SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
San Francisco-Oakland Bay BridgeSan Francisco-Oakland Bay BridgeEast Span Seismic Safety ProjectEast Span Seismic Safety Project
March 12, 2002March 12, 2002
Contractor Outreach
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
Project LimitsProject Limits
Project IntroductionProject Introduction
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
YBITRANSITION
SUSPENSION SKYWAY
OAKLANDAPPROACH
SKYWAYSUSPENSION
YBI
TRANSITION
OAKLANDAPPROACH
OAKLANDGEOFILL
Existing Bridge
Contract Limits
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
Project IntroductionProject Introduction
Bridge Cross SectionBridge Cross Section
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
Replacement - Computer simulationReplacement - Computer simulation
AlternativesAlternatives
Photo simulation of the Replacement Alternative N-6 as viewed from Yerba Buena Island
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
YBI Eastbound On-RampYBI Eastbound On-Ramp
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
Yerba Buena IslandYerba Buena Island
Heavy topography -- 60 meter elevation change
Steep slopes
Narrow winding roads
USCG base for 24 hour Search and Rescue unit
Lots of underground utilities
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
Contractor Access on YBIContractor Access on YBI
Potential Barge Mooring Areas
USCG Search and Rescue Base
Vehicular Access
USCGAccess
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
Environmental Constraints on YBIEnvironmental Constraints on YBI
USCG Facilities
Historic Structures
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
YBI Special Aquatic SitesYBI Special Aquatic Sites
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
Construction IssuesConstruction Issues
STAGE 1 Construct new
Bridge Construct
eastbound (EB) and westbound (WB) detours
Construction StagingConstruction StagingReplacement AlternativeReplacement Alternative
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
Construction IssuesConstruction Issues
STAGE 2 Shift traffic on to
detours at Oakland TD
Construct new WB approach at Oakland TD
Complete construction of detours at YBI
Construction StagingConstruction StagingReplacement AlternativeReplacement Alternative
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
Viaduct Modifications:• Retrofit existing YBI viaduct• Widen existing viaduct for westbound detour• Construct temporary portal frame• Remove columns
YBI Viaduct Modifications
To Oak
land
To
San
Fra
ncis
co
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
Remove existing Caltrans electrical substation and garage
Electrical Substation
WB On-rampto SF
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
Reroute WB Traffic
Plan
WB detour
Typical Section
Route WB traffic to WB detour
Existing Bridge
EB Detour
WB EB (lower deck)
Plan
WB detour
Existing Bridge
EB Detour
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
EB
WB
WB Traffic is on new Skyway, new SAS, and WB detour.
EB Traffic is still on existing bridge (lower deck).
Traffic
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
Portal Frame and Seat Extension
Plan
WB detour
EB Detour
Construct seat extension at south side
… and construct portal frameExisting Bridge
Typical Section
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
Load Transferred to Portal Frame
Plan
WB detour
EB Detour
Typical Section
Portal frame:• Supports upper deck• Creates opening for EB detour operation
Existing Bridge
WB
EB
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
Eastbound Detour
(7) Route EB Traffic to EB Detour
Existing Bridge
To San Francisco
To Oakland
Eastbound Detour
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
Construction IssuesConstruction Issues
STAGE 3 Shift traffic to new
WB bridge and detours at YBI
Construct EB landing at Oakland TD
Remove existing bridge from Bent 48 to YB1
Construction StagingConstruction StagingReplacement AlternativeReplacement Alternative
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
Construction IssuesConstruction IssuesConstruction StagingConstruction Staging
Replacement AlternativeReplacement Alternative
STAGE 4 Construct remaining
section of the new bridge at YBI
Shift all traffic to new bridge
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
Construction IssuesConstruction IssuesConstruction StagingConstruction Staging
Replacement AlternativeReplacement Alternative
STAGE 5 Dismantle existing
bridge
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
Yerba Buena Island Traffic Yerba Buena Island Traffic ImpactsImpacts
Westbound on-ramp (east side of island)Westbound on-ramp (east side of island)
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
Yerba Buena Island Traffic Yerba Buena Island Traffic ImpactsImpacts
Eastbound off-ramp (east side of island)Eastbound off-ramp (east side of island)
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
Yerba Buena Island Traffic Yerba Buena Island Traffic ImpactsImpacts
Southgate RoadSouthgate Road
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
Cut columns to transfer load to portal frame
Number ofClosures
Activity Requiring EB and WB Full Bridge Closures
4
Hours per Closure
6
Closure Alternatives
28
Simultaneous Eastbound and Westbound Full Bridge Closures
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
Activity Requiring EB Only Full Bridge Closures
6 23Remove 96 upper deck concrete panels
8 13Remove 48 stringers and 9 floor beams
Remove side trusses and replace steel curbs with temporary “K” rails
12 11
Closure Alternatives
Number ofClosures
Hours per Closure
Eastbound Only Full Bridge Closures
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
UtilitiesUtilities
Westbound Eastbound
6 NPS ReclaimedWater
10 NPS Sanitary Sewer with
18 NPS Casing
12 NPS Water
NOT TO SCALE
CT Airand Water
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
FLOOR BEAM SECTION
INSTALLATION OF UTILITIES INSIDE MAIN SPANINSTALLATION OF UTILITIES INSIDE MAIN SPAN
E LINE
UTILITY TRAYS
TRAVELER
BIKE PATH
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
YBI SUBSTATION
MACALLA ROAD
USCG ROAD
W LINE
E LINE
UTILITY TRENCH PIER W2
PROPOSED UTILITY RELOCATIONS ON YBIPROPOSED UTILITY RELOCATIONS ON YBI
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
ELEVATION
CONCRETE DUCT BANK ANCHORS
SECTION A-A
SECTION B-B
SECTION C-C
ELEVATION
SLOPE STABILIZATION
UTILITY DUCT INSTALLATION DETAILSUTILITY DUCT INSTALLATION DETAILS
1.500
0.300
0.800
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
PLAN AT GRADE
PLAN AT BOTTOM DECK
SECTION A-AMAIN SPAN DETAILS OF CONDUIT
RISER UP TO W2 WB
TRAYS
CONDUITS
ROUTING OF UTILITY DETAILS AT PIER W2ROUTING OF UTILITY DETAILS AT PIER W2
W2
C.L. PIER W2
UTILITY TRAYS
TRAVELER
RETAINING WALL
SFOBB East Span Seismic Safety ProjectSFOBB East Span Seismic Safety Project
• Covers domestic transportation of merchandise
• Requires floating cranes to be domestically built, owned, and operated
• Foreign floating cranes can be used as long as they do not “transport” merchandise
JONES ACT INFORMATION