SAN FRANCISCO-OAKLAND BAY BRIDGE EAST SPAN SEISMIC SAFETY PROJECT BCDC COMMISSION HEARING JULY 19, 2018 AGENDA ITEM NO. 8 AMENDMENT REQUEST TO BCDC PERMIT NO. 2001.008 1

Transcript of BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic...

Page 1: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

SAN FRANCISCO-OAKLAND BAY BRIDGE EAST SPAN SEISMIC SAFETY PROJECT

BCDC COMMISSION HEARING

JULY 19, 2018

AGENDA ITEM NO. 8

AMENDMENT REQUEST TO BCDC PERMIT NO. 2001.008

1

Page 2: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

SPEAKERS

• STEFAN GALVEZ, CALTRANS

• BLAKE SANBORN, AECOM

2

INTRODUCTION

Page 3: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

PARTNERS

3

Page 4: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

E2 El E4 ES E6 E7 ES E9 ElO Ell E12 Ell E14 ElS E16 E17 E18 E22 E2l

SFOBB PROJECT UPDATE

Yerba Buena Island Oakland

Retain Marine Foundation Demo Complete4 Remove Retain

Superstructure Demo Complete

4

Page 5: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

PROJECT SCHEDULE

PIER RETENTION PROJECT MILESTONES •In-water Construction July – December 2018 •Opening to the Public – Spring 2019

•Controlled Implosion – September 2018•Clean-up – October-November 2018

5

Page 6: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

AGENCIES

66

Page 7: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

7

Controlled Blasting of Piers E19 and E20

•Two of the smallest piers, to be removed via controlled implosion

•Single blast event conducted in sequence

PIERS E19 / E20

•Blast attenuation system (bubble curtain)

•Rubble removed to removal depth and hauled for disposal

•Extensive monitoring and reporting program

•Same blasting contractor as Piers E3-E18

Page 8: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

Implosion Video Piers E11-E13

10/14/17

8

Page 9: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

PIER E2

PIER RETENTION SITES

99

PIERS E19-E23

Page 10: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

PIER E2

YERBA BUENA ISLAND SITE

1010

Page 11: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

YERBA BUENA ISLAND

PIER E2

TREASURE ISLAND

BAY BRIDGE BIKE TRAIL

COAST GUARD

CONTEXT

11

Page 12: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

EXISTING CONDITIONS

12

Page 13: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

VEHICULAR PARKING & BIKE RACKS

TREASURE ISLAND

“GREAT WHITES

BAY TRAIL

TORPEDO BUILDING BAY BRIDGE

VIEWS

WATERFRONT PROMENADE

OBSERVATION DECK PUBLIC PLAZA

YBI SITE FEATURES

13

Page 14: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

TURN-AROUND AREA

4.5% SLOPED WALKWAY

SHORELINE PROTECTION

VIEW TOWARD BRIDGE LANDING

1414

SEATING AREA

Page 15: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

STEPS TO BRIDGE LANDING

SHADE TREE

SEAT STEPS

BAY BRIDGE STEEL COUNTER WITH SEATING

VIEW TOWARD OAKLAND

15

Page 16: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

VIEW TOWARD BAY BRIDGE

VIEWS TO BRIDGE AND EAST BAY

BAY BRIDGE STEEL CUSTOM RAILING BAY BRIDGE STEEL CUSTOM COMMUNAL TABLE

INTERPRETIVE SIGNAGE

CUSTOM SEATING

16 16

Page 17: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

LANDING PLAZA

19’ WIDE PEDESTRIAN BRIDGE

PIER E2

OPPORTUNITY FOR REUSE OF HISTORIC TORPEDO BUILDING

AERIAL VIEW

17

Page 18: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

LEGEND: DEDICATED PUBLIC ACCESS AREA

IR SITE 11 BOUNDARY 18

DEDICATED PUBLIC ACCESS

Page 19: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

DEDICATED PUBLIC ACCESS

PEDESTRIAN BRIDGE AND OBSERVATION DECK

3

4

2

5

6

PEDESTRIAN AND BICYCLE SHARED PATH

1

5

7

8

9

10

11

LEGEND: DEDICATED PUBLIC ACCESS AREA

LEGEND:

1 12’ SHARED PATH/MAINTENANCE ROAD

2 SLOPED WALKWAY

3 SEAT STEPS

4 RE‐PURPOSED STEEL AND WOOD COUNTER WITH BAR SEATING

5 BENCH(ES) 6 COMMUNAL TABLE

7 BIKE RACKS

8 SWING GATE

9 VEHICULAR DROP‐OFF (ADA)

10 PARKING

11 BIOSWALE

19

Page 20: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

--

ACCESS & CIRCULATION

BIKE AND PEDESTRIAN

VIEW OF BAY BRIDGE TRAIL LANDING

OAKLAND ROUTE-BIKE

TREASURE ISLAND-BIKE

ACCESS

20

Page 21: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

gy

-U.S. COAST GUARD (RESTRICTED ACCESS)

0 I I I WB 1-80 (OVERHEAD)

- OAKLAND ROUTE-VEHICLE

- TREASURE ISLAND ROUTE-VEHICLE

~ 1-1-l I \l.) 0 SO 100 200

ACCESS & CIRCULATION

VEHICULAR ACCESS

21

Page 22: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

PIERS E19-E23

OAKLAND SITE LOCATION

2222

Page 23: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

--~-,...

,,., _,,..,,,, ,,,., .,, .... .,,,,,. -,,,,,,...,,---

~,,,,,,,,.,---..-- -=:;:;:.--~

NORTH BAY + MOUNT TAM

SITE FEATURES OAKLAND SKYLINE

HISTORICAL BUILDINGS

FUTURE GATEWAY PARK

BAY BRIDGE

INDUSTRIAL WATERFRONT

BAY TRAIL

BRIDGEYARD BUILDING

PROPOSED PARKING

PROPOSED PARKING

CITY SKYLINE VIEWS

Page 24: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

PROPOSED GATEWAY PARK

24

Page 25: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

E23

EXISTING SITE

2525

Page 26: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

EXISTING CONDITIONS

26

Page 27: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

PIER DETAIL

WIDENED OBSERVATION AREA

FLEX SPACE

INTEGRATED RAIL LIGHTING

OUTDOOR CLASSROOM

INTERPRETIVE SIGNAGE

SALVAGED BAY BRIDGE STEEL COUNTER

SALVAGED BAY BRIDGE STEEL RAIL

LIGHTING

HISTORIC GATEWAY

Page 28: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

PROGRAMMING OPPORTUNITIES

OUTDOOR MARKET + EVENTS

HISTORIC GATEWAY

OUTDOOR CLASSROOM

EDUCATIONAL EXHIBITS

SOCIAL GATHERING

CEREMONIAL SPACE

OBSERVATION DECK

ACTIVITY ZONE

28

Page 29: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

J.

VIEW

ENTRY TO PIER UNIVERSALLY ACCESSIBLE ENTRY TO PIER

SALVAGED BAY BRIDGE STEEL

HISTORIC PIER E23

Page 30: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

LOOKING EAST - TOWARDS PIER E23 SALVAGED BAY BRIDGE STEEL COUNTER

CUSTOM SEATING

EDUCATIONAL EXHIBITS

30

VIEW

Page 31: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

1 <

VIEW

LOOKING WEST - TOWARDS PIER E21

ACTIVITY ZONE

OBSERVATION DECK

PEDESTRIAN LIGHTING

CUSTOM SEATING 31

Page 32: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

VIEW

LOOKING SOUTHWEST - FROM BAY BRIDGE BICYCLE PATH32

Page 33: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

--

EXISTING BAY BRIDGE BIKE PATH

EXISTING BAY BRIDGE BIKE PATH TOUCHDOWN

ACCESS & CIRCULATION

PROPOSED PEDESTRIAN-BIKE PATH CIRCULATION

33

Page 34: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

POLICY

•ALLOWABLE BAY FILL •Public Benefit vs. Detriment – Water-oriented uses

•Meets the ‘recreation’ and ‘ public assembly’ criteria •No alternative upland location •Minimum fill through design approach•Minimal negative effect on Bay resources •Designed for “end of century” SLR projections (66”) + 100-year

storm event (~30”)

3434

Page 35: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

I

POLICY

•MAXIMUM FEASIBLE PUBLIC ACCESS •Creates new public access to the shoreline and over the water •Connects to existing public access networks •Synergizes with long-term public access developments

3535

Page 36: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

CONCLUSION

•Creates new public assetsunlike anything in the Bay

•Views of the SFOBB that cannot be replicatedelsewhere

•Renews interest in shoreline access in both locations

•Provides much-need publicopen space on the Bay

36

Page 37: BCDC COMMISSION HEARING · 2018. 10. 30. · san francisco-oakland bay bridge east span seismic safety project bcdc commission hearing july 19, 2018 agenda item no. 8 amendment request

THANK YOU