    CHAPTER NO. 24

    ELECTRIC INSTALLATION

    DESCRIPTION OF ITEM:

    Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull

    boxes, inspection boxes, bends, tees, etc., complete with all specials.

    (a) On surface including clamps etc.

    (i) " dia (15 mm i/d).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 7 Metre)

    1 G.I. pipe " dia (15 mm i/d) 7.00 metre 52.82 per mtr. 369.74

    2 Clamp " dia (15 mm i/d) 10.00 Nos. 4.00 each 40.00

    3 G.I bend " dia (15 mm i/d) 1.00 No. 8.00 each 8.004 Gutties 20.00 Nos. 6.00 dozen 10.00

    5 Screw 1" to " (25 to 20 mm) 1.50 Dozen 1.68 dozen 2.52

    6 Inspection box " dia (15 mm) 1.00 No. 2.08 each 2.08

    7 Cement 0.021 Cft. 230.00 P. Bag 4.83

    8 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

    Total 437.45

    Contractor's Profit & Overheads 20 Percent 87.49

    Total 524.94

    Material per metre 479.84 7 = 74.99 74.99

    LABOUR (For 25 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00

    Sundries 10 Percent 33.00

    Total 363.00

    Contractor's Profit & Overheads 20 Percent 72.60

    Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 17.42 Say 17.40Labour rate per Rft Rs. 5.31 Say 5.30

    Composite rate per Metre Rs. 92.42 Say 92.40

    Composite rate per Rft Rs. 28.18 Say 28.20

    Page 1

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    2/271

    DESCRIPTION OF ITEM:

    Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,

    inspection boxes, bends, tees, etc., complete with all specials.

    (a) On surface including clamps etc.

    (ii) " dia (20 mm i/d).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 7 Metre)

    1 G.I. pipe " dia (20 mm i/d) 7.00 metre 68.07 per mtr. 476.49

    2 G.I bend " dia (20 mm i/d) 1.00 No. 14.00 each 14.00

    3 Clamp " dia (20 mm i/d) 10.00 Nos. 6.00 each 60.00

    4 Gutties 20.00 Nos. 6.00 dozen 10.00

    5 Screw 1" to " (25 to 20 mm) 1.50 Dozen 1.68 dozen 2.52

    6 Inspection box " dia (20 mm) 1.00 No. 2.33 each 2.33

    7 Cement 0.021 Cft. 230.00 P. Bag 4.83

    8 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

    Total 570.45

    Contractor's Profit & Overheads 20 Percent 114.09

    Total 684.54

    Material per metre 626.14 7 = 97.79 97.79

    LABOUR (For 25 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00Sundries 10 Percent 33.00

    Total 363.00

    Contractor's Profit & Overheads 20 Percent 72.60

    Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 17.42 Say 17.40

    Labour rate per Rft Rs. 5.31 Say 5.30

    Composite rate per Metre Rs. 115.22 Say 115.20Composite rate per Rft Rs. 35.13 Say 35.15

    Page 2

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    3/271

    DESCRIPTION OF ITEM:

    Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,

    inspection boxes, bends, tees, etc., complete with all specials.

    (a) On surface including clamps etc.

    (iii) 1" dia (25 mm i/d).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 7 Metre)

    1 G.I. pipe 1" dia (25 mm i/d) 7.00 metre 99.90 per mtr. 699.30

    2 G.I bend 1" dia (25 mm i/d) 1.00 No. 18.00 each 18.00

    3 Clamp 1" dia (25 mm i/d) 10.00 Nos. 8.00 each 80.00

    4 Gutties 20.00 Nos. 6.00 dozen 10.00

    5 Screw " to 1" (25 to 20 mm) 1.50 Dozen 1.68 dozen 2.52

    6 Inspection box 1" dia (25 mm) 1.00 No. 2.33 each 2.33

    7 Cement 0.021 Cft. 230.00 P. Bag 4.83

    8 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

    Total 817.26

    Contractor's Profit & Overheads 20 Percent 163.45

    Total 980.71

    Material per metre 897.63 7 = 140.10 140.10

    LABOUR (For 25 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00Sundries 10 Percent 33.00

    Total 363.00

    Contractor's Profit & Overheads 20 Percent 72.60

    Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 17.42 Say 17.40

    Labour rate per Rft Rs. 5.31 Say 5.30

    Composite rate per Metre Rs.

    157.53 Say 157.55Composite rate per Rft Rs. 48.03 Say 48.05

    Page 3

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    4/271

    DESCRIPTION OF ITEM:

    Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,

    inspection boxes, bends, tees, etc., complete with all specials.

    (a) On surface including clamps etc.

    (iv) 1" dia (32 mm i/d).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 7 Metre)

    1 G.I. pipe 1" dia (32 mm i/d) 7.00 metre 125.03 per mtr. 875.21

    2 Clamp 1" dia (32 mm i/d) 10.00 Nos. 10.00 each 100.00

    3 G.I bend 1" dia (32 mm i/d) 1.00 No. 30.00 each 30.00

    4 M.S. Inspection box 1" dia (32 mm) 1.00 No. 2.33 each 2.33

    5 Gutties 20.00 Nos. 6.00 dozen 10.00

    6 Screw " to 1" (25 to 20 mm) 1.50 Dozen 1.68 dozen 2.52

    7 Cement 0.021 Cft. 230.00 P. Bag 4.83

    8 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

    Total 1025.17

    Contractor's Profit & Overheads 20 Percent 205.03

    Total 1230.21

    Material per metre 1126.33 7 175.74 175.74

    LABOUR (For 50 Metre)

    1 Electrician 2.00 Nos. 170.00 per day 340.00

    2 Coolies skilled 3.00 Nos. 160.00 per day 480.00

    Total 820.00Sundries 10 Percent 82.00

    Total 902.00

    Contractor's Profit & Overheads 20 Percent 180.40

    Total 1082.40

    ITEM RATES

    Labour rate per Metre Rs. 21.65 Say 21.65

    Labour rate per Rft Rs. 6.60 Say 6.60

    Composite rate per Metre Rs.

    197.39 Say 197.40Composite rate per Rft Rs. 60.18 Say 60.20

    Page 4

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    5/271

    DESCRIPTION OF ITEM:

    Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,

    inspection boxes, bends, tees, etc., complete with all specials.

    (a) On surface including clamps etc.

    (v) 1" dia (40 mm i/d).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 7 Metre)

    1 G.I. pipe 1" dia (40 mm i/d) 7.00 metre 150.06 per mtr. 1050.42

    2 G.I bend 1" dia (40 mm i/d) 1.00 Nos. 38.00 each 38.00

    3 M.S. Inspection box 1" dia (40 mm) 1.00 No. 2.67 each 2.67

    4 G.I. Clamp 1" dia (40 mm i/d) 10.00 Nos. 10.00 each 100.00

    5 Gutties 20.00 Nos. 6.00 dozen 10.00

    6 Screw 1 to " (25 to 20 mm) 1.50 Dozen 1.68 dozen 2.52

    7 Cement 0.021 Cft. 230.00 P. Bag 4.83

    8 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

    Total 1208.72

    Contractor's Profit & Overheads 20 Percent 241.74

    Total 1450.46

    Material per metre 1330.43 7 207.21 207.21

    LABOUR (For 50 Metre)

    1 Electrician 2.00 No. 170.00 per day 340.00

    2 Coolies skilled 3.00 Nos. 160.00 per day 480.00

    Total 820.00Sundries 10 Percent 82.00

    Total 902.00

    Contractor's Profit & Overheads 20 Percent 180.40

    Total 1082.40

    ITEM RATES

    Labour rate per Metre Rs. 21.65 Say 21.65

    Labour rate per Rft Rs. 6.60 Say 6.60

    Composite rate per Metre Rs.

    228.86 Say 228.85Composite rate per Rft Rs. 69.77 Say 69.75

    Page 5

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    6/271

    DESCRIPTION OF ITEM:

    Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,

    inspection boxes, bends, tees, etc., complete with all specials.

    (a) On surface including clamps etc.

    (vi) 2" dia (50 mm i/d).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 7 Metre)

    1 G.I. pipe 2" dia (50 mm i/d) 7.00 metre 199.27 per mtr. 1394.89

    2 G.I bend 2" dia (50 mm i/d) 1.00 No. 65.00 each 65.00

    3 M.S. Inspection box 2" dia (50 mm) 1.00 No. 2.66 each 2.66

    4 G.I. Clamp 2" dia (50 mm i/d) 10.00 Nos. 12.00 each 120.00

    5 Gutties 20.00 Nos. 6.00 dozen 10.00

    6 Screw 1 to " (25 to 20 mm) 1.50 Dozen 1.68 dozen 2.52

    7 Cement 0.021 Cft. 230.00 P. Bag 4.83

    8 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

    Total 1600.18

    Contractor's Profit & Overheads 20 Percent 320.04

    Total 1920.22

    Material per metre 1758.85 7 274.32 274.32

    LABOUR (For 42 Metre)

    1 Electrician 2.00 No. 170.00 per day 340.00

    2 Coolies skilled 3.00 Nos. 160.00 per day 480.00

    Total 820.00Sundries 10 Percent 82.00

    Total 902.00

    Contractor's Profit & Overheads 20 Percent 180.40

    Total 1082.40

    ITEM RATES

    Labour rate per Metre Rs. 25.77 Say 25.75

    Labour rate per Rft Rs. 7.86 Say 7.85

    Composite rate per Metre Rs.

    300.09 Say 300.10Composite rate per Rft Rs. 91.49 Say 91.50

    Page 6

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    7/271

    DESCRIPTION OF ITEM:

    Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,

    inspection boxes, bends, tees, etc., complete with all specials.

    (a) On surface including clamps etc.

    (vii) 3" dia (80 mm i/d).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 7 Metre)

    1 G.I. pipe 3" dia (80 mm i/d) 7.00 metre 329.65 per mtr. 2307.55

    2 G.I. Clamp 3" dia (80 mm i/d) 10.00 Nos. 18.00 each 180.00

    3 M.S. Inspection box 3" dia (80 mm) 1.00 No. 2.67 each 2.67

    4 G.I bend 3" dia (80 mm i/d) 1.00 No. 175.00 each 175.00

    5 Gutties 20.00 Nos. 6.00 dozen 10.00

    6 Screw 1 to " (25 to 20 mm) 1.50 Dozen 1.68 dozen 2.52

    7 Cement 0.021 Cft. 230.00 P. Bag 4.83

    8 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

    Total 2682.85

    Contractor's Profit & Overheads 20 Percent 536.57

    Total 3219.42

    Material per metre 2949.77 7 459.92 459.92

    LABOUR (For 33 Metre)

    1 Electrician 2.00 No. 170.00 per day 340.00

    2 Coolies skilled 3.00 Nos. 160.00 per day 480.00

    Total 820.00Sundries 10 Percent 82.00

    Total 902.00

    Contractor's Profit & Overheads 20 Percent 180.40

    Total 1082.40

    ITEM RATES

    Labour rate per Metre Rs. 32.80 Say 32.80

    Labour rate per Rft Rs. 10.00 Say 10.00

    Composite rate per Metre Rs.

    492.72 Say 492.70Composite rate per Rft Rs. 150.22 Say 150.20

    Page 7

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    8/271

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    9/271

    DESCRIPTION OF ITEM:

    Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,

    inspection boxes, bends, tees, etc., complete with all specials.

    (b) Recessed in walls, including hooks, cutting, jharries and repairing surface.

    (ii) " dia (20 mm i/d).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 7 Metre)

    1 G.I. Pipe " dia (20 mm i/d) 7.00 metre 68.07 per mtr. 476.49

    2 G.I. Bend " dia (20 mm i/d) 1.00 Nos. 14.00 each 14.00

    3 Hooks 7.00 No. 2.00 each 14.00

    4 M.S. Inspection box " dia (20 mm) 1.00 Nos. 2.33 each 2.33

    5 Cement 0.021 Cft. 230.00 P. Bag 4.83

    6 Sand 0.18 Cft. 350.00 Per % Cft. 0.63

    Total 512.28Contractor's Profit & Overheads 20 Percent 102.46

    Total 614.74

    Material per metre 564.44 7 = 87.82 87.82

    LABOUR (For 25 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Coolies skilled 2.00 Nos. 160.00 per day 320.00

    Total 490.00

    Sundries 10 Percent 49.00

    Total 539.00Contractor's Profit & Overheads 20 Percent 107.80

    Total 646.80

    ITEM RATES

    Labour rate per Metre Rs. 25.87 Say 25.85

    Labour rate per Rft Rs. 7.89 Say 7.90

    Composite rate per Metre Rs.

    113.69 Say 113.70

    Composite rate per Rft Rs. 34.66 Say 34.65

    Page 9

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    10/271

    DESCRIPTION OF ITEM:

    Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,

    inspection boxes, bends, tees, etc., complete with all specials.

    (b) Recessed in walls, including hooks, cutting, jharries and repairing surface.

    (iii) 1" dia (25 mm i/d).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 7 Metre)

    1 G.I. Pipe 1" dia (25 mm i/d) 7.00 metre 99.90 per mtr. 699.30

    2 G.I. Bend 1" dia (25 mm i/d) 1.00 Nos. 18.00 each 18.00

    3 Hooks 8.00 No. 1.67 each 13.36

    4 M.S. Inspection box 1" dia (25 mm) 1.00 Nos. 2.33 each 2.33

    5 Cement 0.052 Cft. 230.00 P. Bag 11.96

    6 Sand 0.18 Cft. 350.00 Per % Cft. 0.63

    Total 745.58

    Contractor's Profit & Overheads 20 Percent 149.12Total 894.70

    Material per metre 820.19 7 = 127.81 127.81

    LABOUR (For 24 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Coolies skilled 2.00 Nos. 160.00 per day 320.00

    Total 490.00

    Sundries 10 Percent 49.00

    Total 539.00

    Contractor's Profit & Overheads 20 Percent 107.80Total 646.80

    ITEM RATES

    Labour rate per Metre Rs. 26.95 Say 26.95

    Labour rate per Rft Rs. 8.22 Say 8.20

    Composite rate per Metre Rs. 154.76 Say 154.75

    Composite rate per Rft Rs. 47.18 Say 47.20

    Page 10

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    11/271

    DESCRIPTION OF ITEM:

    Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,

    inspection boxes, bends, tees, etc., complete with all specials.

    (b) Recessed in walls, including hooks, cutting, jharries and repairing surface.

    (iv) 1" dia (32 mm i/d).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 7 Metre)

    1 G.I. Pipe 1" dia (32 mm i/d) 7.00 metre 125.03 per mtr. 875.21

    2 G.I. Bend 1" dia (32 mm i/d) 1.00 Nos. 30.00 each 30.00

    3 Hooks 8.00 No. 4.00 each 32.00

    4 M.S. Inspection box 1" dia (32 mm) 1.00 Nos. 2.33 each 2.33

    5 Cement 0.063 Cft. 230.00 P. Bag 14.49

    6 Sand 0.18 Cft. 350.00 Per % Cft. 0.63

    Total 954.66

    Contractor's Profit & Overheads 20 Percent 190.93Total 1145.59

    Material per metre 1046.69 7 163.66 163.66

    LABOUR (For 24 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Coolies skilled 2.00 Nos. 160.00 per day 320.00

    Total 490.00

    Sundries 10 Percent 49.00

    Total 539.00

    Contractor's Profit & Overheads 20 Percent 107.80Total 646.80

    ITEM RATES

    Labour rate per Metre Rs. 26.95 Say 26.95

    Labour rate per Rft Rs. 8.22 Say 8.20

    Composite rate per Metre Rs. 190.61 Say 190.60

    Composite rate per Rft Rs. 58.11 Say 58.10

    Page 11

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    12/271

    DESCRIPTION OF ITEM:

    Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,

    inspection boxes, bends, tees, etc., complete with all specials.

    (b) Recessed in walls, including hooks, cutting, jharries and repairing surface.

    (v) 1" dia (40 mm i/d).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 7 Metre)

    1 G.I. Pipe 1" dia (40 mm i/d) 7.00 metre 150.06 per mtr. 1050.42

    2 G.I. Bend 1" dia (40 mm i/d) 1.00 Nos. 38.00 each 38.00

    3 M.S. Inspection box 1" dia (40 mm i/d) 1.00 No. 2.67 each 2.67

    4 Hooks 8.00 Nos. 4.00 each 32.00

    5 Cement 0.074 Cft. 230.00 P. Bag 17.02

    6 Sand 0.20 Cft. 350.00 Per % Cft. 0.70

    Total 1140.81Contractor's Profit & Overheads 20 Percent 228.16

    Total 1368.97

    Material per metre 1252.99 7 195.57 195.57

    LABOUR (For 22 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Coolies skilled 2.00 Nos. 160.00 per day 320.00

    Total 490.00

    Sundries 10 Percent 49.00

    Total 539.00Contractor's Profit & Overheads 20 Percent 107.80

    Total 646.80

    ITEM RATES

    Labour rate per Metre Rs. 29.40 Say 29.40

    Labour rate per Rft Rs. 8.96 Say 8.95

    Composite rate per Metre Rs. 224.97 Say 224.95

    Composite rate per Rft Rs.

    68.59 Say 68.60

    Page 12

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    13/271

    DESCRIPTION OF ITEM:

    Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,

    inspection boxes, bends, tees, etc., complete with all specials.

    (b) Recessed in walls, including hooks, cutting, jharries and repairing surface.

    (vi) 2" dia (50 mm i/d).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 7 Metre)

    1 G.I. Pipe 2" dia (50 mm i/d) 7.00 metre 199.27 per mtr. 1394.89

    2 G.I. Bend 2" dia (50 mm i/d) 1.00 Nos. 65.00 each 65.00

    3 M.S. Inspection box 2" dia (50 mm i/d) 1.00 No. 2.66 each 2.66

    4 Hooks 8.00 Nos. 6.00 each 48.00

    5 Cement 0.084 Cft. 230.00 P. Bag 19.32

    6 Sand 0.24 Cft. 350.00 Per % Cft. 0.84

    Total 1530.71Contractor's Profit & Overheads 20 Percent 306.14

    Total 1836.85

    Material per metre 1679.21 7 262.41 262.41

    LABOUR (For 16 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Coolies skilled 2.00 Nos. 160.00 per day 320.00

    Total 490.00

    Sundries 10 Percent 49.00

    Total 539.00Contractor's Profit & Overheads 20 Percent 107.80

    Total 646.80

    ITEM RATES

    Labour rate per Metre Rs. 40.43 Say 40.45

    Labour rate per Rft Rs. 12.32 Say 12.35

    Composite rate per Metre Rs. 302.83 Say 302.85

    Composite rate per Rft Rs.

    92.33 Say 92.35

    Page 13

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    14/271

    DESCRIPTION OF ITEM:

    Item No. 1 Supply and erection of G.I pipes for wiring purposes including pull boxes,

    inspection boxes, bends, tees, etc., complete with all specials.

    (b) Recessed in walls, including hooks, cutting, jharries and repairing surface.

    (vii) 3" dia (80 mm i/d).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 7 Metre)

    1 G.I. Pipe 3" dia (80 mm i/d) 7.00 metre 329.65 per mtr. 2307.55

    2 G.I. Bend 3" dia (80 mm i/d) 1.00 No. 175.00 each 175.00

    3 M.S. Inspection box 3" dia (80 mm) 1.00 No. 2.67 each 2.67

    4 Hooks 8.00 Nos. 8.00 each 64.00

    5 G.I. Socket 3" dia (80 mm) 1.00 No. 45.00 each 45.00

    6 Cement 0.08 Cft. 230.00 P. Bag 19.32

    7 Sand 0.24 Cft. 350.00 Per % Cft. 0.84

    Total 2614.38

    Contractor's Profit & Overheads 20 Percent 522.88

    Total 3137.25

    Material per metre 2871.23 7 448.18 448.18

    LABOUR (For 10 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Coolies skilled 2.00 Nos. 160.00 per day 320.00

    Total 490.00

    Sundries 10 Percent 49.00Total 539.00

    Contractor's Profit & Overheads 20 Percent 107.80

    Total 646.80

    ITEM RATES

    Labour rate per Metre Rs. 64.68 Say 64.70

    Labour rate per Rft Rs. 19.72 Say 19.70

    Composite rate per Metre Rs. 512.86 Say 512.85

    Composite rate per Rft Rs. 156.36 Say 156.35

    Page 14

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    15/271

    DESCRIPTION OF ITEM:

    Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection

    boxes, pull boxes, bends, tees, etc., complete with all specials.

    (a) On surface, including clamps.

    (i) " dia (16 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 7 Metre)

    1 M.S. Conduit pipe " dia (16 mm) 7.00 metre 27.39 per mtr. 191.73

    2 M.S. Bend " dia (16 mm) 1.00 No. 7.00 each 7.00

    3 M.S. Inspection box " dia (16 mm) 1.00 No. 24.96 dozen 2.08

    4 Clamps " dia (16 mm) 10.00 Nos. 2.00 each 20.00

    5 Screw 1.20 Dozen 1.68 dozen 2.02

    6 Gutties 1.00 Dozen 6.00 dozen 6.00

    Total 228.83Contractor's Profit & Overheads 20 Percent 45.77

    Total 274.59

    Material per metre 251.69 7 = 39.23 39.23

    LABOUR (For 36 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00

    Sundries 10 Percent 33.00

    Total 363.00Contractor's Profit & Overheads 20 Percent 72.60

    Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 12.10 Say 12.10

    Labour rate per Rft Rs. 3.69 Say 3.70

    Composite rate per Metre Rs. 51.33 Say 51.35

    Composite rate per Rft Rs. 15.65 Say 15.65

    Page 15

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    16/271

    DESCRIPTION OF ITEM:

    Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection

    boxes, pull boxes, bends, tees, etc., complete with all specials.

    (a) On surface, including clamps.

    (ii) " dia (20 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 7 Metre)

    1 M.S. Conduit pipe " dia (20 mm) 7.00 metre 34.28 per mtr. 239.96

    2 M.S. Bend " dia (20 mm) 1.00 No. 12.00 each 12.00

    3 M.S. Inspection box " dia (20 mm) 1.00 No. 27.96 per doz. 2.33

    4 M.S. Clamps " dia (20 mm) 10.00 Nos. 3.00 each 30.00

    5 Screw 1.20 Dozen 1.68 dozen 2.02

    6 Gutties 1.00 Dozen 6.00 dozen 6.00

    7 Cement 0.02 Cft. 230.00 P. Bag 4.83

    8 Sand 0.06 Cft. 350.00 Per % Cft. 0.21

    Total 297.35

    Contractor's Profit & Overheads 20 Percent 59.47

    Total 356.82

    Material per metre 325.92 7 = 50.97 50.97

    LABOUR (For 36 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00Sundries 10 Percent 33.00

    Total 363.00

    Contractor's Profit & Overheads 20 Percent 72.60

    Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 12.10 Say 12.10

    Labour rate per Rft Rs. 3.69 Say 3.70

    Composite rate per Metre Rs. 63.07 Say 63.05Composite rate per Rft Rs. 19.23 Say 19.25

    Page 16

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    17/271

    DESCRIPTION OF ITEM:

    Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection

    boxes, pull boxes, bends, tees, etc., complete with all specials.

    (a) On surface, including clamps.

    (iii) 1" dia (25 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 7 Metre)

    1 M.S. Conduit pipe 1" dia (25 mm) 7.00 metre 43.20 per mtr. 302.40

    2 M.S. Bend 1" dia (25 mm) 1.00 No. 16.00 each 16.00

    3 M.S. Inspection box 1" dia (25 mm) 1.00 No. 27.96 per doz. 2.33

    4 M.S. Clamps 1" dia (25 mm) 10.00 Nos. 6.00 each 60.00

    5 Screw 1.20 Dozen 1.68 dozen 2.02

    6 Gutties 1.00 Dozen 6.00 dozen 6.00

    7 Cement 0.042 Cft. 230.00 P. Bag 9.66

    8 Sand 0.12 Cft. 350.00 Per % Cft. 0.42

    Total 398.83

    Contractor's Profit & Overheads 20 Percent 79.77

    Total 478.59

    Material per metre 334.40 7 = 68.37 68.37

    LABOUR (For 36 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00Sundries 10 Percent 33.00

    Total 363.00

    Contractor's Profit & Overheads 20 Percent 72.60

    Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 12.10 Say 12.10

    Labour rate per Rft Rs. 3.69 Say 3.70

    Composite rate per Metre Rs. 80.47 Say 80.45Composite rate per Rft Rs. 24.53 Say 24.55

    Page 17

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    18/271

    DESCRIPTION OF ITEM:

    Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection

    boxes, pull boxes, bends, tees, etc., complete with all specials.

    (a) On surface, including clamps.

    (iv) 1" dia (32 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 7 Metre)

    1 M.S. Conduit pipe 1" dia (32 mm) 7.00 metre 56.39 per mtr. 394.73

    2 M.S. Conduit Bend 1" dia (32 mm) 1.00 No. 27.50 each 27.50

    3 M.S. Inspection box 1" dia (32 mm) 1.00 No. 28.00 per doz. 2.33

    4 M.S. Clamps 1" dia (32 mm) 10.00 Nos. 8.00 each 80.00

    5 Screw 1.20 Dozen 1.68 dozen 2.02

    6 Gutties 1.00 Dozen 6.00 dozen 6.00

    7 Cement 0.042 Cft. 230.00 P. Bag 9.66

    8 Sand 0.12 Cft. 350.00 Per % Cft. 0.42

    Total 522.66

    Contractor's Profit & Overheads 20 Percent 104.53

    Total 627.19

    Material per metre 572.62 7 = 89.60 89.60

    LABOUR (For 36 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00Sundries 10 Percent 33.00

    Total 363.00

    Contractor's Profit & Overheads 20 Percent 72.60

    Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 12.10 Say 12.10

    Labour rate per Rft Rs. 3.69 Say 3.70

    Composite rate per Metre Rs. 101.70 Say 101.70Composite rate per Rft Rs. 31.01 Say 31.00

    Page 18

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    19/271

    DESCRIPTION OF ITEM:

    Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection

    boxes, pull boxes, bends, tees, etc., complete with all specials.

    (a) On surface, including clamps.

    (v) 1" dia (40 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 7 Metre)

    1 M.S. Conduit pipe 1" dia (40 mm) 7.00 metre 65.25 per mtr. 456.75

    2 M.S. Bend 1" dia (40 mm) 1.00 No. 38.00 each 38.00

    3 M.S. Inspection box 1" dia (40 mm) 1.00 No. 32.00 per doz. 2.67

    4 M.S. Clamps 1" dia (40 mm) 10.00 Nos. 8.00 each 80.00

    5 Screw 1.20 Dozen 1.68 dozen 2.02

    6 Gutties 1.00 Dozen 6.00 dozen 6.00

    7 Cement 0.042 Cft. 230.00 P. Bag 9.66

    8 Sand 0.12 Cft. 350.00 Per % Cft. 0.42

    Total 595.51

    Contractor's Profit & Overheads 20 Percent 119.10

    Total 714.62

    Material per metre 652.76 7 = 102.09 102.09

    LABOUR (For 32 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00Sundries 10 Percent 33.00

    Total 363.00

    Contractor's Profit & Overheads 20 Percent 72.60

    Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 13.61 Say 13.60

    Labour rate per Rft Rs. 4.15 Say 4.15

    Composite rate per Metre Rs. 115.70 Say 115.70Composite rate per Rft Rs. 35.27 Say 35.30

    Page 19

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    20/271

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    21/271

    DESCRIPTION OF ITEM:

    Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection

    boxes, pull boxes, bends, tees, etc., complete with all specials.

    (b) Recessed in walls including cutting, jharries, cost of hooks and repairing

    surface etc.

    (i) " dia (16 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 7 Metre)

    1 M.S. Conduit pipe " dia (16 mm) 7.00 metre 27.39 per mtr. 191.73

    2 M.S. Bend " dia (16 mm) 1.00 No. 7.00 each 7.00

    3 M.S. Inspection box " dia (16 mm) 1.00 No. 24.96 per doz. 2.08

    4 M.S. Hooks 10.00 Nos. 2.00 each 20.00

    5 Cement 0.021 Cft. 230.00 P. Bag 4.83

    6 Sand 0.08 Cft. 350.00 Per % Cft. 0.28

    Total 225.92

    Contractor's Profit & Overheads 20 Percent 45.18

    Total 271.10

    Material per metre 247.29 7 = 38.73 38.73

    LABOUR (For 28 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

    Total 490.00

    Sundries 10 Percent 49.00Total 539.00

    Contractor's Profit & Overheads 20 Percent 107.80

    Total 646.80

    ITEM RATES

    Labour rate per Metre Rs. 23.10 Say 23.10

    Labour rate per Rft Rs. 7.04 Say 7.05

    Composite rate per Metre Rs.

    61.83 Say 61.85

    Composite rate per Rft Rs. 18.85 Say 18.85

    Page 21

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    22/271

    DESCRIPTION OF ITEM:

    Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection

    boxes, pull boxes, bends, tees, etc., complete with all specials.

    (b) Recessed in walls including cutting, jharries, cost of hooks and repairing

    surface etc.

    (ii) " dia (20 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 7 Metre)

    1 M.S. Condict pipe " dia (20 mm) 7.00 metre 34.28 per mtr. 239.96

    2 M.S. Bend " dia (20 mm) 1.00 No. 12.00 each 12.00

    3 M.S. Inspection box " dia (20 mm) 1.00 No. 27.96 per doz. 2.33

    4 M.S. Hooks 10.00 Nos. 2.00 each 20.00

    5 Cement 0.042 Cft. 230.00 P. Bag 9.66

    6 Sand 0.12 Cft. 350.00 Per % Cft. 0.42

    Total 284.37

    Contractor's Profit & Overheads 20 Percent 56.87

    Total 341.24

    Material per metre 310.12 7 = 48.75 48.75

    LABOUR (For 28 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

    Total 490.00

    Sundries 10 Percent 49.00Total 539.00

    Contractor's Profit & Overheads 20 Percent 107.80

    Total 646.80

    ITEM RATES

    Labour rate per Metre Rs. 23.10 Say 23.10

    Labour rate per Rft Rs. 7.04 Say 7.05

    Composite rate per Metre Rs. 71.85 Say 71.85

    Composite rate per Rft Rs. 21.91 Say 21.90

    Page 22

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    23/271

    DESCRIPTION OF ITEM:

    Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection

    boxes, pull boxes, bends, tees, etc., complete with all specials.

    (b) Recessed in walls including cutting, jharries, cost of hooks and repairing

    surface etc.

    (iii) 1" dia (25 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 7 Metre)

    1 M.S. Conduit pipe 1" dia (25 mm) 7.00 metre 43.20 per mtr. 302.40

    2 M.S. Bend 1" dia (25 mm) 1.00 No. 16.00 each 16.00

    3 M.S. Inspection box 1" dia (25 mm) 1.00 No. 27.96 per doz. 2.33

    4 Hooks 10.00 Nos. 2.00 each 20.00

    5 Cement 0.052 Cft. 230.00 P. Bag 11.96

    6 Sand 0.18 Cft. 350.00 Per % Cft. 0.63

    Total 353.32

    Contractor's Profit & Overheads 20 Percent 70.66

    Total 423.98

    Material per metre 385.81 7 = 60.57 60.57

    LABOUR (For 25 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

    Total 490.00

    Sundries 10 Percent 49.00Total 539.00

    Contractor's Profit & Overheads 20 Percent 107.80

    Total 646.80

    ITEM RATES

    Labour rate per Metre Rs. 25.87 Say 25.85

    Labour rate per Rft Rs. 7.89 Say 7.90

    Composite rate per Metre Rs. 86.42 Say 86.40

    Composite rate per Rft Rs. 26.35 Say 26.35

    Page 23

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    24/271

    DESCRIPTION OF ITEM:

    Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection

    boxes, pull boxes, bends, tees, etc., complete with all specials.

    (b) Recessed in walls including cutting, jharries, cost of hooks and repairing

    surface etc.

    (iv) 1" dia (32 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 7 Metre)

    1 M.S. Conduit pipe 1" dia (32 mm) 7.00 metre 56.39 per mtr. 394.73

    2 M.S. Conduit Bend 1" dia (32 mm) 1.00 No. 27.50 each 27.50

    3 M.S. Inspection box 1" dia (32 mm) 1.00 No. 28.00 per doz. 2.33

    4 M.S. Hooks 10.00 Nos. 4.00 each 40.00

    5 Cement 0.063 Cft. 230.00 P. Bag 14.49

    6 Sand 0.18 Cft. 350.00 Per % Cft. 0.63

    Total 479.68

    Contractor's Profit & Overheads 20 Percent 95.94

    Total 575.62

    Material per metre 524.22 7 = 82.23 82.23

    LABOUR (For 24 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

    Total 490.00

    Sundries 10 Percent 49.00Total 539.00

    Contractor's Profit & Overheads 20 Percent 107.80

    Total 646.80

    ITEM RATES

    Labour rate per Metre Rs. 26.95 Say 26.95

    Labour rate per Rft Rs. 8.22 Say 8.20

    Composite rate per Metre Rs. 109.18 Say 109.20

    Composite rate per Rft Rs. 33.29 Say 33.30

    Page 24

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    25/271

    DESCRIPTION OF ITEM:

    Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection

    boxes, pull boxes, bends, tees, etc., complete with all specials.

    (b) Recessed in walls including cutting, jharries, cost of hooks and repairing

    surface etc.

    (v) 1" dia (40 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 7 Metre)

    1 M.S. Conduit pipe 1" dia (40 mm) 7.00 metre 65.25 per mtr. 456.75

    2 M.S. Conduit Bend 1" dia (40 mm) 1.00 No. 38.00 each 38.00

    3 M.S. Inspection box 1" dia (40 mm) 1.00 No. 32.00 per doz. 2.67

    4 M.S. Hooks 10.00 Nos. 4.00 each 40.00

    5 Cement 0.074 Cft. 230.00 P. Bag 17.02

    6 Sand 0.20 Cft. 350.00 Per % Cft. 0.70

    Total 555.14

    Contractor's Profit & Overheads 20 Percent 111.03

    Total 666.16

    Material per metre 606.56 7 = 95.17 95.17

    LABOUR (For 23 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

    Total 490.00

    Sundries 10 Percent 49.00Total 539.00

    Contractor's Profit & Overheads 20 Percent 107.80

    Total 646.80

    ITEM RATES

    Labour rate per Metre Rs. 28.12 Say 28.10

    Labour rate per Rft Rs. 8.57 Say 8.55

    Composite rate per Metre Rs. 123.29 Say 123.30

    Composite rate per Rft Rs. 37.59 Say 37.60

    Page 25

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    26/271

    DESCRIPTION OF ITEM:

    Item No. 2 Supply and erection of M.S conduit pipes for wiring, including inspection

    boxes, pull boxes, bends, tees, etc., complete with all specials.

    (b) Recessed in walls including cutting, jharries, cost of hooks and repairing

    surface etc.

    (vi) 2" dia (50 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 7 Metre)

    1 M.S. Conduit pipe 2" dia (50 mm) 7.00 metre 81.00 per mtr. 567.00

    2 M.S. Conduit Bend 2" dia (50 mm) 1.00 No. 62.00 each 62.00

    3 M.S. Inspection box 2" dia (50 mm) 1.00 No. 32.00 per doz. 2.67

    4 Hooks 10.00 Nos. 6.00 each 60.00

    5 Cement 0.084 Cft. 230.00 P. Bag 19.32

    6 Sand 0.24 Cft. 350.00 Per % Cft. 0.84

    Total 711.83

    Contractor's Profit & Overheads 20 Percent 142.37

    Total 854.19

    Material per metre 778.43 7 = 122.03 122.03

    LABOUR (For 22 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

    Total 490.00

    Sundries 10 Percent 49.00Total 539.00

    Contractor's Profit & Overheads 20 Percent 107.80

    Total 646.80

    ITEM RATES

    Labour rate per Metre Rs. 29.40 Say 29.40

    Labour rate per Rft Rs. 8.96 Say 8.95

    Composite rate per Metre Rs. 151.43 Say 151.45

    Composite rate per Rft Rs. 46.16 Say 46.15

    Page 26

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    27/271

    DESCRIPTION OF ITEM:

    Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in walls,

    including inspection boxes, pull boxes, hooks, cutting, jharriers and

    repairing surface etc., complete with all specials.

    (i) " dia (12 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 10 Metre)

    1 PVC pipe " dia (12 mm) 10.00 metre 8.25 per mtr. 82.50

    2 PVC Bend " dia (12 mm) 2.00 No. 1.50 each 3.00

    3 M.S. Hook 10.00 No. 2.00 each 20.00

    4 PVC Inspection box " (12 mm) 2.00 Nos. 25.00 per doz. 4.17

    5 Cement 0.042 Cft. 230.00 P. Bag 9.66

    6 Sand 0.12 Cft. 350.00 Per % Cft. 0.42

    Total 119.75

    Contractor's Profit & Overheads 20 Percent 23.95Total 143.70

    Material per metre 129.43 10 = 14.37 14.37

    LABOUR (For 31 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

    Total 490.00

    Sundries 10 Percent 49.00

    Total 539.00

    Contractor's Profit & Overheads 20 Percent 107.80Total 646.80

    ITEM RATES

    Labour rate per Metre Rs. 20.86 Say 20.85

    Labour rate per Rft Rs. 6.36 Say 6.35

    Composite rate per Metre Rs. 35.23 Say 35.25

    Composite rate per Rft Rs. 10.74 Say 10.75

    Page 27

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    28/271

    DESCRIPTION OF ITEM:

    Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in walls,

    including inspection boxes, pull boxes, hooks, cutting, jharriers and

    repairing surface etc., complete with all specials.

    (ii) " dia (20 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 10 Metre)

    1 PVC pipe " dia (20 mm) 10.00 metre 10.85 per mtr. 108.50

    2 PVC Bend " dia (20 mm) 2.00 No. 3.00 each 6.00

    3 M.S. Hook 10.00 No. 2.00 each 20.00

    4 PVC Inspection box " dia (20 mm) 2.00 Nos. 25.00 per doz. 4.17

    5 Cement 0.052 Cft. 230.00 P. Bag 11.96

    6 Sand 0.18 Cft. 350.00 Per % Cft. 0.63

    Total 151.26

    Contractor's Profit & Overheads 20 Percent 30.25Total 181.51

    Material per metre 163.53 10 = 18.15 18.15

    LABOUR (For 30 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

    Total 490.00

    Sundries 10 Percent 49.00

    Total 539.00

    Contractor's Profit & Overheads 20 Percent 107.80Total 646.80

    ITEM RATES

    Labour rate per Metre Rs. 21.56 Say 21.55

    Labour rate per Rft Rs. 6.57 Say 6.55

    Composite rate per Metre Rs. 39.71 Say 39.70

    Composite rate per Rft Rs. 12.10 Say 12.10

    Page 28

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    29/271

    DESCRIPTION OF ITEM:

    Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in walls,

    including inspection boxes, pull boxes, hooks, cutting, jharriers and

    repairing surface etc., complete with all specials.

    (iii) 1" dia (25 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 10 Metre)

    1 PVC pipe 1" dia (25 mm) 10.00 metre 14.90 per mtr. 149.00

    2 PVC Bend 1" dia (25 mm) 2.00 No. 4.00 each 8.00

    3 M.S. Hook 10.00 No. 4.00 each 40.00

    4 PVC Inspection box 1" dia (25 mm) 2.00 Nos. 28.00 per doz. 4.67

    5 Cement 0.063 Cft. 230.00 P. Bag 14.49

    6 Sand 0.18 Cft. 350.00 Per % Cft. 0.63

    Total 216.79

    Contractor's Profit & Overheads 20 Percent 43.36Total 260.14

    Material per metre 235.03 10 = 26.01 26.01

    LABOUR (For 27 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

    Total 490.00

    Sundries 10 Percent 49.00

    Total 539.00

    Contractor's Profit & Overheads 20 Percent 107.80Total 646.80

    ITEM RATES

    Labour rate per Metre Rs. 23.96 Say 23.95

    Labour rate per Rft Rs. 7.30 Say 7.30

    Composite rate per Metre Rs. 49.97 Say 49.95

    Composite rate per Rft Rs. 15.23 Say 15.25

    Page 29

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    30/271

    DESCRIPTION OF ITEM:

    Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in walls,

    including inspection boxes, pull boxes, hooks, cutting, jharriers and

    repairing surface etc., complete with all specials.

    (iv) 1" dia (30 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 10 Metre)

    1 PVC pipe 1" dia (30 mm) 10.00 metre 22.90 per mtr. 229.00

    2 PVC Bend 1" dia (30 mm) 2.00 No. 6.00 each 12.00

    3 M.S. Hook 10.00 No. 4.00 each 40.00

    4 PVC Inspection box 1" dia (30 mm) 2.00 Nos. 28.00 per doz. 4.67

    5 Cement 0.065 Cft. 230.00 P. Bag 14.95

    6 Sand 0.37 Cft. 350.00 Per % Cft. 1.30

    Total 301.91

    Contractor's Profit & Overheads 20 Percent 60.38Total 362.29

    Material per metre 228.053 10 36.23 36.23

    LABOUR (For 25 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

    Total 490.00

    Sundries 10 Percent 49.00

    Total 539.00

    Contractor's Profit & Overheads 20 Percent 107.80Total 646.80

    ITEM RATES

    Labour rate per Metre Rs. 25.87 Say 25.85

    Labour rate per Rft Rs. 7.89 Say 7.90

    Composite rate per Metre Rs. 62.10 Say 62.10

    Composite rate per Rft Rs. 18.93 Say 18.95

    Page 30

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    31/271

    DESCRIPTION OF ITEM:

    Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in walls,

    including inspection boxes, pull boxes, hooks, cutting, jharriers and

    repairing surface etc., complete with all specials.

    (v) 1" dia (40 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 10 Metre)

    1 PVC pipe 1" dia (40 mm) 10.00 metre 33.60 per mtr. 336.00

    2 PVC Bend 1" dia (40 mm) 2.00 No. 9.00 each 18.00

    3 M.S. Hook 10.00 No. 4.00 each 40.00

    4 PVC Inspection box 1" dia (40 mm) 2.00 Nos. 32.00 per doz. 5.33

    5 Cement 0.070 Cft. 230.00 P. Bag 16.10

    6 Sand 0.40 Cft. 350.00 Per % Cft. 1.40

    Total 416.83

    Contractor's Profit & Overheads 20 Percent 83.37Total 500.20

    Material per metre 454.67 10 = 50.02 50.02

    LABOUR (For 24 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

    Total 490.00

    Sundries 10 Percent 49.00

    Total 539.00

    Contractor's Profit & Overheads 20 Percent 107.80Total 646.80

    ITEM RATES

    Labour rate per Metre Rs. 26.95 Say 26.95

    Labour rate per Rft Rs. 8.22 Say 8.20

    Composite rate per Metre Rs. 76.97 Say 76.95

    Composite rate per Rft Rs. 23.47 Say 23.45

    Page 31

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    32/271

    DESCRIPTION OF ITEM:

    Item No. 3 Supply and erection of P.V.C pipe for wiring purposes recessed in walls,

    including inspection boxes, pull boxes, hooks, cutting, jharriers and

    repairing surface etc., complete with all specials.

    (vi) 2" dia (50 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 10 Metre)

    1 PVC pipe 2" dia (50 mm) 10.00 metre 48.25 per mtr. 482.50

    2 PVC Bend 2" dia (50 mm) 2.00 No. 15.00 each 30.00

    3 M.S. Hook 10.00 No. 4.00 each 40.00

    4 Cement 0.084 Cft. 230.00 P. Bag 19.32

    5 Sand 0.24 Cft. 350.00 Per % Cft. 0.84

    Total 572.66

    Contractor's Profit & Overheads 20 Percent 114.53

    Total 687.19Material per metre 625.35 10 = 68.72 68.72

    LABOUR (For 23 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

    Total 490.00

    Sundries 10 Percent 49.00

    Total 539.00

    Contractor's Profit & Overheads 20 Percent 107.80

    Total 646.80

    ITEM RATES

    Labour rate per Metre Rs. 28.12 Say 28.10

    Labour rate per Rft Rs. 8.57 Say 8.55

    Composite rate per Metre Rs. 96.85 Say 96.85

    Composite rate per Rft Rs. 29.53 Say 29.55

    Page 32

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    33/271

    DESCRIPTION OF ITEM:

    Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including clamps

    inspection boxes, pull boxes bends, tees repairing surface etc., complete

    with all specials.

    (i) " dia (12 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 10 Metre)

    1 PVC pipe " dia (12 mm) 10.00 metre 8.25 per mtr. 82.50

    2 PVC Bend " dia (12 mm) 2.00 Nos. 1.50 each 3.00

    3 M.S. Clamp/saddle 20.00 Nos. 2.00 each 40.00

    4 Gutties 20.00 Nos. 0.50 each 10.00

    5 Screws for " dia clamp 20.00 Nos. 10.00 per doz. 16.67

    6 PVC Inspection Box " dia (12 mm) 2.00 Nos. 25.00 per doz. 4.17

    7 Cement 0.021 Cft. 230.00 P. Bag 4.83

    8 Sand 0.06 Cft. 350.00 Per % Cft. 0.21

    Total 161.37

    Contractor's Profit & Overheads 20 Percent 32.27

    Total 193.65

    Material per metre 176.37 10 = 19.36 19.36

    LABOUR (For 80 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00

    Sundries 10 Percent 33.00Total 363.00

    Contractor's Profit & Overheads 20 Percent 72.60

    Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 5.45 Say 5.45

    Labour rate per Rft Rs. 1.66 Say 1.65

    Composite rate per Metre Rs. 24.81 Say 24.80

    Composite rate per Rft Rs. 7.57 Say 7.55

    Page 33

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    34/271

    DESCRIPTION OF ITEM:

    Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including clamps

    inspection boxes, pull boxes bends, tees repairing surface etc., complete

    with all specials.

    (ii) " dia (20 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 10 Metre)

    1 PVC pipe " dia (20 mm) 10.00 metre 10.85 per mtr. 108.50

    2 PVC Bend " dia (20 mm) 2.00 Nos. 3.00 each 6.00

    3 M.S. Clamp " dia (20 mm) 10.00 Nos. 3.00 each 30.00

    4 Screws for " dia clamp 20.00 Nos. 10.00 per doz. 16.67

    5 PVC Inspection Box " dia (20 mm) 2.00 Nos. 25.00 per doz. 4.17

    6 Cement 0.021 Cft. 230.00 P. Bag 4.83

    7 Sand 0.06 Cft. 350.00 Per % Cft. 0.21

    Total 170.37Contractor's Profit & Overheads 20 Percent 34.07

    Total 204.45

    Material per metre 186.27 10 = 20.44 20.44

    LABOUR (For 80 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00

    Sundries 10 Percent 33.00

    Total 363.00Contractor's Profit & Overheads 20 Percent 72.60

    Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 5.45 Say 5.45

    Labour rate per Rft Rs. 1.66 Say 1.65

    Composite rate per Metre Rs. 25.89 Say 25.90

    Composite rate per Rft Rs. 7.89 Say 7.90

    Page 34

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    35/271

    DESCRIPTION OF ITEM:

    Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including clamps

    inspection boxes, pull boxes bends, tees repairing surface etc., complete

    with all specials.

    (iii) 1" dia (25 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 10 Metre)

    1 PVC pipe 1" dia (25 mm) 10.00 metre 14.90 per mtr. 149.00

    2 PVC Bend 1" dia (25 mm) 2.00 Nos. 4.00 each 8.00

    3 M.S. Clamp/saddle 1 dia (25 mm) 20.00 Nos. 6.00 each 120.00

    4 Screws for 1" dia clamp 20.00 Nos. 12.00 per doz. 20.00

    5 Gutties 20.00 Nos. 6.00 per doz. 10.00

    6 PVC Inspection Box 1" dia (25 mm) 2.00 Nos. 28.00 per doz. 4.67

    7 Cement 0.021 Cft. 230.00 P. Bag 4.83

    8 Sand 0.06 Cft. 350.00 Per % Cft. 0.21

    Total 316.71

    Contractor's Profit & Overheads 20 Percent 63.34

    Total 380.05

    Material per metre 347.23 10 = 38.00 38.00

    LABOUR (For 80 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00

    Sundries 10 Percent 33.00Total 363.00

    Contractor's Profit & Overheads 20 Percent 72.60

    Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 5.45 Say 5.45

    Labour rate per Rft Rs. 1.66 Say 1.65

    Composite rate per Metre Rs. 43.45 Say 43.45

    Composite rate per Rft Rs. 13.25 Say 13.25

    Page 35

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    36/271

    DESCRIPTION OF ITEM:

    Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including clamps

    inspection boxes, pull boxes bends, tees repairing surface etc., complete

    with all specials.

    (iv) 1" dia (30 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 10 Metre)

    1 PVC pipe 1" dia (30 mm) 10.00 metre 22.90 per mtr. 229.00

    2 PVC Bend 1" dia (30 mm) 2.00 Nos. 6.00 each 12.00

    3 M.S. Clamp/saddle 1" dia (30 mm) 20.00 Nos. 8.00 each 160.00

    4 Gutties 20.00 Nos. 6.00 per doz. 10.00

    5 Screws for 1" dia clamp 20.00 Nos. 15.00 per doz. 25.00

    6 PVC Inspection Box 1" dia (30 mm) 2.00 Nos. 28.00 per doz. 4.67

    Total 440.67

    Contractor's Profit & Overheads 20 Percent 88.13Total 528.80

    Material per metre 484.73 10 = 52.88 52.88

    LABOUR (For 70 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00

    Sundries 10 Percent 33.00

    Total 363.00

    Contractor's Profit & Overheads 20 Percent 72.60Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 6.22 Say 6.20

    Labour rate per Rft Rs. 1.90 Say 1.90

    Composite rate per Metre Rs. 59.10 Say 59.10

    Composite rate per Rft Rs. 18.02 Say 18.00

    Page 36

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    37/271

    DESCRIPTION OF ITEM:

    Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including clamps

    inspection boxes, pull boxes bends, tees repairing surface etc., complete

    with all specials.

    (v) 1" dia (40 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 10 Metre)

    1 PVC pipe 1" dia (40 mm) 10.00 metre 33.60 per mtr. 336.00

    2 PVC Bend 1" dia (40 mm) 2.00 Nos. 9.00 each 18.00

    3 M.S. Clamp/saddle 1" dia (40 mm) 20.00 Nos. 8.00 each 160.00

    4 Gutties 20.00 Nos. 6.00 per doz. 10.00

    5 Screws for 1" dia clamp 20.00 Nos. 18.00 per doz. 30.00

    6 PVC Inspection Box 1" dia (40 mm) 2.00 Nos. 32.00 per doz. 5.33

    7 Cement 0.021 Cft. 230.00 P. Bag 4.83

    8 Sand 0.06 Cft. 350.00 Per % Cft. 0.21

    Total 564.37

    Contractor's Profit & Overheads 20 Percent 112.87

    Total 677.24

    Material per metre 619.67 10 = 67.72 67.72

    LABOUR (For 70 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00

    Sundries 10 Percent 33.00Total 363.00

    Contractor's Profit & Overheads 20 Percent 72.60

    Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 6.22 Say 6.20

    Labour rate per Rft Rs. 1.90 Say 1.90

    Composite rate per Metre Rs. 73.95 Say 73.95

    Composite rate per Rft Rs. 22.55 Say 22.55

    Page 37

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    38/271

    DESCRIPTION OF ITEM:

    Item No. 4 Supply and erection of P.V.C pipe for wiring on surface including clamps

    inspection boxes, pull boxes bends, tees repairing surface etc., complete

    with all specials.

    (vi) 2" dia (50 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 10 Metre)

    1 PVC pipe 2" dia (50 mm) 10.00 metre 48.25 per mtr. 482.50

    2 PVC Bend 2" dia (50 mm) 2.00 Nos. 15.00 each 30.00

    3 M.S. Clamp/saddle 2" dia (50 mm) 20.00 Nos. 10.00 each 200.00

    4 Gutties 20.00 Nos. 6.00 per doz. 10.00

    5 Screws for 2" dia clamp 20.00 Nos. 30.00 per doz. 50.00

    6 PVC Inspection Box 2" dia (50 mm) 2.00 Nos. 32.00 per doz. 5.33

    7 Cement 0.021 Cft. 230.00 P. Bag 4.83

    8 Sand 0.06 Cft. 350.00 Per % Cft. 0.21

    Total 782.66

    Contractor's Profit & Overheads 20 Percent 156.53

    Total 939.20

    Material per metre 860.02 10 = 93.92 93.92

    LABOUR (For 58 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00

    Sundries 10 Percent 33.00Total 363.00

    Contractor's Profit & Overheads 20 Percent 72.60

    Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 7.51 Say 7.50

    Labour rate per Rft Rs. 2.29 Say 2.30

    Composite rate per Metre Rs. 101.43 Say 101.45

    Composite rate per Rft Rs. 30.92 Say 30.90

    Page 38

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    39/271

    DESCRIPTION OF ITEM:

    Item No. 5 Supply and erection of G.I Flexible pipe for wiring including welding of

    sockets, nipples and check nuts etc complete.

    (i) " dia (12 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL

    1 G.I. Flexible Pipe " dia (12 mm) 1.00 metre 14.40 per mtr. 14.40

    2 Socket " dia (12 mm) 2.00 Nos. 3.50 each 7.00

    3 Nipple " dia (12 mm) 2.00 Nos. 3.50 each 7.00

    4 Check Nuts " dia (12 mm) 2.00 Nos. 5.00 each 10.00

    5 Soldering etc. L.S 8.00

    Total 46.40

    Contractor's Profit & Overheads 20 Percent 9.28

    Total 55.68

    LABOUR (For 32 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    3 Welding charges 2.00 joints 8.00 per joints 16.00

    Total 346.00

    Sundries 10 Percent 34.60

    Total 380.60

    Contractor's Profit & Overheads 20 Percent 76.12

    Total 456.72

    ITEM RATES

    Labour rate per Metre Rs. 14.27 Say 14.25

    Labour rate per Rft Rs. 4.35 Say 4.35

    Composite rate per Metre Rs. 69.95 Say 69.95

    Composite rate per Rft Rs. 21.33 Say 21.35

    Page 39

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    40/271

    DESCRIPTION OF ITEM:

    Item No. 5 Supply and erection of G.I Flexible pipe for wiring including welding of

    sockets, nipples and check nuts etc complete.

    (ii) " dia (20 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL

    1 G.I. Flexible Pipe " dia (20 mm) 1.00 metre 19.68 per mtr. 19.68

    2 G.I. Socket " dia (20 mm) 2.00 Nos. 5.00 each 10.00

    3 G.I. Nipple " dia (20 mm) 2.00 Nos. 6.00 each 12.00

    4 Check Nuts " dia (20 mm) 2.00 Nos. 8.00 each 16.00

    5 Solder joint L.S 8.00

    Total 65.68

    Contractor's Profit & Overheads 20 Percent 13.14

    Total 78.82

    LABOUR (For 30 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    3 Welding charges 2.00 joints 8.00 per joint 16.00

    Total 346.00

    Sundries 10 Percent 34.60

    Total 380.60

    Contractor's Profit & Overheads 20 Percent 76.12

    Total 456.72

    ITEM RATES

    Labour rate per Metre Rs. 15.22 Say 15.20

    Labour rate per Rft Rs. 4.64 Say 4.65

    Composite rate per Metre Rs. 94.04 Say 94.05

    Composite rate per Rft Rs. 28.67 Say 28.65

    Page 40

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    41/271

    DESCRIPTION OF ITEM:

    Item No. 5 Supply and erection of G.I Flexible pipe for wiring including welding of

    sockets, nipples and check nuts etc complete.

    (iii) 1" dia (25 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL

    1 G.I. Flexible Pipe 1" dia (25 mm) 1.00 metre 22.60 per mtr. 22.60

    2 G.I. Socket 1" dia (25 mm) 2.00 Nos. 7.00 each 14.00

    3 G.I. Nipple 1" dia (25 mm) 2.00 Nos. 8.00 each 16.00

    4 Check Nuts 1" dia (25 mm) 2.00 Nos. 12.00 each 24.00

    5 Solder L.S 8.00

    Total 84.60

    Contractor's Profit & Overheads 20 Percent 16.92

    Total 101.52

    LABOUR (For 29 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    3 Welding charges 2.00 joints 8.00 per joints 16.00

    Total 346.00

    Sundries 10 Percent 34.60

    Total 380.60

    Contractor's Profit & Overheads 20 Percent 76.12

    Total 456.72

    ITEM RATES

    Labour rate per Metre Rs. 15.75 Say 15.75

    Labour rate per Rft Rs. 4.80 Say 4.80

    Composite rate per Metre Rs. 117.27 Say 117.25

    Composite rate per Rft Rs. 35.75 Say 35.75

    Page 41

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    42/271

    DESCRIPTION OF ITEM:

    Item No. 5 Supply and erection of G.I Flexible pipe for wiring including welding of

    sockets, nipples and check nuts etc complete.

    (iv) 1" dia (32 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL

    1 G.I. Flexible Pipe 1" dia (32 mm) 1.00 metre 29.52 per mtr. 29.52

    2 G.I. Socket 1" dia (32 mm) 2.00 Nos. 12.00 each 24.00

    3 G.I. Nipple 1" dia (32 mm) 2.00 Nos. 14.00 each 28.00

    4 Check Nuts 1" dia (32 mm) 2.00 Nos. 16.00 each 32.00

    5 Solder L.S 8.00

    Total 121.52

    Contractor's Profit & Overheads 20 Percent 24.30

    Total 145.82

    LABOUR (For 24 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    3 Welding charges 2.00 joints 8.00 per joints 16.00

    Total 346.00

    Sundries 10 Percent 34.60

    Total 380.60

    Contractor's Profit & Overheads 20 Percent 76.12

    Total 456.72

    ITEM RATES

    Labour rate per Metre Rs. 19.03 Say 19.05

    Labour rate per Rft Rs. 5.80 Say 5.80

    Composite rate per Metre Rs. 164.85 Say 164.85

    Composite rate per Rft Rs. 50.26 Say 50.25

    Page 42

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    43/271

    DESCRIPTION OF ITEM:

    Item No. 5 Supply and erection of G.I Flexible pipe for wiring including welding of

    sockets, nipples and check nuts etc complete.

    (v) 1" dia (40 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL

    1 G.I. Flexible Pipe 1" dia (40 mm) 1.00 metre 39.37 per mtr. 39.37

    2 G.I. Socket 1" dia (40 mm) 2.00 Nos. 15.00 each 30.00

    3 G.I. Nipple 1" dia (40 mm) 2.00 Nos. 20.00 each 40.00

    4 Check Nuts 1" dia (40 mm) 2.00 Nos. 20.00 each 40.00

    5 Solder L.S 8.00

    Total 157.37

    Contractor's Profit & Overheads 20 Percent 31.47

    Total 188.84

    LABOUR (For 22 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    3 Welding charges 2.00 joints 8.00 per joints 16.00

    Total 346.00

    Sundries 10 Percent 34.60

    Total 380.60

    Contractor's Profit & Overheads 20 Percent 76.12

    Total 456.72

    ITEM RATES

    Labour rate per Metre Rs. 20.76 Say 20.75

    Labour rate per Rft Rs. 6.33 Say 6.35

    Composite rate per Metre Rs. 209.60 Say 209.60

    Composite rate per Rft Rs. 63.90 Say 63.90

    Page 43

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    44/271

    DESCRIPTION OF ITEM:

    Item No. 5 Supply and erection of G.I Flexible pipe for wiring including welding of

    sockets, nipples and check nuts etc complete.

    (vi) 2" dia (50 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL

    1 G.I. Flexible Pipe 2" dia (50 mm) 1.00 metre 55.77 per mtr. 55.77

    2 G.I. Socket 2" dia (50 mm) 2.00 Nos. 21.00 each 42.00

    3 G.I. Nipple 2" dia (50 mm) 2.00 Nos. 22.00 each 44.00

    4 Check Nuts 2" dia (50 mm) 2.00 Nos. 25.00 each 50.00

    5 Solder L.S 8.00

    Total 199.77

    Contractor's Profit & Overheads 20 Percent 39.95

    Total 239.72

    LABOUR (For 20 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    3 Welding charges 2.00 joints 8.00 per joints 16.00

    Total 346.00

    Sundries 10 Percent 34.60

    Total 380.60

    Contractor's Profit & Overheads 20 Percent 76.12

    Total 456.72

    ITEM RATES

    Labour rate per Metre Rs. 22.84 Say 22.85

    Labour rate per Rft Rs. 6.96 Say 6.95

    Composite rate per Metre Rs. 262.56 Say 262.55

    Composite rate per Rft Rs. 80.05 Say 80.05

    Page 44

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    45/271

    DESCRIPTION OF ITEM:

    Item No. 5 Supply and erection of G.I Flexible pipe for wiring including welding of

    sockets, nipples and check nuts etc complete.

    (vii) 3" dia (80 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL

    1 G.I. Flexible Pipe 3" dia (80 mm) 1.00 metre 110.00 per mtr. 110.00

    2 G.I. Socket 3" dia (80 mm) 2.00 Nos. 45.00 each 90.00

    3 G.I. Nipple 3" dia (80 mm) 2.00 Nos. 25.00 each 50.00

    4 Check Nuts 3" dia (80 mm) 2.00 Nos. 20.00 each 40.00

    5 Solder L.S 12.00

    Total 302.00

    Contractor's Profit & Overheads 20 Percent 60.40

    Total 362.40

    LABOUR (For 15 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    3 Welding charges 2.00 joints 8.00 per joints 16.00

    Total 346.00

    Sundries 10 Percent 34.60

    Total 380.60

    Contractor's Profit & Overheads 20 Percent 76.12

    Total 456.72

    ITEM RATES

    Labour rate per Metre Rs. 30.45 Say 30.45

    Labour rate per Rft Rs. 9.28 Say 9.30

    Composite rate per Metre Rs.

    392.85 Say 392.85

    Composite rate per Rft Rs. 119.77 Say 119.75

    Page 45

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    46/271

    DESCRIPTION OF ITEM:

    Item No. 6 Supply and erection of PVC pipe for recessed wiring (main and sub-main)

    purposes including bends special etc., in floor, wall or trenches.

    (i) 2" dia (50 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 10 Metre)

    1 PVC Pipe 2" dia (50 mm) 10.00 metre 48.25 per mtr. 482.50

    2 PVC Bend 2" dia (50 mm) 2.00 Nos. 15.00 each 30.00

    3 M.S Hooks 10.00 Nos. 4.00 each 40.00

    4 PVC Inspection box 2.00 Nos. 32.00 per doz. 5.33

    5 Cement 0.084 Cft. 230.00 P. Bag 19.32

    6 Sand 0.24 Cft. 350.00 Per % Cft. 0.84

    Total 577.99

    Contractor's Profit & Overheads 20 Percent 115.60

    Total 693.59Material per metre 631.22 10 69.36 69.36

    LABOUR (For 23 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

    Total 490.00

    Sundries 10 Percent 49.00

    Total 539.00

    Contractor's Profit & Overheads 20 Percent 107.80

    Total 646.80

    ITEM RATES

    Labour rate per Metre Rs. 28.12 Say 28.10

    Labour rate per Rft Rs. 8.57 Say 8.55

    Composite rate per Metre Rs. 97.48 Say 97.50

    Composite rate per Rft Rs. 29.72 Say 29.70

    Page 46

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    47/271

    DESCRIPTION OF ITEM:

    Item No. 6 Supply and erection of PVC pipe for recessed wiring (main and sub-main)

    purposes including bends special etc., in floor, wall or trenches.

    (ii) 3" dia (80 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 10 Metre)

    1 PVC Pipe 3" dia (75 mm) 10.00 metre 66.75 per mtr. 667.50

    2 PVC Bend 3" dia (75 mm) 2.00 Nos. 25.00 each 50.00

    3 PVC Inspection box 2.00 Nos. 40.00 per doz. 6.67

    4 Cement 0.106 Cft. 230.00 P. Bag 24.38

    5 Sand 0.25 Cft. 350.00 Per % Cft. 0.88

    Total 749.42

    Contractor's Profit & Overheads 20 Percent 149.88

    Total 899.31

    Material per metre 818.58 10 89.93 89.93

    LABOUR (For 20 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

    Total 490.00

    Sundries 10 Percent 49.00

    Total 539.00

    Contractor's Profit & Overheads 20 Percent 107.80

    Total 646.80

    ITEM RATES

    Labour rate per Metre Rs. 32.34 Say 32.35

    Labour rate per Rft Rs. 9.86 Say 9.85

    Composite rate per Metre Rs.

    122.27 Say 122.25

    Composite rate per Rft Rs. 37.28 Say 37.30

    Page 47

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    48/271

    DESCRIPTION OF ITEM:

    Item No. 6 Supply and erection of PVC pipe for recessed wiring (main and sub-main)

    purposes including bends special etc., in floor, wall or trenches.

    (iii) 4" dia (100 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 10 Metre)

    1 PVC Pipe 4" dia (100 mm) 10.00 metre 88.00 per mtr. 880.00

    2 PVC Bend 4" dia (100 mm) 2.00 Nos. 65.00 each 130.00

    3 PVC Inspection box 2.00 Nos. 48.00 per doz. 8.00

    4 Cement 0.106 Cft. 230.00 P. Bag 24.38

    5 Sand 0.25 Cft. 350.00 Per % Cft. 0.88

    Total 1043.26

    Contractor's Profit & Overheads 20 Percent 208.65

    Total 1251.91

    Material per metre 1141.80 10 125.19 125.19

    LABOUR (For 20 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 2.00 Nos. 160.00 per day 320.00

    Total 490.00

    Sundries 10 Percent 49.00

    Total 539.00

    Contractor's Profit & Overheads 20 Percent 107.80

    Total 646.80

    ITEM RATES

    Labour rate per Metre Rs. 32.34 Say 32.35

    Labour rate per Rft Rs. 9.86 Say 9.85

    Composite rate per Metre Rs. 157.53 Say 157.55

    Composite rate per Rft Rs. 48.03 Say 48.05

    Page 48

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    49/271

    DESCRIPTION OF ITEM:

    Item No. 7 Supply and erection of PVC pipe for on surface wiring (main and sub main)

    including clamps bends etc., complete with all specials.

    (i) 2" dia (50 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 10 Metre)

    1 PVC Pipe 2" dia (50 mm) 10.00 metre 48.25 per mtr. 482.50

    2 PVC Bend 2" dia (50 mm) 2.00 Nos. 15.00 each 30.00

    3 M.S Clamp 20.00 Nos. 10.00 each 200.00

    4 PVC Inspection boxes 2.00 Nos. 32.00 per doz. 5.33

    5 Gutties 20.00 Nos. 6.00 per doz. 10.00

    6 Cement 0.021 Cft. 230.00 P. Bag 4.83

    7 Sand 0.06 Cft. 350.00 Per % Cft. 0.21

    Total 732.87

    Contractor's Profit & Overheads 20 Percent 146.57Total 879.44

    Material per metre 802.27 10 = 87.94 87.94

    LABOUR (For 58 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00

    Sundries 10 Percent 33.00

    Total 363.00

    Contractor's Profit & Overheads 20 Percent 72.60Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 7.51 Say 7.50

    Labour rate per Rft Rs. 2.29 Say 2.30

    Composite rate per Metre Rs.

    95.45 Say 95.45

    Composite rate per Rft Rs. 29.10 Say 29.10

    Page 49

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    50/271

    DESCRIPTION OF ITEM:

    Item No. 7 Supply and erection of PVC pipe for on surface wiring (main and sub main)

    including clamps bends etc., complete with all specials.

    (ii) 3" dia (80mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 10 Metre)

    1 PVC Pipe 3" dia (75 mm) 10.00 metre 66.75 per mtr. 667.50

    2 PVC Bend 3" dia (75 mm) 2.00 Nos. 25.00 each 50.00

    3 M.S Clamp 20.00 Nos. 18.00 each 360.00

    4 PVC Inspection boxes 2.00 Nos. 32.00 per doz. 5.33

    5 Screws for 3" dia clamp 40.00 Nos. 12.00 per doz. 40.00

    6 Gutties 40.00 Nos. 6.00 per doz. 20.00

    7 Cement 0.042 Cft. 230.00 P. Bag 9.66

    8 Sand 0.12 Cft. 350.00 Per % Cft. 0.42

    Total 1152.91Contractor's Profit & Overheads 20 Percent 230.58

    Total 1383.50

    Material per metre 1155.92 10 138.35 138.35

    LABOUR (For 40 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00

    Sundries 10 Percent 33.00

    Total 363.00Contractor's Profit & Overheads 20 Percent 72.60

    Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 10.89 Say 10.90

    Labour rate per Rft Rs. 3.32 Say 3.30

    Composite rate per Metre Rs.

    149.24 Say 149.25

    Composite rate per Rft Rs. 45.50 Say 45.50

    Page 50

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    51/271

    DESCRIPTION OF ITEM:

    Item No. 7 Supply and erection of PVC pipe for on surface wiring (main and sub main)

    including clamps bends etc., complete with all specials.

    (iii) 4" dia (100 mm dia).

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 10 Metre)

    1 PVC Pipe 4" dia (100 mm) 10.00 metre 88.00 per mtr. 880.00

    2 PVC Bend 4" dia (100 mm) 2.00 Nos. 65.00 each 130.00

    3 M.S Clamp 20.00 Nos. 15.00 each 300.00

    4 Gutties 40.00 Nos. 6.00 per doz. 20.00

    5 Screws for 4" dia clamp 40.00 Nos. 12.00 per doz. 40.00

    6 PVC Inspection boxes 2.00 Nos. 48.00 per doz. 8.00

    7 Cement 0.084 Cft. 230.00 P. Bag 19.32

    8 Sand 0.24 Cft. 350.00 Per % Cft. 0.84

    Total 1398.16Contractor's Profit & Overheads 20 Percent 279.63

    Total 1677.79

    Material per metre 1533.77 10 167.78 167.78

    LABOUR (For 35 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00

    Sundries 10 Percent 33.00

    Total 363.00Contractor's Profit & Overheads 20 Percent 72.60

    Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 12.45 Say 12.45

    Labour rate per Rft Rs. 3.79 Say 3.80

    Composite rate per Metre Rs.

    180.22 Say 180.25

    Composite rate per Rft Rs. 54.95 Say 54.95

    Page 51

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    52/271

    DESCRIPTION OF ITEM:

    Item No. 8 Supply and erection of wooden strip batten for wiring purposes including clips,

    insulation cleats etc.

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 100 Metre)

    1 Strip casing 100.00 metre 300.00 % per mtr. 300.00

    2 Gutties 10.00 Nos. 6.00 per doz. 5.00

    3 Clamp & nails 300.00 Nos. 10.00 % No. 30.00

    4 Screw 7.25 Dozen 1.68 Dozen 12.18

    5 Insulated cleats 100.00 Nos. 1.00 each 100.00

    Total 447.18

    Contractor's Profit & Overheads 20 Percent 89.44

    Total 536.62

    Material per metre 491.70 100 5.37 5.37

    LABOUR (For 200 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00

    Sundries 10 Percent 33.00

    Total 363.00

    Contractor's Profit & Overheads 20 Percent 72.60

    Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 2.18 Say 2.20

    Labour rate per Rft Rs. 0.66 Say 0.65

    Composite rate per Metre Rs. 7.54 Say 7.55

    Composite rate per Rft Rs. 2.30 Say 2.30

    Page 52

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    53/271

    DESCRIPTION OF ITEM:

    Item No. 9 Supply and erection of sahl wood casing and capping for wiring purposes,

    including insulation cleats, screws etc., complete.

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 100 Metre)

    1 Casing Sahlwood 100.00 metre 24.00 per mtr. 2400.00

    2 Screw 20.00 Nos. 3.25 P. Doz. 5.42

    3 Gutties 20.00 Nos. 6.00 per doz. 10.00

    4 Insulated cleats 20.00 Nos. 0.25 each 5.00

    5 Screw for cover 0.60 Dozen 1.68 Dozen 1.01

    Total 2421.42

    Contractor's Profit & Overheads 20 Percent 484.28

    Total 2905.71

    Material per metre 2662.00 10 29.06 29.06

    LABOUR (For 200 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00

    Sundries 10 Percent 33.00

    Total 363.00

    Contractor's Profit & Overheads 20 Percent 72.60

    Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 2.18 Say 2.20

    Labour rate per Rft Rs. 0.66 Say 0.65

    Composite rate per Metre Rs.

    31.24 Say 31.25

    Composite rate per Rft Rs. 9.52 Say 9.50

    Page 53

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    54/271

    DESCRIPTION OF ITEM:

    Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,

    in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden

    casing and capping/G.I wire/trenches (rate for cable only).

    (a) 250/440 Volts PVC insulated.

    (i) 3/0.74 mm (3/0.029")

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 90 Metre)

    1 PVC cable 3/0.029" = 1 coil 90.00 metre 4.31 per mtr. 387.90

    Wastage (3%) 11.64

    Total 399.54

    Contractor's Profit & Overheads 20 Percent 79.91

    Total 479.44

    Material per metre 439.49 90 = 5.33 5.33

    LABOUR (For 100 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00

    Sundries 10 Percent 33.00

    Total 363.00

    Contractor's Profit & Overheads 20 Percent 72.60

    Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 4.36 Say 4.35

    Labour rate per Rft Rs. 1.33 Say 1.35

    Composite rate per Metre Rs. 9.68 Say 9.70

    Composite rate per Rft Rs. 2.95 Say 2.95

    Page 54

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    55/271

    DESCRIPTION OF ITEM:

    Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,

    in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden

    casing and capping/G.I wire/trenches (rate for cable only).

    (a) 250/440 Volts PVC insulated.

    (ii) 3/0.91 mm (3.036")

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 90 Metre)

    1 PVC cable 3/0.036" = 1 coil 90.00 metre 6.24 per mtr. 561.60

    Wastage (3%) 16.85

    Total 578.45

    Contractor's Profit & Overheads 20 Percent 115.69

    Total 694.14

    Material per metre 636.29 90 = 7.71 7.71

    LABOUR (For 100 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00

    Sundries 10 Percent 33.00

    Total 363.00

    Contractor's Profit & Overheads 20 Percent 72.60

    Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 4.36 Say 4.35

    Labour rate per Rft Rs. 1.33 Say 1.35

    Composite rate per Metre Rs. 12.07 Say 12.05

    Composite rate per Rft Rs. 3.68 Say 3.70

    Page 55

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    56/271

    DESCRIPTION OF ITEM:

    Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,

    in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden

    casing and capping/G.I wire/trenches (rate for cable only).

    (a) 250/440 Volts PVC insulated.

    (iii) 7/0.74 mm (7/0.029")

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 90 Metre)

    1 PVC cable 7/0.029" = 1 coil 90.00 metre 8.91 per mtr. 801.90

    Wastage (3%) 24.06

    Total 825.96

    Contractor's Profit & Overheads 20 Percent 165.19

    Total 991.15

    Material per metre 908.55 90 = 11.01 11.01

    LABOUR (For 100 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00

    Sundries 10 Percent 33.00

    Total 363.00

    Contractor's Profit & Overheads 20 Percent 72.60

    Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 4.36 Say 4.35

    Labour rate per Rft Rs. 1.33 Say 1.35

    Composite rate per Metre Rs. 15.37 Say 15.35

    Composite rate per Rft Rs. 4.69 Say 4.70

    Page 56

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    57/271

    DESCRIPTION OF ITEM:

    Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,

    in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden

    casing and capping/G.I wire/trenches (rate for cable only).

    (a) 250/440 Volts PVC insulated.

    (iv) 7/0.91 mm (7/0.036")

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 90 Metre)

    1 PVC cable 7/0.036" = 1 coil 90.00 metre 11.28 per mtr. 1015.20

    Wastage (3%) 30.46

    Total 1045.66

    Contractor's Profit & Overheads 20 Percent 209.13

    Total 1254.79

    Material per metre 1150.22 90 13.94 13.94

    LABOUR (For 90 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00

    Sundries 10 Percent 33.00

    Total 363.00

    Contractor's Profit & Overheads 20 Percent 72.60

    Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 4.84 Say 4.85

    Labour rate per Rft Rs. 1.48 Say 1.50

    Composite rate per Metre Rs. 18.78 Say 18.80

    Composite rate per Rft Rs. 5.73 Say 5.75

    Page 57

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    58/271

    DESCRIPTION OF ITEM:

    Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,

    in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden

    casing and capping/G.I wire/trenches (rate for cable only).

    (a) 250/440 Volts PVC insulated.

    (v) 7/1.12 mm (7/0.044")

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 90 Metre)

    1 PVC cable 7/0.044" = 1 coil 90.00 metre 16.09 per mtr. 1448.10

    Wastage (3%) 43.44

    Total 1491.54

    Contractor's Profit & Overheads 20 Percent 298.31

    Total 1789.85

    Material per metre 1640.70 90 19.89 19.89

    LABOUR (For 80 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00

    Sundries 10 Percent 33.00

    Total 363.00

    Contractor's Profit & Overheads 20 Percent 72.60

    Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 5.45 Say 5.45

    Labour rate per Rft Rs. 1.66 Say 1.65

    Composite rate per Metre Rs. 25.33 Say 25.35

    Composite rate per Rft Rs. 7.72 Say 7.70

    Page 58

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    59/271

    DESCRIPTION OF ITEM:

    Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,

    in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden

    casing and capping/G.I wire/trenches (rate for cable only).

    (a) 250/440 Volts PVC insulated.

    (vi) 7/1.63 mm (7/0.064")

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 90 Metre)

    1 PVC cable 7/0.064" = 1 coil 90.00 metre 42.87 per mtr. 3858.30

    Wastage (3%) 115.75

    Total 3974.05

    Contractor's Profit & Overheads 20 Percent 794.81

    Total 4768.86

    Material per metre 4371.45 90 52.99 52.99

    LABOUR (For 65 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00

    Sundries 10 Percent 33.00

    Total 363.00

    Contractor's Profit & Overheads 20 Percent 72.60

    Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 6.70 Say 6.70

    Labour rate per Rft Rs. 2.04 Say 2.05

    Composite rate per Metre Rs. 59.69 Say 59.70

    Composite rate per Rft Rs. 18.20 Say 18.20

    Page 59

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    60/271

    DESCRIPTION OF ITEM:

    Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,

    in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden

    casing and capping/G.I wire/trenches (rate for cable only).

    (a) 250/440 Volts PVC insulated.

    (vii) 19/1.32 mm (19/0.052")

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 90 Metre)

    1 PVC cable 19/0.052" = 1 coil 90.00 metre 57.04 per mtr. 5133.60

    Wastage (2%) 102.67

    Total 5236.27

    Contractor's Profit & Overheads 20 Percent 1047.25

    Total 6283.53

    Material per metre 5759.90 90 69.82 69.82

    LABOUR (For 70 Metre)

    1 Electrician 2.00 Nos. 170.00 per day 340.00

    2 Cooly skilled 3.00 Nos. 160.00 per day 480.00

    Total 820.00

    Sundries 10 Percent 82.00

    Total 902.00

    Contractor's Profit & Overheads 20 Percent 180.40

    Total 1082.40

    ITEM RATES

    Labour rate per Metre Rs. 15.46 Say 15.45

    Labour rate per Rft Rs. 4.71 Say 4.70

    Composite rate per Metre Rs. 85.28 Say 85.30

    Composite rate per Rft Rs. 26.00 Say 26.00

    Page 60

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    61/271

    DESCRIPTION OF ITEM:

    Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,

    in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden

    casing and capping/G.I wire/trenches (rate for cable only).

    (a) 250/440 Volts PVC insulated.

    (viii) 19/1.63 mm (19/0.064")

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 90 Metre)

    1 PVC cable 19/0.064" = 1 coil 90.00 metre 133.33 per 90 mtr. 11999.70

    Wastage (2%) 239.99

    Total 12239.69

    Contractor's Profit & Overheads 20 Percent 2447.94

    Total 14687.63

    Material per metre 13464.0 90 163.20 163.20

    LABOUR (For 60 Metre)

    1 Electrician 2.00 Nos. 170.00 per day 340.00

    2 Cooly skilled 3.00 Nos. 160.00 per day 480.00

    Total 820.00

    Sundries 10 Percent 82.00

    Total 902.00

    Contractor's Profit & Overheads 20 Percent 180.40

    Total 1082.40

    ITEM RATES

    Labour rate per Metre Rs. 18.04 Say 18.05

    Labour rate per Rft Rs. 5.50 Say 5.50

    Composite rate per Metre Rs. 181.24 Say 181.25

    Composite rate per Rft Rs. 55.25 Say 55.25

    Page 61

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    62/271

    DESCRIPTION OF ITEM:

    Item No. 10 Supply and erection of single core PVC insulated copper conductor cables,

    in prelaid PVC pipe M.S conduit/G.I pipe/wooden strip batten/wooden

    casing and capping/G.I wire/trenches (rate for cable only).

    (b) 250/440 volts. PVC insulated cotton braided and compounded cables.

    (i) 3/0.74 mm (3/0.029")

    Detail Unit Rate (Metric System) per Metre

    Qty Rate Per Unit Amount (Rs.)

    MATERIAL (For 90 Metre)

    1 PVC cable 3/0.029" = 1 coil 90.00 metre 5.00 per mtr. 450.00

    Wastage (3%) 13.50

    Total 463.50

    Contractor's Profit & Overheads 20 Percent 92.70

    Total 556.20

    Material per metre 509.85 90 = 6.18 6.18

    LABOUR (For 90 Metre)

    1 Electrician 1.00 No. 170.00 per day 170.00

    2 Cooly skilled 1.00 No. 160.00 per day 160.00

    Total 330.00

    Sundries 10 Percent 33.00

    Total 363.00

    Contractor's Profit & Overheads 20 Percent 72.60

    Total 435.60

    ITEM RATES

    Labour rate per Metre Rs. 4.84 Say 4.85

    Labour rate per Rft Rs. 1.48 Say 1.50

    Composite rate per Metre Rs. 11.02 Say 11.00

    Composite rate per Rft Rs. 3.36 Say 3.35

    Page 62

  • 8/9/2019 Rate analsis Chapter No. 24 (Electric Installation)

    63/271

    DESCRIPTION OF ITEM:

    Item No. 10 Supply and erection of singl