Schenectady City School District
Mosaic Associates
Mike Fanning, AIA
Turner Construction
Larry E Tune, PM
Phase I – Capital Project Update
16th of November, 2016
1
![Page 2: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second](https://reader036.fdocuments.in/reader036/viewer/2022081523/5fe0ae7a5e300760c6381f6b/html5/thumbnails/2.jpg)
CAPITAL PROJECT UPDATE| Outline
• Update on Current Capital Work• Group B Projects
• Group C Projects
• Group D Projects
• Overview of Capital Projects• Timelines
• Long Range Planning
• PH II - Schedule
• Next Steps:• Critical & Milestone Dates
2SCSD Capital Project Update – 16th of November, 2016
![Page 3: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second](https://reader036.fdocuments.in/reader036/viewer/2022081523/5fe0ae7a5e300760c6381f6b/html5/thumbnails/3.jpg)
3SCSD Capital Project Update – 16th of November, 2016
• MPMS – Phases 1, 2 & 3
CAPITAL PROJECT | Group B
Work substantially complete
( Second Floor Only )
Work in progressuntil Dec 2016.
Work in progress( Second Floor Only )
Work commence Dec. 2016
Work commence June 2017
![Page 4: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second](https://reader036.fdocuments.in/reader036/viewer/2022081523/5fe0ae7a5e300760c6381f6b/html5/thumbnails/4.jpg)
CAPITAL PROJECT | Group B
• OMS Substantially complete.
Punch List & close out in progress.
4SCSD Capital Project Update – 16th of November, 2016
![Page 5: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second](https://reader036.fdocuments.in/reader036/viewer/2022081523/5fe0ae7a5e300760c6381f6b/html5/thumbnails/5.jpg)
5
• CENTRAL PARK MIDDLE SCHOOL
SCSD Capital Project Update – 16th of November, 2016
CAPITAL PROJECT | Group C
Turnover next week
Occupied by district
Ground Floor
First Floor
Second Floor
![Page 6: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second](https://reader036.fdocuments.in/reader036/viewer/2022081523/5fe0ae7a5e300760c6381f6b/html5/thumbnails/6.jpg)
CAPITAL PROJECT | Group C
6SCSD Capital Project Update – 16th of November, 2016
• Howe Elementary School -• Product submittal process 75%.
• Construction in progress.
Building Addition Existing Building Renovation
![Page 7: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second](https://reader036.fdocuments.in/reader036/viewer/2022081523/5fe0ae7a5e300760c6381f6b/html5/thumbnails/7.jpg)
CAPITAL PROJECT | Group C
7SCSD Capital Project Update – 16th of November, 2016
• Van Corlaer ES -• Product submittals process 75%.
• Phase 1 December substantial completion.
• Phase 1A February substantial completion.
![Page 8: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second](https://reader036.fdocuments.in/reader036/viewer/2022081523/5fe0ae7a5e300760c6381f6b/html5/thumbnails/8.jpg)
CAPITAL PROJECT | Group D
• Hometown Health Centers• MPMS Hometown Health; Operational 10/11/2016.
• SHS Hometown Health; Operational 10/26/2016.
8SCSD Capital Project Update – 16th of November, 2016
MPMS SHS
![Page 9: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second](https://reader036.fdocuments.in/reader036/viewer/2022081523/5fe0ae7a5e300760c6381f6b/html5/thumbnails/9.jpg)
CAPITAL PROJECT | Group D
• Phase 1B - CPMS – Roof Repairs / Exterior Masonry• Project 1 – Roof Repair
• Approved by SED.
• Substantial completion next week.
• Project 2 – Exterior Masonry Reconstruction
• Design in progress.
9SCSD Capital Project Update – 16th of November, 2016
![Page 10: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second](https://reader036.fdocuments.in/reader036/viewer/2022081523/5fe0ae7a5e300760c6381f6b/html5/thumbnails/10.jpg)
CAPITAL PROJECT UPDATE| Long Range Planning
• 70MM – Phase I - Capital Project:
10SCSD Capital Project Update – 16th of November, 2016
![Page 11: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second](https://reader036.fdocuments.in/reader036/viewer/2022081523/5fe0ae7a5e300760c6381f6b/html5/thumbnails/11.jpg)
CAPITAL PROJECT UPDATE| Long Range Planning
• LRP-2• $50 M +
• Elementary School focus
• Referendum Vote – May 2017
• Admin meetings to develop planning process.
11SCSD Capital Project Update – 16th of November, 2016
![Page 12: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second](https://reader036.fdocuments.in/reader036/viewer/2022081523/5fe0ae7a5e300760c6381f6b/html5/thumbnails/12.jpg)
12SCSD Capital Project Update – 16th of November, 2016
![Page 13: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second](https://reader036.fdocuments.in/reader036/viewer/2022081523/5fe0ae7a5e300760c6381f6b/html5/thumbnails/13.jpg)
CAPITAL PROJECT UPDATE| Next Steps & Milestones
• December 2016 Finish Phase 3 at MPMS and Phase 1 at VCES.
On-going construction at OMS & CPMS
• March 2017 Adopt Phase 2 plan – (Scope & Budget)
• May 2017 Phase 2 Referendum vote.
• Summer 2017 - Ongoing construction MPMS, HOWE, VCES &
Fall 2017 CPMS exterior.
• September 2017 Reopen HOWE ES.
• November 2017 Turnover VCES elevator.
13SCSD Capital Project Update – 16th of November, 2016
![Page 14: Schenectady City School District · SCSD Capital Project Update –16th of November, 2016 3 • MPMS –Phases 1, 2 & 3 CAPITAL PROJECT | Group B Work substantially complete ( Second](https://reader036.fdocuments.in/reader036/viewer/2022081523/5fe0ae7a5e300760c6381f6b/html5/thumbnails/14.jpg)
THANK YOU | Any Questions?
14SCSD Capital Project Update – 16th of November, 2016
OMS COMMONS