SESAME, TAC 2012, 9/10.Nov.2012, Erhard Huttel, SESAME STATUS TAC 2012 Synchrotron light...
-
Upload
patricia-hopkins -
Category
Documents
-
view
215 -
download
0
Transcript of SESAME, TAC 2012, 9/10.Nov.2012, Erhard Huttel, SESAME STATUS TAC 2012 Synchrotron light...
SESAME STATUS TAC 2012
Synchrotron light Experimental Science Application Middle East
The means have become available to built up SESAME now!
Israel, Iran, Jordan, Turkey committed to contribute 1.25 M$ next four years.
Pakistan committed to comparable in kind contribution.
CERN/EU contribute 5 M€ for the purchasing of the magnet system
Financial Aspects till 2016
Income
EU-CERN: 5.00 M€Jordan: 5 x 1.25 M$Turkey: 5 x 1.25 M$Israel: 5 x 1.25 M$Iran: 5 x 1.25 M$ ?Pakistan: in kind contribution?USA?Norwegian?
Injector-upgrade 0.9 M€Magnets and PS:5.0 M€Girder: 0.8 M€Vacuum: 3.0 M€RF: 3.0 M€Diagnostics: 1.5 M€SR-Cooling: 0.5 M€Cabling: 0.5 M€Commissioning: 1.5 M€Control-System 1.1 M€Safety P+A 0.8 M€Front-Ends: 0.5 M€
Sum [€] 19.0 M€Sum [$] 23.3 M$10% 25.6 M$
Machine: 25.6 M$4 Beamlines upgrade: 8.7 M$Guesthouse+ 1.3 M$
Sum 35.6 M$
Project-Development
Operational-Cost-Development
Power: Based on 4000 h operation time, 1GWh / ySalary: Increase 35-75 employees
Organization
Design/MechanicsMaher S.ThaerAkrumMohammad
AhmadOpen position 2012N.N.
Machine-PhysicsMaher A.Open position 2012.
Cooling/VacuumFirasOsamaAdelSaed
BeamlinesXABS:MessaoudIR: IbraheemOpen Position 2012
ComputingSalmanMustafa
ControlZiaIbrahimOpen position 2012
Radiation-SafetyAdliMorteza
Electronics/ElectricSofian (Power supplies)Ifikhar (pulsed PS)
Yazeed (beam lines)Farouq (beam-lines)
Open position (Electric)RF/DiagnosticsDarweeshNashat (RF)Alaa (RF)Hussain (D)
AdministrationMajeda (Purchasing)Sonia (Assistant)Ayman (Human resources)Ibrahim (Accountant)Abd Al (Bus-driver)
General-Director:Directorate: Yasser (Administrative), Erhard (Technical), Hafeez (Scientific)
Responsibility of technical sector for beamlines?
Strategic Plan: 2.2 Project organizationThe task of the Technical Sector is to design, build and operate the machine from the microtron to the front ends. The shielding wall between the storage ring and the experimental hall is the border line that separates what falls within the responsibility of the Technical Sector and what lies with the Scientific Sector. Nevertheless, though the installation of beamlines would normally be within the purview of the Scientific Sector it has been decided that provisionally the technical team will be in charge of this due to the lack of staff in the Scientific Sector. Beamlines will be built individually in coordination with the corresponding beamline scientists.
Mechanical Workshop to be built up
Need for doing basic mechanical work!
Need mechanical craftsman!
Job request for mechanical craftsman on SESAME-web.
Built up of a mechanical workshop:
machines for sawing, drilling, cutting, milling.
Short term alternative:
Workshop at universities or private companies (few available)
Establish regular contact to these external workshops
Training
IAEA, LOUNDSBURY, ALBA, SOLEIL, JSR, …Training abroad at Synchrotron-Radiation-facility:1-9 month
IAEA (2007-2012) : Total: 35 trainee 114 months At SESAME: 6 15 months
Problem: Participant leaves SESAME Trainee is needed for work at SESAME (now)
Change of concept:More Training at SESAME with SESAME (Microtron / Booster)Invite experts to SESAME for training (Reach the complete team)Limit stay at foreign labs to 1 month (Technical sector)
Training is a center point of the SESAME Concept for capacity building
Response to TAC Recommendations
ManagementSchedule revision(Control system) staffingInitiated tendering processBudget revisionIn kind distribution Palestine
BoosterSextupole component booster rampingEstimate alignment errorEnergy spread Booster injectionCablingGrounding, cross-talk, noiseVacuum chamber fixation
SafetyShutter booster storage-ringRails on shielding wall
SR-MagnetsSR magnets field qualityInstallation dipole
Clear upOld cable trays Dissolve Free zoneCleaning
AOBFront-end designIR front-end radiation shielding
cooled first mirror?
Crane
‘Blue’ Girders had been damaged due to miss-alignment.Repaired: Damaged parts exchanged, girders aligned.Power feeds damaged during installation of air ducts.Repaired.‘Yellow’ Girder found to be damaged at one end.
The crane is an essential tool, which has to work reliable and safe!!
We must have an maintenance contract with a firm specialized on crane in duty for repair and inspection, warranty its safe operation!
Microtron in Operation, Beam in the transfer line
Achieved:Energy: 22MeVPulse-Width: 2 µsPulse-Current: 2 mA
More: Maher Attal
Microtron-Next Steps
Replace main Power-supply! In progress.
Replace gun positioning (motor-drives).
Replace Magnetron-Modulator?
Modify fluorescent Screen to allow Quadrupole scan
(determine emittance)
Replace Microtron?
Bessy II-Microtron? New racetrack-Micrtron? LINAC?
Prof. Dr. Andreas Jankowiak:…In diesem Sinne ist das Mikrotron zur Zeit noch unser „HotSpare“
und wird es auch noch für einige Zeit sein. Eine endgültige Außerbetriebnahme werden wir wohl
erst 2014 in Betracht ziehen.
Pulsed-Magnets
Keep MagnetsReplace Power-Supplies
Buy charging unitBuild switch in cooperation with SOLEIL
Injection Septum
Electro-Static SeptumU = E g/r Voltage: 110 kVGap: 0.01 mRadius: 2.00 mC: 30 pFT (half sine) 250 µs
New magnetic septum (50 MeV) ?BESSY II Microtron, LINAC
S M
S M
Q Pole Triplet
A
A
31
, 3
More Ifikhar Abid
Injection-Kicker
Injection Kicker
Magnetic Field 0.0017 T
Length 0.3 m
Current 200 A
Kick (22 MeV ~ 0.733 Tm) 7 mrad
Needed kick strength 4 mrad
Needed Current (50 MeV) 280 A
Pulse-length (half sine) 4 µs
More Ifikhar Abid
Booster-Optics
Energy 0.022-0.8 GeV
circumference 38.4 m
emittance 170 nmrad
alpha 0.18
Energy loss 14 keV
tune 2.2 / 1.3
Chromaticity -2.0 / -0.5
Periodicity 6
More Maher Attal
Booster-Magnets
Quadrupole
Gradient 5.77 T/m
Length 0.25 m
Bore- 78 mm
Current 146 A
No windings 4 x 24
Resistance 0.054
Inductance 6.8 µH
Dipole
B-field 1 T
Radius 2.67 m
Gap 40 mm
Current 1000 A
No windings 2x16
Resistance 0.015
Inductance 8.6 µH
RF Acceptance
2 kW in 3 MΩ (Doris-cavity) 100 kV3 kV 0.3 %10 kV 0.5 %20 kV 0.7 %
Task-List Booster
Layout of cable trays, purchasing of cable trays, cabling
Alignment of magnets
Installation of vacuum chamber
Grounding
Installation of Booster-RF
Layout of pulsed magnets PS, purchasing/built up
Layout of Booster corrector PS, purchasing
Set up of PLC-controller (vacuum, magnets)
Set up of ramped Power-supply control-system (EPICS+ Ethernet Interface)
Set up of corrector Power-supply control-system (EPICS+ Ethernet Interface)
Set up of Booster-RF-PLC-Controller
Set up of timing system
Grounding ANKA
Steel pillars connected to floor grid
Ground-copper-stripBus-bar 3 x 400 V
No grounding (concept) at SESAME,to be defined!
Ramping-Curve
Specification:340 V , 1040 ASquare function for VoltageNo smoothing at injection/extraction
No smoothing, Injection
No Smoothing extraction
Proposed ramping
More Sofian
Booster-Sextupole-Components
Calculation with FEMM (FEA) and ‘real’ vacuum chamber
10 Hz / 0.3 mm / sin: 1.6 1/m3
1 Hz / 1-2 mm / sin : 0.9 1/m3
Square voltage: x 10Smoothed: x 2
Booster-Correctors
Ordered Power supplies: 12 units: 1.5 A 30 V ????To be renegotiated with BRUKER
Number of Units: 6Turns: 18/36/18Resistance: 0.3 ΩCurrent for 1 mrad kick: 6 A
Aturns for 1 mrad kick: 6600 ATurns ?
More Sofian Javar
Radiation-Safety
Purchasing of Radiation Monitors in progress
5 movable +2 portable stations: Gamma: 10 nSv/h – 1 Sv/h
30 keV -10 MeV Neutrons:
10 nSv/h – 0.1 Sv/h25 meV – 100 MeV
Request for Tender in preparation for interlock system based on Safety PLC
Rules: Keep radiation level < 1 mSv / y (2000 h)0.5 µSv/h
More talk MortezaMansour
Offline-Monitoring (TLT) local provider with coarse monitoring
Girder
Design readyModified ALBA design
Achieved tolerances at ALBA:Flatness: 25 µmPosition: 50 µm
Needed Tolerances?? 50 µm?In kind contribution from Pakistan?
6 feeds3 struts used for transverse and longitudinal adjustment3 jacks used for vertical adjustment and clampingAdditional 3 vertical jacks used for clampingAdditional clampingTotal weight: ALBA: 7 t, SESAME:?Calculated Eigen frequency: ALBA: 50 Hz SESAME: 25Hz
More Maher Shehab
Alignment
Main Tools:Auto-Level: 1 mm / 1km?Total Station: 0.5’’, 0.6 mmTo be purchased:Measuring-arm or Laser-trecker? 50 µm.
Alignment Booster:Measuring done by SESAME staff withTotal-Station / Auto-LevelEvaluation done at SOLEIL expert (SOLEIL)Comparison of first campaign and present
Storagering Magnets
More Maher Shehab
SESAME-CERN-Management
EU provides 5M € to CERN for materialCERN provides manpower
SESAME has done designCERN has optimized design (3d)
CERN writes specification1)SESAME releases specificationCERN decides1)SESAME contractsCERN follows up manufacturingCERN/SESAME do measuring
CERN subcontracts PS to SESAMESESAME does complete purchasing
1) In mutual agreement with SESAME
More Attilio Milanese
Constrains from Optics
Multipoles:Dipole: dB/B < 510-4 @ 18 mmQuadrupole: dB/B < 510-4 @ 24 mm
RMS Orbit distortion due to alignment error
dipole qf
dx dB/B dy dφ dx dy
0.2 0.001 0.2 mm 0.2 mrad 0.2 mm 0.2 mm
0.6 1.8 mm 4.5 mm 1.8 mm 2.8 mm 2.1 mm
More Maher Attal
-40 -30 -20 -10 0 10 20 30 40X [mm]
0
1
2
3
4
5
6
7
Y [mm]
-40 -30 -20 -10 0 10 20 30 40X [mm]
0
1
2
3
4
5
6
7
Y [mm]
qf: db/dB = 10-4 qf: db/dB = 10-3
Storagering-Quadrupoles
Hyperbolic part approximated by circular arcB6 component optimized for 0.8 or 2.5 GeV?Chamfer size as ANKA QP
Gradient 17 T/m
Length 280 mm
Bore-diam. 70 mm
Turns 34
Current 240 A
Conductor 8.5x8.5,Ø4 mm2,mm
Resistance 45 mmΩ
More Attilio Milanes
Storagering-Sextupoles
SESAME: Select experienced manufacturer for complete magnet CERN: Separate production of lamination (EU) and joke (Middle East)
Capacity building or qualification
For core assembling: machined holes or using shouldersNo machining no chamfer
S = ½ B’’ = B/r2
2d b9 = 123d ∫ b9 = 0
Gradient 17 T/m
Length 280 mm
Bore-diam. 70 mm
Turns 34
Current 240 A
Conductor 8.5x8.5,Ø4 mm2,mm
Resistance 45 mmΩ
More Attilio Milanese
Storagering Power-Supplies
No of magnets
No in series
Current [A]
Voltage per magnet [V]
U-PS [V]
P-PS [kW]
Dipole 16 16 700 34 550 380
Quadrupole-H 32 32 240 11 390 94
Quadrupole-V 32 32 200 2.4 85 17
Sextupole-H 32 32 100 2.4 85 8.5
Sextupole-V 32 32 150 3.5 123 18
Corrector-H 35 1 5 15 17 0.085
Corrector-V 35 1 5 15 17 0.085
Skew-quad 16 1
Storagering-RF
2 donated ELETTRA-Cavityold test devices, bad brazing
SOLEIL: 350 MHz RF Solid-State-AmplifierCollaboration SOLEIL-SESAME:
Development of 70 kW 500 MHz tower 70kW / tower, 500 k€
Low Level Electronics:Collaboration with ALBA?
RF-Amplifier
Foreseen: 70 kW solid state amplifier based on 650 W modules.
Prototype developed by SOLEIL
financed partly by SESAME.
SOLEIL has licensed 500 MHz technology to BRUKER.
Price BRUKER for SESAME?
Number of units needed?
Initial plan 4 x 140 kW
Start with 2 old ELETTRA cavities (60 kW)
Install 4 Cavities (ELETTRA, ALBA, KEKII?)
4 Towers 80 kW enough for Phase 1 and II.
Allow expansion to more towers.
Cavities
No cavities
P/cavity
[kW]
Max. current
[mA]
2.5 GeV
Max. current
[mA]
2.2 GeV
Touschek
2% coupl. [h]
Gas
2 nbar
[h]
2 60 30 100
2 80 50 200
2 120 200 400
4 80 400 400 22 88
4 120 400 400 55 88
500 MHz Prototype-Module
0.65 kW module10 kW test-stand
More: Derweesh Foudeh
50 V Powersupply
Diagnostics
BPM Electronics:6 ITECH Electrons purchased for booster (6k€)Option for SR Electron a same price
Purchasing?
Current MonitorsIn purchasing process from BERGOZ:1 DCCT for booster1 DCCT for storage-ring3 FCT for transfer-lines
To de done: Layout/Design:Fluorescent-MonitorsTune-MonitorSynchrotron-Radiation-MonitorScraper
More:Hussein Al-Mahammad
Vacuum
Design ready, no change since 2010Some smaller parts (transitions) missing Begin 2013
Specification to be written Begin 2013
More Firas Makhaleh
Cooling PlantBuilt-up:Chiller / Compressor 2200 kW10° waterHeat Exchanger 1940 kW20° demineralized WaterLoad: Therm. Electr.
RF: 640 kW 640 kWSR-Magnets 600 kW 600 kWAir conditioning 300 kW 80 kW
ANKA
More:Firas Makhaleh
Status:Chillers, Compressor installedPumps Heat exchanger installedPiping for Booster installedAir conditioning installed
Next: Storage ring-PipingLayout to be done (Firas) Mid 2013Specification written End 2013
Control-System-Concept
Control-Panel Manager Field-controller (ADC/DAC) Devices
EDM EPICS PLC+ADC/DAC / DIA / MC Valves/FSC/PSMicrotron
EDM EPICS Embedded serverITCH-Electron
EDM EPICS virtual server (ADC/DAC/Power supplies)Gauges
EDM / CSS EPICS VME+ADC/DAC / DIO / MC Devices
Do we need VME?Expensive! Fast! Outdated when fast not needed!
A: analogD:digitalC: controllerM: MotionCSS: Controlsystem StudioEPICS: Exp.Phys.Ind.Cont. Sys.EDM: Editor Display ManagerPS: Power-supplies
Control-System
Problem is the lack of knowledge when people leave SESAME.
ICALEPCS 2011: Saed Abu Ghannam spent one month at CLS, attended the PCaPAC 2010 workshop then spent two months at SLS, one week at SOLEIL and visited IRFU. He was trained in EPICS and discovered the different aspects of a synchrotron radiation facility. He left SESAME 2011.
To be done general:
Cooperation with ComputingConcept (VME?)Back upDocumentationLoggingData-base
To be done next:PLC Booster vac.-/mag. interlockPLC RF-interlock
Done:Control by PLC:
Microtron, Transferline 1(Valves, Screen, PS)
Set up of (virtual) Servers.Graphical interfaces (EDM)Serial connection to EPICSTiming SystemVME running