DESCRIPTION OF ITEM NO 1: Formation, dressing and preparing sub-grade.
a) In Bed.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Labour
Rate Analyses for 125 Sft
Dresser 0.33 No 85.00 P. Day 28.05
Unskilled Cooly 0.77 No 140.00 P. Day 107.80
Total 135.85
Sundries 10 Percent 13.59
Total 149.44
Contractor's Profit & Overheads 20 Percent 29.89
Total 179.32
Item Rates
Labour Rate for 100 Sft Rs. 143.46 Say 143.45
Labour Rate for 1 Sqm Rs. 15.44 Say 15.45
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Unit Rate (British System) per 100 Sft
Page 1
8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 2/23
Item No. 1 Formation, dressing and preparing sub-grade.
b) On Slope.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
LabourRate Analyses for 125 Sft
Dresser 0.50 No 85.00 P. Day 42.50
Unskilled Cooly 1.00 No 140.00 P. Day 140.00
Total 182.50
Sundries 10 Percent 18.25
Total 200.75
Contractor's Profit & Overheads 20 Percent 40.15
Total 240.90
Item Rates
Labour Rate for 100 Sft Rs. 192.72 Say 192.70
Labour Rate for 1 Sqm Rs. 20.74 Say 20.75
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Unit Rate (British System) per 100 Sft
Page 2
8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 3/23
DESCRIPTION OF ITEM NO 2: Stabilized layer of cement sand ratio 1:30 2"
(50mm) thick on slope.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Cement 0.50 Bag 230.00 P. Bag 115.00 Sand 18.00 Cft 3.50 Cft 63.00
Total 178.00
Contractor's Profit & Overheads 20 Percent 35.60
Total 213.60
Labour
Rate Analyses for 125 Sft
Mason 0.50 No 300.00 P. Day 150.00
Unskilled Cooly 1.50 No 140.00 P. Day 210.00
Bahishti 0.50 No 160.00 P. Day 80.00
Total 440.00
Sundries 10 Percent 44.00
Total 484.00
Contractor's Profit & Overheads 20 Percent 96.80
Total 580.80
Item Rates
Labour Rate for 100 Sft Rs. 464.64 Say 464.65 Labour Rate for 1 Sqm Rs. 50.00 Say 50.00
Composite Rate for 100 Sft Rs. 678.24 Say 678.25
Composite Rate for 1 Sqm Rs. 72.98 Say 73.00
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Unit Rate (British System) per 100 Sft
Page 3
8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 4/23
DESCRIPTION OF ITEM NO 3: Cement plaster ½" (12mm) thick, ratio 1:10.
a) In Bed.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Cement 0.34 Bag 230.00 P. Bag 78.20
Sand 4.20 Cft 3.50 Cft 14.70
Total 92.90
Contractor's Profit & Overheads 20 Percent 18.58
Total 111.48
Labour
Rate Analyses for 125 Sft
Mason 0.33 No 300.00 P. Day 99.00
Unskilled Cooly 1.00 No 140.00 P. Day 140.00
Bahishti 0.50 No 160.00 P. Day 80.00
Total 319.00
Sundries 10 Percent 31.90
Total 350.90
Contractor's Profit & Overheads 20 Percent 70.18
Total 421.08
Item RatesLabour Rate for 100 Sft Rs. 336.86 Say 336.85
Labour Rate for 1 Sqm Rs. 36.25 Say 36.25
Composite Rate for 100 Sft Rs. 448.34 Say 448.35
Composite Rate for 1 Sqm Rs. 48.24 Say 48.25
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Unit Rate (British System) per 100 Sft
Page 4
8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 5/23
Item No. 3 Cement plaster ½" (12mm) thick, ratio 1:10.
b) On Slope.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Cement 0.34 Bag 230.00 P. Bag 78.20
Sand 4.20 Cft 3.50 Cft 14.70
Total 92.90
Contractor's Profit & Overheads 20 Percent 18.58
Total 111.48
Labour
Rate Analyses for 125 Sft
Mason 0.50 No 300.00 P. Day 150.00
Unskilled Cooly 1.25 No 140.00 P. Day 175.00
Bahishti 0.50 No 160.00 P. Day 80.00
Total 405.00
Sundries 10 Percent 40.50
Total 445.50
Contractor's Profit & Overheads 20 Percent 89.10
Total 534.61
Item RatesLabour Rate for 100 Sft Rs. 427.68 Say 427.70
Labour Rate for 1 Sqm Rs. 46.02 Say 46.00
Composite Rate for 100 Sft Rs. 539.16 Say 539.15
Composite Rate for 1 Sqm Rs. 58.01 Say 58.00
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Unit Rate (British System) per 100 Sft
Page 5
8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 6/23
DESCRIPTION OF ITEM NO 4: Cement plaster 3/8"(10mm) thick, ratio 1:3
a) In Bed.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Cement 0.70 Bag 230.00 P. Bag 161.00
Sand 2.50 Cft 3.50 Cft 8.75
Total 169.75
Contractor's Profit & Overheads 20 Percent 33.95
Total 203.70
Labour
Rate Analyses for 125 Sft
Mason 0.33 No 300.00 P. Day 99.00
Unskilled Cooly 1.00 No 140.00 P. Day 140.00
Bahishti 0.50 No 160.00 P. Day 80.00
Total 319.00
Sundries 10 Percent 31.90
Total 350.90
Contractor's Profit & Overheads 20 Percent 70.18
Total 421.08
Item RatesLabour Rate for 100 Sft Rs. 336.86 Say 336.85
Labour Rate for 1 Sqm Rs. 36.25 Say 36.25
Composite Rate for 100 Sft Rs. 540.56 Say 540.55
Composite Rate for 1 Sqm Rs. 58.16 Say 58.15
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Unit Rate (British System) per 100 Sft
Page 6
8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 7/23
Item No. 4 Cement plaster 3/8"(10mm) thick, ratio 1:3.
b) On Slope.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Cement 0.70 Bag 230.00 Each 161.00
Sand 2.50 Cft 3.50 Cft 8.75
Total 169.75
Contractor's Profit & Overheads 20 Percent 33.95
Total 203.70
Labour
Rate Analyses for 125 Sft
Mason 0.50 No 300.00 P. Day 150.00
Unskilled Cooly 1.25 No 140.00 P. Day 175.00
Bahishti 0.50 No 160.00 P. Day 80.00
Total 405.00
Sundries 10 Percent 40.50
Total 445.50
Contractor's Profit & Overheads 20 Percent 89.10
Total 534.61
Item RatesLabour Rate for 100 Sft Rs. 427.68 Say 427.70
Labour Rate for 1 Sqm Rs. 46.02 Say 46.00
Composite Rate for 100 Sft Rs. 631.38 Say 631.40
Composite Rate for 1 Sqm Rs. 67.94 Say 67.95
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Unit Rate (British System) per 100 Sft
Page 7
8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 8/23
DESCRIPTION OF ITEM NO 5: Cement plaster 1½" (40mm) thick, ratio 1:6.
a) In Bed.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Cement 1.56 Bag 230.00 P. Bag 358.80
Sand 11.70 Cft 3.50 Cft 40.95
Total 399.75
Contractor's Profit & Overheads 20 Percent 79.95
Total 479.70
Labour for 125 Sft
Mason 0.50 No 300.00 P. Day 150.00
Unskilled Cooly 1.25 No 140.00 P. Day 175.00
Bahishti 0.50 No 160.00 P. Day 80.00
Total 405.00
Sundries 10 Percent 40.50
Total 445.50
Contractor's Profit & Overheads 20 Percent 89.10
Total 534.61
Item RatesLabour Rate for 100 Sft Rs. 427.68 Say 427.70
Labour Rate for 1 Sqm Rs. 46.02 Say 46.00
Composite Rate for 100 Sft Rs. 907.38 Say 907.40
Composite Rate for 1 Sqm Rs. 97.63 Say 97.65
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Unit Rate (British System) per 100 Sft
Page 8
8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 9/23
Item No. 5 Cement plaster 1½" (40mm) thick, ratio 1:6.
b) On Slope.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Cement 1.56 Bag 230.00 P. Bag 358.80
Sand 11.70 Cft 3.50 Cft 40.95
Total 399.75
Contractor's Profit & Overheads 20 Percent 79.95
Total 479.70
Labour for 125 Sft
Mason 0.75 No 300.00 P. Day 225.00
Unskilled Cooly 1.50 No 140.00 P. Day 210.00
Bahishti 0.50 No 160.00 P. Day 80.00
Total 515.00
Sundries 10 Percent 51.50
Total 566.50
Contractor's Profit & Overheads 20 Percent 113.30
Total 679.80
Item RatesLabour Rate for 100 Sft Rs. 543.84 Say 543.85
Labour Rate for 1 Sqm Rs. 58.52 Say 58.50
Composite Rate for 100 Sft Rs. 1023.54 Say 1,023.55
Composite Rate for 1 Sqm Rs. 110.13 Say 110.15
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Unit Rate (British System) per 100 Sft
Page 9
8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 10/23
DESCRIPTION OF ITEM NO 6: Tile lining (12"x6"x2") (300x150x50mm) in 1:6
cement sand mortar.
a) In Bed.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
er Brick Tiles 1200.00 Nos 1250.00 1000 Nos 1,500.00
Cement 3.44 Bag 230.00 P. Bag 791.20
Sand 25.70 Cft 3.50 Cft 89.95
Total 2,381.15
Contractor's Profit & Overheads 20 Percent 476.23
Total 2,857.38
Labour
Mason 2.50 No 300.00 750.00 Unskilled Cooly 5.00 No 140.00 700.00
Bahishti 0.75 No 160.00 120.00
Total 1,570.00
Sundries 10 Percent 157.00
Total 1,727.00
Contractor's Profit & Overheads 20 Percent 345.40
Total 2,072.40
Item RatesLabour Rate for 100 Cft Rs. 2,072.40 Say 2,072.40
Labour Rate for 1 Cum Rs. 731.97 Say 731.95
Composite Rate for 100 Cft Rs. 4,929.78 Say 4,929.80
Composite Rate for 1 Cum Rs. 1,741.20 Say 1,741.20
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
The rates are only for laying tiles over 1/8" Ø (6mm) thick layer of 1:6 mortar items 1 to 5
above are payable separately.
Unit Rate (British System) per 100 Sft
Page 10
8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 11/23
Item No. 6 Tile lining (12"x6"x2") (300x150x50mm) in 1:6
cement sand mortar.
b) On Slope.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Brick Tiles 1200.00 Nos 1250.00 1000 Nos 1,500.00
Cement 3.44 Bag 230.00 P. Bag 791.20
Sand 25.70 Cft 3.50 Cft 89.95
Total 2,381.15
Contractor's Profit & Overheads 20 Percent 476.23
Total 2,857.38
Labour
Mason 2.75 No 300.00 P. Day 825.00
Unskilled Cooly 6.00 No 140.00 P. Day 840.00
Bahishti 0.75 No 160.00 P. Day 120.00
Total 1,785.00
Sundries 10 Percent 178.50
Total 1,963.50
Contractor's Profit & Overheads 20 Percent 392.70
Total 1,187.32
Item Rates
Labour Rate for 100 Cft Rs. 1,187.32 Say 1,187.30
Labour Rate for 1 Cum Rs. 419.36 Say 419.35
Composite Rate for 100 Cft Rs. 4,044.70 Say 4,044.70
Composite Rate for 1 Cum Rs. 1,428.59 Say 1,428.60
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
The rates are only for laying tiles over 1/8" Ø (6mm) thick layer of 1:6 mortar items 1 to 5
above are payable separately.
Unit Rate (British System) per 100 Sft
Page 11
8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 12/23
DESCRIPTION OF ITEM NO 7: Tile lining (12"x6"x2") (300x150x50mm) in 1:3
cement sand mortar.
a) In Bed.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Brick Tiles 1200.00 Nos 1250.00 1000 Nos 1,500.00
Cement 6.00 Bag 230.00 P. Bag 1,380.00
Sand 22.50 Cft 3.50 Cft 78.75
Total 2,958.75
Contractor's Profit & Overheads 20 Percent 591.75
Total 3,550.50
Labour
Mason 2.50 No 300.00 P. Day 750.00
Unskilled Cooly 5.00 No 140.00 P. Day 700.00
Bahishti 0.75 No 160.00 P. Day 120.00
Total 1,570.00
Sundries 10 Percent 157.00
Total 1,727.00
Contractor's Profit & Overheads 20 Percent 345.40
Total 2,072.40
Item Rates
Labour Rate for 100 Cft Rs. 2,072.40 Say 2,072.40
Labour Rate for 1 Cum Rs. 731.97 Say 731.95
Composite Rate for 100 Cft Rs. 5,622.90 Say 5,622.90
Composite Rate for 1 Cum Rs. 1,986.01 Say 1,986.00
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
The rates are only for laying tiles over 1/8" (6mm) thick layer of 1:3 mortar items
1 to 5 above are payable separately.
Unit Rate (British System) per 100 Sft
Page 12
8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 13/23
Item No. 7 Tile lining (12"x6"x2") (300x150x50mm) in 1:3
cement sand mortar.
b) On Slope.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Brick Tiles 1200.00 Nos 1250.00 1000 Nos 1,500.00
Cement 6.00 Bag 230.00 P. Bag 1,380.00
Sand 22.50 Cft 3.50 Cft 78.75
Total 2,958.75
Contractor's Profit & Overheads 20 Percent 591.75
Total 3,550.50
Labour
Mason 2.75 No 300.00 P. Day 825.00
Unskilled Cooly 6.00 No 140.00 P. Day 840.00
Bahishti 0.75 No 160.00 P. Day 120.00
Total 1,785.00
Sundries 10 Percent 178.50
Total 1,963.50
Contractor's Profit & Overheads 20 Percent 392.70
Total 1,187.32
Item Rates
Labour Rate for 100 Cft Rs. 1,187.32 Say 1,187.30
Labour Rate for 1 Cum Rs. 419.36 Say 419.35
Composite Rate for 100 Cft Rs. 4,737.82 Say 4,737.80
Composite Rate for 1 Cum Rs. 1,673.40 Say 1,673.40
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
The rates are only for laying tiles over 1/8" (6mm) thick layer of 1:3 mortar items
1 to 5 above are payable separately.
Unit Rate (British System) per 100 Sft
Page 13
8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 14/23
DESCRIPTION OF ITEM 8: Brick lining (9"x4½"x3") (225x114x75mm) in
1:6 cement sand mortar.
a) In Bed.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Bricks 1350.00 Nos 1200.00 1000 Nos 1,620.00
Cement 3.44 Bags 230.00 P. Bag 791.20
Sand 25.70 Cft 3.50 Cft 89.95
Total 2,501.15
Contractor's Profit & Overheads 20 Percent 500.23
Total 3,001.38
Labour
Mason 2.50 No 300.00 P. Day 750.00
Unskilled Cooly 5.00 No 140.00 P. Day 700.00
Bahishti 0.75 No 160.00 P. Day 120.00
Total 1,570.00
Sundries 10 Percent 157.00
Total 1,727.00
Contractor's Profit & Overheads 20 Percent 345.40
Total 2,072.40
Item Rates
Labour Rate for 100 Cft Rs. 2,072.40 Say 2,072.40
Labour Rate for 1 Cum Rs. 731.97 Say 731.95
Composite Rate for 100 Cft Rs. 5,073.78 Say 5,073.80
Composite Rate for 1 Cum Rs. 1,792.06 Say 1,792.05
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
The rates are only for laying bricks over 1/8" (6mm) thick layer of 1:6 mortar items
1 to 5 above are payable separately.
Unit Rate (British System) per 100 Sft
Page 14
8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 15/23
Item No. 8 Brick lining (9"x4½"x3") (225x114x75mm) in
1:6 cement sand mortar.
b) On Slope.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Bricks 1350.00 Nos 1200.00 1000 Nos 1,620.00
Cement 3.44 Bags 230.00 P. Bag 791.20
Sand 25.70 Cft 3.50 Cft 89.95
Total 2,501.15
Contractor's Profit & Overheads 20 Percent 500.23
Total 3,001.38
Labour
Mason 2.75 No 300.00 P. Day 825.00
Unskilled Cooly 6.00 No 140.00 P. Day 840.00
Bahishti 0.75 No 160.00 P. Day 120.00
Total 1,785.00
Sundries 10 Percent 178.50
Total 1,963.50
Contractor's Profit & Overheads 20 Percent 392.70
Total 2,356.20
Item Rates
Labour Rate for 100 Cft Rs. 2,356.20 Say 2,356.20
Labour Rate for 1 Cum Rs. 832.21 Say 832.20
Composite Rate for 100 Cft Rs. 5,357.58 Say 5,357.60
Composite Rate for 1 Cum Rs. 1,892.30 Say 1,892.30
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
The rates are only for laying bricks over 1/8" (6mm) thick layer of 1:6 mortar items
1 to 5 above are payable separately.
Unit Rate (British System) per 100 Sft
Page 15
8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 16/23
DESCRIPTION OF ITEM No 9: Brick lining (9"x4½"x3") (225x114x75mm) in
1:3 cement sand mortar.
a) In Bed.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Bricks 1350.00 Nos 1200.00 1000 Nos 1,620.00
Cement 6.00 Bags 230.00 P. Bag 1,380.00
Sand 22.50 Cft 3.50 Cft 78.75
Total 3,078.75
Contractor's Profit & Overheads 20 Percent 615.75
Total 3,694.50
Labour
Mason 2.50 No 300.00 P. Day 750.00
Unskilled Cooly 5.00 No 140.00 P. Day 700.00
Bahishti 0.75 No 160.00 P. Day 120.00
Total 1,570.00
Sundries 10 Percent 157.00
Total 1,727.00
Contractor's Profit & Overheads 20 Percent 345.40
Total 2,072.40
Item Rates
Labour Rate for 100 Cft Rs. 2,072.40 Say 2,072.40
Labour Rate for 1 Cum Rs. 731.97 Say 731.95
Composite Rate for 100 Cft Rs. 5,766.90 Say 5,766.90
Composite Rate for 1 Cum Rs. 2,036.87 Say 2,036.85
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
The rates are only for laying bricks over 1/8" (6mm) thick layer of 1:3 mortar items
1 to 5 above are payable separately.
Unit Rate (British System) per 100 Sft
Page 16
8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 17/23
Item No. 9 Brick lining (9"x4½"x3") (225x114x75mm) in
1:3 cement sand mortar.
b) On Slope.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Bricks 1350.00 Nos 1200.00 1000 Nos 1,620.00
Cement 6.00 Bags 230.00 P. Bag 1,380.00
Sand 22.50 Cft 3.50 Cft 78.75
Total 3,078.75
Contractor's Profit & Overheads 20 Percent 615.75
Total 3,694.50
Labour
Mason 2.75 No 300.00 P. Day 825.00
Unskilled Cooly 6.00 No 140.00 P. Day 840.00
Bahishti 0.75 No 160.00 P. Day 120.00
Total 1,785.00
Sundries 10 Percent 178.50
Total 1,963.50
Contractor's Profit & Overheads 20 Percent 392.70
Total 2,356.20
Item Rates
Labour Rate for 100 Cft Rs. 2,356.20 Say 2,356.20
Labour Rate for 1 Cum Rs. 832.21 Say 832.20
Composite Rate for 100 Cft Rs. 6,050.70 Say 6,050.70
Composite Rate for 1 Cum Rs. 2,137.11 Say 2,137.10
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
The rates are only for laying bricks over 1/8" (6mm) thick layer of 1:3 mortar items
1 to 5 above are payable separately.
Unit Rate (British System) per 100 Sft
Page 17
8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 18/23
DESCRIPTION OF ITEM NO 10: Cement concrete lining, using washed screened
and graded stone aggregate.
a) In Bed.
i) Ratio 1:2:4
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Cement 17.60 Bags 230.00 P. Bag 4,048.00
Sand 44.00 Cft 3.50 Cft 154.00
Aggregate 88.00 Cft 18.50 Cft 1,628.00
Total 5,830.00
Contractor's Profit & Overheads 20 Percent 1,166.00
Total 6,996.00
Labour
Mason 1.00 No 300.00 P. Day 300.00
Unskilled Cooly 6.00 No 140.00 P. Day 840.00
Bahishti 0.60 No 160.00 P. Day 96.00
Total 1,236.00
Sundries 10 Percent 123.60
Total 1,359.60
Contractor's Profit & Overheads 20 Percent 271.92 Total 1,631.52
Item Rates
Labour Rate for 100 Cft Rs. 1,631.52 Say 1,631.50
Labour Rate for 1 Cum Rs. 576.25 Say 576.25
Composite Rate for 100 Cft Rs. 8,627.52 Say 8,627.50
Composite Rate for 1 Cum Rs. 3,047.24 Say 3,047.25
1 Rates for all finished work include the removal of surplus debris, unused materialand byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Unit Rate (British System) per 100 Sft
Page 18
8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 19/23
Item No. 10 Cement concrete lining, using washed screened
and graded stone aggregate.
a) In Bed.
ii) Ratio 1:3:6
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Cement 13.00 Bags 230.00 P. Bag 2,990.00
Sand 46.00 Cft 3.50 Cft 161.00
Aggregate 92.00 Cft 18.50 Cft 1,702.00
Total 4,853.00
Contractor's Profit & Overheads 20 Percent 970.60
Total 5,823.60
Labour
Mason 1.00 No 300.00 P. Day 300.00
Unskilled Cooly 6.00 No 140.00 P. Day 840.00
Bahishti 0.60 No 160.00 P. Day 96.00
Total 1,236.00
Sundries 10 Percent 123.60
Total 1,359.60
Contractor's Profit & Overheads 20 Percent 271.92 Total 1,631.52
Item Rates
Labour Rate for 100 Cft Rs. 1,631.52 Say 1,631.50
Labour Rate for 1 Cum Rs. 576.25 Say 576.25
Composite Rate for 100 Cft Rs. 7,455.12 Say 7,455.10
Composite Rate for 1 Cum Rs. 2,633.15 Say 2,633.15
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Unit Rate (British System) per 100 Sft
Page 19
8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 20/23
Item No. 10 Cement concrete lining, using washed screened
and graded stone aggregate.
a) In Bed.
iii) Ratio 1:4:8
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Cement 9.60 Bags 230.00 P. Bag 2,208.00
Sand 48.00 Cft 3.50 Cft 168.00
Aggregate 96.00 Cft 18.50 Cft 1,776.00
Total 4,152.00
Contractor's Profit & Overheads 20 Percent 830.40
Total 4,982.40
Labour
Mason 1.00 No 300.00 P. Day 300.00
Unskilled Cooly 6.00 No 140.00 P. Day 840.00
Bahishti 0.60 No 160.00 P. Day 96.00
Total 1,236.00
Sundries 10 Percent 123.60
Total 1,359.60
Contractor's Profit & Overheads 20 Percent 271.92 Total 1,631.52
Item Rates
Labour Rate for 100 Cft Rs. 1,631.52 Say 1,631.50
Labour Rate for 1 Cum Rs. 576.25 Say 576.25
Composite Rate for 100 Cft Rs. 6,613.92 Say 6,613.90
Composite Rate for 1 Cum Rs. 2,336.04 Say 2,336.05
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Unit Rate (British System) per 100 Sft
Page 20
8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 21/23
Item No. 10 Cement concrete lining, using washed screened
and graded stone aggregate.
b) On Slope.
i) Ratio 1:2:4
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Cement 17.60 Bags 230.00 P. Bag 4,048.00
Sand 44.00 Cft 3.50 Cft 154.00
Aggregate 88.00 Cft 18.50 Cft 1,628.00
Total 5,830.00
Contractor's Profit & Overheads 20 Percent 1,166.00
Total 6,996.00
Labour
Mason 1.25 No 300.00 P. Day 375.00
Unskilled Cooly 7.00 No 140.00 P. Day 980.00
Bahishti 0.50 No 160.00 P. Day 80.00
Total 1,435.00
Sundries 10 Percent 143.50
Total 1,578.50
Contractor's Profit & Overheads 20 Percent 315.70 Total 1,894.20
Item Rates
Labour Rate for 100 Cft Rs. 1,894.20 Say 1,894.20
Labour Rate for 1 Cum Rs. 669.03 Say 669.05
Composite Rate for 100 Cft Rs. 8,890.20 Say 8,890.20
Composite Rate for 1 Cum Rs. 3,140.02 Say 3,140.00
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Unit Rate (British System) per 100 Sft
Page 21
8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 22/23
Item No. 10 Cement concrete lining, using washed screened
and graded stone aggregate.
b) On Slope.
ii) Ratio 1:3:6
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Cement 13.00 Bags 230.00 P. Bag 2,990.00
Sand 46.00 Cft 3.50 Cft 161.00
Aggregate 92.00 Cft 18.50 Cft 1,702.00
Total 4,853.00
Contractor's Profit & Overheads 20 Percent 970.60
Total 5,823.60
Labour
Mason 1.25 No 300.00 P. Day 375.00
Unskilled Cooly 7.00 No 140.00 P. Day 980.00
Bahishti 0.50 No 160.00 P. Day 80.00
Total 1,435.00
Sundries 10 Percent 143.50
Total 1,578.50
Contractor's Profit & Overheads 20 Percent 315.70 Total 1,894.20
Item Rates
Labour Rate for 100 Cft Rs. 1,894.20 Say 1,894.20
Labour Rate for 1 Cum Rs. 669.03 Say 669.05
Composite Rate for 100 Cft Rs. 7,717.80 Say 7,717.80
Composite Rate for 1 Cum Rs. 2,725.93 Say 2,725.95
1 Rates for all finished work include the removal of surplus debris, unused material
and byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Unit Rate (British System) per 100 Sft
Page 22
8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 23/23
Item No. 10 Cement concrete lining, using washed screened
and graded stone aggregate.
b) On Slope.
iii) Ratio 1:4:8
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Cement 9.60 Bags 230.00 P. Bag 2,208.00
Sand 48.00 Cft 3.50 Cft 168.00
Aggregate 96.00 Cft 18.50 Cft 1,776.00
Total 4,152.00
Contractor's Profit & Overheads 20 Percent 830.40
Total 4,982.40
Labour
Mason 1.25 No 300.00 P. Day 375.00
Unskilled Cooly 7.00 No 140.00 P. Day 980.00
Bahishti 0.50 No 160.00 P. Day 80.00
Total 1,435.00
Sundries 10 Percent 143.50
Total 1,578.50
Contractor's Profit & Overheads 20 Percent 315.70 Total 1,894.20
Item Rates
Labour Rate for 100 Cft Rs. 1,894.20 Say 1,894.20
Labour Rate for 1 Cum Rs. 669.03 Say 669.05
Composite Rate for 100 Cft Rs. 6,876.60 Say 6,876.60
Composite Rate for 1 Cum Rs. 2,428.82 Say 2,428.80
1 Rates for all finished work include the removal of surplus debris, unused materialand byproducts.
2 The rates include curing for specified period wherever necessary.
3 Nominal dimensions of tile or brick shall be taken for the purpose on measurement
& payments.
Unit Rate (British System) per 100 Sft