REPOWERING OF A WIND FARM AT EDAYARPALAYAM
-
Upload
ashok-kumar -
Category
Documents
-
view
336 -
download
2
description
Transcript of REPOWERING OF A WIND FARM AT EDAYARPALAYAM
REPOWERING OF A WIND FARM AT
EDAYARPALAYAM
A PROJECT REPORT
Submitted by
M.Arthanareswaran
K.Ashokkumar
R.Hariprasanth
R.Sriram
In partial fulfilment for the award of the degree
of
POST GRADUATE DIPLOMA
In
WIND RESOURCE ANALYSIS
DEPARTMENT OF ENERGY
PSG COLLEGE OF TECHNOLOGY (Autonomous Institution)
COIMBATORE – 641 004
PSG COLLEGE OF TECHNOLOGY (Autonomous Institution)
COIMBATORE – 641 004
BONAFIDE CERTIFICATE
Certified that this project report “REPOWERING OF A WIND FARM
AT EDAYARPALAYAM” is the bonafide work of “M.Arthanareswaran,
K.Ashokkumar, R.Hariprasanth and R.Sriram” who carried out the project work
under my supervision.
Dr R. VELAVAN Dr S. BALACHANDRAN Associate Professor and Project Supervisor Head of The Department
Energy Engineering Energy Engineering
PSG College Of Technology PSG College Of Technology
Coimbatore – 641 004 Coimbatore – 641 004
Submitted for the final Viva-voce Examination held on 21.08.2012
INTERNAL EXAMINER EXTERNALEXAMINER
ABSTRACT
The main objective of the project is to assess the repowering potential of a wind farm
using the wind atlas analysis and application program (WAsP). With repowering, the first-
generation wind turbines can be replaced with modern multi-megawatt wind turbines. To
carry-out the study an old wind farm located at Edayarpalayam near Pappampatti is selected.
The wind farm was commissioned in 1990’s with a capacity of 11.58MW, which consists of
39 Wind Turbines.
The intent of this project is to calculate the generation of the existing wind farm using
WAsP and to compare with the actual generation. To carry out the micro-siting for the same
wind farm with different wind turbines and to predict the annual energy output of the wind
farm after the repowering. Further, the energy yield ratio and repowering ratio of this
repowering project also to be calculated. This will facilitate to develop a method to assess the
repowering potential, since the best locations for wind in India are occupied by old wind
turbines with lower energy output compared with new wind turbines.
TABLE OF CONTENTS
CHAPTER NO TITLE PAGE NO
ABSTRACT i
LIST OF TABLES ii
LIST OF FIGURES iii
LIST OF ABBREVATIONS iv
1 INTRODUCTION 1
1.1 GENERAL 1
1.2 OBJECTIVES OF THE PROJECT 2
1.3 ORGANISATION OF THE PROJECT 4
2 RE-POWERING OF WIND FARMS 5
2.1 INTRODUCTION 5
2.2 NEED FOR REPOWERING 5
2.3 ADVANTAGES OF WIND REPOWERING 6
2.4 METHODOLOGY TO ASSESS REPOWERING
POTENTIAL 8
2.5 SUMMARY 10
3. WIND ATLAS, ANALYSIS AND APPLICATION PROGRAM
(WAsP) 10
3.1 INTRODUCTION 10
3.2 WIND POWER PRODUCTION CALCULATION 12
3.3 SUMMARY 15
4. MICROSITING OF WIND TURBINES 16
4.1 INTRODUCTION 16
4.2 WIND RESOURCE ASSESSMENT METHODOLOGY 16
4.3 MICROSURVEY & MICROSITING 17
4.7 SUMMARY 17
5. CALCULATION OF EXISTING GENERATION USING
WAsP 18
5.1 INTRODUCTION 18
5.2 EXISTING INSTALLED CAPACITY AND RATING OF
TURBINES 18
5.3 WAsP OUTPUT - EXISTING WIND FARM GENERATION 18
5.4 SUMMARY 23
6. ESTIMATION OF NEW INSTALLED CAPACITY AND
GENERATION AFTER REPOWERING 23
6.1 INTRODUCTION 23
6.2 INPUTS REQUIRED FOR WAsP 23
6.3 EXISTING WIND TURBINES 33
6.4 NEW TECHNOLOGY SELECTION FOR REPOWERING 39
6.5 AEP CALCULATION OF REPOWERED WIND FARM 42
6.6 CALCULATION OF AEP FROM WAsP FOR
CONFIGURATION I 45
6.7 CALCULATION OF AEP FROM WAsP FOR
CONFIGURATION II 50
6.8 SUMMARY 51
7. CO2 REDUCTION FOR THE REPOWERED WIND FARM 55
7.1 INTRODUCTION 55
7.2 CALCULATION OF CO2 REDUCTION FOR
CONFIGURATION I 55
7.3 CALCULATION OF CO2 REDUCTION FOR
CONFIGURATION II 58
7.4 SUMMARY 59
8. CONCLUSION 61
8.1 INTRODUCTION 61
8.2 PROJECT SUMMARY 61
ANNEXURES 63
REFERENCES 67
LIST OF TABLES
TABLE NO. TITLE PAGENO.
5.1 Existing Installed Capacity and Rating of Turbines 18
6.1 Summary of the verification for wind speed for each modelling 25
8.1 Summary of the Work done 62
LIST OF FIGURES
Fig No. TITLE Page No.
5.1 Existing Wind Farm Layout. 19
5.2 Google Synchronised 3D Image. 20
5.3 AEP Calculation. 21
5.4 Energy Losses Due to Wake 21
6.1 Numerical Wind Atlas 24
6.2 Wind atlas for Edayarpalayam. 26
6.3 Vector Map 27
6.4 Creating Vector Map in Surfer 29
6.5 Change the Coordinate System to UTM 30
6.6 Making Contour Map in DXF format 31
6.7 Making WAsP Contour Map by Map Editor 32
6.8 WAsP ASCII Map 32
6.9 Power Curve for VESTAS ‘V39’ 500kW 33
6.10 Power Curve for VESTAS ‘V27’ 225kW 34
6.11 Power Curve for SUZLON ‘S33’ 350kW 35
6.12 Power Curve for Pioneer Wincon 250kW 36
6.13 Power Curve for Enercon ‘E30’ 200kW 37
6.14 Power Curve for BONUS 300kW. 38
6.15 Power Curve for SUZLON ‘S64’ 1250Kw 39
6.16 Power Curve for GAMESA ‘G90’ 2.0MW. 40
6.17 Power Curve for SUZLON ‘S88’ 2.1MW. 41
6.18 Power Curve for GAMESA ‘G114’ 2.0 MW. 42
6.19 Layout for Configuration I 43
6.20 Vector Map 44
6.21 Vector Map 45
6.22 AEP for GAMESA G90 45
6.23 Wake Losses for GAMESA G90 46
6.24 AEP for SUZLON S88. 47
6.25 Wake Losses for SUZLON S88. 47
6.26 AEP for GAMESA G114. 48
6.27 Wake Losses for GAMESA G114. 49
6.28 AEP for GAMESA G90 50
6.29 Wake Losses for GAMESA G90 50
6.30 AEP for SUZLON S88. 51
6.31 Wake Losses for SUZLON S88. 52
6.32 AEP for GAMESA G114. 53
6.33 Wake Losses for GAMESA G114. 53
LIST OF ABBREVIATIONS
WAsP : WIND ATLAS ANALYSIS APPLICATION PROGRAM
AEP : ANNUAL ENERGY PRODUCTION
PLF : PLANT LOAD FACTOR
CUF : CAPACITY UTILIZATION FACTOR
SRTM : SHUTTLE RADAR TOPOGRAPHY MISSION
WTG : WIND TURBINE GENERATOR
PEI : PRIMARY ENERGY INPUT
1
CHAPTER 1
INTRODUCTION
1.1 GENERAL
India started with a unit size of 55 kW in 1986, when the first demonstration wind farms
were built. Installation of 90 kW, 110 kW, and 150 kW unit sizes quickly followed.
Thereafter, 200-kW wind-energy generators were used in the 20 MW demonstration wind-
farms built with assistance from the Danish International Development Agency (DANIDA).
When the private sector entered the wind market in the early 1990s, turbines of 225 kW to
300 kW unit sizes were the preferred choices. Today, 600 kW, 750 kW, 800 kW, 1250 kW,
2000 kW and 2500kW are popular unit sizes in India. The hub height of wind-turbines, which
was 26 m to start with, has increased to about 90 m today. Also, the energy generation per
kW rating of these WTGs or capacity factor was around 15-20%. In current scenario, much
larger capacity WTGs are available with taller tower, higher rotor diameter and advanced
design features. Consequently the CUF now available is almost double. Similarly, the rotor
diameter has increased from 16 m to 100 m in the larger unit sizes now in operation. The
pace has quickened now. The standard commercially available wind turbine size, which
was150 kW, 15 Years ago and 500 kW, 10 Years ago, has now moved up to 2500 kW. In
India, old wind turbines were placed at locations where the wind is often very good. Since the
best locations for wind in India are occupied by old wind turbines with lower energy output
compared with new wind turbines. Programs are started to replace the old turbines with new
ones. With repowering, the first-generation wind turbines can be replaced with modern multi-
megawatt wind turbines. This study is essential for devising a method for assessing the
repowering potential and to improve the energy output from the wind farms. Repowering
seeks to efficiently harness the wind energy potential and subsequently increase energy
generation per hectare of land area used. As a thumb rule re-powering is a process which,
with half the infrastructure, will double the capacity and triple the energy. In addition re-
powering offers several technical, operational, financial and environmental advantages also.
India has significant re-powering potential in some of its most wind rich states including
Tamilnadu, Gujarat, Andhra Pradesh and Karnataka. Wind repowering in India is still at the
demonstration stage and is expected to take off only by 2012. So an opportunity exists to
repower the wind mill turbines, which are operational for more than 15 Years with the
presently available high efficient high capacity turbines. This project evaluates the
2
repowering opportunities for wind farms using the Wind Atlas Analysis and Application
Program (WAsP).
1.2 OBJECTIVE OF THE PROJECT
The objective of the project work is
To calculate the gross and net generation of the existing wind farm using WAsP.
To estimate the new installed capacity and gross and net generation after repowering
using WAsP with different micro-siting and turbine spacing criteria and turbine rating
selection and calculating energy yield ratio and re-powering ratio.
1.3 LITERATURE REVIEW
A. Filgueira et al (2009) described the technical and economic aspects of the
repowering process for the wind farms in Bustelo and S. Xoan, situated in the municipalities
of Muras (Lugo) and As Pontes de Garcia Rodriguez (A Coruna), Galicia, North-Western
Spain. This process was the result of a growing demand for renewable energies, facilitated by
the great potential of wind energy for Galicia. Both farms were set up in 1998. The other
factors they have in common - the same type of machinery, their location and a shared
substation- mean they can be studied together and independently. L. M. Neto et al (2009)
described the useful life of winding insulation. When retrofitting is undertaken an increase
to a higher insulation class is recommendable. So the generator‘s capacity should be
increased, and this will not just more than fully compensate for the investment made it will
also result in a more efficient use of the raw materials used and thus contribute to sustainable
development. Brazilian experience shows that retrofitting with repowering is successful. The
objective of this study is to present two cases of repowering, in which the old insulating
materials were replaced by other, modern ones. So, eight SG of a Power Plant in Cubatao,
S.P and two SG of CEMIG, MG had its power increased up to 40%. Niels G. et al (2008)
described the Wind Atlas Analysis and Application Program (WAsP). It is a software
program for horizontal and vertical extrapolation of wind data. The program contains a
complete set of models to calculate the effects on the wind of sheltering obstacles, surface
roughness changes and terrain height variations. The analysis part consists of a
transformation of an observed wind climate (speed and direction distributions) to a wind atlas
data set. The wind atlas data set can subsequently be applied for estimation of the wind
climate and wind power potential, as well as forsiting of specific wind turbines. Facility
includes a Quick Start Tutorial, a User's Guide and a Technical Reference.
3
Rajendra Kharul Sr. Fellow and Head, Centre for Wind Power, World Institute of
Sustainable Energy, outlines the most important highlights of the wind-power market,
including installations, geographical spread, and wind-turbine technology up gradation in
India. Also explains the variations in capacities of wind-turbines installed in Tamil Nadu and
in India. It further introduces the concept of re-powering and deliberates on various ways of
re-powering, its need, its benefits, barriers and associated concerns in India. Also covered the
criteria for selection of project; selection of Tamil Nadu for study and describes the different
projects sites selected as samples in the state. It also provides details of each project chosen
for the study, and the type of data collected from selected sites. It includes a detailed
methodology to calculate repowering potential considering different technology and
micrositing alternatives. Jacques Roeth (2010) presented industry-accepted guidelines for
planning and conducting a wind resource assessment program. A comprehensive overview of
the wind monitoring process, which involves the siting, installation, and operation of a
meteorological towers, as well as advanced remote sensing technologies are discussed.
Recommended best practices for the subsequent data collection and validation are provided.
These analyses include extrapolating observed wind measurements to hub height, adjusting
the measured data to the long-term historical norm, wind flow modelling and the assessing
the uncertainty associated with resulting energy production estimates. Jacques Roeth (2009)
investigated the influence of rugged terrain on the predictions by the wind analysis and
application program (WAsP) using a case study of field measurements taken over 3 and.
Years in rugged terrain. The parameters that could cause substantial errors in a prediction are
identified and discussed. In particular, the effects from extreme orography are investigated. A
suitable performance indicator is, developed which predicts the sign and approximate
magnitude of such prediction error. This procedure allows the user to assess the consequences
of using WAsP outside its operating envelope and could provide a means of correcting for
rugged terrain effects. Infraline energy in its report (2011) ―Repowering of old wind farms:
Opportunities and challenges‖ identifies the potential and opportunities available for the
concerned stakeholders to take up the wind re-powering projects at different windy sites in
the country. The report also discusses several advantages along with the cost estimates of
repowering projects and different policy initiatives that are required to accelerate the
repowering activities in India. MICRO-SITING Guidelines of C-WET explains Micro-siting
techniques and procedures, level and complex terrain sites and micro-siting rules. It is the art
of developing wind machines in a most optimal manner for achieving best wind farm
4
capacity. A number of wind turbines are installed in arrays and spacing between these arrays
is generally 5Dx7D. (D is the rotor diameter). The factor by which the output of a wind farm
would be less than what we should ideally get is known as ―array efficiency‖. Array
efficiency is not affected in case of strong wind conditions, but is strongly affected in the case
of low wind conditions.
1.4 ORGANIZATION OF THE PROJECT
The project is organized as follows:
Chapter 2 Provides the concept of re-powering, need for repowering, methodology to assess
repowering potential and advantages of wind repowering.
Chapter 3 Describes about Wind Atlas, Analysis and Application Program (WAsP).
Chapter 4 Deals with the wind resource assessment methodology micro survey & micro
siting.
Chapter 5 Deals with calculation of existing generation using WAsP and comparison between
actual generation and WAsP output.
Chapter 6 Deals with the estimation of new installed capacity and generation after
repowering.
Chapter 7 Provides the details of CO2 reduction for the repowered wind farm.
Chapter 8 Review the entire works done in the course of the project.
5
CHAPTER 2
RE-POWERING OF WIND FARMS
2.1 INTRODUCTION
This chapter throws light on the concept of Re-powering. Repowering refers to the
refurbishment of older wind turbines, or to their removal and replacement with newer, more
efficient turbines. Where older turbines have been removed and replaced with newer turbines,
these have generally been accomplished by installing fewer, larger turbines.
2.2 NEED FOR REPOWERING
In countries that started early with wind energy, old wind turbines were placed at
locations where the wind is often very good. Since the best locations for wind in these
countries are occupied by old wind turbines with lower energy output compared with new
wind turbines, programs are started to replace the old turbines with new ones. With
repowering, the first-generation wind turbines can be replaced with modern multi megawatt
wind turbines. In general, many factors speak in favour of repowering programs:
More wind power from the same area of land: wind power generation is multiplied
without the need for utilizing additional land.
Fewer wind turbines: the number of turbines can be reduced while enhancing the
natural landscape. The construction height can be raised.
Higher efficiency, lower costs: modern turbines make better use of available wind
energy. The cost of production is significantly lowered.
Better appearance: modern turbines rotate at much lower speeds and are thus more
visually pleasing than older, faster-rotating turbines.
Better power grid integration: modern turbines offer much better grid integration,
since they use a connection method similar to conventional power plants and also
achieve a higher utilization degree.
Wind speed and direction are known: at an existing wind turbine location wind speed
and direction are already known, so it is easy to calculate the expected annual energy
production for an existing location.
6
Additionally, it is often easier to get licenses to build a wind turbine (farm) on an existing
location than on a new location. But also for government and local authorities, the results of
repowering can be positive:
Additional wind energy power will create a larger basis for wind energy;
Although the wind turbines are higher after repowering, the quality of the landscape is
often perceived as being improved, since the number of wind turbines is reduced;
Replacement can be used to achieve national (or local) targets for renewable energy
or for CO2 reduction.
But there are also practical reasons for repowering; for example, in situations in which
the manufacturer of the wind turbine no longer exists, and no other company can carry out
the refurbishment of the wind turbine.
2.3 ADVANTAGES OF WIND REPOWERING
Wind energy plants typically have a life span of approximately 20 Years. However,
the rapid development of technology in the last two Years has made it economically
justifiable to replace the older low capacity turbine by more efficient and larger turbine even
before expiration of the technical life span.
2.3.1 TECHNICAL ADVANTAGE
Repowering is the replacement of first –generation small capacity turbines of less than
500kW rating usually operating for more than 15 Years with the modern high capacity and
more sophisticated wind-turbines .This results in the efficient utilisation of potential wind
sites and producing high quantum of energy. In addition, the modern WTGs come with much
higher efficiency, which improves the total Capacity Utilization Factor (CUF) significantly
for the wind farm. The CUF for the old turbine was around 15-20 percentage, which would
get doubled post repowering mainly because of improved design, taller tower and higher
rotor diameter.
2.3.2 OPERATIONAL ADVANTAGE
The re-powering of wind turbine results in the reduction of operation and maintenance
(O&M) cost of the farm as the number of turbines operating in the farm reduces by more than
half. Presently older turbines are fitted with critical and outdated component which causes
7
high failure rate and increased Mean Time between Failures (MTBF), lapses in O&M and
increased machine down time and which in-turn reduces the total energy production.
Additionally, for aging WTGs, wear and tear due to longer operating hours also increases
O&M costs. In comparison, repowering would deploy more advanced and state-of-the-art
technology wind turbines, which requires less maintenance and incur very low O&M cost as
compared to the previously installed low rating small turbines. Modern wind turbines are
fitted with modern power electronics converters which use similar connection method as used
in conventional power plant. This offers much better integration of the wind farm with the
grid, which results achieving a higher degree of utilization.
2.3.3 FINANCIAL ADVANTAGES
Repowering results in more wind turbine capacity addition per unit of land area,
which also increases total kWh of electricity produced because of the improved CUF.
Further, wind speed and direction known for longer duration and a particular site makes it
easy to estimate the expected annual energy production from the modern high capacity wind
turbines. This helps in maximizing the revenue from the project, thus achieving better wind
power economics. A prominent barrier faced by the wind power developers today is the
availability of sites with sufficient wind velocity and its acquisition thereafter. Repowering of
old turbines with larger turbines would result in significant reduction in land area/MW of
wind farm. Further, increased electricity output post re-powering presents an opportunity for
the states to achieve the Renewable Purchase Obligations (RPO) targets and national targets
as set in the National Action Plan on Climate Change (NAPCC).It also offers prospects to the
developers to generate and sell Renewable Energy Certificates (RECs), thus improving the
return on investment and reducing the payback period. In addition to the clean development
mechanism (CDM) benefits can be maximised by reducing more greenhouse gas (GHG)
emissions from the project. An additional foreign exchange can be generated from the project
through the sale of certified emission reductions (CERs).
2.3.4 SOCIAL AND ENVIRONMENT ADVANTAGE
Repowering offers many social and environmental advantages over the old turbines.
The modern turbines rotate at much lower speed and have much quite operation than the
typical first and second generation design. A reduced density of wind turbines and their
reduced speed would not only increase the visual appeal of the farm but would also ring
8
down the number of collision of birds and addresses the avian mortality issue to a great
extent. The quality of the landscape also improves as the number of turbines are much less
per unit area, which results in maximizing the benefits from ancillary land uses, such as
access roads ,intercropping and transmission lines, right-of-ways etc., Presently, majority of
the onshore wind power projects are located far from the public view and away from the
residential locations. Repowering would enable the wind industry to rehabilitate to sites with
modern, more aesthetically pleasing designs and less dense arrays causing less noise
pollution .This would increase the visibility of wind plants and improve the public acceptance
for the same.
2.4 METHODOLOGY TO ASSESS REPOWERING POTENTIAL
To assess financial impacts and implications of re-powering wind power project, wind
energy generation estimates are required. Establishing a methodology for calculation or
repowering serves a two-fold purpose. It gives new wind power potential capacity and
estimates of energy generation. To calculate the re-powering potential of any site or wind
power project, the following important technical aspects need to be considered.
1. Wind resource at the site.
2. Existing installed capacity (MW), rating of turbines.
3. New technology selection (higher capacity turbine specifications).
4. Available land area and necessary set-off.
5. Estimation of new installed capacity after re-powering (with different micrositing or
turbine-spacing criteria and turbine-rating selection, the estimation of new capacity
will vary).
6. Estimation of gross and net energy generation (with different micrositing criteria).
7. Energy-yield ratio (ratio of new generation to old generation from same land area or
same project location). Re-powering ratio (ratio of new wind power project capacity
to old project capacity).
2.5 SUMMARY
The concept of re-powering of wind farms, its methodology and its advantages are discussed
briefly.
9
CHAPTER 3
WIND ATLAS, ANALYSIS AND APPLICATION PROGRAM (WAsP)
3.1 INTRODUCTION
WAsP was developed and distributed by the Wind Energy Department at Risǿ DTU,
Denmark. It is a PC program for predicting wind climate, wind resources and power
production from wind turbine and wind farm- includes complex terrain flow model,
roughness change model, and model for sheltering obstacles. Its predictions are based on
wind data measured at 10 minute/hour intervals at stations in the same region for a Year, and
site details such as contour map, turbine location, turbine characteristics, etc.
3.1.2 WHAT IS WASP?
WAsP is a PC-program for the vertical and horizontal extrapolation of wind climate
statistics. It contains several models to describe the wind flow over different terrains and
close to sheltering obstacles. WAsP consists of five main calculation blocks:
Analysis of raw data:
This option enables an analysis of any time-series of wind measurements to provide a
statistical summary of the observed, site-specific wind climate. This part is implemented in a
separate tool, the Observed Wind Climate (OWC) Wizard.
Generation of wind atlas data:
Analysed wind data can be converted into a regional wind climate or wind atlas data set.
In a wind atlas data set the wind observations have been 'cleaned' with respect to site-specific
conditions. The wind atlas data sets are site independent and the wind distributions have been
reduced to some standard conditions.
Wind climate estimation:
Using a wind atlas data set calculated by WAsP or one obtained from another source –
e.g. the European Wind Atlas – the program can estimate the wind climate at any specific
point by performing the inverse calculation as is used to generate a wind atlas. By introducing
10
descriptions of the terrain around the predicted site, the models can predict the actual,
expected wind climate at this site.
Estimation of wind power potential:
The total energy content of the mean wind is calculated by WAsP. Furthermore, an
estimate of the actual, annual mean energy production of a wind turbine can be obtained by
providing WAsP with the power curve of the wind turbine in question.
Calculation of Wind Farm Production:
Given the thrust coefficient curve of the wind turbine and the wind farm layout,
WAsP can finally estimate the wake losses for each turbine in a farm and thereby the net
annual energy production of each wind turbine and of the entire farm, i.e. the gross
production minus the wake losses. The program thus contains analysis and application parts,
which may be summarised as follows:
Analysis
1. Time-series of wind speed and direction —> observed wind climate (OWC).
2. Observed wind climate + met. station site description —> regional wind climate
(RWC, wind atlas data sets)
Application
1. Regional wind climate + turbine site description —> predicted wind climate (PWC).
2. Predicted wind climate + power curve —> annual energy production (AEP) of wind
turbine
Wind farm production
1. Predicted wind climates + WTG characteristics —> gross AEP of wind farm
2. Predicted wind climates + WTG characteristics + wind farm layout —> wind farm
wake losses
3. Gross annual energy productions + wake losses —> net AEP of wind farm.
11
3.2 WIND POWER PRODUCTION CALCULATION
We need to equip with the following to predict the wind power production of a wind
farm:
• A contour map of the area
• The wind data from the airport
• A simple description of the land use in the area
• An annotated sketch of the buildings near the met. Station
• A description of the power-generating characteristics of the turbine
These data have been converted into digital files, as follows:
• A digital map of elevations and roughness
• A data file containing wind data
• A data file describing the buildings at the site
• A data file containing a power production curve for the turbine
3.2.1 METHODOLOGY
From engineering data, we know how much power will be generated by the turbine at
a given wind speed. If the plan was to erect the turbine at exactly the same place where the
meteorological data had been collected, then it would be a really simple task to work out how
much power to expect.
However, just from looking at the map if the proposed turbine site is completely
different from the meteorological station: the properties of the meteorological station itself
will affect the wind data recorded there. In addition, the properties of the turbine site will
have an effect on the way that the wind behaves near the turbine. It is also unlikely that the
hub height of the turbine would be the same as the height of the anemometer. What we need
is a way to take the wind climate recorded at the meteorological station, and use it to predict
the wind climate at the turbine site. That is what WAsP does. Using WAsP, we can analyse
the recorded wind data, correcting for the recording site effects to produce a site-independent
12
characterization of the local wind climate. This site independent characterization of the local
wind climate is called a wind atlas data set or regional wind climate. We can also use WAsP
to apply site effects to wind atlas data to produce a site-specific interpretation of the local
wind climate.
3.2.1.1 Calculating the wind atlas
Setting up a met. Station
To Setting up a met. Station WAsP requires the following
A description of the data-recording site
A summary of the wind data recorded at the site
Adding Wind Observations
Now we need to insert some wind data to the hierarchy. Select the met. Station and insert
an Observed wind climate describing the site. Now WAsP needs to know about the site where
the data were collected at the met. Station site, if buildings and shelterbelts of trees were
found in the vicinity of the anemometer mast WAsP needs to know about these.
The Atlas Calculation
WAsP is now ready to calculate the wind atlas for WAsPdale. Now get WAsP to generate
the wind atlas. In a wind atlas data set the wind observations have been 'cleaned' with respect
to the site specific conditions. The wind atlas data sets are site-independent and the wind
distributions have been reduced to some standard conditions; i.e. four standard roughness
classes and five standard heights above ground level.
3.2.1.2 Estimating Wind Power
Setting Up a Turbine Site
Now the project contains a wind atlas with site-independent wind climate data, we can
apply those data to the proposed turbine site. WAsP will adjust the data for the situation
found at the turbine site, and will produce a prediction of the wind climate for the site itself.
13
WAsP now requires:
The location of the site in the map
A description of the type of wind turbine that you propose to use.
If there are no obstacles near the hilltop, so there is no need to add an obstacle list to this site.
Locating the Turbine Site
First, locate the turbine site in the map. Because the map and the turbine site are in the
same project, WAsP automatically knows that the site lies in the area covered by the map. All
that we need to do is provide the co-ordinates.
Assigning the Power Curve
In order to predict how much power will be produced by the turbine, WAsP needs to
know the power production characteristics of the turbine. We provide this information to
WAsP by associating a wind turbine generator hierarchy member with the turbine site.
Predicting Wind Climate and AEP
WAsP is now ready to predict the wind climate at the turbine site. We can now open
the turbine site window to view the results. WAsP will estimate that about GWh per Year
would be generated by erecting a turbine on the hilltop. This number is referred to as the
Annual Energy Production (AEP).
3.2.1.3 Estimating wind farm production
Setting up a wind farm
WAsP now requires
The locations of wind farm turbine sites in the map
A description of the type of wind turbine that you propose to use
There are still no obstacles near the hilltop, so there is no need to add an obstacle list to this
wind farm.
14
Locating the turbine sites
First, locate the turbine site in the map. Because the map and the turbine site are in the same
project, WAsP automatically knows that the site lies in the area covered by the map. All that
we need to do is provide the co-ordinates.
Assigning wind turbine generators
In order to predict how much power will be produced by the wind farm, WAsP needs to
know the power production and thrust curve characteristics of each turbine. If the turbines in
your farm are all of the same type, you provide this information to WAsP by associating a
wind turbine generator hierarchy member with the wind farm. If one or more turbines in a
farm are different from the rest, we must provide a separate wind turbine generator hierarchy
member for this or these turbines.
Predicting wind farm production
WAsP is now ready to predict the power production of the wind farm.
3.3 SUMMARY
The concept and the working of WAsP are discussed in detail along with the procedure for
the calculation of wind power production.
15
CHAPTER 4
MICROSITING OF WIND FARMS
4.1 INTRODUCTION
This section describes the wind resource assessment methodology, micro-survey &
micro-siting and location of the site selected to carry out the study on repowering and the
wind resource at the site, the terrain description, orographic variations and orographic
elements and the turbine characteristics of the existing wind turbines and the turbines chosen
for repowering.
4.2 WIND RESOURCE ASSESSMENT METHODOLOGY
Understanding the characteristics of the wind resource is critical to all aspects of wind
energy utilization right from identification of suitable sites to economic viability of projects,
design of turbines, etc. The presence or absence of certain essential factors will decide
whether or not a particular site can become a potential wind farm. Thus, wind resource
assessment is the first step in designing any wind power project. This activity includes the
estimation and review of the existing wind resource data, nature of terrain, vegetation cover,
accessibility and other features in the region of interest. The quality of a wind resource
assessment program depends on sound siting, measurement techniques, quality equipment
and data analysis techniques. The various steps involved in wind resource assessment process
are,
Large area screening & Field visit
Validation (Data collection & Screening)
Micro siting
Estimation of the wind resource ranges from overall estimates of the mean energy
content of the wind over a large area called Regional assessment to the prediction of the
average Yearly energy production of a specific wind turbine or wind farm at a specific
location called Siting. If there is no on-site data available, modeling is commonly used to
translate long-term reference station data to the site. Statistical dynamical downscaling
method is one of the methods used to model the potential of a remote location from a bigger
picture. Modeling can be accurate in many cases, but should not replace on-site
measurements for more formal wind farm energy assessment. It is also possible to make
16
predictions of wind speeds at a site using numerical wind atlas methodology. Measure-
Correlate-Predict – is the method that involves comparing the wind speeds on the site with
the wind speeds at the reference station and using the comparison to estimate the long-term
wind speed on the site.
4.3 MICROSURVEY & MICROSITING (OPTIMIZATION)
In a wind farm, turbines will typically be placed in rows perpendicular to the
prevailing wind direction. Due to wake losses, wind shear, turbulence in wind and turbulence
added by the turbines power generation from the turbines will reduce. Because If the wind
striking a second row turbine before the wind speed has been restored from striking the first
row turbine, then the energy production from the second row turbine will be reduced compare
to the normal production. So proper distance should be maintained between turbines. If the
space between the turbines is more, then each turbine will produce maximum power, but less
number of turbines can only be installed and this could make the project activity
uneconomical. So an optimum layout is required with optimum number of turbines and
optimum amount of generation. This can be done with the help of micrositing.
Micrositing can provide high quality estimate over the wind farm area so that each
turbine can be placed for optimal energy yield. Energy estimates must be adjusted to reflect
long term yield of the wind farm, generally for 20 Years. The micro siting process involves
conducting surveys, monitoring and flow modeling at individual sites to quantify small scale
variations in the wind resource over the area. Modeling requires three types of inputs
essentially and they are,
Topographical inputs (site characteristics)
Climatological inputs ( wind characteristics)
Wind turbine generator characteristics
4.4 SUMMARY
The wind resource assessment methodology and micro-survey & micro-siting were discussed
in this section.
17
CHAPTER 5
CALCULATION OF EXISTING GENERATION USING WAsP
5.1 INTRODUCTION
This section outlines the input files calculated for WAsP and the calculation of
Existing generation. Also the calculated the existing generation and actual generation were
compared and conclusions were arrived.
5.2 EXISTING INSTALLED CAPACITY AND RATING OF TURBINES
Existing farm consist of 39 turbines of total capacity 11.58MW of which 36 turbines
ranging from 200kw to 500kw commissioned during the Year 1990-95 and three turbines of
1250kw was commissioned recently.
MAKE CAPACITY NOs
VESTAS RRB
225kw 9
500kw 9
SUZLON
350kw 5
1250kw 3
BONUS 300kw 4
PIONEER WINCON 250kw 6
ENERCON 200kw 3
Table 5.1 Existing Installed Capacity and Rating of Turbines
5.3 WAsP OUTPUT - EXISTING WIND FARM GENERATION
The created WAsP inputs are given to WAsP and the annual energy output of the
wind farm are estimated. WAsP will give average wind speed of each machine and the Gross
output and Net output of each machine. Then the Final output also calculated by considering
the following parameters
18
5.3.1 Existing Wind Farm Layout
Fig.5.1 Existing Wind Farm Layout.
5.3.2 Google Synchronised 3D Image
Fig. 5.2 Google Synchronised 3D Image.
19
5.3.4 AEP Calculation
Fig. 5.3 AEP Calculation.
AEP from WAsP⇒28.679GWh
5.3.5 Energy Losses Due To Wake
Fig. 5.4 Energy Losses Due To Wake
20
Then the Actual output is calculated by assuming the following parameters
Machine availability 95 %
Grid availability 90%
Transmission Efficiency 95%
WAsP prediction error 5%
Then the total generation of the wind farm and the plant load factor is calculated.
Existing Capacity ⇒11.58MW
Theoretical AEP ⇒ Farm Capacity×8760hrs
⇒101.4298GWh
AEP from WAsP ⇒28.679GWh
Actual Generation ⇒AEP from WAsP ×0.95×0.95×0.95×0.90
⇒22.130GWh
Plant Load Factor ⇒0.218
5.3.6 Observation from the results
The actual generation of the wind farm is very low when compare to the WAsP
predicted output
One of the reason behind is, the efficiency of the machines is reducing due to the
ageing of the machines
The above can be eliminated by repowering with high capacity (megawatt) machines
by accurate micrositing
5.4 SUMMARY
Using WAsP the generation of the existing wind farm was calculated. For the calculation
input files were created using the data collected during the field visit. Finally the existing
generation was calculated and compared with the actual generation.
21
CHAPTER 6
ESTIMATION OF NEW INSTALLED CAPACITY AND GENERATION
AFTER REPOWERING
6.1 INTRODUCTION
Using WAsP the annual energy output of the wind farm after the repowering was
predicted. Further, the energy yield ratio and repowering ratio of this repowering project also
calculated.
6.2 INPUTS REQUIRED FOR WAsP
6.2.1 NUMERICAL WIND ATLAS
CWET in association with Riso DTU, Denmark has developed Numerical wind atlas
of India. Numerical wind atlas methodologies have been devised to solve the issue of
insufficient wind measurements. One such methodology is the so-called KAMM/WAsP
method developed at Risø National Laboratory, Denmark.
In this methodology an approach called statistical-dynamical downscaling is used
(Frey-Buness et al, 1995). The basis for the method is that there is a robust relationship
between meteorological situations at the large scale and meteorological situations at the small
scale.
Karlsruhe Atmospheric Mesoscale Model (KAMM) is used to model the mesoscale
effects on the wind flow over India using modeling domains. KAMM calculates the
mesoscale wind field using as input a description of the synoptic-scale climatology, as well as
suitable orography and roughness maps. The climatology of the post-processed simulated
wind fields and the local orography and roughnesses are subsequently used by WAsP (Wind
Atlas Analysis and Application Programme) to predict the local wind climate.
Creating a numerical wind atlas demands a large computational effort, and this
computation effort increases with the size of the region to be mapped. India‘s very large size
means that it is not possible to perform the numerical wind atlas calculations at sufficient
resolution for the whole country using a single modeling domain. Therefore it was decided to
split the numerical wind atlas effort into twelve calculation domains (See Fig.6.1).
22
Fig. 6.1 Numerical Wind Atlas
Figure.6.1 Map of India showing the 12 modeling domains used. A complete
numerical wind atlas calculation is made for each domain.
The .lib files with 5 km resolution generated by KAMM have been verified with the
.lib file generated by WAsP with reference to the actual measurements at very limited
location. Summary of the verification for wind speed for each modelling domain at 10/20m
agl. Is given in table 6.1. (For more details please refer Indian Wind Atlas book published by
CWET, Chennai)
The output of KAMM wind atlas file (.lib file) can be used as an input file of WAsP
for the further analysis after the validation of results with nearby sites. Figure 6.2 gives an
example of wind atlas file (.lib). This can also be referred to get an idea of wind
characteristics over the given area at different height levels with reference to the roughness.
23
Table 6.1 Summary of the Verification for Wind Speed for Each Modeling Domain
.
Domain Nos. of stations
used for verification
Mean abs. error of wind
speed at 10/20m (%)
ISA 5 10.77
ISB 5 13.32
ICA 5 12.45
ICB 4 7.68
ITE 4 10.17
ITF 1 6.64
ITB 3 17.05
ITC 4 18.7
ITD 4 33.69
INU 5 51.30
IIW 1 6.92
IIE 2 30.95
24
Fig. 6.2 Wind atlas for edayarpalayam (long. 77.150E lat. 10.950N) obtained from
CWET.
6.2.2 VECTOR MAP
Vector maps are used to describe the elevation (orography) and land cover (surface
roughness) of the area surrounding calculation sites such as meteorological stations, reference
sites, turbine sites or the sites in a resource grid.
WAsP uses vector maps, in which terrain surface elevation is represented by height
contours and roughness lengths by roughness change lines. The map coordinate system must
be Cartesian and the coordinates must be given in meters.
It is not possible to create and edit maps from within the WAsP program itself; this
must be done with the WAsP Map Editor which can be invoked from the Tools menu.
25
Furthermore, there is no direct link between WAsP and the Map Editor – they only
communicate through the map file itself. When a map file has been changed in the Map
Editor, it must be reloaded into WAsP in order to take effect.
Fig. 6.3 Vector Map
6.2.3 TRANSFORMING SRTM DATA TO WAsP MAPS
SRTM coordinates are non-projected (latitude, longitude). Horizontal reference
system (datum) is WGS84 and vertical reference is the EGM96 geoid. Transforming SRTM
data to WAsP elevation maps therefore require the following:
Transformation of geo. Coordinates to a metric system
Transformation of grid point elevations to height contours
26
Transformation of WGS84 to another datum – if need be
The tools required for transforming SRTM data to vector map are:
Surfer
WAsP Map Editor
WAsP Geo projection utility
Step 1: Download data from the SRTM data for the required site
SRTM HGT format is supported by Surfer.
Step 2: Convert the HGT file to GRD format using Surfer
Unzip the downloaded ZIP file
Rename the HGT file to DEM
Create HDR and STX files (with the same file name)
Insert upper left corner coordinates (signed) in the HDR file
Start Surfer and choose Grid | Convert…
Open the *.HDR file
Save grid as *.GRD file (with the same file name)
27
Fig.6.4 Creating Vector Map in Surfer
The result is a Surfer GRD file in geographical coordinates (WGS84). Inspect the grid
for voids (undefined values) and spikes and wells using Surfer. Remove spikes and wells by
inserting a sensible elevation value using the Surfer grid editor.
Step 3: Change the coordinate system to UTM
1. First, convert the grid file to a list-of-points file in Surfer:
2. Choose Grid | Convert…
3. Open GRD file and save as ASCII XYZ (*.dat)
Now, you can use the Geo-Projection Transformer utility program to make this
transformation, using File | Transform XYZ-file.
28
Fig. 6.5 Change the Coordinate System to UTM
The result in both cases should be an ASCII XYZ file in metric map coordinates
(WGS84).
Step 4: Make a metric GRD file
In Surfer, choose Grid | Data…
Open the XYZ file as ‗Golden Software Data‘
1. Choose ‗Skip leading spaces‘ and ‗Treat consecutive delimiters as one‘
2. Choose a name for ‗Output Grid File‘
3. Invoke Filter data... if you want exclude e.g. certain high z-values in the data
4. Set values for ‗Grid Line Geometry‘, i.e. grid size and extents of modelling domain
5. The result is a Surfer GRD file in metric map coordinates (WGS84) covering the
modelling domain. Surfer has made a complete grid without voids by interpolation
(e.g. Kriging).
Step 5: Make a contour map in DXF format
1. Create a new contour map in Surfer, using the GRD file as input
2. Choose the appropriate contour levels in the Properties | Levels window
29
3. Export the height contours to a 3-D AutoCAD DXF file from the Map | Contour
map... menu
Fig. 6.6 Making Contour Map in DXF format
Step 6: Make a WAsP contour map
1. Open the DXF file in the WAsP Map Editor
2. Add and Replace... to merge several maps
3. Check the map contours for spikes and wells
4. Transform to any other datum, if need be
5. Compare to a scanned background map
6. Check vertical datum‘s and compare elevations
7. Add spot heights and other details close to the site(s)
30
8. Add roughness change lines – including the coastline, if any
9. Save the map as WAsP ASCII map file (*.map)
Fig. 6.7 Making WAsP Contour Map by Map Editor
The result is a WAsP ASCII map that can used for WAsP analysis and/or application
Fig. 6.8 WAsP ASCII Map
31
6.2.4 WIND TURBINE GENERATOR FILE
Wind turbine generators are used to describe wind turbines. They can be associated
with (be a child of) turbine sites, turbine site groups, wind farms and resource grids. If a wind
turbine generator is inserted at the project level, it will be used for all sites and grids in the
project. WAsP can also read wind turbine data in the standard WAsP *.pow format.
Wind turbine generators contain information about how turbines transform wind
energy into electrical power, and the hub height usual for the turbine when deployed. The
wind turbine generator file also contains the rotor diameter, values of the thrust coefficient,
Ct, and some general information relating to the wind turbine generator. Wind turbine
generator files can contain several performance tables, each relating to a specific air density
or noise level.
32
The power curve and other turbine characteristics of the turbine used are given below:
6.3 EXISTING WIND TURBINES
6.3.1 VESTAS ‘V39’ 500kW
Fig. 6.9 Power Curve for VESTAS ‗V39‘ 500kW
33
6.3.2 VESTAS ‘V27’ 225kW
Fig. 6.10 Power Curve for VESTAS ‗V27‘ 225kW
34
6.3.3 SUZLON ‘S33’ 350kW
Fig. 6.11 Power Curve for SUZLON ‗S33‘ 350kW
35
6.3.4 Pioneer Wincon 250kW
Fig. 6.12 Power Curve for Pioneer Wincon 250kW
36
6.3.5 Enercon ‘E30’ 200kW
Fig. 6.13 Power Curve for Enercon ‗E30‘ 200kW
37
6.3.6 Bonus 300kW
Fig. 6.14 Power Curve for BONUS 300kW.
38
6.3.7 SUZLON ‘S64’ 1250kW
Fig. 6.15 Power Curve for SUZLON ‗S64‘ 1250kW
6.4 NEW TECHNOLOGY SELECTION FOR REPOWERING
For Repowering three different types of wind turbines were selected namely
‗GAMESA G90‘, ‗GAMESA G114 and ‗SUZLON S88. GAMESA G90 is doubly fed
induction generator with rotor diameter of 90m and GAMESA G114 is also a doubly fed
induction generator with rotor diameter of 114m.Both have a rated capacity of 2000kW.And
SUZLON S88 is an asynchronous generator with rotor diameter of 88m rated capacity of
2100kW The wind turbine specifications and the power curve and thrust curves are shown
below
39
6.4.1 GAMESA ‘G90’ 2.0MW
Fig. 6.16 Power Curve for GAMESA ‗G90‘ 2.0MW
40
6.4.2 SUZLON ‘S88’ 2.1MW
Fig. 6.17 Power Curve for SUZLON ‗S88‘ 2.1MW
41
6.4.3 GAMESA ‘G114’ 2.0 MW
Fig. 6.18 Power Curve for GAMESA ‗G114‘ 2.0 MW
6.5 AEP CALCULATION OF REPOWERED WIND FARM
Repowering is carried out for 36 turbines on existing wind farm with capacity from
200kw to 500kw. Annual energy production is calculated for different turbine models and
different spacing options. Then the energy yield ratio and repowering ratio are estimated. The
various turbines model are selected for repowering are listed below
SUZLON S88-2.1MW
GAMESA G90-2MW
GAMESA G114-2MW
42
6.5.1 MICROSITING FOR REPOWERING
6.5.1.1 Configuration I:
This is the art of developing wind machines in a most optimal manner for achieving best
wind farm capacity
In this set up 15 turbines are used.
The 15 turbines are installed in arrays.
Spacing in these arrays are generally 5Dx7D. (D is the rotor diameter)
The factor by which the output of a wind farm would be less than what we should
ideally get is known as ―array efficiency‖
Array efficiency is not affected in case of strong wind conditions, but is strongly
affected in the case of low wind conditions.
In the same wind farm site and in the same land area new selected wind turbine were
placed with 5D×7D spacing and the images are shown below
Layout for configuration I:
Fig. 6.19 Layout for Configuration I
43
Vector Map for Configuration I
Fig. 6.20 Vector Map
6.5.1.2 Configuration II
In this set up 9 turbines are used.
In the wind rose shown in figure 6.2, 9th
sector is having more wind speed for most of
the times in a Year. The 9 turbines are placed in a manner according to the wind
direction in order to reduce wake losses as shown in the figure 6.21.
44
Vector Map with Turbine Spacing for Configuration II
Fig. 6.21 Vector Map
6.6 CALCULATION OF AEP FROM WAsP FOR CONFIGURATION I
6.6.1 FOR GAMESA G90
Fig. 6.22 AEP for GAMESA G90
45
Wake Losses
Fig. 6.23 Wake Losses for GAMESA G90
Farm Capacity ⇒ 33.75MW
Theoretical AEP ⇒ 295.65GWh
AEP Using WAsP ⇒ 102.556GWh
Actual Generation ⇒ 79.136GWh
Plant Load Factor ⇒ 0.268
Repowering ratio ⇒ Capacity of the existing farm : Capacity of the repowered wind farm
⇒ 1:2.915
Energy yield ratio ⇒ Energy from the existing farm : Energy from the repowered farm
⇒ 1:3.576
46
6.6.2 FOR SUZLON S88:
Fig. 6.24 AEP for SUZLON S88.
Wake Losses
Fig. 6.25 Wake Losses for SUZLON S88.
47
Farm Capacity ⇒ 35.250MW
Theoretical AEP ⇒ 308.790GWh
AEP Using WAsP ⇒ 90.074GWh
Actual Generation ⇒ 69.504GWh
Plant Load Factor ⇒ 0.225
Repowering ratio ⇒ Capacity of the existing farm: Capacity of the repowered wind farm
⇒ 1:3.044
Energy yield ratio ⇒ Energy from the existing farm : Energy from the repowered farm
⇒ 1:3.141
6.6.3 FOR GAMESA G114:
Fig. 6.26 AEP for GAMESA G114.
48
Wake Losses
Fig. 6.27 Wake Losses for GAMESA G114
Farm Capacity ⇒ 33.75MW
Theoretical AEP ⇒ 295.65GWh
AEP Using WAsP ⇒ 162.195GWh
Actual Generation ⇒ 125.156GWh
Plant Load Factor ⇒ 0.423
Repowering ratio ⇒ Capacity of the existing farm: Capacity of the repowered wind farm
⇒ 1:2.915
Energy yield ratio ⇒ Energy from the existing farm : Energy from the repowered farm
⇒ 1:5.655
49
6.7 CALCULATION OF AEP FROM WAsP FOR CONFIGURATION II
6.7.1 FOR GAMESA G90:
Fig. 6.28 AEP for GAMESA G90.
Wake Losses
Fig. 6.29 Wake Losses for GAMESA G90
50
Farm Capacity ⇒ 21.75MW
Theoretical AEP ⇒ 190.53GWh
AEP Using WAsP ⇒ 67.227GWh
Actual Generation ⇒ 51.875GWh
Plant Load Factor ⇒ 0.272
Repowering ratio ⇒ Capacity of the existing farm : Capacity of the repowered wind farm
⇒ 1:1.878
Energy yield ratio ⇒ Energy from the existing farm : Energy from the repowered farm
⇒ 1:2.344
6.7.2 FOR SUZLON S88:
Fig. 6.30 AEP for SUZLON S88
51
Wake Losses
Fig. 6.31 Wake Losses for SUZLON S88
Farm Capacity ⇒ 22.65MW
Theoretical AEP ⇒ 198.414GWh
AEP Using WAsP ⇒ 63.628GWh
Actual Generation ⇒ 49.098GWh
Plant Load Factor ⇒ 0.247
Repowering ratio ⇒ Capacity of the existing farm : Capacity of the repowered wind farm
⇒ 1:1.956
Energy yield ratio ⇒ Energy from the existing farm : Energy from the repowered farm
⇒ 1:2.219
52
6.7.3 FOR GAMESA G114
Fig. 6.32 AEP for GAMESA G114.
Wake Losses
Fig. 6.33 Wake Losses for GAMESA G114.
53
Farm Capacity ⇒ 21.75MW
Theoretical AEP ⇒ 190.53GWh
AEP Using WAsP ⇒ 101.103GWh
Actual Generation ⇒ 78.015GWh
Plant Load Factor ⇒ 0.409
Repowering ratio ⇒ Capacity of the existing farm : Capacity of the repowered wind farm
⇒ 1:1.878
Energy yield ratio ⇒ Energy from the existing farm : Energy from the repowered farm
⇒ 1:3.525
54
CHAPTER 7
CO2 REDUCTION FOR THE REPOWERED WIND FARM
7.1 INTRODUCTION
The power sector accounts for around 40% of global CO2 emissions, and it is clear
that we cannot win the fight against climate change without a dramatic shift in the way we
produce and consume electricity. With dramatic increases in global power demand,
renewable energy technologies must be rolled out quickly to provide emissions-free
renewable electricity for industrialised and developing countries alike.
7.2 HOW MUCH CO2 CAN WIND ENERGY SAVE?
Wind energy does not emit any greenhouse gases, and has an extremely good energy
balance. The calculations on just how much CO2 could be saved by wind energy is based on
an assumption for the carbon intensity of the global electricity sector, i.e. the typical amount
of CO2 emitted by producing one kWh of power. Individual countries emissions differ
substantially, but here we use the IEA‘s estimate of 0.950/MWh as an average value for the
carbon dioxide reduction to be obtained from wind generation.
In India, wind energy is expected to generate up to 338 TWh of electricity in 2020,
which would reduce CO2 emissions by 203 tons. Again based on a reduction of 15% from
the business-as-usual scenario by 2020, India could achieve 46-74% of the emissions
reductions required in the energy sector by wind energy only (depending on IEA model).
7.2 CALCULATION OF CO2 REDUCTION FOR CONFIGURATION I
7.2.1 FOR GAMESA G90 FARM
1. Determination of the Fossil Primary Energy Input (PEI) of the Project
⇒0 (only power from the wind turbine is used)
2. Determination of the Direct CO2 Emissions Produced by the Project
⇒0 (the wind turbine produces no CO2 emissions for
electricity production)
3. The PEI Baseline
The efficiency factor in the Farm is assumed with 26.8%.
Thus, the PEI ⇒ 79.136 GWh / Year/26.8%
55
⇒ (79.136 x 100) / 26.8
⇒ 295.28 GWh / Year
4. Calculation of the CO2 Emissions Baseline
Take the electricity production and multiply it with the country´s emission factor in
electricity production (Table A.1):
⇒ 79.136 GWh / Year x 0.000950 tCO2 / kWh
⇒ 79136000 kWh / Year x 0.000950 tCO2 / kWh
⇒ 75179 tCO2 / Year
5. Calculation of the Reduction in PEI and CO2 Emissions
PEI: Baseline (Step 4) – PEI (Step 1)
⇒ 295280000 kWh / Year – 0
⇒ 295280000 kWh
CO2: Baseline (Step 5) – CO2project (Step2)
⇒ 75179 tCO2 – 0
⇒ 75179 tCO2 / Year
7.2.2 FOR SUZLON S88 FARM
1. Determination of the Fossil Primary Energy Input (PEI) of the Project
⇒0 (only power from the wind turbine is used)
2. Determination of the Direct CO2 Emissions Produced by the Project
⇒0 (the wind turbine produces no CO2 emissions for
electricity production)
3. The PEI Baseline
The efficiency factor in the Farm is assumed with 22.5%.
Thus, the PEI ⇒ 69.504 GWh / Year/ 22.5%
⇒ (69.504 x100) / 22.5
⇒ 308.906 GWh / Year
4. Calculation of the CO2 Emissions Baseline
Take the electricity production and multiply it with the country´s emission factor in
electricity production (Table A.1):
⇒ 69.504 GWh / Year x 0.000950 tCO2 / kWh
⇒ 69504000 kWh / Year x 0.000950 tCO2 / kWh
⇒ 66028.8 tCO2 / Year
56
5. Calculation of the Reduction in PEI and CO2 Emissions
PEI: Baseline (Step 4) – PEI (Step 1)
⇒ 308906000 kWh / Year – 0
⇒ 308906000 kWh
CO2: Baseline (Step 5) – CO2project (Step2)
⇒ 66028.8 tCO2 – 0
⇒ 66028.8 tCO2 / Year
7.2.3 FOR GAMESA G114 FARM
1. Determination of the Fossil Primary Energy Input (PEI) of the Project
⇒0 (only power from the wind turbine is used)
2. Determination of the Direct CO2 Emissions Produced by the Project
⇒0 (the wind turbine produces no CO2 emissions for
electricity production)
3. The PEI Baseline
The efficiency factor in the Farm is assumed with 42.3%.
Thus, the PEI ⇒ 125.156 GWh / Year / 42.3%
⇒ (125.156 x100) / 42.3
⇒ 295.877 GWh / Year
4. Calculation of the CO2 Emissions Baseline
Take the electricity production and multiply it with the country´s emission factor in
electricity production (Table A.1):
⇒ 125.156 GWh / Year x 0.000950 tCO2 / kWh
⇒ 125156000 kWh / Year x 0.000950 tCO2 / kWh
⇒ 118898.2 tCO2 / Year
5. Calculation of the Reduction in PEI and CO2 Emissions
PEI: Baseline (Step 4) – PEI (Step 1)
⇒ 295877000 kWh / Year – 0
⇒ 295877000 kWh
CO2: Baseline (Step 5) – CO2project (Step2)
⇒ 118898.2 tCO2 – 0
⇒ 118898.2 tCO2 / Year
57
7.3 CALCULATION OF CO2 REDUCTION FOR CONFIGURATION II
7.3.1 FOR GAMESA G90 FARM
1. Determination of the Fossil Primary Energy Input (PEI) of the Project
⇒0 (only power from the wind turbine is used)
2. Determination of the Direct CO2 Emissions Produced by the Project
⇒0 (the wind turbine produces no CO2 emissions for
electricity production)
3. The PEI Baseline
The efficiency factor in the Farm is assumed with 27.2%.
Thus, the PEI ⇒ 51.875GWh / Year / 27.2%
⇒ (51.875x100) / 27.2
⇒ 190.716 GWh / Year
4. Calculation of the CO2 Emissions Baseline
Take the electricity production and multiply it with the country´s emission factor in
electricity production (Table A.1):
⇒ 51.875 GWh / Year x 0.000950 tCO2 / kWh
⇒ 51875000kWh / Year x 0.000950 tCO2 / kWh
⇒ 49281.25 tCO2 / Year
5. Calculation of the Reduction in PEI and CO2 Emissions
PEI: Baseline (Step 4) – PEI (Step 1)
⇒ 190716000 kWh / Year – 0
⇒ 190716000 kWh
CO2: Baseline (Step 5) – CO2project (Step2)
⇒ 49281.25 tCO2 – 0
⇒ 49281.25 tCO2 / Year
7.3.2 FOR SUZLON S88 FARM
1. Determination of the Fossil Primary Energy Input (PEI) of the Project
⇒0 (only power from the wind turbine is used)
2. Determination of the Direct CO2 Emissions Produced by the Project
⇒0 (the wind turbine produces no CO2 emissions for
electricity production)
58
3. The PEI Baseline
The efficiency factor in the Farm is assumed with 24.7%.
Thus, the PEI ⇒ 49.098 GWh / Year / 24.7%
⇒ (49.098x100) / 24.7
⇒ 198.777 GWh / Year
4. Calculation of the CO2 Emissions Baseline
Take the electricity production and multiply it with the country´s emission factor in
electricity production (Table A.1):
⇒ 49.098 GWh / Year x 0.000950 tCO2 / kWh
⇒ 49098000 kWh / Year x 0.000950 tCO2 / kWh
⇒ 46643.1 tCO2 / Year
5. Calculation of the Reduction in PEI and CO2 Emissions
PEI: Baseline (Step 4) – PEI (Step 1)
⇒ 198777000 kWh / Year – 0
⇒ 198777000 kWh
CO2: Baseline (Step 5) – CO2 project (Step2)
⇒ 46643.1 tCO2 – 0
⇒ 46643.1 tCO2 / Year
7.3.3 FOR GAMESA G114 FARM
1. Determination of the Fossil Primary Energy Input (PEI) of the Project
⇒0 (only power from the wind turbine is used)
2. Determination of the Direct CO2 Emissions Produced by the Project
⇒0 (the wind turbine produces no CO2 emissions for
electricity production)
3. The PEI Baseline
The efficiency factor in the Farm is assumed with 40.9%.
Thus, the PEI ⇒ 78.015 GWh / Year / 40.9%
⇒ (78.015 x100) / 40.9
⇒ 190.745 GWh / Year
4. Calculation of the CO2 Emissions Baseline
Take the electricity production and multiply it with the country´s emission factor in
electricity production (Table A.1):
59
⇒ 78.015 GWh / Year x 0.000950 tCO2 / kWh
⇒ 78015000 kWh / Year x 0.000950 tCO2 / kWh
⇒ 74114.25 tCO2 / Year
5. Calculation of the Reduction in PEI and CO2 Emissions
PEI: Baseline (Step 4) – PEI (Step 1)
⇒ 190745000 kWh / Year – 0
⇒ 190745000 kWh
CO2: Baseline (Step 5) – CO2project (Step 2)
⇒ 74114.25 tCO2 – 0
⇒ 74114.25 tCO2 / Year
7.4 SUMMARY
The importance of CO2 reduction and methodology of calculating CO2 reduction for the
wind farm are discussed briefly.
60
CHAPTER 8
CONCLUSION
8.1 INTRODUCTION
The purpose of this chapter is to review the significant results obtained during present
work. In the larger interest of the nation, the repowering activities should be taken up on a
priority basis which would significantly increase the share of renewable energy in the total
energy mix.
8.2 SUMMARY OF THE WORKDONE
This thesis aims at assessing the repowering potential of a wind farm. To carry out the
study an old wind farm located at Edayarpalayam near Pappampatti, Tamilnadu was selected.
The methodology to assess the repowering potential and the repowering potential of India
and the various states are discussed. The Wind Atlas, Analysis and application program
(WAsP) and its features and the methodology to calculate the annual energy productions are
described. The input data for the WAsP were collected and converted into WAsP input files.
Annual energy production of the Edayarpalayam wind farm was calculated and the annual
energy output of the wind farm after repowering also predicted.
The results of the WAsP for Existing generation and the output of the wind farm after
repowering are analysed to understand the significance of repowering to overcome the energy
crisis of the nation. The following are the observations and conclusions from the above study.
REPOWERING
EXISTING Configuration I Configuration II
G90 S88 G114 G90 S88 G114
AEP in GWh
/ Year 79.136 69.504 125.156 51.875 49.098 78.015 23.130
PLF in % 26.8 22.5 42.3 27.2 24.7 40.9 21.8
Repowering
Ratio 1:2.915 1:3.044 1:2.915 1:1.878 1:1.956 1:1.878 -
Energy Yield
Ratio 1:3.576 1:3.141 1:5.655 1:2.344 1:2.219 1:3.525 -
Wake Losses
in % 7.41 9.06 6.22 3.67 4.63 2.99 6.5
61
Table 8.1 Summary of the Work done
1. Configuration I is the most efficient in which G114 and G90 are the two dominant
machines giving more energy yield, however G114 is not entered into the Indian wind
industry, it‘s just preferred to show how the generation varies when the diameter and hub
height increases. Hence G90 is opted in our project.
2. Plant load factor (PLF) is increased from 21.8 % to 26.8 % for GAMESA G90
3. Energy yield ratio is 1:3.576 for GAMESA G90. i.e. Generation of the wind farm is
increased more than 3 times.
4. Repowering ratio for GAMESA G90 is 1:2.915 i.e. Capacity of the wind farm became
triple.
62
ANNEXURE-I
Region/C
ountry
tCO2/
MWh
Region/Co
untry
tCO2/
MWh
Region/
Country
tCO2/
MWh
Region/Cou
ntry
tCO2/M
Wh
OECD
Americas
0.485 Armenia 0.145 Singapor
e
0.523 Marocco 0.690
USA
(average)
0.531 Azerbaijan 0.462 Sri
Lanka
0.425 Mozambiqu
e
0.000
Canada 0.184 Belarus 0.300 Thailand 0.530 Namibiae 0.253
Mexico 0.455 Bosnia-
Herzegovi
na
0.908 Vietnam 0.409 Nigeria 0.396
Chile 0.398 Bulgaria 0.492 Other
Asia
0.274 Senegal 0.594
OECD
Europe
0.341 Croatie 0.337 Middle
East
0.687 South
Africa
0.900
Austria 0.183 Estonia 0.735 Bahrain 0.718 Sudan 0.470
Belgium 0.239 FYR of
Macedoni
a
0.753 Cyprus 0.755 Togo 0.271
Czech
Republic
0.534 Georgia 0.127 Iraq 0.731 Tunisia 0.547
Denmark 0.311 Gibraltar 0.756 Islamic
Rep. Of
Iran
0.609 United Rep.
OfTanzani
0.257
Finland 0.207 Kazakhsta
n
0.485 Israel 0.721 Zambia 0.003
France 0.089 Kyrgyzsta
n
0.087 Jordan 0.586 Zimbabwe 0.619
Germany 0.447 L.atvia 0.160 Kuwait 0.810 Other
Africa
0.489
Greece 0.739 Lithuania 0.116 Lebanon 0.698 America 0.178
Hungary 0.326 Malta 0.904 Oman 0.859 Argentina 0.358
Iceland 0.001 Republico
fMoldova
0.513 Qatar 0.496 Bolivia 0.368
Ireland 0.482 Romania 0.436 Saudi
Arabia
0.740 Brazil 0.075
Italy 0.416 Russia 0.322 Syria 0.649 Colombia 0.136
Luxembo
urg
0.382 Serbia 0.662 United
Arab
Emirates
0.694 Costa Rica 0.058
Netherlan
ds
0.389 Slovenia 0.337 Yemen 0.649 Cuba 0.735
Norway 0.010 Tajikistan 0.031 Africa 0.641 Dominican
Republic
0.633
Poland 0.652 Turkmenis
tan
0.810 Algeria 0.590 Ecuador 0.301
Portugal 0.379 Ukraine 0.373 Angola 0.220 El Salvador 0.304
Slovak
Republic
0.223 Uzbekista
n
0.462 Benine 0.695 Guatemala 0.354
Spain 0.337 Banglades
h
0.575 Botswan
ae
1.916 Haiti 0.513
Sweden 0.041 Brunei
Darussala
m
0.738 Cameroo
n
0.228 Honduras 0.391
Switzerla
nd
0.040 China
(mci. Hong
Kong)
0.765 Congoe 0.139 Jamaica 0.478
Turkey 0.484 Chinese
Taipei
0.647 Côte
dIvoire
0.428 Netherlands
Antilles
0.707
United
Kingdom
0.480 DPR of
Korea
0.483 DR of
Congo
0.003 Nicaragua 0.506
OECD
Asia
0.503 India 0.950 Egypt 0.459 Panama 0.297
Australia 0.862 Indonesia 0.757 Eritrea 0.665 Paraguay 0.000
Japan 0.435 Malaysia 0.638 Ethiopia 0.094 Peru 0.225
Korea 0.471 Myanmar 0.249 Gabon 0.366 Trinidad and
Tobago
0.725
New
Zealand
0.191 Nepal 0.004 Ghana 0.254 Uruguay 0.221
Non-
OECD
0.503 Pakistan 0.447 Kenya 0.321 Venezuela 0.203
Albania 0.023 Philippine
s
0.471 Libya 0.868 Other Latin
America
0.242
63
Table A.1 Electricity Emission Factors (EFel) For Different Countries (tCO2/MWh)2