SCTSG - 17 October 2006 A. Ciocio 1 SCT Services Installation Update Recent Full Report: September ID week SCT Cables Web page: http://www- atlas.lbl.gov/ciocio/SCTcables / Workpackage: https://edms.cern.ch/document/593278/ EDMS: 624679 SpSSSSSSStSons oS SST powSr SSSlSsS tSpS SSS SSS SnS SV 783753 SST SowSr SSSlSs LSSout

Transcript of SCTSG - 17 October 2006 A. Ciocio1 SCT Services Installation Update Recent Full Report: September ID...

Page 2: SCTSG - 17 October 2006 A. Ciocio1 SCT Services Installation Update Recent Full Report: September ID week SCT Cables Web page:

SCTSG - 17 October 2006 A. Ciocio 2

Type II/III cables status

4088 cables: installation and testing completed ! 2112 barrel cables & 1976 Endcap cables

3594 cables (including all the 2112 Barrel) installed between March-July 494 (EC sector 11&15) installed in September

-------------------------

• 100% of the type III cables fixed on cable trays and positioned in PP3 (by TC)

• One recent faulty cable replaced (last week)

• Additional inspection, final verification and repair of damaged wires ongoing

• Re-position (and insulation) of EC bundles and clamp on the flange ongoing

• Test of the whole chain from Cryostat to Power Supply ongoing

• Test of connectivity with Peter Phillips November

Page 3: SCTSG - 17 October 2006 A. Ciocio1 SCT Services Installation Update Recent Full Report: September ID week SCT Cables Web page:

SCTSG - 17 October 2006 A. Ciocio 3

PP3 Rework Completed

• Because of insulation problem (see previous reports) ALL PP3 subracks of 30 units were:

– disassembled– cleaned– glued properly – plastic layers (0.25 mm polyethylene terephthalate) inserted between all sides of PP3 units

• Disconnection of all cables was completed at the end of August (by the SCT cabling/testing team)

– 8000+ cables were hanging by the racks for several days– ~4000 PP3 units in B161

• Scott Moncrieff and Ashley French were at CERN for 4 weeks in September to do this rework

– Many SCT collaborators participated in the re-assembling (THANKS!)– The last couple of weeks of September were very intense due to the late arrival of parts from

Australia and running out of glue

• All PP3 subracks back in the pit and all re-installed by October 1st

• 70 % of cables are re-connected to PP3

Page 4: SCTSG - 17 October 2006 A. Ciocio1 SCT Services Installation Update Recent Full Report: September ID week SCT Cables Web page:

SCTSG - 17 October 2006 A. Ciocio 4

PP3 Racks - USA side

Sector 7

Type IV cables

from

Power Supplies racks in USA15

Type II-III cables

from Cryostat

Sector 9

Through corridorsAbout 70 meters

Sector 11

Page 5: SCTSG - 17 October 2006 A. Ciocio1 SCT Services Installation Update Recent Full Report: September ID week SCT Cables Web page:

SCTSG - 17 October 2006 A. Ciocio 5

PP3 Racks - US side

Sector 3

Sector 1

Sector 15

Type II-III cables

from Cryostat

Type IV cables

from

Power Supplies

racks in US15

Through wall holes

About 30 meters

Page 6: SCTSG - 17 October 2006 A. Ciocio1 SCT Services Installation Update Recent Full Report: September ID week SCT Cables Web page:

SCTSG - 17 October 2006 A. Ciocio 6

Plan for PP3 Racks Rework Cables Reconnection & Testing(as of September 23)

Taking into account:

• Connector in situ work• PS installation• Time to reconnect• Time to test whole chain

Page 7: SCTSG - 17 October 2006 A. Ciocio1 SCT Services Installation Update Recent Full Report: September ID week SCT Cables Web page:

SCTSG - 17 October 2006 A. Ciocio 7

Type IV Cables Installation

• US side: – Type IV cables (2044+spares) from PP3 racks in the ATLAS

cavern to PS racks in US15• Installed in 2005 (as double harness)• Connectors in situ (March 06)• 9 PS racks (8 for barrel) installed and cables plugged into PS

backplanes (July)• All type IV and type III (except for sector 15 EC) were

connected to PP3 and test of whole chain done (in August) but then disconnected for PP3 rework

• USA side: – Type IV from PP3 to USA15 installation completed (end of July)– All type IV were connected to PP3 (17 racks in UX15)

but then disconnected for PP3 rework– extra spare cables just added in several racks (USA side)

• All cables tested before and after installation

Page 8: SCTSG - 17 October 2006 A. Ciocio1 SCT Services Installation Update Recent Full Report: September ID week SCT Cables Web page:

SCTSG - 17 October 2006 A. Ciocio 8

Type IV Cables – cont’d

• Connector in situ (CPE)– All connectors (2100+) in

US15 completed in March– “saga” to resume work in

USA15

finally it started on Aug 1st

– 8 USA racks with Barrel cables completed last week

– The last 3 racks (EC) by End-October

Page 9: SCTSG - 17 October 2006 A. Ciocio1 SCT Services Installation Update Recent Full Report: September ID week SCT Cables Web page:

SCTSG - 17 October 2006 A. Ciocio 9

Type IV Cables – cont’d

• PS installation in USA15 (see next talk)– started 4 weeks ago– first plug-in/testing started on Sept 25

• Testing– 2 test systems are used for testing connector work and 2 test

systems for PS/whole chain– 1 test system failed 2 weeks ago repaired after one week– Cables are first tested after connector work (plugged in PP3 – or not)

to check connectors (rack by rack)– All cables are tested (whole chain) as they are plugged in row by row

during PS connection– Test of whole chain in USA15 75% done now (sector 7, 9, 11)– Test of whole chain was performed on the US side (80 %) in end-

July/August (but needs to be redone after PP3 rework)– Test of whole chain (again) in US15 started this week (sector 1, 3,

15)

Test of sector 1, 3, 7, 9 will be completed in 2 weeks and partially sector 11 and 15

Page 10: SCTSG - 17 October 2006 A. Ciocio1 SCT Services Installation Update Recent Full Report: September ID week SCT Cables Web page:

SCTSG - 17 October 2006 A. Ciocio 10

PS rackslayout

priorities for connector in-situ and plug-in

Page 11: SCTSG - 17 October 2006 A. Ciocio1 SCT Services Installation Update Recent Full Report: September ID week SCT Cables Web page:

SCTSG - 17 October 2006 A. Ciocio 11

SCT DCS CablesRichard Brenner + Lars Lindquist

• 128 type II and 40 type IV + 4 canbus

• Almost all cables between cavern and USA15 are installed

• Interlock cables in US15 installed

• Interlock cables between PS racks in USA15 and DCS rack in USA15 installed (4 cables x 11 racks)

• In the next few days we’ll resolve the rest of the cables to be installed:

– Y34-23.X0 : 6+6 type II cables missing for Barrel but they have been routed from the cryostat to Z=0

– Y29-01.X1: 6+6 type II cables missing for Barrel but they have been routed from the cryostat to Z=0

– type IV interlock cables have been routed to Y04-05.S2 in US15, but unfortunately incorrectly

– Y35-05.X8 : All type II cables are missing from the rack. The cables were left to the cable tray 2 m below the rack (Sergei told me that they have already started to route them)

Page 12: SCTSG - 17 October 2006 A. Ciocio1 SCT Services Installation Update Recent Full Report: September ID week SCT Cables Web page:

SCTSG - 17 October 2006 A. Ciocio 12

SCT Readout Cable Installation

• All 144 SCT Readout Cables installed and tested• See (September) ID week report • No update

Page 13: SCTSG - 17 October 2006 A. Ciocio1 SCT Services Installation Update Recent Full Report: September ID week SCT Cables Web page:

SCTSG - 17 October 2006 A. Ciocio 13

Schedule(Power Cables & PP3)

Barrel

• All Connector in situ (USA15) + testing end-October • PS crates (USA15) mid-October• Test of whole chain (sector 1, 3, 7, 9) end-October

sector 11, 15 mid-November

PP3 & cabling

• PP3 rework (done) end-September• All cables re-plugged into PP3/PS end-October

Endcap

• 3 USA15 PS racks installation November • 3 US15 PS racks installation January 07• Test of whole chain November and January 07

Page 14: SCTSG - 17 October 2006 A. Ciocio1 SCT Services Installation Update Recent Full Report: September ID week SCT Cables Web page:

SCTSG - 17 October 2006 A. Ciocio 14

PEOPLE

2006

+ Freiburg, MPI, Japan, Glasgow, Manchester, Lancaster, UCL, Oxford, Cambridge, Geneva…

Page 15: SCTSG - 17 October 2006 A. Ciocio1 SCT Services Installation Update Recent Full Report: September ID week SCT Cables Web page:

SCTSG - 17 October 2006 A. Ciocio 15

Final Remarks• PP3 rework has added extra load to an already dense schedule of activities

– The help received in the last few weeks has been crucial to make progress • 2 days per week (over the last 3 weeks) of 2 techs (Jean and Gilbert) from Geneva• Tony W. + Ellie D. • Janet, Stephen H., Richard B. • Nobu + Reisaburo • Last week 2 techs (Andy and Mike) from Manchester• This week 3 techs (Ines, Dieter, Patrick) from Freiburg• Next week 2 techs (Joe B. and Richard S.) from Oxford• October 30 (for 2 weeks) 3 students from Bergen

Need additional technical people (two) from October 30 until mid-November

• Consequences of PP3 rework and delay of connector in situ work added difficulties to keep up with the schedule – We are falling behind schedule with reconnecting to PP3 and testing

of the whole chain (also due to the test system failure)– We are one week behind with connection to PS– USA15 was very crowed and hectic in the last 3 weeks

Hoping to catch up in the next 2 weeks and be ready for the final connectivity test with Peter Phillips