Business Process Procedures
EHP4 for SAP ERP 6.0June 2010English
APOLogistics Planning (144)
SAP AGDietmar-Hopp-Allee 1669190 WalldorfGermanyBusiness Process Documentation
Copyright
Copyright 2010 SAP AG. All rights reserved. No part of this publication may be reproduced or transmitted in any form or for any purpose without the express permission of SAP AG. The information contained herein may be changed without prior notice. Some software products marketed by SAP AG and its distributors contain proprietary software components of other software vendors. Microsoft, Windows, Excel, Outlook, and PowerPoint are registered trademarks of Microsoft Corporation. IBM, DB2, DB2 Universal Database, System i, System i5, System p, System p5, System x, System z, System z10, System z9, z10, z9, iSeries, pSeries, xSeries, zSeries, eServer, z/VM, z/OS, i5/OS, S/390, OS/390, OS/400, AS/400, S/390 Parallel Enterprise Server, PowerVM, Power Architecture, POWER6+, POWER6, POWER5+, POWER5, POWER, OpenPower, PowerPC, BatchPipes, BladeCenter, System Storage, GPFS, HACMP, RETAIN, DB2 Connect, RACF, Redbooks, OS/2, Parallel Sysplex, MVS/ESA, AIX, Intelligent Miner, WebSphere, Netfinity, Tivoli and Informix are trademarks or registered trademarks of IBM Corporation. Linux is the registered trademark of Linus Torvalds in the U.S. and other countries.Adobe, the Adobe logo, Acrobat, PostScript, and Reader are either trademarks or registered trademarks of Adobe Systems Incorporated in the United States and/or other countries.Oracle is a registered trademark of Oracle Corporation. UNIX, X/Open, OSF/1, and Motif are registered trademarks of the Open Group. Citrix, ICA, Program Neighborhood, MetaFrame, WinFrame, VideoFrame, and MultiWin are trademarks or registered trademarks of Citrix Systems, Inc. HTML, XML, XHTML, and W3C are trademarks or registered trademarks of W3C, World Wide Web Consortium, Massachusetts Institute of Technology. Java is a registered trademark of Sun Microsystems, Inc. JavaScript is a registered trademark of Sun Microsystems, Inc., used under license for technology invented and implemented by Netscape. SAP, R/3, SAP NetWeaver, Duet, PartnerEdge, ByDesign, SAP Business ByDesign, and other SAP products and services mentioned herein as well as their respective logos are trademarks or registered trademarks of SAP AG in Germany and other countries. Business Objects and the Business Objects logo, BusinessObjects, Crystal Reports, Crystal Decisions, Web Intelligence, Xcelsius, and other Business Objects products and services mentioned herein as well as their respective logos are trademarks or registered trademarks of Business Objects S.A. in the United States and in other countries. Business Objects is an SAP company.All other product and service names mentioned are the trademarks of their respective companies. Data contained in this document serves informational purposes only. National product specifications may vary.These materials are subject to change without notice. These materials are provided by SAP AG and its affiliated companies ("SAP Group") for informational purposes only, without representation or warranty of any kind, and SAP Group shall not be liable for errors or omissions with respect to the materials. The only warranties for SAP Group products and services are those that are set forth in the express warranty statements accompanying such products and services, if any. Nothing herein should be construed as constituting an additional warranty.Icons
IconMeaning
Caution
Example
Note
Recommendation
Syntax
External Process
Typographic Conventions
Type StyleDescription
Example textWords or characters that appear on the screen. These include field names, screen titles, pushbuttons as well as menu names, paths, and options.
Cross-references to other documentation.
Example textEmphasized words or phrases in body text, titles of graphics and tables.
EXAMPLE TEXTNames of elements in the system. These include report names, program names, transaction codes, table names, and individual key words of a programming language, when surrounded by body text, for example, SELECT and INCLUDE.
Example textScreen output. This includes file and directory names and their paths, messages, source code, names of variables and parameters as well as names of installation, upgrade and database tools.
EXAMPLE TEXTKeys on the keyboard, for example, function keys (such as F2) or the ENTER key.
Example textExact user entry. These are words or characters that you enter in the system exactly as they appear in the documentation.
Variable user entry. Pointed brackets indicate that you replace these words and characters with appropriate entries.
Contents
5Logistics Planning
51Purpose
52Prerequisites
52.1Master Data and Organizational Data
62.2Business Conditions
62.3Preliminary Steps
72.4Roles
83Process Overview Table
104Process Steps
104.1Sales and Operation Planning
134.2Long Term Planning
235Follow-Up Processes
235.1Operational Production Planning and Control
246Appendix
246.1Reversal of Process Steps
246.2SAP ERP Reports
Logistics Planning
1 Purpose
The purpose of logistics planning is to make sure that future demand can be satisfied by your companys available resources and to point out situations where demand cannot be met in time or in the desired quantities.
This process sometimes is called Sales and Operations Planning. The process usually takes place in a simulative mode and at an aggregated (usually product group) level. Once a feasible production plan is found that satisfies demand it can be used as the basis for operational production planning (MRP and Detailed Capacity Scheduling).
The Best Practices scenarios in this section cover the following planning workflow:
Planning/forecasting of future demand
Aggregated production planning including capacity check to check at product group level if demand can be satisfied (using the SOP functionality)
Transfer of results to Long Term Planning (using the LTP module) to enable simulation of material requirements, based on the production plans Planning takes place in separate (simulative) planning versions within LTP
Review and adjustments of planned requirements as needed
Once the simulated requirements are accepted, the demand (independent requirements) is then transferred to active demand management for detailed MRP and Production Planning / Scheduling in the active version.
2 Prerequisites
2.1 Master Data and Organizational Data
A range of indispensable master and organizational data was created in your ERP system in the implementation phase, such as the data that reflects the organizational structure of your company, and master data that suits its operational focus, such as master data for materials, vendors, customers, and so on.This master data usually consists of standardized SAP Best Practices default values and enables you to go through the process steps of this scenario.
You can test the scenario with other material, or organizational data for which you have created master data. To find out how to create master data, refer to the Master Data Procedures documentation.
Use the following master data in the process steps described in this document:
Master dataValueOther Master DataBus. ConditionComments
Product Group
Level 100001B001
You have completed all steps described in the Business Process Documentation Sales Qty Budget and Transfer to SOP (with CO-PA), Revenue Planning (172).
The product groups corresponds to the product hierarchies
Product Group
Level 200001B000100000001
Product Group
Level 200001B000100000002
Product Group
Level 200001B000100000003
Plant1000(1100)
SOP version 001Use these versions in the demo script
LTP Version 001Use these versions in the demo script
2.2 Business Conditions
The business process described in this Business Process Documentation is part of a bigger chain of integrated business processes or scenarios. As a consequence, you must have completed the following processes and fulfilled the following business conditions before you can start going through this scenario:
Business conditionScenario
You have completed all steps described in the Business Process Documentation Prerequisite Process Steps (154).Prerequisite Process Steps (154)
You have completed all steps described in the Business Process Documentation Sales Qty Budget and Transfer to SOP (with CO-PA), Revenue Planning (172). In this scenario, you perform revenue planning. The result is a sales plan in value and/or quantity. Usually the sales plan is based on the sales history and is in quarterly, monthly, or weekly buckets.Sales Qty Budget and Transfer to SOP (with CO-PA), Revenue Planning (172)
You have completed all steps described in the Business Process Documentation Sales Quantity forecast (179).Sales Quantity forecast (179)
2.3 Preliminary Steps
No preliminary steps are required to test this scenario.
2.4 Roles
Use
The following roles must have been installed to test this scenario in the SAP NetWeaver Business Client (NWBC). The roles in this Business Process Documentation must be assigned to the user or users testing this scenario. You do not need these roles if you are not using the NWBC interface, but the standard SAP GUI.
Prerequisites
The business roles have been assigned to the user who is testing this scenario.
Business roleTechnical nameProcess step
Employee (Professional User)SAP_NBPR_EMPLOYEE-SAssignment of this role is necessary for basic functionality.
Strategic PlannerSAP_NBPR_STRATPLANNER-SAll process steps
3 Process Overview Table
Process stepExternal process referenceBusiness conditionBusiness roleTrans-action codeExpected results
Sales Qty Budget and Transfer to SOP (with CO-PA), Revenue PlanningSee scenario Sales Qty Budget and Transfer to SOP (with CO-PA), Revenue Planning (172)See scenario (172)See scenario (172)The sales plan is created.
Sales Quantity forecast (179)See scenario Sales Quantity forecast (179)See scenario (179)See scenario (179)The sales plan is created.
Demand Verification (Check Sales Plan)After sales figures have been transferred to SOP Strategic PlannerMC76Sales Plan has been verified
Create Rough-Cut Production PlanAfter Sales plan has been checkedStrategic PlannerMC76Production Plan created
Transfer Rough Cut Production plan to Inactive Demand Management Production Plan has been checkedStrategic PlannerMC75The Production Plan from SOP has been transferred to inactive demand management
Create Long Term Planning Scenario Before running simulated LTP MRPStrategic PlannerMS31LTP Planning scenario is created
Execute LTP MRP RunStrategic PlannerMS01The LTP MRP run is simulated.
Evaluate Capacity RequirementsStrategic PlannerCM38Capacity consumption updated on cost center
Activate a planned independent requirements versionYou have evaluated and adjusted the simulative planning result Strategic PlannerMS32Planned independent requirements version is activated for planning scenario
Copy to Demand Management (active version)Strategic PlannerMS64Active version created in Demand Management
Operational Production Planning and ControlSee all production scenariosSee all production scenarios See all production scenarios See all production scenarios
4 Process Steps
4.1 Sales and Operation Planning
Sales & Operation Planning (SOP) is the link between sales planning and manufacturing.
It is a forecasting and planning transaction to enable sales, production, inventory targets to be reached based on historical, existing, and estimated future data. In the process described below we use SOP to:
Verify the sales (demand) plan coming from COPA or other sources
Create a Rough-cut production plan aimed to satisfy demand and to meet inventory targets
Visualize capacity utilization of the critical resources (usually the bottleneck resources) to verify the feasibility of the plan at an aggregated level.
SOP is suitable for long- and medium-term planning.
In this process, you view the S&OP figures. This is done after sales figures have been transferred from CO-PA to SOP.
You can visualize the following key figures
Sales plan
Production plan
Projected Stock
4.1.1 Demand Verification (Check Sales Plan)
Use
In this activity, you check the sales plan at material level. In this scenario it is assumed that the sales plan has been created at product group level.
Therefore you can disaggregate your sales figures to a material to verify demand at an aggregated level.
Also the opposite direction is possible (but not shown in this scenario): If your sales plan has been created at product group level you can disaggregate the plan according to predefined proportional factors to the material level. In this case it is useful to define the proportional factors according to historical sales figures to come to realistic forecasts at material level.
Prerequisites
This can be done after sales figures have been transferred to SOP from CO-PA.
Procedure
1. Access the transaction choosing one of the following navigation options:
Option 1: SAP Graphical User Interface (SAP GUI)
SAP menuLogistics ( Production ( SOP ( Disaggregation ( Break Down PG Plan
Transaction codeMC76
Option 2: SAP NetWeaver Business Client (SAP NWBC) via business role
Business roleStrategic Planner(SAP_NBPR_STRATPLANNER-S)
Business role menuProduction ( SOP ( Disaggregation ( Disaggregation: Planning
2. On the initial screen, make the following entries:
Field nameDescriptionUser action and valuesComment
Product group00001B000100000001Product group ID defined in central master data BB in layer 2.
Plant1000Production Plant
Inactive versionSelect the button.
Version001Check which version must be used
3. Choose Inactive version.
4. In the Product group members dialog box, select the materials.
5. In the Disaggregation dialog box, select Create sales plans and Disaggregate sales plan and choose Enter.
6. If the Check proportions dialog box displays, choose Yes.
7. Save your entries.Result
You have viewed the S&OP figures on product group level and created the sales plan on material level based on the sales plan on product group level.
4.1.2 Create Rough-Cut Production Plan
Use
In this activity, you generate the rough cut production plan based on your sales forecast. For this you have several options (see below).
Procedure
1. Access the transaction choosing one of the following navigation options:
Option 1: SAP Graphical User Interface (SAP GUI)
SAP menuLogistics ( Production ( SOP ( Disaggregation ( Break Down PG Plan
Transaction codeMC76
Option 2: SAP NetWeaver Business Client (SAP NWBC) via business role
Business roleStrategic Planner(SAP_NBPR_STRATPLANNER-S)
Business role menuProduction ( SOP ( Disaggregation ( Disaggregation: Planning
You are still in the transaction for Demand verification (see previous chapter) and continue without leaving it. If you have left the transaction run through step 1 - 5 of this process before continuing with the next step.
2. From the menu, choose Edit ( Create production plan ( Synchronous to sales. This makes production figures equal to sales at product group and material levels.
3. In standard SOP, additional strategies for generating production plants exist. These can be activated from the following menu path:Edit ( Create production plan ( a. Production quantities are the same as sales quantities in each period ("synchronous to sales")
b. Production quantities are such that target stock levels are reached
c. Production quantities are such that target days supplies are reached
d. Production quantities are such that the stock level at the end of each period is zero.
Result
You have created the production plan on material level based on the sales plan on product group level.4.1.3 Transfer Rough-Cut Production Plan to Inactive Demand Management
Use
In this activity, you transfer the inactive version of the production plan from SOP to Demand Management where the quantities are posted as planned independent requirements.
For several purposes you can post the production plan at first in an inactive version.
In our scenario we use inactive versions for the following purposes:
Version 001 for simulation and long term procurement purposes (forecast)described in this document
Version 002: for supporting the annual budgeting process (see 173: SOP through Long Term Planning Transfer to LIS/PIS/Capacity)
Procedure
1. Access the transaction choosing one of the following navigation options:
SAP menuLogistics ( Production ( SOP ( Planning ( For Product Group ( Transfer Product Group to Planning
Transaction codeMC75
Option 2: SAP NetWeaver Business Client (SAP NWBC) via business role
Business roleStrategic Planner
(SAP_NBPR_STRATPLANNER-S)
Business role menuProduction ( SOP ( Product Group ( Transfer PG to Demand Management
2. Make the following entries:
Field nameDescriptionUser action and valuesComment
Product group00001B000100000001
Plant1000Production Plant
Version001 Selectable from dropdown.
Depends on version used in scenario: Quarterly Plan - Sales Quantity Forecast with CO-PA (179)
Production plan for material or PG memberSelected
From dateTypically first day of current month
To dateEighteen months in the future
Requirements typeLeave blank
Version01
ActiveDeselected
Make sure that you deselect Active on the initial screen to make sure it is inactive in demand management. To transfer a single material, use transaction MC74.
3. Choose Transfer now.
Result
The inactive version is transferred to demand management. To display the inactive version for a single material in Demand Management, use transaction MD63 (or menu path Logistics ( Production ( Production Planning ( Demand Management ( Planned Independent Requirements ( Display).
4.2 Long Term Planning
In long-term planning, future demand programs are simulated within a planning run. This allows you to calculate capacity requirements, activity type requirement of the cost centers, and of the requirement of purchased parts.
The demand programs that can be simulated may include planned independent requirements and/or sales orders.
You can evaluate and optimize the simulation regarding material requirements planning, capacity planning, order volumes, purchasing budget, cost center planning, and inventory controlling. Following the evaluation of the simulative planning results, you can replace the current demand program with the preferred version in long-term planning and can continue it there.
You can transfer the data for external procurement to the purchasing information system using a special report and evaluate it there.
The principle of long-term planning is to simulate different versions of the demand program. The simulation can take into account operative data (for example, master data, sales orders, purchase orders, production orders).
The simulation can be used to optimize the demand program and the production and procurement data regarding material requirements planning, capacity planning, order volumes, purchasing budget, cost center planning, and inventory controlling.
Long-term planning can also be executed based on operative master data: BoMs, routings, work centers, and material masters. This means you do not have to create any new operative data.
4.2.1 Create Long Term Planning Scenario
Use
For simulation purposes, you set up LTP-Planning scenarios that represent planning areas you can use independently from each other.
In this activity, you create the LTP Planning Scenario.
If the LTP planning scenario already exists, use transaction MS32 to make changes.
Procedure
1. Access the transaction choosing one of the following navigation options:
SAP menuLogistics ( Production ( Production Planning ( Long-Term Planning ( scenario ( Create
Transaction codeMS31
Option 2: SAP NetWeaver Business Client (SAP NWBC) via business role
Business roleStrategic Planner
(SAP_NBPR_STRATPLANNER-S)
Business role menuProduction ( Production Planning ( Long-Term Planning ( Create Planning Scenario
Always use scenario 001. If the scenario already exists, change the scenario according to the steps described below. Choose Planning Scenario ( Change or switch to change mode. Choose Edit ( Cancel Release to reset the released status to change the existing values.
2. Make the following entries:
Field nameDescriptionUser action and valuesComment
Planning scenario001
Always use planning scenario 001. If the scenario already exists skip this process step.
Long-term planningSelected
3. Choose Enter.
4. Make the following entries:
Field nameDescriptionUser action and valuesComment
From date
To dateEighteen months in the future
Dep.reqmts for reorder point materialsSelected
Consider sales ordersSelected
Include firm receiptsSelected
Include firm purchase requisitionsSelected
Include firm planned ordersSelected
5. Choose Planned Independent Requirements.
6. In the dialog box, choose New entry.
7. Make the following entries:
Field nameDescriptionUser action and valuesComment
Version01Inactive version from demand management
From date
To dateEighteen months in the future
8. Choose Confirm.
9. Choose Plants.
10. In the dialog box, choose New entry.
11. Make the following entries:
Field nameDescriptionUser action and valuesComment
Planning plant1000You can repeat the steps for all planning plants.
12. Choose Confirm.
13. Choose Release and Save.
Result
The LTP Planning scenario is created. Make a note of the Planning Scenario number here:
_________
4.2.1.1 Execute LTP MRP Run
Use
In this activity, you simulate the execution of the LTP MRP run.
Procedure
1. Access the transaction choosing one of the following navigation options:
Option 1: SAP Graphical User Interface (SAP GUI)
SAP menuLogistics ( Production ( Production Planning ( Long-term Planning ( Long-term planning ( Planning run ( Online
Transaction codeMS01
2. On the Long-Term Planning Run screen, enter the following entries:
Field nameDescriptionUser action and valuesComment
Planning Scenario
Plant1000Production Plant
Display material listSelected
Scheduling2Lead time scheduling and capacity planning
3. Choose Enter.
4. The system displays the message Please check input parameters.
5. Choose Enter.
6. The system displays the message To start the planning run, press enter. Choose Enter.
Use transaction MS04 to check the planning results for planning scenario 001, material Finished Good MTO (for example F1000-M1) in plant 1 (1000) or in the NWBC role menu Production ( Production Planning ( Long-Term Planning( Planning Scenario: Stock/Reqmts List Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business RoleBusiness roleStrategic Planner
(SAP_NBPR_STRATPLANNER-S)
Business role menuProduction ( Production Planning ( Long-Term Planning ( Long-Term Planning: Total Planning
1. Select the planning scenario you created one step before, choose button Long-Term Planning and select Long-Term Planning Run Online from the menu.
2. On the Long-Term Planning Run screen, check the following parameters and press enter.
Field nameDescriptionUser action and valuesComment
Planning Scenario
Plant1000Production Plant
Display material listSelected
Scheduling2Lead time scheduling and capacity planning
3. The system displays the message Please check input parameters.
4. Choose Enter.
5. The system displays the message To start the planning run, press enter. Choose Enter.
Use transaction MS04 to check the planning results for planning scenario 001, material Finished Good MTO (for example F1000-M1) in plant 1 (1000) or in the NWBC role menu Strategic Planning ( Long-Term Planning (LTP) ( Planning Scenario: Stock/Reqmts List ResultYou have run the simulated LTP MRP.
4.2.1.2 Evaluate Capacity Requirements
Use
In this activity, you perform capacity planning for all relevant work centers you want to check.
After you run this activity, you can assess if the plan is acceptable.
Procedure
1. Access the transaction choosing one of the following navigation options:
SAP menuLogistics ( Production ( Production Planning ( Long-Term Planning ( Evaluations ( Capacity requirements ( Work centers
Transaction codeCM38
2. Enter Profile YBLTP01 - LTP: Capacity requirements for AOP.
Use transaction SU01 or SU3 (SAPGUI) to predefine the profile in your user parameter or in the role menu (NWBC) IT-Administration ( User Management ( User Maintenance (Role: SAP_NBPR_IT_ADMIN-S)
Parameter ID: CYX
Parameter Value: YBLTP01
3. Make the following entries
Field nameDescriptionUser action and valuesComment
Planning Scenario Long-Term PlanningFrom previous steps
Work CenterSelect a work center such as Assembly
PlantPlant 1 (1000)
4. From the menu, choose Settings General and make / check the following entries:
Field nameUser action and values
Cumulation of requirements X
HierarchyTOT_PLANT
Plant1000
Entry typeD
Start ( )
Int.finish (mm/yyyy)
5. Choose Standard Overview.
6. Repeat this activity for each work center of your planning model (which is used in the routings of the materials that have been planned).
Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role
Business roleStrategic Planner
(SAP_NBPR_STRATPLANNER-S)
Business role menuProduction ( Production Planning ( Long-Term Planning ( Capacity Leveling L-T Planning
1. Select the planning scenario you created before.
2. On the Capacity Planning: Selection screen, choose More ( Planning ( Profiles ( Overall profile.3. Select the profile YBLTP01 - LTP: Capacity requirements for AOP and choose Continue.
Use transaction SU01 or SU3 (SAPGUI) to predefine the profile in your user parameter or in the role menu (NWBC) Administration ( User Management ( User Maintenance (Role: SAP_NBPR_IT_ADMIN-S)
Parameter ID: CYX
Parameter Value: YBLTP01
4. Make the following entries
Field nameDescriptionUser action and valuesComment
Planning Scenario Long-Term PlanningFrom previous steps
Work CenterSelect a work center for example Assembly
PlantPlant 1 (1000)
5. From the menu, choose More( Settings General and make / check the following entries:
Field nameDescriptionUser action and valuesComment
Cumulation of requirements X
HierarchyTOT_PLANT
Plant1000
Entry typeD
Start ( )
Int.finish (mm/yyyy)
6. Choose Continue and Standard Overview.
7. Repeat this activity for each work center of your planning model (which is used in the routings of your planed materials).
Result
Capacity planning has been checked. If the plan is acceptable, you can execute the next step.
4.2.1.3 Activate a planned independent requirements version
Use
Once you have evaluated and adjusted the simulative planning result, you can activate a planned independent requirements version in the planning scenario and, if necessary, you can give it a new version number. As the validity period of the new version, the system either enters the period recorded when maintaining the simulative planned independent requirements version, or, if no period has been maintained here, the system records the planning period of the planning scenario. Once you have activated the planned independent requirements version, it is valid for operative planning.
Procedure
1. Access the transaction choosing one of the following navigation options:
SAP menuLogistics ( Production ( Production planning ( Long-Term Planning ( scenario(> Change
Transaction codeMS32
2. Make the following entries:
Field nameDescriptionUser action and valuesComment
Planning scenarioEnter a new number and description.
3. Choose Activate ind.req.
4. Make the following entries:
Field nameDescriptionUser action and valuesComment
VersionSelected
Target version00Active version
Test modeDeselected
Create listSelected
5. Choose Activate.
Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business RoleBusiness roleStrategic Planner
(SAP_NBPR_STRATPLANNER-S)
Business role menuProduction ( Production Planning ( Long-Term Planning ( Change Planning Scenario
1. Make the following entries and choose Enter:
Field nameDescriptionUser action and valuesComment
Planning scenarioChoose an existing scenario (001).
2. Choose Activate Independent Requirements.
3. Make the following entries:
Field nameDescriptionUser action and valuesComment
VersionSelected
Target version00Active version
Test modeDeselected
Create listSelected
4. Choose Activate.
Result
You have activated your planned independent requirements version.
4.2.1.4 Copy to Active Demand Management
Use
Alternatively to the previous step you can copy the LTP Version 01 into an active version (such as 00). In this activity, you create an active version in Demand Management by the following procedure.
The advantage of this step is the activation in batch mode.
Procedure
1. Access the transaction choosing one of the following navigation options:
SAP menuLogistics ( Production ( Production Planning ( Long-Term Planning ( Planned indep.reqmts ( Copy version
Transaction codeMS64
Option 2: SAP NetWeaver Business Client (SAP NWBC) via business role
Business roleSAP_AIO_STRATEGICPLANNER-S(Strategic Planner-Professional User)
Business role menuProduction ( Production Planning ( Demand Management ( DM) ( Create Simulation Version
2. Make the following entries:
Field nameDescriptionUser action and valuesComment
PlantEnter all plants.
MaterialLeave blank
From date
To dateEighteen months in the future
Source version01Inactive version from demand management
Target version00
Target version activeSelected
No database changes (Simulation)Deselected
3. Choose Execute.
Result
An active version is created in Demand Management. To display the active version for a single material in Demand Management, use transaction MD63 (or menu path Logistics ( Production ( Production Planning ( Demand Management ( Planned Independent Requirements ( Display).
5 Follow-Up Processes
You have finished all activities that are part of the business process described in this document.
To accomplish subsequent activities of this business process, carry out the process steps described in one or more of the following scenarios, using the master data from this document.
5.1 Operational Production Planning and Control
Use
In this activity, you may run the different production scenarios.
Procedure
To execute this activity, run the following scenarios
Make-to-Stock Production - Discrete Industry (145)
Make-to-Stock Production - Process Industry (146)
Make-to-Order Production with Variant Configuration (147)
Make-to-Order Production w/o Variant Configuration (148)
Repetitive Manufacturing (149).
6 Appendix
6.1 Reversal of Process Steps
In the following section, you can find the most common reversal steps that you can take to reverse some of the activities described in this document,
Create Long Term Planning Scenario
Transaction code ( SAP GUI)MS31
Reversal:Change Planning scenario
Transaction code ( SAP GUI)MC75
Business roleSAP_BPR_STRATEGICPLANNER-S
Business role menuStrategic Planning ( Long-Term Planning (LTP) ( Change Planning Scenario
CommentYou can change the planning scenario
6.2 SAP ERP Reports
Use
The table below lists the most frequently used reports that help you to obtain additional information on this business process.
You can find detailed descriptions of the individual reports in the following BPD documents that provide a comprehensive compilation of all important reports:
Financial Accounting: SAP ERP Reports for Accounting (221) Logistics Processes: SAP ERP Reports for Logistics (222)The descriptions of some reports that are an indispensable part of the process flow may be located directly in the section where they belong.
Reports
Report titleTransaction code (SAP GUI)Business Role (NWBC)Business Role Menu (NWBC)Comment
Long-Term Capacity PlanningCM38Strategic PlannerProduction ( Production Planning ( Long-Term Planning ( Capacity Leveling L-T PlanningThe capacity evaluation is displayed.
Change PlanMC82Strategic PlannerProduction(SOP ( Change Plan for Product GroupDisplay of planning version.
Evaluation of Product Group PlanningMD47Production PlannerProduction ( Evaluations( Reports ( Product Group Planning Evaluation Planning situation is displayed.
Long-Term Planning: MRP-listMS05Strategic PlannerProduction ( Production Planning ( Long-Term Planning ( Long-Term Planning: Display MRP ListSimulation of MRP-list
SAP AG
Page 25 of 25