SAP S/4HANA Implementation Plant Maintenance Overview
Transcript of SAP S/4HANA Implementation Plant Maintenance Overview
SAP S/4HANA Implementation
Plant Maintenance OverviewMay 2019
© 2019 Deloitte Consulting Southeast Asia
Agenda
Plant Maintenance Overview
Organisational Structure
Business Processes
Integration with other modules
Plant Maintenance Overview
SAP Plant MaintenanceAs part of Logistics, SAP Plant Maintenance supports the following activities:
Inspection All tasks for determining and assessing the actual condition of a
technical object, including identifying the cause of wear and tear and deducing the consequences necessary to ensure its future use
Maintenance All tasks for delaying the reduction of the wear reserve
Repair All tasks that return a technical object to its operational state
Improvement All technical, administrative and management tasks for improving
the functional safety of a technical object, without having to change its required function
Fundamentals of Maintenance
• Check
• Measure
• Observe
• Assess
• Deduce
consequences
• Visual inspection
• Adjust
• Replace
• Supplement
• Lubricate
• Preserve
• Clean
• Functional testing
• Replace
• Restore functions
• Correct malfunctions
• Elimination of weak points
• Improved design of machines, tech. systems
• Optimized business processes
• Faster exchange of information
Overview of Plant Maintenance (PM)
4) Unplanned Maintenance
3) Planned Maintenance
1) PM Organization 2) Technical Objects5) Reporting
Overview of Maintenance Process
Raise Maint. RequestRaise Maint. Request
Review Maint. RequestReview Maint. Request
Convert OrderConvert Order
Plan OrderPlan Order
Release OrderRelease Order
Procurement/ WarehouseProcurement/ Warehouse
Schedule OrderSchedule OrderMaintenance ExecutionMaintenance Execution
Time ConfirmationTime Confirmation
Technical CompletionTechnical Completion
Settlement/ Close OrderSettlement/ Close Order
Maintenance
Request
3
Planning
SchedulingExecution
4
2
1
6
5
Completion
Confirmation
Notification
313029282726
25242322212019
18171615141312
111098765
4321
FTWTMSS
2019
Preventive
CorrectiveWork Order
Mavin Project | SAP S/4HANA Implementation 7
Organisational Structure
Mavin Project | SAP S/4HANA Implementation 8
Company Code
Maintenance Plant
Work Center
MAVIN
Planning Plant
Planner Group
Pla
nt
Main
ten
an
ce
Team 1
MECHANIC
Team 1
…
Planner Grp. Elec.
PG1
Planner Grp. Mec.
PG2
Planner Group
…
Planner Group
…
Team 2
ELECTRIC
Controlling Area /
Chart of Account
MAVIN
Work Center
…
Organization Levels in Plant Maintenance
Hanoi Hưng Yên 2 Nghệ An Bình ĐịnhĐồng ThápHưng Yên 1
Hanoi Nghệ An Bình ĐịnhĐồng ThápHưng Yên 1
Planner Group
…
Planner Group
…
Mavin Project | SAP S/4HANA Implementation 9
Plant-Specific and Cross-Plant MaintenanceFor business processes in plant maintenance, you need to differentiate between order planning and execution in the same plant and order planning and executionin different plants:• Plant-Specific Maintenance: Plant-specific planning is done in the maintenance plant.• Cross-Plant Maintenance: Multiple maintenance plants are assigned to a planning plant.
Maintenance Requirement
Plant 2000
Maintenance Requirement
Plant 1000
Planning of Maintenance Requirement
Spare Part Storage
Maintenance Requirement
Work Center Work Center
Work Center Work Center Work Center
Material
Plant 1100
Mavin Project | SAP S/4HANA Implementation 10
Work Center
DefinitionDefinition
UsageUsage Work centers are used in orders / task lists.
A work center is an organizational unit where
work can be carried out.
Scheduling Default ValuesCosting
2200123
2323
Capacity Planning
Cap
acit
yLabour
Functions
Mavin Project | SAP S/4HANA Implementation 11
Master Data
Mavin Project | SAP S/4HANA Implementation 12
High Level Plant Maintenance Process
Maintain Master Data
Maintain Work Center
Maintain Functional Location
Maintain Equipment
Maintain BOM
Maintain Catalog
Analyse Work
Reports
PM Corrective/ Unplanned
Maintenance
Notification Creation
Work Order Creation
Work Order Execution &
Closing
PM Planned Maintenance
Preventive Maintenance
Planning
Schedule Plan
Work Order Generated
Automatically
Work Order Execution &
Closing
Mavin Project | SAP S/4HANA Implementation 13
The key elements of Plant Maintenance consist of master data and transactional processing
PM Basic Data Overview
Equipment
Notification
Maint. Order
Maintenance Plan
ArbeitsplanTask list
TskLstGrp C1
10 Center 1
20
30
Functional Location
Structuring of technical systems Maintenance processing
Master Data Transaction Data
Confirmation
Bill of material
Catalog
Mavin Project | SAP S/4HANA Implementation 14
Production Layout Example
Administration
Station 3
Station 1 Station 2
Station 4
Paint Booth DryPreparation
Trim 1 Trim 2
L e v e l 1 – P l a n t C o d e
Facilities
Mixing
L e v e l 2 – S h o p C o d e
Welding Shop
L e v e l 4 – W o r k s t a t i o n
L e v e l 3 – L i n e S e g m e n t
Assem
bly
Paint Shop
Office
Line 1
XXXX XX XX XXXX
3001
(Plant)
G1
(GA Shop)
T1
(Trim 1)
01
(Wkst 1)
SAP Representation
3001-G1-T1-0100
Functional Location Coding of Maintenance Site
Plant Code Shop CodeLine Segment
Code
Workstation
Code
Mavin Project | SAP S/4HANA Implementation 15
Technical Object StructureTechnical object structure are comprised of 4 elements:
Functional Location
Equipment
Bill of Materials (BOM): Assembly BOM, Equipment BOM, Funct. Loc. BOM
BOM Component
3001-G1-T1 Trim 1
3001-G1-T1-02 Station 02
2100000000
52000020
51000002
51000020
Assembly BOM
BOM Component
BOM Component
Casing
Pump SIHI 200
Chassis Liner
Main Bed Assembly
3001
3001-G1
Plant
General Assembly 1
Plant Code
Production Shop
Production Line
Workstation
Equipment
Functional Location: Functional locations are hierarchically ordered
structure that represent a plant, technical system, building, or part thereof, where
equipment can be installed
Equipment: An individual physical object for which
maintenance tasks should be performed or recorded
Able to remove and transfer to another functional location
Bills of Material Group of spare parts list, assigned to each
individual piece of equipment There are 3 different BOM Categories:
(1) Assembly BOM(2) Equipment BOM
(3) Functional Location BOM
BOM Component (Spare Part) Spare part used to replace when the part is
damaged
Mavin Project | SAP S/4HANA Implementation 16
Functional Location
Functional locations are hierarchically ordered structures that represent a technical system, building, or part
thereof according to the following criteria:
Spatial: “building 1”, “building 2”
Functional: “hydraulic press”, “mechanical press”
Process-oriented: “press”, “body”, “paint”, “assembly”, “vehicle audit”
Criteria for Functional Locations
• Execution of maintenance tasks• Recording of maintenance
tasks• Data collection over longer
periods• Cost monitoring by area• Analysis of usage conditions
V1 eScooter
V1-01 Press
V1-01-PRD Production
V1-01-PRD-01 Hydraulic
Press
V1-01-PRD-02 Pneumatic
Press
V1-02 Body
V1-03 Paint
V1-04 Assembly
V1-04-ADM Administration
V1-04-PRD Production
V1-04-PRD-01 Production
Line 1
V1-04-PRD-02 Production
Line 2
Mavin Project | SAP S/4HANA Implementation 17
Functional Location Structure Indicator
Edit mask XXXX-XX-XX-XX
Hier. Level 1 -2 -3 -4
A = Alpha
N = Numeric
X = Alphanumeric
Functional location structure indicator defines:
the naming convention and
hierarchy levels of the plant structure.
User has to refer to a structure indicator to create a functional location.
Level Edit Mask Type Description
Level 1 XXXX Alphanumeric Plant
Level 2 XX Alphanumeric Process/Shop
Level 3 XX Alphanumeric Production Line
Level 4 XX Alphanumeric Workshop
Functional Location Label Level
3001 Car Plant
3001-G1 GA 1 Shop
3001-G1-T1 Production Production Line
3001-G1-T1-01 Station 1 Workshop
3001-G1-T1-02 Station 2 Workshop
… … …
Mavin Project | SAP S/4HANA Implementation 18
Equipment
A piece of equipment is an individual object that is to be maintained independently, such as pumps, motors,
and vehicles for which:
maintenance tasks are to be performed and recorded
can be installed at functional locations
can be linked to a material if there is a need for inventory management
Criteria for Equipment
• Management of individual data• Recording of maintenance
tasks• Object-based recording of
costs• Evaluation of technical data• Recording of usage times
V1
Usage list
03/01/18-15/01/18 3001-G1-T1
V1-01-PRD-01 V4-02-PRD-01
15/01/18-31/22/99 3001-G1-T2
Equipment Master Record
General
Location
Organization
Structure
• Location data • Address
• Object type, Class• Manufacturer data…
• Higher-level function location• Superior equipment
• Account assignment data • Responsibilities
Mavin Project | SAP S/4HANA Implementation 19
Bills of Material
A bill of material
is a complete, formally structured list of the components of a product or assembly,
contains the description and object number of each component, the quantity and unit of measure.
In plant maintenance, BOM is used for the following two purposes:
Structure description
Spare parts planning
Worm Gear Assembly # Parts Qty.
1 Body 1
2 Worm wheel 1
3 Worm shaft 1
4 End bell 1
5 Flange 1
6 Seal cover 1
7 Bearing A 2
8 Bearing B 2
9 Oil seal A 1
10 Oil seal B 2
11 O ring 1
12 Oil plug 1
Mavin Project | SAP S/4HANA Implementation 20
A task list consists a series of standard maintenance operations that can be used repeatedly for different
maintenance orders. Three types of task lists are available:
Equipment task list
Functional task list
General maintenance task list
Task list
Operation 20
Operation 10
Material components
Production Resources
and Tools
Task list group
Work center Texts Control data Times
V1-01-PRD
Functional Location
20001001
Equipment
PRESS_WTG
(General)
Mavin Project | SAP S/4HANA Implementation 21
Transaction Data in Plant MaintenanceElements of maintenance process are:
Notification
Maintenance Order
Confirmation
Notification
What is the problem?• Where?• What time?• How long?
What kind of damage/ how did it fail? (eg. cracked, broken, burnt)
What is the cause/why did it fail? • Wear and tear• Corrosion• Lubrication failure• Fatigue
Maint. Order
What needs to be done?• Operations• No. of people• Planned hours
What component is required?• Stock spare part• External material• External Services
How much will it cost?• Planned Cost
Confirmation
Confirmation Data:• Actual Work
Mavin Project | SAP S/4HANA Implementation 22
Business Processes
Mavin Project | SAP S/4HANA Implementation 23
PM Work Order Process
NotificationMaintenance
Plan
Internal Labor
External Service
Non-Stock Spare Part
Stock Spare Part
Work Order
Operation
ComponentPR
Reservation
Confirmation
POExternal Service
PONon-Stock Spare Part
Good ReceiptExternal Service
Good ReceiptNon-Stock Spare Part
Good Issue
MaterialAvailability ?
PR
Yes
No
Good ReceiptTo Store
POStock Spare Part
MRP
DocumentTechnicalHistory
TECO
Settlement
Close
Maintenance Process
Related Process
Legend
Automatic Process
Mavin Project | SAP S/4HANA Implementation 24
Corrective and Unplanned Maintenance Process
PM process flow involves following processes, activities and roles
Request
Planning
Scheduling
Execution
Confirmation
1
2
3
4
5
Notification
• Technical object
• Description
• Date
• Malfunction
• Work to perform
• Internal/External
Resources
• Material
• Tools
• Order Release
• Paper Printout
• Capacity Leveling
• Availability Check
• Material Withdrawal planned/unplanned
• External Procurement
• Time Confirmation • Techn. Confirm.
Maint. Order
Maint. Order
Confirmation
Requestor
Maintenance Planner
RolesContentProcess Steps
Maintenance Planner
Technician /
Warehouse Clerk
Maintenance Planer/
Supervisor/ Controller
Technician /
Maintenance Planner
CompletionMaint. Order
• Techn. Completion • Order Settlement6
Maintenance Planner
Mavin Project | SAP S/4HANA Implementation 25
Data Captured in Notification
Notifications record important information about maintenance requests: what, where, when and how the
request is to be done.
Request
Planning
Scheduling
Execution
Confirmation
1
2
3
4
5
Notification
Maint. Order
Maint. Order
Confirmation
CompletionMaint. Order
6
Notification
• Date / Time / Reported by
• Description
• Maintenance object: Functional Location, Equipment
• Long text
• Breakdown info
• Object Part
• Damage
• Cause of damage
Activities• Activity
• Execution factors
Tasks• Dates
• Task description
Notification ItemsNotification Items
Catalog
Process Steps
Mavin Project | SAP S/4HANA Implementation 26
Catalog
Catalogs are used when maintaining notifications for the coded entry of results and activities.
Catalog Types
• 2 for Task
• 5 for Damage causes
• A for Activities
• B for Object part
• C for Damage
Codes
Code groups
Catalog Type: C - Damages
Code Group: MOT/01 – Engine damage
Code Short text
1000 Broken
1001 Overheated
1002 Cable Snapped
1003 Unbalanced
Code Group: PM01 – General damage
Code Short text
1000 Broken
1001 Torn
1002 Warped
1003 Leaking
Catalog Profile
restricted by
Catalog Type Code Group
5: Causes PM*
B: Object Parts PM*
Mavin Project | SAP S/4HANA Implementation 27
Maintenance Planning and Scheduling
Maintenance Order is the main working document that manages and specifies the maintenance tasks
Request
Planning
Scheduling
Execution
Confirmation
1
2
3
4
5
Notification
Maint. Order
Maint. Order
Confirmation
CompletionMaint. Order
6
Content:
o Scope of activities required for the maintenance job
o Identify the objects to be worked on
o Specify and plan the resources necessary
o Schedule the dates of the activities
o Capture the planned and actual costs incurred.
Planning:
Internal processing
o Internal workshops (work centers) are used to execute the work.
o Planned time and man hour costs are captured.
External processing
o External contractors are hired to perform the work.
o Purchase requests and purchase orders are raised to procure the external services.
Maintenance OrderProcess Steps
Mavin Project | SAP S/4HANA Implementation 28
Material Planning
Materials required for the job can be planned using stocked components
ComponentAssignment
Order Release
Material Reservation
Printout(if needed)
Goods Issue
Availability
Check
Automatic
Availability
Check
Stock Material• Item Category: L
Mavin Project | SAP S/4HANA Implementation 29
Non-stock Material• Item Category: N
Material Purchase
In-direct materials required for the job can be purchased using Non-stocked components.
ComponentAssignment
Purchase Requisition
Order Release
Goods Receipt
Invoice Receipt
Create & Release Purchase Order
CompanyInvoice
Mavin Project | SAP S/4HANA Implementation 30
Execution
Maintenance Activities can be carried out.
Request
Planning
Scheduling
Execution
Confirmation
1
2
3
4
5
Notification
• Technical object
• Description
• Date
• Malfunction
• Work to perform
• Internal/External
Resources
• Material
• Tools
• Order Release
• Paper Printout
• Capacity Leveling
• Availability Check
• Material Withdrawal planned/unplanned
• External Procurement
• Time Confirmation • Techn. Confirm.
Maint. Order
Maint. Order
Confirmation
CompletionMaint. Order
• Techn. Completion • Order Settlement6
Requestor
Maintenance Planner
RolesContent
Maintenance Planner
Technician /
Warehouse Clerk
Maintenance Planer/
Supervisor/ Controller
Technician /
Maintenance Planner
Maintenance Planner
Process Steps
Mavin Project | SAP S/4HANA Implementation 31
External Processing in Plant Maintenance
InvoiceVerification
Vendor Purchasing
Maintenance
GR for Service
Purchase Requisition
Purchase Order
CompanyInvoice
ArbeitsplanMaint. Order
0010 Operation 1
0020
0030
Actual Cost
Reason for External Processing
• Lack of Qualification• Insufficient Capacities• Outsourcing• Costs
External processing means that external companies are used or orders are assigned externally for processing
pending maintenance activities.
Services
Mavin Project | SAP S/4HANA Implementation 32
Confirmation & Completion
Technical Completion means completing the job and updating the maintenance order and notification
Request
Planning
Scheduling
Execution
Confirmation
1
2
3
4
5
Notification
Maint. Order
Maint. Order
Confirmation
CompletionMaint. Order
6
Time Confirmation:
o Capturing costs and time against the job
Technical Confirmation:
o Create notification to record findings of the job (if needed)
Technical Completion:
o Completing the order and notification to denote the job is technically completed.
Settlement Order:
o Maintenance order costs are settled to a cost receiver through Order Settlement.
Process Steps
Mavin Project | SAP S/4HANA Implementation 33
Preventive Maintenance
Preventive Maintenance is characterized by the fact that maintenance orders are planned in advance through
maintenance plans and automatically generated.
Maintenance Plan
Scheduling
Preventive Maint. Order
Execution
Confirmation
After a maintenance plan is scheduled, planned dates are created by the system.
When planned dates are due, preventive maintenance orders are automatically generated.
The required resources are already planned in the maintenance plan and are automatically scheduled for execution.
Completion
Mavin Project | SAP S/4HANA Implementation 34
Preventive Maintenance Types
Preventive Maintenance can be scheduled using time-based, performance-based, condition-based or predictive.
313130302929282827272626
2525242423232222212120201919
1818171716161515141413131212
111110109988776655
44332211
FFTTWWTTMMSSSS
20182018
313029282726
25242322212019
18171615141312
111098765
4321
FTWTMSS
2018
Preventive Maintenance
Time-basedPerformance-
basedCondition-
basedPredictive
Mavin Project | SAP S/4HANA Implementation 35
Time-based Strategy Plan
Scheduling Data
ArbeitsplanTask list
TskLstGrp C1
10 Center 1
20
30
Maintenance Item
Maintenance Plan
3 months
Maintenance
Item
Reference ObjectResponsibilities /
Planning data
In time-based preventive maintenance, maintenance tasks are triggered after a specific time period has
elapsed
Mavin Project | SAP S/4HANA Implementation 36
Interrelationships of Preventive Maintenance
Operations
Material
Maintenance Packages
MAINTENANCE TASK LIST
Scheduling Parameters
Maintenance Packages
MAINTENANCE STRATEGY
Object / Object lists
Maintenance Task List
Organization and Responsibility
MAINTENANCE ITEMTECHNICAL OBJECT
Functional Location
Equipment
SCHEDULE
Start Date
Scheduling Parameter
Scheduling Parameters
Maintenance Item(s)
Call Object (Orders, Notifications,…)
MAINTENANCE PLAN
Order/Notification
Automatically created by the system
Determine due date to generate maintenance call object
SCHEDULING MAINT. PLAN CALL OBJECT
Compulsory
Optional
Legend
Mavin Project | SAP S/4HANA Implementation 37
The refurbishment business process is characterized by spare parts being held as reserves in the warehouse
There are different statuses for the spare parts (e.g., new, functional, faulty)
Refurbishment of Spare Parts
Production
Spare PartWarehouse
Refurbishment
Procurement Scrapping
ProcureSpare Parts
Functional Faulty
Refurbished To be refurbished
Can no longerbe refurbished
1 52
4
3
Mavin Project | SAP S/4HANA Implementation 38
Integration
Mavin Project | SAP S/4HANA Implementation 39
Integration with Other Modules
NotificationNotification
Maintenance OrderMaintenance Order
Goods IssueGoods Issue
Order SettlementOrder Settlement
CompletionConfirmationCompletionConfirmation
Purchase OrderPurchase Order
Goods ReceiptGoods Receipt
Actual Cost UpdateActual Cost Update
G/L Account UpdateG/L Account Update
PS
FI/CO
PM
MM
Project SystemProject System
Purchase RequisitionPurchase Requisition
Stock InventoryStock Inventory
Project System: is used to plan and monitor maintenance project, e.g. shut down project
Materials Management: will generate material reservation again Inventory or purchase requisition in Procurement
Financial and Controlling: Order costing will determine the repair costs in the maintenance order
Mavin Project | SAP S/4HANA Implementation 40