Run II Upgrades Status January 2006

16
Run II PMG 1/19/06 Pushpa Bhat 1 Run II Upgrades Status Run II Upgrades Status January 2006 January 2006 Pushpa Bhat

description

Run II Upgrades Status January 2006. Pushpa Bhat. Outline. Technical Progress Project Status Status Report for December ‘05. Technical Progress. AP2, DB studies Dave’s talk Li Lens - PowerPoint PPT Presentation

Transcript of Run II Upgrades Status January 2006

Run II PMG 1/19/06 Pushpa Bhat 1

Run II Upgrades StatusRun II Upgrades Status January 2006 January 2006

Pushpa Bhat

Run II PMG 1/19/06 Pushpa Bhat 2

OutlineOutline

• Technical Progress• Project Status• Status Report for December ‘05

Run II PMG 1/19/06 Pushpa Bhat 3

Technical ProgressTechnical Progress

• AP2, DB studies Dave’s talk

• Li Lens One each of PT-1 and PT-2 lenses will be filled and

the PT-2 will be tested on the test stand. PT-2 should be ready for beam in June.

• Rapid Transfers Many elements of the upgrade are in place (ramping

power supplies, BPMs) providing benefits to operations in various modes

Transfers without reverse proton tune-up tried many times last week with good results

Run II PMG 1/19/06 Pushpa Bhat 4

Technical Progress (contd.)Technical Progress (contd.)• 2.5 MHz pbar acceleration in MI

Results from 2 pbar study periods promising: 86- 93% eff while tuning, ~ 30%

• Shows 100% efficiency and ~10% emittance growth in proton studies for relevant intensities and emittance

• May save 15% pbars now being lost in MI during acceleration and coalescing

– current scheme acc+ coalescing eff. ~85%, 80%

• better beam quality, hence expect lower losses in Tev and gain in luminosity due to smaller long. Emittance

• Overall expect >20% gain in peak luminosity • Contention on how to proceed. There was a recent review held by

McGinnis/Kourbanis. • McGinnis report: Potential for 5-10% in L.dt now• We should try a few shots before shutdown

Far less risky and far less complicated than trying to recover and recycle pbars!

Compare with many projects in pbar source each <10% gain

Run II PMG 1/19/06 Pushpa Bhat 5

• MI BPM upgrade Most of the hardware designed, ordered or delivered First test system almost ready; will be installed in

MI40 next week, replacing the old system Full upgrade during and immediately after shutdown

• BLM upgrades Prototype system running at MI60 for ~ 3 months,

with PC instead of local control card. Control card + software under test

Production to be completed by 4/15, a month of testing followed by installation

Technical Progress (Contd.)Technical Progress (Contd.)

Run II PMG 1/19/06 Pushpa Bhat 6

• IPM, OTR detectors One each installed in the Tevatron during the Dec.

shutdown. Now fixing some problems. Might have some data after the current shutdown

• Tevatron Electron Lens Good progress TEL-1 upgraded with new SEFT e-gun TEL-2 essentially ready for installation

• Tev ES separators Install in SD’06, 2 new separators and swap 3

existing separators (these were sparking at higher voltages when larger collision helix were tried last Fall.)

Technical Progress (Contd.)Technical Progress (Contd.)

Run II PMG 1/19/06 Pushpa Bhat 7

Project Highlights: Projects 100% completeProject Highlights: Projects 100% complete 1. Luminosity Upgrades 1.1 Protons on Target

• 1.1.1 Slip Stacking• 1.1.2.1, 1.1.2.2 pbar Target & Beam Sweeping (initial)• 1.1.3.1 MI dampers• 1.1.4 Booster Cogging• 1.1.5 Optical Transition Radiation Detectors• 1.1.6 Operational Improvements to Slip Stacking

1.2 Antiproton Acceptance• 1.2.1.1 Modifications to existing lens• 1.2.1.3 General Lens R&D• 1.2.1.4 New Lens (prototype-1) operational (Milestone)• 1.2.2.3.1.1, 1.2.2.3.2.2 AP2 & Debuncher BPM Upgrade• 1.2.2.10 Initial AP2/Debuncher Aperture Improvements Complete (Milestone)

1.3 Antiproton Stacking & Cooling• 1.3.1 Stacking & Cooling Integration Task Force• 1.3.2 Debuncher Cooling• 1.3.3.2 Stacktail Betatron Cooling• 1.3.4 Recycler Stacking & Cooling• 1.3.5 Electron Cooling R&D, Installation & Commissioning

1.4 Tevatron High Luminosity• 1.4.3.1.1, 1.4.3.1.2, 1.4.3.1.3, 1.4.3.1.9 Design and implement new helix with existing and new installed

separators in the Tevatron • 1.4.3.2 Polarity switches for separators• 1.4.5 Improved Control Diagnostics: BPM system upgrade, IPM, Tune tracker, abort gap monitor, 1.7 GHz

Schottky, Dampers, Head-tail Monitor 2. Maintenance & Reliability Upgrades 2.1 2003 White Paper & Vulnerability Report

• 2.1.1 LINAC 7835 Amplifier Tubes• 2.1.2 Orbit Bump Magnets • 2.1.3, 2.1.4, 2.1.5 Booster RF• 2.1.6, 2.1.7 MI: PS transformers, Kicker vacuum tubes• 2.1.8, 2.1.9 Tevatron low beta power supply, centrifugal cold compressors• 2.1.13 Harmonic Filter Damping Resistors

2.2 Maintenance Improvements• 2.2.2 Booster Collimator • 2.2.3 Tevatron Abort Improvements (Initial)• 2.2.5 General Alignment

Run II PMG 1/19/06 Pushpa Bhat 8

Possible AdditionsPossible Additions

• Chromatic Compensation in the Tev Lattice The mom. spread combined with chromatic error in

the optics lead to poorer beam lifetimes. Correct the chromatic errors by implementing new circuits using existing sextupole magnets

Benefits:• Improves beam lifetime leading to 5-10% L.dt gain• Allows Tev to be operated at a new working point near

½ integer resonance. This in turn allows more intense proton bunches to be used in Tev stores. Can lead to another 10% gain in L.dt

A review was held in Dec., 2005 Three versions of the hardware implementation and

cost estimates presented with cost estimates of $620K (v1) (whole ring), $220K (v2) and $107K (v3).

• Since v3 seems to provide optimal benefit and the most cost effective, we would like to pursue v3.

Run II PMG 1/19/06 Pushpa Bhat 9

Possible Gains (Peak Luminosity)Possible Gains (Peak Luminosity)

• Pbar stack rate + aperture up by another 30% ?

• 2.5 MHz pbar acceleration 10-20% • More protons 230E9 ppb 20% • Chromatic Compensation 10%

Run II PMG 1/19/06 Pushpa Bhat 10

Near term Reviews/Decisions (Contd.)Near term Reviews/Decisions (Contd.)

• Beam-beam effects in Tev Jan. 26, ’06

• Tev alignment SD’06 work Feb. ’06

• Pbar aperture SD’06 work Aperture: band-4 cooling tank arrays + DB extraction

kicker magnet (+ DB extraction kicker motorized stand) <7% gain expected; Lot of effort, Risky? Review late

February

• 2.1 Reliability Upgrades Infrastructure: 345-KV switchgear spares for KRS, MMS

Run II PMG 1/19/06 Pushpa Bhat 11

December ’05 Status December ’05 Status

Run II PMG 1/19/06 Pushpa Bhat 12

Uniq WBS Name Finish Baseline3Finish

% MSClass

984 1.1.3.2.1.2 MI BPM: Review (Milestone) 7/25/05 9/15/05 100% C

3135 1.3.5.6.4.3 Observe First Cooling (Milestone) 9/7/05 10/5/05 100% C

2761 2.2.4.4.3 Fully Commissioned Crate 12/5/05 12/5/05 100% C

1494 1.1.3.3.5 MI 2.5 MHz Acceleration complete 12/29/05 12/29/05 0% B

2443 1.3.5.13 Electron Cooling Operational (start to contrib to HEP) 10/3/05 1/2/06 100% C

921 1.6.5.5 Start Phase 3 (Milestone) 10/3/05 1/2/06 100% A

2708 2.2.4.2.12.9 Prototype System Operational 1/19/06 1/3/06 0% C

2706 2.2.4.2.12.7 Production Readiness Review 1/10/06 1/10/06 0% C

2451 1.4.7.1.3 Review Tevatron Alignment Plans 2006 (Milestone) 2/2/06 2/2/06 0% C

2368 1.4.5.5.3.2.6 IPM Commissioning Tranferred to TEV Department 11/30/05 2/13/06 100% C

866 1.3.6.8 Rapid Transfers Operational (Milestone) 3/31/06 2/24/06 0% A

93 1.5.5 Start Summer 06 Shutdown 3/1/06 3/1/06 0% C

853 1.2.2.11 Intermediate AP2&DB Improvements Complete(Milestone)

6/6/06 6/6/06 0% A

1527 1.5.6 Finish Summer 06 Shutdown 6/6/06 6/6/06 0% C

7/25

9/7

12/5

10/3

10/3

11/30

Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 22005 2006 2007 2008

Milestones Milestones

Baseline Finish Date

Actual Finish Date

Forecast Date

100% complete?

Run II PMG 1/19/06 Pushpa Bhat 13

Progress as of December 31, 2005Progress as of December 31, 2005

% Complete

WBS Name Actual % Planned % A/P %0 Run II 82% 82% 100%

1 Luminosity Upgrades 82% 84% 98%1.1 Protons on Pbar Target 77% 80% 96%1.2 Pbar Acceptance 69% 72% 95%1.3 Pbar Stacking & Cooling 87% 88% 98%1.4 Tevatron High Luminosity 85% 87% 97%1.5 Shutdowns 50% 50% 100%1.6 Project Management 74% 74% 101%

2 Maintenance & Reliability 84% 71% 117%2.1 2003 White Paper/Vulnerability Report 87% 63% 137%2.2 Maintenance Improvements 79% 81% 97%

Run II PMG 1/19/06 Pushpa Bhat 14

M&S Spending through Dec. ‘05M&S Spending through Dec. ‘05

M&S Spending through December 2005 % Fy06 Budget Used ITD Obl+RIP YTD Obl+RIP

FY06 FY07 Total Obl+RIP Actual Obligations Obl+RIP /Total Est /FY06 Allocation0 Run II Upgrades 4,518 197 18,607 857 14,964 14,910 15,159 81% 21%1 Luminosity Upgrades 3,145 197 14,346 728 11,734 11,634 11,722 82% 20%1.1 Protons on Target 379 0 1,859 372 1,942 1,587 1,622 87% 55%1.1.1 Slip Stacking 0 0 416 0 937 406 406 98%1.1.2 Pbar Target and Sweeping 12 0 55 0 12 12 12 22% 0%1.1.3 MI Upgrades 295 0 1,074 329 680 855 855 80% 64%1.1.4 Booster-MI Cogging 0 0 0 0 0 0 01.1.5 OTR 0 0 174 0 255 255 255 147%1.1.6 Operational Improvements for Protons on Target (Rapid Response Task Force)71 0 140 43 58 58 93 67%1.2 pbar Acceptance 672 9 1,433 22 865 870 870 61% 3%1.2.1 LiLens 267 0 513 10 317 309 309 60% 4%1.2.2 AP2 and DB Acceptance 404 9 920 12 548 562 562 61% 3%1.3 pbar Stacking and Cooling 1,030 188 5,678 265 4,148 4,371 4,425 78% 19%1.3.1 S&C Task Force 0 0 0 0 0 0 01.3.2 Debuncher Cooling 0 0 0 0 0 0 01.3.3 Stacktail Upgrade 407 188 1,512 80 886 921 956 63% 13%1.3.4 Recycler Commissioning 0 0 376 1 295 295 295 79% 0%1.3.5 Electron Cooling 0 0 2,536 38 2,471 2,546 2,546 100%

AIP 0 0 1,796 0 1,582 2,109 1,837 102%

Non AIP 0 0 739 38 889 437 709 96%

1.3.6 Rapid Transfers 26 0 582 16 492 498 498 86% 16%1.3.7 Additional Recycler Upgrades 233 0 311 0 0 0 0 0% 0%1.3.8 Additional E-Cool Upgrades 146 0 146 0 0 0 0 0% 0%1.3.9 Pbar Stack Rate Task Force 217 0 217 0 0 0 0 0% 0%1.4 Tevatron High Luminosity 956 0 5,175 69 4,676 4,704 4,703 91% 29%1.4.1 Beam Studies and Simulation 27 0 65 3 44 44 44 68% 12%1.4.2 Active BBC 451 0 1,124 29 855 939 939 84% 40%1.4.3 Increased Helix Separation 389 0 1,268 17 1,023 1,034 1,034 82% 43%1.4.5 Improved Controls and Diagnostics 0 0 2,174 3 2,198 2,176 2,176 100%1.4.6 Tevatron Vacuum Improvements 41 0 235 11 239 239 239 102% 161%1.4.7 Tevatron Alignment 48 0 309 4 317 271 271 88% 5%1.6 Management 108 0 201 0 102 102 102 51% 0%2 Reliability Upgrades 1,372 0 4,261 130 3,231 3,276 3,437 81% 33%2.1 2003 White Paper/Vulnerability Report 1,085 0 2,598 -90 1,932 1,952 1,955 75%2.2 Reliability Upgrades 287 0 1,663 220 1,299 1,325 1,482 89% 57%

Inception To date Costs % Plan usedv4 Plan Estimate(then yr$)

FY06

Run II PMG 1/19/06 Pushpa Bhat 15

Effort for December 2005Effort for December 2005

Adjusted FTE December 2005 PlanAD TD PPD CD Totals 3 MO rolling ave.

Run II Upgrades 28.7 5.8 10.4 9.0 53.8 53.01 Luminosity Upgrades 27.2 2.9 3.4 9.0 42.4 40.21.1 Protons on Target 5.6 0.0 0.0 7.9 13.5 11.51.2 pbar Acceptance 3.8 1.0 0.6 0.0 5.4 4.11.3 pbar Stacking and Cooling 4.9 0.0 0.0 0.0 4.9 9.31.4 Tevatron High Luminosity 10.9 1.9 2.8 1.1 16.6 12.31.6 Management 2.1 0.0 0.0 0.0 2.1 3.02 Reliability Upgrades 1.5 2.9 7.1 0.0 11.4 12.8

Division

Run II PMG 1/19/06 Pushpa Bhat 16

Project Highlights Project Highlights

• Project Status V4 of the plan issued in December Changes documented Project 82% complete as of Jan. 1, 2006

• Costs: M&S estimate now (v4) = $18,607K Jan ’05 status (DOE review) : $17,587K $15.2 M spent; ~$3.45M to complete;

Contingency: $550K ($1,791 K taken away in the past year)