Jacarandas Avenue Storm Drain Rehabilitation
Author: Arq. Octaviano Figueroa Salazar
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011
Rincón de Guayabitos
• “Rincón de Guayabitos is the perfect for those who want to experience the "real" Mexico –friendly people, dusty narrow cobblestone streets, and cement block houses in various states of repair – unspoiled and unchanged.
• The people who live here are kind, hard-working, generous, and proud. The majority are fisherman, farmers, waiters, cooks, maids, and construction workers. Their lives are filled with long-standing traditions and strong family values.” JaltembaBayLife.com
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011
Rincón de Guayabitos“Rincon de Guayabitos, a small town with a great beach that's laid back and perfect for relaxing and taking it easy. Soft golden sand and tranquil waves make this an ideal spot for families with young children. Mexican families come here on weekends and holidays”
About.Com Mexico Travel
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011
Rincón de Guayabitos
• Locals depend on Tourist Industry• March - November only Mexican Tourism• Summer Flooding causes economic hardship and Health Hazard
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011 5
Issue and Challenge
• Objective – Summer Rains cause extensive flooding in downtown Guayabitos
which infrastructure can’t support. – Solve the public health emergency crisis in Rincon de Guayabitos from
sewage discharges into the sea during flooding season.
• Solution– Construction of two new storm drains and rehabilitation of two existing
ones at the intersection of Jacaranda and Nuevo Sol.– Rehabilitation of retaining walls at the discharge of the Jacarandas
walkway.
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011
Objective: Avoid FloodingObjective: Avoid Flooding
August 7, 2011August 7, 2011
5th Flood of the Season5th Flood of the Season
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011
August 7, 2011August 7, 20115th Flood of the Season5th Flood of the Season
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011
August 7, 2011 August 7, 2011 5th Flood of the Season5th Flood of the Season
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011
August 7, 2011 August 7, 2011 5th Flood of the Season5th Flood of the Season
August 7, 2011August 7, 2011
5th Flood of the Season5th Flood of the Season
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011
August 19, 2011 August 19, 2011 8th Flood of the Season8th Flood of the Season
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011
August 19, 2011 August 19, 2011 8th Flood of the Season8th Flood of the Season
August 19, 2011August 19, 2011
8th Flood of the Season8th Flood of the Season
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011
Objective: Avoid FloodingObjective: Avoid Flooding
• Close of businessClose of business• Contamination of cisternsContamination of cisterns• Cancellation of reservationsCancellation of reservations• Spread of diseasesSpread of diseases
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011 13
Proposal• Description
– Largely resolve the health emergency caused by sewage discharge– Benefits over 8,000 residents and hundreds of thousands of visitors– Must be conducted this year or early 2012 prior to the rainy season – Part of a major State renovation project of 1.4 million pesos ($105,000 US)
• Project status• Flood area has been surveyed
• Detailed architectural drawings and hydraulic calculations of the hotel zone
• A preliminary budget estimate and resource availability
• The support of the College of Civil Engineers & Architects for technical validation.
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011
Hidrologic Area GuayabitosHidrologic Area Guayabitos
• The plan is to drain the collecting rain water The plan is to drain the collecting rain water from a 3'867 m2 hydrologic area. from a 3'867 m2 hydrologic area.
• The area has an annual average rainfall of The area has an annual average rainfall of 968.5 mm.968.5 mm.
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011
Hidrologic Area GuayabitosHidrologic Area Guayabitos
POLÍGONO DE LA INUNDACIÓNPOLÍGONO DE LA INUNDACIÓN
VIERNES 19 DE AGOSTOVIERNES 19 DE AGOSTO
Flood Zone in GuayabitosFlood Zone in Guayabitos
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011
Storm Drain Discharges Storm Drain Discharges in Need of Repairin Need of Repair
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011 17
Hydrologic Zone in Guayabitos
WATER MAIN OUTPUTWATER MAIN OUTPUT
SECOND WATER DUMPSECOND WATER DUMP
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011 18
(SECOND)Rehabilitation Area
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011 19
Storm Drain Discharge to OceanStorm Drain Discharge to Ocean
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011 20
Rehabilitate 4 Storm Drains
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011
Proposed Storm Drain SolutionProposed Storm Drain Solution
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011 22
Detail of Storm Drain Grating
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011 23
Detail of Storm Drain discharge
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011 24
Budget
206,000
16,000
46,000
42,000
76,000
14,000
12,000
TotalPesos
CONCEPT QUANTITY UNIT Cost Pesos
USD
1 PRELIMINARIES 1 LOT 12,000 $ 892
2 EXCAVATIONS 1 LOT 14,000 $ 1,041
3 MASONRY DS 2 LOT 38,000 $ 5,650
4 MASONRY DESC 1 LOT 42,000 $ 3,123
5 BLACKSMITHING 2 LOT 23,000 $ 3,420
6 COBBLESTONE 1 LOT 16,000 $ 1,890
TOTAL: $16,016
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011 25
Matching Grant
• Club Rotario Jaltemba BayClub Rotario Jaltemba Bay $ 4,994$ 4,994
● Guayabitos Hotel Association Guayabitos Hotel Association
● Municipality of CompostelaMunicipality of Compostela
● Festival of Brotherhood ClubFestival of Brotherhood Club $ 2,250$ 2,250
● District 5130District 5130 $ 2,575$ 2,575
● The Rotary FoundationThe Rotary Foundation $ 6,197$ 6,197
TotalTotal $16,016$16,016** U.S. Dollars U.S. Dollars
11/06/11 GUAYABITOS STORM DRAIN REHABILITATION 2011 26
MAIN PROJECT
• The main project will be executed by the State of Nayarit.The main project will be executed by the State of Nayarit.
• With support from the National Water CommissionWith support from the National Water Commission
• Government investment in the main work 1´365,960.18 PMXGovernment investment in the main work 1´365,960.18 PMX
TotalTotal USDUSD $106,218.00$106,218.00
** U.S. Dollars U.S. Dollars