Rate analsis Chapter No. 8 (Stone Masonary)

98
Page 1 CHAPTER NO. 8 STONE MASONRY DESCRIPTION OF ITEM NO 1: Random, rubble masonry (uncoursed), foundation and plinth. a) Dry Masonry Detail Unit Rate (British System) per Qty Rate Per Unit (Rs) Material Quarried Stone 100 Cft 300.00 Per % Cft Headers or through stones Note: Special size of stone for headers average size = 20x1.5'x8"x10" (457x200x250mm) 20 Nos. 20 Nos 15.00 Each Total Contractor's Profit & Overh ### Percent Total Labour Mason 2.00 Nos 300.00 Per Day Unskilled Coolies 3.00 Nos 140.00 Per Day Total Sundries ### Percent Total Contractor's Profit & Overh ### Percent Total Labour Rate for 100 Cft Rs. ### Say Labour Rate P/ Cum Rs. 475.55 Say Composite Rate for 100 Cft Rs. ### Say Composite Rate P/ Cum Rs. 729.85 Say

Transcript of Rate analsis Chapter No. 8 (Stone Masonary)

Page 1: Rate analsis Chapter No. 8 (Stone Masonary)

Page 1

CHAPTER NO. 8

STONE MASONRY

DESCRIPTION OF ITEM NO 1: Random, rubble masonry (uncoursed), infoundation and plinth.

a) Dry Masonry

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Headers or through stonesNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00

Total 600.00 Contractor's Profit & Overhead 20.00 Percent 120.00 Total 720.00

Labour

Mason 2.00 Nos 300.00 Per Day 600.00 Unskilled Coolies 3.00 Nos 140.00 Per Day 420.00

Total 1,020.00 Sundries 10.00 Percent 102.00 Total 1,122.00

Contractor's Profit & Overhead 20.00 Percent 224.40 Total 1,346.40

Labour Rate for 100 Cft Rs. 1,346.40 Say 1,346.40 Labour Rate P/ Cum Rs. 475.55 Say 475.55

Composite Rate for 100 Cft Rs. 2,066.40 Say 2,066.40 Composite Rate P/ Cum Rs. 729.85 Say 729.85

Page 2: Rate analsis Chapter No. 8 (Stone Masonary)

Page 2

Item No. 1 b) In Mud Mortar

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Headers or through stonesNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Good earth 45 Cft 150.00 %Cft 67.50

Total 667.50 Contractor's Profit & Overhead 20.00 Percent 133.50 Total 801.00

Labour

Mason 2.50 Nos 300.00 Per Day 750.00 Unskilled Coolies 3.50 Nos 140.00 Per Day 490.00 Bahishti 0.25 No 160.00 Per Day 40.00

Total 1,280.00 Sundries 10.00 Percent 128.00 Total 1,408.00

Contractor's Profit & Overhead 20.00 Percent 281.60 Total 1,689.60

Labour Rate for 100 Cft Rs. 1,689.60 Say 1,689.60 Labour Rate P/ Cum Rs. 596.77 Say 596.75

Composite Rate for 100 Cft Rs. 2,490.60 Say 2,490.60 Composite Rate P/ Cum Rs. 879.68 Say 879.70

Page 3: Rate analsis Chapter No. 8 (Stone Masonary)

Page 3

Item No. 1 c) In Lime Mortar, Ratio (1 Lime 2 Sand).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or headersNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Lime Slaked (Ground) 224 Kg 2.00 Per Kg. 448.00 Sand 30 Cft 350.00 Per %Cft 105.00

Total 1,153.00 Contractor's Profit & Overhead 20.00 Percent 230.60 Total 1,383.60

Labour

Mason 4.00 Nos 300.00 Per Day 1,200.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.50 No 160.00 Per Day 80.00

Total 1,980.00 Sundries 10.00 Percent 198.00 Total 2,178.00

Contractor's Profit & Overhead 20.00 Percent 435.60 Total 2,613.60

Labour Rate for 100 Cft Rs. 2,613.60 Say 2,613.60 Labour Rate P/ Cum Rs. 923.12 Say 923.10

Composite Rate for 100 Cft Rs. 3,997.20 Say 3,997.20 Composite Rate P/ Cum Rs. 1,411.81 Say 1,411.80

Page 4: Rate analsis Chapter No. 8 (Stone Masonary)

Page 4

Item No. 1 d) In Cement Sand Mortari) Ratio ( 1:3 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or headersNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Cement 9 Bag 230.00 P. Bag 2,070.00 Sand 33.75 Cft 350.00 Per %Cft 118.13

Total 2,788.13 Contractor's Profit & Overhead 20.00 Percent 557.63 Total 3,345.75

Labour

Mason 4.00 Nos 300.00 Per Day 1,200.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.50 No 160.00 Per Day 80.00

Total 1,980.00 Sundries 10.00 Percent 198.00 Total 2,178.00

Contractor's Profit & Overhead 20.00 Percent 435.60 Total 2,613.60

Labour Rate for 100 Cft Rs. 2,613.60 Say 2,613.60 Labour Rate P/ Cum Rs. 923.12 Say 923.10

Composite Rate for 100 Cft Rs. 5,959.35 Say 5,959.35 Composite Rate P/ Cum Rs. 2,104.84 Say 2,104.85

Page 5: Rate analsis Chapter No. 8 (Stone Masonary)

Page 5

Item No. 1 d) In Cement Sand Mortarii) Ratio ( 1:4 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or headersNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Cement 7.20 Bag 230.00 Each 1,656.00 Sand 36.0 Cft 350.00 Per % Cft 126.00

Total 2,382.00 Contractor's Profit & Overhead 20.00 Percent 476.40 Total 2,858.40

Labour

Mason 4.00 Nos 300.00 Per Day 1,200.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.50 No 160.00 Per Day 80.00

Total 1,980.00 Sundries 10.00 Percent 198.00 Total 2,178.00

Contractor's Profit & Overhead 20.00 Percent 435.60 Total 2,613.60

Labour Rate for 100 Cft Rs. 2,613.60 Say 2,613.60 Labour Rate P/ Cum Rs. 923.12 Say 923.10

Composite Rate for 100 Cft Rs. 5,472.00 Say 5,472.00 Composite Rate P/ Cum Rs. 1,932.71 Say 1,932.70

Page 6: Rate analsis Chapter No. 8 (Stone Masonary)

Page 6

Item No. 1 d) In Cement Sand Mortariii) Ratio ( 1:6 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or headersNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Cement 5.14 Bag 230.00 Each 1,182.20 Sand 38.57 Cft 350.00 Per%Cft 135.00

Total 1,917.19 Contractor's Profit & Overhead 20.00 Percent 383.44 Total 2,300.63

Labour

Mason 4.00 Nos 300.00 Per Day 1,200.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.50 No 160.00 Per Day 80.00

Total 1,980.00 Sundries 10.00 Percent 198.00 Total 2,178.00

Contractor's Profit & Overhead 20.00 Percent 435.60 Total 2,613.60

Labour Rate for 100 Cft Rs. 2,613.60 Say 2,613.60 Labour Rate P/ Cum Rs. 923.12 Say 923.10

Composite Rate for 100 Cft Rs. 4,914.23 Say 4,914.25 Composite Rate P/ Cum Rs. 1,735.71 Say 1,735.70

Page 7: Rate analsis Chapter No. 8 (Stone Masonary)

Page 7

Item No. 1 d) In Cement Sand Mortariv) Ratio ( 1:8 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or headersNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Cement 4 Bag 230.00 Each 920.00 Sand 40 Cft 350.00 Per%Cft 140.00

Total 1,660.00 Contractor's Profit & Overhead 20.00 Percent 332.00 Total 1,992.00

Labour

Mason 4.00 Nos 300.00 Per Day 1,200.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.50 No 160.00 Per Day 80.00

Total 1,980.00 Sundries 10.00 Percent 198.00 Total 2,178.00

Contractor's Profit & Overhead 20.00 Percent 435.60 Total 2,613.60

Labour Rate for 100 Cft Rs. 2,613.60 Say 2,613.60 Labour Rate P/ Cum Rs. 923.12 Say 923.10

Composite Rate for 100 Cft Rs. 4,605.60 Say 4,605.60 Composite Rate P/ Cum Rs. 1,626.70 Say 1,626.70

Page 8: Rate analsis Chapter No. 8 (Stone Masonary)

Page 8

DESCRIPTION OF ITEM NO 2: Coursed Rubble Masonry hammer dressed,foundation and plinth.

a) Dry Masonry

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Headers or through stonesNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00

Total 600.00 Contractor's Profit & Overhead 20.00 Percent 120.00 Total 720.00

Labour

Mason 3.00 Nos 300.00 Per Day 900.00 Unskilled Coolies 3.00 Nos 140.00 Per Day 420.00

Total 1,320.00 Sundries 10.00 Percent 132.00 Total 1,452.00

Contractor's Profit & Overhead 20.00 Percent 290.40 Total 1,742.40

Labour Rate for 100 Cft Rs. 1,742.40 Say 1,742.40 Labour Rate P/ Cum Rs. 615.42 Say 615.40

Composite Rate for 100 Cft Rs. 2,462.40 Say 2,462.40 Composite Rate P/ Cum Rs. 869.72 Say 869.70

Page 9: Rate analsis Chapter No. 8 (Stone Masonary)

Page 9

Item No. 2 b) In Mud Mortar

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Headers or through stonesNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Good earth 45 Cft 150.00 Per% Cft 67.50

Total 667.50 Contractor's Profit & Overhead 20.00 Percent 133.50 Total 801.00

Labour

Mason 4.00 Nos 300.00 Per Day 1,200.00 Unskilled Coolies 4.00 Nos 140.00 Per Day 560.00 Bahishti 0.50 No 160.00 Per Day 80.00

Total 1,840.00 Sundries 10.00 Percent 184.00 Total 2,024.00

Contractor's Profit & Overhead 20.00 Percent 404.80 Total 2,428.80

Labour Rate for 100 Cft Rs. 2,428.80 Say 2,428.80 Labour Rate P/ Cum Rs. 857.85 Say 857.85

Composite Rate for 100 Cft Rs. 3,229.80 Say 3,229.80 Composite Rate P/ Cum Rs. 1,140.77 Say 1,140.75

Page 10: Rate analsis Chapter No. 8 (Stone Masonary)

Page 10

Item No. 2 c) In Lime Sand Mortar. (Ratio 1:2)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or headers 20 Nos 15.00 Each 300.00 Lime Slaked (Ground) 5.33/ 199 Kg 2.00 Per Per Kg. 398.00 Sand 26.67 Cft 350.00 Per%Cft 93.35

Total 1,091.35 Contractor's Profit & Overhead 20.00 Percent 218.27 Total 1,309.61

Labour

Mason 4.75 Nos 300.00 Per Day 1,425.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,245.00 Sundries 10.00 Percent 224.50 Total 2,469.50

Contractor's Profit & Overhead 20.00 Percent 493.90 Total 2,963.40

Labour Rate for 100 Cft Rs. 2,963.40 Say 2,963.40 Labour Rate P/ Cum Rs. 1,046.67 Say 1,046.65

Composite Rate for 100 Cft Rs. 4,273.01 Say 4,273.00 Composite Rate P/ Cum Rs. 1,509.22 Say 1,509.20

Page 11: Rate analsis Chapter No. 8 (Stone Masonary)

Page 11

Item No. 2 d) In Cement Sand Mortari) Ratio ( 1:3 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or bond stone Note: Special size of stone for headersaverage size = 35x1.5'x8"x10"(457x200x250mm) 35 Nos. 35 Nos 15.00 Each 525.00 Cement 8 Bag 230.00 Each 1,840.00 Sand 30 Cft 350.00 Per%Cft 105.00

Total 2,770.00 Contractor's Profit & Overhead 20.00 Percent 554.00 Total 3,324.00

Labour

Mason 4.75 Nos 300.00 Per Day 1,425.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,245.00 Sundries 10.00 Percent 224.50 Total 2,469.50

Contractor's Profit & Overhead 20.00 Percent 493.90 Total 2,963.40

Labour Rate for 100 Cft Rs. 2,963.40 Say 2,963.40 Labour Rate P/ Cum Rs. 1,046.67 Say 1,046.65

Composite Rate for 100 Cft Rs. 6,287.40 Say 6,287.40 Composite Rate P/ Cum Rs. 2,220.71 Say 2,220.70

Page 12: Rate analsis Chapter No. 8 (Stone Masonary)

Page 12

Item No. 2 d) In Cement Sand Mortarii) Ratio ( 1:4 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone including wastage 100 Cft 300.00 Per % Cft 300.00

Through Stone or bond stone Note: Special size of stone for headersaverage size = 35x1.5'x8"x10"(450x200x250mm) 35 Nos. 35 Nos 15.00 Each 525.00 Cement 6.40 Bag 230.00 Each 1,472.00 Sand 32 Cft 350.00 Per%Cft 112.00

Total 2,409.00 Contractor's Profit & Overhead 20.00 Percent 481.80 Total 2,890.80

Labour

Mason 4.75 Nos 300.00 Per Day 1,425.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,245.00 Sundries 10.00 Percent 224.50 Total 2,469.50

Contractor's Profit & Overhead 20.00 Percent 493.90 Total 2,963.40

Labour Rate for 100 Cft Rs. 2,963.40 Say 2,963.40 Labour Rate P/ Cum Rs. 1,046.68 Say 1,046.70

Composite Rate for 100 Cft Rs. 5,854.20 Say 5,854.20 Composite Rate P/ Cum Rs. 2,067.70 Say 2,067.70

Page 13: Rate analsis Chapter No. 8 (Stone Masonary)

Page 13

Item No. 2 d) In Cement Sand Mortariii) Ratio ( 1:6 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or bond stone Note: Special size of stone for headersaverage size = 35x1.5'x8"x10"(450x200x250mm) 35 Nos. 35 Nos 15.00 Each 525.00 Cement 4.57 Bag 230.00 Each 1,051.10 Sand 34.20 Cft 350.00 Per%Cft 119.70

Total 1,995.80 Contractor's Profit & Overhead 20.00 Percent 399.16 Total 2,394.96

Labour

Mason 4.75 Nos 300.00 Per Day 1,425.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,245.00 Sundries 10.00 Percent 224.50 Total 2,469.50

Contractor's Profit & Overhead 20.00 Percent 493.90 Total 2,963.40

Labour Rate for 100 Cft Rs. 2,963.40 Say 2,963.40 Labour Rate P/ Cum Rs. 1,046.67 Say 1,046.65

Composite Rate for 100 Cft Rs. 5,358.36 Say 5,358.35 Composite Rate P/ Cum Rs. 1,892.57 Say 1,892.55

Page 14: Rate analsis Chapter No. 8 (Stone Masonary)

Page 14

Item No. 2 d) In Cement Sand Mortariv) Ratio ( 1:8 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or bond stoneNote: Special size of stone for headersaverage size = 35x1.5'x8"x10"(457x200x250mm) 35 Nos. 35 Nos 15.00 Each 525.00 Cement 3.56 Bag 230.00 Each 818.80 Sand 35.60 Cft 350.00 Per%Cft 124.60

Total 1,768.40 Contractor's Profit & Overhead 20.00 Percent 353.68 Total 2,122.08

Labour

Mason 4.75 Nos 300.00 Per Day 1,425.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,245.00 Sundries 10.00 Percent 224.50 Total 2,469.50

Contractor's Profit & Overhead 20.00 Percent 493.90 Total 2,963.40

Labour Rate for 100 Cft Rs. 2,963.40 Say 2,963.40 Labour Rate P/ Cum Rs. 1,046.67 Say 1,046.65

Composite Rate for 100 Cft Rs. 5,085.48 Say 5,085.50 Composite Rate P/ Cum Rs. 1,796.19 Say 1,796.20

Page 15: Rate analsis Chapter No. 8 (Stone Masonary)

Page 15

DESCRIPTION OF ITEM NO 3: Random Rubble Masonry (uncoursed) in groundfloor or 20'(6 M) height,building/other than building.

a) Dry Masonry

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Headers or through stonesNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00

Total 600.00 Contractor's Profit & Overhead 20.00 Percent 120.00 Total 720.00

Labour

Mason 2.50 Nos 300.00 Per Day 750.00 Unskilled Coolies 3.00 Nos 140.00 Per Day 420.00

Total 1,170.00 Sundries 10.00 Percent 117.00 Total 1,287.00

Contractor's Profit & Overhead 20.00 Percent 257.40 Total 1,544.40

Labour Rate for 100 Cft Rs. 1,544.40 Say 1,544.40 Labour Rate P/ Cum Rs. 545.48 Say 545.50

Composite Rate for 100 Cft Rs. 2,264.40 Say 2,264.40 Composite Rate P/ Cum Rs. 799.79 Say 799.80

Page 16: Rate analsis Chapter No. 8 (Stone Masonary)

Page 16

Item No. 3 b) In Mud Mortar

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Headers or through stonesNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Good earth 45 Cft 150.00 Per % Cft 67.50

Total 667.50 Contractor's Profit & Overhead 20.00 Percent 133.50 Total 801.00

Labour

Mason 3.00 Nos 300.00 Per Day 900.00 Unskilled Coolies 4.00 Nos 140.00 Per Day 560.00 Bahishti 0.50 No 160.00 Per Day 80.00

Total 1,540.00 Sundries 10.00 Percent 154.00 Total 1,694.00

Contractor's Profit & Overhead 20.00 Percent 338.80 Total 2,032.80

Labour Rate for 100 Cft Rs. 2,032.80 Say 2,032.80 Labour Rate P/ Cum Rs. 717.99 Say 718.00

Composite Rate for 100 Cft Rs. 2,833.80 Say 2,833.80 Composite Rate P/ Cum Rs. 1,000.90 Say 1,000.90

Page 17: Rate analsis Chapter No. 8 (Stone Masonary)

Page 17

Item No. 3 c) In Lime Sand Mortar. (Ratio 1:2)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or headersNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Lime Slaked (Ground) 224 Kg 2.00 Per Per Kg. 448.00 Sand 30 Cft 350.00 Per % Cft 105.00

Total 1,153.00 Contractor's Profit & Overhead 20.00 Percent 230.60 Total 1,383.60

Labour

Mason 4.50 Nos 300.00 Per Day 1,350.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,170.00 Sundries 10.00 Percent 217.00 Total 2,387.00

Contractor's Profit & Overhead 20.00 Percent 477.40 Total 2,864.40

Labour Rate for 100 Cft Rs. 2,864.40 Say 2,864.40 Labour Rate P/ Cum Rs. 1,011.71 Say 1,011.70

Composite Rate for 100 Cft Rs. 4,248.00 Say 4,248.00 Composite Rate P/ Cum Rs. 1,500.39 Say 1,500.40

Page 18: Rate analsis Chapter No. 8 (Stone Masonary)

Page 18

Item No. 3 d) In Cement Sand Mortari) Ratio ( 1:3 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or headersNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Cement 9 Bag 230.00 Each 2,070.00 Sand 33.75 Cft 350.00 Per % Cft 118.13

Total 2,788.13 Contractor's Profit & Overhead 20.00 Percent 557.63 Total 3,345.75

Labour

Mason 4.50 Nos 300.00 Per Day 1,350.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,170.00 Sundries 10.00 Percent 217.00 Total 2,387.00

Contractor's Profit & Overhead 20.00 Percent 477.40 Total 2,864.40

Labour Rate for 100 Cft Rs. 2,864.40 Say 2,864.40 Labour Rate P/ Cum Rs. 1,011.71 Say 1,011.70

Composite Rate for 100 Cft Rs. 6,210.15 Say 6,210.15 Composite Rate P/ Cum Rs. 2,193.42 Say 2,193.45

Page 19: Rate analsis Chapter No. 8 (Stone Masonary)

Page 19

Item No. 3 d) In Cement Sand Mortarii) Ratio ( 1:4 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or bond stone Note: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Cement 7.2 Bag 230.00 Each 1,656.00 Sand 36 Cft 350.00 Per % Cft 126.00

Total 2,382.00 Contractor's Profit & Overhead 20.00 Percent 476.40 Total 2,858.40

Labour

Mason 4.50 Nos 300.00 Per Day 1,350.00 Unskilled Coolies 5 Nos 140.00 Per Day 700.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,170.00 Sundries 10.00 Percent 217.00 Total 2,387.00

Contractor's Profit & Overhead 20.00 Percent 477.40 Total 2,864.40

Labour Rate for 100 Cft Rs. 2,864.40 Say 2,864.40 Labour Rate P/ Cum Rs. 1,011.71 Say 1,011.70

Composite Rate for 100 Cft Rs. 5,722.80 Say 5,722.80 Composite Rate P/ Cum Rs. 2,021.29 Say 2,021.30

Page 20: Rate analsis Chapter No. 8 (Stone Masonary)

Page 20

Item No. 3 d) In Cement Sand Mortariii) Ratio ( 1:6 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100.00 Cft 300.00 Per % Cft 300.00

Through Stone or bond stone Note: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Cement 5.14 Bag 230.00 Each 1,182.20 Sand 38.57 Cft 350.00 Per % Cft 135.00

Total 1,917.19 Contractor's Profit & Overhead 20.00 Percent 383.44 Total 2,300.63

Labour

Mason 4.50 Nos 300.00 Per Day 1,350.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,170.00 Sundries 10.00 Percent 217.00 Total 2,387.00

Contractor's Profit & Overhead 20.00 Percent 477.40 Total 2,864.40

Labour Rate for 100 Cft Rs. 2,864.40 Say 2,864.40 Labour Rate P/ Cum Rs. 1,011.71 Say 1,011.70

Composite Rate for 100 Cft Rs. 5,165.04 Say 5,165.05 Composite Rate P/ Cum Rs. 1,824.29 Say 1,824.30

Page 21: Rate analsis Chapter No. 8 (Stone Masonary)

Page 21

Item No. 3 d) In Cement Sand Mortariv) Ratio ( 1:8 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or bond stoneNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250) 20 Nos. 20 Nos 15.00 Each 300.00 Cement 4 Bag 230.00 Each 920.00 Sand 40 Cft 350.00 Per % Cft 140.00

Total 1,660.00 Contractor's Profit & Overhead 20.00 Percent 332.00 Total 1,992.00

Labour

Mason 4.50 Nos 300.00 Per Day 1,350.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,170.00 Sundries 10.00 Percent 217.00 Total 2,387.00

Contractor's Profit & Overhead 20.00 Percent 477.40 Total 2,864.40

Labour Rate for 100 Cft Rs. 2,864.40 Say 2,864.40 Labour Rate P/ Cum Rs. 1,011.71 Say 1,011.70

Composite Rate for 100 Cft Rs. 4,856.40 Say 4,856.40 Composite Rate P/ Cum Rs. 1,715.28 Say 1,715.30

Page 22: Rate analsis Chapter No. 8 (Stone Masonary)

Page 22

DESCRIPTION OF ITEM NO 4: Coursed Rubble Masonry hammer dressed inground floor or 20' (6 M) height, building otherthan building.

a) Dry Masonry

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Headers or through stonesNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00

Total 600.00 Contractor's Profit & Overhead 20.00 Percent 120.00 Total 720.00

Labour

Mason 3.50 Nos 300.00 Per Day 1,050.00 Unskilled Coolies 3.50 Nos 140.00 Per Day 490.00

Total 1,540.00 Sundries 10.00 Percent 154.00 Total 1,694.00

Contractor's Profit & Overhead 20.00 Percent 338.80 Total 2,032.80

Labour Rate for 100 Cft Rs. 2,032.80 Say 2,032.80 Labour Rate P/ Cum Rs. 717.99 Say 718.00

Composite Rate for 100 Cft Rs. 2,752.80 Say 2,752.80 Composite Rate P/ Cum Rs. 972.29 Say 972.30

Page 23: Rate analsis Chapter No. 8 (Stone Masonary)

Page 23

Item No. 4 b) In Mud Mortar

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Headers or through stonesNote: Special size of stone for headersaverage size = 30x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Good earth 43 Cft 150.00 Per % Cft 64.50

Total 664.50 Contractor's Profit & Overhead 20.00 Percent 132.90 Total 797.40

Labour

Mason 5.00 Nos 300.00 Per Day 1,500.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.50 No 160.00 Per Day 80.00

Total 2,280.00 Sundries 10.00 Percent 228.00 Total 2,508.00

Contractor's Profit & Overhead 20.00 Percent 501.60 Total 3,009.60

Labour Rate for 100 Cft Rs. 3,009.60 Say 3,009.60 Labour Rate P/ Cum Rs. 1,063.00 Say 1,063.00

Composite Rate for 100 Cft Rs. 3,807.00 Say 3,807.00 Composite Rate P/ Cum Rs. 1,344.63 Say 1,344.65

Page 24: Rate analsis Chapter No. 8 (Stone Masonary)

Page 24

Item No. 4 c) In Lime Sand Mortar. (Ratio 1:2)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone including wastage 100 Cft 300.00 Per % Cft 300.00

Through Stone or headers 20 Nos 15.00 Each 300.00 Lime Slaked (Ground) 5.33 Mds(19 9)Kg 2.00 Per Per Kg. 398.00 Sand 26.67 Cft 350.00 Per % Cft 93.35

Total 1,091.35 Contractor's Profit & Overhead 20.00 Percent 218.27 Total 1,309.61

Labour

Mason 5.50 Nos 300.00 Per Day 1,650.00 Unskilled Coolies 5.50 Nos 140.00 Per Day 770.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,540.00 Sundries 10.00 Percent 254.00 Total 2,794.00

Contractor's Profit & Overhead 20.00 Percent 558.80 Total 3,352.80

Labour Rate for 100 Cft Rs. 3,352.80 Say 3,352.80 Labour Rate P/ Cum Rs. 1,184.21 Say 1,184.20

Composite Rate for 100 Cft Rs. 4,662.42 Say 4,662.40 Composite Rate P/ Cum Rs. 1,646.76 Say 1,646.75

Page 25: Rate analsis Chapter No. 8 (Stone Masonary)

Page 25

Item No. 4 d) In Cement Sand Mortari) Ratio ( 1:3 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or headersNote: Special size of stone for headersaverage size = 35x1.5'x8"x10"(457x200x250) 35 Nos. 35 Nos 15.00 Each 525.00 Cement 8 Bag 230.00 Each 1,840.00 Sand 30 Cft 350.00 Per % Cft 105.00

Total 2,770.00 Contractor's Profit & Overhead 20.00 Percent 554.00 Total 3,324.00

Labour

Mason 5.50 Nos 300.00 Per Day 1,650.00 Unskilled Coolies 5.50 Nos 140.00 Per Day 770.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,540.00 Sundries 10.00 Percent 254.00 Total 2,794.00

Contractor's Profit & Overhead 20.00 Percent 558.80 Total 3,352.80

Labour Rate for 100 Cft Rs. 3,352.80 Say 3,352.80 Labour Rate P/ Cum Rs. 1,184.21 Say 1,184.20

Composite Rate for 100 Cft Rs. 6,676.80 Say 6,676.80 Composite Rate P/ Cum Rs. 2,358.25 Say 2,358.25

Page 26: Rate analsis Chapter No. 8 (Stone Masonary)

Page 26

Item No. 4 d) In Cement Sand Mortarii) Ratio ( 1:4 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or bond stone Note: Special size of stone for headersaverage size = 35x1.5'x8"x10"(457x200x250mm) 35 Nos. 35 Nos 15.00 Each 525.00 Cement 6 Bag 230.00 Each 1,472.00 Sand 32 Cft 350.00 Per % Cft 112.00

Total 2,409.00 Contractor's Profit & Overhead 20.00 Percent 481.80 Total 2,890.80

Labour

Mason 5.50 Nos 300.00 Per Day 1,650.00 Unskilled Coolies 5.50 Nos 140.00 Per Day 770.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,540.00 Sundries 10.00 Percent 254.00 Total 2,794.00

Contractor's Profit & Overhead 20.00 Percent 558.80 Total 3,352.80

Labour Rate for 100 Cft Rs. 3,352.80 Say 3,352.80 Labour Rate P/ Cum Rs. 1,184.21 Say 1,184.20

Composite Rate for 100 Cft Rs. 6,243.60 Say 6,243.60 Composite Rate P/ Cum Rs. 2,205.24 Say 2,205.25

Page 27: Rate analsis Chapter No. 8 (Stone Masonary)

Page 27

Item No. 4 d) In Cement Sand Mortariii) Ratio ( 1:6 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or bond stone Note: Special size of stone for headersaverage size = 35x1.5'x8"x10"(457x200x250mm) 35 Nos. 35 Nos 15.00 Each 525.00 Cement 4.57 Bag 230.00 Each 1,051.10 Sand 34.20 Cft 350.00 Per % Cft 119.70

Total 1,995.80 Contractor's Profit & Overhead 20.00 Percent 399.16 Total 2,394.96

Labour

Mason 5.50 Nos 300.00 Per Day 1,650.00 Unskilled Coolies 5.50 Nos 140.00 Per Day 770.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,540.00 Sundries 10.00 Percent 254.00 Total 2,794.00

Contractor's Profit & Overhead 20.00 Percent 558.80 Total 3,352.80

Labour Rate for 100 Cft Rs. 3,352.80 Say 3,352.80 Labour Rate P/ Cum Rs. 1,184.21 Say 1,184.20

Composite Rate for 100 Cft Rs. 5,747.76 Say 5,747.75 Composite Rate P/ Cum Rs. 2,030.11 Say 2,030.10

Page 28: Rate analsis Chapter No. 8 (Stone Masonary)

Page 28

Item No. 4 d) In Cement Sand Mortariv) Ratio ( 1:8 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or bond stoneNote: Special size of stone for headersaverage size = 35x1.5'x8"x10"(457x200x250mm) 35 Nos. 35 Nos 15.00 Each 525.00 Cement 3.56 Bag 230.00 Each 818.80 Sand 35.60 Cft 350.00 Per % Cft 124.60

Total 1,768.40 Contractor's Profit & Overhead 20.00 Percent 353.68 Total 2,122.08

Labour

Mason 5.50 Nos 300.00 Per Day 1,650.00 Unskilled Coolies 5.50 Nos 140.00 Per Day 770.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,540.00 Sundries 10.00 Percent 254.00 Total 2,794.00

Contractor's Profit & Overhead 20.00 Percent 558.80 Total 3,352.80

Labour Rate for 100 Cft Rs. 3,352.80 Say 3,352.80 Labour Rate P/ Cum Rs. 1,184.21 Say 1,184.20

Composite Rate for 100 Cft Rs. 5,474.88 Say 5,474.90 Composite Rate P/ Cum Rs. 1,933.73 Say 1,933.75

Page 29: Rate analsis Chapter No. 8 (Stone Masonary)

Page 29

DESCRIPTION OF ITEM NO 5: Ashlar block in course or scabbled masonry(including dressing etc.) in ground floor or 20' (6 M) height, Building other than building.

a) In Lime Sand. (Ratio 1:2)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 200 Cft 300.00 Per % Cft 600.00 Lime Slaked (Ground) 4Md (149.30 Kg) 2.00 Per Kg. 298.60 Sand 20 Cft 3.50 Cft 70.00 Charcoal 30Lb (13.61 Kg) 4.00 Per Kg. 54.44 Steel 3.3Lb (1.50 Kg) 17.00 Per Kg. 25.50

Total 1,048.54 Contractor's Profit & Overhead 20.00 Percent 209.71 Total 1,258.25

Labour

Mason 17.00 Nos 300.00 Per Day 5,100.00 Unskilled Coolies 10.00 Nos 140.00 Per Day 1,400.00 Bahishti 1.00 No 160.00 Per Day 160.00 Blacksmith 1.00 No 170.00 Per Day 170.00 Bellow-man 1.00 No 75.00 Per Day 75.00

Total 6,905.00 Sundries 10.00 Percent 690.50 Total 7,595.50

Contractor's Profit & Overhead 20.00 Percent 1,519.10 Total 9,114.60

Labour Rate for 100 Cft Rs. 9,114.60 Say 9,114.60 Labour Rate P/ Cum Rs. 3,219.28 Say 3,219.30

Composite Rate for 100 Cft Rs. ### Say ###Composite Rate P/ Cum Rs. 3,663.68 Say 3,663.70

Page 30: Rate analsis Chapter No. 8 (Stone Masonary)

Page 30

Item No. 5 b) In Cement Sand Mortari) Ratio ( 1:3 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 200 Cft 300.00 Per % Cft 600.00 Cement 6 Bag 230.00 Each 1,380.00 Sand 22.50 Cft 3.50 Cft 78.75 Charcoal 30Lb (13.61 Kg) 4.00 Per Kg. 54.44 Steel 3.3Lb (1.50 Kg) 17.00 Per Kg. 25.50

Total 2,138.69 Contractor's Profit & Overhead 20.00 Percent 427.74 Total 2,566.43

Labour

Mason 17.00 Nos 300.00 Per Day 5,100.00 Unskilled Coolies 10.00 Nos 140.00 Per Day 1,400.00 Bahishti 1.00 No 160.00 Per Day 160.00 Blacksmith 1.00 No 170.00 Per Day 170.00 Bellow-man 1.00 No 75.00 Per Day 75.00

Total 6,905.00 Sundries 10.00 Percent 690.50 Total 7,595.50

Contractor's Profit & Overhead 20.00 Percent 1,519.10 Total 9,114.60

Labour Rate for 100 Cft Rs. 9,114.60 Say 9,114.60 Labour Rate P/ Cum Rs. 3,219.28 Say 3,219.30

Composite Rate for 100 Cft Rs. ### Say ###Composite Rate P/ Cum Rs. 4,125.75 Say 4,125.75

Page 31: Rate analsis Chapter No. 8 (Stone Masonary)

Page 31

Item No. 5 b) In Cement Sand Mortarii) Ratio ( 1:4 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 200 Cft 300.00 Per % Cft 600.00 Cement 4.80 Bag 230.00 Each 1,104.00 Sand 24 Cft 350.00 % Cft 84.00 Charcoal 30Lb (13.61 Kg) 4.00 Per Per Kg. 54.44 Steel 3.3Lb (1.50 Kg) 17.00 Per Per Kg. 25.50

Total 1,867.94 Contractor's Profit & Overhead 20.00 Percent 373.59 Total 2,241.53

Labour

Mason 17.00 Nos 300.00 Per Day 5,100.00 Unskilled Coolies 10.00 Nos 140.00 Per Day 1,400.00 Bahishti 1.00 No 160.00 Per Day 160.00 Blacksmith 1.00 No 170.00 Per Day 170.00 Bellow-man 1.00 No 75.00 Per Day 75.00

Total 6,905.00 Sundries 10.00 Percent 690.50 Total 7,595.50

Contractor's Profit & Overhead 20.00 Percent 1,519.10 Total 9,114.60

Labour Rate for 100 Cft Rs. 9,114.60 Say 9,114.60 Labour Rate P/ Cum Rs. 3,219.28 Say 3,219.30

Composite Rate for 100 Cft Rs. ### Say ###Composite Rate P/ Cum Rs. 4,010.98 Say 4,011.00

Page 32: Rate analsis Chapter No. 8 (Stone Masonary)

Page 32

Item No. 5 b) In Cement Sand Mortariii) Ratio ( 1:6 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 200 Cft 300.00 Per % Cft 600.00 Cement 3.44 Bag 230.00 Each 791.20 Sand 25.70 Cft 3.50 Cft 89.95 Charcoal 30Lb (13.61 Kg) 4.00 Per Per Kg. 54.44 Steel 3.3Lb (1.50 Kg) 17.00 Per Per Kg. 25.50

Total 1,561.09 Contractor's Profit & Overhead 20.00 Percent 312.22 Total 1,873.31

Labour

Mason 17.00 Nos 300.00 Per Day 5,100.00 Unskilled Coolies 10.00 Nos 140.00 Per Day 1,400.00 Bahishti 1.00 No 160.00 Per Day 160.00 Blacksmith 1.00 No 170.00 Per Day 170.00 Bellow-man 1.00 No 75.00 Per Day 75.00

Total 6,905.00 Sundries 10.00 Percent 690.50 Total 7,595.50

Contractor's Profit & Overhead 20.00 Percent 1,519.10 Total 9,114.60

Labour Rate for 100 Cft Rs. 9,114.60 Say 9,114.60 Labour Rate P/ Cum Rs. 3,219.28 Say 3,219.30

Composite Rate for 100 Cft Rs. ### Say ###Composite Rate P/ Cum Rs. 3,880.93 Say 3,880.95

Page 33: Rate analsis Chapter No. 8 (Stone Masonary)

Page 33

DESCRIPTION OF ITEM NO 6: Ashlar fine masonry (including dressing etc.) inground floor or 20' (6 M) height, Building otherthan building.

a) In Lime Sand Mortar. (Ratio 1:2)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 250 Cft 300.00 Per % Cft 750.00 Lime Slaked (Ground) 2Md (74.65 Kg) 2.00 Per Per Kg. 149.30 Sand 10 Cft 3.50 Cft 35.00 Charcoal 0.73Md(27.2 5)Kg 4.00 Per Per Kg. 109.00 Steel 4Lb (1.82 Kg) 17.00 Per Per Kg. 30.94

Total 1,074.24 Contractor's Profit & Overhead 20.00 Percent 214.85 Total 1,289.09

Labour

Mason 40.00 Nos 300.00 Per Day 12,000.00 Unskilled Coolies 8.00 Nos 140.00 Per Day 1,120.00 Bahishti 1.00 No 160.00 Per Day 160.00 Blacksmith 1.50 No 170.00 Per Day 255.00 Bellow-man 1.50 No 75.00 Per Day 112.50

Total ###Sundries 10.00 Percent 1,364.75 Total ###

Contractor's Profit & Overhead 20.00 Percent 3,002.45 Total ###

Labour Rate Per 100 Cft Rs. ### Say ###Labour Rate P/ Cum Rs. 6,362.79 Say 6,362.80

Composite Rate Per 100 Cft Rs. ### Say ###Composite Rate P/ Cum Rs. 6,818.10 Say 6,818.10

Page 34: Rate analsis Chapter No. 8 (Stone Masonary)

Page 34

Item No. 6 b) In Cement Sand Mortari) Ratio ( 1:3 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 250 Cft 300.00 Per % Cft 750.00 Cement 3 Bag 230.00 Each 690.00 Sand 11.25 Cft 3.50 Per % Cft 39.38 Charcoal 0.73Md (27.25 Kg) 4.00 Per Per Kg. 109.00 Steel 4Lb (1.82 Kg) 17.00 Per Per Kg. 30.94

Total 1,619.32 Contractor's Profit & Overhead 20.00 Percent 323.86 Total 1,943.18

Labour

Mason 40.00 Nos 300.00 Per Day 12,000.00 Unskilled Coolies 8.00 Nos 140.00 Per Day 1,120.00 Bahishti 1.00 No 160.00 Per Day 160.00 Blacksmith 1.50 No 170.00 Per Day 255.00 Bellow-man 1.50 No 75.00 Per Day 112.50

Total ###Sundries 10.00 Percent 1,364.75 Total ###

Contractor's Profit & Overhead 20.00 Percent 3,002.45 Total ###

Labour Rate for 100 Cft Rs. ### Say ###Labour Rate P/ Cum Rs. 6,362.79 Say 6,362.80

Composite Rate for 100 Cft Rs. ### Say ###Composite Rate P/ Cum Rs. 7,049.13 Say 7,049.15

Page 35: Rate analsis Chapter No. 8 (Stone Masonary)

Page 35

Item No. 6 b) In Cement Sand Mortarii) Ratio 1:4

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 250 Cft 300.00 Per % Cft 750.00 Cement 2.40 Bag 230.00 Each 552.00 Sand 12 Cft 3.50 Per % Cft 42.00 Charcoal 60Lb (27.22 Kg) 4.00 Per Per Kg. 108.88 Steel 4Lb (1.82 Kg) 17.00 Per Per Kg. 30.94

Total 1,483.82 Contractor's Profit & Overhead 20.00 Percent 296.76 Total 1,780.58

Labour

Mason 40.00 Nos 300.00 Per Day 12,000.00 Unskilled Coolies 8.00 Nos 140.00 Per Day 1,120.00 Bahishti 1.00 No 160.00 Per Day 160.00 Blacksmith 1.50 No 170.00 Per Day 255.00 Bellow-man 1.50 No 75.00 Per Day 112.50

Total ###Sundries 10.00 Percent 1,364.75 Total ###

Contractor's Profit & Overhead 20.00 Percent 3,002.45 Total ###

Labour Rate for 100 Cft Rs. ### Say ###Labour Rate P/ Cum Rs. 6,362.79 Say 6,362.80

Composite Rate for 100 Cft Rs. ### Say ###Composite Rate P/ Cum Rs. 6,991.69 Say 6,991.70

Page 36: Rate analsis Chapter No. 8 (Stone Masonary)

Page 36

Item No. 6 b) In Cement Sand Mortariii) Ratio 1:6

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 250 Cft 300.00 Per % Cft 750.00 Cement 1.73 Bag 230.00 Each 397.90 Sand 13 Cft 350.00 Per % Cft 45.50 Charcoal 60Lb (27.22 Kg) 4.00 Per Per Kg. 108.88 Steel 4Lb (1.82 Kg) 17.00 Per Per Kg. 30.94

Total 1,333.22 Contractor's Profit & Overhead 20.00 Percent 266.64 Total 1,599.86

Labour

Mason 40.00 Nos 300.00 Per Day 12,000.00 Unskilled Coolies 8.00 Nos 140.00 Per Day 1,120.00 Bahishti 1.00 No 160.00 Per Day 160.00 Blacksmith 1.50 No 170.00 Per Day 255.00 Bellow-man 1.50 No 75.00 Per Day 112.50

Total ###Sundries 10.00 Percent 1,364.75 Total ###

Contractor's Profit & Overhead 20.00 Percent 3,002.45 Total ###

Labour Rate for 100 Cft Rs. ### Say ###Labour Rate P/ Cum Rs. 6,362.79 Say 6,362.80

Composite Rate for 100 Cft Rs. ### Say ###Composite Rate P/ Cum Rs. 6,927.87 Say 6,927.85

Page 37: Rate analsis Chapter No. 8 (Stone Masonary)

Page 37

DESCRIPTION OF ITEM NO 7: Extra labour on items 3,4,5 and 6 for work in.

i) First Floor

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Labour for 125 Cft.

Mason 0.40 No 300.00 Per Day 120.00 Unskilled Coolies 1.35 No 140.00 Per Day 189.00

Total 309.00 Sundries 10.00 Percent 30.90 Total 339.90

Contractor's Profit & Overhead 20.00 Percent 67.98 Total 407.88

Labour Rate for 100 Cft Rs. 326.31 Say 326.30

Labour Rate P/ Cum Rs. 115.25 Say 115.25

Page 38: Rate analsis Chapter No. 8 (Stone Masonary)

Page 38

Item No. 7 ii) Second Floor

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Labour for 125 Cft.

Mason 1.20 No 300.00 Per Day 360.00 Unskilled Coolies 2.60 Nos 140.00 Per Day 364.00

Total 724.00 Sundries 10.00 Percent 72.40 Total 796.40

Contractor's Profit & Overhead 20.00 Percent 159.28 Total for 125 Cft. 955.68 Rate for 100 Cft. 764.54

Labour Rate for 100 Cft Rs. 764.54 Say 764.55

Labour Rate P/ Cum Rs. 270.04 Say 270.05

Page 39: Rate analsis Chapter No. 8 (Stone Masonary)

Page 39

Item No. 7 iii) Third Floor

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Labour for 125 Cft.

Mason 2 Nos 300.00 Per Day 600.00 Unskilled Coolies 3.90 Nos 140.00 Per Day 546.00

Total 1,146.00 Sundries 10.00 Percent 114.60 Total 1,260.60

Contractor's Profit & Overhead 20.00 Percent 252.12 Total for 125 Cft. 1,512.72 Rate for 100 Cft. 1,210.18

Labour Rate for 100 Cft Rs. 1,210.18 Say 1,210.20

Labour Rate P/ Cum Rs. 427.43 Say 427.45

Item No. 7 iv) Fourth Floor

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Labour for 125 Cft.

Mason 3.60 Nos 300.00 Per Day 1,080.00 Unskilled Coolies 5.60 Nos 140.00 Per Day 784.00

Total 1,864.00 Sundries 10.00 Percent 186.40 Total 2,050.40

Contractor's Profit & Overhead 20.00 Percent 410.08 Total for 125 Cft. 2,460.48 Rate for 100 Cft. 1,968.38

Labour Rate for 100 Cft Rs. 1,968.38 Say 1,968.40

Labour Rate P/ Cum Rs. 695.23 Say 695.25

Page 40: Rate analsis Chapter No. 8 (Stone Masonary)

Page 40

DESCRIPTION OF ITEM NO 8: Extra labour on items 3,4,5 and 6 above for every5ft (1.5 M) additional height building other thanbuilding part thereof.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Labour for 125 Cft.

Mason 0.50 No 300.00 Per Day 150.00 Unskilled Coolies 1 No 140.00 Per Day 140.00

Total 290.00 Sundries 10.00 Percent 29.00 Total 319.00

Contractor's Profit & Overhead 20.00 Percent 63.80 Totalfor 125 Cft. 382.80 Rate for 100 Cft. 306.24

Labour Rate for 100 Cft Rs. 306.24 Say 306.25

Labour Rate P/ Cum Rs. 108.16 Say 108.15

Page 41: Rate analsis Chapter No. 8 (Stone Masonary)

Page 41

DESCRIPTION OF ITEM NO 9: Extra labour for arch work in stone masonryincluding centering and de-centering, etc.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Kikar wood = 3.75 Cft to be used for60 times 3.75/60 = 0.06 Cft 0.06 Cft 250.00 Per Cft 15.00 Earth 2.00 Cft 150.00 % Cft 3.00

18.00 Contractor's Profit & Overhead 20.00 Percent 3.60 Total for 33.8 Cft 21.60 Total for 100 Cft 19.8 x 100 63.91

33.8Labour

Mason 1.50 Nos 300.00 Per Day 450.00 Unskilled Coolies 1.50 Nos 140.00 Per Day 210.00

Total 660.00 Sundries 10.00 Percent 66.00 Total 726.00

Contractor's Profit & Overhead 20.00 Percent 145.20 Total 871.20 Total (i+ii) 935.12

Labour Rate for 100 Cft Rs. 935.12 Say 935.10

Labour Rate P/ Cum Rs. 330.28 Say 330.30

Semi circular opening 15'x1.5'x1.5' = 33.8 Cft

Page 42: Rate analsis Chapter No. 8 (Stone Masonary)

Page 42

DESCRIPTION OF ITEM NO 10: Extra labour for :-

a) Coping and caps etc

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material for 125 Cft.

Stone 12" (300mm) and above 30 Cft 300.00 Per % Cft 90.00 Steel 0.75Lb (0.34 Kg) 17.00 Per Kg. 5.78 Charcoal 10Lb (4.54 Kg) 4.00 Per Kg. 18.16

Total 113.94 Contractor's Profit & Overhead 20.00 Percent 22.79 Total 136.73

Labour

Mason 18.00 Nos 300.00 Per Day 5,400.00

Total 5,400.00 Sundries 10.00 Percent 540.00 Total 5,940.00

Contractor's Profit & Overhead 20.00 Percent 1,188.00 Total for 125 Cft. 7,128.00 Rate for 100 Cft. 5,702.40

Extra Rate Per 100 Cft Rs. 5,702.40 Say 5,702.40

Extra Rate P/ Cum Rs. 2,014.09 Say 2,014.10

Page 43: Rate analsis Chapter No. 8 (Stone Masonary)

Page 43

Item No. 10 b) Cornice and string course

Detail Unit Rate (British System) per 100 Rft

Qty Rate Per Unit (Rs) Amount (Rs)

Labour for 125 Rft

Mason 18 Nos 300.00 Per Day 5,400.00

Total 5,400.00 Sundries 10.00 Percent 540.00 Total 5,940.00

Contractor's Profit & Overhead 20.00 Percent 1,188.00 Total for 125 Rft 7,128.00 Rate for 100 Rft 5,702.40

Labour Rate for 100 Rft Rs. 5,702.40 Say 5,702.40

Labour Rate P/ LM. Rs. 187.04 Say 187.05

Page 44: Rate analsis Chapter No. 8 (Stone Masonary)

Page 44

DESCRIPTION OF ITEM NO 11: Dressing Stones

a) Hammer Dressed

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit (Rs) Amount (Rs)

Labour for 125 Sft

Mason 5 Nos 300.00 Per Day 1,500.00 Unskilled Coolies 2.50 Nos 140.00 Per Day 350.00

Total 1,850.00 Sundries 10.00 Percent 185.00 Total 2,035.00

Contractor's Profit & Overhead 20.00 Percent 407.00 Total for 125 Sft 2,442.00 Rate for 100 Sft. 1,953.60

Labour Rate for 100 Sft Rs. 1,953.60 Say 1,953.60

Labour Rate P/ Sq.m Rs. 210.21 Say 210.20

Item No. 11 b) Rough tooled dressed

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit (Rs) Amount (Rs)

Labour for 125 Sft

Mason 10 Nos 300.00 Per Day 3,000.00 Unskilled Coolies 4 Nos 140.00 Per Day 560.00

Total 3,560.00 Sundries 10.00 Percent 356.00 Total 3,916.00

Contractor's Profit & Overhead 20.00 Percent 783.20 Total for 125 Sft 4,699.20 Rate for 100 Sft 3,759.36

Labour Rate for 100 Sft Rs. 3,759.36 Say 3,759.35 Labour Rate P/ Sq.m Rs. 404.51 Say 404.50

Page 45: Rate analsis Chapter No. 8 (Stone Masonary)

Page 45

Item No. 11 c) Chisel dressed

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit (Rs) Amount (Rs)

Labour for 125 Sft

Mason 12 Nos 300.00 Per Day 3,600.00 Unskilled Coolies 5 Nos 140.00 Per Day 700.00

Total 4,300.00 Sundries 10.00 Percent 430.00 Total 4,730.00

Contractor's Profit & Overhead 20.00 Percent 946.00 Total for 125 Sft 5,676.00 Rate for 100 Sft 4,540.80

Labour Rate for 100 Sft Rs. 4,540.80 Say 4,540.80

Labour Rate P/ Sq.m Rs. 488.59 Say 488.60

Item No. 11 d) Fine dressed

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit (Rs) Amount (Rs)

Labour for 125 Sft

Mason 28 Nos 300.00 Per Day 8,400.00 Unskilled Coolies 5 Nos 140.00 Per Day 700.00 Blacksmith 1 No 170.00 Per Day 170.00

Total 9,270.00 Sundries 10.00 Percent 927.00 Total ###

Contractor's Profit & Overhead 20.00 Percent 2,039.40 Total for 125 Sft ###Rate for 100 Sft 9,789.12

Labour Rate for 100 Sft Rs. 9,789.12 Say 9,789.10

Labour Rate P/ Sq.m Rs. 1,053.31 Say 1,053.30

Page 46: Rate analsis Chapter No. 8 (Stone Masonary)

Page 46

DESCRIPTION OF ITEM NO 12: Dhajji walling 5"x5" (125x125mm) thickdeodar framing with stone laid in 1:6 cementsand mortar and (1:4) cement sand plaster onboth sides.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit (Rs) Amount (Rs)

Rate Analysis for 234 Sft

a) Detail of Woodi) Top bottom

12x12ii) Vertical post 4" (100mm) apart

6x13'x5/12x5/12 = 13.55 Cftiii) Horizontal Pieces

3x18'x5/12x¼ = 5.62 Cftiv) Diagonl Strutts

31.67 Cft

38.00 CftThis wood can be used 10 time hencewood for our operation would be = 38/10 3.80 Cft

b) Stone (Quarried) 1x18x13x5/12 = 98.00 Cft

66.00 CftTherefore stone required = 66 x 2 112 Cft

Material

Wood as above 2nd Class 3.80 Cft 300.00 Cft 1,140.00 Spikes ¾" (20mm) 0.333 Kg. 30.00 Per Kg. 9.99 Wire nail 4" (100mm) 0.333 Kg. 45.00 Per Kg. 14.99 Wood preservative 0.304 Ltr 625.00 Per Litre 190.00 Stone quarried 112.00 Cft 300.00 Per % Cft 336.00 Cement for 1:6 ratio for laying 3.00 Bag 230.00 Per Bag 690.00 Cement for plastering ½" thick bothside (1:4) 3.40 Bag 230.00 Per Bag 782.00

2x18'x5x5 = 6.25 Cft

20x6x5/12x1/6 = 6.25 Cft

Wastage 20% = 6.33

Deduct Scantling = 32.00 Cft

Page 47: Rate analsis Chapter No. 8 (Stone Masonary)

Page 47

Item No. 12

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit (Rs) Amount (Rs)

Sand 40 Cft 350.00 % Cft 140.00 Steel 3Lb (1.36 Kg) 17.00 Per Kg. 23.12 Coal 0.5Md (18.66 Kg) 4.00 Per Kg. 74.64

Total 3,400.74 Contractor's Profit & Overhead 20.00 Percent 680.15 Total 4,080.88

Labour

Carpenters for wood work 4.00 Nos 300.00 Per Day 1,200.00 UnsKilled Coolies 2.00 Nos 140.00 Per Day 280.00 Masons for dressing of stones includinglaying 10.00 Nos 300.00 Per Day 3,000.00 Unskilled Coolies for laying 5.00 Nos 140.00 Per Day 700.00 Masson for plaster 3.00 Nos 300.00 Per Day 900.00 Unskilled Coolies 3.00 Nos 140.00 Per Day 420.00 Blacksmith 0.50 No 170.00 Per Day 85.00 Bellow-man 0.50 No 75.00 Per Day 37.50

Total 6,622.50 Sundries 10.00 Percent 662.25 Total 7,284.75

Contractor's Profit & Overhead 20.00 Percent 1,456.95 Total for 234 Sft 8,741.70 Rate for 100 Sft 3,735.77

Labour Rate for 100 Sft Rs. 3,735.77 Say 3,735.75 Labour Rate P/ Sqm Rs. 401.97 Say 401.95

Composite Rate for 100 Sft Rs. 5,479.74 Say 5,479.75 Composite Rate P/ Sqm Rs. 589.62 Say 589.60

Page 48: Rate analsis Chapter No. 8 (Stone Masonary)

Page 48

DESCRIPTION OF ITEM NO 13: Providing and fixing stone blocks from 2 Cft to 6Cft (0.06 to 017 M³) each, including lift upto20' (6 M).

Detail Unit Rate (British System) per Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Rate Analysis for 4 Cft

Material

Hand dressed stone average 4 Cft 1 No 70.00 Each 70.00 Cement 0.06 Bag 230.00 Bag 14.03 Sand 0.30 Cft. 350.00 % Cft 1.05

Total 85.08 Contractor's Profit & Overhead 20.00 Percent 17.02 Total 102.10

Labour

Mason 0.25 No 300.00 Per Day 75.00 Unskilled Coolies 2.00 Nos 140.00 Per Day 280.00 Blacksmith 0.12 No 170.00 Per Day 20.40

Total 375.40 Sundries 10.00 Percent 37.54 Total 412.94

Contractor's Profit & Overhead 20.00 Percent 82.59 Total for 4 Cft 495.53 Rate for Per Cft 123.88

Labour Rate Per Cft Rs. 123.88 Say 123.90 Labour Rate P/ Cum Rs. 4,375.43 Say 4,375.45

Composite Rate Per Cft Rs. 149.41 Say 149.40 Composite Rate P/ Cum Rs. 5,277.02 Say 5,277.00

Page 49: Rate analsis Chapter No. 8 (Stone Masonary)

Page 49

DESCRIPTION OF ITEM NO 14: Providing and fixing stone blocks under 2 Cft(0.05 M³) each, including lift upto 20 Cft (6 M).

Detail Unit Rate (British System) per Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Hand dressed stone average (2 Cft) 1 No 35.00 Each 35.00 Cement 0.03 Bag 230.00 Bag 6.90 Sand 0.17 Cft. 350.00 % Cft 0.60

Total 42.50 Contractor's Profit & Overhead 20.00 Percent 8.50 Total 51.00 51.00

2.00 25.50

Mason 0.05 No 300.00 Per Day 15.00 Unskilled Coolies 0.25 No 140.00 Per Day 35.00 Blacksmith 0.03 No 170.00 Per Day 5.10

Total 55.10 Sundries 10.00 Percent 5.51 Total 60.61

Contractor's Profit & Overhead 20.00 Percent 12.12 Total 72.73

Labour Rate Per Cft Rs. 72.73 Say 72.75 Labour Rate P/ Cum Rs. 2,568.89 Say 2,568.90

Composite Rate Per Cft Rs. 98.23 Say 98.25 Composite Rate P/ Cum Rs. 3,469.62 Say 3,469.65

Material Rate Analysis for 2 Cft

Labour Rate Analysis for 1 Cft

Page 50: Rate analsis Chapter No. 8 (Stone Masonary)

Page 50

Amount (Rs)

Page 51: Rate analsis Chapter No. 8 (Stone Masonary)

Page 51

Amount (Rs)

Page 52: Rate analsis Chapter No. 8 (Stone Masonary)

Page 52

Amount (Rs)

Page 53: Rate analsis Chapter No. 8 (Stone Masonary)

Page 53

Amount (Rs)

Page 54: Rate analsis Chapter No. 8 (Stone Masonary)

Page 54

Amount (Rs)

Page 55: Rate analsis Chapter No. 8 (Stone Masonary)

Page 55

Amount (Rs)

Page 56: Rate analsis Chapter No. 8 (Stone Masonary)

Page 56

Amount (Rs)

Page 57: Rate analsis Chapter No. 8 (Stone Masonary)

Page 57

Amount (Rs)

Page 58: Rate analsis Chapter No. 8 (Stone Masonary)

Page 58

Amount (Rs)

Page 59: Rate analsis Chapter No. 8 (Stone Masonary)

Page 59

Amount (Rs)

Page 60: Rate analsis Chapter No. 8 (Stone Masonary)

Page 60

Amount (Rs)

Page 61: Rate analsis Chapter No. 8 (Stone Masonary)

Page 61

Amount (Rs)

Page 62: Rate analsis Chapter No. 8 (Stone Masonary)

Page 62

Amount (Rs)

Page 63: Rate analsis Chapter No. 8 (Stone Masonary)

Page 63

Amount (Rs)

Page 64: Rate analsis Chapter No. 8 (Stone Masonary)

Page 64

floor or 20'(6 M) height,building/other than building.

Amount (Rs)

Page 65: Rate analsis Chapter No. 8 (Stone Masonary)

Page 65

Amount (Rs)

Page 66: Rate analsis Chapter No. 8 (Stone Masonary)

Page 66

Amount (Rs)

Page 67: Rate analsis Chapter No. 8 (Stone Masonary)

Page 67

Amount (Rs)

Page 68: Rate analsis Chapter No. 8 (Stone Masonary)

Page 68

Amount (Rs)

Page 69: Rate analsis Chapter No. 8 (Stone Masonary)

Page 69

Amount (Rs)

Page 70: Rate analsis Chapter No. 8 (Stone Masonary)

Page 70

Amount (Rs)

Page 71: Rate analsis Chapter No. 8 (Stone Masonary)

Page 71

Amount (Rs)

Page 72: Rate analsis Chapter No. 8 (Stone Masonary)

Page 72

Amount (Rs)

Page 73: Rate analsis Chapter No. 8 (Stone Masonary)

Page 73

Amount (Rs)

Page 74: Rate analsis Chapter No. 8 (Stone Masonary)

Page 74

Amount (Rs)

Page 75: Rate analsis Chapter No. 8 (Stone Masonary)

Page 75

Amount (Rs)

Page 76: Rate analsis Chapter No. 8 (Stone Masonary)

Page 76

Amount (Rs)

Page 77: Rate analsis Chapter No. 8 (Stone Masonary)

Page 77

Amount (Rs)

Page 78: Rate analsis Chapter No. 8 (Stone Masonary)

Page 78

Amount (Rs)

Page 79: Rate analsis Chapter No. 8 (Stone Masonary)

Page 79

Amount (Rs)

Page 80: Rate analsis Chapter No. 8 (Stone Masonary)

Page 80

Amount (Rs)

Page 81: Rate analsis Chapter No. 8 (Stone Masonary)

Page 81

Amount (Rs)

Page 82: Rate analsis Chapter No. 8 (Stone Masonary)

Page 82

Amount (Rs)

Page 83: Rate analsis Chapter No. 8 (Stone Masonary)

Page 83

Amount (Rs)

Page 84: Rate analsis Chapter No. 8 (Stone Masonary)

Page 84

Amount (Rs)

Page 85: Rate analsis Chapter No. 8 (Stone Masonary)

Page 85

Amount (Rs)

Page 86: Rate analsis Chapter No. 8 (Stone Masonary)

Page 86

Amount (Rs)

Page 87: Rate analsis Chapter No. 8 (Stone Masonary)

Page 87

Amount (Rs)

Page 88: Rate analsis Chapter No. 8 (Stone Masonary)

Page 88

Amount (Rs)

Amount (Rs)

Page 89: Rate analsis Chapter No. 8 (Stone Masonary)

Page 89

Amount (Rs)

Page 90: Rate analsis Chapter No. 8 (Stone Masonary)

Page 90

Amount (Rs)

Page 91: Rate analsis Chapter No. 8 (Stone Masonary)

Page 91

Amount (Rs)

Page 92: Rate analsis Chapter No. 8 (Stone Masonary)

Page 92

Amount (Rs)

Page 93: Rate analsis Chapter No. 8 (Stone Masonary)

Page 93

Amount (Rs)

Amount (Rs)

Page 94: Rate analsis Chapter No. 8 (Stone Masonary)

Page 94

Amount (Rs)

Amount (Rs)

Page 95: Rate analsis Chapter No. 8 (Stone Masonary)

Page 95

Amount (Rs)

Page 96: Rate analsis Chapter No. 8 (Stone Masonary)

Page 96

Amount (Rs)

Page 97: Rate analsis Chapter No. 8 (Stone Masonary)

Page 97

Amount (Rs)

Page 98: Rate analsis Chapter No. 8 (Stone Masonary)

Page 98

Amount (Rs)