SCT Services Installation

18
ID week - 26 September 2006 A. Ciocio 1 SCT Services Installation SCT Cables Web page http://www-atlas.lbl.gov/ciocio/SCTcables/ Workpackage https://edms.cern.ch/document/593278/

description

SCT Services Installation. SCT Cables Web page http://www-atlas.lbl.gov/ciocio/SCTcables/ Workpackage https://edms.cern.ch/document/593278/. 5. 7. 3. 1. 9. 15. 11. 13. Cable trays from Calorimeter Barrel to HS. Type II cables. Type III cables. PP1. Type II-III cables - PowerPoint PPT Presentation

Transcript of SCT Services Installation

Page 1: SCT Services Installation

ID week - 26 September 2006 A. Ciocio 1

SCT Services Installation

SCT Cables Web page http://www-atlas.lbl.gov/ciocio/SCTcables/Workpackage https://edms.cern.ch/document/593278/

Page 2: SCT Services Installation

ID week - 26 September 2006 A. Ciocio 2

Cable trays from Calorimeter Barrel to HS

1

35

7

9

15

1311

Type II cablesPP1 Type III cables

Page 3: SCT Services Installation

ID week - 26 September 2006 A. Ciocio 3

PP3 Racks - USA side

Sector 7

Type IV cables from

Power Supplies racks

in USA15

Type II-III cables

from Cryostat

Sector 9

Through corridorsAbout 70 meters

Sector 11

Page 4: SCT Services Installation

ID week - 26 September 2006 A. Ciocio 4

PP3 Racks - US side

Sector 3

Sector 1

Sector 15

Type II-III cables

from Cryostat

Type IV cables

from

Power Supplies

racks in US15

Through wall holes

About 30 meters

Page 5: SCT Services Installation

ID week - 26 September 2006 A. Ciocio 5

Type II/III power cables 4088 cables: installation and testing completed !

2112 barrel cables & 1976 Endcap cables

• 3594 cables (including all the 2112 Barrel) installed between March-July• 494 (EC sector 11&15) installed in the past 3 weeks

Yield 99% production (defects) + installation (damage)

Page 6: SCT Services Installation

ID week - 26 September 2006 A. Ciocio 6

Type II/III cables - THANKS

THANKS to TC for the fantastic job to complete successfully such complex installation

THANKS to the all SCT institutes for sending their technical staff to work on the preparation of cables and testing

THANKS to our PL for supporting through CERN or SCT the more long-term technical staff over the past several months

July 18th 2006Celebration for the completion of Barrel cables installation

Page 7: SCT Services Installation

ID week - 26 September 2006 A. Ciocio 7

Type II/III cables in progress

• 80% of the cables fixed on cable trays and positioned in PP3 (TC)

• Additional inspection, final verification and repair of damaged wires(yield might go down)

• Re-position of EC bundles and clamp on the flange

• Test of the whole chain from Cryostat to Power Supply

Page 8: SCT Services Installation

ID week - 26 September 2006 A. Ciocio 8

PP3 Parts Summary (original)

PP3 units installed in racks

Channel

Spare units in racks

4261

4088

173

Subracks (30 PP3 units in a shell) 137

Subracks - special

(shells of 30 partially filled with PP3 and the rest with empty boxes)

9

Subracks – mini (shells of 5 units for spares PP3 in a full rack)

4

PP3 units

Shells

Mini shells

Empty boxes

2

2

4

110

Page 9: SCT Services Installation

ID week - 26 September 2006 A. Ciocio 9

PP3 Assembly & Installation

• Assembly and Installation started last January and was completed in July• All type IV were plugged in + type III barrel cable (and EC) of sector 1, 3, 9• Test of whole chain was almost completed for Barrel (US side)• Since first installation (January) of PP3 many problems were found and

repairs implemented (see previous reports)– Insulation between units – Sliding units in subracks – Failed units (2+)– Shorts to the top hat outer shell

• During test of whole chain new shorts appeared suggesting that the insulation of the units near the corners of the subracks is not strong enough to resist wearing or puncturing from any metallic dust and it can be damaged by just plugging in more cables

Therefore it was decided to rework ALL subracks in the 17 PP3 racks

Page 10: SCT Services Installation

ID week - 26 September 2006 A. Ciocio 10

PP3 Rework

• PP3 subracks containing 30 units to be:– disassembled– Cleaned– glued properly – plastic layers (0.25 mm polyethylene terephthalate) to be inserted

between all sides of PP3 units

• Disconnection of all cables was completed last week (by the SCT cabling/testing team)– 8000+ cables were hanging by the racks for several days

• Scott Moncrieff and Ashley French were back Sept 4 (leaving next week) to do this rework

• Rework has started (last Thursday) but with 2 ½ weeks delay because the material arriving from Australia (new/larger outer shells, etc.) was late

Page 11: SCT Services Installation

ID week - 26 September 2006 A. Ciocio 11

PP3 Rework Plan

Taking into account:

• Connector in situ work• PS installation• Time to reconnect• Time to test whole chain

Page 12: SCT Services Installation

ID week - 26 September 2006 A. Ciocio 12

Type IV Cables Installation

• US side: – Type IV cables (2044+spares) from PP3 racks in the

ATLAS cavern to PS racks in US15• Installed in 2005• With connectors (March 06)• 9 PS racks (8 for barrel) installed and cables

plugged into PS backplanes

• USA side: – Type IV from PP3 to USA15 installation completed

(end of July)– All type IV were connected to PP3 (17 racks in UX15)

until 1 month ago– Currently installing a few more spare cables in several

racks (USA side)

Page 13: SCT Services Installation

ID week - 26 September 2006 A. Ciocio 13

Type IV Cables – Related • Connector in situ (CPE)

– All connectors (2100+) in US15 completed in March– 2+1 CPE techs returned in mid-April for a few weeks

• Rework of faulty connectors in US side• Started 2 USA racks but left again because more USA15 racks were needed

to be completed for the full team to operate efficiently– 4 CPE techs returned on August 1st

• Very slow startup - problems with the Company– 5 barrel (or mixed) racks in USA15 are completed as of today

• 2 racks this week (probably only one)– The 7th 8th USA racks with Barrel cables will be completed during PS

installation• all barrel cables will be at least cut to length before PS installation

– The last 3 racks (EC) by Mid/End-October • Testing

– All cables are tested as they are plugged in row by row during PS connection– All cables are tested 100 at a time as connectors are made– Test of whole chain was performed on the US side (80 %) in end-July/August

• PS installation in USA15 (see next talk)– started last week– first plug-in Sept 25

Page 14: SCT Services Installation

ID week - 26 September 2006 A. Ciocio 14

PS rackslayout

priorities for connector in-situ and plug-in

Page 15: SCT Services Installation

ID week - 26 September 2006 A. Ciocio 15

Schedule

Barrel

• Type IV installation (spares) end-September• All Connector in situ + testing mid/end-October

• PS crates (Barrel USA15) mid-October

• PP3 rework end-September

• All cables re-plugged into PP3/PS mid/end-October • Test of whole chain (Barrel) end-October

Endcap• 2 (US15) + 3 (USA15) PS racks installation November• Test of whole chain December

Page 16: SCT Services Installation

ID week - 26 September 2006 A. Ciocio 16

Work Plan

Page 17: SCT Services Installation

ID week - 26 September 2006 A. Ciocio 17

Manpower• PP3 rework is in progress

– Need (crucial!) 3 additional techs/physicist this week

• 2 techs to help connecting• 1 person (student OK) to help with the rework in the lab

– Need3 additional techs the first 3 weeks of October

• To help connecting

• Testing– Delay of connector in situ will involve more flexibility

and additional adjustment of the schedule for • Re-connecting cables and testing the whole chain

More help needed in October

Page 18: SCT Services Installation

ID week - 26 September 2006 A. Ciocio 18

PEOPLE