DEMOLITION
26 0923 LIGHTING CONTROL SYSTEMS
26 0943 PLUG LOAD CONTROL SYSTEMS
26 5119
26 5619
LED INTERIOR LIGHTING
EXTERIOR LIGHTING
APPENDIX A – RETROFIT SCHEDULE
Performance Specification – Shasta COE Executive Summary
3
EXECUTIVE SUMMARY
1. ECM L-1: Retrofit Linear Fluorescent Fixtures with New LED Bypass Lamps
This measure proposes to retrofit linear fluorescent fixtures with new 18‐watt LED bypass
lamps. This would trigger the Title 24 Code and would require installation of interior
occupancy sensors to control the retrofitted fixtures.
2. ECM L-3: Install Occupancy Sensors for Interior Lighting Control
Retrofitting interior fluorescent fixtures would trigger Title 24 Compliance. This measure entails
installation of occupancy sensors to control the fixtures retrofitted as a part of ECM L‐1.
3. ECM L-4: Install A-shape LED Lamps for Interior Spaces
This measure proposes re‐lamping interior screw‐in and/or pin‐based fixture lamps with new
lower wattage LED A‐shape lamps, or equivalent.
4. ECM L-5A: Install A-shape LED Lamps for Exterior Spaces
This measure proposes re‐lamping exterior screw‐in and/or pin‐based fixture lamps with new
lower wattage LED A‐shape lamps, or equivalent.
5. ECM L-5B: Install Photocells for Exterior Circuits and Fixtures
This measure entails installation of exterior photocell sensors to control the fixtures retrofitted
as a part of ECM L‐5A.
6. ECM L-6A: Replace Exterior HID Fixtures with New LED Fixtures
This measure proposes replacing exterior high‐intensity discharge fixtures with new lower
wattage LED fixtures.
7. ECM L-6B: Install Exterior Smart Controls for New Exterior LED Fixtures
Replacing exterior HID fixtures would trigger Title 24 Compliance. This measure entails
installation of exterior smart controls to control the fixtures replaced as a part of ECM L‐6A.
8. ECM M-5: Re-Insulate Refrigerant Lines for HVAC Systems
This measure proposes re‐insulating deteriorating insulation for refrigerant lines on split HVAC
systems.
Performance Specification – Shasta COE Executive Summary
4
9. ECM E-1: Provide Occupancy Sensor Controller for Vending Machine
This measure proposes use of occupancy sensor controllers to control the vending machines.
10. ECM E-2: Install Plug Load Occupancy Sensors for Copy Machines
This measure proposes installing plug load occupancy sensors and controlling power strip for
controlling copy machines. The devices activate the controlled receptacles only when the space
is occupied and de‐energize them when the space is vacant.
Performance Specification – Shasta COE Section 02 4100
5
SECTION 02 4100 DEMOLITION
PART 1 - GENERAL
1.1 SUMMARY A. Related Documents:
General provisions of the Subcontract apply to this Section.
Review these documents for coordination with additional requirements and
information that apply to work under this Section.
B. This section specifies demolition and removal of buildings, portions of buildings,
utilities, other structures and debris from trash dumps shown.
C. Related Sections:
Division 01 Section, General Requirements.
Division 01 Section, Safety Requirements Article, ACCIDENT PREVENTION
PLAN (APP).
Division 01 Section, Temporary Environmental Control.
Division 01 Section, Construction Waste Management.
Division 01 Section, Temporary Facilities and Controls.
Division 02 Section, Traditional Asbestos Abatement.
Division 02 Section, Lead based Paint Removal and Disposal.
Division 31 Section, Grading: Topsoil removal.
Division 31 Section, Fill: Fill material for filling holes, pits, and excavations
generated as a result of removal operations.
1.2 REFERENCES A. 29 CFR 1926 ‐ U.S. Occupational Safety and Health Standards (OSHA); current edition.
B. NFPA 241 ‐ Standard for Safeguarding Construction, Alteration, and Demolition
Operations; 2013.
1.3 SUBMITTALS A. Comply with Division 01 Section, Submittal Procedures.
B. Demolition Plan: The Contractor shall furnish a demolition plan (drawings) as
specified by OSHA and local authorities.
Indicate extent of demolition, removal sequence, bracing and shoring, and
location and construction of barricades and fences.
Identify demolition firm and submit qualifications.
Include a summary of safety procedures.
C. Project Record Documents: Accurately record actual locations of capped and active
utilities and subsurface construction.
Performance Specification – Shasta COE Section 02 4100
6
1.4 PROTECTION A. Perform demolition in such manner as to eliminate hazards to persons and property; to
minimize interference with use of adjacent areas, utilities and structures or
interruption of use of such utilities; and to provide free passage to and from such
adjacent areas of structures. Comply with requirements of General Conditions Article,
Accident Prevention.
B. Provide safeguards, including warning signs, barricades, temporary fences, warning
lights, and other similar items that are required for protection of all personnel during
demolition and removal operations. Comply with requirements of Division 01
Sections, General Requirements, Article Protection of Existing Vegetation, Structures,
Equipment, Utilities and Improvements.
C. Maintain fences, barricades, lights, and other similar items around exposed
excavations until such excavations have been completely filled.
D. Provide enclosed dust chutes with control gates from each floor to carry debris to truck
beds and govern flow of material into truck. Provide overhead bridges of tight board
or prefabricated metal construction at dust chutes to protect persons and property
from falling debris.
E. Prevent spread of flying particles and dust. Sprinkle rubbish and debris with water to
keep dust to a minimum. Do not use water if it results in hazardous or objectionable
condition such as, but not limited to; ice, flooding, or pollution. Vacuum and dust the
work area daily.
F. In addition to previously listed fire and safety rules to be observed in performance of
work, include following:
No wall or part of wall shall be permitted to fall outwardly from structures.
Wherever a cutting torch or other equipment that might cause a fire is used,
provide and maintain fire extinguishers nearby ready for immediate use. Insure
all possible users know how to properly use fire extinguishers.
Keep hydrants clear and accessible at all times. Prohibit debris from
accumulating within a radius of 4500 mm (15 ft.) of fire hydrants.
G. Before beginning any demolition work, the Contractor shall survey the site and
examine the demolition drawings (if available) and specifications to determine the
extent of the work. The contractor shall take necessary precautions to avoid damages to
existing items to remain in place or to be reused; any damaged items shall be repaired
or replaced as approved by the Resident Engineer. The Contractor shall coordinate the
work of this section with all other work and shall construct and maintain shoring,
bracing, and supports as required. The Contractor shall ensure that structural elements
are not overloaded and shall be responsible for increasing structural supports or
adding new supports as may be required as a result of any cutting, removal, or
demolition work performed under this contract. Do not overload structural elements.
Provide new supports and reinforcement for existing construction weakened by
demolition or removal works. Repairs, reinforcement, or structural replacement must
have Resident Engineer’s approval.
Performance Specification – Shasta COE Section 02 4100
7
H. The work shall comply with the requirements of Division 01 Section, Temporary
Facilities and Controls.
I. The work shall comply with the requirements of Division 01 Section, General
Requirements, Article 1.7 Infection Prevention Measures.
PART 2 - PRODUCTS – Not Applicable
PART 3 - EXECUTION
3.1 SCOPE A. Remove other items indicated for salvage, relocation, and recycling.
B. Fill excavations, open pits, and holes in ground areas generated as result of removals,
using specified fill.
3.2 GENERAL PROCEDURES AND PROJECT CONDITIONS A. Comply with other requirements specified in Division 01.
B. Comply with applicable codes and regulations for demolition operations and safety of
adjacent structures and the public.
Obtain required permits.
Comply with applicable requirements of NFPA 24 ‐ Standard for Safeguarding
Construction.
Take precautions to prevent catastrophic or uncontrolled collapse of structures to
be removed; do not allow worker or public access within range of potential
collapse of unstable structures.
Provide, erect, and maintain temporary barriers and security devices.
Use physical barriers to prevent access to areas that could be hazardous to
workers or the public.
Conduct operations to minimize effects on and interference with adjacent
structures and occupants.
Do not close or obstruct roadways or sidewalks without permit.
Conduct operations to minimize obstruction of public and private entrances and
exits; do not obstruct required exits at any time; protect persons using entrances
and exits from removal operations.
Obtain written permission from owners of adjacent properties when demolition
equipment will traverse, infringe upon or limit access to their property.
C. Do not begin removal until receipt of notification to proceed from Owner.
D. Protect existing structures and other elements that are not to be removed.
Provide bracing and shoring.
Prevent movement or settlement of adjacent structures.
Stop work immediately if adjacent structures appear to be in danger.
Performance Specification – Shasta COE Section 02 4100
8
E. Minimize production of dust due to demolition operations; do not use water if that will
result in ice, flooding, sedimentation of public waterways or storm sewers, or other
pollution.
F. If hazardous materials are discovered during removal operations, stop work and notify
Architect and Owner; hazardous materials include regulated asbestos containing
materials, lead, PCBʹs, and mercury.
G. Perform demolition in a manner that maximizes salvage and recycling of materials.
Comply with requirements of Division 01 Section, Waste Management.
Dismantle existing construction and separate materials.
Set aside reusable, recyclable, and salvageable materials; store and deliver to
collection point or point of reuse.
3.3 EXISTING UTILITIES A. Coordinate work with utility companies; notify before starting work and comply with
their requirements; obtain required permits.
B. Protect existing utilities from being damaged.
C. Do not disrupt public utilities without permit from authority having jurisdiction.
D. Do not close, shut off, or disrupt existing life safety systems that are in use without at
least 7 days prior written notification to Owner.
E. Do not close, shut off, or disrupt existing utility branches or take‐offs that are in use
without at least 3 days prior written notification to Owner.
F. Locate and mark utilities to remain; mark using highly visible tags or flags, with
identification of utility type; protect from damage due to subsequent construction,
using substantial barricades if necessary.
G. Remove exposed piping, valves, meters, equipment, supports, and foundations of
disconnected and abandoned utilities.
3.4 SELECTIVE DEMOLITION FOR ALTERATIONS A. Existing drawings (plans) showing existing construction and utilities are based on
casual field observation and existing record documents only.
Verify that construction and utility arrangements are as shown.
Report discrepancies to Architect before disturbing existing installation.
Beginning of demolition work constitutes acceptance of existing conditions that
would be apparent upon examination prior to starting demolition.
B. Separate areas in which demolition is being conducted from other areas that are still
occupied.
Provide, erect, and maintain temporary dustproof partitions of construction
specified in Division 01 Section, Temporary Facilities and Controls, in locations
indicated on demolition drawings.
C. Maintain weatherproof exterior building enclosure except for interruptions required
for replacement or modifications; take care to prevent water and humidity damage.
Performance Specification – Shasta COE Section 02 4100
9
D. Remove existing work as indicated and as required to accomplish new work.
E. Services (Including but not limited to HVAC, Plumbing, Fire Protection, Electrical, and
Telecommunications):
Remove existing systems and equipment as indicated.
Maintain existing active systems that are to remain in operation; maintain access
to equipment and operational components.
Where existing active systems serve occupied facilities, but are to be replaced
with new services, maintain existing systems in service until new systems are
complete and ready for service.
Verify that abandoned services serve only abandoned facilities before removal.
Remove abandoned pipe, ducts, conduits, and equipment, including those above
accessible ceilings; remove back to source of supply where possible, otherwise
cap stub and tag with identification.
F. Protect existing work to remain.
Prevent movement of structure; provide shoring and bracing if necessary.
Perform cutting to accomplish removals neatly and as specified for cutting new
work.
Repair adjacent construction and finishes damaged during removal work.
Patch as specified for patching new work.
G. No services or equipment are to be abandoned in place. All decommissioned elements
are to be removed.
3.5 DEBRIS AND WASTE REMOVAL A. Remove debris, junk, and trash from site.
B. Remove from site all materials not to be reused on site; comply with requirements of
Division 01 Section, Waste Management.
C. Leave site in clean condition, ready for subsequent work.
D. Clean up spillage and wind‐blown debris from public and private lands.
END OF SECTION 02 4100
Performance Specification – Shasta COE Section 02 8416
10
SECTION 02 8416 HANDLING OF LIGHTING BALLASTS AND LAMPS
CONTAINING PCBS AND MERCURY
PART 1 - GENERAL
1.1 SUMMARY A. Section includes:
1. Furnish labor, materials, services, and equipment necessary for the removal of
Polychlorinated Biphenyl (PCB) containing lighting ballasts, associated mercury
containing fluorescent lamps, and High Intensity Discharge (HID) lamps in
accordance with local, state, or federal regulations. Do not expose PCBs to open
flames or other high temperature sources since toxic decomposition by‐products
may be produced. Do not break mercury containing fluorescent lamps or HID
lamps.
1.2 REFERENCES A. Environmental Protection Agency (EPA) Regulations:
1. 40 CFR 260‐40 CFR 265 ‐ Various Hazardous Waste Standards.
2. 40 CFR 268 ‐ Land Disposal Restrictions.
3. 40 CFR 270 ‐ EPA Administered Permit Programs: The Hazardous Waste Permit
Program.
4. 40 CFR 273 ‐ Standards for Universal Waste Management.
5. 40 CFR 761 ‐ Polychlorinated Biphenyls (PCBs) Manufacturing, Processing,
Distribution in Commerce, and Use Prohibitions.
B. U.S. Department of Labor, Occupational Safety and Health Administration (OSHA)
Regulation:
1. 29 CFR 1910.1000 ‐ Air Contaminants.
C. Department of Transportation (DOT):
1. 49 CFR 178 ‐ Regulations for Shipping Container Specifications.
1.3 DESCRIPTION OF WORK A. Removal and disposal of PCB containing lighting ballasts and associated mercury
containing lamps. Contractor may encounter leaking PCB ballasts.
Performance Specification – Shasta COE Section 02 8416
11
1.4 DEFINITIONS A. Certified Industrial Hygienist (CIH) – An industrial hygienist hired by the contractor shall
be certified by the American Board of Industrial Hygiene.
B. Leak – Leak or leaking means any instance in which a PCB article, PCB container, or PCB
equipment has any PCBs on any portion of its external surface.
C. Lamps – Lamp, also referred to as ʺuniversal waste lamp,ʺ is defined as the bulb or tube
portion of an electric lighting device. A lamp is specifically designed to produce radiant
energy, most often in the ultraviolet, visible, and infra‐red regions of the electromagnetic
spectrum. Examples of common universal waste electric lamps include, but are not limited
to, fluorescent, high intensity discharge, neon, mercury vapor, high pressure sodium, and
metal halide lamps.
D. Polychlorinated Biphenyls (PCBs) – PCBs as used in this specification shall mean the same
as PCBs, PCB containing lighting ballast, and PCB container, as defined in 40 CFR 761,
Section 3, Definitions.
E. Spill – Spill means both intentional and unintentional spills, leaks, and other uncontrolled
discharges when the release results in any quantity of PCBs running off or about to run off
the external surface of the equipment or other PCB source, as well as the contamination
resulting from those releases.
F. Universal Waste – Universal Waste means any of the following hazardous wastes that are
managed under the universal waste requirements 40 CFR 273:
1. Batteries
2. Pesticides
3. Thermostats
4. Lamps
1.5 QUALITY ASSURANCE A. Regulatory Requirements: Perform PCB related work in accordance with 40 CFR 761.
Perform mercury containing lamps storage and transport in accordance with 40 CFR 261,
40 CFR 264, 40 CFR 265, and 40 CFR 273.
B. Training: Certified Industrial Hygienist (CIH) shall instruct and certify the training of all
persons involved in the removal of PCB containing lighting ballasts and mercury
containing lamps. The instruction shall include: The dangers of PCB and mercury
exposure, decontamination, safe work practices, and applicable OSHA and EPA
regulations. The CIH shall review and approve the PCB and Mercury Containing Lamp
Removal Work Plans.
C. Regulation Documents: Maintain, at all times, one copy each at the office and one copy
each in view at the job site of 29 CFR 1910.1000, 40 CFR 260, 40 CFR 261, 40 CFR 262, 40
CFR 263, 40 CFR 265, 40 CFR 268, 40 CFR 270, and 40 CFR 273 and of the Contractor
removal work plan and disposal plan for PCB and for associated mercury containing
lamps.
Performance Specification – Shasta COE Section 02 8416
12
1.6 SUBMITTALS A. Submit in accordance with Division 01 Section, Submittal Procedures. Final payments will
not be made until all copies of all submittals have been furnished to the Officer‐in‐Charge.
B. Certificates:
1. Qualifications of CIH: Submit the name, address, and telephone number of the
Industrial Hygienist selected to perform the duties in paragraph entitled ʺCertified
Industrial Hygienist.ʺ
2. Training Certification: Submit training certification that the Industrial Hygienist is
certified, including certification number and date of certification or re certification.
3. PCB and Lamp Removal Work Plan: Submit a job specific plan within 20 calendar
days after award of contract of the work procedures to be used in the removal,
packaging, and storage of PCB containing lighting ballasts and associated mercury
containing lamps. Include in the plan: Requirements for Personal Protective
Equipment (PPE), spill cleanup procedures and equipment, eating, smoking, and
restroom procedures. The plan shall be approved and signed by the Certified
Industrial Hygienist. Obtain approval of the plan by the Officer‐in‐Charge prior to
the start of PCB and/or lamp removal work.
4. PCB and Lamp Disposal Plan: Submit a PCB and Lamp Disposal Plan within 45
calendar days after award of contract. The PCB and Lamp Disposal Plan shall
comply with applicable requirements of federal, state, and local PCB and Universal
waste regulations and address:
a. Estimated quantities of wastes to be generated, disposed of, and recycled.
b. Names and qualifications of each Contractor that will be transporting, storing,
treating, and disposing of the wastes. Include the facility location. Furnish two
copies of EPA and state PCB and mercury containing lamp waste permit
applications and EPA identification numbers, as required.
c. Names and qualifications (experience and training) of personnel who will be
working on‐site with PCB and mercury containing lamp wastes.
d. Spill prevention, containment, and cleanup contingency measures to be
implemented.
e. Work plan and schedule for PCB and mercury containing lamp waste removal,
containment, storage, transportation, disposal and/or recycling. Wastes shall
be cleaned up and containerized daily.
C. Closeout Submittals:
1. Transporter certification of notification to EPA of their PCB waste activities and EPA
ID numbers.
2. Certification of Decontamination.
3. Certificate of Disposal and/or recycling. Submit to the State before application for
payment within 30 days of the date that the disposal of the PCB and mercury
containing lamp waste identified on the manifest was completed.
PART 2 - PRODUCTS – Not Applicable
Performance Specification – Shasta COE Section 02 8416
13
PART 3 - EXECUTION
3.1 WORK OPERATIONS A. Ensure that work operations or processes involving PCB or PCB contaminated materials
are conducted in accordance with 40 CFR 761, 40 CFR 262, 40 CFR 263, and the applicable
requirements of this section, including but not limited to:
1. Obtaining suitable PCB and mercury containing lamp storage sites.
2. Notifying Officer‐in‐Charge prior to commencing the operation.
3. Reporting leaks and spills to the Officer‐in‐Charge.
4. Cleaning up spills.
5. Inspecting PCB and PCB contaminated items and waste containers for leaks and
forwarding copies of inspection reports to the Officer‐in‐Charge.
6. Maintaining inspection, inventory and spill records.
3.2 PCB SPILL CLEANUP REQUIREMENTS A. PCB Spills: Immediately report to the Officer‐in‐Charge any PCB spills.
B. PCB Spill Control Area: Rope off an area around the edges of a PCB leak or spill and post a
ʺPCB Spill Authorized Personnel Onlyʺ caution sign. Immediately transfer leaking items to
a drip pan or other container.
C. PCB Spill Cleanup: 40 CFR 761, subpart G. Initiate cleanup of spills as soon as possible, but
no later than 24 hours of its discovery. Mop up the liquid with rags or other conventional
absorbent. The spent absorbent shall be properly contained and disposed of as solid PCB
waste.
D. Records and Certification: Document the cleanup with records of decontamination in
accordance with 40 CFR 761, Section 125, Requirements for PCB Spill Cleanup. Provide
test results of cleanup and certification of decontamination.
3.3 REMOVAL A. Ballasts: As ballasts are removed from the lighting fixture, inspect label on ballast. Ballasts
without a ʺNo PCBʺ label shall be assumed to contain PCBs and containerized and
disposed of as required under paragraphs STORAGE FOR DISPOSAL and DISPOSAL. If
there are less than 1600 ʺNo PCBʺ labeled lighting ballasts, dispose of them as normal
demolition debris.
B. Lighting Lamps: Remove lighting tubes/lamps from the lighting fixture and carefully place
(unbroken) into appropriate containers (original transport boxes or equivalent). In the
event of a lighting tube/lamp breaking, sweep and place waste in double plastic taped
bags and dispose of as universal waste as specified herein.
Performance Specification – Shasta COE Section 02 8416
14
3.4 STORAGE FOR DISPOSALL A. Storage Containers for PCBs: 49 CFR 178. Store PCB in containers approved by DOT for
PCB.
B. Storage Containers for lamps: Store mercury containing lamps in appropriate DOT
containers. The boxes shall be stored and labeled for transport in accordance with 40 CFR
273.
C. Labeling of Waste Containers – Label with the following:
1. Date the item was placed in storage and the name of the cognizant activity/building.
2. ʺCaution Contains PCB,ʺ conforming to 40 CFR 761, CFR Subpart C. Affix labels to
PCB waste containers.
3. Label mercury containing lamp waste in accordance with 40 CFR 273. Affix labels to
all lighting waste containers.
3.5 DISPOSAL A. Identification Number: Federal regulations 40 CFR 761, and 40 CFR 263 require that
generators, transporters, commercial storage, and disposers of PCB waste possess U.S.
EPA identification numbers. The contractor shall verify that the activity has a U.S. EPA
generator identification number for use on the Uniform Hazardous Waste manifest. If not,
the contractor shall advise the activity that it must file and obtain an I.D. number with EPA
prior to commencement of removal work. For mercury containing lamp removal, Federal
regulations 40 CFR 273 require that large quantity handlers of Universal waste (LQHUW)
must provide notification of universal waste management to the appropriate EPA Region
(or state director in authorized states), obtain an EPA identification number, and retain
records for three years of off‐site shipments of universal waste.
B. Transporter Certification: Comply with disposal and transportation requirements outlined
in 40 CFR 761 and 40 CFR 263. Before transporting the PCB waste, sign and date the
manifest acknowledging acceptance of the PCB waste from the City. Return a signed copy
to the City before leaving the job site. Ensure that the manifest accompanies the PCB waste
at all times. Submit transporter certification of notification to EPA of their PCB waste
activities (EPA Form 7710‐53).
C. Certificate of Disposal and/or Recycling: 40 CFR 761. Certificate for the PCBs and PCB
items disposed shall include:
1. The identity of the disposal and/or recycling facility; by name, address, and EPA
identification number.
2. The identity of the PCB waste affected by the Certificate of Disposal including
reference to the manifest number for the shipment.
3. A statement certifying the fact of disposal and/or recycling of the identified PCB
waste, including the date(s) of disposal, and identifying the disposal process used.
4. A certification as defined in 40 CFR 761.
END OF SECTION 02 8416
Performance Specification – Shasta COE Section 11 2000
15
SECTION 11 2000 COMMERCIAL EQUIPMENT – VENDING MISERS
PART 1 - GENERAL
1.1 SUMMARY A. Related Documents:
1. General provisions of the Subcontract apply to this Section.
2. Review these documents for coordination with additional requirements and
information that apply to work under this Section.
B. Section Includes:
1. Vending Machine Occupancy Sensors.
C. Related Sections:
1. Division 01 Section, General Requirements.
2. Division 01 Section, Special Procedures.
3. Division 26 Section, Electrical service and distribution.
1.2 REFERENCES A. General:
1. The following documents form part of the Specifications to the extent stated. Where
differences exist between codes and standards, the one affording the greatest
protection shall apply.
2. Unless otherwise noted, the referenced standard edition is the current one at the
time of commencement of the Work.
3. Refer to Division 01 Section, General Requirements for the list of applicable
regulatory requirements.
4. Refer to Division 23 Section, Common Results for HVAC for codes and standards,
and other general requirements.
B. American National Standards Institute (ANSI):
1. ANSI/NFPA 101 – Life Safety Code.
2. ANSI/NFPA 70 – National Electrical Code.
C. Underwriters Laboratories, Inc. (UL).
D. National Electrical Manufacturers Association (NEMA) Publications.
E. California Title 24, Non‐Residential: Section 120 (Mechanical).
1.3 SUBMITTALS A. Provide complete system drawings, wiring diagrams, and written detailed operational
description of sequences, and description and engineering data on each control system
component. Include sizing as requested.
Performance Specification – Shasta COE Section 11 2000
16
B. Samples: Submit samples for finish, color, and texture.
C. Submit manufacturerʹs installation instructions.
D. Submit warranty documentation.
1.4 QUALITY ASSURANCE A. Electrical components, devices, and accessories will be listed and labeled as defined in
NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and
marked for intended use.
1.5 WARRANTY A. Warranty Period: Five years from date of purchase.
PART 2 - PRODUCTS
2.1 MANUFACTURERS A. Occupancy Sensors
1. EnergyMiser – VendingMiser VM150, or equivalent.
B. Substitutions: Under provisions of Division 01 Section, General Requirements
2.2 SYSTEM REQUIREMENTS A. Provide control systems consisting of occupancy sensors to operate vending machines and
to perform functions specified.
B. Provide materials and field work necessary to connect control components factory‐
supplied as part of equipment controlled, unless specified otherwise.
C. Unless specified otherwise, provide fully proportional components.
2.3 OCCUPANCY SENSORS A. Shall use Passive Infrared (PIR) motion detection.
B. Shall use PIR to initially detect motion and turn on vending machine units. PIR shall be
used to keep vending machine units on while occupied.
C. Manual timer settings shall be available up to 15 min.
PART 3 - EXECUTION
3.1 INSTALLATION A. Check and verify location of vending machines with plans and room details before
installation. Locate EnergyMisers on wall or on machine.
B. Occupancy Sensor Locations: Sensor locations indicated are diagrammatic. Within the
design intent, reasonably minor adjustments to locations may be made in order to
optimize coverage and avoid conflicts or problems affecting coverage, in accordance with
manufacturerʹs recommendations.
C. Contractor is responsible for coordinating, delivery, proper storage (if necessary),
installation, startup and first year of labor warranty. Installation includes replacement of
missing and/or damaged materials and final connections to vending machine units.
3.2 FIELD QUALITY CONTROL
Performance Specification – Shasta COE Section 11 2000
17
A. Perform the following field tests and inspections:
1. Operational Test: After electrical circuitry has been energized, start units to confirm
proper unit operation.
2. Test and adjust controls and safeties.
3. Test each control loop to verify stable mode of operation and compliance with
sequence of operations.
3.3 DEMONSTATION A. Engage a factory authorized service representative to train Ownerʹs maintenance
personnel or Owner’s authorized maintenance company to adjust, operate, and maintain
vending machine instrumentation and controls.
PART 4 - MATERIAL SCHEDULE
4.1 OCCUPANCY SENSORS FOR VENDING MACHINE CONTROL A. EnergyMiser – VendingMiser VM150, or equivalent.
1. Includes PIR occupancy sensor and indoor wall mount
a. For use in locations where vending machine placements are not subject to
change
b. Separate sensor assembly provides flexibility in placement to achieve best
occupancy detection
2. External EnergyMisers use a controller and machine mounted sensor to monitor
room occupancy and temperature
a. If 15 minutes pass without pedestrian traffic, the EnergyMiser will power
down the machine
b. The machine is powered back up when people return and at regular intervals
to keep products cold.
3. Specifications:
a. Input voltage: 115V
b. Input frequency 50/60 Hz
c. Maximum load: 12A (steady‐state)
d. Power consumption: less than 1W (standby)
e. Occupancy timeout: 15 minutes
f. Auto re‐power: 90 minutes maximum. Dynamically adjusted, based on
ambient temperature
g. Dimensions: 4.5ʺW x 1.75ʺH x 3.25ʺD
h. Weight: 2.2 lb
END OF SECTION – 11 2000
Performance Specification – Shasta COE Section 23 0000
18
SECTION 23 0000 GENERAL MECHANICAL REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY A. General provisions of the Subcontract apply to this Section.
B. Review these documents for coordination with additional requirements and
information that apply to work under this Section.
1.2 SCOPE A. Basic mechanical requirements specifically applicable to Division 23 Sections.
B. Work includes but is not necessarily limited to the following:
Labor, materials, services, equipment, and appliances required for completion of
tasks as indicated in specification or as inherently necessary to prepare spaces
and systems for new installations as follows:
a. Heating, ventilating, and air conditioning systems and equipment
b. Testing, adjusting, and balancing
1.3 DRAWINGS AND SPECIFICATIONS A. The Contractor shall furnish mechanical plans/drawings showing the scope of the
project.
B. Drawings accompanying these Specifications show intent of Work to be done.
Specifications shall identify quality and grade of installation and where equipment and
hardware is not particularly specified, Contractor shall provide submittals for all
products and install them per manufacturers’ recommendations, and in a first‐class
manner.
C. Examine specifications for elements in connection with this Work; determine existing
and new general construction conditions and be familiar with all limitations caused by
such conditions.
D. Plans are intended to show general arrangement and extent of Work contemplated.
Exact location and arrangement of parts shall be determined after the Owner has
reviewed equipment, as Work progresses, to conform in best possible manner with
surroundings, and as directed by the Owner.
E. Follow dimensions without regard to scale. Where no figures or notations are given,
the Plans shall be followed.
1.4 UTILITIES A. Location and sizes of electrical, mechanical, and plumbing service facilities are shown
in accordance with data secured from existing record drawings and site observations.
Data shown are offered as an estimating guide without guarantee of accuracy. Check
Performance Specification – Shasta COE Section 23 0000
19
and verify all data given, and verify exact location of all utility services pertaining to
Work prior to excavation or performing Work.
1.5 APPLICABLE REFERENCE STANDARDS, CODES, AND REGULATIONS A. Meet requirements of all state codes having jurisdiction.
B. State of California Code of Regulations:
Title 8, Industrial Relations
Title 19, State Fire Marshal Regulations
2016 California Building Code, Title 24, Part 2
2016 California Electrical Code, Title 24, Part 3
2016 California Mechanical Code, Title 24, Part 4
2016 California Plumbing Code, Title 24, Part 5
2016 California Fire Code, Title 24, Part 9
2016 California Standards Code, Title 24, Part 12
2016 California Title 24, Energy Conservation Standards
C. Additional Reference Standards:
AABC – Associated Air Balance Council
AMCA – Air Moving and Conditioning Association
AHRI – Air Conditioning, Heating and Refrigeration Institute
ASHRAE – American Society of Heating, Refrigeration and Air Conditioning
Engineers
ASME – American Society of Mechanical Engineers
ASTM – American Society of Testing Materials
NEMA – National Electrical Manufacturer’s Association
NFPA – National Fire Protection Association Standards
PDA – Plumbing and Drainage Institute
UL – Underwriters Laboratories
D. Codes and ordinances having jurisdiction over Work are minimum requirements; but,
if Contract Documents indicate requirements, which are in excess of those minimum
requirements, then requirements of the Contract Documents shall be followed. Should
there be any conflicts between Contract Documents or codes or any ordinances having
jurisdiction, report these to the Owner.
E. Obtain permits and request inspections from authority having jurisdiction.
1.6 PROJECT AND SITE CONDITIONS A. The arrangement of, and connection to, equipment shown on the Drawings is based
upon information available and is not intended to show exact dimensions peculiar to a
specific manufacturer. The Mechanical Drawings are, in part, diagrammatic and some
features of the illustrated equipment installations may require revision to meet actual
equipment installation requirements. Structural supports, housekeeping pads, piping
connections, and adjacent equipment may have to be altered to accommodate the
Performance Specification – Shasta COE Section 23 0000
20
equipment provided. No additional payment will be made for such revisions or
alterations.
B. Examine all specifications to be fully cognizant of all work required under this
Division.
C. Examine site related work and surfaces before starting work of any Section.
D. Prepare revised shop drawings showing proposed rearrangement of Work to meet
Project conditions, including changes to Work specified in other Sections. Obtain
permission from the Owner before proceeding.
E. Beginning work of any Section constitutes acceptance of conditions.
1.7 COOPERATION WITH WORK UNDER OTHER DIVISIONS A. Cooperate with other trades to facilitate general progress of Work. Allow all other
trades every reasonable opportunity for installation of their work.
B. Work under this Division shall follow general building construction closely. Set pipe
sleeves and inserts and verify that openings for chases and pipes are provided.
C. Work with other trades in determining exact location of outlets, pipes, and pieces of
equipment to avoid interference with lines required to maintain proper installation of
Work.
D. Make such progress in the Work to not delay work of other trades.
E. Mechanical Work shall have precedence over the other in the following sequence:
Soil and waste piping
Hydronic piping
Ductwork
Fire sprinkler piping
Domestic water piping
1.8 DISCREPANCIES A. The Contractor shall check conduct the site visit and shall promptly notify the Owner
of any discrepancies.
B. Where requirements between Drawings (if available) and Specifications conflict, the
more restrictive provisions shall apply. Also, see Contract General Conditions.
C. If any part of the Specifications or Drawings (if available) appears unclear or
contradictory, apply to Owner for interpretation and decision as early as possible,
including during bidding period. Beginning work of any Section constitutes acceptance
of conditions.
1.9 CHANGES A. The Contractor shall be responsible to make and obtain approval from the Owner for
all necessary adjustments in piping and equipment layouts as required to
accommodate the relocations of equipment and/or devices, which are affected by any
approved authorized changes or Product substitutions. All changes shall be clearly
indicated on the ʺRecordʺ drawings.
1.10 SUBMITTALS
Performance Specification – Shasta COE Section 23 0000
21
A. Refer to Division 01 for additional requirements.
B. The manufacturer, contractor, or supplier shall include a written statement that the
submitted equipment, hardware, or accessory complies with the requirement of that
particular specification section.
The manufacturer shall resubmit the specification section showing compliance
with each respective paragraph and specified items and features in that
particular specification section.
All exceptions shall be clearly identified by referencing respective paragraph and
other requirements along with proposed alternative.
C. Note that prior to acceptance of shop drawings for review, a submittal schedule shall
be submitted to the Owner.
D. Submit all Division 23 shop drawings and product data grouped and referenced by the
specification technical section numbers in one complete submittal package.
E. Shop Drawings:
Provide all shop drawings in latest version of AutoCAD format. FTP upload is
acceptable.
Drawings shall be a minimum of 8.5 inches by 11 inches in size with a minimum
scale of ¼ inch per foot, except as specified otherwise.
Include installation details of equipment indicating proposed location, layout
and arrangement, accessories, piping, and other items that must be shown to
assure a coordinated installation.
Indicate adequate clearance for operation, maintenance, and replacement of
operating equipment devices.
If equipment is disapproved, revise drawings to show acceptable equipment and
resubmit.
F. Whenever more than one manufacturer’s product is specified, the first named product
is the basis of design used in the Work and the use of alternate named manufacturer’s
products or substitutes may require modifications in that design.
G. Proposed Products List: Include Products as required by the individual section in this
Division.
H. The Contractor shall be responsible for all equipment ordered and/or installed prior to
receipt of shop drawings returned from the Owner bearing a stamp of ʺReviewed.ʺ All
corrections or modifications to the equipment as noted on the shop drawings shall be
performed and equipment be removed from the job site at the request of the Owner
without additional compensation.
I. Manufacturerʹs Data: For each manufactured item, provide current manufacturerʹs
descriptive literature of cataloged products, certified equipment drawings, diagrams,
performance and characteristic curves if applicable, and catalog cuts.
J. Standard Compliance: When materials or equipment provided by the Contractor must
conform to the standards of organizations such as American National Standards
Institute (ANSI) or American Water Works Association (AWWA), submit proof of such
Performance Specification – Shasta COE Section 23 0000
22
conformance to the Owner for approval. If an organization uses a label or listing to
indicate compliance with a particular standard, the label or listing will be acceptable
evidence, unless otherwise specified. In lieu of the label or listing, submit a certificate
from an independent testing organization, which is competent to perform acceptance
testing and is approved by the Owner. The certificate shall state that the item has been
tested in accordance with the specified organizationʹs test methods and that the item
conforms to the specified organizationʹs standard.
K. Certified Test Reports: Before delivery of materials and equipment, certified copies of
all test reports specified in individual sections shall be submitted for approval.
L. Certificates of Compliance or Conformance: Submit manufacturerʹs certifications as
required on products, materials, finish, and equipment indicated in the technical
sections. Certifications shall be documents prepared specifically for this Contract. Pre‐
printed certifications and copies of previously submitted documents will not be
acceptable. The manufacturerʹs certifications shall name the appropriate products,
equipment, or materials and the publication specified as controlling the quality of that
item. Certification shall not contain statements to imply that the item does not meet
requirements specified, such as ʺas good as,ʺ or ʺachieve the same end use and results
as materials formulated in accordance with the referenced publications,ʺ or ʺequal or
exceed the service and performance of the specified material.ʺ Certifications shall
simply state that the item conforms to the requirements specified. Certificates shall be
printed on the manufacturerʹs letterhead and shall be signed by the manufacturerʹs
official authorized to sign certificates of compliance or conformance.
1.11 PRODUCT ALERTNATIVES OR SUBSTITUTIONS A. Refer to General Conditions and Division 01 for additional requirements
1.12 POSTED OPERATING INSTRUCTIONS A. Furnish approved operating instructions for systems and equipment indicated in the
technical sections for use by operation and maintenance personnel.
B. The operating instructions shall include control diagrams, and control sequence for
each principal system and equipment. Print or engrave operating instructions and
frame under glass or in approved laminated plastic. Post instructions as directed.
Attach or post operating instructions adjacent to each principal system and equipment.
Provide weather‐resistant materials or weatherproof enclosures for operating
instructions exposed to the weather. Operating instructions shall not fade when
exposed to sunlight and shall be secured to prevent easy removal or peeling.
1.13 MANUFACTURER’S RECOMMENDATION A. Where installation procedures or any part thereof are required to be in accordance with
manufacturerʹs recommendations, furnish printed copies of the recommendations
prior to installation. Installation of the item shall not proceed until recommendations
are received. Failure to furnish recommendations shall be cause for rejection of the
equipment or material.
Performance Specification – Shasta COE Section 23 0000
23
1.14 DELIVERY AND STORAGE A. Refer to Division 01 for additional requirements.
B. Handle, store, and protect equipment and materials in accordance with the
manufacturerʹs recommendations. Replace damaged or defective items with new
items.
1.15 EXTRA MATERIALS A. Refer to Division 01 for additional requirements.
B. Unless otherwise specified, spare parts, wherever required by detailed specification
sections, shall be stored in accordance with the provisions of this paragraph. Spare
parts shall be tagged by project equipment number and identified as to part number,
equipment manufacturer, and subassembly component (if appropriate). Spare parts
subject to deterioration, such as ferrous metal items and electrical components, shall be
properly protected by lubricants or desiccants and encapsulated in hermetically sealed
plastic wrapping. Spare parts with individual weights less than 50 pounds and
dimensions less than 2 feet wide, or 18 inches high, or 3 feet in length shall be stored in
a wooden box with a hinged wooden cover and locking hasp. Hinges shall be strap
type. The box shall be painted and identified with stenciled lettering stating the name
of the equipment, equipment numbers, and the words “spare parts.” A neatly typed
inventory of spare parts shall be taped to the underside of the cover.
PART 2 - PRODUCTS – Not Applicable
Performance Specification – Shasta COE Section 23 0000
24
PART 3 - EXECUTION
3.1 GENERAL A. Obtain and pay for all permits and inspections, including any independent testing
required to verify standard compliance, and deliver certificates for same to the Owner.
3.2 WORK RESPONSIBILITIES A. The Mechanical Drawings indicate diagrammatically the desired locations or
arrangement of piping, equipment, etc., and are to be followed as closely as possible.
Proper judgment must be exercised in executing the work to secure the best possible
installation in the available space and to overcome local difficulties due to space
limitations or interference with structural conditions
B. The Contractor is responsible for the correct placing of Work and the proper location
and connection of Work in relation to the work of other trades. Advise appropriate
trade as to locations of access panels.
C. In the event that changes in the indicated locations or arrangements are necessary due
to developed conditions in the building construction or rearrangement of furnishings
or equipment, such changes shall be made without extra cost, providing the change is
ordered before the ductwork, piping, etc., and work directly connected to same is
installed and no extra materials are required.
D. Where equipment is furnished by others, verify dimensions and the correct locations of
this equipment before proceeding with the roughing‐in of connections.
E. All scaled and figured dimensions are approximate of typical equipment of the class
indicated. Before proceeding with any work, carefully check and verify all dimensions,
sizes, etc., with the drawings to see that the equipment will fit into the spaces provided
without violation of applicable codes.
F. Should any changes to the Work indicated on the Drawings or described in the
Specifications be necessary in order to comply with the above requirements, notify the
Owner immediately and cease work on all parts of the contract, which are affected
until approval for any required modifications to the construction has been obtained
from the Owner.
G. Be responsible for any cooperative work, which must be altered due to lack of proper
supervision or failure to make proper provisions in time. Such changes shall be under
direction of the Owner and shall be made to his satisfaction. Perform all Work with
competent and skilled personnel.
H. All work, including aesthetic as well as mechanical aspects of the Work, shall be of the
highest quality consistent with the best practices of the trade.
I. Replace or repair, without additional compensation, any Work which, in the opinion of
the Owner, does not comply with these requirements.
Performance Specification – Shasta COE Section 23 0000
25
3.3 PAINTING A. Factory Applied:
Mechanical equipment shall have factory applied painting systems which shall,
at a minimum, meet the requirements of NEMA ICS 6 corrosion resistance test.
Refer to individual sections of this Division for more stringent requirements.
B. Field Applied:
Paint all mechanical equipment as required to touch up, to match finish on other
equipment in adjacent spaces or to meet safety criteria
END OF SECTION 23 0000
Performance Specification – Shasta COE Section 23 0700
26
SECTION 23 0700 HVAC INSULATION
PART 1 - GENERAL
1.1 SUMMARY A. Section Includes:
1. Insulation Materials:
a. Flexible elastomeric.
b. Mineral fiber.
2. Insulating cements.
3. Adhesives.
4. Mastics.
5. Sealants.
6. Field‐applied jackets.
7. Tapes.
8. Securements.
9. Corner angles.
B. Related Sections:
1. Division 22 Section ʺPlumbing Insulation.ʺ
1.2 SUBMITTALS A. Product Data: For each type of product indicated.
B. Shop Drawings:
1. Detail application of protective shields, saddles, and inserts at hangers for each
type of insulation and hanger.
2. Detail insulation application at elbows, fittings, flanges, valves, and specialties
for each type of insulation.
3. Detail removable insulation at piping specialties, equipment connections, and
access panels.
4. Detail application of field‐applied jackets.
5. Detail application at linkages of control devices.
6. Detail field application for each equipment type.
C. Field quality‐control reports.
1.3 QUALITY ASSURANCE A. Fire‐Test‐Response Characteristics: Insulation and related materials shall have fire‐test‐
response characteristics indicated, as determined by testing identical products per
ASTM E 84, by a testing and inspecting agency acceptable to authorities having
jurisdiction. Factory label insulation and jacket materials and adhesive, mastic, tapes,
and cement material containers, with appropriate markings of applicable testing and
inspecting agency.
Performance Specification – Shasta COE Section 23 0700
27
1. Insulation Installed Indoors: Flame‐spread index of 25 or less, and smoke‐
developed index of 50 or less.
2. Insulation Installed Outdoors: Flame‐spread index of 75 or less, and smoke‐
developed index of 150 or less.
PART 2 - PRODUCTS
2.1 INSULATION MATERIALS A. Comply with requirements in Part 3 schedule articles for where insulating materials
shall be applied.
B. Products shall not contain asbestos, lead, mercury, or mercury compounds.
C. Products that come in contact with stainless steel shall have a leachable chloride
content of less than 50 ppm when tested according to ASTM C 871.
D. Insulation materials for use on austenitic stainless steel shall be qualified as acceptable
according to ASTM C 795.
E. Foam insulation materials shall not use CFC or HCFC blowing agents in the
manufacturing process.
F. Mineral‐Fiber Board Insulation: Mineral or glass fibers bonded with a thermosetting
resin. Comply with ASTM C 612, Type IA or Type IB. For duct and plenum
applications, provide insulation with factory‐applied FSK jacket. For equipment
applications, provide insulation with factory‐applied ASJ. Factory‐applied jacket
requirements are specified in ʺFactory‐Applied Jacketsʺ Article.
1. Products: Subject to compliance with requirements, provide one of the
following:
a. CertainTeed Corp.; Commercial Board.
b. Johns Manville; 800 Series Spin‐Glas.
c. Knauf Insulation; Insulation Board.
d. Owens Corning; Fiberglas 700 Series.
G. Mineral‐Fiber, Preformed Pipe Insulation:
1. Products: Subject to compliance with requirements, provide one of the
following:
a. Johns Manville; Micro‐Lok.
b. Knauf Insulation; 1000 Pipe Insulation.
c. Owens Corning; Fiberglas Pipe Insulation.
2. Type I, 850 deg F Materials: Mineral or glass fibers bonded with a thermosetting
resin. Comply with ASTM C 547, Type I, Grade A, with factory‐applied ASJ.
Factory‐applied jacket requirements are specified in ʺFactory‐Applied Jacketsʺ
Article.
2.2 INSULATING CEMENTS A. Mineral‐Fiber, Hydraulic‐Setting Insulating and Finishing Cement: Comply with
ASTM C 449/C 449M.
Performance Specification – Shasta COE Section 23 0700
28
1. 1. Products: Subject to compliance with requirements, provide one of the
following:
a. Insulco, Division of MFS, Inc.; SmoothKote.
b. P. K. Insulation Mfg. Co., Inc.; PK No. 127, and Quik‐Cote.
c. Rock Wool Manufacturing Company; Delta One Shot.
2.3 ADHESIVES A. Materials shall be compatible with insulation materials, jackets, and substrates and for
bonding insulation to itself and to surfaces to be insulated, unless otherwise indicated.
B. Adhesives to be waterproof fire‐retardant type.
C. For indoor applications, use adhesive for Flexible Elastomeric, ASJ, and PVC Jacket
that has a VOC content of 50 g/L or less and for Mineral‐Fiber Adhesive that has a
VOC content of 80 g/L or less when calculated according to 40 CFR 59, Subpart D (EPA
Method 24).
2.4 MASTICS A. Materials shall be compatible with insulation materials, jackets, and substrates.
2.5 SEALANTS A. Joint Sealants:
1. Materials shall be compatible with insulation materials, jackets, and substrates.
2. Permanently flexible, elastomeric sealant.
3. Service Temperature Range: Minus 100 to plus 300 deg F.
4. For indoor applications, use sealants that have a VOC content of 420 g/L or less
when calculated according to 40 CFR 59, Subpart D (EPA Method 24).
B. FSK and Metal Jacket Flashing Sealants:
1. Products: Subject to compliance with requirements, provide one of the
following:
a. Childers Products, Division of ITW; CP‐76‐8.
b. Foster Products Corporation, H. B. Fuller Company; 95‐44.
c. Vimasco Corporation; 750.
2. Materials shall be compatible with insulation materials, jackets, and substrates.
3. Fire‐ and water‐resistant, flexible, elastomeric sealant.
4. Service Temperature Range: Minus 40 to plus 250 deg F.
5. Color: Aluminum.
6. For indoor applications, use sealants that have a VOC content of 420 g/L or less
when calculated according to 40 CFR 59, Subpart D (EPA Method 24).
C. ASJ Flashing Sealants, and Vinyl, PVDC, and PVC Jacket Flashing Sealants:
1. Materials shall be compatible with insulation materials, jackets, and substrates.
2. Fire‐ and water‐resistant, flexible, elastomeric sealant.
3. Service Temperature Range: Minus 40 to plus 250 deg F.
4. Color: White.
Performance Specification – Shasta COE Section 23 0700
29
5. For indoor applications, use sealants that have a VOC content of 420 g/L or less
when calculated according to 40 CFR 59, Subpart D (EPA Method 24).
2.6 FACTORY-APPLIED JACKETS A. Insulation system schedules indicate factory‐applied jackets on various applications.
When factory‐applied jackets are indicated, comply with the following:
1. ASJ: White, kraft‐paper, fiberglass‐reinforced scrim with aluminum‐foil backing;
complying with ASTM C 1136, Type I.
2. FSK Jacket: Aluminum‐foil, fiberglass‐reinforced scrim with kraft‐paper backing;
complying with ASTM C 1136, Type II.
2.7 TAPES A. ASJ Tape: White vapor‐retarder tape matching factory‐applied jacket with acrylic
adhesive, complying with ASTM C 1136.
1. Products: Subject to compliance with requirements, provide one of the
following:
a. Avery Dennison Corporation, Specialty Tapes Division; Fasson 0835.
b. Compac Corp.; 104 and 105.
c. Ideal Tape Co., Inc., an American Biltrite Company; 428 AWF ASJ.
d. Venture Tape; 1540 CW Plus, 1542 CW Plus, and 1542 CW Plus/SQ.
2. Width: 3 inches.
3. Thickness: 11.5 mils.
4. Adhesion: 90 ounces force/inch in width.
5. Elongation: 2 percent.
6. Tensile Strength: 40 lbf/inch in width.
7. ASJ Tape Disks and Squares: Precut disks or squares of ASJ tape.
B. FSK Tape: Foil‐face, vapor‐retarder tape matching factory‐applied jacket with acrylic
adhesive; complying with ASTM C 1136.
1. Products: Subject to compliance with requirements, provide one of the
following:
a. Avery Dennison Corporation, Specialty Tapes Division; Fasson 0827.
b. Compac Corp.; 110 and 111.
c. Ideal Tape Co., Inc., an American Biltrite Company; 491 AWF FSK.
d. Venture Tape; 1525 CW, 1528 CW, and 1528 CW/SQ.
2. Width: 3 inches.
3. Thickness: 6.5 mils.
4. Adhesion: 90 ounces force/inch in width.
5. Elongation: 2 percent.
6. Tensile Strength: 40 lbf/inch in width.
7. FSK Tape Disks and Squares: Precut disks or squares of FSK tape.
C. PVC Tape: White vapor‐retarder tape matching field‐applied PVC jacket with acrylic
adhesive. Suitable for indoor and outdoor applications.
Performance Specification – Shasta COE Section 23 0700
30
1. Products: Subject to compliance with requirements, provide one of the
following:
a. Avery Dennison Corporation, Specialty Tapes Division; Fasson 0555.
b. Compac Corp.; 130.
c. Ideal Tape Co., Inc., an American Biltrite Company; 370 White PVC tape.
d. Venture Tape; 1506 CW NS.
2. Width: 2 inches.
3. Thickness: 6 mils.
4. Adhesion: 64 ounces force/inch in width.
5. Elongation: 500 percent.
6. Tensile Strength: 18 lbf/inch in width.
2.8 SECUREMENTS A. Aluminum Bands: ASTM B 209, Alloy 3003, 3005, 3105, or 5005; Temper H‐14, 0.020
inch thick, 1/2 inch wide with wing or closed seal.
B. Insulation Pins and Hangers:
1. Metal, Adhesively Attached, Perforated‐Base Insulation Hangers: Baseplate
welded to projecting spindle that is capable of holding insulation, of thickness
indicated, securely in position indicated when self‐locking washer is in place.
Comply with the following requirements:
a. Baseplate: Perforated, galvanized carbon‐steel sheet, 0.030 inch thick by 2
inches square.
b. Spindle: Copper‐ or zinc‐coated, low carbon steel, fully annealed, 0.106‐
inchdiameter shank, length to suit depth of insulation indicated.
c. Adhesive: Recommended by hanger manufacturer. Product with
demonstrated capability to bond insulation hanger securely to substrates
indicated without damaging insulation, hangers, and substrates.
2. Self‐Sticking‐Base Insulation Hangers: Baseplate welded to projecting spindle
that is capable of holding insulation, of thickness indicated, securely in position
indicated when self‐locking washer is in place. Comply with the following
requirements:
a. Baseplate: Galvanized carbon‐steel sheet, 0.030 inch thick by 2 inches
square.
b. Spindle: Copper‐ or zinc‐coated, low carbon steel, fully annealed, 0.106‐
inchdiameter shank, length to suit depth of insulation indicated.
c. Adhesive‐backed base with a peel‐off protective cover.
3. Insulation‐Retaining Washers: Self‐locking washers formed from 0.016‐inch‐
thick, galvanized‐steel sheet, with beveled edge sized as required to hold
insulation securely in place but not less than 1‐1/2 inches in diameter.
Performance Specification – Shasta COE Section 23 0700
31
a. Protect ends with capped self‐locking washers incorporating a spring steel
insert to ensure permanent retention of cap in exposed locations.
C. Wire: 0.062‐inch soft‐annealed, stainless steel.
2.9 CORNER ANGLES A. PVC Corner Angles: 30 mils thick, minimum 1 by 1 inch, PVC according to ASTM D
1784, Class 16354‐C. White or color‐coded to match adjacent surface.
B. Aluminum Corner Angles: 0.040 inch thick, minimum 1 by 1 inch, aluminum
according to ASTM B 209, Alloy 3003, 3005, 3105 or 5005; Temper H‐14.
PART 3 - EXECUTION
3.1 PREPARATION A. Surface Preparation: Clean and dry surfaces to receive insulation. Remove materials
that will adversely affect insulation application.
B. Coordinate insulation installation with the trade installing heat tracing. Comply with
requirements for heat tracing that apply to insulation.
C. Mix insulating cements with clean potable water; if insulating cements are to be in
contact with stainless‐steel surfaces, use demineralized water.
3.2 GENERAL INSTALLATION REQUIREMENTS A. Install insulation materials, accessories, and finishes with smooth, straight, and even
surfaces; free of voids throughout the length of equipment, ducts and fittings, and
piping including fittings, valves, and specialties.
B. Install insulation materials, forms, vapor barriers or retarders, jackets, and thicknesses
required for each item of equipment, duct system, and pipe system as specified in
insulation system schedules.
C. Install accessories compatible with insulation materials and suitable for the service.
Install accessories that do not corrode, soften, or otherwise attack insulation or jacket in
either wet or dry state.
D. Install insulation with longitudinal seams at top and bottom of horizontal runs.
E. Install multiple layers of insulation with longitudinal and end seams staggered.
F. Do not weld brackets, clips, or other attachment devices to piping, fittings, and
specialties.
G. Keep insulation materials dry during application and finishing.
H. Install insulation with tight longitudinal seams and end joints. Bond seams and joints
with adhesive recommended by insulation material manufacturer.
I. Install insulation with least number of joints practical.
J. Where vapor barrier is indicated, seal joints, seams, and penetrations in insulation at
hangers, supports, anchors, and other projections with vapor‐barrier mastic.
1. Install insulation continuously through hangers and around anchor attachments.
2. For insulation application where vapor barriers are indicated, extend insulation
on anchor legs from point of attachment to supported item to point of
Performance Specification – Shasta COE Section 23 0700
32
attachment to structure. Taper and seal ends at attachment to structure with
vapor‐barrier mastic.
3. Install insert materials and install insulation to tightly join the insert. Seal
insulation to insulation inserts with adhesive or sealing compound
recommended by insulation material manufacturer.
4. Cover inserts with jacket material matching adjacent pipe insulation. Install
shields over jacket, arranged to protect jacket from tear or puncture by hanger,
support, and shield.
K. Apply adhesives, mastics, and sealants at manufacturerʹs recommended coverage rate
and wet and dry film thicknesses.
L. Install insulation with factory‐applied jackets as follows:
1. Draw jacket tight and smooth.
2. Cover circumferential joints with 3‐inch‐ wide strips, of same material as
insulation jacket. Secure strips with adhesive and outward clinching staples
along both edges of strip, spaced 4 inches o.c.
3. Overlap jacket longitudinal seams at least 1‐1/2 inches. Install insulation with
longitudinal seams at bottom of pipe. Clean and dry surface to receive self‐
sealing lap.
4. Cover joints and seams with tape as recommended by insulation material
manufacturer to maintain vapor seal.
5. Where vapor barriers are indicated, apply vapor‐barrier mastic on seams and
joints and at ends adjacent to pipe flanges and fittings.
M. Cut insulation in a manner to avoid compressing insulation more than 75 percent of its
nominal thickness.
N. Finish installation with systems at operating conditions. Repair joint separations and
cracking due to thermal movement.
O. Repair damaged insulation facings by applying same facing material over damaged
areas. Extend patches at least 4 inches beyond damaged areas. Adhere, staple, and seal
patches similar to butt joints.
P. For above ambient services, do not install insulation to the following:
1. Vibration‐control devices.
2. Testing agency labels and stamps.
3. Nameplates and data plates.
4. Manholes.
5. Handholes.
6. Cleanouts.
3.3 PENETRATIONS A. Insulation Installation at Roof Penetrations: Install insulation continuously through
roof penetrations.
1. Seal penetrations with flashing sealant.
Performance Specification – Shasta COE Section 23 0700
33
2. For applications requiring only indoor insulation, terminate insulation above
roof surface and seal with joint sealant. For applications requiring indoor and
outdoor insulation, install insulation for outdoor applications tightly joined to
indoor insulation ends. Seal joint with joint sealant.
3. Extend jacket of outdoor insulation outside roof flashing at least 2 inches below
top of roof flashing.
4. Seal jacket to roof flashing with flashing sealant.
B. Insulation Installation at Underground Exterior Wall Penetrations: Terminate
insulation flush with sleeve seal. Seal terminations with flashing sealant.
C. Insulation Installation at Aboveground Exterior Wall Penetrations: Install insulation
continuously through wall penetrations.
1. Seal penetrations with flashing sealant.
2. For applications requiring only indoor insulation, terminate insulation inside
wall surface and seal with joint sealant. For applications requiring indoor and
outdoor insulation, install insulation for outdoor applications tightly joined to
indoor insulation ends. Seal joint with joint sealant.
3. Extend jacket of outdoor insulation outside wall flashing and overlap wall
flashing at least 2 inches.
4. Seal jacket to wall flashing with flashing sealant.
D. Insulation Installation at Interior Wall and Partition Penetrations (That Are Not Fire
Rated): Install insulation continuously through walls and partitions.
E. Insulation Installation at Fire‐Rated Wall and Partition Penetrations: Install insulation
continuously through penetrations of fire‐rated walls and partitions. Terminate
insulation at fire damper sleeves for fire‐rated wall and partition penetrations.
Externally insulate damper sleeves to match adjacent insulation and overlap duct
insulation at least 2 inches.
1. Comply with requirements in Division 07 Section ʺPenetration Firestoppingʺ
Firestopping and fire‐resistive joint sealers.
F. Insulation Installation at Floor Penetrations:
1. Duct: Install insulation continuously through floor penetrations that are not fire
rated. For penetrations through fire‐rated assemblies, terminate insulation at fire
damper sleeves and externally insulate damper sleeve beyond floor to match
adjacent duct insulation. Overlap damper sleeve and duct insulation at least 2
inches.
2. Pipe: Install insulation continuously through floor penetrations.
3. Seal penetrations through fire‐rated assemblies. Comply with requirements in
Division 07 Section ʺPenetration Firestopping.ʺ
G. Insulation Installation on Pumps:
1. Fabricate metal boxes lined with insulation. Fit boxes around pumps and
coincide box joints with splits in pump casings. Fabricate joints with outward
bolted flanges. Bolt flanges on 6‐inch centers, starting at corners. Install 3/8‐inch‐
diameter fasteners with wing nuts. Alternatively, secure the box sections
together using a latching mechanism.
Performance Specification – Shasta COE Section 23 0700
34
2. Fabricate boxes from aluminum, at least 0.050 inch thick.
3. For below ambient services, install a vapor barrier at seams, joints, and
penetrations. Seal between flanges with replaceable gasket material to form a
vapor barrier.
3.4 GENERAL PIPE INSULATION INSTALLATION A. Requirements in this article generally apply to all insulation materials except where
more specific requirements are specified in various pipe insulation material installation
articles.
B. Insulation Installation on Fittings, Valves, Strainers, Flanges, and Unions:
1. Install insulation over fittings, valves, strainers, flanges, unions, and other
specialties with continuous thermal and vapor‐retarder integrity, unless
otherwise indicated.
2. Insulate pipe elbows using preformed fitting insulation or mitered fittings made
from same material and density as adjacent pipe insulation. Each piece shall be
butted tightly against adjoining piece and bonded with adhesive. Fill joints,
seams, voids, and irregular surfaces with insulating cement finished to a smooth,
hard, and uniform contour that is uniform with adjoining pipe insulation.
3. Insulate tee fittings with preformed fitting insulation or sectional pipe insulation
of same material and thickness as used for adjacent pipe. Cut sectional pipe
insulation to fit. Butt each section closely to the next and hold in place with tie
wire. Bond pieces with adhesive.
4. Insulate valves using preformed fitting insulation or sectional pipe insulation of
same material, density, and thickness as used for adjacent pipe. Overlap
adjoining pipe insulation by not less than two times the thickness of pipe
insulation, or one pipe diameter, whichever is thicker. For valves, insulate up to
and including the bonnets, valve stuffing‐box studs, bolts, and nuts. Fill joints,
seams, and irregular surfaces with insulating cement.
5. Insulate strainers using preformed fitting insulation or sectional pipe insulation
of same material, density, and thickness as used for adjacent pipe. Overlap
adjoining pipe insulation by not less than two times the thickness of pipe
insulation, or one pipe diameter, whichever is thicker. Fill joints, seams, and
irregular surfaces with insulating cement. Insulate strainers so strainer basket
flange or plug can be easily removed and replaced without damaging the
insulation and jacket. Provide a removable reusable insulation cover. For below
ambient services, provide a design that maintains vapor barrier.
6. Insulate flanges and unions using a section of oversized preformed pipe
insulation. Overlap adjoining pipe insulation by not less than two times the
thickness of pipe insulation, or one pipe diameter, whichever is thicker.
7. Cover segmented insulated surfaces with a layer of finishing cement and coat
with a mastic. Install vapor‐barrier mastic for below ambient services and a
breather mastic for above ambient services. Reinforce the mastic with fabric‐
reinforcing mesh. Trowel the mastic to a smooth and well‐shaped contour.
Performance Specification – Shasta COE Section 23 0700
35
8. For services not specified to receive a field‐applied jacket except for flexible
elastomeric, install fitted PVC cover over elbows, tees, strainers, valves, flanges,
and unions. Terminate ends with PVC end caps. Tape PVC covers to adjoining
insulation facing using PVC tape.
9. Stencil or label the outside insulation jacket of each union with the word
ʺUNION.ʺ Match size and color of pipe labels.
C. Insulate instrument connections for thermometers, pressure gages, pressure
temperature taps, test connections, flow meters, sensors, switches, and transmitters on
insulated pipes, vessels, and equipment. Shape insulation at these connections by
tapering it to and around the connection with insulating cement and finish with
finishing cement, mastic, and flashing sealant.
D. Install removable insulation covers at locations indicated. Installation shall conform to
the following:
1. Make removable flange and union insulation from sectional pipe insulation of
same thickness as that on adjoining pipe. Install same insulation jacket as
adjoining pipe insulation.
2. When flange and union covers are made from sectional pipe insulation, extend
insulation from flanges or union long at least two times the insulation thickness
over adjacent pipe insulation on each side of flange or union. Secure flange cover
in place with stainless‐steel or aluminum bands. Select band material compatible
with insulation and jacket.
3. Construct removable valve insulation covers in same manner as for flanges
except divide the two‐part section on the vertical center line of valve body.
4. When covers are made from block insulation, make two halves, each consisting
of mitered blocks wired to stainless‐steel fabric. Secure this wire frame, with its
attached insulation, to flanges with tie wire. Extend insulation at least 2 inches
over adjacent pipe insulation on each side of valve. Fill space between flange or
union cover and pipe insulation with insulating cement. Finish cover assembly
with insulating cement applied in two coats. After first coat is dry, apply and
trowel second coat to a smooth finish.
5. Unless a PVC jacket is indicated in field‐applied jacket schedules, finish exposed
surfaces with a metal jacket.
3.5 MINERAL-FIBER INSULLATINO INSTALLATION A. Insulation Installation on Straight Pipes and Tubes:
1. Secure each layer of preformed pipe insulation to pipe with wire or bands and
tighten bands without deforming insulation materials.
2. Where vapor barriers are indicated, seal longitudinal seams, end joints, and
protrusions with vapor‐barrier mastic and joint sealant.
3. For insulation with factory‐applied jackets secure tabs with additional adhesive
as recommended by insulation material manufacturer and seal with vapor‐
barrier mastic and flashing sealant.
B. Insulation Installation on Pipe Flanges:
Performance Specification – Shasta COE Section 23 0700
36
1. Install preformed pipe insulation to outer diameter of pipe flange.
2. Make width of insulation section same as overall width of flange and bolts, plus
twice the thickness of pipe insulation.
3. Fill voids between inner circumference of flange insulation and outer
circumference of adjacent straight pipe segments with mineral‐fiber blanket
insulation.
4. Install jacket material with manufacturerʹs recommended adhesive, overlap
seams at least 1 inch, and seal joints with flashing sealant.
C. Insulation Installation on Pipe Fittings and Elbows:
1. Install preformed sections of same material as straight segments of pipe
insulation when available.
2. When preformed insulation elbows and fittings are not available, install mitered
sections of pipe insulation, to a thickness equal to adjoining pipe insulation.
Secure insulation materials with wire or bands.
D. Insulation Installation on Valves and Pipe Specialties:
1. Install preformed sections of same material as straight segments of pipe
insulation when available.
2. When preformed sections are not available, install mitered sections of pipe
insulation to valve body.
3. Arrange insulation to permit access to packing and to allow valve operation
without disturbing insulation.
4. Install insulation to flanges as specified for flange insulation application.
3.6 FIELD-APPLIED JACKET INSTALLATION A. Where FSK jackets are indicated, install as follows:
1. Draw jacket material smooth and tight.
2. Install lap or joint strips with same material as jacket.
3. Secure jacket to insulation with manufacturerʹs recommended adhesive.
4. Install jacket with 1‐1/2‐inch laps at longitudinal seams and 3‐inch‐ wide joint
strips at end joints.
5. Seal openings, punctures, and breaks in vapor‐retarder jackets and exposed
insulation with vapor‐barrier mastic.
B. Where PVC jackets are indicated, install with 1‐inch overlap at longitudinal seams and
end joints; for horizontal applications, install with longitudinal seams along top and
bottom of tanks and vessels. Seal with manufacturerʹs recommended adhesive.
1. Apply two continuous beads of adhesive to seams and joints, one bead under
lap and the finish bead along seam and joint edge.
C. Where metal jackets are indicated, install with 2‐inch overlap at longitudinal seams
and end joints. Overlap longitudinal seams arranged to shed water. Seal end joints
with weatherproof sealant recommended by insulation manufacturer. Secure jacket
with stainless‐steel bands 12 inches o.c. and at end joints.
3.7 FIELD QUALITY CONTROL A. Perform tests and inspections.
Performance Specification – Shasta COE Section 23 0700
37
B. Tests and Inspections:
1. Inspect pipe, fittings, strainers, and valves, randomly selected by Architect, by
removing field‐applied jacket and insulation in layers in reverse order of their
installation. Extent of inspection shall be limited to three locations of straight
pipe, three locations of threaded fittings, three locations of welded fittings, two
locations of threaded strainers, two locations of welded strainers, three locations
of threaded valves, and three Insert number locations of flanged valves for each
pipe service defined in the ʺPiping Insulation Schedule, Generalʺ Article.
C. All insulation applications will be considered defective Work if sample inspection
reveals noncompliance with requirements.
END OF SECTION 23 0700
Performance Specification – Shasta COE Section 26 0160
38
SECTION 26 0160 ELECTRICAL DEMOLITION
PART 1 - GENERAL
1.1 SUMMARY A. Section includes:
1. Removal of existing electrical feeders, receptacles, electrical conduits/conductors
associated with mechanical equipment intended to be demolished or replaced.
2. The Contractor shall dispose of demolished electrical equipment as directed by
the Owner. The Owner has first right of refusal for all equipment including
copper cabling.
1.2 REFERENCES A. Environmental Protection Agency (EPA) Regulations:
1. 40 CFR 261, Identification and Listing of Hazardous Waste.
2. 40 CFR 263, Standards Applicable to Transporters of Hazardous Wastes.
3. Hazardous Waste Facilities.
B. U.S. Department of Labor, Occupational Safety and Health Administration (OSHA)
Regulation:
1. 29 CFR 1910 Subpart G, Occupational Health and Environmental Control.
C. Department of Transportation (DOT):
1. 49 CFR 178, Regulations for Shipping Container Specifications.
PART 2 - PRODUCTS
2.1 MATERIALS AND EQUIPMENT A. Materials and equipment for patching and extending work: As specified in individual
Sections, if applicable.
PART 3 - EXECUTION
3.1 EXAMINATION A. Verify that abandoned wiring and equipment serve only abandoned facilities.
B. Conduct site inspection and report discrepancies to Engineer before disturbing
existing installation.
C. Beginning of demolition means installer accepts existing conditions.
3.2 PREPARATION A. Disconnect electrical systems in and under walls, concrete, and structures scheduled
for removal.
Performance Specification – Shasta COE Section 26 0160
39
B. Coordinate electrical outages with the Facility.
C. Provide temporary wiring and connections to maintain existing systems in‐service
during construction. When work must be performed on energized equipment or
circuits, use personnel experienced in such operations.
3.3 DEMOLITION AND EXTENSION OF EXISTING ELECTRICAL WORK A. Demolish existing electrical work under provisions of this Section.
B. Remove abandoned wiring to source of supply unless otherwise indicated.
C. Remove exposed abandoned conduit. Cut conduit flush with walls and floors, and
patch surfaces.
D. Disconnect and remove abandoned distribution equipment.
E. Repair adjacent construction and finishes damaged during demolition and extension
work.
F. Maintain access to existing electrical installations which remain active. Modify
installation or provide access panel as appropriate.
3.4 CLEAUP AND REPAIR A. Clean and repair existing materials and equipment which remain or are to be reused.
END OF SECTION 26 0160
Performance Specification – Shasta COE Section 26 0923
40
SECTION 26 0923 LIGHTING CONTROL SYSTEMS
PART 1 - GENERAL
1.1 SUMMARY A. Related Documents:
1. Drawings and general provisions of the Subcontract apply to this Section.
2. Review these documents for coordination with additional requirements and
information that apply to work under this Section.
B. Section Includes:
1. Occupancy Sensors for Interior Lighting.
2. Photocell Sensors for Exterior Lighting.
3. Exterior Smart Controls.
C. Related Sections:
1. Division 01 Section, General Requirements.
2. Division 01 Section, Special Procedures.
3. Division 26 Section, Common Work Results for Electrical.
4. Division 26 Section, Electrical Conduit.
5. Division 26 Section, 600 Volt Conductors and Cable.
6. Division 26 Section, Boxes for Electrical Systems.
7. Division 26 Section, Lighting.
8. Division 26 Section, Wiring Devices.
1.2 REFERENCES A. General:
1. The following documents form part of the Specifications to the extent stated. Where
differences exist between codes and standards, the one affording the greatest
protection shall apply.
2. Unless otherwise noted, the referenced standard edition is the current one at the
time of commencement of the Work.
3. Refer to Division 01 Section, General Requirements for the list of applicable
regulatory requirements.
4. Refer to Division 26 Section, Common Results for Electrical for codes and standards,
and other general requirements.
Performance Specification – Shasta COE Section 26 0923
41
B. Illuminating Engineering Society (IES):
1. RP‐33‐99 – Recommended Practices for Exterior Environmental Lighting.
2. LM‐79 – Electrical and Photometric Measurements of Solid‐State Lighting Products.
3. LM‐80 – Measuring Lumen Maintenance of LED Light Sources.
4. TM‐15 – Luminaire Classification System for Outdoor Luminaires.
5. TM‐21 – Projecting Long Term Lumen Maintenance of LED Light Sources.
C. American National Standards Institute (ANSI):
1. ANSI/NFPA 101 – Life Safety Code.
2. ANSI/NFPA 70 – National Electrical Code.
D. National Electrical Manufacturers Association (NEMA):
1. NEMA WD 6 – Wiring Devices Dimensional Requirements.
E. Underwriters Laboratories, Inc. (UL):
1. UL 1598 – Standard for Luminaires.
2. UL 8750 – Light Emitting Diode Equipment for Use in Lighting Products.
F. California Title 24, Non‐Residential Lighting: Section 130.
1. California Building Code (CBC).
2. California Electrical Code (CEC).
G. OSHA Illumination Standards
1.3 SUBMITTALS A. Manufacturerʹs Data: Submit catalog cuts and description of each system component.
B. Provide wiring diagrams and installation details for lighting control equipment.
C. Shop Drawings: Submit a complete set of detailed Shop Drawings for the entire lighting
control system; the shop drawings shall include but not be limited to relay panels with
designations and dimensions, daylight sensors locations based on manufacturer’s
recommendations, and system components with manufacturer’s part numbers.
D. Installation Instructions: Submit manufacturerʹs written installation instructions and
wiring diagrams. Instructions shall include recommendations for handling of equipment
and parts, and protection and storage requirements.
1.4 QUALITY ASSURANCE A. Components shall be listed and labeled by Underwriterʹs Laboratories (UL), or another
Nationally Recognized Testing Laboratory (NRTL).
B. Lighting Control Systems shall comply with the state of California Building and Electrical
Codes, and Title 24 energy requirements in effect at time of submittal for building permit.
C. Conduct a coordination meeting with the lighting control contractor, electrical contractor
and Manufacturer Representative to validate the location of lighting control system
components, including daylight sensors. Sensors shall be located based on manufacturer’s
recommendations.
Performance Specification – Shasta COE Section 26 0923
42
1.5 DELIVERY, STORAGE, AND HANDLING A. Store product in clean, dry space, protected from weather.
1.6 WARRANTY A. Provide a five year warranty for the Occupancy Sensors.
B. Provide a one year warranty for the Photocell Sensors.
C. Provide a five year warranty for the Wireless Sensors and one year warranty for the
Network Gateway.
PART 2 - PRODUCTS
2.1 MANUFACTURERS A. Occupancy Sensors:
1. WattStopper – Legrand North America, LLC
2. Leviton Manufacturing Co., Inc.
3. Lutron Electronics Co., Inc.
B. Photocell Sensors:
1. WattStopper – Legrand North America, LLC
2. Leviton Manufacturing Co., Inc.
3. Intermatic, Inc.
C. Exterior Smart Controls
1. Cree
2. WattStopper – Legrand North America, LLC
D. Substitutions: Under provisions of Division 01 Section, General Requirements.
2.2 OCCUPANCY SENSORS FOR INTERIOR LIGHTING A. General
1. Coordinate occupancy sensor locations, coverages and required quantities with
manufacturer’s recommendations. Coverage areas indicated on the Drawings are for
minor motion (6 to 8 inches of hand movement). Provide additional occupancy
sensors and control units as required to achieve complete minor motion coverage of
the space indicated.
2. Adjust occupancy sensors and test that complete minor motion coverage. Provide
written confirmation of testing to owner, architect and engineer.
3. Provide occupancy sensors with a bypass switch to override the “ON” function in
the event of sensor failure.
4. Provide occupancy sensors with an LED indicator indicating when motion is being
detected during testing and normal operation of the sensor.
5. Provide occupancy sensors and occupancy sensor control units from single
manufacturer.
B. Occupancy Sensor Control Units
Performance Specification – Shasta COE Section 26 0923
43
1. Description: Transformer and relay combined in single unit to provide 24DC power
to sensors and provide 20A contact(s) for control of lighting loads at 120 or 277V.
Control unit input power shall be from unswitched leg of lighting circuit it is
controlling.
a. Control units shall be provided as required to power ceiling mounted
occupancy sensors, control lighting loads and provide a minimum of one
auxiliary contact.
b. Occupancy sensor control units shall mount external to 4 sq. in. junction box in
the ceiling space. Wiring between control unit and occupancy sensor shall be
plenum rated.
c. Additional auxiliary relay modules shall be provided as required to provide
control of all lighting circuits and additional auxiliary contacts as required.
d. It is acceptable to provide controls and auxiliary contacts as required integral
to the ceiling sensor, provided all required contacts are provided.
e. Maximum of 3 sensors per power pack. Verify exact quantities required with
manufacturer.
2.3 PHOTOCELL SENSORS A. Photocells work with other components in the system to automatically adjust light levels
to a user defined level.
B. Photocells must be hardwired to a compatible lighting control system. The photocell
measures ambient light in a specific area and sends this data to a dimmer or relay that, in
turn, adjusts fixtures to a constant lighting level as measured in that specific area.
C. With the addition of photocells, the added control will provide savings for lighting
operations. Between dusk and dawn only, the photocell will keep the interior or exterior
lights on until adequate natural light becomes available.
2.4 EXTERIOR LIGHT SENSORS A. Title 24 guidelines mandate that all exterior lighting must be controlled with either a
photocell or astronomical time clock that automatically turns off the lights as daylight
becomes available. Additionally, the luminaires, with some exceptions, mounted at 24 ft.
or less from the ground must comply with the following requirements:
1. Must have motion sensors or other controls that automatically reduce lighting power
by 40 to 80 percent when the area is vacant.
2. The controls must provide auto‐on when area is occupied.
3. No more than 1,500 watt of lighting power shall be controlled together.
4. Includes wall packs as well as pole mounted fixtures.
B. The intelligent lighting control system should have the following hardware:
1. Sensor ‐ Sensor installed at each lighting fixture; integrated with occupancy,
daylight, and temperature sensors.
2. Gateways – Gateways are intermediary devices that wirelessly connect sensors with
to the server. One gateway should be adequate for the mock‐up.
Performance Specification – Shasta COE Section 26 0923
44
3. Energy Manager –The energy manager acts as the server. Control sequences
including occupancy, scheduling, and energy use are programmed and viewed
through the energy manager.
PART 3 - EXECUTION
3.1 INSTALLATION A. Occupancy Sensors for Interior Lighting
1. Install wall mounted occupancy sensors as noted on plan. Arrange occupancy
sensors with adjacent switch devices so that device plates line‐up and are equally
spaced.
2. Install ceiling mounted sensors at approximate locations as indicated on plan. Sensor
manufacturer shall provide quantity of sensors as required to provide complete
coverage for rooms.
3. Locate sensors such that motion through open doors will not falsely activate sensors.
4. Do not locate ultrasonic sensors within six feet of supply air diffusers.
5. Locate infrared sensors to avoid obstructions.
6. Provide the services of a manufacturer’s representative for commissioning of
occupancy sensor installation. This shall include consultation on layout and location
prior to installing sensors, testing of each sensor for compliance with Contract
Documents and field adjustment and fine tuning after installation is complete.
Provide written confirmation of testing to the Owner, Architect and Engineer.
7. Field adjustments shall take place in the presence of the owner and the engineer.
This shall include owner training on adjustment techniques for the occupancy
sensors
B. Photocell Controllers for Exterior Lighting
1. Prior to initiating service, follow all safety precautions associated with working on
exterior lighting fixtures.
2. Installation and wiring shall be conducted by a certified electrician. Installation shall
be based on the manufacturer’s recommendations.
3. Install the sensor on the exterior or roof of a building with the light level window
facing north.
4. The photocell sensor should be positioned correctly and not exposed to bright light
sources.
5. Installation shall be in compliance with the latest NEC and all applicable regulations.
C. Exterior Smart Controls
1. Prior to initiating service, follow all safety precautions associated with working on
exterior lighting fixtures.
2. Installation and wiring shall be conducted by a certified electrician. Installation shall
be based on the manufacturer’s recommendations.
3. Install a sensor at each existing lighting fixture being controlled.
4. Install a power pack per manufacturerʹs instructions.
Performance Specification – Shasta COE Section 26 0923
45
5. The photocell control probe should be positioned correctly and not exposed to bright
light sources.
6. Install the gateway and energy manager in a suitable location per the manufacturer’s
recommendation.
7. Program the system to provide the desired modes of operation.
8. Installation shall be in compliance with the latest NEC and all applicable regulations.
3.2 FIELD QUALITY CONTROL A. Confirm the operation of individual relays, switches, occupancy sensors, and daylight
sensors.
B. Provide training to cover installation, maintenance, troubleshooting, and repair and
operation of the lighting control system.
3.3 CLEANUP A. Remove rubbish, debris, and waste materials and legally dispose of off the Project site.
PART 4 - MATERIAL SCHEDULE
4.1 OCCUPANCY SENSORS FOR INTERIOR LIGHTING (MEASURE L-3) A. WattStopper Dual Technology Ceiling Mount (DT‐355)/ Wall Switch Occupancy Sensor
(LMDW‐100)
1. DT‐355 (or equivalent):
a. Time Delay 5 min ‐ 30 min
b. Coverage up to 1000 sq. ft.
c. 360 degree Fresnel lens for superior occupancy detection
2. DW ‐100‐24 (or equivalent)
a. Input voltage: 18‐24VDC
b. Time Delay 5 min ‐ 30 min
c. Coverage:
Major motion, PIR 35’ x 30’, Ultrasonic 20’ x 20’
Minor motion, PIR 20’ x 15’, Ultrasonic 15’ x 15’
B. Leviton Multi‐Technology Ceiling Mount Occupancy Sensors (OSC‐10‐RMW)/ Decora
Wall Switch Lev‐Lok Occupancy Sensor (MSSMT‐GDW)
1. OSC‐10‐RMW (or equivalent)
a. Input Voltage: 24VDC
b. Manual Time Adjustment: 30 sec. – 30 min
c. Operating Temperature: 32 °F to 104 °F (0 °C to 40 °C)
d. Operating Humidity: 0% to 95% Relative, Non‐Condensing
e. Pattern Degrees: 360 degree
f. Coverage: 1000 sq. ft.
2. MSSMT‐GDW (or equivalent)
Performance Specification – Shasta COE Section 26 0923
46
a. Manual Time Adjustment: 30 sec. – 30 min
b. Operating Temperature: 32 °F to 104 °F (0 °C to 40 °C)
c. Operating Humidity: 20% to 90% Relative, Non‐Condensing
d. Pattern Degrees: 180 degree
e. Coverage: 2400 sq. ft.
C. Lutron Dual Technology Ceiling Mount Sensor (LOS‐CDT)/ Maestro Dual Technology
Wall Sensor Switch (MS‐B102‐XX)
1. LOS‐CDT‐2000‐WH (or equivalent)
a. Input Voltage: 20‐24VDC
b. Manual Time Adjustment: 8 sec. – 30 min
c. Operating Temperature: 32 °F to 104 °F (0 °C to 40 °C)
d. Operating Humidity: 0% to 95% Relative, Non‐Condensing
e. Pattern Degrees: 360 degree
f. Coverage: 2000 sq. ft.
2. MS‐B102‐XX (or equivalent)
a. Manual Time Adjustment: 30 sec. – 30 min
b. Operating Temperature: 32 °F to 104 °F (0 °C to 40 °C)
c. Operating Humidity: 0% to 90% Relative, Non‐Condensing
d. Pattern Degrees: 180 degree
e. Coverage: 900 sq. ft.
4.2 PHOTOCELL SENSORS (MEASURE L-5B) A. WattStopper Photocell (EM‐24A2 or equivalent)
1. Rain tight enclosure
2. Input Voltage: 24 VAC
3. Default range: 0‐32 footcandles
B. Leviton Photocells (PCOUT‐000 or equivalent)
1. Outdoor photocells are IP54 rated to guarantee ultimate protection from dirt, dust,
oil and other non‐corrosive material.
2. Input Voltage: 24 VDC
3. Operating Temperature: ‐40 °F to 122 °F (‐40 °C to 50 °C)
4. Default range: 0‐15 footcandles
C. Intermatic Electronic Photo Control (EK4136S or equivalent)
1. Operating Temperature: ‐40 °F to 158 °F (‐40 °C to 70 °C)
2. Turn ON footcandles: 1.5
3. Turn OFF footcandles: 2.25
Performance Specification – Shasta COE Section 26 0923
47
4.4 EXTERIOR SMART CONTROLS (MEASURE L-6B) A. Cree LED Multi‐Level Options:
1. The Cree Multi‐Level options include a factory installed sensor integrated into the
luminaire which allows the luminaire to produce different lumen outputs in High
Mode and Low Mode. The multi‐level option is designed to operate all LEDs at the
same output for maximum and uniform life.
2. The occupancy sensor uses passive infrared technology that reacts to changes in
infrared energy (moving heat) within the coverage area of the sensor. When motion
is detected the luminaire is switched to High Mode. After motion is no longer
detected and the time delay cycle has been completed, the luminaire is returned to
its Low Mode setting.
3. Multi‐Level option available with Photocell option.
4. Multi‐Level options are available for use with Cree Edge Series, LED way Series, 228
Series, 304 Series, XSP Series, CPY Series, OSQ series and VG Series Luminaires.
5. Cree Edge Series Luminaire – Flood
a. Mounting Height – 10 ft. to 30 ft.
b. Optimal Lens Coverage – 40 ft. diameter coverage with a 360° circular pattern
(at 20 ft. mounting height). Lens mounting height to coverage radius ratio is
1:1
c. Voltage: 120‐277 Volts
6. XPS Series – XPSW Wall Mount
a. Maximum Mounting Height – 15 ft.
b. Optimal Lens Coverage – 50 ft. diameter coverage with a 360° circular pattern
(at 10 ft. mounting height). Lens mounting height to coverage radius ratio is
1:2.5
c. Voltage: 120‐277 Volts
7. Five Year Limited Warranty: If Seller determines the Product is defective, Seller will
elect, in its sole discretion, to refund you the purchase price of the Product, repair the
Product or replace the Product. This limited warranty excludes field labor and
service charges related to the repair or replacement of the Product.
B. Watt Stopper Wireless Exterior Lighting Controls
1. Intelligent, fixture mounted control nodes replace traditional twist‐lock photocells
and deliver unprecedented functionality including:
a. Wireless connectivity via self‐healing IP network.
b. Full range 0‐10 volt dimming control.
c. Connection via NEMA standard ANSI C136.41‐2013 twist‐lock.
d. Initiation of self‐contained astronomic and scheduled control events.
e. Compatibility with secure, web‐enabled Building Automation Systems (BAS).
2. Wireless Control Node (NWTL‐111 BULIT® or equivalent) ® is a distributed
intelligence controller designed to replace standard photocell modules on outdoor
Performance Specification – Shasta COE Section 26 0923
48
lighting fixtures. It connects to a 5‐ or 7‐pin twist‐lock receptacle compliant with
NEMA standard C136.41 to provide ON/OFF and dimming control. The BULIT also
connects to a WattStopper Wireless Network Manager via a robust and scalable self‐
healing wireless IP network.
a. Operating voltage: 120/277/347 VAC, single phase
b. Radio: 2.4 GHz IEEE 802.15.4
c. Up to 1000 ft. range between nodes
d. Operating conditions: ‐40 °F to 158 °F (‐40 to 70°C)
3. The Wireless Network Manager and Supervisor are scalable hardware and software
designed to manage exterior lighting control networks. A network consists of at least
one wireless control node, such as the NWTL‐111, and a Network Manager.
Networks can be expanded by adding nodes, and, if needed, more managers.
Network Supervisor software can coordinate control of multiple managers, and
provide long term data storage.
a. Operating voltage: 15 VDC from 120 VAC plug‐in power supply (included) or
auxiliary enclosure.
b. Wired and wireless connectivity for data and user interface.
c. Operating conditions: 32 °F – 122 °F (0 –50 °C); 0% ‐ 90% RH, non‐condensing.
END OF SECTION 26 0923
Performance Specification – Shasta COE Section 26 0943
49
SECTION 26 0943 PLUG LOAD CONTROL SYSTEMS
PART 1 - GENERAL
1.1 SUMMARY A. Related Documents:
1. Drawings and general provisions of the Subcontract apply to this Section.
2. Review these documents for coordination with additional requirements and
information that apply to work under this Section.
B. Section Includes:
1. Plug Load Controls
1.2 RELATED SECTIONS A. Section 27 05 39 ‐ Surface Raceways for Communications Systems.
B. Section 25 55 00 ‐ Integrated Automation Control of HVAC‐ Integrated Automation,
Building integrator shall provide integration of the lighting control system with
Building Automation Systems.
1.3 REFERENCES A. NFPA 70 ‐ National Electrical Code; National Fire Protection Association.
B. NEMA ‐ National Electrical Manufacturers Association
C. FCC emission standards
D. UL ‐ Underwriters Laboratories, Inc. Listings
E. UL 2043 ‐ Standard for Fire Test for Heat and Visible Smoke Release for Discrete
Products Installed in Air‐Handling Spaces.
F. UL 20 ‐ General Use Switches, Plug Load Controls
G. UL 924 ‐ Standard for Emergency Lighting and Power Equipment
H. ULC ‐ Underwriter Laboratories of Canada Listings
1.4 DESIGN / PERFORMANCE REQUIREMENTS A. System shall conform to requirements of NFPA 70.
B. System shall comply with FCC emission standards specified in part 15, sub‐part J for
commercial and residential application.
C. System shall be listed under UL sections 916 and/or 508.
1.5 SUBMITTALS A. Manufacturerʹs Data: Submit catalog cuts and description of each system component.
B. Provide wiring diagrams and installation details for lighting control equipment.
C. Shop Drawings: Submit a complete set of detailed Shop Drawings for the entire
lighting control system; the shop drawings shall include but not be limited to relay
panels with designations and dimensions, daylight sensors locations based on
Performance Specification – Shasta COE Section 26 0943
50
manufacturer’s recommendations, and system components with manufacturer’s part
numbers.
D. Installation Instructions: Submit manufacturerʹs written installation instructions and
wiring diagrams. Instructions shall include recommendations for handling of
equipment and parts, and protection and storage requirements.
1.6 QUALITY ASSURANCE A. Manufacturer Qualifications: Company specializing in manufacturing of centralized
and distributed control systems with a minimum of 10 years documented experience.
B. Installer Qualifications: Company certified by the manufacturer and specializing in
installation of networked control products with minimum three years documented
experience.
C. System Components: Demonstrate that individual components have undergone
quality control and testing prior to shipping.
1.7 DELIVERY, STORAGE, AND HANDLING A. Store products in a clean, dry space in original manufacturerʹs packaging in accordance
with manufacturerʹs written instructions until ready for installation.
1.8 PROJECT CONDITIONS A. Maintain environmental conditions (temperature, humidity, and ventilation) within
limits recommended by manufacturer for optimum results. Do not install products
under environmental conditions outside manufacturerʹs absolute limits.
B. Do not install equipment until following conditions can be maintained in spaces to
receive equipment:
1. Ambient temperature: 32 to 104 degrees F (0 to 40 degrees C).
2. Relative humidity: Maximum 90 percent, non‐condensing.
1.9 WARRANTY A. Manufacturer shall provide a 5 year limited warranty on products within this
installation, except where otherwise noted, and consisting of a one for one device
replacement.
PART 2 - PRODUCTS
2.1 MANUFACTURERS A. Acceptable Manufacturer: WattStopper
2.2 DISTRIBUTED DIGITAL LIGHTING CONTROL SYSTEM A. System General: Provide a WattStopper, complete with all necessary enclosures,
wiring, and system components to ensure a complete and properly functioning system
as indicated on the Drawings and specified herein. If a conflict is identified, between
the Drawing and this Specification, contact the Architect for clarification prior to
proceeding.
Performance Specification – Shasta COE Section 26 0943
51
1. Plug Loads: Provide automatic shut off of non essential plug loads in spaces as
required by the applicable energy code. Provide Automatic‐ON of plug loads
whenever spaces are occupied. For spaces with multiple occupants a single shut
off consistent with the overhead lighting may be used for the area.
B. Equipment Required: Lighting Control and Automation system as defined under this
section covers the following equipment.
1. Digital Plug Load Controllers: Self‐configuring, digitally addressable, single
relay, plenum‐rated application‐specific controllers. Selected models include
integral current monitoring capabilities.
2.3 DIGITAL LOAD CONTROLLERS (PLUG LOAD CONTROLLERS) A. Digital Load Controllers: Digital controllers for lighting zones, fixtures and/or plug
loads automatically bind room loads to the connected control devices in the space
without commissioning or the use of any tools. Provide controllers to match the room
lighting and plug load control requirements. Controllers are simple to install, and do
not have dip switches/potentiometers, or require special configuration for standard
Plug nʹ Go applications. Control units include the following features
1. Automatic room configuration to the most energy‐efficient sequence of
operation based upon the devices in the room.
2. Simple replacement using the default automatic configuration capabilities, a
room controller may be replaced with an off‐the‐shelf device.
3. Multiple room controllers connected together in a local network must
automatically arbitrate with each other, without requiring any configuration or
setup, so that individual load numbers are assigned starting with load 1 to a
maximum of 64, assigned based on each controllerʹs device IDʹs from highest to
lowest.
4. Device Status LEDs to indicate:
a. Data transmission
b. Device has power
c. Status for each load
d. Configuration status
5. Quick installation features including:
a. Standard junction box mounting
b. Quick low voltage connections using standard RJ‐45 patch cable
6. Based on individual configuration, each load shall be capable of the following
behavior on power up following the loss of normal power:
a. Turn on to 100 percent
b. Turn off
c. Turn on to last level
Performance Specification – Shasta COE Section 26 0943
52
7. Each load be configurable to operate in the following sequences based on
occupancy:
a. Auto‐on/Auto‐off (Follow on and off)
b. Manual‐on/Auto‐off (Follow off only)
8. Polarity of each load output shall be reversible, via digital configuration, so that
on is off and off is on.
9. BACnet object information shall be available for the following objects:
a. Load status
b. Schedule state, normal or after‐hours
c. Demand Response enable and disable
d. Room occupancy status
e. Total room lighting and plug loads watts
f. Electrical current
g. Total watts per controller
h. Total room watts/sq ft.
i. Force on/off all loads
10. UL 2043 plenum rated
11. Manual override and LED indication for each load
12. Zero cross circuitry for each load
13. All digital parameter data programmed into an individual room controller or
plug load controller shall be retained in non‐volatile FLASH memory within the
controller itself. Memory shall have an expected life of no less than 10 years.
B. Plug Load Controllers shall include:
1. 120 VAC, 60 Hz rated for 20A total load. Controller carries application‐specific
UL 20 rating for receptacle control.
2. One relay configuration with additional connection for unswitched load
3. Configurable additive time delay to extend plug load time delay beyond
occupancy sensor time delay (e.g. a 10 minute additive delay in a space with a 20
minute occupancy sensor delay ensures that plug loads turn off 30 minutes after
the space is vacated).
4. Factory default operation is Auto‐on/Auto‐off, based on occupancy
5. Real time current monitoring of both switched and un‐switched load (LMPL‐201
only)
6. Switching power supply
a. Simple 150mA ‐ Only 4 100 series devices on a Cat 5e local network
(LMPL‐101)
b. Smart 250mA (LMPL‐201)
7. RJ‐45 DLM local network ports
a. Three RJ‐45 ports (LMPL‐101)
Performance Specification – Shasta COE Section 26 0943
53
b. Four RJ‐45 ports (LMPL‐201)
8. Provide a wireless transmitter that can be connected to any Cat 5e network of the
lighting controls that will communicate the roomʹs occupancy state to
receptacles mounted in the area with integral relays. Binding of the transmitter
to the receptacles shall be accomplished by pressing a test button on the
transmitter, and then a test button on the receptacle.
9. WattStopper product numbers:
a. Plug Load Controllers: LMPL‐101, LMPL‐201.
b. Wireless Transceiver and Receptacles: WRC‐TX‐LM, WRC‐15‐1/2, WRC‐20‐
1/2
PART 3 - EXECUTION
3.1 PREPARATION A. Do not begin installation until measurements have been verified and work areas have
been properly prepared.
B. If preparation is the responsibility of another installer, notify Architect of
unsatisfactory preparation before proceeding.
C. Verify that required pre‐installation meeting specified in Part 1 of this specification has
been completed, recorded meeting minutes have been distributed and all outstanding
issues noted have been resolved prior to the start of installation.
3.2 INSTALLATION A. Install system in accordance with the approved system shop drawings and
manufacturerʹs instructions.
B. Install all room/area devices using manufacturerʹs factory‐tested Cat 5e cable with pre‐
terminated RJ‐45 connectors.
1. If pre‐terminated cable is not used for room/area wiring, each field‐terminated
cable shall be tested following installation and testing results submitted to the
Manufacturerʹs Representative for approval prior to proceeding with the Work.
2. If fixtures have internal DLM Control Modules, ensure that they are also
connected with Cat 5e cable.
3. Install all room to room network devices using manufacturer‐supplied LM‐
MSTP network wire or wireless devices. Network wire substitution is not
permitted and may result in loss of product warranty.
4. Low voltage wiring topology must comply with manufacturerʹs specifications.
5. Route network wiring as indicated on the Drawings as closely as possible.
Document final wiring location, routing and topology on as built drawings.
C. All line voltage connections shall be tagged to indicate circuit and switched legs.
D. Test all devices to ensure proper communication.
E. Calibrate all sensor time delays and sensitivity to guarantee proper detection of
occupants and energy savings. Adjust time delay so that controlled area remains
lighted while occupied.
Performance Specification – Shasta COE Section 26 0943
54
F. Provide written or computer‐generated documentation on the configuration of the
system including room by room description including:
1. Sensor parameters, time delays, sensitivities, and daylighting setpoints.
2. Sequence of operation, (e.g. manual ON, Auto OFF. etc.)
3. Load Parameters (e.g. blink warning, etc.)
G. Post start‐up tuning ‐ Adjust sensor time delays and sensitivities to meet the Ownerʹs
requirements 30 days from beneficial occupancy. Provide a detailed report to the
Architect / Owner of post start‐up activity.
H. Tighten all panel Class I conductors from both circuit breaker and to loads to torque
ratings as marked on enclosure UL label.
I. All Class II cabling shall enter enclosures from within low‐voltage wiring areas and
shall remain within those areas. No Class I conductors shall enter a low‐voltage area.
J. Run separate neutrals for any phase dimmed branch load circuit. Different types of
dimming loads shall have separate neutral.
K. Verify all non‐panel‐based lighting loads to be free from short circuits prior to
connection to room controllers.
3.3 FIELD QUALITY CONTROL A. Manufacturerʹs Field Service: Engage a factory‐authorized service representative to
inspect components, assemblies, and equipment installations, including connections,
and to assist in testing. Notify Architect and Manufacturer in writing a minimum of 3
weeks prior to system start‐up and testing.
B. Tests and Inspections: Manufacturerʹs service representative shall perform the
following inspections and prepare reports.
1. Verify Class I and II wiring connections are terminated properly by validating
system performance.
2. Set IP addresses and other network settings of system front end hardware per
facilities IT instructions.
3. Verify / complete task programming for all switches, dimmers, time clocks, and
sensors.
4. Verify that the control of each space complies with the Sequence of Operation.
5. Correct any system issues and retest..
C. Provide a report in table format with drawings, or using a software file that can be
opened in the manufacturerʹs system software including each room or space that has
lighting control installed. Indicate the following:
1. Date of test or inspection.
2. Loads per space, or Fixture Address identification.
3. Quantity and Type of each device installed
4. Reports providing each deviceʹs settings.
END OF SECTION 26 0943
Performance Specification – Shasta COE Section 26 5119
55
SECTION 26 5119 LED INTERIOR LIGHTING
PART 1 - GENERAL
1.1 SUMMARY A. Related Documents:
1. General provisions of the Subcontract apply to this Section.
2. Review these documents for coordination with additional requirements and
information that apply to work under this Section.
B. Section Includes:
1. Interior 4’ LED bypass lamps.
2. Interior LED luminaires
3. LED drivers
4. A‐Shape LED lamps
C. Related Sections:
1. Division 01 Section, General Requirements.
2. Division 01 Section, Special Procedures.
3. Division 26 Section, Common Work Results for Electrical.
4. Division 26 Section, Electrical Conduit.
5. Division 26 Section, Boxes for Electrical Systems.
6. Division 26 Section, Wiring Devices.
1.2 REFERENCES A. General:
1. The following documents form part of the Specifications to the extent stated. Where
differences exist between codes and standards, the one affording the greatest
protection shall apply.
2. Unless otherwise noted, the referenced standard edition is the current one at the
time of commencement of the Work.
3. Refer to Division 01 Section, General Requirements for the list of applicable
regulatory requirements.
4. Refer to Division 26 Section, Common Results for Electrical for codes and standards,
and other general requirements.
B. IES – Illuminating Engineering Society
1. LM‐79 – Electrical and Photometric Measurements of Solid‐State Lighting Products.
2. LM‐80 – Measuring Lumen Maintenance of LED Light Sources.
3. TM‐21 – Projecting Long Term Lumen Maintenance of LED Light Sources.
Performance Specification – Shasta COE Section 26 5119
56
C. ANSI – American National Standards Institute:
1. ANSI/NFPA 101 – Life Safety Code.
2. ANSI/NFPA 70 – National Electrical Code.
3. ANSI C78.377 – Specifications for the Chromaticity of Solid State Lighting Products.
D. NEMA – National Electrical Manufacturers Association:
1. NEMA WD 6 – Wiring Devices Dimensional Requirements.
E. UL – Underwriters Laboratories:
1. UL 1598 – Standard for Luminaires.
2. UL 8750 – Light Emitting Diode Equipment for Use in Lighting Products.
F. California Title 24, Non‐Residential Lighting: Section 130.
1. California Building Code (CBC).
2. California Electrical Code (CEC).
G. OSHA Illumination Standards
1.3 DEFINITIONS A. CCT: Correlated color temperature.
B. CRI: Color Rendering Index.
C. Fixture: See ʺLuminaire.ʺ
D. IP: International Protection or Ingress Protection Rating.
E. LED: Light emitting diode.
F. Lumen: Measured output of lamp and luminaire, or both.
G. Luminaire: Complete lighting unit, including lamp, reflector, and housing.
1.4 PERFORMANCE REQUIREMENTS A. All lighting products as herein after specified shall be a standard product of the
manufacturer, and shall consist of components that will be readily available for future
replacement for a period of five years.
B. Provide all lighting LED lamps as shown complete with all hardware necessary to install
lamps.
C. Luminaire shall be free of light leaks.
D. All wiring shall be adequate for LEDs lamps and Voltage requirements.
1.5 SUBMITTALS A. Submit under provisions of Division 26 Section, Common Results for Electrical and
Division 01 Section, General Requirements.
B. Product Data: Submit catalog cuts, drawings, descriptive matter, and lighting
performance characteristics as required to completely define the materials and
construction details employed, finishes applied, dimensions, hinging, and electrical
characteristics.
C. Manufacturerʹs Instructions: Include instructions for storage, handling, protection,
examination, preparation, and installation of product.
D. Project Record Documents: Accurately record actual locations of each lamp.
Performance Specification – Shasta COE Section 26 5119
57
1.6 QUALITY ASSURANCE A. Products shall be tested, approved, and labeled/listed by Underwriters Laboratories, Inc.,
or by a Nationally Recognized Testing Laboratory (NRTL) as listed in Division 26 Section,
Common Work Results for Electrical.
B. Electrical equipment and materials shall be new and within one year of manufacture,
complying with the latest codes and standards. No used, re‐built, refurbished and/or re‐
manufactured electrical equipment and materials shall be furnished on this project.
1.7 DELIVERY, STORAGE, AND HANDLING A. Deliver lamps individually in factory fabricated fireboard type containers.
B. Handle lamps carefully to prevent breakage.
C. Store product in clean, dry space, protected from weather.
1.8 WARRANTY A. Manufacturers standard form in which manufacturer of LED’s agrees to replace
components that fails in materials or workmanship within specified warranty period.
1. LED lamps: Five years from date of substantial completion.
PART 2 - PRODUCTS
2.1 GENERAL A. Descriptions, type letters, manufacturersʹ names, and general characteristics are shown on
the drawings. Manufacturersʹ names noted are for defining quality of construction only
and do not limit other manufacturersʹ products.
B. Special Adapters, Plates, Brackets, and Anchors: Provide where required by construction
features of the building to suitably mount lighting fixtures; all such appurtenances and
mounting methods approved by the Owner prior to fabrication and installation.
2.2 MANUFACTURERS A. Keystone Technologies.
B. Ledtronics, Inc.
C. Hyperikon, Inc.
D. Cree.
E. RAB Lighting.
F. Philips
G. GE.
H. Lithonia.
I. Sylvania
J. Substitutions: Under provisions of Division 01 Section, General Requirements.
2.3 LIGHT EMITTING DIODE (LED) BYPASS LAMPS A. Provide design information including lumen output and design life in lamp schedule on
project plans for LED lamps.
B. Lamps must have a minimum L70 lumen maintenance value of 45,000 hours as calculated
by IES TM‐21, with data obtained per IES LM‐80 requirements.
C. Luminaires must be tested to IES LM‐79 and IES LM‐80 standards.
Performance Specification – Shasta COE Section 26 5119
58
D. Electrical Contractor is responsible for reviewing all re‐lamping and retrofitting
arrangements prior to ordering any products. Electrical Contractor is responsible for
ordering all of the proper lamps and miscellaneous fasteners to complete project.
2.4 LED DRIVER A. LED driver shall be installed in an electrical enclosure.
B. Wiring inside enclosure shall comply 600V/105 degrees rating or higher.
C. LED driver shall comply with UL standard 8750.
D. LED driver shall have Class A sound rating.
E. LED driver shall be UL certified for use in a dry or damp location.
F. LED driver shall tolerate sustained open circuit and short circuit output conditions without
damage.
2.5 LIGHT EMITTING DIODE (LED) LUMINAIRES A. Provide luminaires with complete power supplies (drivers) and light sources.
B. Provide design information including lumen output and design life in luminaire schedule
on project plans for LED luminaires.
C. Interior High Bay LED luminaires must have a minimum luminaire efficacy of 110 LPW
(lumens per watt) and a minimum Color Rendering Index (CRI) of 70.
D. Luminaires must have a minimum L70 lumen maintenance value of 50,000 hours as
calculated by IES TM‐21, with data obtained per IES LM‐80 requirements.
E. The maximum re‐lamping rated wattage of a luminaire shall be listed on a permanent,
preprinted, factory installed label, as specified by UL 1574, 1598, 2108, or 8750, as
applicable.
F. Luminaires must be tested to IES LM‐79 and IES LM‐80 standards.
G. Luminaire shall have door frame and lens with LED arrays and integral airflow ventilation
system.
H. The light distribution pattern of the luminaires shall be suitable for a S/H ratio of
approximately 1.8.
I. The lighting system shall consist of the type and manufacturer as shown on the drawings
or approved equal. If other than fixture shown is submitted, complete illumination
calculations are required to show equality.
J. Electrical Contractor is responsible for reviewing all mounting arrangements prior to
ordering any products. Electrical Contractor is responsible for ordering all of the proper
fixtures, mounting hardware, and miscellaneous fasteners to complete project.
K. All exposed portions (permanent or adjustable) of fixtures to be finished by the
manufacturer in a finish as specified.
L. Fixtures shall come pre‐assembled and complete with all sockets, lamp ends, ballasts,
transformers, fixture ends, trim rings, plates, and low density mounting kits (as required)
for a complete installation.
2.6 A-SHAPE LED LAMPS A. ECM proposes replacement of existing CFL and incandescent lamps with new, lower
wattage LED A‐shape lamps, or equivalent.
B. Lamps shall be either pin‐based or screw‐in lamps that plug‐and‐play in the existing
fixtures, with the option of pin‐based adapter plugs, where necessary.
Performance Specification – Shasta COE Section 26 5119
59
C. It is recommended that prior to a full‐scale retrofit, pilot measures be done in various
representative areas to determine if light levels are adequate.
PART 3 - EXECUTION
3.1 INSTALLATION, GENERAL REQUIREMENTS A. Fixture Location: Locations shown are approximate only. Install at locations shown on
architectural drawings.
3.2 INDOOR INSTALLATION A. Linear LED Lamps
1. Remove existing linear fluorescent lamps. Follow Local, State, Federal, and industry
recommended guidelines associated with storage, transport, and waste disposal of
lamps and ballasts.
2. Clean the existing fixtures, including all reflective surfaces inside the fixture and
lens. Use an approved cleansing agent that is non‐toxic. Wherever specified, replace
old lenses with new clear prismatic acrylic lenses.
3. Install new LED direct drive tubes in place of existing T8 or T12 fluorescent lamps,
rewire line voltage directly to lamp holders. If the current lamp holders are shunted,
remove them and replace them with non‐shunted lamp holders.
4. Prior to a full‐scale retrofit measure, a pilot measure should be performed to verify
the performance of the new LED system.
5. Conduct retrofits so as to preserve existing switching arrangements. For instance,
newer buildings are typically designed for multi‐level lighting using A/B circuits.
Where fixtures are tandem wired, apply ʺTandemʺ stickers for the benefit of future
maintenance staff, to indicate the location of the ballast.
B. LED Luminaires
1. Install in accordance with manufacturer’s instructions.
2. Install suspended luminaires using pendants supported from swivel hangers.
Provide pendant length required to suspend luminaire at indicated height.
3. Install accessories furnished with each luminaire.
4. Connect luminaires to branch circuit outlets provided under Division 26 Section,
Boxes for Electrical Systems using flexible conduit or as indicated on the drawings.
5. Make wire connections within fixtures using solderless connectors as specified;
automatic splicing devices or connectors will not be allowed. Make wiring
connections to branch circuit using building wire with insulation suitable for
temperature conditions within luminaire.
6. Bond products and metal accessories to branch circuit equipment grounding
conductor.
C. A‐Shape LED Lamps
1. For each lamp to be replaced, confirm the fixture socket type.
2. Remove any existing screws‐in lighting fixtures.
3. Install new low wattage screw‐in or pin‐based LED lamps in their place.
Performance Specification – Shasta COE Section 26 5119
60
4. Take lighting measurements before and after to confirm that the new lighting system
meets or exceeds original lighting levels.
3.3 FIELD QUALITY CONTROL A. Operate each luminaire after re‐lamping. Inspect for improper connections and operation.
B. Measure illumination levels to verify conformance with performance requirements.
3.4 ADJUSTING A. Aim and adjust luminaires to provide illumination levels and distribution indicated on the
drawings.
3.5 CLEANING A. Clean electrical parts to remove conductive and deleterious materials.
B. Remove dirt and debris from enclosure.
C. Clean photometric control surfaces as recommended by manufacturer.
D. Clean finishes and touch up damage.
E. Clean lighting control elements, lamps, fixture interiors, and exposed exterior surfaces
thoroughly before requesting final inspection.
3.6 DIFFUSERS AND ENCLOSURES A. Install lighting fixture diffusers and enclosures only after construction work, painting, and
clean up are completed. Handle with clean white canvas gloves.
PART 4 - MATERIAL SCHEDULE
4.1 INTERIOR LINEAR LED BYPASS LAMPS (MEASURE L-1) A. Keystone Technologies Direct Drive LED lamps (18 watts or equivalent)
1. Bare Lamp Wattage: 18 watts
2. Input Voltage: 120 – 277 V
3. CCT: 5000 K
4. Initial Lumens: 2,000 Lumens
5. Efficacy (LPW): 111 Lumens Per Watt
6. Lifetime: 50,000 hours
7. Five Year Warranty.
B. Ledtronics 4 ft. LED lamps (18 watts or equivalent)
1. Bare Lamp Wattage: 18 watts
2. Input Voltage: 120 – 277 V
3. CCT: 5000 K
4. Initial Lumens: 1,800 Lumens
5. Efficacy (LPW): 100 Lumens Per Watt
6. Lifetime: 50,000 hours
7. Five Year Warranty.
Performance Specification – Shasta COE Section 26 5119
61
D. Hyperikon 4 ft. LED T8 lamps (18 watts or equivalent)
1. Bare Lamp Wattage: 18 watts
2. Input Voltage: 120 – 277 V
3. CCT: 5000 K
4. Initial Lumens: 2,016 Lumens
5. Efficacy (LPW): 112 Lumens Per Watt
6. Lifetime: 45,000 hours
7. Five Year Warranty.
4.2 A-SHAPE LED LAMPS (OR EQUIVALENT) (MEASURE L-4) A. Philips A‐Shape LED Lamps
1. Bare Lamp Wattage: 8 watts (13W CFL replacement), 9.5 watts (100W incandescent
replacement), 22 Watts (42 CFL Replacement)
2. Input Voltage: 120 V
3. CCT: 5000 K
4. Initial Lumens: 800 Lumens (8 watts) , 1000 (9.5 watts), 2,200 (22 watts).
5. Efficacy (LPW): 100 Lumens Per Watt (8 watts) and 105 Lumens Per Watt.
6. Lifetime: 10,950 hours.
B. Cree A‐Shape LED Lamps
1. Bare Lamp Wattage: 8.5 watts (13W CFL replacement) and 10.2 watts (100W
incandescent replacement).
2. CCT: 5000 K
3. Initial Lumens: 820 Lumens (8.5 watts) and 1150 (10.2 watts).
4. Efficacy (LPW): 96 Lumens Per Watt (8.5 watts) and 112 Lumens Per Watt (10.2
watts).
5. Lifetime: 25,000 hours.
C. Sylvania A‐Shape LED Lamps
1. Bare Lamp Wattage: 8.5 watts (13W CFL replacement) and 9.5 watts (100W
incandescent replacement).
2. Input Voltage: 120 V
3. CCT: 5000 K
4. Initial Lumens: 800 Lumens (8.5 watts) and 1100 (9.5 watts).
5. Efficacy (LPW): 94 Lumens Per Watt (8.5 watts) and 115 Lumens Per Watt (9.5
watts).
6. Lifetime: 25,000 hours.
END OF SECTION 26 5119
Performance Specification – Shasta COE Section 26 5619
62
SECTION 26 5619 EXTERIOR LIGHTING
PART 1 - GENERAL
1.1 SUMMARY A. Related Documents:
1. General provisions of the Subcontract apply to this Section.
2. Review these documents for coordination with additional requirements and
information that apply to work under this Section.
B. Section Includes:
1. Outdoor LED luminaire.
2. LED drivers.
3. A‐Shape LED Lamps
C. Related Sections:
1. Division 01 Section, General Requirements.
2. Division 01 Section, Special Procedures.
3. Division 03 Section, Cast‐in‐Place Concrete.
4. Division 26 Section, Common Work Results for Electrical.
5. Division 26 Section, Electrical Conduit.
6. Division 26 Section, 600 Volt Conductors and Cable.
7. Division 26 Section, Boxes for Electrical Systems.
8. Division 26 Section, Wiring Devices.
1.2 REFERENCES A. General:
1. The following documents form part of the Specifications to the extent stated. Where
differences exist between codes and standards, the one affording the greatest
protection shall apply.
2. Unless otherwise noted, the referenced standard edition is the current one at the
time of commencement of the Work.
3. Refer to Division 01 Section, General Requirements for the list of applicable
regulatory requirements.
4. Refer to Division 26 Section, Common Results for Electrical for codes and standards,
and other general requirements.
B. IES – Illuminating Engineering Society
1. RP‐33‐99 – Recommended Practices for Exterior Environmental Lighting.
2. LM‐79 – Electrical and Photometric Measurements of Solid State Lighting Products.
3. LM‐80 – Measuring Lumen Maintenance of LED Light Sources.
4. TM‐15 – Luminaire Classification System for Outdoor Luminaires.
5. TM‐21 – Projecting Long Term Lumen Maintenance of LED Light Sources.
Performance Specification – Shasta COE Section 26 5619
63
C. ANSI – American National Standards Institute:
1. ANSI/NFPA 101 – Life Safety Code.
2. ANSI/NFPA 70 – National Electrical Code.
3. ANSI C78.377 – Specifications for the Chromaticity of Solid State Lighting Products.
4. ANSI C136.25‐2013 – Roadway and Area Lighting Equipment ‐ Ingress Protection
(resistance to Dust, Solid Objects and Moisture) for Luminaire Enclosures.
D. NEMA – National Electrical Manufacturers Association:
1. NEMA WD 6 – Wiring Devices Dimensional Requirements.
E. UL – Underwriters Laboratories:
1. UL 1598 – Standard for Luminaires.
2. UL 8750 – Light Emitting Diode Equipment for Use in Lighting Products.
F. California Title 24, Non‐Residential Lighting: Section 130.
1. California Building Code (CBC).
2. California Electrical Code (CEC).
G. International Electrotechnical Commission (IEC) 60529 – Degrees of Protection Provided
by Enclosures.
H. OSHA Illumination Standards
1.3 DEFINITIONS A. CCT: Correlated color temperature.
B. CRI: Color Rendering Index.
C. Fixture: See ʺLuminaire.ʺ
D. LED: Light emitting diode.
E. Lumen: Measured output of lamp and luminaire, or both.
F. Luminaire: Complete lighting unit, including lamp, reflector, and housing.
1.4 PERFORMANCE REQUIREMENTS A. All lighting products as herein after specified shall be a standard product of the
manufacturer, and shall consist of components that will be readily available for future
replacement for a period of five years.
B. Provide all lighting fixtures as shown complete with all hardware necessary to install
fixtures.
C. Luminaire shall be free of light leaks.
D. Luminaire suitable for use in maximum ambient temperatures of 35 °C (95 °F) and
minimum ambient temperature of 0 °C (32 °F).
E. All wiring shall be adequate for LEDs, Driver, and Voltage requirements.
F. Luminaire suitable for wet locations.
1.5 SUBMITTALS A. Submit under provisions of Division 26 Section, Common Results for Electrical and
Division 01 Section, General Requirements.
Performance Specification – Shasta COE Section 26 5619
64
B. Product Data: Submit catalog cuts, drawings, descriptive matter, and lighting
performance characteristics as required to completely define the materials and
construction details employed, finishes applied, dimensions, hinging, latching and re‐
lamping provisions, and electrical characteristics.
C. Manufacturerʹs Instructions: Include instructions for storage, handling, protection,
examination, preparation, and installation of product.
D. Project Record Documents: Accurately record actual locations of each luminaire.
1.6 QUALITY ASSURANCE A. Products shall be tested, approved, and labeled/listed by Underwriters Laboratories, Inc.,
or by a Nationally Recognized Testing Laboratory (NRTL) as listed in Division 26 Section,
Common Work Results for Electrical.
B. Electrical equipment and materials shall be new and within one year of manufacture,
complying with the latest codes and standards. No used, re‐built, refurbished and/or re‐
manufactured electrical equipment and materials shall be furnished on this project.
1.7 DELIVERY, STORAGE, AND HANDLING A. Deliver luminaires individually in factory fabricated fireboard type containers.
B. Handle luminaires carefully to prevent breakage, denting, and scouring of the luminaire
finish.
C. Store product in clean, dry space, protected from weather.
1.8 WARRANTY A. Manufacturers standard form in which manufacturer of LED’s and drivers agrees to
replace components that fails in materials or workmanship within specified warranty
period.
1. LED arrays: Five years from date of substantial completion.
PART 2 - PRODUCTS
2.1 GENERAL A. Descriptions, type letters, manufacturersʹ names, and general characteristics are shown on
the drawings. Manufacturersʹ names noted are for defining quality of construction only
and do not limit other manufacturersʹ products.
B. Metal Parts of Exterior Fixtures: Corrosion resisting metal, (non‐ferrous or stainless steel)
and in all cases, suitable for outdoor service without tarnishing or other damage due to
exposure; manufacturerʹs standard colors, unless specified otherwise; cadmium plate all
metal parts concealed by canopies, including screws, plates and brackets.
C. Special Adapters, Plates, Brackets, and Anchors: Provide where required by construction
features of the building to suitably mount lighting fixtures; all such appurtenances and
mounting methods approved by the University prior to fabrication and installation.
D. Lighting fixtures replacement shall not require removal or alteration to a permanent
section of the structure i.e. permanent ceiling. Fixtures shall be easily replaceable otherwise
a different type of fixture should be provided.
Performance Specification – Shasta COE Section 26 5619
65
2.3 MANUFACTURERS A. Cree.
B. Current powered by GE.
C. Lithonia Lighting.
D. Philips
E. Sylvania
F. Substitutions: Under provisions of Division 01 Section, General Requirements.
2.4 LED DRIVER A. LED driver shall be installed in an electrical enclosure.
B. Wiring inside enclosure shall comply 600V/105 degrees rating or higher.
C. LED driver shall comply with UL standard UL 8750.
D. LED driver shall have Class A sound rating.
E. LED driver shall be UL certified for use in a dry or damp location.
F. LED driver shall tolerate sustained open circuit and short circuit output conditions without
damage.
2.5 LIGHT EMITTING DIODE (LED) LUMINAIRES A. Provide luminaires with complete power supplies (drivers) and light sources.
B. Provide design information including lumen output and design life in luminaire schedule
on project plans for LED luminaires.
C. Outdoor high output LED luminaires must have a minimum luminaire efficacy of 90 LPW
(lumens per watt) and a minimum color rendering index (CRI) of 70.
D. Luminaires must have a minimum L70 lumen maintenance value of 50,000 hours as
calculated by IES TM‐21, with data obtained per IES LM‐80 requirements.
E. Luminaires must be tested to IES LM‐79 and IES LM‐80 standards.
F. Outdoor luminaires shall have provisions for house side shield to prevent glare to uphill
neighbors.
G. Luminaire shall have door frame and lens with LED arrays and integral airflow ventilation
system.
H. The light distribution pattern of the luminaires shall be suitable for a S/H ratio of
approximately 1.8.
I. Pole mounted lights shall have in line/in pole fusing.
J. The lighting system shall consist of the type and manufacturer as shown on the drawings
or approved equal. If other than fixture shown is submitted, complete illumination
calculations are required to show equality.
K. Electrical Contractor is responsible for reviewing all mounting arrangements prior to
ordering any products. Electrical Contractor is responsible for ordering all of the proper
fixtures, mounting hardware, and miscellaneous fasteners to complete project. Fixtures to
be secured to the structure from a minimum of two points, at opposing ends of the fixture
when ceiling recessed or surface mounted.
L. All exposed portions (permanent or adjustable) of fixtures to be finished by the
manufacturer in a finish as specified.
M. Fixtures shall come pre‐assembled and complete with all sockets, lamp ends, ballasts,
transformers, fixture ends, trim rings, plates, and low density mounting kits (as required)
for a complete installation.
Performance Specification – Shasta COE Section 26 5619
66
N. Luminaire should have IP66 rate optical enclosure per ANSI C136.25‐2013, Roadway and
Area Lighting Equipment ‐ Ingress Protection (resistance to Dust, Solid Objects and
Moisture) for Luminaire Enclosures.
2.6 A-SHAPE LED LAMPS A. ECM proposes replacement of existing CFL and incandescent lamps with new, lower
wattage LED A‐shape lamps, or equivalent.
B. Lamps shall be either pin‐based or screw‐in lamps that plug‐and‐play in the existing
fixtures, with the option of pin‐based adapter plugs, where necessary.
C. It is recommended that prior to a full‐scale retrofit, pilot measures be done in various
representative areas to determine if light levels are adequate.
PART 3 - EXECUTION
3.1 INSTALLATION, GENERAL REQUIREMENTS A. Fixture Location: Locations shown are approximate only. Install at locations shown on
architectural drawings and as required to coordinate with tile patterns, architectural
features, and Mechanical Work.
3.2 OUTDOOR INSTALLATION A. Install in accordance with manufacturersʹ instructions.
B. Install lighting poles at locations indicated.
C. Install poles plumb. Provide double nuts to adjust plumb. Grout around each base.
D. Install lamps in each luminaire.
E. Fasten luminaire to structural support.
F. Supports:
1. Sized and rated for luminaire weight.
2. Able to maintain luminaire position after cleaning and re‐lamping.
3. Support luminaires without causing deflection of finished surface.
4. Luminaire mounting devices shall be capable of supporting a horizontal force of 100
percent of luminaire weight and a vertical force of 400 percent of luminaire weight.
G. Wall Mounted Luminaire Support:
1. Attached to structural members in walls.
H. Bond luminaires, metal accessories, and metal poles to branch circuit equipment
grounding conductor or provide supplementary grounding electrode at each pole as
shown on the drawings.
I. Coordinate layout and installation of luminaires with other construction.
J. Comply with requirements in Division 26 Section, Low Voltage Electrical Power
Conductors and Cables and Section, Raceways and Boxes for Electrical Systems for wiring
connections and wiring methods.
3.3 FIELD QUALITY CONTROL A. Operate each luminaire after installation and connection. Inspect for improper connections
and operation.
B. Measure illumination levels to verify conformance with performance requirements.
Performance Specification – Shasta COE Section 26 5619
67
C. Take measurements during night sky, without moon, or with heavy overcast clouds
effectively obscuring moon.
D. Operational Test: After installing luminaires, switches, and accessories, and after electrical
circuitry has been energized, test units to confirm proper operation.
E. Luminaire will be considered defective if it does not pass tests and inspections.
3.4 ADJUSTING A. Aim and adjust luminaires to provide illumination levels and distribution indicated on the
drawings.
B. Re‐lamp luminaires which have failed lamps at Date of Substantial Completion.
3.5 CLEANING A. Clean electrical parts to remove conductive and deleterious materials.
B. Remove dirt and debris from enclosure.
C. Clean photometric control surfaces as recommended by manufacturer.
D. Clean finishes and touch up damage.
E. Clean lighting control elements, lamps, fixture interiors, and exposed exterior surfaces
thoroughly before requesting final inspection.
3.6 DIFFUSERS AND ENCLOSURES A. Install lighting fixture diffusers and enclosures only after construction work, painting, and
clean up are completed. Handle with clean white canvas gloves.
3.7 A-SHAPE LED LAMPS 1. For each lamp to be replaced, confirm the fixture socket type.
2. Remove any existing screws‐in lighting fixtures.
3. Install new low wattage screw‐in or pin‐based LED lamps in their place.
4. Take lighting measurements before and after to confirm that the new lighting system
meets or exceeds original lighting levels.
PART 4 - MATERIAL SCHEDULE
4.1 EXTERIOR 70 WATT HIGH PRESSURE SODIUM AND 100 WATT METAL HALIDE TO LED FIXTURE REPLACEMENT (MEASURE L-6A)
A. Cree Edge Series LED Wall Pack Luminaire (37 watts or equivalent)
1. Replacement for 70 watt high pressure sodium fixtures.
2. Input Wattage: 37 watts
3. Input Voltage: 120 – 277 V
4. CCT: 4000 K (+/‐ 300 K)
5. Minimum CRI: 70+
6. Initial Lumens: 3,310 Lumens (4000 K)
7. Lumens Per Watt (LPW): 90 LPW
8. Temperature rated at 5 °C (41 °F) to 25 °C (77 °F)
9. IP66 rate optical enclosure per IEC 60529
10. Lifetime: 100,000 hours
11. Ten Year Limited Warranty: If Seller determines the Product is defective, Seller will
elect, in its sole discretion, to refund you the purchase price of the Product, repair the
Performance Specification – Shasta COE Section 26 5619
68
Product or replace the Product. This limited warranty excludes field labor and
service charges related to the repair or replacement of the Product.
B. Lithonia Lighting D‐Series LED Wall Luminaire (36 watts or equivalent)
1. Replacement for 70 watt high pressure sodium fixtures.
2. Input Wattage: 36 watts
3. Input Voltage: 120 – 277 V
4. CCT: 4000 K
5. Minimum CRI: 70+
6. Initial Lumens: 4,079 Lumens (4000 K)
7. Lumens Per Watt (LPW): 113 LPW
8. Temperature rated at ‐40 °C (‐40 °F) to 32 °C (104 °F)
9. Lifetime: 100,000 hours
10. Warranty: Commercial LED fixtures, including the LED arrays and the LED drivers,
to be free from defect in material and workmanship for a period of five years from
the date of shipment.
C. GE Evolve Series EWS3 LED Wall Pack (32 watts or equivalent)
1. Replacement for 70 watt high pressure sodium fixtures.
2. Input Wattage: 32 watts
3. Input Voltage: 120 – 277 V
4. CCT: 4000 K
5. Minimum CRI: 70+
6. Initial Lumens: 3,800 Lumens (4000 K)
7. Lumens Per Watt (LPW): 128 LPW
8. Temperature rated at –40 °C (‐40 °F) to 50 °C (122 °F)
9. Lifetime: 50,000 hours
10. Warranty: LED Luminaires purchased directed from GE to be free from defects in
material and workmanship unit the earlier of (1) Five years, and (2) 22,000 hours. If a
Product fails to meet this warrant, the GE will at its option, either (1) repair the
defective Product, (2) provide a free replacement product or replacement parts, or (3)
refund the purchase price paid to GE of the Product or replacement parts.
4.2 EXTERIOR 70 WATT HIGH PRESSURE SODIUM AND 100 WATT METAL HALIDE TO LED FIXTURE REPLACEMENT (MEASURE L-6A)
A. Cree Edge Series LED Canopy Luminaire (46 watts or equivalent)
1. Replacement for 70 watt high pressure sodium fixtures.
2. Input Wattage: 46 watts
3. Input Voltage: 120 – 480 V
4. CCT: 4000 K (+/‐ 300 K)
5. Minimum CRI: 70+
6. Initial Lumens: 4,054 Lumens (4000 K)
7. Lumens Per Watt (LPW): 88 LPW
8. Temperature rated at 5 °C (41 °F) to 25 °C (77 °F)
9. IP66 rate optical enclosure per IEC 60529
Performance Specification – Shasta COE Section 26 5619
69
10. Lifetime: 100,000 hours
11. Ten Year Limited Warranty
B. Lithonia Lighting VRC LED Canopy Luminaire (41 watts or equivalent)
1. Replacement for 70 watt high pressure sodium fixtures.
2. Input Wattage: 41 watts
3. Input Voltage: 120 – 277 V
4. CCT: 5000 K
5. Minimum CRI: 70+
6. Initial Lumens: 3,389 Lumens (5000 K)
7. Lumens Per Watt (LPW): 82 LPW
8. Temperature rated at ‐40 °C (‐40 °F) to 32 °C (104 °F)
9. Lifetime: 100,000 hours
10. Five Year Limited Warranty
C. GE Evolve Series ECBB LED Canopy Luminaire (35 watts or equivalent)
1. Replacement for 70 watt high pressure sodium fixtures.
2. Input Wattage: 35 watts
3. Input Voltage: 120 – 277 V
4. CCT: 5000 K
5. Minimum CRI: 70+
6. Initial Lumens: 4,230 Lumens (5000 K)
7. Lumens Per Watt (LPW): 120 LPW
8. Temperature rated at –40 °C (‐40 °F) to 50 °C (122 °F)
9. Five Year Limited Warranty
4.3 EXTERIOR 150 WATT HIGH PRESSURE SODIUM AND 150 WATT METAL HALIDE TO LED FIXTURE REPLACEMENT (MEASURE L-6A)
A. Cree Edge Series LED Wall Pack Luminaire (66 watts or equivalent)
1. Replacement for 150 watt high pressure sodium and 150 watt metal halide fixtures.
2. Input Wattage: 66 watts
3. Input Voltage: 120 – 480 V
4. CCT: 5700 K (+/‐ 500 K)
5. Minimum CRI: 70+
6. Initial Lumens: 6,584 lumens for 150‐watt HPS and 7,012 lumens for 150‐watt MH
(5700 K)
7. Lumens Per Watt (LPW): 100 LPW and 106 LPW, respectively
8. Temperature rated at 5 °C (41 °F) to 25 °C (77 °F)
9. IP66 rate optical enclosure per IEC 60529
10. Ten Year Limited Warranty
B. Lithonia Lighting D‐Series LED Wall Luminaire (73 watts or equivalent)
1. Replacement for 150 watt high pressure sodium and 150 watt metal halide fixtures.
2. Input Wattage: 73 watts
3. Input Voltage: 120 – 480 V
Performance Specification – Shasta COE Section 26 5619
70
4. CCT: 4000 K
5. Minimum CRI: 70+
6. Initial Lumens: 6,896 lumens for 150‐watt HPS and 7,373 lumens for 150‐watt MH
(4000 K)
7. Lumens Per Watt (LPW): 94 LPW and 101 LPW, respectively
8. Temperature rated at ‐40 °C (‐40 °F) to 32 °C (104 °F)
9. Lifetime: 100,000 hours
10. Five Year Limited Warranty
C. GE Evolve Series EWNB LED Wall Pack (70 watts or equivalent)
1. Replacement for 150 watt high pressure sodium and 150 watt metal halide fixtures.
2. Input Wattage: 70 watts
3. Input Voltage: 120 – 480 V
4. CCT: 3000 K
5. Minimum CRI: 70+
6. Initial Lumens: 7,500 Lumens (3000 K)
7. Lumens Per Watt (LPW): 107 LPW
8. Temperature rated at –40 °C (‐40 °F) to 50 °C (122 °F)
9. Lifetime: 50,000 hours
10. Five Year Limited Warranty
4.4 EXTERIOR 250 WATT METAL HALIDE AND 250 WATT HIGH PRESSURE SODIUM TO FLOOD LED FIXTURE REPLACEMENT (MEASURE L-6A)
A. Cree Edge Series LED Flood Luminaire (130 watts or equivalent)
1. Replacement for 250 watt metal halide fixtures.
2. Input Wattage: 130 watts
3. Input Voltage: 120 – 277 V
4. CCT: 4000 K (+/‐ 300 K)
5. Minimum CRI: 70+
6. Initial Lumens: 15,762 Lumens (4000 K)
7. Lumens Per Watt (LPW): 121 LPW
8. Temperature rated at 5 °C (41 °F) to 25 °C (77 °F)
9. IP66 rate optical enclosure per IEC 60529
10. Lifetime: 100,000 hours
11. Ten Year Limited Warranty: If Seller determines the Product is defective, Seller will
elect, in its sole discretion, to refund you the purchase price of the Product, repair the
Product or replace the Product. This limited warranty excludes field labor and
service charges related to the repair or replacement of the Product.
B. Lithonia Lighting D‐Series LED Flood Luminaire (125 watts or equivalent)
1. Replacement for 250 watt metal halide fixtures.
2. Input Wattage: 125 watts
3. Input Voltage: 120 – 277 V
4. CCT: 5000 K
5. Minimum CRI: 70+
Performance Specification – Shasta COE Section 26 5619
71
6. Initial Lumens: 15,271 Lumens (5000 K)
7. Lumens Per Watt (LPW): 122 LPW
8. Temperature rated at ‐40 °C (‐40 °F) to 35 °C (95 °F)
9. Lifetime: 100,000 hours
10. Five Year Limited Warranty
C. GE Evolve LED Flood Light EFM1 (96 watts or equivalent)
1. Replacement for 250 watt metal halide fixtures.
2. Input Wattage: 96 watts
3. Input Voltage: 120 – 277 V
4. CCT: 5000 K
5. Minimum CRI: 70+
6. Initial Lumens: 15,000 Lumens (5000 K)
7. Lumens Per Watt (LPW): 156 LPW
8. Temperature rated at –40 °C (‐40 °F) to 50 °C (122 °F)
9. Lifetime: 100,000 hours
10. Warranty: LED Luminaires purchased directed from GE to be free from defects in
material and workmanship unit the earlier of (1) Five years, and (2) 22,000 hours. If a
Product fails to meet this warrant, the GE will at its option, either (1) repair the
defective Product, (2) provide a free replacement product or replacement parts, or (3)
refund the purchase price paid to GE of the Product or replacement parts.
4.5 EXTERIOR 250 WATT METAL HALIDE TO LED FIXTURE REPLACEMENT (MEASURE L-6A)
A. Cree Edge Series LED Wall Pack Luminaire (90 watts or equivalent)
1. Replacement for 250 watt metal halide fixtures.
2. Input Wattage: 90 watts
3. Input Voltage: 120 – 480 V
4. CCT: 5700 K (+/‐ 500 K)
5. Minimum CRI: 70+
6. Initial Lumens: 9,349 lumens (5700 K)
7. Lumens Per Watt (LPW): 103 LPW
8. Temperature rated at 5 °C (41 °F) to 25 °C (77 °F)
9. IP66 rate optical enclosure per IEC 60529
10. Ten Year Limited Warranty
B. Lithonia Lighting D‐Series LED Wall Luminaire (109 watts or equivalent)
1. Replacement for 250 watt metal halide fixtures.
2. Input Wattage: 109 watts
3. Input Voltage: 120 – 480 V
4. CCT: 3000 K
5. Minimum CRI: 70+
6. Initial Lumens: 10,184 lumens (3000 K)
7. Lumens Per Watt (LPW): 93 LPW
8. Temperature rated at ‐40 °C (‐40 °F) to 32 °C (104 °F)
Performance Specification – Shasta COE Section 26 5619
72
9. Lifetime: 100,000 hours
10. Five Year Limited Warranty
C. GE Evolve Series EWNB LED Wall Pack (89 watts or equivalent)
1. Replacement for 250 watt metal halide fixtures.
2. Input Wattage: 89 watts
3. Input Voltage: 120 – 480 V
4. CCT: 4000 K
5. Minimum CRI: 70+
6. Initial Lumens: 9,800 Lumens (4000 K)
7. Lumens Per Watt (LPW): 110 LPW
8. Temperature rated at –40 °C (‐40 °F) to 50 °C (122 °F)
9. Lifetime: 50,000 hours
10. Five Year Limited Warranty
4.6 A-SHAPE LED LAMPS (MEASURE L-5A) A. Philips A‐Shape LED Lamps
1. Bare Lamp Wattage: 8 watts (13W CFL replacement) and 9.5 watts (100W
incandescent replacement).
2. Input Voltage: 120 V
3. CCT: 5000 K
4. Initial Lumens: 800 Lumens (8 watts) and 1000 (9.5 watts).
5. Efficacy (LPW): 100 Lumens Per Watt (8 watts) and 105 Lumens Per Watt (9.5 watts).
6. Lifetime: 10,950 hours.
B. Cree A‐Shape LED Lamps
1. Bare Lamp Wattage: 8.5 watts (13W CFL replacement) and 10.2 watts (100W
incandescent replacement).
2. CCT: 5000 K
3. Initial Lumens: 820 Lumens (8.5 watts) and 1150 (10.2 watts).
4. Efficacy (LPW): 96 Lumens Per Watt (8.5 watts) and 112 Lumens Per Watt (10.2
watts).
5. Lifetime: 25,000 hours.
C. Sylvania A‐Shape LED Lamps
1. Bare Lamp Wattage: 8.5 watts (13W CFL replacement) and 9.5 watts (100W
incandescent replacement).
2. Input Voltage: 120 V
3. CCT: 5000 K
4. Initial Lumens: 800 Lumens (8.5 watts) and 1100 (9.5 watts).
5. Efficacy (LPW): 94 Lumens Per Watt (8.5 watts) and 115 Lumens Per Watt (9.5
watts).
6. Lifetime: 25,000 hours.
Performance Specification – Shasta COE Section 26 5619
73
END OF SECTION 26 5619