RPRS
description
Transcript of RPRS
RPRS
Market Support ServicesMarch 30, 2005
March 23, 2006
Presented by ERCOT Art Deller Bill Kettlewell
2
RPRS
Overview of RPRS Operations
How and Why does ERCOT use it?How does a QSE bid it?How does a QSE deploy it?
SettlementsHow does a QSE get paid?How does the Market get charged?
3
RPRS
Overview of RPRS
4
Definition
Capacity procured from Resources otherwise unavailable to ERCOT in the hours ERCOT requests RPRS.
Includes: Generation Resources Off-line. Generation Resources expected to be Off-line in the requested
hours LaaRs that are On-line and available time of procurement *
* LaaRs will not be able to participate initially upon initiation of the RPRS functionality.
Section 6.5.6
5
Definition
Two Components
Market Solution
Based on RPRS bids
Also can use Generic Cost
Out of Merit Capacity – OOMC
Capacity selected due to place, or absence, from the bid stack
LaaRs not availble for OOMC
Section 6.1.6 and 6.1.10
6
Definition
Purpose:
Purchase Capacity in order to make Energy available to solve the following system issues:
Capacity Insufficiency
Zonal Congestion
Local Congestion
Section 6.1.6 and 6.1.10
7
Operational Assumptions
Units expected to come on-line in selected hours, to LSL.
Capacity considered on-line for Local and Zonal Congestion requirements
Energy from procured units is placed in the Balancing Energy Service bid stackQuantity >= HSL (HOL) – LSL (LOL)
Definition
Section 6.4.2 and 6.7.5
8
Why do we need RPRS?
Generation
Available
Online
Forecast
Load
9
Payment to Providers
Providers of RPRS are paid for three distinct types of service:
Capacity Insufficiency
Zonal Congestion
Local Congestion
Section 6.8.1.10 and 6.8.1.11
10
Payment to Providers
Units selected for Capacity Insufficiency or Zonal Replacement are paid:
the higher of their bid or,
the highest MCPC for all RPRS procured during the procurement processes.
Section 6.8.1.10 and 6.8.1.11
11
Payment to Providers
Units selected for Local Replacement are paid:
Resource Category Generic Startup Cost for starting
Resource Category Minimum Energy Cost
minus MCPE for operating at the LSL.
Section 6.8.1.10 and 6.8.1.11
12
Payment from Market
Payment from the Market is collected through the following charges:
Under Scheduled Capacity Charge
RPRS Zonal Congestion Charge
RPRS Uplift Charge
Section 6.9.2.1.1
13
Payment from Market
Under Scheduled Capacity Charge
Costs for Capacity Insufficiency are directly assigned to the QSE whose schedules show insufficient capacity scheduled compared to Adjusted Metered Load. This can also result from Mismatches.
Section 6.9.2.1.1
14
Payment from Market
RPRS Zonal Congestion Charge
RPRS Zonal Congestion costs will be directly allocated to QSEs whose schedules have an impact on a congested Commercially Significant Constraint
Section 7.3.4.2
15
Payment from Market
RPRS Uplift Charge
The total payments for Zonal, Local and Capacity Insufficiency RPRS are netted with;
the direct assigned costs for Zonal RPRS plus direct assigned Congestion impact and TCR Payments
The difference is uplifted at Load Ratio Share to all QSEs.
Section 6.9.2.1.2
16
RPRS
Overview of RPRS Operations
How and Why does ERCOT use it?
17
Why
Correct total Capacity Insufficiency, Zonal Congestion and Local Congestion
Based on scheduled resources and load forecasts
Procure Capacity in appropriate locations to provide for system security
To ensure operational security
Section 6.4.2
18
Provide capacity from which energy would be available to solve the following system security violations:
System Capacity insufficiency Using any RPRS bid (or Generic for units with no bids)
Zonal Congestion Using RPRS bids by Zone in Merit Order (or Generic for units with
no bids)
Local Congestion Using Resource Category Generic Cost
Section 6.6.3.2.1
How
19
InputsResource Plans (at time of
procurement) HSL LSL
Load ForecastQSE Schedules (at time of
procurement)
RPRS Inputs
Section 6.6.3.2.1
20
OutputUnit specific deployment for RPRSOptimized for entire 24 Hr period
RPRS Outputs
Section 6.6.3.2.1
21
RPRS
Overview of RPRS Operations
How and Why does ERCOT use it?How does a QSE bid it?
22
Bidding Requirements Resource Parameters
Designation of specific Resource Amount of Capacity
Time Constraints Startup Time (Resource Plan) Minimum Run Time (Registration) Minimum Down Time (Registration) Hours the bid is effective (Bid) Expiration time of bid (Bid)
Costs Start-up - $/MW (< $1,000/MW) Operating - $/MW/Hr (<$1,000/MWh) Balancing Energy Bid Point in $/MWh
RPRS Bid
Section 4.4.16
23
Balancing Energy Bid Point in $/MWh
Max price that balancing energy bids will be entered for the capacity accepted in the RPRS market.
RPRS Bid
Section 4.4.16
24
<?xml version=”1.0”><!DOCTYPE Bids SYSTEM “bids.dtd”><Bids> <ReplacementBid> <DAY>20010101</DAY> <FIRSTHOUR>1300</FIRSTHOUR> <LASTHOUR>1800</LASTHOUR> <CAPACITY>100</CAPACITY> <RSRC_ID>GT-1</RSRC_ID> <RSRC_TY>GEN</RSRC_TY> <CMZONE>A</CMZONE> <STARTUP_PRICE>30.00</STARTUP_PRICE> <PERHOUR_PRICE>50.00</PERHOUR_PRICE> <EXPIRATION_DATE>20010101</EXPIRATION_DATE> <EXPIRATION_TIME>1100</EXPIRATION_TIME> <BES_BIDPOINT>9.99</BES_BIDPOINT> </ReplacementBid></Bids>
RPRS Bid Example
ERCOT Participant interface: XML v 4.o, Sec 3.4
25
Requirements
RPRS Requirements
Resources must provide telemetered output signal, including breaker status
Minimum amount is 1 MW
Resources must meet additional technical requirements (Protocol Section 6.10)
Section 6.5.6
26
Requirements
RPRS Requirements cont.
Only one RPRS bid from any Resource
Selected Resource must be able to respond in the hours selected
QSEs supplying RPRS must comply with Balanced Schedule
Bids in accordance with Section 4
Section 6.5.6
27
Requirements
RPRS Requirements cont.
QSEs may not self-arrange RPRS
Eligible Resources with no bids can still be selected
Bid price set by generic cost times an adjustment factor
If selected, deployed and paid as an OOMC deployment
Section 6.5.6
28
RPRS
Overview of RPRS Operations
How and Why does ERCOT use it?How does a QSE bid it?How does a QSE deploy it?
29
RPRS procured at 1800, based on:ERCOT’s 1100 Load forecast1100 Day-ahead schedules (unless modified
by 1300 in accordance with 4.4.10)Bids submitted by 1600Resource PlansERCOT notify accepted RPRS bids by 1800
* Insufficient RPRS bids addressed with OOMC
Day-Ahead Procurement
Section 4.4.17
30
RPRS procured during Adjustment Period based on:RPRS Bids (can be modified after 1800)Resource PlansERCOT next day Load Forecast
Adjustment Period Procurement
Section 6.6.3.2.1 and 4.5.6
31
The goal of the RPRS Clearing Engine is 24 Hour Optimization to minimize total cost, based on:
Resource Category Generic Cost Capacity price Operation Price Resource Shift Factors
And also respect; Lead time Minimum Up time Minimum Down time
For the whole Operating Day while meeting security constraints for each hour.
Objective of RPRS Engine
Section 4.4.17 and 6.6.3.2.1
32
Three Step Clearing ProcessLocal Congestion firstZonal Congestion & System Balance
simultaneously Operator optional intervention
MCPC Calculation Marginal cost for insufficiency determines MCPC Marginal cost to solve CSC determines Shadow
Price for Capacity for CSC Congestion
RPRS
Section 6.6.3.2.1
33
<?xml version=”1.0”?><!DOCTYPE Notifications SYSTEM “notes.dtd”><Notifications> <RepBidSelected> <DAY>20010101</DAY> <STRIKEHOUR>1200</STRIKEHOUR> <FIRSTHOUR>1100</FIRSTHOUR> <LASTHOUR>1800</LASTHOUR> <RSRC_ID>GT-1</RSRC_ID> <RSRC_TY>GEN</RSRC_TY> <BIDMW>100</BIDMW> <STRIKEMW>100</STRIKEMW> <STARTUP_PRICE>25.00</STARTUP_PRICE> <PERHOUR_PRICE>10.00</PERHOUR_PRICE> <LEADTIME>30</LEADTIME> <STARTHOUR>1200</STARTHOUR> <STOPHOUR>1600</STOPHOUR> <CONGESTION>F</CONGESTION> </RepBidSelected></Notifications>
RPRS Notification Example
ERCOT Participant interface: XML v 4.o, Sec 5.12
34
Which Resources are Eligible for RPRS?
Local Congestion – any generation resource offline and available will be eligible.
Zonal Congestion, Capacity – any offline and available generator or online, available, and active LaaR* resource with a RPRS bid.
RMR units may be used to offset RPRS, if economical.
* LaaRs will not be able to participate initially upon initiation of the RPRS functionality.
RPRS
Section 6.6.3.2.1
35
What does the QSE do when RPRS is Procured from the QSE?
Updates their Resource Plan accordingly Adds Capacity from RPRS resource into Balancing
Bids Brings specified resource online for specified hours
at LSL Incorporate LSL into Energy Schedules. Options
include: Reducing output of other Resources Selling additional BES Using Relaxed Balanced Schedules
RPRS is not an instructed deviation
RPRS
Section 6.4.2
36
RPRS
Overview of RPRS Operations
How and Why does ERCOT use it?How does a QSE bid it?How does a QSE deploy it?
Settlements
37
Inputs to Settlements:
RPRS Procured (Type and Quantity) MCPC and Shadow Prices Bids Schedules Resource Plans Generic Cost Adjusted Metered Load
RPRS Settlement
38
Process:
Pay Providers: Capacity Insufficiency Zonal Congestion Local Congestion
RPRS Settlement
Collect from Users: Under Scheduled QSEs Zonal Congestion Uplift to Market
39
RPRS
Overview of RPRS Operations
How and Why does ERCOT use it?How does a QSE bid it?How does a QSE deploy it?
SettlementsHow does a QSE get paid?
40
If a unit was selected for Local Congestion, how does the QSE get paid?
Payment
41
Decide if deployment was Local,Zonal or System Balance
Determine Awarded Amount
Determine Hours Of Award
Determine Startup and Operating Payment
Local Award
42
Local Replacement Reserve (LCFLAG = 1)
Steps
1. LRPQ – Awarded amount
2. LRPHR – Number of hours awarded
3. LPS – Start up payment
4. LPO – Operation price
RPRS
43
LRPQ – Local Replacement Quantity
Hour 5 (Intervals 17 – 20):
LRPQ = ( 141 + 145 + 151 + 155 ) / 4 = 148
(Used to calculate RCGSC)
Hours Hr03 Hr04 Hr05 Hr06 Hr07 Hr08 Hr09 Hr10 Hr11 Hr12 Hr13 Hr14 Hr13
LCFLAG ........ 2 2 1 1 1 0 0 0 2 2 2 2 .......
Interval Int17 Int18 Int19 Int20 Int21 Int22 Int23 Int24 Int25 Int26 Int27 Int28
Hour 4:15 4:30 4:45 5:00 5:15 5:30 5:45 6:00 6:15 6:30 6:45 7:00
HSL ........ 141 145 151 155 160 165 170 165 161 155 151 145 .......
Hours Hr03 Hr04 Hr05 Hr06 Hr07 Hr08 Hr09 Hr10 Hr11 Hr12 Hr13 Hr14 Hr13
LRPQ ........ 0 0 148 165 153 0 0 0 0 0 0 0 .......
RPRS
44
LRPHR – number of hours instructed
LRPHR = 3
Hours Hr03 Hr04 Hr05 Hr06 Hr07 Hr08 Hr09 Hr10 Hr11 Hr12 Hr13
LRPQ ........ 0 0 148 165 153 0 0 0 0 0 .......
LRPHR ........ 0 0 3 3 3 0 0 0 0 0 .......
RPRS
45
LPS – Local RPRS start up payment
•Determine if “Hot” or “Cold” start (Combined Cycle only)•Hot = Less than 5 hours from shut down to start up•Cold = 5 hours or more from shut down to start up.
LRPHR
RCGSCLPS
RPRS
Section 6.8.1.11
46
LPO – Local RPRS Operating payment
•Unit will get paid for what it generated, up to it’s LSL.
4
1
4/min*
GSITETOT
LSLMCPERRCGMECLPO i
RPRS
Section 6.8.1.11
47
GSITETOT
0
100
120
Low Sustainable Limit
LSL < GSITETOT
30MWh 25MWh
RPRS
48
0
120 Low Sustainable Limit
GSITETOT100
LSL > GSITETOT
30MWh 25MWh
RPRS
49
)),0((*1 LPRPADJLPOLPSMAXLPCRPAMT
LPCRPAMT – Local Procured Capacity Replacement Amount
RPRS
Section 6.8.1.11
50Section 6.9.2.1.2
Local Replacement
Local Replacement Payment
51
If a unit was selected for Capacity Insufficiency or Zonal Replacement, how does the QSE get paid?
Payment
52
Decide if deployment was Local,Zonal or System Balance
Determine Awarded Amount
Determine Hours Of Award
Zonal or System Balance Award
Apply RPRS Bids
53
Zonal Replacement Reserve (LCFLAG = 0)
Steps
1. ZRPQ – Awarded amount
2. ZRPHR – Number of hours awarded
3. Apply Bids
RPRS
54
ZRPQ – Zonal Replacement Quantity
Hour 8 (Intervals 29 – 32):
ZRPQ = MIN[156,( 143 + 144 + 146 + 147 )/ 4] = 145
RPRSMW = 156 (Min of Procured MW and HSL at Procurement)
Hours Hr03 Hr04 Hr05 Hr06 Hr07 Hr08 Hr09 Hr10 Hr11 Hr12 Hr13 Hr14 Hr13
LCFLAG ........ 2 2 1 1 1 0 0 0 2 2 2 2 .......
Interval Int29 Int30 Int31 Int32 Int33 Int34 Int35 Int36 Int37 Int38 Int39 Int40Hours 7:15 7:30 7:45 8:00 8:15 8:30 8:45 9:00 9:15 9:30 9:45 10:00
HSL ........ 143 144 146 147 157 161 156 154 158 155 157 154 .......
Hours Hr03 Hr04 Hr05 Hr06 Hr07 Hr08 Hr09 Hr10 Hr11 Hr12 Hr13 Hr14 Hr13
ZRPQ ........ 0 0 0 0 0 145 156 156 0 0 0 0 .......
RPRS
55
ZRPHR – number of hours instructed
ZRPHR = 3
Hours Hr03 Hr04 Hr05 Hr06 Hr07 Hr08 Hr09 Hr10 Hr11 Hr12 Hr13
ZRPQ ........ 0 0 0 0 0 145 156 156 0 0 .......
ZRPHR ........ 0 0 0 0 0 3 3 3 0 0 .......
RPRS
56
ZPCRPAMT – Zonal Procured Capacity Replacement Amount
ZRPQ
MCPCRP
ZRPHRBPZRPHR
ZRPSUBP
ZPCRPAMT *
,
max*1
RPRS
Section 6.8.1.10
57
Decide if deployment was Local,Zonal or System Balance
Determine Awarded Amount
Determine Hours Of Award
Determine Startup and Operating Payment
Local Award
Determine Awarded Amount
Determine Hours Of Award
Zonal or System Balance Award
Apply RPRS Bids
58Section 6.9.2.1.2
Capacity Insufficiency
Zonal Replacement
Local Replacement
Zonal Replacement and Cap. Insufficiency Payment
59
RPRS
Overview of RPRS Operations
How and Why does ERCOT use it?How does a QSE bid it?How does a QSE deploy it?
SettlementsHow does a QSE get paid?How does the Market get charged?
60
A QSE can be directly assigned RPRS charges if they:
under-schedule their load
have mismatches where they are receiving more than the supplying party has scheduled
scheduled ERCOT as a resource
RPRS Under Scheduled Charge
Section 6.9.2.1
61
Steps:
Use maximum MCPC for any RPRS Market for the Operating day
Find the Maximum difference between the QSEs Adjusted Metered Load and Scheduled Load for any interval in which there was an RPRS Market
Add the amount of the Maximum Mis-Matched quantity for any Interval with an RPRS Market
RPRS Under Scheduled Charge
Section 6.9.2.1
62
RPRS Under Scheduled Charge
Adjustment Period
Day-Ahead MCPCRP = $55
MCPCRP = $45
Example: Direct assigned RPRS costs, two RPRS Markets
63
RPRS Under Scheduled Charge
70
75
80
85
90
95
100
105
110
115
1 2 3 4
70
75
80
85
90
95
100
105
110
115
1 2 3 4
Adjustment Period
Day-Ahead
20 MW
Sc
he
du
led
Sc
he
du
led
Sc
he
du
led
Sc
he
du
led
Sc
he
du
led
Sc
he
du
led
Ac
tua
l
Ac
tua
l
Ac
tua
l
Ac
tua
l
Ac
tua
l
Ac
tua
l
64
RPRS Under Scheduled Charge
Adjustment Period
Day-Ahead
Resource Obligation
QSE BResource Obligation
QSE A
Resource Obligation
QSE BResource Obligation
QSE A
100 B 100 A 110 B 110 A
100 B 100 A 100 B 100 A
No Mismatch
Mismatch quantity – 10MW
65
Maximum MCPC = $55
Maximum Under Scheduled amount = 20MW
Maximum Mismatch amount = 10MW
RPRS Under Scheduled Charge
66
Under Scheduled Charge =
$55 * (20MW + 10MW) = $1,650
RPRS Under Scheduled Charge
67
RPRS Under Scheduled Charge
Section 6.9.2.1
0,
MaxM(AMLi1zq-CLi1zq)
USRPizq= MaxM(MCPCRPizq) * Max MaxM(AMLi2zq-CLi2zq) +MMQizq
MaxM(AMLi3zq-CLi3zq)
MaxM(AMLi4zq-CLi4zq)
Variables
US = RPRS Under Scheduled ChargeAML = Adjusted Meter LoadCL = Current Scheduled LoadMCPC = Market Clearing Price for CapacityMMQ = Mismatched Amount
Subscripts
M = Marketi = Intervalz = Congestion Management Zoneq = QSERP = Replacement Reserve
68
RPRS Under Scheduled Charge
Section 6.9.2.1
0,
MaxM(MMSMi1zqaqb)
MMQizq = Σ Max MaxM(MMSMi2zqaqb)
MaxM(MMSMi3zqaqb)
MaxM(MMSMi4zqaqb)
Variables
MMQ = Mismatched QuantityMMS = Mismatched Schedule Quantity
Subscripts
M = Marketi = Intervalz = Congestion Management Zoneqa = Buying QSEqb = Selling QSE
69
RPRS Under Scheduled Charge
Section 6.9.2.1
0,
MMSMi1zqaqb = Max QSSATORPi1z - QOSBTORPi1z
Variables
MMS = Mismatched Schedule Quantity
QSSA = QSE Supply Schedule for Buying QSE
QOSB = QSE Obligation Schedule for Supplying QSE
Subscripts
M = MarketI = IntervalZ Congestion Management ZoneTORP = Time of Replacement
70Section 6.9.2.1.2
Capacity Insufficiency
Zonal Replacement
Local Replacement
RPRS Under Scheduled Charge
Under Scheduled
Charge
71
RPRS Zonal Congestion Charge
Criteria: If a QSE’s schedule has an impact on a CSC, and:ERCOT has procured Zonal RPRS, then:
The QSE can be charged for Congestion Impact.Multiply the CSC Shadow Price for Capacity by
the QSE CSC Impact per interval.
72South
West North
Res = 548MW
Load = 140MW
RPRS Zonal Congestion ChargeExample:
Net = 408MW
73
Shift Factors
CM Zone names
Average Weighted Shift Factor
West to North
Average Weighted Shift Factor
South to North
Average Weighted Shift Factor
South to West
West2003 0.489911548 -0.004425342 -0.016725781
North2003 -0.008056712 -0.120276952 -0.003225342
South2003 0.002302236 0.503257831 0.104328870
CSC Zonal Average Weighted Shift Factors
RPRS Zonal Congestion Charge
74
South Zone Schedule impacts the South to North constraint as follows:
Impact = (Resource – Obligation) * SFSN
= (548 MW – 140MW) * 0.503257831= 205.33 MW
RPRS Zonal Congestion Charge
Calculate the Impact for a Zone
Impact = Net Zonal Schedule * Shift Factor
75
Now the Congestion Charge for a particular CSC is simply a quantity times a price:
Congestion Charge = (Max of Impact) * Shadow Price for Capacity
= (205.33MW)($100/MW)
= $20533.00
RPRS Zonal Congestion Charge
76
RPRS Zonal Congestion Charge
CSCRPhq = SPCCSCh* MAX (0, ICSChq))
ICSChq = MAX [0,MAX [Σ ((QSSTOPiqz – QOSTOPiqz) * SFzcsc)z ]n]
Variables
CSC = Commercially Significant ConstraintI =Scheduled MW ImpactQSS = QSE Supply ScheduleQOS = QSE Obligation ScheduleSF = Shift FactorSPC = Shadow Price for Capacity
Subscripts
i = Intervalh = Hour being calculatedn = Number of time RPRS is procuredTOP = Time of Replacementq = QSEz = Congestion Management Zone
Section 7.3.4.2
77Section 6.9.2.1.2
Capacity Insufficiency
Zonal Replacement
Local Replacement
Zonal Congestion
Impact
RPRS Zonal Congestion Charge
Under Scheduled
Charge
78
TCR Holders are paid the Shadow Price for Capacity times the number of TCRs held on the active constraint:
TCRPAY = Number of TCRs Held * Shadow Price Capacity
TCR Payment
79
TCRPAYRP = -1 * [ Σ (TCRCSC) * SPCSC ]CSC
TCRPAY
Variables
TRCRPAY = TCR Payment per HourTCR = Total Number of TCRs ownedSP = RPRS Capacity Shadow Price
Subscripts
RP = Replacement ReserveCSC = Commercially Significant Constraint
Section 6.9.2.1.2
80Section 6.9.2.1.2
≠ 0
Capacity Insufficiency
Zonal Replacement
Local Replacement
TCRPAY
Zonal Congestion
Impact
TCRPAY
Under Scheduled
Charge
81
RPRS Uplift Charge
Section 6.9.2.1.2
RPRS Uplift Charge =
Payments to Capacity and Zonal Replacement +Payments to Local Replacement +Payments to TCR Holders +Collection from Under Scheduled Capacity +Collection from RPRS Congestion Impact
Multiplied by each QSE’s Load Ratio Share
82
UCRP = -1 * [ Σ ( PCRP + LPCRP ) + Σ (USRP) + TCRPAYRP + Σ CSCRP ]* LRS
RPRS Uplift Charge
Variables
UC = RPRS Uplift ChargePC = Cost of Capacity for Zonal
Congestion and Capacity Insufficiency
LPC = Cost of RPRS for Local Congestion
US = RPRS Under Scheduled ChargeTRCRPAY = TCR Payment per HourCSC = RPRS CSC Impact Capacity
ChargeLRS = Load Ratio Share
Subscripts
RP = Replacement Reserve
Section 6.9.2.1.2
83Section 6.9.2.1.2
RPRSUplift
Charge
Capacity Insufficiency
Zonal Replacement
Local Replacement
TCRPAY
Zonal Congestion
Impact
RPRS Uplift Charge
Under Scheduled
Charge
84
Questions
85
LCFLAG Hourly cut 0 = awarded Zonal RPRS 1 = awarded Local RPRS 2 = No award
Local Replacement
LPO Hourly cut Determined in settlements with RCGMEC, MCPER, GSITETOT
and LSL
LPS Hourly cut Determined in Settlements with RCGSC, LRPHR
New Determinants
86
LRPADJ Hourly cut Adjustment to Local RPRS Payment (LPCRPAMT)
LRPHR Hourly cut Number of hours a unit is continuously procured for Local RPRS
LRPQ Hourly cut MW quantity of Local RPRS awarded. Determined in Settlement
using LCFLAG and HSL
New Determinants cont.
87
Zonal and Capacity Insufficiency
RPRSMW Hourly cut Minimum of average hourly HSL (at the time of procurement) or
MW awarded from RPRS bid
ZRPHRBP Hourly bid price for RPRS ($/MW) Only used in Zonal RPRS
ZRPADJ Hourly cut Adjustment to Zonal RPRS Payment (ZPCRPAMT)
New Determinants cont.
88
ZRPHR Hourly cut Number of hours a unit is continuously procured for Zonal RPRS
ZRPSUBP Hourly start up bid price ($/MW) Only used in Zonal RPRS
ZRPQ Hourly cut MW quantity of Zonal RPRS awarded. Determined in Settlement
using LCFLAG and HSL
New Determinants cont.
89
PRRs
•413 – Optimization for the Whole Operating Day in RPRS Procurement Process
•491 – Clarification to PRR413 RPRS Market
•594 – Replacement Reserve Service Payment Formulas
•604 – Replacement Reserve Service Bid Cap
•613 – Replacement Reserve Under Scheduled Capacity Delineation
•614 – Balancing Bids for replacement Capacity
•641 - Clarifying RPRS Scheduling Language
90
•4.4.11 - Ancillary Services Bid Submittal
•4.4.16 – ERCOT Receipt of Replacement Reserve Service Bids
•4.5.6 – ERCOT Notice of Need to Procure RPRS Resources
•6.1.6 – Replacement Reserve Service
•6.3.1 – ERCOT Responsibilities
•6.4.1 – Determination of ERCOT Control Area Requirements
•6.5.6 – Replacement Reserve Service
•6.5.9 – Reliability Must-Run Service
Protocol Sections
91
Protocol Sections
•6.5.9 – Reliability Must-Run Service
•6.6.3.2.1 – Specific Procurement Process Requirements for Replacement Reserve Service in the Adjustment Period
•6.7.5 – Deployment of Replacement Reserve Service
•6.7.8 – Deployment of RMR Service
•6.8.1.1 – Payments for Ancillary Service Capacity
•6.8.1.10 – Zonal or System Wide Replacement Reserve Service Capacity Payment to QSE
•6.8.1.11 – Local Congestion Replacement Reserve Payment to QSE When a Market Solution Exists
•6.8.2.2 – Capacity and Minimum Energy Payments
92
Protocol Sections…cont.
•6.9.2.1 – Settlement for RPRS
•6.9.2.1.1 – Replacement Reserve Under Scheduled Capacity
•6.9.2.1.2 – Replacement Reserve Uplift Charge
•6.10.8 – Replacement Reserve and OOMC Performance Criteria
•7.3.4.2 – Replacement Reserve Service Zonal Congestion Charge
•7.4.2 – Resolution of Local Congestion
•7.5.5 – TCR Settlement