Section F – Capital Projects
Annual Operating Budget Capital Projects
Substations$1,266,8222.15%
TransmissionLines$15,5520.03%
RevenueMetering$1,161,1161.97%
Transformers$5,2340.01%
CapacitorsRegulators$287,2530.49%
ElectricDistributionConstruction$9,108,85615.48%
EnergyControl$1,241,1632.11%
KellyPlant$2,460,0004.18%
DeerhavenPlant$9,263,50015.74%DistrictEnergy
$19,886,89233.79%
OtherSystemProjectsandAllocations$14,160,33524.06%
Electric System
FY15 Budget
ElectricProjectsProposed
Budget2015Substations 1,266,822$TransmissionLines 15,552RevenueMetering 1,161,116Transformers 5,234CapacitorsRegulators 287,253ElectricDistributionConstruction 9,108,856EnergyControl 1,241,163KellyPlant 2,460,000DeerhavenPlant 9,263,500DistrictEnergy 19,886,892OtherSystemProjectsandAllocations 14,160,335TotalProjects 58,856,723$
F - 1
Electric System Energy Supply Major Projects FY15 EnergySupplywillbeimplementingsomeofthecapitalimprovementcountermeasurerecommendations
ofacomprehensivecostofcyclingstudiesonDeerhavenUnit2andJ.R.KellyCombinedCycleUnit1toreducethecostofcycle,optimizehighoperatingreliability,andmaximizeelectricaldispatchgenerationmixwiththeadditionofbiomass.
TheEnergySupplycapitalbudgetincludesfundingforDeerhavenCT3gasturbinereplacementpartsin
preparationforCT3’smajorinspectioninFY17.Purchasingportionsofthecapitalsparesoverthenexttwoyearsisrequiredinordertofullyprepareforthismajorwork.Thecapitalsparesincludeasetof1ststageshrouds,3rdstagenozzles,3rdstagebuckets,and3rdstageshrouds.GRUisabletoobtainsignificantdiscountsinpriceasaresultofitsmembershipinaconsortiumofmunicipalutilities.
Deerhavencrusherhouseandprecipitatorbuildingsrequiretargetedelectricalbreakerreplacementsto
ensurereliabilityandsupportlife‐cyclemanagement. RefurbishmentoftheDeerhavenUnit2coolingtowerisamulti‐yearlife‐cyclemanagementproject
addressingsafetyandreliability.InFY15,twotoeightremainingcellswillhavedeterioratedwoodsupportsreplacedwithfiberglass.
DemolitionofthedecommissionedJ.R.KellyUnit7coolingtowerandasbestosassessmentoftheboiler,
turbineandbalanceofplant. CapitalreplacementofDeerhavenUnit2hightemperaturesuperheattubesaspartoftheboilerlifecycle
managementtoensurereliability. TheEnergySupplycapitalbudgetincludesfundsforreplacementofDeerhavenUnit2airqualitycontrol
systemcomponentsandequipment(i.e.capitalspares,catalystreplacement,bagreplacements,etc.)thatarenecessarytomaintainefficiencyandreliability,andtocomplywithenvironmentalregulatoryairemissionsrequirements.FundingisalsoincludedforcontrolmeasuresnecessarytocomplywiththeMercuryAirToxinsStandard(MATS)April2015implementationdate.
DeerhavenUnit2coalpipingimprovementstopreventfuturecoalleaksandreplaceportionsofthe
systemthatareattheendofusefullife. ReplacementofDeerhavenUnit2airheatercoldendbasketswhichhavereachedtheendofusefullife. PerforminspectionofportionsofDeerhavenUnit2highenergysteampipingtoassesstheremaining
usefullifeandidentifyanyhighriskareasthatneedtobeaddressedinsubsequentoutages. RefurbishmentofoneofthetwoDeerhavendemineralizertrainstorestorefullcapabilityofbothquality
andquantityofdemineralizedwaterneededforallDeerhavengeneratingassets. TheJ.R.KellyCombinedCycle1DistributiveControlSystem(DCS)hascomponentsapproachingtheend
oflifeandobsolescence.Assuch,numerousfailuresdirectlyaffectingunitreliabilityhavebeenexperienced.Selectedcomponentswillbereplacedwithnewerversionsthatwillenhancereliabilityandredundancy,andwhicharefullysupportedbytheoriginalequipmentmanufacturer.
TheJ.R.KellyUnit8steamturbinecontrolsareover40yearsoldandoutdated.Findingboththematerial
andtechnicalresourcestomaintainthissystemisdifficult.TheJ.R.KellyUnit8TurbineControlSystem
F - 2
willbeconvertedfromamechanichydraulicsystemtoamodernElectroHydraulicControl(EHC)systemandwillbemoreeasilymaintainedwhileprovidingbetterprocesscontrol.
Refurbishment of the J. R. Kelly Unit 8 cooling tower is a multi‐year life‐cycle management project
addressingsafetyandreliability.InFY15,25percentofthedistributionfillandfillstructureforallfourcellswillbereplaced.
District Energy Major Projects FY15 TheSouthEnergyCenterwilladdelectricalgenerationandchilledwatercapacitytosupportthenewUF
Health Cardiovascular and Neurosurgery hospital. This project will provide GRU with an increase inrevenues,benefitingallelectriccustomers,whilethehospitalisexpectedtobring800jobstoGainesville.Thecombinedelectrical loadtotheSECandthenewhospital isexpectedtoincreasebyat least4MW,whilethechilledwaterloadwill increasebyapproximately2,000tons.ConstructionwillbegininearlyFY15andwillbecompletedbyearlyFY18.
FundsarebudgetedtopurchasethepropertythattheInnovationEnergyCenterresideson.Thesefunds
wereoriginallybudgetedinFY12. The InnovationEnergy Centerwill add chilledwater capacity to serve newbuildings builtwithin and
aroundInnovationSquare.Chilledwaterservicewillprovideadditional,diversifiedrevenuetoGRU.ThechilledwatercapacitywillbeaddedonlyasnewbuildingsconnecttoGRU’schilledwatersystem.
Energy Delivery Major Projects FY15
Electric system construction is necessary to serve residential, commercial and industrial customer
growthwithin newdevelopments. Themajor component is building underground infrastructure. Theproposedbudgetfortheseprojectsis$1.5million.
Aging overhead and underground distribution system components, some elements ofwhich aremore
than50yearsold,willbesystematicallyandproactivelyrenewedorreplacedtomaintainGRU’sexcellentsystemreliability,qualityofserviceandcustomersatisfaction.PlannedworkextendsthroughoutGRU’sservicearea.Theproposedbudgetfortheseprojectsis$1.22million.
Defectivedistributionsystemcomponents, includingpoles,overheadandundergroundconductors,and
transformers,willbereplaced.Theproposedbudgetfortheseprojectsis$2.76million. Overhead and undergroundmain line electric system extensions and improvements are necessary to
serveneworexistingdevelopments.Theproposedbudgetfortheseprojectsis$766,000. TheEnergyManagementSystem(EMS)isamissioncriticalsystemthatwillbereplacedwithanew
system.Thesystemisrequiredtomonitorandoperatetheelectricgeneration,transmissionanddistributionsystems,economically,safelyandreliably.ThereplacementoftheEMSisnecessarysincethecontractwithGeneralElectrictoprovidethisfunctionalitywillexpireDecember2015.TheproposedbudgetforthisprojectforFY14is$500,000andFY15is$1.3million.
F - 3
Annual Operating Budget Capital Projects
WaterTreatmentPlant$1,735,00017.81%
DistributionandStorageTanks
$100,0001.03%
TransmissionandDistributionSystems
$1,345,00013.81%
FireSupportSystemEnhancements
$50,0000.51%TransmissionDistribution
Extension$130,0001.33%
RelocationforRoadConstruction$1,210,00012.42%
BackflowPreventionDevices$20,0000.21%
MetersandServicesLaterals
$1,650,00016.94%
OtherSystemProjectsandAllocations$3,501,10335.94%
Water System
FY15 Budget
WaterProjectsProposed
Budget2015WaterTreatmentPlant 1,735,000$DistributionandStorageTanks 100,000TransmissionandDistributionSystems 1,345,000FireSupportSystemEnhancements 50,000TransmissionDistributionExtension 130,000RelocationforRoadConstruction 1,210,000BackflowPreventionDevices 20,000MetersandServicesLaterals 1,650,000OtherSystemProjectsandAllocations 3,501,103TotalProjects 9,741,103$
F - 4
Water System Major Projects FY15
DesignofanewelectricalbuildingwithnewMotorControlCenters(MCCs)willbegininFY15and
constructionisanticipatedtobecompletedinFY18.TheexistingMCCshavebeeninservicesince1976.Theprojectwillalsoincludereplacingthe1,000kWplantenginegeneratorset.
TheChlorineScrubberR&Rprojectreplacesanobsolete“wet”scrubberwithanewtechnologydry
scrubber.Thenewunitisfactorysupportedandsignificantlyimprovesworkersafetyduetousingadrymediatechnologyinsteadofaliquidchemicalbeingusedinthecurrentwetscrubber.
GRUisimplementingan“InfrastructureImprovementArea”(IIA)policyintheInnovationDistrict
andsurroundingarea.GRUismakingwaterdistribution,reclaimedwaterdistribution,andwastewatercollectionsystemimprovementswithindefinedareasaheadofdevelopmentinordertoensurethatcapacityisavailabletoservefutureredevelopment.InordertorecoverGRU’sexpenditures,GRUisdevelopinganinfrastructureimprovementareachargetobepaidbydevelopmentprojectswithintheIIA.Thepolicywillensurethatcapacityismadeavailablewhenitisneeded,thattheimprovementsareperformedasefficientlyandcost‐effectivelyaspossible,andthatthecostoftheseimprovementsareallocatedfairlybetweendevelopmentprojects.WaterSystemimprovementsintheInnovationDistrictWaterIIAintheFY15budgetincludeconstructionofanewwaterlinebetweenthe1200and1300blockofSW3rdAvenue,whichwillbedoneinconjunctionwithconstructionoftheroadsegmentsthemselvesbyCRA.
TheDepotAvenueSegment2roadwayprojectconsistsofreconstructingDepotAvenuefromPK
YongeSchoolatS.W.11thStreeteasttoMainStreet.GRU’sworkwillincluderemovingandreplacingwatermainsandservices.
TheDepotAvenueSegment4roadwayprojectconsistsofrebuildingSoutheast7thAvenuefrom
LewisOilCompanyatS.E.7thStreeteasttoWillistonRoad.GRU’sworkwillincluderemovingandreplacingwatermainsandservices.
F - 5
Annual Operating Budget Capital Projects
WaterReclamationFacilities
$12,912,25056.82%
ReclaimedWaterSystems$745,0003.28%
LiftStations$709,3303.12%
WWCollectionSystemExtensions$80,0000.35%
ForceMainSystems$450,0001.98%
GravityCollectionSystems$2,130,0009.37%
RelocationsforRoadConstruction$890,0003.92%
ServiceLaterals$680,0002.99%
OtherSystemProjectsandAllocations$4,129,26718.17%
Wastewater System
FY15 Budget
WastewaterProjectsProposed
Budget2015WaterReclamationFacilities 12,912,250$ReclaimedWaterSystems 745,000LiftStations 709,330WWCollectionSystemExtensions 80,000ForceMainSystems 450,000GravityCollectionSystems 2,130,000RelocationsforRoadConstruction 890,000ServiceLaterals 680,000OtherSystemProjectsandAllocations 4,129,267TotalProjects 22,725,847$
F - 6
Wastewater System Major Projects FY15
ThePaynesPrairieSheetflowRestorationprojectisacooperativeprojectbetweenGRUandPublic
Workstomeetthetotalmaximumdailyload(TMDL)fornitrogenatAlachuaSink.Thetotalprojectcostisestimatedat$26million.OtherfundingsourcesincludetheCityStormwaterUtilityandgrants.Also,theMainStreetWaterReclamationFacilitywillbeupgradedforphosphorousremoval(separatelineitem).ConstructionforthisprojectwillbecompletedinFY15andperformancetestingwillbegin.
TheBiosolidsDewateringprojectisadirectresultofasettlementagreementandconsentorder
withAlachuaCountytoceasetheutility’scurrentoperationofapplyingClass‐BbiosolidsattheWhistlingPinesRanch.Astudyconductedtodetermineavailablealternativestolandapplicationshowedthattheviablealternativesrequireddewateringtoasignificantlyhigherlevelthanexisting(minimumof20percentsolidsratherthan5percentsolidsasisourcurrentpractice).ThedewateringprojectincludestheconstructionofafacilityutilizingcentrifugetechnologytodewaterwasteactivatedsludgefromKanapahaWaterReclamationFacilityandMainStreetWaterReclamationFacility.TheprojectwillbecompletedinFY16inordertomeetthescheduledFebruary2016compliancedate.
KanapahaWaterReclamationFacilityBarScreens:Theinstallationofnewbarscreensatthe
KanapahaWRFwillbethefirststepinpreparingforanewbiosolidsdewateringfacility.Thenewbiosolidsdewateringfacilitywillutilizecentrifugeequipmentthatoperatesathighspeedstodewaterthebiosolids.Thenewscreenswillremovemoredebrisfromthewastestream,inturnprotectingthetreatmentprocessandallowingthenewdewateringcentrifugestooperateproperly.ThisinstallationwillbecompletedinFY16inordertobeinplacebeforethedewateringfacilityisplacedinoperation.
TheSW20thAvenue/SW61stStreetprojectisbeingcompletedinconjunctionwithaCountyPublic
Worksproject.GRUwillrelocateexistingforcemainandgravitymainwastewaterfacilities.
F - 7
Annual Operating Budget Capital Projects
GasProjectsProposed
Budget2015Regulators/RevenueMetering 44,077$Meters&RegulatorInstallations 534,992LiquidPropane 24,121Measuring&RegulatingStationEquipment 250,039NewDevelopments‐DistributionMains 1,409,356Renewal&Replacement 501,554Services 641,019OtherSystemProjectsandAllocations 2,757,382TotalProjects 6,162,540$
F - 8
Gas System
Major Projects FY15
Gasmainextensionsandimprovementsarenecessarytoserveneworexistingdevelopments.Theproposed
budgetfortheseprojectsis$840,000.
Newservicelinesandassociatedequipmentwillbeinstalledtoservenewcustomers.Agingservicepipeswillbesystematicallyandproactivelyrenewedorreplacedtoimprovesystemreliability,qualityofserviceandcustomersatisfaction.Theproposedbudgetfortheseprojectsis$545,000.
Gassystemconstructionisnecessarytoservenewresidential,commercialandindustrialcustomerswithinnewdevelopments.Theproposedbudgetfortheseprojectsis$381,000.
Newmetersandassociatedequipmentwillbeinstalledtoservenewcustomers.Aginginstallationswillbesystematicallyandproactivelyrenewedorreplacedtopromoteandensurebillingaccuracy.Theproposedbudgetfortheseprojectsis$542,000.
Aginggasdistributionsystempipeswillbesystematicallyandproactivelyrenewedorreplacedtoimprovesystemreliability,qualityofserviceandcustomersatisfaction.Theplannedworktoreplacecastiron,blackplasticandsteelpipingextendsthroughoutthecoreofGRU’sservicearea.Theproposedbudgetfortheseprojectsis$416,000.
Measuringandregulatingstationequipmentwillbeinstalledandinsomeinstancesrenewedtoenhance
systemreliability,qualityofserviceandcustomersatisfaction.Theproposedbudgetfortheseprojectsis$220,000.
F - 9
Annual Operating Budget Capital Projects
F/ONetworkExpansion$3,752,43256.09%
SpecialProjects$543,6008.13%
OtherSystemProjectsandAllocations$2,393,98535.78%
GRUCom
FY15 Budget
TelecommunicationsProjectsProposed
Budget2015F/ONetworkExpansion 3,752,432$SpecialProjects 543,600OtherSystemProjectsandAllocations 2,393,985TotalProjects 6,690,017$
F - 10
GRUCom System Major Projects FY15 DuringFY15,GRUComwillcontinuetobuildfibertoadditionaltowerlocationsandinstallinfrastructure
tosupportcellularcarrierdatagrowth.FundsforthisinitiativeareincludedintheNetworkExpansioncapitalbudget.
GRUComwillcontinuetoexpandtherecentlyannouncedGigabitInternetaccessoptionsGATORNET
productline.FundsforthisinitiativeareincludedintheNetworkExpansioncapitalbudget. GRUComwillbebegintheinitialphaseofanupgradetothePublicSafetyTrunkedRadioSystem(TRS)to
addP25functionality.FundsforthisinitiativeareincludedintheGRUComTRSupgradebudget. GRUComwillcontinuetoinvestininfrastructurewithintheInnovationDistrictandotherrelatedareas
throughoutthecommunity.Timingofnewfacilitieswilldependonprivateindustryconstructionplans.TheinstallationofthefacilitieswillprepareGRUComtoprovideleading‐edgetechnologyservicesinatimelyandcost‐effectivemanner.FundsforthisprojectareincludedintheFY15NetworkExpansioncapitalbudget.
ThroughincreasednetworkefficiencyGRUComwillreducetheprojectionsfortheFY15/FY16capital
budgetbyapproximately$140,000inFY15andanadditional$100,000inFY16.